    BASIC REQUIREMENTS

    DATA REQUIREMENTS

    MATERIAL REQUIREMENT

    2

    OVERVIEW OF :

    INSTALLATION PROCEDURE

    QUALITY CHECK POINTS

    DISCUSSBRIEFLY ABOUT :

    INTRODUCTION

    TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    3/28

    INDEX

    A. Basic Requirements

    1) Data Requirementsa) RF plan

    2) Material Requirements

    a)GSM / Panel antenna

    b)Feeder cable

    c)Feeder cable Accessories:

    (i)Surge arrestor

    (ii)RF connectors

    (iii)RF clamps

    (iv)Jumper cable(v)Earthing kit

    (vi)Weatherproofing kit

    (vii)ROXTEC

    3TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    4/28

    3) List of other Items

    a)Grounding cableb)Lugs

    c)Cable ties

    d)Nuts and bolts

    e)Label set

    B. Installation Procedure Of :

    1) GSM Antenna

    2) Antenna Line

    4

    INDEX

    TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    5/28

    (A) BASIC REQUIREMENTS

    5TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    6/28

    6

    (a) RF Plan

    Site Name: Tech - Vidya

    Site ID: RJTV1234Address: Plot No. 97-98-99, 2nd Floor, NMC Complex,

    Ram Nagar Shopping Centre, Shastri Nagar, Jaipur-302016

    S No Particulars Sector A Sector B Sector C1 Azimuth 60 90 150

    2 Height 20 m 45 m 30 m

    3

    Mechanical

    Tilt 2 0 0

    4 Electrical Tilt 0 2 5

    5

    Type Of

    Antenna XYZ123 XWE412 JKI589

    1. DATA REQUIREMENTS

    TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    7/28

  • 8/12/2019 Telecom Training and Placement

    8/28

    (b) Feeder Cable

    Inner core

    Outer core

    Soft Insulation

    Outer

    Aluminium

    Core

    Copper Aluminium

    2. MATERIAL REQUIREMENTS

    8TECH VIDYA

    Outer Hard BlackInsulation

    Outer Core

    Soft Insulation

    Inner Core

    Inner Core

    filled with Softinsulation

    Outer HardBlack Insulation

    Outer Copper

    Core

  • 8/12/2019 Telecom Training and Placement

    9/28

    Specification:

    1. Inner corePure copper

    cylindrical tube of

    inches.

    2. Outer corePure copper

    cylindrical tube of 7/8inches.

    3. Soft InsulationWhite

    soft foam.

    4. Hard outer insulationBlack insulation material.

    5. Impedance50.

    6. Flexibility- More.

    1. Inner core Pure copper

    cylindrical tube of inches

    filled with soft insulation.

    2. Outer core Pure Aluminium

    cylindrical tube of 5/4 incheswith thin layer of silver foil.

    3. Soft Insulation White soft

    foam.

    4. Hard outer insulation Blackinsulation material.

    5. Impedance 50.

    6. Flexibility- Manageable.

    Copper Aluminium(b) Feeder Cable

    9TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    10/28

    (i) Surge Arrestor

    (ii) RF Connectors

    7/8

    Male

    7/8

    female

    7/8

    L- Male

    2. MATERIAL REQUIREMENTS(c) Feeder Cable Accessiories

    10TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    11/28

    (iii) RF Clamp

    1 - Way 2 -Way 3 - Way 6 - Way

    (iv) Jumper Cable

    Specification:

    1. Size - inches..

    2. Soft InsulationWhite soft

    foam.3. Impedance50.

    4. Flexibility- High.

    5. Length- 1m ,1.5m, 2m, 2m.5m,3m, 5m, 7 m,10m, 15m.

    (c) Feeder Cable Accessiories

    11TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    12/28

    (v) Earthing Kit

    Specification:

    1. Strip - Pure Copper.2. Grounding cableApprox. 0.5m ,

    10 sq. mm Black color.

    3. Lug- Ring type , 10 sq. mm.

    4. Fixed below the jumper cable at a

    distance 11.5 m.5. It is fixed on the outer core of the

    feeder cable.

    (vi) Weather Proofing Kit

    Here in weatherproofing kit we usethree type of tape :

    1. Butyl tape

    2. Rubber tape

    3. Pvc tape

    (c) Feeder Cable Accessiories

    12TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    13/28

    (vii) Roxtex

    Roxtec plate with Rubber boots

    7/8

    Rubber boot

    rubber boot

    Roxtec installation on the shelter.

    (c) Feeder Cable Accessiories

    13TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    14/28

    1414

    (b) Lugs

    (a) Grounding Cable

    35 mm2Yellow Green

    CABLE LUGS (RING/HOLE TYPE)

    TECH VIDYA

    3. LIST OF OTHER ITEMS

  • 8/12/2019 Telecom Training and Placement

    15/28

    15

    (c) Cable Ties

    (d) Nuts & Bolts

    3. LIST OF OTHER ITEMS

    TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    16/28

    16

    (e) Label Set

    3. LIST OF OTHER ITEMS

    TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    17/28

    17

    (B) INSTALLATION PROCEDURE

    TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    18/28

    18

    1. GSM ANTENNA

    TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    19/28

    19

    1. GSM ANTENNA

    TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    20/28

    20

    2. ANTENNA LINEFeeder Cable Installation

    Firstly measure the length of the feeder cable from therequired height where it has to be connected with jumper

    cable on the tower to a certain point inside the shelter 5m

    from the roxtec by using a measuring tape.

    RF clamps are then fixed with the cable tray at adistance symmetrical to the edges of the tray.

    For VCT- 1.5m between two RF clamps

    For HCT- 0.6 between two RF clamps.

    Cut the six RF cables and insulate the cable openings

    temporarily.

    Assemble the RF connecter on ground and again put

    the temporary insulation on all the connector openings.

    TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    21/28

    21

    Give the proper bend VCT to

    HCT corner in RF cable.

    Lay the RF cable on HCT.

    Provide the dummy clamp at

    the bend

    Give the proper way S-loop in RF

    cable and insert it in shelter through

    the roxtec (firstly loose the metallic tieover rubber boot of roxtec.

    Major the half meter through the

    roxtec and leaf a mark on the cable by

    marker

    Feeder Cable Installation

    TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    22/28

    Take out all cable from roxtec

    Cut the RF cable from mark point by RF cutter and again make

    the RF connector on all the cable and again insert all the cable

    through roxtec inside the shelterSeal the roxtec properly

    Again lay the RF cable properly over RF clamp near the shelter

    Make the earthing kit between the shelter and tower

    Feeder Cable Installation

    22TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    23/28

    23

    And crimp the lugs on

    EGB properly by

    crimping toolWeather proofing

    properly wrapped upon

    the all earthing kit

    Nearly shelter earthing

    kit connect with EGB

    by 16 sq mm G.C. lugs

    Feeder Cable Installation

    TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    24/28

    24

    Come inside shelter and connect the surge arrestor with all jumper

    cable and RF cable .by (30-32) no spanner

    Feeder Cable Installation

    TECH VIDYA

    When connect the earthing kit with tower body firstly remove

    the tower paint by the help of flat file

    After connect the c-clamp at the tower body properly by (12-13)no spanner

    For six cables use a three c-clamp

    So connect two cable earthing kit one c-clamp this process apply

    all the cable

    Again weather proofing properly wrapped upon the all earthingkit

    C i

  • 8/12/2019 Telecom Training and Placement

    25/28

    25

    Surge arrestor G.C. connect with

    IGB by lugs and crimp the lugs

    by crimping tool

    Now go to the tower cut cable tie

    and lay the properly with RF

    clamp

    CABLE TIES

    Feeder Cable Installation

    TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    26/28

    26

    * Provide the loop and connect the

    RF connector with jumper

    connector by(30-32) no spannerand provide the PBC tape only

    OK Not OK

    *Now again comes inside the

    shelter and connect the jumper

    connector with BTS by (30-32) nospanner

    Feeder Cable Installation

    TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    27/28

    27

    Finally weather

    proofing wrapped all

    the RF connector* Do the labeling of antenna

    line(on jumper cable near BTSport, on jumper near RF connector,

    RF cable near OD jumper

    connector, at the band HCT-VCT,

    outside the roxtec, on RF cable

    inside the shelter, on both of the

    end of ID jumper near BTS port)

    Feeder Cable Installation

    TECH VIDYA

  • 8/12/2019 Telecom Training and Placement

    28/28

    28TECH VIDYA