Telecommunication issues on a smart grid mock-up

ETSI Smart Grid Workshop

[email protected] R&D

ETSI Smart Grid Workshop05-06 April 2011Sophia Antipolis

Contents

1. Context • Smart metering trial : Linky • On the field crew mobility trial

2. Smart Grids platform : Menofis• Business issues : smart metering, electrical network operations, mobility• The design of the platform

2 ETSI Smart Grid Workshop 5-6 april 2011

• The design of the platform• Mobility issues

3. Conclusion and next steps

Context : Smart Metering with AMI infrastructure (Linky trial)

PLC GPRS

3 ETSI Smart Grid Workshop 5-6 april 2011 - Context

AMI : Advanced Metering Infrastructure

Context : on the field crew mobility

4 ETSI Smart Grids Workshop 5-6 april 2011 - Context

The Smart Grid platform : Menofis

Menofis : MEtering, Network, On the Field operations, Information System

Menofis is a smart grid test platform led by EDF R&D including in the same

Smart Metering

5 ETSI Smart Grid Workshop 5-6 april 2011 - The Smart Grid Platform

by EDF R&D including in the same infrastructure :

Advanced Metering Infrastructure (AMI)Supervision network devicesAdvanced mobility infrastructure for on the field crew

Networkoperations Mobility

Goal of this mock-up : to assess devices and technologies addressing some smart grids business requirements

Business issue : Smart Metering

Load profiles are automatically collected Several LAN have been tested :

Power Line Communication (PLC) :“Linky” PLC meters : PLC G1 (2.4 kbps) and (very soon) PLC G3 (30 kbps)

Low power Radio ISM 869 MHzEthernet

Several WAN have been tested :

6 ETSI Smart Grid Workshop 5-6 april 2011 - Business Issues

Several WAN have been tested :Ethernet, GPRS, BPL on MV, Wimax

Linky data

collector

30mn

interval

Load profile

Meters readings

repository

Business issue : Network Operations

Merge in the same device the DC (Data Collector) for metering and the RTU (Remote Terminal Unit) for network,Various sensors : T°, I, V, alarms, fault detectors

Substation

7 ETSI Smart Grid Workshop 5-6 april 2011 - Business Issues

WAN

Information system

DC&RTU

Transformer

Business issue : MobilityImprove network connectivity for mobile crew

Mobile Router in a truck with Multihoming on the WAN : Wimax, 3G, Wifi, DMRDMR (Digital Mobile Radio) : low bandwidth mediaWIFI on the LAN side of the routerHandover management on the WAN sideIP Mobility management : Mobile IP NEMO protocolLocal network to retrieve data from substations : Wifi

Meters Substation

8 ETSI Smart Grid Workshop 5-6 april 2011 - Business Issues

Meters

Sensors

Substation

DCRTU

Truck

The design of the Smart Grid platform

An AMI infrastructure extended for network operation and mobility needs

Substation

PDA

PDA

Substation

DCRTU

Substation

DCRTU

SensorsSensors

9 Metering Australia 3-4 November 2010 21 mai 2010

Information System

In-homeequipment

DC

PDA

PDA

WimaxBackBone

3G

IS

9 ETSI Smart Grid Workshop 5-6 april 2011 – The design of the platform

Internet

KMesures (P,Q,V)

Alarms (intrusion, t°, water)

LV PLC

MV/LV substation

Measurements (P,Q,V)

Remote commands

Workorders databaseMetering database

AP Wifi

CPE SDSL

IPsec

Home Agent

IPsec IPsec

SDSL

AP Wifi Ipsec Router

Wimax

Network database

RTU DC

substation substation

Global Architecture of the platform

10 ETSI Smart Grid Workshop 5-6 april 2011 - The design of the platform

3G Bouygues3G OrangeDMR WifiHotSpotMeter

Wifi

Wifi

Mobile IP - NEMO

Mobile Router

Public APN Public APN

RTU

@IP 10.101.1.6

10.20.9.2 CPE WiMax

Wifi 2.4 GHz10.21.2.0/24

SSID « posteTB »

RTURTU

10.21.9.1

FE1

KPA Current

CPE WiMax

@IP10.101.1.4

@Mac ….-79

10.101.1.3

FE2

10.21.2.1

FE0

Substation Z

Substation TB

10.21.2.2AP Wifi

Cisco router 871IDU

Wifi g/2.4 GHz10.22.2.0/24

SSID « poste D »

@IP 10.101.1.10

10.22.2.2AP WiFi

Cisco 871

10.22.2.1

FE1

10.22.8.210.101.1.9

FE2

Wimax

Base Station

10.22.8.1

FE0

Wimax5.4 GHz

IDU

Workorders

NOC

Metering

Home Agent

Cisco 2811

IPsec

Cisco 2811

10.1.7.1

10.1.8.1

FE0/0

10.1.8.2

FE0/2/0

10.1.6.1

CPE WiMax

10.1.3.1

DMR

Central IS

@IP

10.101.1.8

10.101.1.7

FE0/1

Network

Operations

10.100.1.1

Loopback

10.1.3.2 10.0.0.2

PPP client

10.21.4.1

FE3

10.21.4.2

IDU

DC

IP view of the platformSubstation D

RTURTU

DC 10.20.8.2 Cisco router

871/W

10.20.9.1

FE1

10.20.9.2

MR

10.101.3.1

DMR

CPE WiMax

@IP 10.101.1.2

AP WiFi

Camion

10.101.2.2

Client WiFi

Mobile

Router

Cisco 2811

CPE WiMax

Wifi g/2.4 GHz

10.20.2.0/24SSID

« posteZ »

10.20.8.1

FE0

Wifi g/2.4 GHz10.101.2.0/24

SSID « camion »

10.101.2.1

FE0/110.101.7.1

10.101.1.1

FE0/0

10.20.2.1

3G Orange

3G Bouygues

InternetAltitude Telecom

Public APN

Public APN

10.101.1.5

FE2

10.100.1.2

Loopback

Wifi bridge

5 GHzAP WiFiWifi g/2.4 GHz10.101.2.0/24

SSID « NOMADE »

IDU

5.4 GHz

10.101.1.0/2410.1.6.1

FE0/0

10.1.6.2AP WiFi

Central

10.1.2.2Wifi g2.4 GHz10.1.2.0/24

SSID « central » SDSL

10.101.3.2

10.0.0.1

PPP

serveur

PPP tunnel

DMR

AP Wifi

Nomade

10.101.2.3

TRUCK

IPSec

tunnels

Mobile IP

tunnel

11 ETSI Smart Grid Workshop 5-6 april 2011 - The design of the platform

Focus on DMRDMR : Digital Mobile Radio

ETSI StandardBandwidth12.5 kHz, data rate 9.6 kbpsVoice + Data

Base station compliant with analogic and numeric CPE allowing gradual roll-outDMR level 1 : without licence

446 MHz, FDMA

DMR level 2 : professionnal with licenceUHF (from 300 MHz to 3 GHz) and VHF (from 30 MHz to 300 MHz) : compliant with analogic 70 MHz UHF (from 300 MHz to 3 GHz) and VHF (from 30 MHz to 300 MHz) : compliant with analogic 70 MHz radio system currently in operation by the french DSOTDMA2 slots : Voice and/or dataFrench DSO (Distribution System Operator) wishes to have a third slot in order to control MV switches

Slot B Slot S

Data or simplex Voice Data or simplex Voice Commands for MV actuators

Data ou duplex Voice Commands for MV switches

Data

Radio chanel

or

or

Slot A

12 ETSI Smart Grid Workshop 5-6 april 2011 - The design of the platform

Focus on WimaxFree 5.4 GHz band1 BS (base station) et 4 CPE (Customer Premises Equipement)

IS

BS

CPE

13 ETSI Smart Grid Workshop 5-6 april 2011 - The design of the platform

Mobile IP

Protocols for mobility

HA

FA

MN

Home Network

Foreign Network

MN

Moving

tunnel

CN

NEMO : Network Mobility

Foreign Network

14 ETSI Smart Grid Workshop 5-6 april 2011 – Mobility issues

Conclusion and next steps

Menofis has yet produced results :Metering, network operations and mobility integration through a common architectureIntegration of heterogeneous materials and technologiesFull IP infrastructure that permits interoperabilityMobility :

Handover with different media, especially DMR very helpful during crisis situationsLocal access to substation

15 ETSI Smart Grid Workshop 5-6 april 2011 - Conclusion

Local access to substation Interaction with local and remote DC and RTUAccess to central IS through wimax backbone

Menofis platform will be enhanced this year :More technologies : PLC G3, PLC “Prime”, mesh Wifi, extended realityHAN issuesSecurity

Test platform for European Projects : “Open Meter” and “Open Node”

Thank you for your attention