SECTION 8 GENERAL CONDITIONS V20170731

TENDER DOCUMENTS

SECTION 8

GENERAL CONDITIONS

Page 2: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS i V20181214 TABLE OF CONTENTS

TABLE OF CONTENTS

PAGE

GC1  INTERPRETATION .............................................................................................................. 1 

GC2  SUCCESSORS AND ASSIGNS ............................................................................................. 4 

GC3  ASSIGNMENT OF CONTRACT ............................................................................................. 4 

GC4  SUBCONTRACTING BY CONTRACTOR ................................................................................. 5 

GC5  AMENDMENTS .................................................................................................................. 5 

GC6  NO IMPLIED OBLIGATIONS ................................................................................................. 6 

GC7  TIME OF THE ESSENCE ..................................................................................................... 6 

GC8  INDEMNIFICATION BY CONTRACTOR ................................................................................... 7 

GC9  INDEMNIFICATION BY THE OWNER ..................................................................................... 7 

GC10  NO BRIBE ......................................................................................................................... 7 

GC11  NOTICES .......................................................................................................................... 7 

GC12  MATERIAL, PLANT AND REAL PROPERTY SUPPLIED BY OWNER .......................................... 8 

GC13  MATERIAL, PLANT AND REAL PROPERTY BECOME PROPERTY OF OWNER .......................... 9 

GC14  MUNICIPAL PERMITS ......................................................................................................... 9 

GC15  PERFORMANCE OF WORK UNDER DIRECTION OF ENGINEER ............................................. 10 

GC16  COOPERATION WITH OTHER CONTRACTORS ................................................................... 10 

GC17  EXAMINATION OF WORK ................................................................................................. 10 

GC18  CLEARING OF SITE ......................................................................................................... 11 

GC19  CONTRACTOR'S SUPERINTENDENT .................................................................................. 11 

GC20  NATIONAL SECURITY ...................................................................................................... 12 

GC21  UNSUITABLE WORKERS .................................................................................................. 12 

GC22  INCREASED OR DECREASED COSTS ................................................................................ 12 

GC23  CANADIAN LABOUR AND MATERIAL .................................................................................. 13 

GC24  PROTECTION OF WORK AND DOCUMENTS ....................................................................... 14 

GC25  PUBLIC CEREMONIES AND SIGNS .................................................................................... 14 

GC26  PRECAUTIONS AGAINST DAMAGE, FIRE AND OTHER HAZARDS ......................................... 14 

GC27  INSURANCE .................................................................................................................... 15 

GC28  INSURANCE PROCEEDS .................................................................................................. 15 

GC29  CONTRACT SECURITY ..................................................................................................... 16

Page 3: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS ii V20181214 TABLE OF CONTENTS

GC30  CHANGES IN THE WORK .................................................................................................. 17 

GC31  INTERPRETATION OF CONTRACT BY ENGINEER ................................................................ 18 

GC32  WARRANTY AND RECTIFICATION OF DEFECTS IN WORK ................................................... 18 

GC33  NON-COMPLIANCE BY CONTRACTOR ............................................................................... 19 

GC34  PROTESTING ENGINEER'S DECISIONS ............................................................................. 19 

GC35  CHANGES IN SOIL CONDITIONS ....................................................................................... 19 

GC36  EXTENSION OF TIME ....................................................................................................... 20 

GC37  ASSESSMENTS AND DAMAGES FOR LATE COMPLETION .................................................... 20 

GC38  TAKING THE WORK OUT OF THE CONTRACTOR'S HANDS .................................................. 21 

GC39  EFFECT OF TAKING THE WORK OUT OF THE CONTRACTOR'S HANDS ................................ 22 

GC40  SUSPENSION OF WORK BY OWNER ................................................................................. 23 

GC41  TERMINATION OF CONTRACT .......................................................................................... 23 

GC42  CLAIMS AGAINST AND OBLIGATIONS OF THE CONTRACTOR OR SUBCONTRACTOR ............. 24 

GC43  SECURITY DEPOSIT – FORFEITURE OR RETURN............................................................... 25 

GC44  ENGINEER'S CERTIFICATES ............................................................................................. 25 

GC45  RETURN OF SECURITY DEPOSIT ...................................................................................... 27 

GC46  CLARIFICATION OF TERMS IN GC47 TO GC50 ................................................................. 27 

GC47  ADDITIONS OR AMENDMENTS TO PRICE TABLE ................................................................ 28 

GC48  DETERMINATION OF COST – PRICE TABLE ....................................................................... 28 

GC49  DETERMINATION OF COST – NEGOTIATION ...................................................................... 29 

GC50  DETERMINATION OF COST – FAILING NEGOTIATION ......................................................... 29 

GC51  RECORDS TO BE KEPT BY CONTRACTOR ......................................................................... 31 

GC52  DISPUTE RESOLUTION PROCEDURE ................................................................................ 31 

GC53  CONFLICT OF INTEREST .................................................................................................. 36 

GC54  CONTRACTOR STATUS .................................................................................................... 36 

GC55  HUMAN REMAINS, ARCHAEOLOGICAL REMAINS AND ITEMS OF HISTORICAL OR SCIENTIFIC

INTEREST ....................................................................................................................... 36 

GC56  CONTAMINATED SITE CONDITIONS .................................................................................. 37 

GC57  APPLICABLE LAWS .......................................................................................................... 38 

GC58  INTEGRITY PROVISIONS – CONTRACT .............................................................................. 38 

GC59  CONFIDENTIALITY ........................................................................................................... 43 

Page 4: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 1 V20181214

SECTION 8 GENERAL CONDITIONS

GC1 INTERPRETATION

GC1.1 In the Contract

GC1.1.1 Where reference is made to a part of the Contract by means of numbers preceded by letters, the reference shall be construed to be a reference to the particular part of the contract that is identified by that combination of letters and numbers and to any other part of the Contract referred to therein;

GC1.1.2 “Affiliate”:

GC1.1.2.1 Person, including, without however being limited to, parent companies, subsidiaries, whether or not wholly or partially owned, as well as a Senior Officer;

GC1.1.2.2 one Person is an Affiliate of another Person if:

GC1.1.2.2.1 one Person is controlled by the other Person;

GC1.1.2.2.2 both Persons are controlled by a third Person;

GC1.1.2.2.3 both Persons are under common control; or

GC1.1.2.2.4 each Person is controlled by a third Person and the third Person by whom one Person is controlled is affiliated with the third Person by whom the other Person is controlled;

GC1.1.2.3 indicia of control, whether direct or indirect, exercised or not, include, but are not limited to, common management, common ownership, identity of interests (often found in members of the same family), shared facilities and equipment or common use of employees;

GC1.1.2.4 an Affiliate may also exist in instances of an amalgamation or merger. Where at any time two or more corporations (in this provision referred to as the “predecessors”) amalgamate or merge to form a new corporation, the new corporation and any predecessor are deemed to have been affiliated with each other where they would have been affiliated with each other immediately before the amalgamation or merger if:

GC1.1.2.4.1 the new corporation had existed immediately before the amalgamation or merger; and

GC1.1.2.4.2 the Persons who were the shareholders of the new corporation immediately after the amalgamation or fusion had been the shareholders of the new corporation immediately before the amalgamation or fusion.

Page 5: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 2 V20181214

GC1.1.3 “Senior Officer”:

GC1.1.3.1 representative who plays an important role in the establishment of an organization’s policies or is responsible for managing an important aspect of the organization’s activities and, in the case of a body corporate, includes a director, its chief executive officer and its chief financial officer.

GC1.1.4 “Contract”: the Contract documents referred to in the Standard Administrative Conditions;

GC1.1.5 “Control”:

GC1.1.5.1 direct control, such as where:

GC1.1.5.1.1 a Person controls a body corporate if securities of the body corporate to which are attached more than 50 per cent of the votes that may be cast to elect directors of the body corporate are beneficially owned by the Person and the votes attached to those securities are sufficient, if exercised, to elect a majority of the directors of the body corporate;

GC1.1.5.1.2 a Person controls a corporation that is organized on a cooperative basis if the Person and all of the entities controlled by the Person have the right to exercise more than 50 per cent of the votes that may be cast at an annual meeting or to elect the majority of the directors of the corporation;

GC1.1.5.1.3 a Person controls an unincorporated entity, other than a limited partnership, if more than 50 per cent of the ownership interests, however designated, into which the entity is divided are beneficially owned by that Person and the Person is able to direct the business and affairs of the entity;

GC1.1.5.1.4 the general partner of a limited partnership controls the limited partnership;

GC1.1.5.1.5 a Person controls an entity if the Person has any direct or indirect influence that, if exercised, would result in control in fact of the entity.

GC1.1.5.2 deemed control, such as where:

GC1.1.5.2.1 a Person who controls an entity is deemed to control any entity that is controlled, or deemed to be controlled, by that entity.

Page 6: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 3 V20181214

GC1.1.5.3 indirect control, such as where:

GC1.1.5.3.1 a Person is deemed to control, within the meaning of paragraphs GC1.1.5.1 or GC1.1.5.2, an entity where the aggregate of:

GC1.1.5.3.1.1 any securities of the entity that are beneficially owned by that Person;

GC1.1.5.3.1.2 any securities of the entity that are beneficially owned by any entity controlled by that person,

is such that, if that Person and all of the entities referred to in paragraph GC.1.1.5.3.1.2 that beneficially own securities of the entity were one Person, that Person would control the entity.

GC1.1.6 “Contract security”: any security given by the Contractor to the Owner in accordance with the Contract;

GC1.1.7 “Engineer” means any person authorized, on behalf of the Owner, to perform any function assigned to him under the Contract, including, without being limited to and depending on the context, any entity retained by the Owner to design the work or any entity retained by the Owner to supervise the work;

GC1.1.8 “review by the Engineer”: the Engineer reviews documents, procedures or requests submitted and grants permission to proceed with the work according to the documents or procedures submitted, or accepts the request submitted. Permission to proceed is granted when the Engineer indicates that no corrections are noted. Permission to proceed may also be granted conditionally to the implementation of corrections which the Engineer has indicated on the documents. The Contractor may not proceed if the document is rejected or the review stamp requires a revised document to be resubmitted.

GC1.1.8.1 Review by the Engineer does not, in any way, relieve the Contractor from full responsibility for the correctness of submitted documents, procedures and of the Contractor's work and their conformity with the Contract documents and the field conditions.

GC1.1.9 “material” includes all commodities, articles and things required to be furnished by or for the Contractor under the Contract for incorporation into the work;

GC1.1.10 “Person” includes, unless the context otherwise requires, a partnership, proprietorship, firm, joint venture, consortium and a corporation;

Page 7: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 4 V20181214

GC1.1.11 “Chief Executive Officer”: the person holding the position of Chief Executive Officer of The Jacques Cartier and Champlain Bridges Incorporated, and includes a person acting for, or if the office is vacant, in the place of such Chief Executive Officer, and his successors in the office, and his or their lawful deputy and any of his or their representatives appointed for the purposes of the Contract;

GC1.1.12 “plant” includes all tools, implements, machinery, vehicles, buildings, structures, equipment and commodities, articles and things other than material, that are necessary for the due performance of the work;

GC1.1.13 “subcontractor”: a person to whom the Contractor has, subject to GC4 Subcontracting by Contractor, subcontracted the whole or any part of the work;

GC1.1.14 “superintendent”: the employee of the Contractor who is designated by the Contractor to act pursuant to GC19 Contractor's Superintendent;

GC1.1.15 “work” includes, subject only to any express stipulation in the Contract to the contrary, everything that is necessary to be done, furnished or delivered by the Contractor to perform the Contract.

GC1.2 The headings in the Contract documents, other than in the Drawings and Specifications, form no part of the Contract but are inserted for convenience of reference only.

GC1.3 In interpreting the drawings and specifications, in the event of discrepancies or conflicts between:

GC1.3.1 the drawings and specifications, the specifications govern;

GC1.3.2 the drawings, the drawings drawn with the largest scale govern; and

GC1.3.3 figured dimensions and scaled dimensions, the figured dimensions govern.

GC2 SUCCESSORS AND ASSIGNS

GC2.1 The Contract shall inure to the benefit of and be binding upon the parties hereto and their lawful heirs, executors, administrators, successors and assigns.

GC3 ASSIGNMENT OF CONTRACT

GC3.1 The Contract may not be assigned by the Contractor, either in whole or in part, without the written consent of the Owner.

Page 8: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 5 V20181214

GC4 SUBCONTRACTING BY CONTRACTOR

GC4.1 Subject to these General Conditions, the Contractor may subcontract any part of the work.

GC4.1.1 The Contractor shall not however subcontract to a contractor who holds a limited license within the meaning of the Building Act (CQLR, c.B-1.1), that is listed in the Register of Enterprises Ineligible for Public Contracts (“Registre des entreprises non admissibles aux contrats publics, (RENA)”) within the meaning of the Act respecting Contracting by Public Bodies (CQLR c. C-65.1) or on the Ineligibility and Suspension List in accordance with the Ineligibility and Suspension Policy issued by Public Services and Procurement Canada (hereinafter « PSPC »).

GC4.2 The Contractor shall notify the Engineer in writing of its intention to subcontract.

GC4.3 A notification referred to in GC4.2 shall identify the part of the work, and the subcontractor with whom it is intended to subcontract.

GC4.4 The Engineer may object to the intended subcontracting by notifying the Contractor in writing within six (6) days of receipt by the Engineer of notification referred to in GC4.2.

GC4.5 If the Engineer objects to a subcontracting pursuant to GC4.4, the Contractor shall not enter into the intended subcontract.

GC4.6 The Contractor shall not, without the written consent of the Engineer, change a subcontractor who has been engaged by it in accordance with these General Conditions.

GC4.7 Every subcontract entered into by the Contractor shall adopt all of the terms and conditions of this Contract that are of general application.

GC4.8 Neither a subcontracting nor the Engineer's consent to a subcontracting by the Contractor shall be construed to relieve the Contractor from any obligation under the Contract or to impose any liability upon the Owner, and cannot create a business contract between the Owner and any subcontractor, their representatives or employees.

GC5 AMENDMENTS

GC5.1 No amendment or change in any of the provisions of the Contract shall have any force or effect until it is reduced to writing.

GC5.2 The Contractor shall, from the outset of the event giving rise to an amendment or change request:

Page 9: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 6 V20181214

GC5.2.1 give the Engineer, within the prescribed time limit or, failing that, as soon as possible, a written notice informing him of the Contractor’s intention to submit an amendment request;

GC5.2.2 take all reasonable steps to mitigate any loss or expense and any delay that may be incurred as a result of that event;

GC5.2.3 keep the detailed and full records comprising all that is necessary to assess the amendment request in accordance with GC51 Records to be kept by Contractor.

GC5.3 The Engineer decides whether there is in fact any amendment or change to the Contract and, if so, whether the amendment or change increases or decreases the cost of the work for the Contractor.

GC5.4 The increase or decrease in the cost of the work is calculated in accordance with GC47 Additions or Amendments to Price Table to GC50 Determination of Cost – Failing Negotiation.

GC5.5 The Contractor shall perform the work in accordance with the decisions and directions of the Engineer.

GC5.6 If the Contractor does not keep detailed and full records of the means used to execute the amendment or change in accordance with GC5.2.3, such failure shall be deemed to be a waiver of any right that it might have had.

GC6 NO IMPLIED OBLIGATIONS

GC6.1 No implied terms or obligations of any kind by or on behalf of the Owner shall arise from anything in the Contract and the express covenants and agreements therein contained and made by the Owner are the only covenants and agreements upon which any rights or recourse against the Owner are to be founded.

GC6.2 The Contract supersedes and cancels all communications, negotiations and agreements, written or oral, relating to the work that was made prior to the date of the Contract.

GC7 TIME OF THE ESSENCE

GC7.1 Time is of the essence of the Contract.

Page 10: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 7 V20181214

GC8 INDEMNIFICATION BY CONTRACTOR

GC8.1 The Contractor shall indemnify and save the Owner and Her Majesty in right of Canada harmless from and against all claims, demands, losses, costs, damages, actions, suits, or proceedings by whomever made, brought or prosecuted and in any manner based upon, arising out of, related to, occasioned by or attributable to the activities of the Contractor, its employees, agents, subcontractors and subcontractors in performing the work including an infringement or an alleged infringement of a patent of invention or any other kind of intellectual property.

GC8.2 For the purposes of GC8.1, "activities" includes any act improperly carried out, any omission to carry out an act and any delay in carrying out an act.

GC9 INDEMNIFICATION BY THE OWNER

GC9.1 The Owner shall, subject to the Crown Liability and Proceedings Act, the Patent Act, and any other law that affects the Owner's rights, powers, privileges or obligations, indemnify and save the Contractor harmless from and against all claims, demands, losses, costs, damage, actions, suits or proceedings arising out of its activities under the Contract that are directly attributable to:

GC9.1.1 lack of or a defect in the Owner's title to the work site whether real or alleged; or

GC9.1.2 an infringement or an alleged infringement by the Contractor of any patent of invention or any other kind of intellectual property occurring while the Contractor was performing any act for the purposes of the Contract employing a model, plan or design or any other thing related to the work that was supplied by the Owner to the Contractor.

GC10 NO BRIBE

GC10.1 The Contractor hereby represents that no bribe, gift, benefit, nor other inducement has been nor will be given, promised or offered, directly or indirectly, to any official or employee of the Owner or of Her Majesty in right of Canada of whom the Owner is an agent, or to a member of the family of such a person, with a view to influencing the entry into the Contract or the administration of the Contract.

GC11 NOTICES

GC11.1 Any notice, consent, order, decision, direction or other communication required to be given in writing, to any party pursuant to the Contract shall, subject to paragraph GC11.4, be deemed to have been effectively given:

GC11.1.1 to the Contractor, if delivered personally to the Contractor or the Contractor's superintendent, or forwarded by mail or email to the Contractor at the address or email address indicated in its Tender Forms; or

Page 11: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 8 V20181214

GC11.1.2 to the Owner, if delivered personally to the Engineer, or forwarded by mail or email to the Engineer at the address or email address set out in paragraph 5.5.12 of the Standard Administrative Conditions.

GC11.2 Any such notice, consent, order, decision, direction or other communication given in accordance with GC11.1 shall be deemed to have been received by either party:

GC11.2.1 if delivered personally, on the day that it was delivered;

GC11.2.2 if forwarded by mail, on the earlier of the day it was received and the sixth day after it was mailed; and

GC11.2.3 if forwarded by email, the day the recipient confirms receipt of the email with a read receipt.

GC11.3 Any notice delivered personally, shall be delivered to the Contractor if the Contractor is doing business as a sole proprietor or, if the Contractor is a partnership or corporation, to a Senior Officer thereof.

GC11.4 Where the postal service is disrupted by a strike, a notice, consent, order, direction, decision or other communication may be given to the Contractor by email and shall be deemed to have been received by the Contractor twenty-four (24) hours after it was transmitted.

GC12 MATERIAL, PLANT AND REAL PROPERTY SUPPLIED BY OWNER

GC12.1 Subject to GC12.2, the Contractor is liable to the Owner for any loss of or damage to material, plant or real property that is supplied or placed in the care, custody and control of the Contractor by the Owner for use in connection with the Contract, whether or not that loss or damage is attributable to causes beyond the Contractor's control.

GC12.2 The Contractor is not liable to the Owner for any loss or damage to material, plant or real property referred to in GC12.1 if that loss or damage results from and is directly attributable to reasonable wear and tear.

GC12.3 The Contractor shall not use any material, plant or real property referred to in GC12.1 except for the purposes of performing this Contract.

GC12.4 When the Contractor fails to make good any loss or damage for which it is liable under GC12.1 within a reasonable time after being required to do so by the Engineer, the Engineer may cause the loss or damage to be made good at the Contractor's expense, and the Contractor shall thereupon be liable to the Owner for the cost thereof and shall, on demand, pay to the Owner an amount equal to that cost.

Page 12: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 9 V20181214

GC12.5 The Contractor shall keep such records of all material, plant and real property referred to in GC12.1 as the Engineer from time to time requires and shall satisfy the Engineer, when requested, that such material, plant and real property are at the place and in the condition in which they ought to be.

GC13 MATERIAL, PLANT AND REAL PROPERTY BECOME PROPERTY OF OWNER

GC13.1 All material and plant and the interest of the Contractor in all real property, licences, powers and privileges acquired, used or provided by it for the Contract shall, from the time of their acquisition, use or provision, be the property of the Owner for the purposes of the work and they shall continue to be the property of the Owner:

GC13.1.1 in the case of material, until the Engineer indicates that he is satisfied that it will not be required for the work; and

GC13.1.2 in the case of plant, real property, licences, powers and privileges, until the Engineer indicates that he is satisfied that the interest vested in the Owner therein is no longer required for the purposes of the work.

GC13.2 Material or plant that is the property of the Owner by virtue of GC13.1 shall not be taken away from the work site or used or disposed of except for the purposes of the work without the written consent of the Engineer.

GC13.3 The Owner is not liable for loss of or damage from any cause to the material or plant referred to in GC13.1 and the Contractor is liable for such loss or damage notwithstanding that the material or plant is the property of the Owner.

GC14 MUNICIPAL PERMITS

GC14.1 The Contractor shall, within thirty (30) days after the Contract Award date, tender to a municipal authority an amount equal to all fees and charges that would be lawfully payable to that municipal authority in respect of building permits as if the work were being performed for a person other than the Owner.

GC14.2 Within ten (10) days of making a tender pursuant to GC14.1, the Contractor shall notify the Engineer of its action and of the amount tendered and whether or not the municipal authority has accepted that amount.

GC14.3 If the municipal authority does not accept the amount tendered pursuant to GC14.1 the Contractor shall pay that amount to the Owner within six (6) days after the time stipulated in GC14.2.

GC14.4 For the purposes of GC14.1 to GC14.3 "municipal authority" means any authority that would have jurisdiction respecting permission to perform the work if the owner were not the Owner.

Page 13: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 10 V20181214

GC15 PERFORMANCE OF WORK UNDER DIRECTION OF ENGINEER

GC15.1 The Contractor shall:

GC15.1.1 permit the Engineer to have access to the work and its site at all times during the performance of the Contract;

GC15.1.2 furnish the Engineer with such information respecting the performance of the Contract as he may require; and

GC15.1.3 give the Engineer every possible assistance to enable the Engineer to carry out his duty to see that the work is performed in accordance with the Contract and to carry out any other duties and exercise any powers specially imposed or conferred on the Engineer under the Contract.

GC16 COOPERATION WITH OTHER CONTRACTORS

GC16.1 Where, in the opinion of the Engineer, it is necessary that other contractors or workers with or without plant and material, be sent onto the work or its site, the Contractor shall, to the satisfaction of the Engineer, allow them access and cooperate with them in the carrying out of their duties and obligations.

GC16.2 If:

GC16.2.1 the sending onto the work or its site of other contractors or workers pursuant to GC16.1 could not have been reasonably foreseen or anticipated by the Contractor when entering into the Contract; and

GC16.2.2 the Contractor incurs, in the opinion of the Engineer, extra expense in complying with GC16.1; and

GC16.2.3 the Contractor has given the Engineer written notice of its claim for the extra expense referred to in GC16.2.2 within thirty (30) days of the date that the other contractors or workers were sent onto the work or its site;

the Owner will pay the Contractor the cost, calculated in accordance with GC48 Determination of Cost – Price Table to GC50 Determination of Cost – Failing Negotiation, of the extra labour, plant and material that was necessarily incurred.

GC17 EXAMINATION OF WORK

GC17.1 If, at any time after the commencement of the work but prior to the expiry of the warranty or guarantee period, the Engineer has reason to believe that the work or any part thereof has not been performed in accordance with the Contract, the Engineer may have that work examined by an expert of his choice.

Page 14: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 11 V20181214

GC17.2 If, as a result of an examination of the work referred to in GC17.1, it is established that the work was not performed in accordance with the Contract, then, in addition to and without limiting or otherwise affecting any of the Owner's rights and remedies under the Contract either at law or in equity, the Contractor shall pay the Owner, on demand, all reasonable costs and expenses that were incurred by the Owner in having that examination performed.

GC18 CLEARING OF SITE

GC18.1 The Contractor shall maintain the work site in a tidy condition and free from the accumulation of waste material and debris, in accordance with any directions of the Engineer.

GC18.2 Before the issuance of the Interim Certificate of Completion referred to in GC44.1, the Contractor shall remove all the plant and material not required for the performance of the remaining work, and all waste material and other debris, and shall cause the work site to be clean and suitable for occupancy by the Owner's employees, unless otherwise stipulated in the Contract.

GC18.3 Before the issuance of the Final Certificate of Completion referred to in GC44.8, the Contractor shall remove from the work and its site all of the surplus plant and material and any waste material and other debris.

GC18.4 The Contractor's obligations described in GC18.1 to GC18.3 do not extend to waste material and other debris caused by the Owner's employees or contractors and workers referred to in GC16.1.

GC19 CONTRACTOR'S SUPERINTENDENT

GC19.1 The Contractor shall, forthwith upon the award of the Contract, designate a superintendent.

GC19.2 The Contractor shall forthwith notify the Engineer of the name, address and telephone number of the superintendent designated pursuant to GC19.1.

GC19.3 The superintendent designated pursuant to GC19.1 shall be in full charge of the operations of the Contractor in the performance of the work and is authorized to accept any notice, consent, order, direction, decision or other communication on behalf of the Contractor that may be given to the superintendent under the Contract.

GC19.4 The Contractor shall, until the work has been completed, keep a competent superintendent at the work site during working hours.

Page 15: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 12 V20181214

GC19.5 The Contractor shall, upon the request of the Engineer, remove any superintendent who, in the opinion of the Engineer, is incompetent or has been conducting himself improperly and shall forthwith designate another superintendent who is acceptable to the Engineer.

GC19.6 Subject to GC19.5, the Contractor shall not substitute a superintendent without the written consent of the Engineer.

GC19.7 A breach by the Contractor of GC19.6 entitles the Engineer to refuse to issue any Certificate referred to in GC44 Engineer's Certificates until the superintendent has returned to the work site or another superintendent who is acceptable to the Engineer has been substituted.

GC20 NATIONAL SECURITY

GC20.1 If the Owner is of the opinion that the work is of a class or kind that involves the national security, it may order the Contractor:

GC20.1.1 to provide the Owner with any information concerning persons employed or to be employed by it for purposes of the Contract; and

GC20.1.2 to remove any person from the work site if, in the opinion of the Owner, that person may be a risk to the national security.

GC20.2 Without limiting the generality of paragraph GC4.7, the Contractor shall, in all contracts with persons who are to be employed in the performance of the Contract, make provision for its performance of any obligation that may be imposed upon it under GC19 Contractor's Superintendent to GC21 Unsuitable Workers.

GC20.3 The Contractor shall comply with an order of the Owner under paragraph GC20.1.

GC21 UNSUITABLE WORKERS

GC21.1 The Contractor shall, upon the request of the Engineer, remove any person employed by it for purposes of the Contract who, in the opinion of the Engineer, is incompetent or has conducted himself improperly, and the Contractor shall not permit a person who has been removed to return to the work site.

GC22 INCREASED OR DECREASED COSTS

GC22.1 No amounts entered in the Price Table shall be increased or decreased by reason of any increase or decrease in the cost of the work that is brought about by an increase or decrease in the cost of labour, plant or material or the wage rates set out in or prescribed pursuant to the Labour Conditions.

Page 16: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 13 V20181214

GC22.2 Notwithstanding GC22.1 and GC35 Changes in Soil Conditions, all relevant amounts entered in the Price Table shall be adjusted in the manner provided in GC22.3, if any change in a tax imposed under the Excise Act, the Excise Tax Act, the Old Age Security Act, the Customs Act or the Customs Tariff or any Provincial Sales Tax legislation imposing a Retail Sales Tax on the purchase of tangible personal property incorporated into Real Property:

GC22.2.1 occurs after the date of the submission by the Contractor of its tender for the Contract;

GC22.2.2 applies to material; and

GC22.2.3 affects the cost to the Contractor of that material.

GC22.3 If a change referred to in GC22.2 occurs, all relevant amounts entered in the Price Table shall be increased or decreased by an amount equal to the amount that is established by an examination of the relevant records of the Contractor referred to in GC51 Records to be kept by Contractor to be the increase or decrease in the cost incurred that is directly attributable to that change.

GC22.4 For the purposes of GC22.2, where a tax is changed after the date of submission of the tender but public notice of the change has been given by the Minister of Finance before that date, the change shall be deemed to have occurred before the date of submission of the tender.

GC23 CANADIAN LABOUR AND MATERIAL

GC23.1 The Contractor shall use Canadian labour and material in the performance of the work to the full extent to which they are procurable, consistent with proper economy and the expeditious carrying out of the work.

GC23.2 Subject to GC23.1, the Contractor shall, in the performance of the work, employ labour from the locality where the work is being performed to the extent to which it is available, and shall use the offices of the Canada Employment Centres for the recruitment of workers wherever practicable.

GC23.3 Subject to GC23.1 and GC23.2, the Contractor shall, in the performance of the work, employ a reasonable proportion of persons who have been on active service with the armed forces of Canada and have been honourably discharged therefrom.

Page 17: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 14 V20181214

GC24 PROTECTION OF WORK AND DOCUMENTS

GC24.1 The Contractor shall guard and protect the work and its site, and protect the Contract, specifications, plans, drawings, information, material, plant and real property, whether or not they are supplied by the Owner to the Contractor, against loss or damage from any cause, and it shall not use, issue, disclose or dispose of them without the written consent of the Owner, except as may be essential for the performance of the work.

GC24.2 If any document or information given or disclosed to the Contractor is assigned a security rating by the person who gave or disclosed it, the Contractor shall take all measures directed by the Engineer to be taken to ensure the maintenance of the degree of security that is ascribed to that rating.

GC24.3 The Contractor shall provide all necessary security devices and assistance to any person authorized by the Owner to inspect or to take security measures in respect of the work and its site.

GC24.4 The Engineer may direct the Contractor to do such things and to perform such additional work as the Engineer considers reasonable and necessary to ensure compliance with or to remedy a breach of GC24.1 to GC24.3.

GC25 PUBLIC CEREMONIES AND SIGNS

GC25.1 The Contractor shall not permit any public ceremony in connection with the work without the prior consent of the Owner.

GC25.2 The Contractor shall not erect or permit the erection of any sign or advertising on the work site without the prior consent of the Engineer.

GC26 PRECAUTIONS AGAINST DAMAGE, FIRE AND OTHER HAZARDS

GC26.1 The Contractor shall, at its own expense, do whatever is necessary to ensure that:

GC26.1.1 no person, property, right, easement or privilege is injured, damaged or infringed by reason of the Contractor's activities in performing the Contract;

GC26.1.2 pedestrian and other traffic on any public or private road or waterway is not unduly impeded, interrupted or endangered by the performance or existence of the work or plant;

GC26.1.3 fire hazards in or about the work or its site are eliminated and, subject to any direction that may be given by the Engineer, any fire is promptly extinguished;

GC26.1.4 the health and safety of all persons employed in the performance of the work is not endangered by the method or means of its performance;

Page 18: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 15 V20181214

GC26.1.5 sufficient medical services be available on site at all times during working hours for all persons performing the work;

GC26.1.6 adequate sanitation measures are taken in respect of the work and its site; and

GC26.1.7 all stakes, buoys and marks placed on the work or its site by or under the authority of the Engineer are protected and are not removed, defaced, altered or destroyed.

GC26.2 The Engineer may direct the Contractor to do such things and to perform such additional work as the Engineer considers reasonable and necessary to ensure compliance with or to remedy a breach of GC26.1.

GC26.3 The Contractor shall, at its own expense, comply with a direction of the Engineer made under GC26.2.

GC27 INSURANCE

GC27.1 The Contractor shall, at its own expense, obtain and maintain insurance contracts in respect of the work and shall provide evidence thereof to the Engineer in accordance with the requirements of the Insurance Conditions.

GC27.2 The insurance contracts referred to in GC27.1 shall:

GC27.2.1 be in a form, of the nature, in the amounts, for the periods and containing the terms and conditions specified in the Insurance Conditions; and

GC27.2.2 provide for the payment of claims under such insurance contracts in accordance with GC28 Insurance Proceeds.

GC28 INSURANCE PROCEEDS

GC28.1 In the case of a claim payable under a Builders' Risk/Installation Floater (All Risk) insurance contract obtained and maintained by the Contractor pursuant to GC27 Insurance, the proceeds of the claim shall be paid directly to the Owner, and:

GC28.1.1 the monies so paid shall be held by the Owner for the purposes of the Contract; or

GC28.1.2 if the Owner decides that it must hold the proceeds, in which event they vest in the Owner absolutely.

GC28.2 In the case of a claim payable under a Comprehensive General Liability insurance contract obtained and maintained by the Contractor pursuant to GC27 Insurance, the proceeds of the claim shall be paid by the Insurer directly to the claimant.

Page 19: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 16 V20181214

GC28.3 If an election is made pursuant to GC28.1, the Owner may cause an audit to be made of the accounts of the Contractor and of the Owner in respect of the part of the work that was lost, damaged or destroyed for the purposes of establishing the difference, if any, between:

GC28.3.1 the aggregate of the amount of the loss or damage suffered or sustained by the Owner, including any costs incurred in respect of the clearing and cleaning of the work site and any other amount that is payable by the Contractor to the Owner under the Contract, minus any monies retained pursuant to GC28.1.2; and

GC28.3.2 the aggregate of the amounts payable by the Owner to the Contractor pursuant to the Contract up to the date of the loss or damage.

GC28.4 A difference that is established pursuant to GC28.3, shall be paid forthwith by the party who is determined by the audit to be the debtor to the party who is determined by the audit to be the creditor.

GC28.5 When payment of a deficiency has been made pursuant to GC28.4, all rights and obligations of the Owner and the Contractor under the Contract shall, with respect only to the part of the work that was the subject of the audit referred to in GC28.3, be deemed to have been expended and discharged.

GC28.6 If an election is not made pursuant to GC28.1.2 the Contractor shall, subject to GC28.7, clear and clean the work site and restore and replace the part of the work that was lost, damaged or destroyed at its own expense as if that part of the work had not yet been performed.

GC28.7 When the Contractor clears and cleans the work site and restores and replaces the work referred to in GC28.6, the Owner shall pay it out of the monies referred to in GC28.1 so far as they will thereunto extend.

GC28.8 Subject to GC28.7, payment by the Owner pursuant to GC28.7 shall be made in accordance with the Contract but the amount of each payment shall be 100% of the amount claimed, notwithstanding TP4.4.1 and TP4.4.2 of the Terms of Payment.

GC29 CONTRACT SECURITY

GC29.1 The Contractor shall obtain and deliver contract security to the Engineer in accordance with the provisions of the Contract Security Conditions.

GC29.2 If the whole or a part of the contract security referred to in GC29.1 is in the form of a security deposit, it shall be held and disposed of in accordance with GC43 Security Deposit - Forfeiture or Return and GC45 Return of Security Deposit.

GC29.3 If a part of the contract security referred to in GC29.1 is in the form of a labour and material payment bond, the Contractor shall post a copy of that bond on the work site.

Page 20: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 17 V20181214

GC30 CHANGES IN THE WORK

GC30.1 Subject to GC5 Amendments, the Engineer may, at any time before he issues his Final Certificate of Completion:

GC30.1.1 order work or material in addition to that provided for in the Drawings and Specifications; and

GC30.1.2 delete or change the dimensions, character, quantity, quality, description, location or position of the whole or any part of the work or material provided for in the Drawings and Specifications or in any order made pursuant to GC30.1.1,

if that additional work or material, deletion, or change are, in his opinion, consistent with the general intent of the original Contract.

GC30.2 The Contractor shall perform the work in accordance with such orders, deletions and changes that are made by the Engineer pursuant to GC30.1 from time to time as if they had appeared in and been part of the Drawings and Specifications.

GC30.3 The Engineer decides whether or not anything done or omitted by the Contractor pursuant to an order, deletion or change referred to in GC30.1 increased or decreased the cost of the work to the Contractor.

GC30.4 If the Engineer determines pursuant to GC30.3 that the cost of the work to the Contractor has been increased, the Owner will pay the Contractor the increased cost that the Contractor necessarily incurred for the additional work calculated in accordance with GC49 Determination of Cost – Negotiation or GC50 Determination of Cost – Failing Negotiation.

GC30.5 If the Engineer determines pursuant to GC30.3 that the cost of the work to the Contractor has been decreased, the Owner will reduce the amount payable to the Contractor under the Contract by an amount equal to the decrease in the cost caused by the deletion or change referred to in GC30.1.2 and calculated in accordance with GC49 Determination of Cost – Negotiation.

GC30.6 GC30.3 to GC30.5 are applicable only to a Contract or a portion of a Contract for which a Fixed Price Arrangement is stipulated in the Contract.

GC30.7 Any order, deletion or change referred to in GC30.1 shall be in writing, signed by the Engineer and given to the Contractor in accordance with GC11.2.

Page 21: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 18 V20181214

GC31 INTERPRETATION OF CONTRACT BY ENGINEER

GC31.1 If, at any time before the Engineer has issued the Final Certificate of Completion referred to in GC44.8, any question arises between the parties about whether anything has been done as required by the Contract or about what the Contractor is required by the Contract to do, and, in particular but without limiting the generality of the foregoing, about:

GC31.1.1 the meaning of anything in the drawings and specifications;

GC31.1.2 the meaning to be given to the drawings and specifications in case of any error therein, omission therefrom, or obscurity or discrepancy in their wording or intention;

GC31.1.3 whether or not the quality or quantity of any material or workmanship supplied or proposed to be supplied by the Contractor meets the requirements of the Contract;

GC31.1.4 whether or not the labour, plant or material provided by the Contractor for performing the work and carrying out the Contract are adequate to ensure that the work will be performed in accordance with the Contract and that the Contract will be carried out in accordance with its terms;

GC31.1.5 what quantity of any kind of work has been completed by the Contractor; or

GC31.1.6 the timing and scheduling of the various phases of the performance of the work and;

GC31.2 in respect of the work, the decision of the Engineer shall, subject to GC52 Dispute Resolution Procedure, be final and binding.

GC31.3 The Contractor shall perform the work in accordance with any decisions and directions of the Engineer that are made under GC31.1 and in accordance with any consequential decisions and directions given by the Engineer.

GC32 WARRANTY AND RECTIFICATION OF DEFECTS IN WORK

GC32.1 Without restricting any warranty or guarantee implied or imposed by law or contained in the Contract documents, the Contractor shall, at its own expense:

GC32.1.1 rectify and make good any defect or fault that appears in the work or comes to the attention of the Owner with respect to those parts of the work accepted in the framework of the Interim Certificate of Completion referred to in GC44.1 within twelve (12) months or any other deadline indicated in the Special Administrative Conditions, and this warranty shall start from the date indicated on the Interim Certificate of Completion as the interim work acceptance date;

Page 22: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 19 V20181214

GC32.1.2 rectify and make good any defect or fault that appears in or comes to the attention of the Owner in connection with those parts of the work that have not been completed to the satisfaction of the Engineer and described in the Interim Certificate of Completion referred to in GC44.1 within twelve (12) months or any other deadline indicated in the Special Administrative Conditions, and this warranty shall start from the date indicated on the Final Certificate of Completion referred to in GC44.8 as the final work acceptance date.

GC32.2 The Engineer may direct the Contractor to rectify and make good any defect or fault referred to in GC32.1 or otherwise covered by any other legal or contractual warranty or guarantee.

GC32.3 A direction referred to in GC32.2 shall be in writing, may include a stipulation in respect of the time within which a defect or fault is required to be rectified and made good by the Contractor.

GC32.4 The Contractor shall rectify and make good any defect or fault described in a direction given pursuant to GC32.2 within the time stipulated therein.

GC33 NON-COMPLIANCE BY CONTRACTOR

GC33.1 If the Contractor fails to comply with any decision or direction rendered or issued by the Engineer under the Contract, the Engineer may employ such methods as he deems advisable to do that which the Contractor failed to do.

GC33.2 The Contractor shall, on demand, pay the Owner an amount that is equal to the aggregate of all costs, expenses and damage incurred or sustained by the Owner by reason of the Contractor's failure to comply with any decision or direction referred to in GC33.1, including the cost of any methods employed by the Engineer pursuant to GC33.1.

GC34 PROTESTING ENGINEER'S DECISIONS

GC34.1 The Contractor may, in accordance with GC52 Dispute Resolution Procedure, protest a decision or direction rendered or issued by the Engineer under the Contract.

GC34.2 Any dispute that is not resolved on the date of issuance of the last Interim Certificate of Completion will be dealt with according to paragraphs GC52.3 et seq.

GC35 CHANGES IN SOIL CONDITIONS

GC35.1 Subject to GC35.2, no payment, other than a payment that is expressly stipulated in the Contract, shall be made by the Owner to the Contractor for any extra expense or any loss or damage incurred or sustained by the Contractor.

Page 23: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 20 V20181214

GC35.2 If the Contractor considers that there is a substantial difference between the information relating to soil conditions at the work site that is contained in the Drawings and Specifications or other documents supplied to the Contractor for its use in preparing its tender or a reasonable assumption of fact based thereon made by the Contractor, and the actual soil conditions encountered by the Contractor at the work site during the performance of the work, it shall, on the day that the soil conditions are observed and before they are modified, give written notice to the Engineer thereof.

GC35.3 The Engineer decides whether there is in fact a substantial difference and, if so, whether the difference increases or decreases the cost of the work for the Contractor.

GC35.4 If, in the opinion of the Engineer, the change increases the cost of the work, the Owner will make an extra payment to the Contractor in an amount that is calculated in accordance with GC47 Additions or Amendments to Price Table to GC50 Determination of Cost – Failing Negotiation.

GC35.5 If, in the opinion of the Engineer, the change decreases the cost of the work, the Owner will reduce the amount payable to the Contractor under the Contract by an amount determined according to the provisions of GC47 Additions or Amendments to Price Table to GC50 Determination of Cost – Failing Negotiation.

GC35.6 The Contractor shall perform the work in accordance with the decisions and directions of the Engineer.

GC35.7 If the Contractor fails to give the notice referred to in GC35.2, no extra payment will, in this case, be made thereto.

GC36 EXTENSION OF TIME

GC36.1 Subject to GC36.2, the Engineer may, on the application of the Contractor made before the day fixed by the Special Administrative Conditions for completion of the work or before any other date previously fixed under this General Condition, extend the time for its completion by fixing a new date if, in the opinion of the Engineer, causes beyond the control of the Contractor have delayed its completion.

GC36.2 An application referred to in GC36.1 shall be accompanied by the written consent of the bonding company whose bond forms part of the contract security.

GC37 ASSESSMENTS AND DAMAGES FOR LATE COMPLETION

GC37.1 For the purposes of this General Condition:

GC37.1.1 the work shall be deemed to be completed on the date that the Interim Certificate of Completion referred to in GC44.1 is issued; and

Page 24: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 21 V20181214

GC37.1.2 “period of delay” means the number of days commencing on the day fixed by the Special Administrative Conditions for completion of the work and ending on the day immediately preceding the day on which the work is completed but does not include any day within a period of extension granted pursuant to GC36.1, and any other day on which, in the opinion of the Engineer, completion of the work was delayed for reasons beyond the control of the Contractor.

GC37.2 If the Contractor does not complete the work by the day fixed for its completion by the Special Administrative Conditions but completes it thereafter, the Contractor shall pay the Owner an amount equal to the aggregate of:

GC37.2.1 all salaries, wages and travelling expenses incurred by the Owner in respect of persons overseeing the performance of the work during the period of delay;

GC37.2.2 the cost incurred by the Owner as a result of the inability to use the completed work for the period of delay; and

GC37.2.3 all other expenses and damages incurred or sustained by the Owner during the period of delay as a result of the work not being completed by the day fixed for its completion.

GC37.3 The Owner may waive its right to the whole or any part of the amount payable by the Contractor pursuant to GC37.2 if, in the Owner believes it is in the public interest to do so.

GC38 TAKING THE WORK OUT OF THE CONTRACTOR'S HANDS

GC38.1 The Owner may, at its sole discretion, by giving a notice in writing to the Contractor take all or any part of the work out of the Contractor's hands, and may employ such means as it sees fit to have the work completed if the Contractor:

GC38.1.1 has not, within six (6) days after receiving notice given by the Owner or the Engineer remedied any delay in the commencement or any default in the diligent performance of the work to the satisfaction of the Engineer;

GC38.1.2 has defaulted in the completion of any part of the work within the time fixed for its completion by the Contract;

GC38.1.3 has become insolvent;

GC38.1.4 has committed an act of bankruptcy, has been declared bankrupt or has made an assignment for the benefit of creditors;

GC38.1.5 has abandoned the work;

GC38.1.6 has made an assignment of the Contract without the consent required by GC3.1; or

Page 25: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 22 V20181214

GC38.1.7 has otherwise failed to observe or perform any of the provisions of the Contract.

GC38.1.8 without limiting the generality of paragraph GC38.1.7, in the course of the Contract, have its license limited within the meaning of the Building Act (CQLR, c. B-1.1), be named in the Register of Enterprises Ineligible for Public Contracts (“Registre des entreprises non admissibles aux contrats publics”) (RENA) within the meaning of the Act Respecting Contracting by Public Bodies (CQLR, c. C-65.1) or listed on the Ineligibility and Suspension List in accordance with the Ineligibility and Suspension Policy issued by PSPC;

GC38.1.9 fails to replace a subcontractor whose services it has retained counter to paragraph GC4.1.1 within the time limit specified by the Owner.

GC38.2 If the whole or any part of the work is taken out of the Contractor's hands pursuant to GC38.1:

GC38.2.1 the Contractor's right to any further payment that is due or accruing due under the Contract is, subject only to GC38.3, extinguished; and

GC38.2.2 the Contractor is liable to pay the Owner, upon demand, an amount that is equal to the amount of all loss and damage incurred or sustained by the Owner in respect of the Contractor's failure to complete the work.

GC38.3 If the whole or any part of the work that is taken out of the Contractor's hands pursuant to GC38.1 is completed by the Owner, the Engineer determines the amount, if any, of the holdback or a progress claim that had accrued and was due prior to the date on which the work was taken out of the Contractor's hands and that is not required for the purposes of having the work performed or of compensating the Owner for any other loss or damage incurred or sustained by reason of the Contractor's default. The Owner may pay the Contractor the amount determined not to be required pursuant to GC38.2.

GC39 EFFECT OF TAKING THE WORK OUT OF THE CONTRACTOR'S HANDS

GC39.1 The taking of the work or any part thereof out of the Contractor's hands pursuant to GC38 Taking the Work Out of the Contractor's Hands does not operate so as to relieve or discharge it from any obligation under the Contract or imposed upon it by law except the obligation to complete the performance of that part of the work that was taken out of its hands.

GC39.2 If the work or any part thereof is taken out of the Contractor's hands pursuant to GC38 Taking the Work Out of the Contractor's Hands, all plant and material and the interest of the Contractor in all real property, licences, powers and privileges acquired, used or provided by the Contractor under the Contract shall continue to be the property of the Owner without compensation to the Contractor.

Page 26: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 23 V20181214

GC39.3 When the Engineer certifies that any plant, material, or any interest of the Contractor referred to in GC39.2 is no longer required for the purposes of the work, or that it is not in the interests of the Owner to retain that plant, material, or interest, it shall revert to the Contractor.

GC40 SUSPENSION OF WORK BY OWNER

GC40.1 The Owner may, when in its opinion it is in the public interest to do so, require the Contractor to suspend performance of the work either for a specified or an unspecified period by giving a notice of suspension in writing to the Contractor.

GC40.2 When a notice referred to in GC40.1 is received by the Contractor, it shall suspend all operations in respect of the work except those that, in the opinion of the Engineer, are necessary for the care and preservation of the work, plant and material.

GC40.3 The Contractor shall not, during a period of suspension, remove any part of the work, plant or material from its site without the consent of the Engineer.

GC40.4 If a period of suspension is thirty (30) days or less, the Contractor shall, upon the expiration of that period, resume the performance of the work and it is entitled to be paid the extra cost, calculated in accordance with GC48 Determination of Cost – Price Table to GC50 Determination of Cost – Failing Negotiation of any labour, plant and material necessarily incurred by it as a result of the suspension.

GC40.5 If, upon the expiration of a period of suspension of more than thirty (30) days, the Owner and the Contractor agree that the performance of the work will be continued by the Contractor, the Contractor shall resume performance of the work subject to any terms and conditions agreed upon by the Owner and the Contractor.

GC40.6 If, upon the expiration of a period of suspension of more than thirty (30) days, the Owner and the Contractor do not agree that performance of the work will be continued by the Contractor or upon the terms and conditions under which the Contractor will continue the work, the notice of suspension shall be deemed to be a notice of termination pursuant to GC41 Termination of Contract.

GC41 TERMINATION OF CONTRACT

GC41.1 The Owner may terminate the Contract at any time by giving a notice of termination in writing to the Contractor.

GC41.2 When a notice referred to in GC41.1 is received by the Contractor, it shall, subject to any conditions stipulated in the notice, forthwith cease all operations in performance of the Contract.

GC41.3 If the Contract is terminated pursuant to GC41.1 the Owner will pay the Contractor, subject to GC41.4, an amount equal to:

Page 27: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 24 V20181214

GC41.3.1 the cost to the Contractor of all labour, plant and material supplied by it under the Contract up to the date of termination in respect of a Contract or part thereof for which a Unit Price Arrangement is stipulated in the Contract:

GC41.3.2 or the lesser of:

GC41.3.2.1 an amount, calculated in accordance with the Terms of Payment, that would have been payable to the Contractor had it completed the work; and

GC41.3.2.2 an amount that is determined to be due to the Contractor pursuant to GC49 Determination of Cost – Negotiation in respect of a Contract or part thereof for which a Fixed Price Arrangement is stipulated in the Contract;

less the aggregate of all amounts that were paid to the Contractor by the Owner and all amounts if there is any that are due to the Owner from the Contractor pursuant to the Contract.

GC41.4 If the Owner and the Contractor are unable to agree about an amount referred to in GC41.3 that amount shall be determined by the method referred to in GC50 Determination of Cost – Failing Negotiation.

GC42 CLAIMS AGAINST AND OBLIGATIONS OF THE CONTRACTOR OR SUBCONTRACTOR

GC42.1 The Owner may, in order to satisfy lawful claims against the Contractor or a subcontractor arising out of the performance of the Contract, pay in accordance with GC42.6, any amount that is due to the Contractor pursuant to the Contract directly to the claimants against the Contractor or the subcontractor.

GC42.2 A payment made pursuant to GC42.1 is, to the extent of the payment, a discharge of the Owner's liability to the Contractor under the Contract and may be deducted from the amounts payable to the Contractor under the Contract.

GC42.3 To the extent that the circumstances of the work being performed for the Owner permit, the Contractor shall comply with all laws in force in the province where the work is being performed relating to payment periods, mandatory holdbacks, and creation and enforcement of mechanics' liens or, in respect of the Province of Quebec, the law relating to construction legal hypothecs.

GC42.4 The Contractor shall discharge all its lawful obligations and shall satisfy all lawful claims against it arising out of the performance of the work at least as often as the Contract requires the Owner to pay the Contractor.

GC42.5 The Contractor shall, whenever requested to do so by the Engineer, make a statutory declaration deposing to the existence and condition of any obligations and claims referred to in GC42.4.

Page 28: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 25 V20181214

GC42.6 GC42.1 shall only apply to claims and obligations that have been received by the Engineer in writing before payment to the Contractor pursuant to TP4.10 and within one hundred and twenty (120) days after a claimant:

GC42.6.1 should have been paid in full under its contract with the Contractor or a subcontractor where the claim is for money that was lawfully required to be held back from the claimant either by contract or by law; or

GC42.6.2 performed the last of the service, work or labour, or furnished the last of the material pursuant to its contract with the Contractor or subcontractor, where the claim is not for money referred to in GC42.6.1.

GC43 SECURITY DEPOSIT – FORFEITURE OR RETURN

GC43.1 If

GC43.1.1 the work is taken out of the Contractor's hands pursuant to GC38 Taking the Work Out of the Contractor's Hands:

GC43.1.2 the Contract is terminated pursuant to GC41 Termination of Contract; or

GC43.1.3 the Contractor is in breach of or in default under the Contract;

the Owner may convert the security deposit, if any, to its own use.

GC43.2 If the Owner converts the contract security pursuant to GC43.1, the amount realized shall be deemed to be an amount due to the Owner by the Contractor under the Contract.

GC43.3 Any balance of an amount referred to in GC43.2 that remains after payment of all costs, losses, damage and claims of the Owner or others shall be paid by the Owner to the Contractor if, in the opinion of the Engineer, it is not required for the purposes of the Contract.

GC44 ENGINEER'S CERTIFICATES

GC44.1 When the following conditions are met and, subject to the terms and conditions set out in article 5.34 of the Standard Administrative Conditions, the Engineer shall issue to the Contractor an Interim Certificate of Completion when:

GC44.1.1 the Engineer determines that the work is sufficiently completed to be used according to its intended use;

GC44.1.2 the estimated value of the work to be made good and completed does not exceed, subject to GC44.2:

Page 29: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 26 V20181214

GC44.1.2.1 5% of the value of the Contract, if this value is less than $2,000,000 (before taxes) on the calculation date; or

GC44.1.2.2 2% of the value of the Contract, if this value is equal to or greater than $2,000,000 (before taxes) on the calculation date;

GC44.1.3 the documents and items to be delivered upon completion of the work have been delivered in accordance with article 5.30 Closeout documents and elements to submit of the Standard Administrative Conditions;

GC44.1.4 the written warranties required by the Contract have been provided;

GC44.1.5 the training required as per the contract documents has been provided and the structure is operational, as applicable.

GC44.2 If the work or a substantial part thereof is sufficiently completed to be used for its intended use and the work to be completed cannot be completed because of other conditions beyond the control of the Contractor, then the value of this work shall be deducted from the calculation set out in paragraph GC44.1 for the purpose of the interim acceptance of the work.

GC44.3 The Interim Certificate of Completion referred to in GC44.1 shall describe the parts of the work not completed to the satisfaction of the Engineer and all things that must be done by the Contractor:

GC44.3.1 so that the Final Certificate of Completion referred to in GC44.8 will be issued; and

GC44.3.2 before the warranty period referred to in GC32.1.2 shall commence for the said parts and all the said things to be executed by the Contractor.

GC44.4 Depending on the nature of the work and the circumstances, the Special Administrative Conditions of the Contract may set out that several Interim Certificates of Completion may be issued.

GC44.5 The Engineer may, in addition to the parts of the work described in the Interim Certificate of Completion referred to in GC44.1, require the Contractor to rectify any other parts of the work not completed to its satisfaction and to do any other things that are necessary for the satisfactory completion of the work.

GC44.6 If the Contract or a part thereof is subject to a Unit Price Arrangement, the Engineer measures and records the quantities of labour, plant and material, performed, used and supplied by the Contractor in performing the work and shall, at the request of the Contractor, inform it of those measurements.

GC44.7 The Contractor shall assist and co-operate with the Engineer in the performance of its duties referred to in GC44.6 and shall be entitled to inspect any record made by the Engineer pursuant to GC44.6.

Page 30: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 27 V20181214

GC44.8 Subject to the terms and conditions in article 5.34 of the Standard Administrative Conditions, the Engineer shall issue a Final Certificate of Completion to the Contractor when the following conditions have been met:

GC44.8.1 the defects have been corrected;

GC44.8.2 no work remains to be completed; and

GC44.8.3 the Contractor has complied with the Contract and all orders and instructions given by the Engineer, to the Engineer’s satisfaction.

GC44.9 After the Engineer has issued the Final Certificate of Completion referred to in GC44.8, he shall, subject to the application of GC44.6, issue a Final Certificate of Measurement.

GC44.10 The Final Certificate of Measurement referred to in GC44.9 shall:

GC44.10.1 contain the aggregate of all measurements of quantities referred to in GC44.6; and

GC44.10.2 be binding upon and conclusive between the Owner and the Contractor as to the quantities referred to therein.

GC45 RETURN OF SECURITY DEPOSIT

GC45.1 After the Interim Certificate of Completion referred to in GC44.1 has been issued, the Owner will, if the Contractor has conformed to its commitment and obligations, return to the Contractor all or any part of the security deposit that, in the opinion of the Engineer, is not required for the purposes of the Contract.

GC45.2 After the Final Certificate of Completion referred to in GC44.8 has been issued, the Owner will return to the Contractor the remainder of any security deposit unless the Contract stipulates otherwise.

GC46 CLARIFICATION OF TERMS IN GC47 TO GC50

GC46.1 For the purposes of GC47 Additions or Amendments to Price Table to GC50 Determination of Cost – Failing Negotiation;

GC46.1.1 “Price Table” means the table contained in the Contractor’s Tender Forms, subject to any amendment mentioned in the Notice of Contract Award; and

GC46.1.2 “plant” does not include tools customarily provided by a tradesman in practicing his trade.

Page 31: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 28 V20181214

GC47 ADDITIONS OR AMENDMENTS TO PRICE TABLE

GC47.1 Where a Unit Price Arrangement applies to the Contract or a part thereof the Engineer and the Contractor may, by an agreement in writing:

GC47.1.1 add classes of labour, plant or material, and units of measurement, prices per unit and estimated quantities to the Price Table if any labour, plant or material that is to be included in the Final Certificate of Measurement referred to in GC44.9 is not included in any class of labour, plant or material set out in the Price Table; or

GC47.1.2 subject to GC47.2, amend a price per unit set out in the Price Table for any class of labour, plant or material included therein if an estimated quantity is set out therein for that class of labour, plant or material, and the Final Certificate of Measurement referred to in GC44.9 shows or is expected to show that the total quantity of that class of labour, plant or material actually performed, used or supplied by the Contractor in performing the work is:

GC47.1.2.1 less than 85% of that estimated total quantity; or

GC47.1.2.2 in excess of 115% of that estimated total quantity.

GC47.2 The quantities of the Tender Forms may be approximate and may be useful for the purposes of comparing tenders; a variation in a quantity may lead to the modification of its unit price solely in accordance with clause GC47 Additions or Amendments to Price Table on condition the result of multiplying the unit price in the tender by the corresponding quantity in the tender exceeds the total price tendered for the work by more than 5%.

GC47.3 If the Engineer and the Contractor do not agree as contemplated in GC47.1, the Engineer determines the class and the unit of measurement of the labour, plant or material and the price per unit therefor shall be determined in accordance with GC50 Determination of Cost – Failing Negotiation.

GC47.4 The payment for an amendment that is made necessary by GC47.1.2.1 shall in no case exceed the amount which would be payable if 85% of the estimated quantity was performed.

GC48 DETERMINATION OF COST – PRICE TABLE

GC48.1 Whenever, for the purposes of the Contract it is necessary to determine the cost of labour, plant or material, it shall be determined by multiplying the quantity of that labour, plant or material expressed in the unit set out in column 3 of the Price Table by the price of that unit set out in column 4 of the Price Table.

Page 32: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 29 V20181214

GC49 DETERMINATION OF COST – NEGOTIATION

GC49.1 If the method described in GC48 Determination of Cost – Price Table cannot be used because the labour, plant or material is of a kind or class that is not set out in the Price Table, the cost of that labour, plant or material for the purposes of the Contract shall be the amount agreed upon from time to time by the Contractor and the Engineer.

GC49.2 For the purposes of GC49.1, the Contractor, when requested by the Engineer, shall provide the Engineer with a detailed estimate of the cost to it of the labour, plant and material referred to in GC49.1. The detailed estimate shall contain a sufficient description of the facts and circumstances, as well as the supporting documentation, in order for the Engineer to be able to determine whether the estimate is fair or not, and the Contractor shall, for this purpose, provide any other information that may be required by the Engineer.

GC49.3 In order to establish the cost of the work, plant and materials involved, the parties shall refer to the provisions of GC50 Determination of Cost – Failing Negotiation as a guide, but the expense items therein described shall not, however, constitute a list of expense that are inclusive to any amendment or change.

GC49.4 In this regard, the Contractor shall keep the detailed and full records necessary to document the cost of the work, plant and materials involved, in accordance with GC51 Records to be kept by Contractor.

GC50 DETERMINATION OF COST – FAILING NEGOTIATION

GC50.1 If the Contractor and the Engineer or the methods described in GC47 Additions or Amendments to Price Table, GC48 Determination of Cost – Price Table, or GC49 Determination of Cost – Negotiation fail for any reason to achieve a determination of the cost of labour, plant and material for the purposes referred to therein, that cost shall be equal to the aggregate of:

GC50.1.1 all reasonable and proper amounts, net of all Federal and Provincial tax credits, actually expended or legally payable by the Contractor in respect of the labour, plant or material that falls within one of the classes of expenditure described in GC50.2 that are directly attributable to the performance of the Contract; and

GC50.1.2 an allowance for profit and all other expenditures or costs, including overhead, general administration costs, financing and interest charges, and every other cost, charge and expense, but not including those referred to in GC50.1.1 or of a class referred to in GC50.2, in an amount that is equal to 10% of the sum of the expenses referred to in GC50.1.1.

GC50.2 For purposes of GC50.1.1 the classes of expenditure that may be taken into account in determining the cost of labour, plant and material are:

GC50.2.1 payments to subcontractors;

Page 33: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 30 V20181214

GC50.2.2 wages, salaries and travelling expenses of employees of the Contractor while they are actually and properly engaged on the work, other than wages, salaries, bonuses, living and travelling expenses of personnel of the Contractor generally employed at the head office or at a general office of the Contractor unless they are engaged at the work site with the approval of the Engineer;

GC50.2.3 assessments payable under any statutory authority relating to workers' compensation, unemployment insurance, pension plan or holidays with pay;

GC50.2.4 rent that is paid for plant or an amount equivalent to the said rent if the plant is owned by the Contractor that is necessary for and used in the performance of the work, if the rent or the equivalent amount is reasonable and use of that plant has been approved by the Engineer;

GC50.2.5 payments for maintaining and operating plant necessary for and used in the performance of the work, and payments for effecting such repairs thereto as, in the opinion of the Engineer, are necessary to the proper performance of the Contract other than payments for any repairs to the plant arising out of defects existing before its allocation to the work;

GC50.2.6 payments for material that is necessary for and incorporated in the work, or that is necessary for and consumed in the performance of the Contract;

GC50.2.7 payments for preparation, delivery, handling, erection, installation, inspection, protection and removal of the plant and material necessary for and used in the performance of the Contract;

GC50.2.8 any other payments made by the Contractor with the approval of the Engineer that are necessary for the performance of the Contract.

GC50.3 The cost of the work, plant and materials involved shall be determined on the basis of the actual expenses incurred and the savings made by the Contractor in the execution of the amendment or change.

GC50.4 In this regard, the Contractor shall keep the detailed and full records necessary to document the cost of the work, plant and materials involved, in accordance with GC51 Records to be kept by Contractor.

Page 34: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 31 V20181214

GC51 RECORDS TO BE KEPT BY CONTRACTOR

GC51.1 The Contractor shall :

GC51.1.1 maintain full records of its estimated and actual cost of the work together with all tender calls, quoted prices, Contracts, correspondence, invoices, receipts and vouchers relating thereto;

GC51.1.2 make all records and material referred to in GC51.1.1 available for audit and inspection by the Owner;

GC51.1.3 allow any of the persons referred to in GC51.1.2 to make copies of and to take extracts from any of the records and material referred to in GC51.1.1; and

GC51.1.4 furnish any person referred to in GC51.1.2 with any information he may require from time to time in connection with such records and material.

GC51.2 The records maintained by the Contractor pursuant to GC51.1.1 shall be kept intact by the Contractor until the expiration of two (2) years after the date that the Final Certificate of Completion referred to in GC44.8 was issued or until the expiration of such other period of time as the Owner may direct.

GC51.3 The Contractor must see to that all subcontractors and all other persons directly or indirectly controlled by or affiliated with the Contractor and all persons directly or indirectly having control of the Contractor to comply with GC51.1 and GC51.2 as if they were the Contractor.

GC52 DISPUTE RESOLUTION PROCEDURE

GC52.1 This procedure shall apply to any dispute or disagreement between the Contractor and the Owner concerning the performance of the work or the obligations of the parties under the Contract and, in particular but without limiting the generality of the foregoing, concerning any decision or direction rendered or issued by the Engineer under the Contract or by any person specially authorized by the Engineer and who directly supervises the execution of the work or the administration or management of the Contract.

GC52.1.1 The parties agree to maintain open and honest communication throughout the performance of the Contract.

GC52.1.2 The parties agree to consult and co-operate with each other in the performance of the work and the resolution of problems or differences that may arise.

Page 35: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 32 V20181214

GC52.1.3 The parties shall make all reasonable efforts to resolve their dispute by amicable negotiations and agree to provide, without prejudice to their rights, frank, candid and timely disclosure of all relevant facts, information and documents to facilitate the negotiations.

GC52.2 During the performance of the work:

GC52.2.1 if the Contractor considers itself aggrieved in any way by the terms of the Contract, it shall, in all cases, as soon as possible but no later than ten (10) days of the date on which the decision or direction was rendered or issued by the Engineer, or of the date of commencement of the difficulty which, in its opinion, warrants a notice of dispute, issue a written notice setting forth and giving the reasons for the grievance. This notice of dispute shall be signed by the Contractor and communicated to the Owner.

GC52.2.1.1 The notice must be sufficiently detailed and substantiated to enable the Owner to make the decisions or take the actions required under the circumstances.

GC52.2.1.2 The notice shall specify the anticipated changes to the detailed work schedule, even, where applicable, in a preliminary manner.

GC52.2.1.3 The notice shall contain a sufficient description of the facts and circumstances that substantiate the grievance in order for the Owner to be able to undertake the review and determine whether the grievance is justified or not.

GC52.2.1.4 To that end, the Contractor shall promptly provide any other information that the Owner may require.

GC52.2.2 The Contractor and the Owner shall attempt to settle a dispute that arises during the course of the work through negotiations. If the persons who, up to that point, have assumed the administration of the Contract are unable to reach an agreement, the parties shall then involve at least one officer of the Contractor and at least one senior manager representing the Owner.

GC52.2.2.1 The Contractor undertakes to provide any other information or document required by the Owner within the period thereby stipulated or otherwise agreed upon.

GC52.2.3 After having reviewed the notice of dispute, the Owner informs the Contractor in writing of its position on the dispute and, where applicable, proposes a settlement solution to the Contractor.

GC52.2.3.1 Subject to GC52.2.3.2, if the Owner determines that the Contractor's grievance is well founded, it will reimburse the Contractor for the cost of the work, plant and additional materials incurred by the Contractor in carrying out the decision or direction that was the subject of the grievance.

Page 36: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 33 V20181214

GC52.2.3.2 The cost mentioned in GC52.2.3.1 shall be calculated in accordance with the provisions of GC47 Additions or Amendments to Price Table to GC50 Determination of Cost – Failing Negotiation.

GC52.2.4 When an agreement is reached, the Owner transmits a rider to the Contractor.

GC52.2.5 Any dispute that is still outstanding on the date of issuance of the last Interim Certificate of Completion will be dealt with according to GC52.3 et seq.

GC52.2.6 Any grievance by the Contractor under GC52.2 does not relieve the Contractor from complying with the decision or direction rendered or issued by the Engineer in respect of this grievance:

GC52.2.6.1 the grievance may not be used as a pretext for the Contractor to slow down the progress of the work or cease the performance of the Contract or any part thereof, even that part that is the subject of the dispute;

GC52.2.6.2 if the Contractor protests pursuant to GC52.2, any compliance by the Contractor with the decision or direction that was protested shall not be construed as an admission by the Contractor of the correctness of that decision or direction and may not constitute a plea of inadmissibility if the dispute is eventually referred to mediation, to arbitration or to a tribunal.

GC52.3 After the completion of the work:

GC52.3.1 if the Contractor still considers itself aggrieved in any way by the terms of the Contract, the Contractor shall, no later than sixty (60) days from the date of issuance of the last Interim Certificate of Completion, deliver to the Owner a detailed claim setting forth and regrouping, without limitation, the following information and documents for each outstanding dispute:

GC52.3.1.1 a description, history and explanation of the dispute as to when, how and why the problem occurred, from the Contractor's point of view, as well as the position taken by the Owner;

GC52.3.1.2 the amount claimed and, where applicable, details of the calculation methods used;

GC52.3.1.3 the effects on the detailed work schedule, determined by means of a delay analysis performed according to an appropriate methodology;

GC52.3.1.4 all supporting documentation in support of its representations;

GC52.3.1.5 an affidavit, signed by an officer of the Contractor, certifying that all information therein contained is true, correct and complete;

Page 37: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 34 V20181214

GC52.3.1.6 an undertaking to provide any other information or documents required by the Owner within the period thereby stipulated.

GC52.3.2 if the Contractor fails to submit a detailed claim within the time limit stipulated in GC52.3.1, the Contractor shall be deemed not to consider being aggrieved in any way by the terms of the Contract and shall be deemed to expressly hold the Owner harmless against any claim relating to the Contract.

GC52.3.3 Following the submission of its detailed claim, the Contractor shall provide the Owner, within the period specified by the latter, with any other information or document required by the Owner.

GC52.3.4 If, within four (4) months from the date of issuance of the last Interim Certificate of Completion, or within any additional period granted by the Owner, the claim does not contain all information and documents referred to in GC52.3.1 in a clear, detailed and complete manner, the Contractor's claim will be deemed inadmissible and will be rejected by the Owner.

GC52.3.5 To the extent that the detailed claim is clear, precise and complete, and accompanied by all supporting documentation, the Owner will study the detailed claim submitted by the Contractor.

GC52.3.5.1 If the Owner determines that the Contractor's detailed claim is well founded, in whole or in part, it will reimburse the Contractor for the cost of the work, plant and materials, calculated in accordance with the provisions of GC47 Additions or Amendments to Price Table to GC50 Determination of Cost – Failing Negotiation.

GC52.3.5.2 The Owner will inform the Contractor in writing of its decision within six (6) months from the date of receipt by the Owner of the last information or document transmitted by the Contractor.

GC52.3.6 Notwithstanding GC52.3.1, the Contractor shall, within sixty (60) days following the issuance of the Final Certificate of Completion referred to in paragraph GC44.8, provide the Owner with the information and documents concerning an outstanding dispute relating to work performed after the issuance of the last Interim Certificate of Completion referred to in paragraph GC44.1.

GC52.4 Confidentiality

GC52.4.1 Unless otherwise required by law, all information exchanged by the parties and representatives thereof under GC52 Dispute Resolution Procedure, by whatever means, shall be without prejudice and in a confidential manner.

GC52.4.2 The parties and their legal advisers or representatives shall protect the confidentiality of all matters and documents disclosed, except where disclosure thereof is necessary for the implementation of any agreement entered into by the parties or required by law.

Page 38: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 35 V20181214

GC52.4.3 However, the admissibility or disclosure of evidence which may otherwise be received as evidence or whose production may be required in the course of an examination or arbitral or legal proceedings is not affected by the use of this evidence in the context of GC52 Dispute Resolution Procedure.

GC52.4.4 Neither party shall make a recording or transcript, record minutes or otherwise document a negotiation session.

GC52.5 Subsequent Proceedings

GC52.5.1 The parties shall not rely on or introduce as evidence, in any mediation or any arbitral or judicial proceeding,

GC52.5.1.1 any documents of other parties that are not otherwise producible in the course of such proceedings;

GC52.5.1.2 any views expressed or suggestions made by any party in respect of a possible settlement of the issues in dispute;

GC52.5.1.3 any admission made by any party, during negotiations or otherwise, unless the admitting party has expressly consented thereto;

GC52.5.1.4 the fact that any party has indicated a willingness to make or accept a proposal or recommendation for settlement.

GC52.5.2 Any proposal or offer of settlement, whether accepted or not, is made subject to the respective rights of the parties, without prejudice or admission of liability. The Owner reserves the right to modify it and even to remove it completely.

GC52.6 Mediation and Arbitration

GC52.6.1 The parties agree to consider the use of mediation or arbitration before resorting to legal action to settle any dispute that has not been resolved under GC52.3.

GC52.6.2 In this regard, the parties agree to meet to examine whether one of these means of settlement, or any other private dispute resolution, should be used to settle any outstanding dispute.

GC52.6.3 If the parties agree to submit any outstanding dispute to arbitration, the arbitral proceedings shall be governed and conducted in accordance with the Commercial Arbitration Act (R.S.C. 1985, c. 17 (2nd Supp.)).

Page 39: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 36 V20181214

GC52.7 Legal Proceedings

GC52.7.1 Subject to the provisions of GC52.3.2, either party may bring such legal action or proceedings as it deems appropriate, including, without limiting the scope of the foregoing, any legal action that it could have instituted immediately, had it not been for the provisions of this GC52 Dispute Resolution Procedure.

GC53 CONFLICT OF INTEREST

GC53.1 It is a term of this Contract that no individual, for whom the post-employment provisions of the conflict of interest and post-employment Code for Public Office Holders or the Values and Ethics Code for the Public Sector apply, shall derive a direct benefit from this Contract unless that individual is in compliance with the applicable post-employment provisions.

GC54 CONTRACTOR STATUS

GC54.1 The Contractor shall be engaged under the Contract as an independent contractor.

GC54.2 The Contractor and any employee of the said Contractor is not engaged under the Contract as an employee, servant or agent of the Owner.

GC54.3 For the purposes of GC54.1 and GC54.2, the Contractor shall be solely responsible for any and all payments and deductions required to be made by law including those required by Canada or Québec Pension Plans, Unemployment Insurance, Worker's Compensation or Income Tax.

GC55 HUMAN REMAINS, ARCHAEOLOGICAL REMAINS AND ITEMS OF HISTORICAL OR SCIENTIFIC INTEREST

GC55.1 For the purposes of this clause:

GC55.1.1 “human remains” means the whole or any part of a deceased human being, irrespective of the time that has elapsed since death;

GC55.1.2 “archaeological remains” are items, artifacts or things made, modified or used by human beings in antiquity and may include, but not be limited to stone, wood or iron structures or monuments, dump deposits, bone artifacts, weapons, tools, coins and pottery;

GC55.1.3 “items of historical or scientific interest” are naturally occurring or manufactured objects or things of any age that are not archaeological remains but may be of interest to society because of their historical or scientific significance, value, rarity, natural beauty or other quality;

Page 40: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 37 V20181214

GC55.2 If, during the course of the work, the Contractor encounters any object, item or thing which is described in GC55.1, or which resembles any object, item or thing described in GC55.1, the Contractor shall:

GC55.2.1 take all reasonable steps, including stopping work in the affected area, to protect and preserve the object, item or thing;

GC55.2.2 immediately notify the Engineer of the circumstances in writing; and

GC55.2.3 take all reasonable steps to minimize additional costs which may accrue as a result of any work stoppage.

GC55.3 Upon receipt of a notification in accordance with GC55.2.2, the Engineer shall, in a timely manner, determine whether the object, item or thing is one described in, or contemplated by, GC55.1, and shall notify the Contractor in writing of any action to be performed, or work to be carried out by, the Contractor as a result of the Engineer's determination.

GC55.4 The Engineer may, at any time, enlist the services of experts, particularly an archaeologist or historian as appropriate, to assist in the investigation, examination, taking of measurements or other such recordings, placing of permanent protection around or removing of the object, item or thing encountered by the Contractor, and monitoring in case of further discoveries, and the Contractor shall, to the satisfaction of the Engineer, allow them access and cooperate with them in the carrying out of their duties and obligations.

GC55.5 Human remains, archaeological remains and items of historic or scientific interest encountered at the site of the work shall remain the property of the Owner.

GC55.6 Except as may be otherwise provided for in the Contract, the provisions of GC30 Changes in the work shall apply.

GC56 CONTAMINATED SITE CONDITIONS

GC56.1 For the purposes of this clause, a contaminated site condition exists when toxic, radioactive or other hazardous substances or materials, or other pollutants, are found to be present at the site of the work to the extent that they constitute a hazard, or potential hazard, to the environment, property, or the health and safety of any person.

GC56.2 If the Contractor encounters a contaminated site condition, or has reasonable grounds to believe that a contaminated site condition exists at the site of the work, the Contractor shall:

GC56.2.1 take all reasonable steps, including stopping the work, to ensure that no person suffers injury, sickness or death, and that neither property nor the environment is injured or destroyed as a result of the contaminated site conditions;

Page 41: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 38 V20181214

GC56.2.3 immediately notify the Engineer of the circumstances in writing;

GC56.2.4 take all reasonable steps to minimize additional costs which may accrue as a result of any work stoppage.

GC56.3 Upon receipt of a notification in accordance with GC56.2.2, the Engineer shall determine, in a timely manner, whether a contaminated site condition as described in, or contemplated by GC56.1 exists, and shall notify the Contractor in writing of any action to be taken, or work to be performed, by the Contractor as a result of the Engineer's determination.

GC56.4 If the Contractor's services are required by the Engineer, the Contractor shall follow the direction of the Engineer with regard to any excavation, treatment and disposal of the contaminated substances or materials.

GC56.5 The Engineer may at any time enlist the services of experts and specialty contractors to assist in determining the existence of, and the extent and treatment of the contaminated site conditions, and the Contractor shall, to the satisfaction of the Engineer, allow them access and cooperate with them in the carrying out of their duties and obligations.

GC56.6 Except as may be otherwise provided for in the Contract, the provisions of GC30 Changes in the work shall apply.

GC57 APPLICABLE LAWS

GC57.1 The Contractor shall comply with all legislative and regulatory provisions whether federal, provincial or municipal applicable to the performance of the work.

GC57.2 Unless otherwise provided in the Contract, the Contractor shall obtain all permits and hold all certificates and licences for the performance of the work.

GC58 INTEGRITY PROVISIONS – CONTRACT

GC58.1 Statement

GC58.1.1 The Contractor undertakes to comply with the terms of GC58 relating to integrity, which is rooted, with some modifications, in the Ineligibility and Suspension Policy issued by PSPC and available at the following website: https://www.tpsgc-pwgsc.gc.ca/ci-if/politique-policy-eng.html. The Contractor further undertakes to comply with the excerpts from the Code of Conduct for Procurement issued by PSPC and attached in Appendix 2-II of the Instructions to Tenderers.

Page 42: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 39 V20181214

GC58.1.2 The Contractor certifies that it understands that the commission of certain acts or offences and the fact of having pleaded guilty to or having been convicted of certain offences, a false statement in its tender under the Contract or failure to keep up to date the information required herein may result in a withdrawal of the work for default under GC38 Taking the Work out of the Contractor’s Hands. In the event that the Contractor has made a false statement in its tender or under the Contract, fails to keep up to date the information required herein or if the Contractor or any of the Contractor’s Affiliates fails to remain free and clear of the convictions specified in GC58 relating to integrity, during the term of the Contract, the Contractor will be considered in default and the Owner will have the right to withdraw the work from the Contractor under GC38 Taking the Work out of the Contractor’s Hands. The Contractor acknowledges that a withdrawal of the work does not restrict the right of the Owner to exercise any other remedies available to the latter against the Contractor and the Contractor agrees to immediately remit the advance payments made.

GC58.2 List of Names

GC58.2.1 In accordance with Article 2.12.3 List of Names of the Instructions to Tenderers, the Contractor shall immediately inform the Owner, in writing, of any changes in the list of the names of the directors and of the owners during the term of the Contract.

GC58.3 Verification of Information

GC58.3.1 The Contractor certifies that it is informed, and that its Affiliates are informed, that the Owner may, at any time during the term of the Contract, verify the information provided by the Contractor, notably the information on the acts, convictions and conditional or absolute discharges specified in GC58 relating to integrity. The Owner may request further information, consent forms and other evidence proving the Contractor’s identity and eligibility to continue the Contract with the Owner.

GC58.4 Lobbying Act

GC58.4.1 The Contractor certifies that neither the Contractor nor any of the Contractor's Affiliates have, at any time during the term of the Contract, been convicted of or pleaded guilty to an offence pursuant to paragraph 14(1), with respect to sections 5 or 7 of the Lobbying Act (R.S.C., 1985, c. 44 (4th Supp.)).

GC58.5 Canadian Offences Resulting in a Legal Incapacity

GC58.5.1 The Contractor certifies that neither the Contractor nor any of the Contractor's Affiliates have been convicted of or pleaded guilty to an offence under any of the following provisions, which would result in a legal incapacity as defined by paragraph 750(3) of the Criminal Code of Canada (R.S.C., 1985, c. C-46) and for which they have not received pardon or obtained discharge in accordance with paragraph GC58.10 Canadian Pardons and Discharges:

Page 43: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 40 V20181214

GC58.5.1.1 subsection 80(1)d) (False entry, certificate or return), subsection 80(2) (Fraud against Her Majesty) or section 154.01 (Fraud against Her Majesty) of the Financial Administration Act (R.S.C., 1985, c. F-11); or

GC58.5.1.2 section 121 (Frauds on the government and Contractor subscribing to election fund), section 124 (Selling or purchasing office), section 380 (Fraud) for fraud committed against Her Majesty or section 418 (Selling defective stores to Her Majesty) of the Criminal Code (R.S.C., 1985, c. C-46); or

GC58.5.2 The Contractor certifies that it has not been convicted of or pleaded guilty to an offence under the provisions described in paragraph GC58.5.1 and has not directed, influenced, authorized, acquiesced in, assented to or participated in the commission or omission of the acts or offences that would render the Contractor’s Affiliate ineligible to be awarded the Contract under paragraph GC58.5.1.

GC58.6 Canadian Offences

GC58.6.1 The Contractor certifies:

GC58.6.1.1 that neither the Contractor nor any of the Contractor's Affiliates have, at any time during the term of the Contract, been convicted of or pleaded guilty to an offence under any of the following provisions that would render them ineligible to be awarded the Contract under this GC58 relating to integrity and for which they have not received pardon or obtained discharge in accordance with paragraph GC58.10 Canadian Pardons and Discharges:

GC58.6.1.1.1 section 119 (Bribery of judicial officers, etc.), section 120 (Bribery of officers), section 346 (Extortion), sections 366 to 368 (Forgery and other offences resembling forgery), section 382 (Fraudulent manipulation of stock exchange transactions), section 382.1 (Prohibited insider trading), section 397 (Falsification of books and documents), section 422 (Criminal breach of contract), section 426 (Secret commissions), section 462.31 (Laundering proceeds of crime), or sections 467.11 to 467.13 (Participation in activities of criminal organization) of the Criminal Code (R.S.C., 1985, c. C-46); or

GC58.6.1.1.2 section 45 (Conspiracies, agreements or arrangements between competitors), section 46 (Foreign directives), section 47 (Bid rigging), section 49 (Agreements or arrangements of federal financial institutions), section 52 (False or misleading representation), or section 53 (Deceptive notice of winning a prize) of the Competition Act (R.S.C., (1985), c. C-34); or

GC58.6.1.1.3 section 239 (False or deceptive statements) of the Income Tax Act (R.S.C., 1985, c. 1 (5th Supp.)); or

GC58.6.1.1.4 section 327 (False or deceptive statements) of the Excise Tax Act (R.S.C., 1985, c. E-25); or

Page 44: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 41 V20181214

GC58.6.1.1.5 section 3 (Bribing a foreign public official), section 4 (Accounting) or section 5 (Offence committed outside Canada) of the Corruption of Foreign Public Officials Act (S.C., 1998, c. 34); or

GC58.6.1.1.6 section 5 (Trafficking in substance), section 6 (Importing and exporting), or section 7 (Production of substance) of the Controlled Drugs and Substance Act (S.C., 1999, c. 19); or

GC58.6.1.2 that the Contractor has not been convicted of or pleaded guilty to an offence under the provisions described in paragraph GC58.6.1.1 and has not directed, influenced, authorized, acquiesced in, assented to or participated in the commission or omission of the acts or offences that would render the Contractor’s Affiliate ineligible to be awarded the Contract under paragraph GC58.6.1.1.

GC58.7 Foreign Offences

GC58.7.1 The Contractor certifies:

GC58.7.1.1 that neither the Contractor nor any of the Contractor's Affiliates have, at any time during the term of the Contract, been convicted of or pleaded guilty to an offence in a jurisdiction other than Canada that would, in the Owner's opinion, be similar to an offence described in paragraphs GC58.4 Lobbying Act, GC58.5 Canadian Offences Resulting in a Legal Incapacity and GC58.6 Canadian Offences, and for which they have not received pardon or obtained discharge in accordance with paragraph GC58.11 Foreign Pardons and that:

GC58.7.1.1.1 the court before which the Contractor or the Contractor’s Affiliates thereof appeared acted within the court's jurisdiction;

GC58.7.1.1.2 the Contractor or the Contractor’s Affiliates thereof appeared during the court's proceedings or submitted to the court's jurisdiction;

GC58.7.1.1.3 the court's decision was not obtained by fraud; and

GC58.7.1.1.4 the Contractor or the Contractor’s Affiliates were entitled to present to the court every defence that the Contractor or Contractor’s Affiliates would have been entitled to present had the proceeding been tried in Canada; or

GC58.7.1.2 that the Contractor has not been been convicted of or pleaded guilty to an offence covered by the provisions described in paragraph GC58.7.1.1 and has not directed, influenced, authorized, acquiesced in, assented to or participated in the commission or omission of the acts or offences that would render the Contractor’s Affiliate ineligible to be awarded the Contract under paragraph GC58.7.1.1.

Page 45: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 42 V20181214

GC58.8 Default of the Contractor

GC58.8.1 The Contractor certifies that it understands that if the Contractor or any of the Contractor’s Affiliates has been convicted of or pleaded guilty to an offence or held responsible for an act as described in paragraphs GC58.4 Lobbying Act, GC58.5 Canadian Offences Resulting in a Legal Incapacity, GC58.6 Canadian Offences and GC58.7 Foreign Offences, the Contractor will be considered in default and the Owner will have the right to withdraw the work from the Contractor under GC38 Taking the Work out of the Contractor’s Hands.

GC58.8.2 The Contractor also certifies that it understands that if, at any time during the term of the Contract, the Contractor is listed on the Ineligibility and Suspension List in accordance with the Ineligibility and Suspension Policy, the Contractor will be considered in default and the Owner will have the right to withdraw the work from the Contractor under GC38 Taking the Work out of the Contractor’s Hands.

GC58.8.3 The Contractor certifies that it understands that if, at any time during the Contract, the Owner determines that the Contractor is a successor to a company that would be ineligible to be awarded the Contract in the circumstances described in paragraph 2.13.7. Anti-Avoidance Provisions of the Instructions to Tenderers, the Contractor will be considered in default and the Owner will have the right to withdraw the work from the Contractor under GC38 Taking the Work out of the Contractor’s Hands.

GC58.9 Declaration of Convicted Offences

GC58.9.1 The Contractor understands that it has an on-going obligation to immediately report to the Owner any conviction or guilty plea as a result of an offence or act as listed in paragraphs GC58.4 Lobbying Act, GC58.5 Canadian Offences Resulting in a Legal Incapacity, GC58.6 Canadian Offences and GC58.7 Foreign Offences.

GC58.10 Canadian Pardons and Discharges

GC58.10.1 The commission of an act or offence or the fact of having pleaded guilty to or having been convicted of an offence or act as listed in paragraphs GC58.4 Lobbying Act, GC58.5 Canadian Offences Resulting in a Legal Incapacity or GC58.6 Canadian Offences will not result in the work being withdrawn under GC38 Taking the Work out of the Contractor’s Hands, if the Contractor or any of the Contractor’s Affiliates:

GC58.10.1.1 has been granted an absolute discharge in respect of the offence, or a conditional discharge in respect of the offence and those conditions have been satisfied;

GC58.10.1.2 has been granted a pardon under Her Majesty's royal prerogative of mercy;

GC58.10.1.3 has been granted a pardon under section 748 of the Criminal Code (R.S.C., 1985, c. C-46);

Page 46: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 43 V20181214

GC58.10.1.4 has received a record of suspension ordered under the Criminal Records Act (R.S.C., 1985, c. C-47);

GC58.10.1.5 has been granted a pardon under the Criminal Records Act (R.S.C., 1985, c. C-47) – as that Act read immediately before the day section 165 of the Safe Streets and Communities Act came into force (S.C., 2012, c. 1).

GC58.11 Foreign Pardons

GC58.11.1 The commission, abroad, of an act or offence or the fact of having pleaded guilty to or having been convicted of an offence or act abroad as listed in paragraph GC58.7 Foreign Offences will not result in the work being withdrawn under GC38 Taking the Work out of the Contractor’s Hands, if the Contractor or any of the Contractor’s Affiliates benefited from foreign measures that the Owner considers to be similar in nature to the Canadian pardon or to the conditional or absolute discharge, record suspension or restoration of the rights by the Governor in Council.

GC58.12 Subcontractors’ Obligations

GC58.12.1 The Contractor certifies that the contracts entered into with its subcontractors comprise provisions relating to integrity that are similar to those imposed in GC58 relating to integrity, and that its subcontractors comply thereto. Any failure by the Contractor to comply with this paragraph GC58.12 may, without however being limited thereto, result in the obligation for the Contractor to replace a subcontractor in accordance with GC4 Subcontracting by Contractor.

GC59 CONFIDENTIALITY

GC59.1 The Contractor shall keep confidential all information provided to the Contractor by or on behalf of the Owner in connection with the Contract, including any information that is confidential or proprietary to third parties, and all information conceived, developed or produced by the Contractor as part of the Contract when copyright or any other intellectual property rights in such information belongs to the Owner under the Contract.

GC59.1.1 The Contractor shall not disclose any such information without the written permission of the Owner.

GC59.1.2 The Contractor may disclose to a subcontractor any information necessary to perform the subcontract as long as the subcontractor agrees to keep the information confidential and that it will be used only to perform the subcontract.

GC59.1.3 The Contractor shall not, among other things, discuss, report on or given an opinion concerning any matter relating to the Contract without the written consent of the Owner.

Page 47: TENDER DOCUMENTS - PJCCI · 2019. 12. 18. · SECTION 8 GENERAL CONDITIONS 3 V20181214 GC1.1.5.3 indirect control, such as where: GC1.1.5.3.1 a Person is deemed to control, within

SECTION 8 GENERAL CONDITIONS 44 V20181214

GC59.2 The Contractor agrees to use any information provided to the Contractor by or on behalf of the Owner only for the purposes of the Contract. The Contractor acknowledges that all this information remains the property of the Owner or the third party, as the case may be.

GC59.2.1 Unless provided otherwise in the Contract, the Contractor shall deliver to the Owner all such information, together with every copy, draft, working paper and note that contains such information, upon completion or termination of the Contract or at such earlier time as the Owner may require.

GC59.3 Subject to the Access to Information Act, R.S.C. 1985, c. A-1 and to any right of the Owner under the Contract to release or disclose, the Owner shall not release or disclose outside its organization or the Government of Canada any information delivered to the Owner under the Contract that is proprietary to the Contractor or a subcontractor.

GC59.4 The obligations of the parties set out in this article do not apply to the following information:

GC59.4.1 information which is publicly available from a source other than the other party; or

GC59.4.2 information which is or becomes known to a party from a source other than the other party, except any source that is known to be under an obligation to the other party not to disclose the information; or

GC59.4.3 information which is developed by a party without use of the information of the other party.

END OF SECTION 8