Terminal 5 Berth Modernization Project 4/4/2017 Master Use Permit status

Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Terminal 5 Berth

Modernization Project

4/4/2017

Master Use Permit status

Page 2: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Land Use Decision published

• Next step towards Big Ship Ready!

• Important, but routine process for any capex project

• NWSA and City of Seattle integrated best practices to mitigate

and track environmental impacts into series of workable permit

conditions

• Necessary requirements to minimize impacts of maritime

transportation facility situated in close proximity to urban setting

• Port and tenant will partner to ensure success.

4/4/20172

Page 3: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Air Quality

4/4/20173

Page 4: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Air Quality Mitigation proposal

• Install Shore Power

• Program to Maximize Shore power use

• Measure consistency with PM 2.5 in FEIS

• Shore power usage commitment – or provide equivalent emissions

reductions

• 30% at start; 50% after 10 years; 70% by 20 years

• Cargo Handling Equipment Tier 4 usage

• 75% at start; 95% after 10 years; 100% by 20 years

OR

• Measure actual emissions: < 6 tons after 10 years; <4 tons after 20

ears

• Track operational data related to Air Quality

• Continue NWPCA strategy

• Air Quality Management agreement with PSCAA

4/4/20174

Page 5: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Noise Mitigation

4/4/20175

Page 6: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Noise Mitigation

• Design and Implement Operations Noise Management Plan

• All mobile cargo equipment handling uses broadband safety

alarms

• Hotline for low frequency vessel noise complaints

• Measurements to agreed upon limits

• Adaptive responses, including shore power hookups

• Rail Quiet zone

4/4/20176

Page 7: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Traffic Mitigation

4/4/20177

Quiet Zone

Signalization

Local Access

TWIC Security Gate

Gate Queue Management

Page 8: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Establish Quiet Zone

4/4/20178

Page 9: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Gate Queue Management Plan

• Goal to avoid backing up past Intersection Spokane St and

Access Bridge

4/4/20179

Page 10: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Restripe Bridge for Local Access

4/4/201710

Page 11: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

New Dual TWIC Security Gate

4/4/201711

Page 12: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Spokane Street Signalization

Improvements

4/4/201712

Page 13: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Future Closure of W Marginal

4/4/201713

Page 14: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Truck Parking

• Continued work with City of Seattle to complete

communications related to truck parking

• Develop brochure and web-based information with allowed/not allowed

locations

• Distribute information

• Survey truck parking in SODO

• Continue operation of off site truck parking facility at T25

4/4/201714

Page 15: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Traffic MitigationQuiet Zone Detail requirements in a MOU between Port

and City. Key component of traffic, noise.

Implementation goal is by

CO

Gate Queue Management

Plan

Require plan to be approved by City, Port,

NWSA, and tenant.

Implement prior to CO

Closure of W Marginal Way

SW at intersection

Detail requirements in a MOU between Port

and City.

Implement when Lifts at

I/M Yard exceed trigger

Local Business Access – T5

Access Bride Re-stripe

If unfeasible, need alternative Feasibility study current.

Implement by CO.

Pedestrian access to T5/T7 Improvements included in QZ. Implement prior to CO

Local Access Refresh Refresh existing signs and striping Implement prior to CO

Driver Information Draylink Implement prior to CO

Driver Information Sign on

W Marginal

Review and approval by SDOT Implement prior to CO

Spokane St Corridor Signals Review and approval by SDOT Implement prior to CO

Pre-Check Gate

Improvements

Move 150 ft in and provide two for two pre-

check gates

Implement prior to CO

Annual Monitoring Throughput, rail lifts and queue plan data. Ongoing after CO

Rail Delay Notification -

Local Businesses

Notify businesses of daytime unit train rail

blockage

Ongoing after CO

Truck Parking Study issue One year after CO

4/4/201715

Page 16: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Water Quality Improvements

4/4/201716

• Water quality treatment to meet state standards• Removal of all treated wood from cargo wharf area• Reduced overwater coverage

Page 17: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Sustainable Practices

4/4/201717

• Energy - Cargo areas with advanced lighting strategies• Recycling - Construction Waste diversion or recycling

Page 18: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Next Steps

Task Dates

City Issues MUP Analysis and Decision Mon 4/3/17

State Receives MUP Wed 4/5/17

State Issues CUP Wed 4/05/17- Mon 4/17/17

State 21 day Appeal Period Tue 4/18/17 -Mon 5/8/17

Hearings Board (if appealed) Tue 5/9/17 -Mon 10/23/17

City Issues SSDP Wed 11/1/17

Tribe Concurrence Mon 10/23/17

USACE Issues Permit Wed 11/1/17

Managing Member Construction Authorization Tue 11/7/17

4/4/201718

Page 19: Terminal 5 Berth Modernization Project... · Noise Mitigation •Design and Implement Operations Noise Management Plan •All mobile cargo equipment handling uses broadband safety

Questions?