Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1
Testing Theory in Process Industry Transformation System using
Case Studies
A Project Funded by University Grants Commission, New Delhi, India under
Grant F. No. 42-409/2013(SR) dated 25-03-2013.
Principal Investigator
Dr. K.S.Thyagaraj
Assistant Professor
Department of Management Studies
Indian School of Mines
Dhanbad, Jharkhand
Co-Investigator
Dr. Sandeep Mondal
Associate Professor
Department of Management Studies
Indian School of Mines
Dhanbad, Jharkhand
2
Acknowledgements
We thank University Grants Commission, New Delhi, India for funding this research under
Grant F. No. 42-409/2013(SR) dated 23 March, 2013. We thank Bokaro Dairy, Tata Steel and
BCCL administration for granting permission to visit their plants. We also thank Indian School
of Mines, Dhanbad, India for providing the necessary facilities and administrative support.
3
Table of Content
Acknowledgements
1. Introduction& Background Literature (4)
2. Method (8)
3. Data
3.1 Sudha Dairy, Bokaro (11)
3.2 Sudha Dairy, Baghalpur (27)
3.3 Tata Steel, Jamshedpur (42)
3.4 BCCL Moonidih Washery (50)
3.5 BCCL Bhojudih Washery (55)
4. Analysis
4.1 Within Case Analysis (59)
4.2 Across Case Analysis (66)
5. Conclusion & Future Research Directions (72)
References
Appendices
Copy of:
A UGC Letter commencing Project Funding on March 1, 2013.
B Appointment of Project Fellow
C Resignation of Project Fellow
D Appointment of Project Fellow
E Information in respect of the Project Fellow
F. Letter of Appointment as Counting Micro-Observer for 23 Dec, 2015 (the scheduled date of
UGC mid-term evaluation)
G. UGC Letter dated 19 Feb, 2015 requiring Project Closure on March 31, 2015.
H. Statement of expenditure (with Chartered Accountant seal and sign)
I. Project Fund Utilization Certificate
J Project Fund Utilization Certificate (UGC format with Chartered Accountant seal and sign)
K. Credit of balance amount to Secretary, UGC, New Delhi (A/c no. 0157101017339)
L. Fellowship Paid to Project Fellow (with Chartered Accountant seal and sign)
M. Field work/Travel expenditure (with Chartered Accountant seal and sign)
4
1. Introduction & Background Literature
American Production and Inventory Control Society (APICS) describe process industries as
businesses that add value to materials by mixing, separating, forming, or chemical reactions. It
further states that these processes may be either batch or continuous and generally require rigid
process control and high capital investment. In batch process short production runs of products are
scheduled. In continuous process there are minimal interruptions in any one production run or
between production runs of products.
Developing the manufacturing sector is fundamental to sustaining a nation’s high growth
regime and ensuring adequate employment opportunities. The process industry is a major
component of the manufacturing sector and a major source of raw-materials. In India, for example,
the eight core industries, namely, Coal, Fertilizer, Steel, Crude Oil, Refined Products, Natural Gas,
Cement, and Electricity account for 38% of weight of items included in the index of Industrial
Production. The contribution of process industries to the nation’s manufacturing output between
1980-2004 obtained from Annual Survey of India (Various Issues) is approximately as follows:
(1) Basic and fabricated metal (17%), (2) Textiles (3%), (3) Leather (1%), (4) Coke petroleum and
Nuclear fuel (14%), (5) Rubber and Plastic (15%), (6) Chemicals (14%), and (7) Food, Beverages,
and Tobacco (16%). Thus process industries account for nearly 80% of the nation’s manufacturing
output. It should be noted that some of the mentioned industries are actually hybrids, that is, the
non-discrete units becomes discrete at some point during the manufacturing process. It is found
that states, e.g., Maharashtra and Gujrat, with high density of capital intensive industries have a
large share of the Nation’s manufacturing output as compared to their employment share (Annual
Industry Survey).
Operations management research has traditionally paid very little attention to this large group
of industries. It is essential to be aware of one’s production environment to gain an understanding
of the managerial issues and accompanying solutions. Process industry is faced today with a
volatile economy, intense competition and rising energy/material costs. Improving operational
efficiency has become a necessity not only for margin purposes, but also for long term success.
Cost reduction and quality/productivity improvement have now become key levers for gaining
competitive advantage. To stay competitive the process industry has to make an attempt at
5
delivering customized goods at commodity costs. At the same time it has to work on sustainability
and environmental and social impacts.
The literature on process industries covers: (i) general Production and Inventory Management
problem (Fransoo 1992), (ii) specific Production and Inventory Management problems and
solutions (Gerchak et al. 1996), (iii) applications of ‘traditional’ Manufacturing Requirement
Planning (MRP) (Dibono 1997), (iv) scheduling in high volume continuous process industry
(Taylor and Bolander 1991), (v) basic Production and Inventory Management taxonomies
(Volmann et al.), and (vi) the differentiating characteristics between process industry and discrete
industry. Some of these differentiating characteristic are: (a) variability (Haxthausen 1995), (b)
co-product/by-product (Nichols and Ricketts 1994), (c) product sequencing (Haxthausen 1995),
(d) units of measure (Appoo 1987), and (e) lot tracking (Haxthausen 1995). Dennis and Meredith
(2000a, 2000b) provide a much more extensive list of work in each of these areas.
This study extends Dennis and Meredith (2000b) work to improve the understanding of
differences within process industry transformation systems. Managerial issues often require
solutions specific to its environment. A better understanding of characteristics of individual
transformation systems should reveal associated productivity improvement techniques, production
planning and control system, and quality control methods to achieve competitive advantage. Also
individual transformation systems technology, information, flexibility and agility needs shall be
better understood. Also an improvement in capacity planning and/or material management based
upon identification of similar process pattern across dissimilar products is foreseen.
Process industries are distinctively organized around production processes (Barnett and Clark,
1996) and efficient supply chain operation is invariably tied to the process design (Shah 2003).
Majority of process industry literature focuses on characteristics that differentiate process industry
(as a whole) from discrete industry. This has only helped us understand that process industry
requires a different type of management emphasis (Utterback, 1996). There are few studies which
provide in-between distinction of process industries. As such our understanding of individual
process industries is fairly limited making it difficult to identify areas of potential improvements.
6
The distinction within process industries is reflected in Taylor et al. (1981) adaption of Hayes
and Wheelwright’s (1979) product/process model of discrete industries to process industries (refer
Figure 1). This product/process model categorized several types of process industries with respect
to product mix and process pattern. The two extremes of product mix were custom and commodity.
The two extremes of process pattern were batch (job shop) and process (flow shop).
Fig. 1.1: Taylor’s Product/Process matrix
Dennis and Meredith (2000b), however, argue that all firms within each industry groups (e.g.,
drugs) doesn’t necessarily have comparable process pattern. As such these firms shouldnot occupy
a common position in the matrix. They further point out the error in assuming that a process firm
shall encounter managerial issues similar to a firm producing discrete products based on its
position in the matrix. Based upon this it is evident that Taylor et al. (1981) product/process model
needs improvement. It is stated that though the product mix largely determines the process pattern
it is important to understandthe specific transformation system characteristics that make up the
process pattern. A better understanding of characteristics of individual transformation systems
should reveal associated productivity improvement techniques, production planning and control
system, and quality control methods to achieve competitive advantage. Also individual
transformation systems technology, information, flexibility and agility needs shall be better
understood. Also an improvement in capacity planning and/or material management based upon
identification of similar process pattern across dissimilar products is foreseen.
7
In this direction, Dennis and Meredith (2000b), propose 16 characteristics to analyze process
industry transformation systems. These 16 characteristics form the basis for their additional
proposal that: (i) process industry transformation systems can be categorized into at least seven
subtypes, and (ii) these subtypes can be loosely grouped into intermittent, continuous, and hybrid
transformation systems.
Dennis and Meredith (2000b) work which is based on empirical study of nineteen industries
does not draw conclusions but puts forth proposals as a step towards theory building. It does not
draw conclusions but puts forth proposals as a step towards theory building. These proposals
neither validate nor falsify existing theory and require further testing. The objective here to test
the following propositions by Dennis and Meredith (2000b):
1. Taylor et al.(1981) product-process model doesn’t convey significant information
regarding transformation systems of individual process industries.
2. Two firms producing same products and occupying the same position on the product-
process matrix could have dissimilar transformation system characteristics and face
different operational challenges.
3. Two firms producing dissimilar products and occupying different position in the product-
process matrix could have similar transformation characteristics.
The remainder of the paper is organized as follows. Section 2 describes the Case Study
methodology used. In Section 3 we describe the individual cases and conduct within and across
case analysis. We conclude finally in Section 4.
8
2. Method
We use case study to test the propositions by Dennis and Meredith (2000b). Case methods, due to
the effort involved, are primarily useful when developing new theory or selective testing of
existing theories in polar type or extreme cases. A case study utilizes multiple methods and tools
for data collection from a number of entities by a direct observer(s). This is done in a single, natural
setting that considers temporal and contextual aspects of the contemporary phenomenon under
study, but without experimental controls or manipulations (Bonoma 1985, Eisenhardt 2007, and
Yin 1994). Both quantitative and qualitative approaches as well as obtrusive and unobtrusive
methods are applicable. The idea is to understand the phenomenon being studied as thoroughly as
possible through ‘perceptual triangulation’ (Bonoma 1985). Triangulation implies the convergence
of evidence on one meaning (Bonama 1985, Stake 1995, Yin 1994).
The confirmatory test procedure consists of developing a theoretical background, and
developing a systematic research design including evaluation criteria. The theoretical background
of this study has been discussed and is also in Dennis and Meredith (2000b). The research design
comprises the: (1) unit of analysis, (2) appropriate cases to study, and (3) data to collect and how
to collect it.
In a process industry the non-discrete units often becomes discrete at some point during the
manufacturing process. We choose Dairy, Steel (includes Steel products), and Coal preparation
plants as unit of analysis. The product becomes discrete in the Dairy at the point of packaging, in
the Steel industry after casting, and Coal preparation plant the material remains discrete during the
entire process.
Table 2.1Description of the unit of analysis
Annual
production
Primary products Ownership
Sudha
Dairy,
Bokaro
1983 100TLPD Milk ,Curd ,Sweets , Churned
Curd (Lassi), cottage Cheese,
Sweetened clotted milk (Rabri)
Cooperative
Society
9
Sudha
Dairy,
Bagalpur
1983 60TLPD Milk ,Butter, Curd ,Sweets
(Peda), cottage Cheese,
Sweetened clotted milk (Rabri)
Cooperative
Society
Tata Steel,
Jamshedpur
1911 27.37
Million ton
Long and Flat product Privately
owned
BCCL
Moonidih
1983 1.60 Metric
ton /Year
Washed coal, Washed power
coal
Government
Owned
BCCL
Bhojudih
1962 1.70 Metric
ton /Year
Washed coal, Washed power
coal
Government
Owned
In case study approach lack in number of cases studied is compensated by careful selection
and replication of cases. Firms are selected to capture extreme product types and process types.
Suggestions for the number of cases to use in multiple case study research vary, but Eisenhart
(1989) suggests seven cases as the maximum that a person can mentally process. Yin (1994) and
others are more circumspect in regards to hard numbers and instead suggest that data should be
collected until saturation. The selection of firms is aimed at producing similar results or produce
contrasting results but for predictable reasons. Our unit of analysis comprises of firms which are
privately and publicly owned, whose market varies from regional to global. The Dairy firms cater
to regional market, the Coal preparation plant market their product nationwide while the Steel
plant supply globally. A set of two firms in each industry is selected leading to six cases. Due to
time restriction we could study only five cases. Within case analysis helps us to analyze
transformation system characteristics in the context of one process industry, while the across case
analysis serves as a form of replication by analyzing characteristics of the transformation system
in the context of process industry as a whole.
Yin (1994) recommends identifying all decisions pertaining to the research design as well
as the information needed and accompanying questions before the data collection phase. These
questions shall be for the purpose of supporting the proposals and not typical survey or interview
questions. A set of probable sources of evidence too shall accompany each question. Ideally
multiple sources are needed to enable triangulation. Only cases that show adequate triangulation
10
with regards to research questions shall be evaluated. Like any other methodology, case studies
are subject to potential researcher biases. The triangulation of evidence within each case and all
study findings is evaluated by an outside auditor(s) to ensure that they are logical and free from
prejudice (Hirschman 1986). Initial permission for plant visit was obtained over telephone and
subsequently a written permission was obtained. Prior to visiting plant, exhaustive background
study was carried out by accessingpublic document. The focus in particular was on the production
process. The data was collected through unstructured interview from high & middle level
managers as well as the shop-floor workers. Information collected from them wasalso verified by
personal observation and company documents.
11
3. Data
3.1 Sudha Dairy, Bokaro
Firm profile
The Bihar State Milk Co-operative Federation Ltd is a dairy cooperative established in 1983.It is
an enterprise of the government of Bihar. It markets its products under the label "Sudha Dairy".
The co-operative facilitates the procurement, processing, and marketing of the dairy products. It
provides education to the unions on successful dairy processing, and assists with animal care
including artificial insemination, vaccination, and feeding.There are six district level Milk
Producers' Cooperative Unions affiliated to the Milk Federation. These milk unions are covering
twenty-six districts and in addition five districts are being covered by the Federation.
List of Milk unions
Name Address
Vaishali Patliputra Dugdh Utpadak Sahkari Sangh Ltd. Patna
Mithila Dugdh Utpadak Sahkari Sangh Ltd Samastipur
T ihut Dugdh Utpadak Sahkari Sangh Ltd. Muzaffarpur
Deshratna Dr . Rajendra Prasad Dugdh Utpadak Sahkari
Sangh Ltd.
Barauni
Shahabad Dugdh Utpadak Sahkari Sangh Ltd. Arrah
Vikramshila Dugdh Utpadak Sahkari Sangh Ltd. Bhagalpur
12
Figure 1 :Processing of milk
Steam
Cold water supply
Valve
Raw milk
Pasteurized milk
Hot water
Electrical feedback
Pasteurized milk
tank
Chilled
water
supply
Hot water
tank
Cleaner/separator
Milk
pump
Chilled
water
supply
Chiller
Raw milk
tank
Temperature
recorder
Diaphragm valve Steam reducing
valve
Balance tank Milk
pump
Homogenizer
Flow controller
Pump
Chilling section Regeneration Section Heating section
Milk
Tanker
13
Figure 2.Processing of milk and its product in Sudha Diary,Bokaro
Butter
Peda
Rabri
Cheese
Misti Doi
SMP/milk
Plain Doi
Water supply Lassi
Raw milk
Homog
enizer
Turboje
t
blender
Heat
Exchanger
Vat
Milk
Silo/Tank
Milk Bed
Heat
Exchanger
Khoa Pan
Packaging
section
Cold
store
vat
14
Figure 3 :Processing of milk
Process:-Processing of milk begins from raw material i.e. crude milk supplied by different unions
established in Bihar. These milk unions receive raw milk from farmers, process them and transport
through milk tanker or milk rail wagon to these plants. It is tested in quality control lab using
lactometer and barometer used for measuring SNF percentage and fat percentage. Depending upon
the fat and SNF percentage present in the milk, its price is being determined. Reading of incubators
determines process to be carried out in the next stage.
Reading of Incubator (bacteria %) Action to be carried out
>25k Raw milk will be sent to Silo whose capacity is
20K*3 and 30K*2
<25k Raw milk will be sent to heat exchanger
There are two alternative channels for mixing butter / skimmed milk powder, Whole milk powder
into the crude milk for increasing/decreasing fat and SNF percentage.
Raw milk Packaging
Machine-3
Packaging
Machine-2
Packaging
Machine-1
Upper head
tank
Cold store-1
Packaging
Machine-5
Packaging
Machine-4
Silo
Heat
exchanger
Homog
e-nizer
Turboj
et
blende
r
Silo
15
Classification of milk
Milk Milk Type Fat (in %) SNF (in %)
Sudha Gold Full cream milk 6 9
Sudha Gold Sudha shakti 4.5 8.5
Sudha Gold Cow milk 3.5 8.5
Sudha Healthy Toned milk 3 8.5
Sudha Smart Double toned milk 1.5 9
Raw milk either from Silo or milk tanker transferred into the heat exchanger for processing
involves subsequently heating @82 degree Celsius for 15 seconds and cooling @ below 5 degree
Celsius. Processed milk is stored in upper head tank with installed capacity 44KL or silo with
capacity of 120KL depending upon their availability. From upper head tank, milk is supplied to
different packaging machine. Packed milk, varying on the basis of quantity and quality, transferred
into crates subsequently stored in cold store @8 degree Celsius.
Number of routings: From figure 3, there is only one production line. So, the number of routings
will be one.
Raw materials used: Raw milk, Skimmed milk powder, Whole milk powder, Whole Butter
Ingredients used: None
Inventory points: In process section, there are three inventory points, points i.e. Milk Silo, upper
head tank and Cold store-1.
Work centers: There are five work centers i.e. Homogenizer, cleaner/separator, turbo-jet blender,
heat exchanger and packaging machine.
Run time: 7 minute is required for processing 1000 liters of milk.
Degree of flexibility in work centre/equipment choice
Dairy industry is exhibiting relatively high degree of flexibility in work center and equipment
choice because of availability of alternative production line and availability of redundant
equipments.
16
List of equipments used in process section:
Name of equipment
quantity
use
Homogenizer 2 Mixing butter with raw milk.
cleaner/separator 1
Separating soil, fat, SNF and any waste
material present in milk.
Turbo-jet blender 1 Sucks SMP and transfer it into vat for
mixing with water/raw milk
Heat exchanger 2 Used for pasteurizing milk
packaging machine 5 Used for packaging milk as well as lassi
Figure 4 :Processing of Peda
Process:-
Milk is heated to a temperature of 78 degree Celsius in milk bed. It is heated for more than 3 hrs.
at 80 degree Celsius in Khoa pan to evaporate water content of milk . Sugar and cardamom powder
is added to solid substance left on the pan. Yield of process depends upon the availability of fat
and SNF in the crude milk .This mixture(Khoa) is then left for cooling after transferring it into
different trays. Later on pressed and packaged to form “peda” of defined dimension .
Number of routings: There is only one production line. So, the number of routings will be one.
Milk tanker Milk bed
Heat
exchanger
Khoa pan Packaging Cold store-2
Upper head
tank/silo
17
Raw materials used: Raw milk
Ingredients used: sugar and cardamom powder
Inventory points: There are two inventory points in the manufacturing of “peda” i.e. before
packaging in tray, Cold store-2.
Work centers: There are four work centers i.e. khoa pan, milk bed and press machine used while
packaging, heat exchanger.
Run time: Run time is more than 3 Hrs., subjected to availability of steam.
Degree of flexibility in work centre/equipment choice
Dairy industry is exhibiting relatively high degree of flexibility in work center and equipment
choice because of availability of alternative production line and availability of redundant
equipments.
List of equipments used in process section:
Name of equipment
quantity
use
Khoa pan 2 Heating milk for preparing khoa.
Milk bed 1
Used for pasteurizing milk
Press machine 2 For giving proper dimension to the ball of
khoa
Heat exchanger 1 Used for pasteurizing milk
18
Figure 5 :Processing of Sudha special(Rabri)
Process:-
Milk is heated to a temperature of 78 degree Celsius in milk bed. It is heated for more than 3 hours
at 80 degree Celsius in Khoa pan to evaporate water content of milk. Sugar, cardamom powder,
citric acid, coconut powder, corn flower, color is added to solid substance left on the pan. Yield of
process depends upon the availability of fat and SNF in the crude milk. This semi-solid is then
transferred into sanitized cups in the packaging stage these filled cups are sealed and stored in cold
store.
Number of routings: There is only one production line. So, the number of routings will be one.
Raw materials used: Raw milk
Ingredients used: sugar, cardamom powder, citric acid, coconut powder, corn flower, color
Inventory points: There are four inventory points i.e. before transferring semi-solid substance
into sanitized cup, twice in Cold store-2, before sealing.
Work centers: There are five work centers i.e. khoa pan, milk bed, packaging, heat exchanger and
sealing machine.
Run time: Run time is more than 3 hours subjected to availability of steam.
Degree of flexibility in work centre/equipment choice
Dairy industry is exhibiting relatively high degree of flexibility in work center and equipment
choice because of availability of alternative production line and availability of redundant
equipments.
List of equipments used in process section:
Milk tanker
Upper head
tank/silo
Milk bed
Heat
exchanger
Khoa
pan Packaging Sealing Cold store-2 Cold store-2
19
Name of equipment
quantity use
Khoa pan 2 Heating milk
milk bed 1 Used for pasteurizing milk
Sealing machine 2 Sealing cups
Heat exchanger 1 Used for pasteurizing milk
Figure 6:Processing of cheese
Whey
Process:-
Milk is heated to a temperature of 78 degree Celsius in milk bed. It is heated for more than 3 hrs.
at 80 degree Celsius. Citric acid, calcium lactate powder and water is added gradually to coagulate
milk and then whey is drained after filtering it using filter bed. White solid pressed using press
machine for more than 45 minutes to give it rectangular shape. Subsequently it is transferred to
cold store-2, for 3-4 Hrs.. It is fragmented in cutting section to a particular volume of 200 gm and
1 kg. Later on it is packed and stored in cold store-2.
Number of routings: There is only one production line. So, the number of routings will be one.
Raw materials used: Raw milk
Ingredients used: citric acid, calcium lactate powder and water
Milk tanker
Upper head
tank/silo
Milk bed
Heat
exchanger
Filter Press
machine
Cutting of
cheese
Packaging
Machine-2
Packaging
Machine-1
Cold store-
2 Cold store-
2
20
Inventory points: There are three inventory points in the manufacturing of cheese i.e. twice in
cold store and before packaging.
Work centers: There are seven work centers i.e. milk bed, filter, packaging machine, heat
exchanger, cutting and pressing machine, weighing pan.
Run time: Run time for manufacturing 1kg of cheese is 7 Hrs. + and 200 gm of cheese is 8
Hrs.+
Degree of flexibility in work centre/equipment choice
Dairy industry is exhibiting relatively high degree of flexibility in work center and equipment
choice because of availability of alternative production line and availability of redundant
equipments.
List of equipments used in process section:
Name of equipment
quantity
use
Filter 1
For filtering cheese from whey
Milk bed
1
For pasteurizing milk
Packaging machine 2 For packing cheese bed
Heat exchanger 1 For pasteurizing milk
Cutting machine 1 For cutting cheese of 200 gm and 1 kg
from cheese bed
Pressing machine 1 For shaping
Weighing pan 1 For weighing cheese
21
Figure 7 :Processing of Dahi
Process:-
Milk is heated to a temperature of 78 degree Celsius in milk bed for 20 minutes. Culture and sugar
(for misti dahi) is added after cooling milk to a temperature of 37-40 degree Celsius. Solution is
transferred into sanitized cups in packaging stage and kept in Dahi incubation room at 37-40 degree
Celsius for 3.0 -4.0 hrs.. Cups are Stored in cold store-2 for 12 Hrs.
Number of routings: There is only one production line. So, the number of routings will be one.
Raw materials used: Raw milk
Ingredients used: Culture and sugar (for misti dahi)
Inventory points: There are three inventory points in the manufacturing of dahi, i.e. twice in
cold store, after packaging.
Work centers: There are five work centers i.e. milk bed, heat exchanger, Dahi incubation room,
sealing machine and before packaging.
Run time: Run time is16 Hrs.+.
Degree of flexibility in work centre/equipment choice
Milk tanker
Milk bed
Heat
exchanger
Upper head
tank/silo
Dahi
incubation
room
Cold store-
2 Sealing
Machine Cold store-
2
P
a
c
k
a
g
i
n
g
22
Dairy industry is exhibiting relatively high degree of flexibility in work center and equipment
choice because of availability of alternative production line and availability of redundant
equipments.
List of equipments used in process section:
Name of equipment
quantity
use
Milk bed 1
Used for pasteurizing milk
Sealing machine 2 For packing cheese bed
Heat exchanger 1 Used for pasteurizing milk
Figure 8 :Processing of Lassi
Milk
tanker
Upper head
tank/silo
Milk bed
Heat
exchanger
Dahi
incubation
room
Vat Tank
Packagin
g
machine-
4
Packagin
g
machine-
3
Cold
store-1
Packagin
g
machine-
5
Packagin
g
machine-
2
Packagin
g
machine-
1
Cold
store-2
23
Process:-
Produced curd is transferred to vat through pump for processing using centrifugal motor and
transferred to tank. From here it is packed into packets through packaging machine. Packed lassi
is stored in cold store-1.
Number of routings: There is only one production line. So, the number of routings will be one.
Raw materials used: Raw milk
Ingredients used: Culture and sugar
Inventory points: There are four inventory points in the manufacturing of lassi i.e. twice in cold
store-1 and 2, vat and tank.
Work centers: There are six work centers i.e. milk bed, heat exchanger, Dahi incubation room,
vat, before Dahi incubation room and Packaging machine.
Run time: Run time is17 Hrs.+.
Degree of flexibility in work centre/equipment choice
Dairy industry is exhibiting relatively high degree of flexibility in work center and equipment
choice because of availability of alternative production line and availability of redundant
equipments.
List of equipments used in process section:
Name of equipment
quantity
use
milk bed 1 Used for pasteurizing milk
Packaging machine 5 For packing lassi and milk
Heat exchanger 1 Used for pasteurizing milk
Vat 1 Used for processing lassi
24
Degree of product variety
There is medium degree of product variety in dairy industry because products are chemically
similar but there is variation in the percentage composition of fats, SNF and water in different
grades of milk
Degree of Structural and Formulation Complexity
This industry exhibit relatively low degree of structural and formulation complexity because of
flexibility in controlling different production parameters i.e. pressure, volume, temperature, PH
level.
Degree of continuity flow
Dairy industry display continuous and intermittent flow with possible economic intentional
interruption because of negligible start up cost. Production process of milk is continuous whereas
process for milk product is intermittent.
25
General purpose equipmentSpecialty equipment
EQUIPMENT MATRIX
Cleaner/Separator
Solar Panel
Balance Tank
Water pump
Boiler Tank
Coal Blower
Paneer Sealing machine
Paneer Press machine
Paneer Cutting machine
Weighing pan
Thermometer/temperature recorder
Milk pump
Homogenizer
Silo
Turbojet blender
Lactometer
Betrometer
MBRT water bath
Centrifuge machine
Incubator
Peter dish
Deep freezer
D
E
D
I
C
A
T
E
D
Heat exchanger
9*9 ammonia compressor
6*6 Ammonia compressor
Vilter compressor
Booster
IBT coil
Air Blower
Milk bed
Sealing machine
Khoa pan
Vat
Upper head tank
Milk Packaging machine
N
O
N
D
E
D
I
C
A
T
E
D
26
Transformation
system
characteristics
Milk Peda Rabri cheese Misti
dahi
Plain
dahi
lassi
Number of
routings
1 1 1 1 1 1 1
Number of raw
materials
4 1 1 1 1 1 1
Number of
ingredients
0 2 6 3 2 1 2
Number of
inventory points
3 2 5 5 6 6 5
Number of
separate work
centers
5 4 4 5 3 3 4
Run time 7 minutes 3 hrs+ 3 hrs+ 1kg 200
gm
16 hrs+ 16 hrs+ 17 hrs+
7
hrs+
8
hrs+
27
3.2 Sudha Dairy, Bhagalpur
Firm profile
The Bihar State Milk Co-operative Federation Ltd is a dairy cooperative established in 1983.It is
an enterprise of the government of Bihar. It markets its products under the label "Sudha Dairy".
The co-operative facilitates the procurement, processing, and marketing of the dairy products. It
provides education to the unions on successful dairy processing, and assists with animal care
including artificial insemination, vaccination, and feeding.There are six district level Milk
Producers' Cooperative Unions affiliated to the Milk Federation. These milk unions are covering
twenty-six districts and in addition five districts are being covered by the Federation.
List of Milk unions
Name Address
Vaishali Patliputra Dugdh Utpadak Sahkari Sangh Ltd. Patna
Mithila Dugdh Utpadak Sahkari Sangh Ltd Samastipur
T ihut Dugdh Utpadak Sahkari Sangh Ltd. Muzaffarpur
Deshratna Dr . Rajendra Prasad Dugdh Utpadak Sahkari
Sangh Ltd.
Barauni
Shahabad Dugdh Utpadak Sahkari Sangh Ltd. Arrah
Vikramshila Dugdh Utpadak Sahkari Sangh Ltd. Bhagalpur
28
Figure 1 :Processing of milk
Steam
Cold water supply
Valve
Figure 2.Processing of milk and its product in Sudha
Diary,Bhagalpur
Raw milk
Pasteurized milk
Hot water
Electrical feedback
Pasteurized milk
tank
Chilled
water
supply
Hot water
tank
Cleaner/separator
Milk
pump
Chilled
water
supply
Chiller
Raw milk
tank
Temperature
recorder
Diaphragm valve Steam reducing
valve
Balance tank Milk
pump
Homogenizer
Flow controller
Pump
Chilling section Regeneration Section Heating section
Milk
Tanker
29
Butter
Peda
Rabri
Cheese
Misti Doi
SMP/milk
Plain Doi
Water supply
Raw milk
Homog
enizer
Turboje
t
blender
Heat
Exchanger
Vat
Milk
Silo/Tank
Khoa Pan
Packaging
section
Cold
store
Milk Bed
Milk cream Ghee boiler
Milk
cream
Ghee
30
Figure 3 :Processing of milk
Process:-Processing of milk begins from raw material i.e. crude milk supplied by different unions
established in Bihar. These milk unions receive raw milk from farmers, process them and transport
through milk tanker or milk rail wagon to these plants. It is tested in quality control lab using
lactometer and barometer used for measuring SNF percentage and fat percentage. Depending upon
the fat and SNF percentage present in the milk, its price is being determined. Reading of incubators
determines process to be carried out in the next stage.
Reading of Incubator (bacteria %) Action to be carried out
>25k Raw milk will be sent to Silo whose capacity is
20K*3 and 30K*2
<25k Raw milk will be sent to heat exchanger
There are two alternative channels for mixing butter / skimmed milk powder, Whole milk powder
into the crude milk for increasing/decreasing fat and SNF percentage.
Raw milk
receiving
bed Packaging
Machine-3
Packaging
Machine-2
Packaging
Machine-1
Upper head
tank
Cold store-1
Packaging
Machine-4
Silo
Heat
exchanger
Homog
e-nizer
Turboj
et
blende
r
Silo
Milk
tanker
Upper head
tank
31
Classification of milk
Milk Milk Type Fat (in %) SNF (in %)
Sudha Gold Full cream milk 6 9
Sudha Gold Sudha shakti 4.5 8.5
Sudha Gold Cow milk 3.5 8.5
Sudha Healthy Toned milk 3 8.5
Sudha Smart Double toned milk 1.5 9
Raw milk either from Silo or milk tanker transferred into the heat exchanger for processing
involves subsequently heating @82 degree Celsius for 15 seconds and cooling @ below 5 degree
Celsius. Processed milk is stored in upper head tank with installed capacity 44KL or silo with
capacity of 120KL depending upon their availability. From upper head tank, milk is supplied to
different packaging machine. Packed milk, varying on the basis of quantity and quality, transferred
into crates subsequently stored in cold store @8 degree Celsius.
Number of routings: From figure 3, there is only one production line. So, the number of routings
will be one.
Raw materials used: Raw milk, Skimmed milk powder, Whole milk powder, Whole Butter
Ingredients used: None
Inventory points: In process section, there are three inventory points, points i.e. Milk Silo, upper
head tank and Cold store-1.
Work centers: There are five work centers i.e. Homogenizer, cleaner/separator, turbo-jet blender,
heat exchanger and packaging machine.
Run time: 7 minute is required for processing 1000 liters of milk.
Degree of flexibility in work centre/equipment choice
Dairy industry is exhibiting relatively high degree of flexibility in work center and equipment
choice because of availability of alternative production line and availability of redundant
equipments.
32
List of equipments used in process section:
Name of equipment
quantity
use
Homogenizer 2 Mixing butter with raw milk.
cleaner/separator 1
Separating soil, fat, SNF and any waste
material present in milk.
Turbo-jet blender 1 Sucks SMP and transfer it into vat for
mixing with water/raw milk
Heat exchanger 2 Used for pasteurizing milk
packaging machine 5 Used for packaging milk as well as lassi
Figure 4 :Processing of Peda
Process:-
Milk is heated to a temperature of 78 degree Celsius in milk bed. It is heated for more than 3 hours
at 80 degree Celsius in Khoa pan to evaporate water content of milk. Sugar and cardamom powder
is added to solid substance left on the pan. Yield of process depends upon the availability of fat
and SNF in the crude milk .This mixture (Khoa) is then left for cooling after transferring it into
different trays. Later on pressed and packaged to form “peda” of defined dimension.
Number of routings: There is only one production line. So, the number of routings will be one.
Raw materials used: Raw milk
Milk container Khoa pan Packaging Walk-in cold
store
33
Ingredients used: sugar and cardamom powder
Inventory points: There are two inventory points i.e. before packaging in tray,Walk-in cold
store.
Work centers: There are three work centers i.e. khoa pan and press machine used while packaging.
Run time: Run time is more than 3 hours subjected to the availability of steam.
Degree of flexibility in work centre/equipment choice
Dairy industry is exhibiting relatively high degree of flexibility in work center and equipment
choice because of availability of alternative production line and availability of redundant
equipments.
List of equipments used in process section:
Name of equipment
quantity
use
Khoa pan 2
Heating milk
Press machine 2 Shaping
Figure 5 :Processing of Sudha special(Rabri)
Process:-
Milk is heated to a temperature of 78 degree Celsius in milk bed. It is heated for more than 3 hours
at 80 degree Celsius in Khoa pan to evaporate water content of milk. Sugar, cardamom powder,
citric acid, coconut powder, corn flower, color is added to solid substance left on the pan. Yield of
process depends upon the availability of fat and SNF in the crude milk. This semi-solid is then
transferred into sanitized cups in the packaging stage these filled cups are sealed and stored in
Walk-in cold store.
Number of routings: There is only one production line. So, the number of routings will be one.
Milk container Khoa
pan Packaging Sealing
Walk-in
cold store
Walk-in
cold store
34
Raw materials used: Raw milk
Ingredients used: sugar, cardamom powder, citric acid, coconut powder, corn flower, color
Inventory points: There are four inventory points in the manufacturing of “Sudha special (Rabri)”
i.e. before transferring semi-solid substance into sanitized cup, twice in Walk-in cold store, before
sealing.
Work centers: There are four work centers i.e. khoa pan, packaging, walk-in cold store and sealing
machine.
Run time: Run time is more than 3 Hours+ subjected to availability of steam.
Degree of flexibility in work centre/equipment choice
Dairy industry is exhibiting relatively high degree of flexibility in work center and equipment
choice because of availability of alternative production line and availability of redundant
equipments.
List of equipments used in process section:
Name of equipment quantity
use
Khoa pan 2 Heating milk
Sealing machine 1 Sealing cups
35
Figure 6:Processing of cheese
Whey
Process:-
Milk is heated to a temperature of 80-85 degree Celsius and subsequently 2% of citric acid, calcium
lactate powder and water is added gradually to coagulate milk. Whey is drained after filtering it
using filter bed. Residue is taken into press machine for more than 25 minutes for shaping.
Subsequently, it is chilled using chilled water for 3-4 hours. It is fragmented to a particular volume
of 200 gm and 1 kg manually using knife. Later on it is packed and stored in walk-in store.
Number of routings: There is only one production line. So, the number of routings will be one.
Raw materials used: Raw milk
Ingredients used: Citric acid, calcium lactate powder and water
Inventory points: There are two inventory points in the manufacturing of cheese i.e. walk-in
store and before packaging.
Work centers: There are six work centers i.e. vat, filter, packaging machine, cutting (manually)
and pressing machine, weighing pan.
Run time: Run time for manufacturing 1kg of cheese is 6 hours and 200 gm of cheese is 7 hours.
Degree of flexibility in work centre/equipment choice
Dairy industry is exhibiting relatively high degree of flexibility in work center and equipment
choice because of availability of alternative production line and availability of redundant
equipments.
Milk container Filter Press
machine
Cutting of
cheese
Packaging
Machine-2
Packaging
Machine-1
Cold store-
2 Vat
36
List of equipments used in process section:
Name of equipment
quantity
use
Filter
1
Filtering cheese from whey
Vat 1
Heating milk with citric acid
Packaging machine 2 For packing cheese bed
Pressing machine 1 For shaping
Weighing pan 1 weighing cheese
37
Figure 7 :Processing of Dahi
Process:-
Milk is heated to a temperature of 78 degree Celsius in milk bed for 20 minutes. Culture and sugar
(for misti dahi) is added after cooling milk to a temperature of 37-40 degree Celsius. Solution is
transferred into sanitized cups in packaging stage and kept in Dahi incubation room at 37-40 degree
Celsius for 3.0 -4.0 hours. Cups are Stored in cold store-2 for 12 hours.
Number of routings: There is only one production line. So, the number of routings will be one.
Raw materials used: Raw milk
Ingredients used: Culture and sugar (for misti dahi)
Inventory points: There are three inventory points in the manufacturing of dahi i.e. twice in cold
store, after packaging.
Work centers: There are three work centers i.e. Dahi incubation room, packaging machine, and
chilling done manually by the help of water.
Run time: Run time is 6 hours.
Degree of flexibility in work centre/equipment choice
Dairy industry is exhibiting relatively high degree of flexibility in work center and equipment
choice because of availability of alternative production line and availability of redundant
equipments.
Milk
Container
Dahi
incubatio
n room
Cold store-
2 Packaging
Machine Cold store-
2
C
h
i
l
l
i
n
g
Milk bed
P
a
c
k
a
g
i
n
g
38
List of equipments used in process section:
Name of equipment
quantity
use
Milk bed 1
For pasteurizing milk
Sealing machine 2 For packing cheese bed
Heat exchanger 1 Used for pasteurizing milk
Figure 8 :Processing of Butter
Process:-
Milk cream is transported from Barauni (Bihar) or available in plant itself after processing of milk
with high Fat and SNF content .It is heated at 90-95 degree Celsius, for 4-5 hours and subsequently
transferred into small tanker and transported to Bihar sharif (Bihar).
Number of routings: There is only one production line. So, the number of routings will be one.
Raw materials used: Milk cream
Ingredients used: None
Inventory points: There are two inventory points i.e. Milk cream stored before processing and
butter before transporting.
Work centers: There are one work centers i.e. Ghee boiler.
Milk
storage
tank
Cleaner/separ
ator
Ghee
boiler
Heat
exchanger
Milk cream
from Barauni
Sent to
Biharshariffor
refinement Stored in
small
tanks
Milk with
low fat
39
Run time: Run time is 4 Hours.
Degree of flexibility in work centre/equipment choice: There are one work centers i.e. Ghee
Boiler.
List of equipments used in process section:
Name of equipment
Quantity
Use
Ghee Boiler 1
Heating milk cream
So, from above table we can conclude that there is very low degree of flexibility in work
centre/equipment choice.
Degree of product variety
There is medium degree of product variety in dairy industry because products are chemically
similar but there is variation in the percentage composition of fats, SNF and water in different
grades of milk
Degree of Structural and Formulation Complexity
This industry exhibit relatively low degree of structural and formulation complexity because of
flexibility in controlling different production parameters i.e. pressure, volume, temperature, PH
level.
Degree of continuity flow
Dairy industry display continuous and intermittent flow with possible economic intentional
interruption because of negligible start up cost. Production process of milk is continuous whereas
process for milk product is intermittent.
40
General purpose equipmentSpecialty equipment
EQUIPMENT MATRIX
Cleaner/Separator
Solar Panel
Balance Tank
Water pump
Boiler Tank
Coal Blower
Paneer Sealing machine
Paneer Press machine
Paneer Cutting machine
Weighing pan
Thermometer/temperature recorder
Milk pump
Homogenizer
Silo
Turbojet blender
Lactometer
Betrometer
MBRT water bath
Centrifuge machine
Incubator
Peter dish
Deep freezer
Press Machine
D
E
D
I
C
A
T
E
D
Heat exchanger
9*9 ammonia compressor
6*6 Ammonia compressor
Vilter compressor
Booster
IBT coil
Air Blower
Milk bed
Sealing machine
Khoa pan
Vat
Upper head tank
Milk Packaging machine
N
O
N
D
E
D
I
C
A
T
E
D
41
Transformation
system
characteristics
Milk Peda Rabri Cheese Misti
dahi
Plain
dahi
Butter
Number of
routings
1 1 1 1 1 1 1
Number of raw
materials
4 1 1 1 1 1 1
Number of
ingredients
0 2 6 3 2 1 0
Number of
inventory points
3 2 5 5 3 3 2
Number of
separate work
centers
5 4 4 5 3 3 1
Run time 85 Kl/17
hrs
3 hrs+ 3 hrs+ 1kg 200
gm
6 hrs+ 6 hrs+ 4 hrs+
7
hrs+
8
hrs+
42
3.3. Tata Steel, Jamshedpur
Tata Steel’s Jamshedpur plant, the very first steel plant in India (production started in 1912).It is
among the country’s largest integrated steel-making facilities, producing 10 million tons of steel
every year. Steel is considered a green product because it is 100-percent recyclable and has an
infinite life cycle. It is among the top 10 global steel companies and one of the worlds’s most
geographically diversified steel producers. Tata Steel is operating in 26 countries and a commercial
presence in more than 50.
Steel manufacturing process at TATA STEEL, Jamshedpur
The basic process of making iron and its tougher alloy — steel — have not changed in the last
three millennia. First, the ore has to be found. Then it must be reacted with other elements at very
high temperatures. Third, the liquid steel must be collected and casted into shape. And, finally, the
steel must be treated to give it the properties needed for end use.
At Tata Steel’s Jamshedpur plant, the steelmaking process starts at the mines. Iron ore
is brought in by trucks/train wagon from Noamundi in Jharkhand and Joda in Odisha. Coal comes
from West Bokaro and Jamadoba in Jharkhand and even as far away as Australia. This plant uses
approximately 25 million tons of iron ore and coal/coke blend every year to produce about 10
million tons of steel.
Untreated ore cannot be used to make steel as it reduces the quality of the metal. Therefore,
the raw iron ore is processed at the sinter /pellet plant, where lump ore is treated along with water
and limestone; thereby it is transformed into granular size. The coal used in the plant is cleansed
of impurities in coke ovens. Conveyor belts carry metallic — pellets and sinters — to the heart of
the steel plant, the blast furnace. The blast furnace is a six-storey tall reactor where the seemingly
magical transformation of dark iron ore into glowing hot liquid iron takes place. The ore is charged
into the blast furnace along with fluxes and limestone. Temperatures in the blast furnace reach up
to 1,500 Degree Celsius and the resulting metallurgical reaction converts iron oxide into molten
iron. The blast furnace works round the clock. Tata Steel has eight blast furnaces and six of these
are operational. Hot metal from the blast furnace is transferred into torpedoes and transported to
the LD shops. Here the molten iron is refined into steel using the ‘Basic Oxygen Furnace’ method.
Tata Steel has three LD shops — one dedicated to making steel for long products (used mainly in
43
the infrastructure and construction sectors) and two others for flat steel products (typically used in
automobiles and appliances). At the LD shop the process begins with charging scrap into the
furnace, where temperatures reach 1,700°C. Large ladles, capable of holding 170 tons of liquid
metal, pour the molten iron into the furnace. A water-cooled lance is lowered into the furnace to
blow in pure oxygen. Iron ore (as coolant) and burnt lime and raw dolomite (as flux) are added
from the top. The oxygen removes carbon, silicon, sulphur and phosphorus content from molten
iron and converts it to steel, an alloy that is tougher than iron. One ‘heat’ (a cycle of steelmaking)
takes 45-50 minutes and produces an average of 158 tons of molten steel. The properties required
for steel depend on the end use. And so, from every heat, a sample of the molten steel is analyzed
to see if it meets the requirement. If there is any variation, a ‘correction blow’ is ordered. Once
perfected to specification, liquid steel — still aglow at about 1,630-1,690°C — is tapped into a
ladle car positioned under the furnace. During tapping, Ferro-alloys and aluminum are added
directly into the steel ladle for alloying and deoxidization. This steel goes through further refining,
depending on requirement, at the online purging station, ladle furnace station or RH degasser.
Ladles with a holding capacity of 160 tons carry the liquid steel to the continuous caster machines.
Here the liquid steel finally takes solid form and is shaped into what are called long products or
flat products. The long products are processed at the wire mill to produce wire rods and rebars.
Tata Steel makes a range of long products, including TMT rebars branded as Tata Tiscon, and steel
wires that sell under the brand name Tata Wiron. Flat steel is further processed at the hot rolling
mill or cold rolling mill, depending on end use. Cold rolling mills have a continuous galvanizing
line and produce the galvanized steel used in the automotive, engineering and appliances sectors.
Tata Steel’s branded flat steel products — Shaktee, Galvano and Steelium — are known for their
world-class quality.
44
TABLE 1Transformation system characteristics for Steel and Steel products
Transformation
system
characteristics
STEEL STEEL PRODUCTS
LONG PRODUCTS FLAT PRODUCTS
Number of
routings
3 3 3
Number of raw
materials
2 1 1
Number of
ingredients
2 0 0
Number of
inventory points
1 1 1
Number of
separate work
centers
5 3 3
Run time 13:30 Hrs. :30 Hrs. :30 Hrs.
For steel
Number of routings: There are three production lines because there are three LD-shops which
transform molten iron into liquid steel.
Raw materials used: Iron ore and Scrap
Ingredients used: Coke, is the only source of heat in the furnace and limestone, is used for
removing impurity in the form of flux.
Inventory points: In the production of Steel there is only one inventory point i.e. when molten
iron is brought from blast furnace into the LD shop through torpedoes.
Work centers: There are five work centers i.e. Sinter plant ,Pellet plant, Coke plant, Blast furnace,
LD-Shop.
45
Degree of flexibility in work centre/equipment choice
List of equipments used in producing steel:
Name of equipment
quantity
use
Sinter plant 4 Used for treating iron ore
Pellet plant 1 Used for treating iron ore
Blast furnace 6 For converting iron ore into molten iron
LD-Shop 3 For making liquid steel from molten iron
Torpedoes For transporting molten iron into LD-
shop
Ladle Receiver of molten iron
vessel 3 each LD-shop Oxygen lancing done
So, from above table we can conclude that there is very high degree of flexibility in work
centre/equipment choice.
Degree of continuity of flow: Flow of material (WIP) is almost continuous. It interrupts at one
point while transporting molten iron from blast furnace to the LD-shop.
Degree of structural and formulation complexity It involves high degree of structural and
formulation complexity because certain level of temperature, pressure, PH level etc. needs to be
maintained for the producing steel. Deviation from defined working conditions may lead to
generation of product of inferior quality.
Degree of product variety Grade of steel to be produced has been pre-determined. Hence, degree
of product variety is low.
46
For steel product
Number of routings: There are three production lines. Billets from LD-1 are processed
simultaneously by merchant mill, new bar mill and wire rod mill for produces long products.
Blooms which is the output of LD-2 and 3 is processed by HSM, CRM and TSCR respectively.
Raw materials used: Liquid steel
Ingredients used: None
Inventory points: In the production of Steel product, there is only one inventory point i.e. when
Billets/Blooms are transported to their respective mills through train.
Work centers: There are three work centers i.e. caster, cutter and mills.
Degree of flexibility in work centre/equipment choice
List of equipments used in producing steel:
Name of equipment Quantity Use
Caster 3 each LD-shop Used for giving shape to liquid steel
Cutter 6 Used for separating billets/blooms
Mills 6 For shaping billets/blooms into flat/long
products.
So, from above table we can conclude that there is very high degree of flexibility in work
centre/equipment choice.
Degree of continuity of flow: Flow of material (WIP) is almost continuous. It interrupts at one
point while transporting billets/blooms form LD-shop to different mills.
Degree of structural and formulation complexity Production process of steel product involves
low degree of structural and formulation complexity
Degree of product variety Degree of product variety is low. Since, steel products are produced
from liquid steel.
47
General Purpose Equipment Specialty equipment
EQUIPMENT MATRIX
NA Sinter plant
Pellet plant
Blast furnace
LD-Shop
Torpedoes
Ladle
Vessel
D
E
D
I
C
A
T
E
D
NA Caster
Cutter
Mills
N
O
N
D
E
D
I
C
A
T
E
D
48
FIGURE 1 . STEPS OF STEEL MANUFACTURING
Conversion of Iron
ore into Sinter/pellet
Charging blast
furnace with sinter,
coke and limestone
Transfer of molten
iron through torpedo
from blast furnace to
LD shop
Charging vessel for
oxygen lancing with
molten iron and
scrap
Billets from LD-1
and blooms from
LD-2 & 3 sent to
rolling mills
Casting the liquid
steel through caster
Flat and long
products available
for suppliers
49
FIGURE 2 . STAGES OF STEEL MANUFACTURING
IRON MAKING
STEEL
MAKING
SHAPING
OF STEEL
Sinter Plant (4)
LD-3
LD-2
LD-1
TSCR
Hot Strip Mill
CRM
Merchant Mill
New Bar Mill
Wire Road Mill
Blast Furnace
(8)
Pellet plant (1)
Coke plant (1)
Limestone plant
(1)
Long
Product
Flat Product
50
3.4 Moonidih Washery
Firm profile
Moonidih Washery is being run by Bharat Coking Coal Limited, one of the subsidiaries of Coal
India limited. Coal India limited is a Public Sector Undertaking engaged in mining of coal and
allied activities. It occupies an important place in as much as it produces bulk of the coking coal
mined in the country. BCCL meets almost 50% of the total prime coking coal requirement of the
integrated steel sector. BCCL was incorporated in January, 1972 to operate coking coal mines
operating in the Jharia & Raniganj Coalfields, taken over by the Govt. of India on 16th Oct, 1971
to ensure planned development of the scarce coking coal resources in the country.
This plant is incorporated in the year 1983 whose operable capacity is 1.60
metric ton /year. Run of Mines (ROM) from various mines and seams are processed to produce
washed coal and washed power coal (Middling). Washed coal is used as fuel in steel manufacturing
firms whereas washed power coal (Middling) is used in power plant. This unit uses Heavy Media
Cyclone Technique for particle size 37 mm and Water-only Cyclone for particle size less than 0.5
mm.
Run of Mines (ROM) of size 450 mm is feed into De sliming screen with water through
rotary breaker and secondary crusher. Particle size feed into the De sliming screen is of 37 mm.
De sliming screen is used for separating fine coal and water. Heavy Media Cyclone method utilizes
Magnetite as media, used for purifying lump coal. Water only Cyclone method is used for
purifying fine coal of particle size less than 0.5 mm.
Coal preparation serves several objectives. One of the significant aims is to increase the
heating value of the coal by motorized removal of impurities. This is often necessary in order to
find market place for the product. Run-of-mine coal from a mine may include as much as 60
percent reject materials. Air pollution control often requires fractional removal of pyrites with the
ash to reduce the sulfur content of the coal. Ash content often must be controlled to conform to a
prescribed quality i.e. ash content should be restricted to 19.4-21%, stipulated in contractual
agreements with state run steel manufacturing firms. Because of firing characteristics, it is often
as important to retain the ash content at a given level as it is to reduce it. Freight savings are
substantial when impurities are removed preceding loading. Finally, the rejected impurities are
51
more easily disposed of at the mine site remote from cities than at the burning site, which is usually
in a populated area.
Number of routings: There is only one production line. So, the number of routings will be one.
Raw materials used: Run of Mines (ROM)
Ingredients used: Magnetite as media for Heavy Media Bath Technique.
Inventory points: There is zero inventory point because production process integrated of different
sub-systems of the plant in a building of height 36 feet.
Work centers: There are five separate work centers i.e. ROM bunker, Rotary Breaker, Secondary
Crusher, C.C. Thicker and C.C. Silo. Equipments related cleaning coal have been assembled in 6
storey building.
Run time: This plant processes 700 Ton of ROM every hour.
Degree of flexibility in work centre/equipment choice
Washery industry demonstrates medium degree of flexibility in work center and equipment choice
because of unavailability of alternative production line and availability of redundant equipments.
List of equipments used:
Name of equipment Quantity
Use
Rotary Breaker 2 Crushing ROM into size of 125 mm
Dilute Pump 2 Circulating water
C.C. Silo 4 Storing cleaned coal
C.C. Thicker 2 Storing cleaned coal (<0.5 mm)
Magnetic separator 4 Regenerating Magnetite.
De sliming screen 4 Separating fine coal and water
Secondary Crusher 3 Crushing ROM into size of 37 mm
HM Cyclone 4 Separating waste material from coal
Dense Media Pump 2 Circulating media
52
Degree of product variety
Medium degree of product variety in the yield of washery industry is prevailing because products
are chemically similar as well as similar percentage composition of constituent elements.
Degree of Structural and Formulation Complexity
Washery industry demonstrates relatively medium degree of structural and formulation complexity
because certain level of specific gravity (1.5 Kg/m3 for HM Cyclone) has to be maintained.
Degree of continuity flow
In Washery industry, flow of material is continuous throughout the production process with
possible economic interruption.
Transformation System characteristics
Number of Routings 1
Total number of Raw materials 1
Number of ingredients used in the product 2
Number of different finished goods 2
Number of inventory points for the routings 0
Number of separate work centers for the routings 5
53
EQUIPMENT MATRIX
General purpose equipment Specialty equipment
NA Dilute Pump
HM Cyclone
Magnetic Separator C.C. Thicker
Dense Media Pump
D
E
D
I
C
A
T
E
D
NA Rotary Breaker
De sliming Screen
Secondary Crusher C.C. Silo
N
O
N
D
E
D
I
C
A
T
E
D
54
PROCESS FLOW DIAGRAM IN MOONIDIH WASHERY
ROM
Bunker
Rotary
Breaker
Storage Pile De-sliming
screen
Secondary
Cyclone
Midd.
HFScreen
Secondary
crusher
Reject Bin
C.C. Silo HF screen
Secon.WO
cyclone
Midd.
Screen
HM Pump
Primary
WOCyclone
HM
Cyclone
Dense
mediaPump
C.C.
Thicker Reject
Bunker
Midd. Silo
Sec.
Mag.Separa
tor
Prim.
Mag.Separa
tor
Dilute Pump
Reject
Screen
CC Screen
55
3.5 Bhojudih Washery
Firm profile
Bhojudih Washery is being run by Bharat Coking Coal Limited, one of the subsidiaries of Coal
India limited. Coal India limited is a Public Sector Undertaking engaged in mining of coal and
allied activities. It occupies an important place in as much as it produces bulk of the coking coal
mined in the country. BCCL meets almost 50% of the total prime coking coal requirement of the
integrated steel sector. BCCL was incorporated in January, 1972 to operate coking coal mines
operating in the Jharia & Raniganj Coalfields, taken over by the Govt. of India on 16th Oct, 1971
to ensure planned development of the scarce coking coal resources in the country.
Operable capacity of this unit is 1.60 metric ton /year, started its operation
since 1962 for processing Run of Mines (ROM). ROM is from various mines and seams. Washed
coal is supplied to government owned steel plant, Steel Authority of India Limited and washed
power coal (Middling) to power plant. Heavy Media Bath Technique is used for processing coal
of particle size 75-16 mm using magnetite as media. Batac jig technique is used for processing
coal of particle size less than 16mm by generating pulsation. Forth Floatation technique uses pine
oil as media for beneficiation of coal of particle size less than 0.5mm.
Coal preparation serves several objectives. One of the
significant aims is to increase the heating value of the coal by motorized removal of impurities.
This is often necessary in order to find market place for the product. Run-of-mine coal from a mine
may include as much as 60 percent reject materials. Air pollution control often requires fractional
removal of pyrites with the ash to reduce the sulfur content of the coal. Ash content often must be
controlled to conform to a prescribed quality i.e. ash content should be restricted to 19.4-21%,
stipulated in contractual agreements with state run steel manufacturing firms. Because of firing
characteristics, it is often as important to retain the ash content at a given level as it is to reduce it.
Freight savings are substantial when impurities are removed preceding loading. Finally, the
rejected impurities are more easily disposed of at the mine site remote from cities than at the
burning site, which is usually in a populated area.
56
Number of routings: There is only one production line. So, the number of routings will be one.
Raw materials used: Run of Mines (ROM)
Ingredients used: Magnetite and Pine oil as media for Heavy Media Bath Technique and Forth
Floatation technique respectively.
Inventory points: There is zero inventory point because production process is entirely continuous.
Work centers: There are no separate work centers. All equipments have been assembled in 6
storey building. Different equipments have been kept at different heights.
Run time: This plant processes 500 Ton of ROM every hour.
Degree of flexibility in work centre/equipment choice
Washery industry demonstrates medium degree of flexibility in work center and equipment choice
because of unavailability of alternative production line and availability of redundant equipments.
List of equipments used:
Name of equipment Quantity
Use
Bath Pump 2 Circulating water used with media
Dilute Media Pump 2 Circulating media
Compressor 2 Maintaining pressure differences
Blower 2 Maintaining pressure differences
Vibrating Screen 4 Generating pulsation for filtration.
Crusher 2 Crushing ROM
Batac Jig 1 Separating waste material from coal
HM Bath 1 Separating waste material from coal
57
Degree of product variety
Medium degree of product variety in the yield of washery industry is prevailing because products
are chemically similar as well as similar percentage composition of constituent elements.
Degree of Structural and Formulation Complexity
Washery industry demonstrates relatively medium degree of structural and formulation complexity
because certain level of specific gravity (1.5 Kg/m3 for HM Bath and1.65 Kg/m3 for Batac Jig)
has to be maintained.
Degree of continuity flow
In Washery industry, flow of material is continuous throughout the production process with
possible economic interruption.
Transformation System characteristics
Number of Routings 1
Total number of Raw materials 1
Number of ingredients used in the product 2
Number of different finished goods 2
Number of inventory points for the routings 0
Number of separate work centers for the routings 0
58
EQUIPMENT MATRIX
General purpose equipment Specialty equipment
NA Dilute Media Pump
HM Bath
Batac Jig
D
E
D
I
C
A
T
E
D
NA Bath Pump
Compressor
Blower
Vibrating Screen
Crusher
N
O
N
D
E
D
I
C
A
T
E
D
59
4. Analysis
Data analysis has two components: within case analysis and across case analysis. Within case
analysis helps us to analyze transformation system characteristics in the context of one firm rather
than one industry, while the across case analysis serves as a form of replication by analyzing
characteristics of the transformation system in the context of one industry rather than one firm
(Yin 1994).
Within case analysis
The objective behind doing “within case analysis” is to structure and refine the information
obtained from plant visit to bring sense i.e. for precise description of characteristics of
transformation system for each firm which is element of unit of analysis. While visiting plant we
were exposed to multiple respondents, with varying degree of knowledge prowess in operational
and technical domain. Therefore, it becomes necessary to compile gathered information in an
organized manner which is subsequently conducive in analyzing the same in best suitable manner.
Dairy Firms
We started our data collection from one unit i.e. unit-1 of dairy industry, involved in collecting
raw milk from different milk unions for processing and producing milk products, serving few
provinces of the state. Dairy industry usually consists of Product producing milk of different
quality defined in terms of Fat and SNF percentage and Process Sections is involved in the
production of different milk products i.e. Curd, Cheese, flavored milk, flavored liquid curd. This
unit is being owned by co-operative society and equipped with machines which are relatively more
automated than our other unit of analysis in dairy industry.
There are two unconventional channels, with single conventional production line, for mixing
butter / skimmed milk powder, Whole milk powder, which serves the purpose of ingredient, into
the crude milk which contributes towards increasing/decreasing fat and SNF percentage
respectively, depending upon the type of milk to be produced. In process section, number of
inventory points depends upon the supply of raw milk and demand of processed milk in the local
market. In case of smooth running of plant there will be no inventory points but in case of supply
- demand mismatch there will be two inventory points i.e. Milk Silo and upper head tank. There
are five work centers i.e. Homogenizer, cleaner/separator, turbo-jet blender, heat exchanger and
60
packaging machine, with high degree of flexibility in equipment/work centre choice because of
availability of alternative production line and availability of redundant equipments. There is
medium degree of product variety because products are chemically similar but there is variation
in the percentage composition of fats, SNF and water in different grades of milk.
In product section, number of routing for each product is one, using raw milk as only raw
material with varying number, from 2-6, and characteristics of ingredients .. Number of inventory
points is one for majority of products. Maximum average number of work centers, for product
section in dairy industry, is six.
Following replication strategy for generalizing the research outcome across industry we
collected data from other manufacturing unit of same firm. But it is different from our previous
unit of analysis in terms of functioning, production capacity as well as degree of automation.
This unit primarily functions as hub because it is among six milk unions, where farmers from
nearby provinces supplies raw milk and majority of milk collected thereof is processed and
supplied through milk tankers and milk wagons to the units situated in the southern part of the
province, which is basically industrial area, with rich deposits of mines and minerals and
geographically plateau region and lacking in cultivatable land. This unit also produces milk and
milk products for serving few nearby districts of the province. As far as production process is
concerned, both plants utilize similar methods, but they vary in terms of degree of automation and
quantity of milk and milk products produced by unit-2.Meanwhile, there process characteristics
pertaining to transformation system is similar to our previous unit of analysis.
Operational issues concerning to dairy industry has been described in this paragraph. Units
of milk, in terms of their quality and quantity, to be produced every day along with the type of
milk product to be produced are driven by demand of the product in the local market. But, they
produce specific product of specific quality every day to meet consistent demand of market. In
other words, they are following combined MTO-MTS strategy. In dairy industry, quality and, in
some cases, quantity of the output depends upon the quality of raw material i.e. crude milk, has
been determined in terms of fat and Solid Non Fat (SNF) content. Due to uncertainty associated
61
with the supply of raw milk, into the plant from different milk unions or farmers, as well as with
the demand of milk and its product, there inventory storage cost increases .In this industry there is
responsiveness issue because of supply demand mismatch between raw material and finished
product.
Steel manufacturing industry
Company-1 is today among the country’s largest integrated steel-making facilities, producing
10 million tons of steel every year. Steel is considered a green product because it is 100-percent
recyclable and has an infinite life cycle. It is among the top 10 global steel companies and one of
the world’s most geographically diversified steel producers, with operations in 26 countries and a
commercial presence in more than 50.
This unit is involved in manufacturing flat products and long products, with very low degree
of product variety because of insignificant variation in constituent element in terms of quality and
quantity, i.e. Hot rolled, Cold rolled, metallic coated, direct rolled, prefinished steels, packaging
steels, electroplated steels, electrical steels, narrow strips, long product i.e. for catering to the need
of infrastructure building and automobile manufacturing industry. It offers a wide range of
standard and differentiated products for different and demanding markets worldwide such as ultra-
high strength steel for Automotive, specialty steels for Aerospace and ultra-high hardness steels
for Defense & Security.
In our analysis, transformation system of steel manufacturing industry has been analyzed for
two products i.e. liquid steel and flat and long product because of prevailing major or substantial
difference in the characteristics of transformation system. In steel manufacturing process, there are
three production lines because there are three LD-shops which transform molten iron into liquid
steel which can be on subsequent stage can be casted into different shapes for producing different
products. Raw material used in manufacturing of liquid steel are iron ore and scrap with few
ingredients which works as catalyst, i.e. expedites conversion rate, are limestone and coal in the
form of coke for providing sufficient amount of heat and oxygen to blast furnace. In the production
of Steel there is only one inventory point i.e. when molten iron is brought from blast furnace into
the LD shop through torpedoes with four work centers, Sinter plant, Pellet plant, Blast furnace,
LD-Shop with high degree of flexibility in selection of work center and equipments. Steel
62
manufacturing process basically involves high degree of structural and formulation complexity
because of high precision in controlling different process parameters.
Whereas in steel product manufacturing process number of production line highly depends upon
the number of products belonging to different class of product i.e. flat and long product. This
industry is involved in manufacturing flat products i.e. Hot Rolled, Cold rolled, metallic coated,
direct rolled, prefinished steels, packaging steels, electroplated steels, electrical steels, narrow
strips, long product i.e. sections , rebar , plates ,rails, wires, wire rods for catering to the need of
infrastructure building and automobile manufacturing industry. It offers a wide range of standard
and differentiated products for different and demanding markets worldwide such as ultra-high
strength steel for Automotive, specialty steels for Aerospace and ultra-high hardness steels for
Defense & Security. Therefore, this industry primarily follows Make-To-Stock (MTS) strategy
and on the other side, for meeting the demand of specialty product placed by automotive,
aerospace, defense and security sector; they adopt Make-To-Order (MTO) Strategy. In the entire
steel product production process, this involves conversion of lump iron ore into steel products by
Blast Oxygen Furnace (BOF) or Electric Arc Furnace (EAF) technology ,there are three inventory
points ,where Work In Progress (WIP) is in queue ,this results into increase in lead time as well
as decrease in production rate .Hence, increases inventory storage cost.
Steel products have certain specific quality standard which has been decided upon percentage
composition of Iron, nickel, Chromium, carbon, Argon and other elements. Quality of steel
depends mostly upon carbon percentage prevailing in the steel .Therefore, for achieving quality
standard different metallurgical tests has been performed on liquid steel and subsequently
electrolytic refining should be done to bridge the gap between predetermined and prevailing carbon
percentage in the hot metal, if any. Hence, the repeated occurrence of electrolytic refining
performed on the same sample or number of samples increases lead time as well as augments cost
of production of steel by consuming more time and valuable resources of the organization.
Coal preparation plant
Unit-1 is incorporated in the year 1983 whose operable capacity is 1.60 metric ton /year , run by
one of the subsidiary of government owned organization, which is enjoying the stature of
Maharatna company and is the single largest coal producer in the world, for processing Run of
Mines (ROM), from various mines and seams, and supplying their yield i.e. washed coal to
63
government owned steel plant and washed power coal (Middling) to power plant using Heavy
Media Cyclone Technique, used for coal of particle size 37 mm and Water-only Cyclone technique
used for coal of particle size less than 0.5 mm.
Run of Mines (ROM) is the raw material for coal beneficiation plant, of size 55 mm, which is
subsequently feed into rotary breaker and, later on, into secondary crusher to fragment it into
particle size of 37 mm..Heavy Media Cyclone method, which utilizes Magnetite as media, is used
for purifying lump coal whereas Water only Cyclone method is used for purifying fine coal of
particle size less than 0.5 mm.
This plant is having single routing with high degree of automation i.e. continuous integration
of different sub-systems of the plant, in a building of height 36 feet, without any inventory point
and without any specific separate work-centers. This plant is having medium degree of flexibility
in equipment / work center choice with moderate level of structural and formulation complexity
because of flexibility in quality of the product. Yield of this industry is having medium degree of
product variety because product is chemically similar but vary in terms of percentage composition
of constituent elements.
Unit-2 whose operable capacity is 1.60 metric ton /year ,started its operation since 1962 ,
operated by one of the subsidiary of government owned coal mining company, which is enjoying
the stature of Maharatna company and is the single largest coal producer in the world, for
processing Run of Mines (ROM), is the raw material for coal beneficiation plant ,from various
mines and seams, and supplying their yield i.e. washed coal to government owned steel plant and
washed power coal (Middling) to power plant using Heavy Media Bath Technique, used for coal
of particle size 75-16 mm ,uses magnetite as media, Batac jig technique used for processing coal
of particle size less than 16mm,by generating pulsation ,and Forth Floatation technique, uses pine
oil as media, for beneficiation of coal of particle size less than 0.5mm.
Characteristics of transformation system of this coal beneficiation plant are almost similar to
our previous unit of analysis. There is variation in the number of ingredients used in this plant is 2
i.e. magnetite and pine oil.
64
Coal preparation serves several objectives. One of the significant aims is to increase the
heating value of the coal by motorized removal of impurities. This is often necessary in order to
find market place for the product. Run-of-mine coal from a mine may include as much as 60
percent reject materials. Air pollution control often requires fractional removal of pyrites with the
ash to reduce the sulfur content of the coal. Ash content often must be controlled to conform to a
prescribed quality i.e. ash content should be restricted to 19.4-21%, stipulated in contractual
agreements with state run steel manufacturing firms. Because of firing characteristics, it is often
as important to retain the ash content at a given level as it is to reduce it. Freight savings are
substantial when impurities are removed preceding loading. Finally, the rejected impurities are
more easily disposed of at the mine site remote from cities than at the burning site, which is usually
in a populated area.
Because of indulgence in contractual agreement with state run steel manufacturing
organization to produce washed/clean coal with ash content limited to 19.4-21%, these state run
coal preparation plant follow Make –To-Order (MTO) strategy.
To achieve the pre-determined quality of coal, specific gravity of 1.5 Kg/m3 and 1.65 Kg/m3
for Heavy Media Bath (HM Bath) and Batac Jig method respectively should be maintained.
Therefore, major operational issues pertaining to this industry is quality issue. In case of non-
conformity with the agreement, mentioning the quality standard, the company will lose their profit.
Use of technology depends upon the size of coal for example for lump coal whose size is 75-
16 mm, Heavy media bath technology is used whereas for coal particles whose size is 16-0.5 mm
,Batac jig is used, for particle size less than 16 mm, froth floatation method is used. Therefore, the
cost of production varies with the technology used in washing coal. Magnetite, iron ore, is used as
media in HM Bath/HM cyclone technology, is costlier than pine oil used as media in froth
floatation process. Therefore, for given plant cost of production entirely depends upon the cost
incurred in procuring media. Therefore, it becomes important, efficient utilization of media used
in a particular process for specified particle size.
65
Since these plants are established in 1960’s and 1980’s,they are not running in full capacity
and producing two types of product i.e. washed coal for metallurgical purpose and washed power
coal, which is also termed as middling, for power plants.
These units are using MTO strategy for producing washed coal of specific quality because
of prior contractual agreement with state run steel manufacturing firm. Therefore; they don’t have
performance issue pertaining to uniform lead time.
Aspects such as (i)The supply of Run of Mines (ROM) to any washery plant is from
different coal seam or different mines, which is varying on certain parameters such as density,
hardness, sizing and cleaning characteristics, coking property, ash, volatile matter, sulphur and
phosphorus content, etc.. Hence, different factors related to production process needs to be
adjusted according to the desired yield of the process. (ii) They are having common process routing
i.e low degree of routing and equipment flexibility in production process, which are operational
issues of washery industries needs concern. Therefore, washery plant primarily involves efficiency
issues, secondarily flexibility and responsiveness issues is not prevalent.
characteristics Dairy Steel Washery
Number of Routings 1 1 3 1 1
Total number of Raw materials 1 1 2 1 1
Number of ingredients used in the
product
9 9 2 1 2
Number of different finished goods 6 6 2 2 2
Number of inventory points for the
routings
1 1 1 0 0
Number of separate work centers
for the routings
6 6 4 0 0
66
Across case analysis
Replication strategy is implemented by us for generalizing our theory across industry by visiting
two plants/units of varying production capacity and production technology and sometimes they
vary on the basis of their yield, of a manufacturing industry in tandem. Data gathered from these
sites is being arranged and later on compared which will be conducive in drawing conclusion after
testing our above mentioned propositions. Therefore, the across case analysis is concerned with
identifying patterns across different organizations and their products. Analysis is being done across
industry as well as across product so that the outcome of our research can be applied to most of
the process industry.
Dairy Industry Vs Steel Industry
Dairy industry is having single production line for each finished product i.e. milk and milk product,
after processing milk with different ingredients, for different milk products, in varying quantity
with one inventory points with six separate work centers whereas, steel industry has three
production because there are three LD-shops which transform molten iron into liquid steel which
can be on subsequent stage can be casted into different shapes for producing flat and long product,
with single inventory points using four separate work centers using iron ore and scrap as raw
material and coke and limestone as catalyst. Dairy industry and steel industry are exhibiting
relatively high degree of flexibility in work center and equipment choice because of availability
of alternative production line and availability of redundant equipments. There is medium degree
of product variety in dairy industry because products are chemically similar but there is variation
in the percentage composition of fats, SNF and water in different grades of milk with relatively
low degree of structural and formulation complexity because of frivolity in controlling different
production parameters whereas steel industry demonstrates relatively very low degree of product
variety because products are chemically similar as well as similar percentage composition of
constituent elements, with high degree of structural and formulation complexity is prevailing in
production of steel because of requisite précised control of different production parameters such
as PH level, pressure, volume, temperature, concentration of reactant etc..In terms of degree of
continuity flow, dairy industry and steel industry displayed continuous and intermittent flow with
possible economic intentional interruption in dairy industry because of negligible start up cost
67
whereas in the situation of shutting down of plant in steel industry will cost higher as well as off
quality product. Production process of milk is continuous whereas process for milk product is
intermittent. In steel plant, production process of pig iron is continuous and production process of
steel product is intermittent. Therefore, after analyzing transformation system of both industries,
we found variation in characteristics of the transformation system with some similarity i.e. number
of inventory points in characteristics of the transformation system.
Dairy Industry Vs Washery Industry
Dairy industry is having single production line for each finished product i.e. milk and milk product,
after processing milk with different ingredients, for different milk products, in varying quantity
with one inventory points with six separate work centers. Washery industry has single production
line, producing washed coal and washed power coal using solution of water and magnetite/pine
oil as ingredients similar to dairy industry without any inventory points, separate work centers.
Dairy industry is exhibiting relatively high degree of flexibility in work center and equipment
choice because of availability of alternative production line and availability of redundant
equipments whereas washery industry demonstrates medium degree of flexibility in work center
and equipment choice because of unavailability of alternative production line and availability of
redundant equipments. There is medium degree of product variety in dairy industry and washery
industries because products are chemically similar but there is variation in the percentage
composition of constituent elements Relatively low degree of structural and formulation
complexity displayed by dairy industries because of frivolity in controlling different production
parameters whereas washery industry demonstrates relatively medium degree of structural and
formulation complexity because of array in the quality of yield. Medium degree of product variety
in the yield of dairy and washery industries are prevailing because products are chemically similar
as well as similar percentage composition of constituent elements. In terms of degree of continuity
flow, dairy industry displayed continuous and intermittent flow with possible economic intentional
interruption because of negligible start up cost whereas in case of washery industries flow of
material is continuous throughout the production process with possible economic interruption.
Therefore, after analyzing transformation system of both industries, we found variation in
characteristics of the transformation system with some similarity such as in number of inventory
points, number of routings, number of raw materials, degree of product variety.
68
Steel Vs Washery industry
Steel industry has three production because there are three LD-shops which transform molten iron
into liquid steel which can be on subsequent stage can be casted into different shapes for producing
flat and long product, with single inventory points using four separate work centers using iron ore
and scrap as raw material and coke and limestone as catalyst though Washery industry has single
production line, producing washed coal and washed power coal from Run- Of –Mines (ROM)
using solution of water and magnetite/pine oil as media, with zero inventory points and no separate
work centers.
Steel industry is exhibiting relatively high degree of flexibility in work center and equipment
choice because of availability of alternative production line and availability of redundant
equipments although washery industry displayed medium degree of flexibility in work center or
equipment choice because of unavailability of alternative production line of existence of
redundant machines. Relatively medium degree of product variety in washery industries is
displayed because products are chemically similar but there is variation in the percentage
composition of constituent elements whereas steel industry demonstrates relatively very low
degree of product variety because products are chemically similar as well as similar percentage
composition of constituent elements .High degree of structural and formulation complexity is
prevailing in production of steel because of requisite précised control of different production
parameters such as PH level, pressure, volume, temperature, concentration of reactant etc. while
washery industry demonstrates relatively medium degree of structural and formulation complexity
because of array in the quality of yield. In terms of degree of continuity flow, steel industry
displayed continuous and intermittent flow of material and in the situation of shutting down of
plant will cost higher as well as off quality product .In steel plant, production process of pig iron
is continuous and production process of steel product is intermittent whereas flow of material is
continuous throughout the production process with possible economic interruption in washery
industries. Therfore, steel and washery industry is varying on every defined parameters without
any similarity.
69
Table-4 Across industry
characteristics Dairy Steel Washery
Number of Routings 1 3 1
Total number of Raw materials 1 2 1
Number of ingredients used in the
product
9 2 3
Number of different finished goods 7 6 2
Number of inventory points for the
routings
1 2 0
Number of separate work centers
for the routings
6 4 0
Run Time (Transformation run time
Move time)
L H M
Degree of flexibility in work
centre/equipment choice
H H M
Degree of continuity of flow Refer to table 5 Refer to table 5 Refer to table
5
Degree of structural and
formulation complexity
L H M
Degree of product variety 2 1 2
70
Table 5 Degree of continuity of flow (Industry Wise)
FLOW ECONOMIC
INTENTIONAL
INTERRUPTION
INDUSTRY
TYPE
Continuous + intermittent Yes
Dairy
Continuous + intermittent No Steel
Continuous Yes Washery
In Table 4 & 5, we are striving to classify different transformation system of process industry in
terms of clearly manifests that the transformation system of different types of process industry
can be clearly distinguished on the basis of different parameters such as number of routings, degree
of continuity of flow, raw materials and ingredients used, yield of transformation system, run time,
number of inventory points within a routing, number of separate work centers used within routing,
flexibility in work center and equipment choice, structural and formulation complexity, Degree of
product variety, Startup cost, safety and environmental issues. Above table we can draw following
conclusion, based upon majority of transformation system characteristics:-
Transformation system of dairy and coal preparation plant is entirely different from steel.
Therefore, we can conclude that, on the dimension of industry, there are three different
transformation systems. But, each one is using similar type of equipment i.e. Specialty Non-
Dedicated equipment.
Table-3 Across Product
characteristics Milk Milk product Steel Steel product Washery
Number of Routings 1 4 3 1 1
71
Total number of Raw materials 1 1 1 1 1
Number of ingredients used in the
product
6 3 2 2
Number of different finished goods 7 1 6 2 2
Number of inventory points for the
routings
H M M L 0
Number of separate work centers
for the routings
3 7 16 0
General purpose equipment
Dedicated (%)
Non-Dedicated (%)
Specialty equipment
Dedicated (%)
Non-Dedicated (%)
Run Time (Transformation run
time Move time)
L H H M M
Degree of flexibility in work
centre/equipment choice
2. 7 3 1
Degree of continuity of flow Refer to
table 5
Refer to table
5
Refer
to table
5
Refer to table
5
Degree of structural and
formulation complexity
L H H M M
Degree of product variety 4 1 1 2 1
Startup cost L H H L L
Safety concerns L H H M M
Environmental concerns L H H M M
Operation Flexibility H L L M L
72
5. Conclusion & Directions for Future Research
This is a study of Process Industry transformation system. The objective was to test the
following propositions by Dennis and Meredith (2000b): (i) Classifying PI on the basis of
production volume and product variety doesn’t convey significant information regarding
individual transformation systems, (ii) Two firms producing same products and occupying the
same position on the product-process matrix could have dissimilar transformation system
characteristics and face different operational challenges, and (iii) Two firms producing dissimilar
products and occupying different position in the product-process matrix could have similar
transformation characteristics
We use case study to test the propositions by Dennis and Meredith (2000b). Case methods, due
to the effort involved, are primarily useful when developing new theory or selective testing of
existing theories in polar type or extreme cases. The confirmatory test procedure consists of
developing a theoretical background, and developing a systematic research design including
evaluation criteria. The research design comprises the: (1) unit of analysis, (2) appropriate cases
to study, and (3) data to collect and how to collect it.
In a process industry the non-discrete units often becomes discrete at some point during the
manufacturing process. We choose Dairy, Steel (includes Steel products), and Coal preparation
plants as unit of analysis. The product becomes discrete in the Dairy at the point of packaging, in
the Steel industry after casting, and Coal preparation plant the material remains discrete during the
entire process. A set of two firms in each industry, Dairy, Coal Preparation, and Steel is selected
leading to six cases. Due to time restriction we however could study only five cases (which is only
one case in Steel industry). Our unit of analysis comprises of firms which are privately and publicly
owned, whose market varies from regional to global. The Dairy firms cater to regional market, the
Coal preparation plant market their product nationwide while the Steel plant supply globally.
The within-case analysis shows in-between differences between the two Dairy plants and two
Coal Preparation plants in terms of transformation system characteristics. These indicates that two
firms producing same products and occupying the same position on the product-process matrix
could have dissimilar transformation system characteristics and face different operational
challenges.
The across-case analysis shows a few in-between similarities between the Dairy plants and Coal
Preparation plants in terms of transformation system characteristics. These indicates that two firms
73
producing widely dissimilar products and occupying different position in the product-process
matrix could have similar transformation characteristics. Though this study supports the
proposition still further evidence using a different set of cases is needed.
References
Appoo, P. (1987). "A practical method of implementing the batch BOM in the process industries."
PROD. INVENTORY MANAGE. 28(2): 79-84.
Barnett, B. D. and K. B. Clark (1996). "Technological newness: an empirical study in the process
industries." Journal of Engineering and Technology Management 13(3): 263-282.
Bonoma, T. V. (1985). "Case research in marketing: opportunities, problems, and a process."
Journal of marketing Research: 199-208.
Dennis, D. R. and J. R. Meredith (2000a). "An analysis of process industry production and
inventory management systems." Journal of Operations Management 18(6): 683-699.
Dennis, D. and J.R. Meredith (2000b). "An empirical analysis of process industry transformation
systems." Management Science 46(8): 1085-1099.
Dibono, P. (1997). Flow Manufacturing Improves Efficiency and Customer Responsiveness.
Eisenhardt, K. M. and M. E. Graebner (2007). "Theory building from cases: Opportunities and
challenges." Academy of management journal 50(1): 25-32.
Fransoo, J. C. (1992). "Demand management and production control in process industries."
International Journal of Operations & Production Management 12(7/8): 187-196.
Gerchak, Y., A. Tripathy, et al. (1996). "Co-production models with random functionality yields."
IIE transactions 28(5): 391-403.
Haxthausen, N. (1995). "The painkiller for batch control headaches." Chemical Engineering
102(10).
Hayes, R. H. and S. C. Wheelwright (1979). "Link manufacturing process and product life cycles."
Harvard business review 57(1): 133-140.
Hirschman, E. C. (1986). "Humanistic inquiry in marketing research: philosophy, method, and
criteria." Journal of marketing Research: 237-249.
Nichols, W. and J. Ricketts (1994). "Identification, tracking, control key to minimizing mill liquor
loss." Pulp and paper 68.
74
Shah, N. (2005). "Process industry supply chains: Advances and challenges." Computers &
Chemical Engineering 29(6): 1225-1236.
Stake, R. E. (1995). The art of case study research, Sage Publications, Incorporated.
Taylor, S. and S. F. Bolander (1991). "Process flow scheduling principles." Production and
Inventory Management Journal 32(1): 67-71.
Taylor, S. G., S. M. Seward, et al. (1981). "Why the process industries are different." Production
and Inventory Management Journal 22(4): 9-24.
Utterback, J. M. (1996). Mastering the dynamics of innovation, Harvard Business Press.
Vollmann, T. E., W. L. Berry, et al. (1997). "Manufacturing planning and control systems."
Yin, R. K. (1999). "Enhancing the quality of case studies in health services research." Health
Services Research 34(5 Pt 2): 1209.