ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
1 of 25
DRAFT January 31, 2017
This guide describes suggested non-mandatory approaches for meeting requirements. Guides are
not requirements documents and are not construed as requirements in any audit or appraisal for
compliance with the parent policy.
TABLE OF CONTENTS
1.0 PURPOSE AND SCOPE ................................................................................................................ 2
2.0 IMPLEMENTATION ..................................................................................................................... 2
3.0 RESPONSIBILITIES ...................................................................................................................... 2
4.0 PROCEDURE ................................................................................................................................. 2
4.1 Process Work Flow Chart ................................................................................................... 2
4.2 Process Work Flow – WRPS acting as PM/Constructor .................................................... 2
4.3 Process Work Flow – WRPS as PM/CMT ......................................................................... 9
5.0 DEFINITIONS .............................................................................................................................. 15
5.1 Administrative change ...................................................................................................... 15
5.2 Construction Representative ............................................................................................. 15
5.3 Non-administrative change. .............................................................................................. 15
5.4 Issue Authorization and Maintenance for Use .................................................................. 16
5.5 Project Management/Constructor Team (PM/Constructor) .............................................. 16
5.6 Project Management & Construction Management Team (PM/CMT)............................. 16
6.0 RECORDS .................................................................................................................................... 16
7.0 SOURCES ..................................................................................................................................... 17
7.1 Requirements .................................................................................................................... 17
7.2 References ......................................................................................................................... 17
TABLE OF FIGURES
Figure 1. Process Work Flow Chart. ......................................................................................................... 19
Figure 2. Construction Execution Process Work Flow Chart. ................................................................... 24
Figure 3. Construction Action Log Process Work Flow Chart. ................................................................. 25
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
2 of 25
DRAFT January 31, 2017
1.0 PURPOSE AND SCOPE
The purpose of this procedure is to establish the WRPS construction management requirements
for EPC projects. This procedure applies to all EPC construction projects executed by WRPS.
Section 4.3 describes the application of this procedure where WRPS EPC has elected to contract
out the construction.
This procedure shall be implemented on any EPC project where, WRPS, acting as the Project
Manager, elects to self-perform as the Constructor to construct the facility. If the Project elects to
contract with an outside entity to act as the Constructor, that entity shall be certified to ASME
NQA-1 2008, with the 2009 Addenda and perform as Constructor to its own processes and
procedures. In that case, this procedure shall be used (in conjunction with other WRPS EPC
procedures) to benchmark the Constructor’s procedures. The results of that benchmarking shall
be the basis for requiring the Constructor to modify its procedures, as necessary, to provide
reasonable assurance that its work products will be of equivalent quality, with sufficient planning
to carry out the work safely, efficiently, on schedule, and meeting any other characteristic
deemed by the Project to be essential. Furthermore, where WRPS has contracted with an outside
entity to act as Constructor, WRPS will provide Construction Management oversight services.
Section 4.3 of this procedure, coupled with the Construction Management Plan (TFC-EPC-PLN-
03) define this service as it applies to this guide.
2.0 IMPLEMENTATION
This procedure is released as a Draft for Low Activity Waste Pretreatment System (LAWPS)
Project (T5L01) use only.
Formal issued date to be determined
3.0 RESPONSIBILITIES
Responsibilities are contained within Section 4.0. Individual tasks may be delegated to qualified
personnel.
4.0 PROCEDURE
4.1 Process Work Flow Chart
See Table of Figure Section, Figure 1 – Process Work Flow Chart.
4.2 Process Work Flow – WRPS acting as PM/Constructor
Figure 1 illustrates the process flow related to pre-construction activities.
A. Acquisition Planning
The first step in the construction work process is acquisition planning. Types of decisions made
are whether the subcontract will be fixed-price versus cost reimbursable, or competitively bid
versus sole source. Issues such as subcontractor experience, personnel qualifications, and
program requirements (e.g., Evaluated Supplier) will be discussed to fully understand the
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
3 of 25
DRAFT January 31, 2017
expectations required of the subcontractor. Acquisition planning requirements and process are
defined in TFC-BSM-CP_CPR-C-05.
Action by Action
Project Manager 1. Involve the CM or designee in the Acquisition Planning Process.
Project Manager/BTR 2. Authorize pre-construction and subcontract execution activities.
Construction Manager 3. Initiate pre-construction activities.
Project Manager 4. Conduct a meeting with appropriate Team members and
Procurement personnel to identify how the work will be
subcontracted.
B. Constructability
Constructability reviews should be performed for all projects. The goal of the constructability
reviews is to optimize benefits to the entire project, not just to a single department or discipline.
Action by Action
CM 1. Ensure Construction participates and performs constructability
reviews on projects and the design documents per TFC-EPC-
CM-D-01.
C. Construction Statement of Work
The Construction SOW document is a critical procurement document that defines the work scope,
processes and requirements of the subcontractor so completed construction work achieves TOC
expectations.
TFC-PRJ-CM-C-18 defines the process for developing a SOW and the contents necessary for
inclusion in the SOW.
Action by Action
Project Manager/BTR
1. Provide the definition of the work to be performed by a
subcontractor to the CM.
CM 2. With concurrence of the Project Manager, determine who is
best suited to be assigned the responsibility of the SOW
Coordinator.
SOW Coordinator
3. Develop the SOW and related appendices in accordance with
TFC-PRJ-CM-C-18.
D. Request for Proposal Issuance and Subcontract Award
The process for procurement of a subcontractor, from SOW entry into Asset Suite, approval
process, issuing an RFP, through subcontract award is addressed in TFC-BSM-CP_CPR-C-05.
The Team will assist procurement during this process by reviewing technical requirements and
providing answers to subcontractor questions during the proposal phase. The Team will also
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
4 of 25
DRAFT January 31, 2017
provide support for the procurement Construction Pre-Proposal Conference as delineated in
TFC-PRJ-CM-C-05.
Action by Action
Procurement Specialist/
BTR/CMT
1. Schedule and conduct Construction Pre-Proposal Conference in
accordance with TFC-PRJ-CM-C-05.
Procurement Specialist 2. Receive proposal(s) and distribute.
Procurement Specialist/
BTR/SEB
3. Review and approve the subcontractor technical proposal in
accordance with TFC-BSM-CP_CPR-C-05.
4. Ensure appropriate Team members review the subcontractor
proposal(s).
BTR 5. Fill out and submit the applicable Technical Evaluation form to
the Procurement Specialist.
Procurement Specialist 6. Process the subcontract release and notify the subcontractor.
7. Perform distribution of the notice of award.
E. Pre-Construction/Mobilization
Documentation for various construction documents shall be in accordance with
TFC-BSM-IRM_DC-C-07 and TFC-PRJ-CM-D-02.
Action by Action
BTR 1. Inform the Procurement Specialist of readiness to proceed.
Procurement Specialist 2. Prepare, issue and distribute Notice to Proceed.
CM/BTR 3. Prepare a letter to the subcontractor for Pre-Construction
(Kick-Off) Meeting with agenda found in TFC-PRJ-CM-C-
05.
4. Submit the Pre-Construction (Kick-Off) Meeting letter to C&C
Document Control.
C&C Document Control
5. Perform distribution of the Pre-Construction (Kick-Off)
Meeting letter.
CM/BTR 6. Conduct a Pre-Construction (Kick-Off) Meeting outlining
subcontractor requirements for performing work using the
“Pre-Construction (Kick-Off) Meeting Minutes,” Form (A-
6006-174) to record minutes of meeting in accordance with
TFC-PRJ-CM-C-05.
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
5 of 25
DRAFT January 31, 2017
Action by Action
Procurement Specialist/BTR 7. Obtain necessary clearances and keys for the subcontractor so
mobilization can proceed (the subcontractor obtains any
badges, clearances, dosimeters, etc.).
F. Contract Execution
Figure 2 illustrates the process flow related to construction execution.
G. Construction Execution
Documentation for various construction documents shall be in accordance with TFC-BSM-
IRM_DC-C-07. All construction communication documents will be submitted to ^LAWPS
VENDOR at [email protected].
H. Execution of the SOW
Action by Action
Project Manager 1. Review subcontractor planned work and ensure necessary field
support through the CM.
CM and BTR 2. Ensure that all subcontract submittals required prior to start of
construction work and baseline construction schedule have been
received.
3. Ensure that the Design Document List (DDL) is complete and
the Work Breakdown Structure (WBS) authorizations and
assignments have been made.
4. The team will have oversight and monitoring responsibility for
safety, quality, progress, cost, change control, and compliance
with EPC guides.
CM or Designee 5. Assist the subcontractor performing the work in all matters
pertaining to the work and ensure the work performed follows
the SOW while being in compliance with applicable TOC and
EPC procedures.
6. Ensure subcontractor understands what work, if any, will be
performed under the work package planning guide TFC-EPC-
CM-C-03.
7. Assist the Procurement Specialist, BTR and/or Project Engineer
in performance of the following:
• Track submittals.
• Initiate, track, and status subcontractor back-charges per
TFC-PRJ-CM-C-12.
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
6 of 25
DRAFT January 31, 2017
Action by Action
• Manage subcontractor initiated “Request for Information”
(RFI) as per guide TFC-EPC-CM-C-09.
• Conduct subcontractor progress meetings using the “Project
Status Meeting Minutes” Form (A-6004-778) in accordance
with TFC-PRJ-CM-C-05.
• Review of Daily Activity and Manpower Report (DAMR)
• Assist in preparation of work control documents in
accordance with TFC-OPS-MAINT-C-01.
• Responding to subcontractor correspondence.
I. Subcontractor Submittals
Action by Action
C&C Document Control
1. Ensure documentation, including logs, for submittals are
handled in accordance with TFC-BSM-IRM_DC-C-07.
2. Distribute submittals to appropriate reviewers for review
and comment.
Reviewers
3. Review submittals for subcontract compliance and comment
as necessary. Return the completed submittal to C&C
Document Control.
4. Consolidate submittal comments, generate a master
document set, and review disposition with the Project
Manager, CM, or Procurement Specialist per TFC-BSM-
IRM_DC-C-07.
5. Transmit dispositioned submittals to the subcontractor.
J. Subcontractor Request for Information
Subcontractor is required to submit a Request for Information (RFI) using “Request for
Information” as per guide TFC-EPC-CM-D-09.
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
7 of 25
DRAFT January 31, 2017
K. Subcontractor Payments
Action by Action
BTR/CMT
1. Receive and process subcontractor payment invoice.
2. Review the subcontractor schedule status information,
including the pay item schedule, and concur with estimates,
quantities, and percentage complete of subcontractor
invoice.
BTR/Procurement Specialist 3. Approve and process subcontractor payment request per
TFC-BSM-CP_CPR-C-05.
L. Revising Contract/Amending the Statement of Work
A Contract Action Log (CAL) is established to assure reconciliation of funds and definitions for
any type of action required to support added/changed contract scope. See Figure 3 for
construction action log process.
Any questions concerning if the work can be covered by the CAL process will be reviewed and
approved by the Project Manager and Manager of Construction.
Any new scope not associated with the original scope of work will be addressed in accordance
with the requirements of TFC-EPC-CM-D-12.
The construction manager, in concert with other project personnel, will review the
subcontractor’s estimate. Once approved, the Construction Manager/BTR will be responsible to
increase the base contract in accordance with the direction in the Terms and Conditions of the
Contract. When the Project Team directs the subcontractor to perform work for the identified
CAL, the Subcontractor will be authorized to invoice all work associated with the issuance of the
CAL.
Action by Action
Construction Manager/BTR
1. Enter the description of work assigned in the CAL and notify
the following:
• Project Manager
• Cost Accounts Manager (CAM)
• Budget Analyst (BA).
2. Request an estimate from the subcontractor.
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
8 of 25
DRAFT January 31, 2017
M. Construction Acceptance Testing and Turnover
Construction Acceptance Test(s) CAT(s) if required by the Company shall be specified in the
subcontractor’s SOW.
Action by Action
Commissioning Manager 1. Ensure CAT(s) are developed in accordance with TFC-EPC-CM-
D-17.
CM 2. Ensure CAT(s) are performed in accordance with
TFC-EPC-CM-D-17.
3. After notification from the subcontractor that the work is
mechanically complete, notify the following;
• Project Manager
• Commissioning Manager
• Testing Lead
• Work Area Construction Manager
• BTR
• Other entities as deemed appropriate.
N. Construction Completion and Turnover
Action by Action
CM 1. Ensure completion and transfer is performed in accordance with
TFC-EPC-CM-D-11, and TFC-PRJ-CM-C-08.
O. Subcontract Closeout
Action by Action
CM 1. Ensure subcontractor closeout is performed in accordance with
TFC-PRJ-CM-C-15 and ensure the “Construction Subcontract
Closeout Checklist” (CSCC) Form (A-6003-226) is complete.
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
9 of 25
DRAFT January 31, 2017
P. Construction & Commissioning Document Control
Action by Action
C&C Document Control 1. When identified as records custodian, maintain project field
files using the “Project Records Index” Form (A-6002-510)
as a guide.
NOTE: Certain construction documents will require a
document number for tracking purposes. Those requiring a
document number will be specified in various Construction
procedures and shall be numbered in accordance with TFC-
BSM-IRM_DC-C-07.
2. Control construction documents in accordance with TFC-
BSM-IRM_DC-C-07.
3. Perform record management in accordance with TFC-BSM-
IRM_DC-C-02.
4. The records custodian identified in the Company Level
Records Inventory and Disposition Schedule (RIDS) is
responsible for record retention in accordance with TFC-
BSM-IRM_DC-C-02.
5. After the system is commissioned convert drawings from
Design Agency title block to Hanford (DOE) title block and
transfer drawings to Hanford Engineering and Operations.
4.3 Process Work Flow – WRPS as PM/CMT
The following instructions relate to the process work flow defined in Section 4.1.
A. Acquisition Planning
CMT Action by Action
Approve Process Task Project
Manager
1. Involve the TCM or designee in the Acquisition
Planning Process.
2. Authorize pre-construction and subcontract
execution activities.
Construction
Manager
3. Initiate pre-construction activities.
Oversight Task Project
Manager
4. Conduct a meeting with appropriate Team
members and Procurement personnel to identify
how the work will be subcontracted.
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
10 of 25
DRAFT January 31, 2017
B. Constructability
CMT Action by Action
Review TCM 1. Ensure Construction participates and performs
constructability reviews on projects and the design
documents per TFC-EPC-CM-D-01.
C. Construction Statement of Work
CMT Action by Action
Review Task Project Manager
1. Provide the definition of the work to be performed
by a subcontractor to the TCM.
TCM
2. With concurrence of the Task Project Manager
and/or the Work Area Project Manager and/or
Manager of Construction, determine who is best
suited to be assigned the responsibility of the SOW
Coordinator.
Review/Approve SOW Coordinator
3. Develop the SOW and related appendices in
accordance with TFC-PRJ-CM-C-18.
D. Request for Proposal Issuance and Subcontract Award
CMT Action by Action
Oversight Procurement
Specialist
1. Schedule and conduct Construction Pre-Proposal
Conference in accordance with TFC-PRJ-CM-C-
05.
2. Receive proposal(s) and distribute.
3. Review and approve the subcontractor technical
proposal in accordance with TFC-BSM-CP_CPR-
C-05.
4. Ensure appropriate Team members review the
subcontractor proposal(s).
Review Project Manager 5. Fill out and submit the applicable Technical
Evaluation form to the Procurement Specialist.
Procurement
Specialist
6. Process the subcontract release and notify the
subcontractor.
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
11 of 25
DRAFT January 31, 2017
CMT Action by Action
7. Perform distribution of the notice of award.
E. Pre-Construction/Mobilization
CMT Action by Action
Project Manager 1. Inform the Procurement Specialist of readiness to
proceed.
Procurement
Specialist
2. Prepare, issue and distribute Notice to Proceed.
CM 3. Prepare a letter to the subcontractor for Pre-
Construction (Kick-Off) Meeting with agenda found
in TFC-PRJ-CM-C-05.
4. Submit the Pre-Construction (Kick-Off) Meeting
letter to C&C Document Control.
C&C Document
Control
5. Perform distribution of the Pre-Construction (Kick-
Off) Meeting letter.
Oversight Project Manager 6. Conduct a Pre-Construction (Kick-Off) Meeting
outlining subcontractor requirements for performing
work using the “Pre-Construction (Kick-Off)
Meeting Minutes,” Form (A-6006-174) to record
minutes of meeting in accordance with TFC-PRJ-
CM-C-05.
Assist Procurement
Specialist
7. Obtain necessary clearances and keys for the
subcontractor so mobilization can proceed (the
subcontractor obtains any badges, clearances,
dosimeters, etc.).
F. Execution of the SOW
CMT Action by Action
Review Project Manager
1. Review subcontractor planned work and ensure
necessary field support through the TCM.
CM 2. Ensure that all subcontract submittals required
prior to start of construction work and baseline
construction schedule have been received.
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
12 of 25
DRAFT January 31, 2017
CMT Action by Action
Review/Approve 3. Ensure that the Design Document List (DDL) is
complete and the Work Breakdown Structure
(WBS) authorizations and assignments have been
made.
4. The team will have oversight and monitoring
responsibility for safety, quality, progress, cost,
change control, and compliance with EPC
procedures.
Oversight CM or Designee 5. Assist the subcontractor performing the work in
all matters pertaining to the work and ensure the
work performed follows the SOW while being in
compliance with EPC procedures.
6. Ensure subcontractor understands that all work is
performed under the EPC work control process.
7. Assist the Procurement Specialist, BTR and/or
Project Engineer in performance of the following:
• Track submittals
• Initiate, track, and status subcontractor back-
charges per TFC-PRJ-CM-C-12.
• Manage subcontractor initiated “Request for
Information” (RFI)
• Conduct subcontractor progress meetings using
the “Project Status Meeting Minutes” Form (A-
6004-778) in accordance with TFC-PRJ-CM-C-
05.
• Review of Daily Activity and Manpower Report
(DAMR)
• Assist in preparation of work control documents
in accordance with TFC-OPS-MAINT-C-01.
• Responding to subcontractor correspondence.
G. Subcontractor Submittals
CMT Action by Action
Oversight C&C Document
Control
1. Ensure documentation, including logs, for
submittals are handled in accordance with TFC-
BSM-IRM_DC-C-07.
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
13 of 25
DRAFT January 31, 2017
CMT Action by Action
2. Distribute submittals to appropriate reviewers for
review and comment.
Review Reviewers 3. Review submittals for subcontract compliance
and comment as necessary. Return the completed
submittal to C&C Document Control.
Review C&C Document
Control
4. Consolidate submittal comments, generate a
master document set, and review disposition with
the Task Project Manager, TCM, or Procurement
Specialist per TFC-BSM-IRM_DC-C-07.
5. Transmit dispositioned submittals to the
subcontractor.
H. Subcontractor Payments
I. Required CAL information
CMT Action by Action
Construction
Manager
1. Enter the description of work assigned in the
CAL and notify the following:
• Task Project Manager
• Cost Accounts Manager (CAM)
• Budget Analyst (BA).
Review 2. Request an estimate from the subcontractor.
CMT Action by Action
Project Controls 1. Receive and process subcontractor payment
invoice.
2. Review the subcontractor schedule status
information, including the pay item schedule, and
concur with estimates, quantities, and percentage
complete of subcontractor invoice.
Approve BTR/ Procurement
Specialist
3. Approve and process subcontractor payment
request per TFC-BSM-CP_CPR-C-05.
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
14 of 25
DRAFT January 31, 2017
J. Construction Acceptance Testing and Turnover
CMT Action by Action
Approve Commissioning
Manager
1. Ensure CAT(s) are developed in accordance with
TFC-EPC-CM-C-17.
Oversight CM 2. Ensure CAT(s) are performed in accordance with
TFC-EPC-CM-C-17.
3. After notification from the subcontractor that the
work is substantially complete, notify the
following;
• Task Project Manager
• Manager of Construction
• Commissioning Manager
• Testing Lead
• Work Area Construction Manager
• BTR
• Other entities as deemed appropriate.
K. Construction Completion and Turnover
CMT Action by Action
Oversight/Approve CM 1. Ensure completion and transfer is performed in
accordance with TFC-EPC-CM-D-11, and TFC-
PRJ-CM-C-08.
L. Subcontract Closeout
CMT Action by Action
Approve CM 1. Ensure subcontractor closeout is performed in
accordance with TFC-PRJ-CM-C-15 and ensure
the “Construction Subcontract Closeout
Checklist” (CSCC) Form (A-6003-226) is
complete.
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
15 of 25
DRAFT January 31, 2017
M. Construction & Commissioning Document Control
CMT Action by Action
C&C Document
Control
1. When identified as records custodian, maintain
project field files using the “Project Records
Index” Form (A-6002-510) as a guide.
NOTE: Certain construction documents will
require a document number for tracking purposes.
Those requiring a document number will be
specified in various Construction procedures and
shall be numbered in accordance with TFC-BSM-
IRM_DC-C-07.
2. Control construction documents in accordance
with TFC-BSM-IRM_DC-C-07.
Oversight 3. Perform record management in accordance with
TFC-BSM-IRM_DC-C-02.
4. The records custodian identified in the Company
Level Records Inventory and Disposition
Schedule (RIDS) is responsible for record
retention in accordance with TFC-BSM-
IRM_DC-C-02.
5.0 DEFINITIONS
5.1 Administrative change
A change to the contract that may involve schedule or cost, but does not involve scope.
• An example of a schedule change would be a schedule extension due to weather delays.
• An example of a cost change would be overtime to perform previously authorized
activities.
5.2 Construction Representative
A Construction Representative can be the Work Area Construction Manager, Task Construction
Manager, Construction Field Lead or Field Work Supervisor.
5.3 Non-administrative change.
A change to the contract that adds or removes fabrications, scope, or evolutions of existing scope.
• An example of a fabrication addition would be to build three top hats instead of two top
hats.
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
16 of 25
DRAFT January 31, 2017
• An example of a scope addition would be to install perimeter lighting not included in the
original contract.
• An example of an addition to evolutions of existing scope would be to install additional
square footage of a parking lot.
5.4 Issue Authorization and Maintenance for Use
The EPC Execution Construction Manager is responsible for the maintenance of this procedure
and will review the procedure annually to determine any necessary updates. Should an individual
employee have a suggestion for improvement or modification to this procedure, he or she may
mark-up a copy of the procedure and send it to the EPC Execution Construction Manager for
review. The EPC Execution Construction Manager will review the recommended changes and
respond back to the employee on plans to address the suggestions. Changes to the procedure will
be distributed to other WRPS Functional Leads and other affected EPC Managers for their
concurrence. When the reviews are complete, the EPC Execution Construction Manager will
consolidate and recommend changes to this procedure to the EPC Project Execution Manager
who has the authority to issue revisions to this procedure.
5.5 Project Management/Constructor Team (PM/Constructor)
The Owner (WRPS) Project Management Team in place during the Project Execution –
Procurement, Construction and Cold Commissioning Phase – (CD-4) that Constructs, provides
verification the work effort meets project requirements, and ensures the Client is receiving value
for money from both cost and schedule perspectives.
5.6 Project Management & Construction Management Team (PM/CMT)
The Owner (WRPS) Project Management team in place during the Project Execution –
Procurement, Construction and Cold Commissioning Phase – (CD-4) that provides construction
management oversight services for the EPC Project construction works when the Constructor is
not WRPS. The PM/CMT provides oversight of the Constructor’s work effort, verification the
work effort meets project requirements, and ensures the Client is receiving value for money from
both cost and schedule perspectives. Where CMT is referred to in this procedure, it refers to the
full Project Management/Construction Management Team (PM/CMT).
6.0 RECORDS
The following records may be generated during the performance of this procedure:
• Daily Activity and Manpower Report Form (A-6003-220)
• Lost Time/Work Delay Form (A-6003-675)
• Pre-Construction (Kick-Off) Meeting Minutes Form (A-6006-174)
• Request for Information Form (A-6003-417)
• Project Status Meeting Minutes Form (A-6006-173)
• Construction Completion Document Form (A-6003-182)
• Exception List Form (A-6003-586)
• Construction Subcontract Closeout Checklist Form (A-6003-226)
• Project correspondence
• Project Records Index Form (A-6002-510).
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
17 of 25
DRAFT January 31, 2017
The records custodian identified in the Company Level Records Inventory and Disposition
Schedule (RIDS) is responsible for record retention in accordance with TFC-BSM-IRM_DC-C-
02.
7.0 SOURCES
7.1 Requirements
1. Tank Operations Contract, Contract Number DE-AC27-08RV14800
2. TFC-EPC-PLN-01, Complex Engineering, Procurement and Construction Project
Execution
3. RPP-MP-003, “Integrated Environment, Safety, and Health Management System
Description for the Tank Operations Contractor.”
4. TFC-PLN-02, “Quality Assurance Program Description.”
5. TFC-PLN-84, “Tank Operations Contractor Project Execution Plan.”
6. TFC-PLN-113, “Construction Management.”
7. TFC-PRJ-PM-C-02, “Project Management.”
8. TFC-EPC-PLN-03 “EPC Construction Management Plan”
7.2 References
1. TFC-BSM-CP_CPR-C-05, “Procurement of Services.”
2. TFC-BSM-IRM_DC-C-02, “Records Management.”
3. TFC-BSM-IRM_DC-C-07, “Vendor Processes.”
4. TFC-PRJ-CM-C-03, “Construction Daily Activity & Manpower Reports.”
5. TFC-PRJ-CM-C-05, “Construction Meetings.”
6. TFC-PRJ-CM-C-08, “Construction Completion and Turnover.”
7. TFC-PRJ-CM-C-12, “Construction Supplier Backcharges.”
8. TFC-PRJ-CM-C-15, “Construction Subcontract Closeout.”
9. TFC-PRJ-CM-C-16, “Construction Acceptance Testing.”
10. TFC-PRJ-CM-C-17, “Constructability Review Process.”
11. TFC-PRJ-CM-C-18, “Development of Technical Requirements for Construction
Statements of Work.”
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-D-13, REV A
18 of 25
DRAFT January 31, 2017
12. TFC-PRJ-CM-D-02, “Construction & Commissioning Document Control Processes.”
13. TFC-EPC-CM-D-01, “EPC Constructability Guide”
14. TFC-EPC-CM-D-11, “EPC Mechanical Completion and Transfer to Operations Guide”
15. TFC-EPC-CM-D-12, “EPC Field Change Request Guide”
16. TFC-EPC-CM-D-17, “EPC Construction Acceptance Testing Guide”
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-C-13, REV A
19 of 25
DRAFT 6/09/2015
Figure 1. Process Work Flow Chart.
TPM involves the TCM or designee in the Acquisition Planning Process.
TPM provides the definition of the work to be performed by a subcontractor to the TCM.
TCM with concurrence of the TPM and/or the Work Area Project Manager and/or Manager of Construction, determine who is best suited to be assigned
the responsibility of the SOW Coordinator.
CM initiates pre-construction activities.
TPM authorizes pre-construction and subcontract execution activities.
TCM ensures Construction participates and performs constructability reviews on project and design documents per TFC-EPC-CM-C-01.
PM/CMT will provide
oversight and/or review
activities throughout
process
TPM will conduct a meeting with appropriate team members and Procurement personnel to identify how the work will be subcontracted.
SOW Coordinator will develop the SOW and related appendices in accordance with TFC-PRJ-CM-C-18.
PS will schedule and conduct Construction Pre-Proposal Conference in accordance with TFC-PRJ-CM-C-05.
A. Acquisition Planning
B. Constructability
C. Construction Statement of Work
D. Request For Proposal Issuance and Subcontract Award
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-C-13, REV A
20 of 25
DRAFT 6/09/2015
PS will receive proposal(s) and distribute.
PS will review and approve the subcontractor technical proposal in accordance with TFC-BSM-CP_CPR-C-05.
Ensure appropriate team members review the subcontractor proposal(s).
PM will fill out and submit the applicable Technical Evaluation form to the PS.
PS will process the subcontract release and notify the subcontractor.
Perform distribution of the notice of award.
PM will inform the PS of readiness to proceed.
PS will prepare, issue, and distribute Notice to Proceed.
TCM will prepare a letter to the subcontractor for Pre-Construction (Kick-Off) Meeting with agenda found in TFC-PRJ-CM-C-05.
Submit the Pre-Construction (Kick-Off) Meeting letter to C&C Document Control.
C&C Document Control distributes Pre-Construction (Kick-Off) Meeting letter.
E. Pre-Construction/Mobilization
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-C-13, REV A
21 of 25
DRAFT 6/09/2015
Ensure documentation, including logs, for submittals are handled in accordance with TFC-BSM-IRM_DC-C-07.
Distribute submittals to appropriate reviewers for review and comment.
Reviewers will review submittals for subcontract compliance and comment as necessary. Return the completed submittal to C&C Document Control.
C&C Document Control will consolidate submittal comments, generate a master document set, and review disposition with the TPM, TCM, or PS per TFC-BSM-IRM_DC-C-07.
Transmit dispositioned submittals to the subcontractor.
Project Controls will receive and process subcontractor payment invoice.
Review the subcontractor schedule status information, including the pay item schedule, and concur with estimates, quantities, and percentage
complete of subcontractor invoice.
Accounts payable will approve and process subcontractor payment request per TFC-BSM-CP_CPR-C-05.
Task CM will enter the description of work assigned in the CAL and notify the following:
• Task Project Manager
• Cost Accounts Manager (CAM)
• Budget Analyst (BA)
TCM requests an estimate from the subcontractor.
G. Subcontractor Submittals
H. Subcontractor Payments
I. Required CAL Information
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-C-13, REV A
22 of 25
DRAFT 6/09/2015
Commissioning Manager ensures CAT(s) are developed in accordance with TFC-EPC-CM-C-17.
TCM ensures CAT(s) are performed in accordance with TFC-EPC-CM-C-17.
After notification from the subcontractor that the work is substantially complete, the TCM will notify the following:
• Task Project Manager
• Manager of Construction
• Commissioning Manager
• Testing Lead
• Work Area Construction Manager
• Other entities as deemed appropriate.
TCM ensures completion and turnover is performed in accordance with TFC-EPC-CM-C-11.
TCM ensures subcontractor closeout is performed in accordance with TFC-PRJ-CM-C-15 and ensures the “Construction Subcontract Closeout Checklist” (CSCC)
Form (A-6003-226) is complete.
C&C Document Control when identified as records custodian, maintain project field files using the “Project Records Index” Form (A-6002-510) as a guide.
Control construction documents in accordance with TFC-BSM-IRM_DC-C-07.
Perform record management in accordance with TFC-BSM-IRM_DC-C-02.
The records custodian identified in the Company Level Records Inventory and Disposition Schedule (RIDS) is responsible for record retention in
accordance with TFC-BSM-IRM_DC-C-02.
J. Construction Acceptance Testing and Turnover
K. Construction Completion and Turnover
L. Subcontract Closeout
M. Construction & Commissioning Document Control
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-C-13, REV A
23 of 25
DRAFT 6/09/2015
WRPS SELF PERFORMING WORK: PM/CONSTRUCTOR
-WRPS CONSTRUCTOR TEAM
ACTIVITIES
-NOT APPLICABLE
LEGENDS:
WRPS CMT OVERSEEING EPC CONSTRUCTOR: PM/CMT
-EPC CONSTRUCTOR ACTIVITIES
-WRPS PM/CMT ENGAGEMENT
WITH EPC CONSTRUCTOR
NOTE: All deliverables are
considered to be a record
and are processed in
accordance with
TFC-BSM-IRM_DC-C-01,
Document Control,
TFC-BSM-IRM_DC-C-02,
Records Management,
and TFC-ENG-DESIGN-C-25,
Technical Document Control.
DA- Design Authority
PS-Procurement Specialist
TPM-Task Project Manager
TCM-Task Construction Manager
CAT-Construction Acceptance Testing
C&C-Construction and Commissioning
CM-Construction Manager
SOW-Statement of Work
PM-Project Manager
WBS-Work Breakdown Structure
DDL-Design Document List
ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT
Manual
Document
Page
Issue Date
EPC
TFC-EPC-CM-C-13, REV A
24 of 25
DRAFT 6/09/2015
Figure 2. Construction Execution Process Work Flow Chart.
WRPS
Construction
Setup
Execute Work
Construction
Walk Down
& Punch List
Construction
Completion
Document
Construction
Performance
Review
Master Submittal Lists
Establish Final Construction Schedule
Project Document Control Stations
Control Design Document List
Control WBS Staff Authorization /
Assignments
Pre-Construction (Kick-Off) Meeting
Mobilization
Facility & Material Turnover
Submittal Tracking / Reporting
Notice to Proceed
Oversee/Manage Subcontractor
Fabrication Oversight / Coordination
Status/Progress Reporting
Safety Assurance
Manage WRPS Support Interface
Manage Third Party Interface
Quality Control Coordination / Oversight
Work Package Prep & Execution
Manage RFI
Construction Design Configuration
Control
Contract Change Control
Maintain Construction Document Control
Manage & Support Accruals, ETC &
EAC
Manage & Support Construction Baseline
Change Request, as needed
Construction Completion Documentation
Construction Subcontract Closeout
Checklist
Construction Performance Review
Operation
Testing (If
Required)
Closeout &
Final
Payment
Construction
Completion
Document