130
The Islamic University Gaza Research and Postgraduate Affairs Faculty of Engineering Construction Management تيس انجبيؼت ا- غشةب وانذراسبث انؼه انبحث انؼه شئىذستت انه كهتذسشزوػبث انه ادارة انThe Applicability of Increasing Transparency Principle within Lean Construction in Gaza Strip زشبء ان ات ضبفبدة انشفك يبذأ س تطبتبهذي لب دراست ي لطبع غشة فAnas M. Abu Daqqa Supervised by: Dr. Khaled Al-Hallaq Assistant Professor in Construction Management A thesis is submitted in partial fulfillment of requirement for Degree of Master of Science in Civil Engineering - Construction Management November /2017

The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

The Islamic University – Gaza

Research and Postgraduate

Affairs Faculty of Engineering

Construction Management

غشة- انجبيؼت االساليت

شئى انبحث انؼه وانذراسبث انؼهب

كهت انهذست

ادارة انشزوػبث انهذست

The Applicability of Increasing Transparency

Principle within Lean Construction in Gaza Strip

دراست يذي لببهت تطبك يبذأ سبدة انشفبفت ض االشبء انز

ف لطبع غشة

Anas M. Abu Daqqa

Supervised by:

Dr. Khaled Al-Hallaq

Assistant Professor in Construction Management

A thesis is submitted in partial fulfillment of requirement for

Degree of Master of Science in Civil Engineering - Construction Management

November /2017

Page 2: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

إقــــــــــــــرار

أنا الموقع أدناه مقدم الرسالة التي تحمل العنوان:

دراسة مدى قابلية تطبيق مبدأ زيادة الشفافية ضمن االنشاء المرن في قطاع غزة

The Applicability of Increasing Transparency Principle within Lean Construction in Gaza Strip

أقر بأن ما اشتممت عميو ىذه الرسالة إنما ىو نتاج جيدي الخاص، باستثناء ما تمت اإلشارة إليو منيا لم يقدم من قبل اآلخرين لنيل درجة أو لقب حيثما ورد، وأن ىذه الرسالة ككل أو أي جزء

عممي أو بحثي لدى أي مؤسسة تعميمية أو بحثية أخرى. وأن حقوق النشر محفوظة لمجامعة غزة. –اإلسالمية

Declaration

I hereby certify that this submission is the result of my own work, except

where otherwise acknowledged, and that this thesis (or any part of it) has

not been submitted for a higher degree or quantification to any other

university or institution. All copyrights are reserves to IUG.

:Anas M. Abu Daqqa Student's name اسم الطالب:

:Signature التوقيع:

:Date 2017 / 11 / 02 التاريخ:

Page 3: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste
Page 4: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

I

Abstract

Wastes have been recognized as a major problem in construction industry in Gaza

Strip, and the level of material waste is higher than the nominal figures due to

managerial problems (Al-Maghony, 2006). Despite that, Lean Construction is still

not applied in construction projects and limited researches have studied this crucial

management approach in Gaza Strip (GS). Therefore, the basic research aim was to

enhance transparency of construction projects throughout lean construction approach,

which has been achieved through evaluating the current status of transparency

practices, identifying benefits, challenges and success factors of transparency

principle, and investigating the proper Lean tools those enhance transparency in GS.

Intensive literature review was done and a questionnaire was designed and then

(SPSS) was used to analyze results obtained from 130 received questionnaires out of

170 distributed copies to the target group, professional engineer work in contracting

companies in GS, with a response rate = 76.5%. Results of data analysis obtained

from the conducted survey showed that factors of transparency principle and LC

tools are limitedly applied in construction projects in GS and 5-S tool is the most

applied one. Further, there is a relationship between the importance and the

application of transparency factors indicating that contracting companies in GS have

a concern to apply what they believe in its importance for projects management; also

they approved the benefits of increasing transparency in construction projects and its

reciprocal relationship with lean construction. The obtained results of success factors

and challenges indicated that projects management in GS should be supported by

managers with higher knowledge and better understand of transparency principle,

techniques and importance. Consequently, it was concluded that building capacities

of project managers is a crucial issue to allow increasing transparency in construction

projects in GS. Also, it was concluded that construction projects in GS need to be

enhanced regarding the communication between different parties, and give attention

to the tidiness and orderings of work place through applying LC tools; Huddle

Meeting, 5-S, and Increased Visualization.

Page 5: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

II

يهخـص انذراست

خالي ظ االشبء اش، ف لطبع غضحاشبس٠غ االشبئ١خ رؼض٠ض اشفبف١خ ف جؾش األعبع اغشع

طجبع اؼب بسعبدرم١١ اػغ اؾب اال (1: األذاف ازب١خ رؾم١ك خاليزا اغشعلذ ر رؾم١ك

رؾذ٠ذ ( 3. رؾذ٠ذ افائذ ازؾذ٠بد ػا غبػ جذأ اشفبف١خ( 2. ف لطبع غضحاالشبءاداشفبف١خ ف لطبع

. اشفبف١خ ف لطبع غضحزؼض٠ض جذأ ابعجخ أداد االشبء اش

ألثؾبس اغبثمخ ازؼمخ ثغبي اذساعخ، ىضفخ ث١بد، دساعخ شاعؼخ ألدر ػ فك اعزجبخ رظ١ ص

ذع١ ٠ؼ ف ششوبد مبالد، ف ؽ١ اعزؼبد اعزجبخ 170 ػذد رص٠غ س . اى ام١بط ظ

ر دل١مخ؛ ل١خ زبئظ اؾظي ػ أع ، %76.5 ثغذ اعزغبثخ ثغجخ باجبؽضبئخ صالص غخخ

..اإلؽظبئ ازؾ١ ثشبظ ثبعزخذا اى ازؾ١ ثطشق اؾظخ ج١ببد ارؾ١

ف االشبء ف شبس٠غ ؾذد رطجك ثشى اشفبف١خ أداد االشبء اشأظشد زبئظ رؾ١ اج١ببرأ ػا

غ ره فا ع١غ ػا أداد اشفبف١خ ال رضاي ثؾبعخ ئ . رطج١مبا األوضش S-5، األداح لطبع غضح

ب ٠ش١شبن ػاللخ ث١ أ١خ رطج١ك ػا اشفبف١خ وب أ . ص٠بدح رؼض٠ض ف شبس٠غ اجبء ف لطبع غضح

أثذ ئداسح اشبس٠غ؛ وب ف ثأ١زرطج١ك ب ٠ؼزمذ ازب ةف لطبع غضح ذ٠ب ششوبد امبالد ئ أ

اغ١ج ػ االعزج١ب اافمخ ػ فائذ ص٠بدح اشفبف١خ ف شبس٠غ اجبء حػاللزب ازىب١خ غ ظ االشبء

.اش

أشبسد ازبئظ از ر اؾظي ػ١ب ػا اغبػ ازؾذ٠بد ئ أ ئداسح اشبس٠غ ف لطبع غضح ٠غت

ثبء ػ ره، اعززظ. ، أ١ز رطج١مبر ف أفؼ جذأ اشفبف١خ٠ دػب ثبداسح راد ؼشفخ ػب١خأ

. أ ثبء لذساد ذ٠ش اشبس٠غ غأخ ؽبعخ رغؼ ثض٠بدح اشفبف١خ ف شبس٠غ اجبء ف لطبع غضحاجبؽش

ث١ خزف ثبالرظبي ازاط ف لطبع غضح رؾزبط ئ رؼض٠ض ف١ب ٠زؼك االشبءاعززظ أ٠ؼب أ شبس٠غ

Huddle: األداد ىب اؼ خالي رطج١ك رظ١فاألؽشاف، ئ٠الء ض٠ذ االزب زشر١ت

Meeting, 5-S, and Increased Visualization.

Page 6: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

III

Dedication

This research is dedicated to all people who supported and encouraged me...

To my Father Prof. Mousa Abu daqqa for his endless support, and encouragement

To my Mother Basma Baraka for her constant inspiration and endless love

To my Wife Eng. Fidaa Fayad who makes my life special and have never left my

side.. To my Daughter Basma who brightens my life

To my brothers and sisters

Last but not least, to my friend and my Sheikh, The martyr Abdel Hamid Al

Moghrabi

To all people who inspire my life.

Eng. Anas Abu Daqqa

Page 7: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

IV

Acknowledgement

These acknowledgements presented to sincerely thank people who supported,

guided, and encouraged me along the way to complete this research. Without their

assistance, encouragement, suggestions and commitment, this dissertation would not

have been a reality.

From the depth of my heart I would like to express sincere gratitude and appreciation

to my supervisor Dr. Khaled Al-Hallaq for his continued support, generous academic

advice, discussions, suggestions, and his incredible assistance, I would like to pass

him special thanks.

Also, I would like to thank all experts especially Dr. Samir Safi and Mr. Ali Sonallah

for their contribution at statistical analysis, and valuable opinions in the

questionnaire design.

Eng. Anas Abu Daqqa

Page 8: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

V

Table of Content

Abstract ...................................................................................................................I

انذراست يهخـص ............................................................................................................ II

Dedication .............................................................................................................III

Acknowledgement ................................................................................................ IV

Table of Content .................................................................................................... V

List of Abbreviations ......................................................................................... VIII

List of Tables ........................................................................................................ IX

List of Figures ....................................................................................................... XI

Chapter 1: Introduction ......................................................................................... 1

1.1 Background .................................................................................................... 1

1.2 Problem Statement .......................................................................................... 2

1.3 Research Aim and Objectives ......................................................................... 2

1.4 Research Questions ......................................................................................... 3

1.5 Research Hypotheses ...................................................................................... 4

1.6 Research Scope ............................................................................................... 5

1.7 Research Structure .......................................................................................... 5

Chapter 2: Literature Review ................................................................................ 7

2.1 Wastes ............................................................................................................ 7

2.1.1 Wastes in Construction Industry ............................................................... 8

2.1.2 Wastes in Gaza Strip .............................................................................. 10

2.2 Lean Philosophy ........................................................................................... 11

2.2.1 Evolution of Lean Concept ..................................................................... 11

2.2.2 Lean Definition ...................................................................................... 12

2.2.3 Lean Principles ...................................................................................... 13

2.2.4 Controversy on Lean Approaches........................................................... 14

Page 9: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

VI

2.2.5 Implementation of Lean Concept ........................................................... 15

2.3 Lean Construction......................................................................................... 18

2.3.1 Adopt Lean to Construction Industry...................................................... 18

2.3.2 Lean Construction Definition ................................................................. 19

2.3.3 Lean Construction Principles ................................................................. 20

2.3.4 Implementation of Lean Construction .................................................... 21

2.3.5 Lean Construction Techniques ............................................................... 22

2.4 The principle of Transparency ...................................................................... 24

2.4.1 Definition of Transparency .................................................................... 24

2.4.2 Transparency within Lean Construction ................................................. 26

2.4.3 Visual Management Approach ............................................................... 27

2.4.4 Benefits of Increasing Process Transparency .......................................... 32

2.4.5 Challenges of Increasing Process Transparency...................................... 34

2.4.6 Success Factors to Increase Process Transparency .................................. 34

Summary ........................................................................................................ 36

Chapter 3: Methodology ...................................................................................... 37

3.1 Research Design ........................................................................................... 37

3.2 Research Period ............................................................................................ 39

3.3 Research Location ........................................................................................ 39

3.4 Research Population ..................................................................................... 39

3.4.1 Sample Elements.................................................................................... 40

3.4.2 Sample Size ........................................................................................... 40

3.4.3 Sampling Procedure ............................................................................... 40

3.5 Questionnaire Design .................................................................................... 41

3.6 Questionnaire References ............................................................................. 43

3.7 Questionnaire Content Validity ..................................................................... 46

3.8 Pilot Study .................................................................................................... 47

3.8.1 Questionnaire Validity ........................................................................... 48

Page 10: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

VII

3.8.2 Questionnaire Reliability ........................................................................ 54

3.8.3 Questionnaire Normality ........................................................................ 55

3.9 Statistical Analysis Tools .............................................................................. 56

Summary ............................................................................................................ 56

Chapter 4: Data Analysis and Results ................................................................. 58

4.1 Data Analysis of Questionnaire Sections ....................................................... 58

4.1.1 Organizational Background of Respondent ............................................ 58

4.1.2 Transparency Factors ............................................................................. 60

4.1.3 Lean Construction Tools ........................................................................ 63

4.1.4 Transparency Effect on LC Principles .................................................... 70

4.1.5 Benefits of Transparency ....................................................................... 71

4.1.6 Success Factors of Transparency ............................................................ 72

4.1.7 Challenges of Transparency ................................................................... 73

4.2 Test of Research Hypothesis..................................................................... 75

Summary ............................................................................................................ 86

Chapter 5: Conclusion.......................................................................................... 87

5.1 Outcomes Related to Objective One.............................................................. 87

5.2 Outcomes Related to Objective Two ............................................................. 88

5.3 Outcomes Related to Objective Three ........................................................... 90

5.3 Research contribution to previous studies ..................................................... 90

5.4 Research value .............................................................................................. 91

References ............................................................................................................. 93

Appendix ............................................................................................................... 99

Page 11: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

VIII

List of Abbreviations

Abbreviation The Interpretation Of Abbreviation

GS Gaza Strip

LC Lean Construction

VM Visual Management

TPS Toyota Production System

JIT Just In Time

TQC Total Quality Control

Five S's 5S

CPM Critical Path Models

IGLC International Group for Lean Construction

LCI Lean Construction Institute

Page 12: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

IX

List of Tables

Table (2.1): T.F.V theory of production…………………………………………….21

Table (2.2): Tools of Lean Construction…………………………………………….24

Table (2.3): Functions of Visual Management……………………………………...29

Table (3.1): Rating Scale for data measurement…………………………………….56

Table (3.2): References of LC tools in the questionnaire…………………………...43

Table (3.3): References of Benefits in the questionnaire……………………………45

Table (3.4): References of Success Factors in the questionnaire……………………45

Table (3.5): References of Challenges in the questionnaire…………...……………46

Table (3.6): Notes gathered from the consultants………………………………...…47

Table (3.7): Correlation coefficient of each item of "Transparency Factors" and the

total of this section…………………………………………………………………..48

Table (3.8): Correlation coefficient of "Lean Construction Tools" and total……….49

Table (3.9): Correlation coefficient of "LC Principles" and total…………..……….51

Table (3.10): Correlation coefficient of each item of The Benefits…………….…...51

Table (3.11): Correlation coefficient of each item of Success Factors..….…..….….52

Table (3.12): Correlation coefficient of each item of The Challenges…………..….53

Table (3.13): Correlation coefficient of each field and the whole questionnaire…...54

Table (3.14): Cronbach's Alpha for each field of the questionnaire………………...55

Table (3.15): Kolmogorov-Smirnov test………………………………………….…56

Table (4.1): Classification of Contracting Company………………………………..58

Table (4.2): Organizational background of respondents…………………….............59

Table (4.3): Means and Test values for “Transparency Factors- Degree of

application”………………………………………………………………………….61

Table (4.4): Means and Test values for “Transparency Factors - Degree of

importance”………………………………………………………………………….62

Table (4.5): Means and Test values for “Lean Construction Tools- Degree of

application”………………………………………………………………………….64

Page 13: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

X

Table (4.6): Means and Test values for “Lean Construction Tools - Degree of

Importance”………………………………………………………………………….68

Table (4.7): Means and Test values “Effect of Transparency on LC Principles”…...71

Table (4.8): Means and Test values for “Benefits of Transparency”……………….72

Table (4.9): Means and Test values for “Success Factors of Transparency”……….73

Table (4.10): Means and Test values for “Challenges of Transparency”…………...74

Table (4.11): ANOVA test of fields and their p-values for "Job title"…..………….76

Table (4.12): ANOVA test of fields and their p-values for years of experience……77

Table (4.13): ANOVA test of fields and their p-values for place of company…..….78

Table (4.14): ANOVA test of fields and p-values years of company experience…..79

Table (4.15): ANOVA test of fields and p-values for number of permanent

employees………………………………………………………………..………….80

Table (4.16): ANOVA test of the fields and their p-values for number of projects

implemented in the last 5 years…………………………………………..………….81

Table (4.17): ANOVA test of the fields and their p-values for annual average value

of projects in the last 5 years………………………………………..……………….83

Page 14: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

XI

List of Figures

Figure (1.1): Hypothesis Model………………………………………………..……..5

Figure (2.1): Waste percentages of time in construction………………………...…...8

Figure (2.2): „„4P‟‟ of the lean way…………………………………………………16

Figure (2.3): The model of visual work place………………………………..……...31

Figure (3.1): Flowchart of research methodology……………………………..……39

Figure (4.1): Familiarity of respondents to LC approach…………………………...60

Figure (4.2): Degrees of importance and application of transparency factors………63

Figure (4.3): Degrees of importance and application of "5S tool" factors……….....64

Figure (4.4): Degrees of importance and application of Huddle Meetings………...66

Figure (4.5): Degrees of importance and application for "LC Tools"…………...….70

Figure (4.6): Means of "Challenges of Transparency" due to "Years of

experience"……………………………………………………………….………....76

Figure (4.7): Means of "Lean Construction Tools - Degree of application" due to

"place of company office"………………………………………………………......78

Figure (4.8): Means of "Benefits of Transparency" due to "Annual average value of

projects"……………………………………………………………..………………82

Figure (4.9): Means of "Challenges of Transparency" due to "Annual average value

of projects" …………………………………………………………………….……82

Page 15: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

Chapter 1

Introduction

Page 16: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

1

Chapter 1: Introduction

This chapter presents a general introduction to the research; introduces

background about the construction industry in Gaza Strip, and Lean Construction

approach. It also provides problem statement, research objectives, questions and

hypothesis, research limitations and research structure.

1.1 Background

Construction industry plays major role in world‟s business. The environment of

construction tends to complexity rapidly and continuously due to increasing users'

requirements, environmental awareness, limited resources, and high competition in

construction business marketplace (Enshassi et al., 2009).

In Gaza Strip (GS), the construction sector has been affected by Israeli aggressions

and blockade for years, which made it susceptible to the political situation and trends

of international donations. Besides that, projects in Gaza Strip are characterized by:

low productivity, errors, poor co-ordination, bad reputation, high accident rates,

insufficient quality and overruns in cost and schedule (Yahia, 2004).

However, the country is moving towards reconstruction and rehabilitation processes

which will reactivate the construction sector in Gaza Strip, so that increase the need

for better planning of construction projects and better management of limited

building resources. So that, the construction industry in Gaza Strip needs great

efforts to apply new culture of management instead of traditional management

thinking in order to prevent or mitigate wastes in construction projects.

Lean Construction (LC) is a new culture of projects management in construction

industry that means eliminating all wastes and non-added value activities of the

construction project through all phases in order to get a profitable delivery. Reducing

wastes in process, time and costs, and maximizing the value added are considered a

crucial strategy to be implemented in construction projects. This practice is

applicable throughout lean construction principles. LC approach raised on the

deficiencies of traditional project management techniques to keep up with lack of

Page 17: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

2

resources, the huge growth, and increasing demands in the construction industry

(Russell et al., 2014).

Increasing process transparency is one of lean thinking criteria adapted by Koskela

(1992) which means to disclose information which is understandable, relevant,

accessible and useful to all project' stakeholders. Despite the importance of

transparency as a remarkable factor affecting the construction sector, there are

limited researches and evidences available to explain it.

Lean construction generally has not been implemented in Gaza Strip construction

industry yet, also the lean principles are unfamiliar for both contractors and

consultant engineers (Enshassi & Abu Zaiter, 2014).

1.2 Problem Statement

Wastes have been recognized as a major problem in construction industry in Gaza

Strip, and the level of material waste is higher than the nominal figures due to

managerial problems (Al-Maghony, 2006). He revealed that the top main cause of

both time and material wastes in Gaza Strip is reworks that do not comply with

drawings and specifications, which are highly related to poor communication

between project's parties; engineers, contractor and workers, which is also one of the

direct causes to time waste in GS's construction industry.

Despite all of that, innovative management approaches such as LC is still not applied

in GS's construction projects and limited researches have been done to investigate the

applicability of this crucial management approach in GS.

Therefore, transparency concept of lean construction is spotlighted in this research to

add valuable contribution to construction industry in GS and to enhance the sector's

performance. This research is the milestone for applying transparency concept and to

gives attention to lean construction approach in Gaza Strip.

1.3 Research Aim and Objectives

The basic research aimed to enhance transparency of construction projects in Gaza

Strip throughout lean construction approach.

Page 18: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

3

The aim of this research can be achieved through the following objectives:

1. To evaluate the current status and general perceptions of transparency

practices in construction industry of Gaza Strip.

2. To identify benefits, challenges and success factors supporting the

implementation of transparency principle.

3. To investigate the proper Lean tools/techniques those enhance transparency

in Gaza Strip.

1.4 Research Questions

Question (1): What is the level of knowledge of lean construction approach in

contracting firms in GS?

Question (2): What is the current status of transparency practices in construction

industry?

Question (3): Is there a significant relationship between the profile of contracting

company and degree of transparency practicing?

Question (4): What is the ranking of transparency tools according to their degree of

importance?

Question (5): Which are the most suitable and applicable LC techniques/tools to

improve transparency in construction firms in Gaza Strip?

Question (6): What are success factors, benefits, and challenges from the point view

of construction firms in Gaza Strip in order to apply transparency concept?

Question (7): What is the ranking of success factors according to their degree of

importance?

Question (8): Are their differences among respondents toward success factors,

benefits, and challenges of transparency concept due to the place of resident,

organization type, projects size and years of experience.

Page 19: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

4

1.5 Research Hypotheses

Research questions were answered by testing the following hypothesis through a

structured questionnaire, the hypothesis model is shown in Figure (1.1).

Hypothesis (1): There are statistically significant differences attributed to the profile

of contracting company at α≤ 0.05 between the averages of their views on the

subject of the application of increasing transparency concept within LC in Gaza

Strip.

Hypothesis (2): There is statistically significant positive relationship at α ≤ 0.05

between the existing status of applying transparency factors and existing status of

applying lean construction tools supporting transparency principle in GS.

Hypothesis (3): There is statistically significant positive relationship at α ≤ 0.05

between importance of transparency factors and importance of lean construction

tools supporting transparency principle.

Hypothesis (4): There is statistically significant positive at α ≤ 0.05 between

importance of increasing transparency factors and benefits of increasing transparency

principle.

Hypothesis (5): There is statistically significant at α ≤ 0.05 between importance of

lean construction tools supporting transparency principle and benefits of increasing

transparency principle.

Hypothesis (6): There is statistically significant at α ≤ 0.05 between importance of

lean construction tools supporting transparency principle and the effect of

transparency on lean construction principles.

Hypothesis (7): There is statistically significant positive relationship at α ≤ 0.05

between benefits of increasing transparency principle and the effect of transparency

on the lean construction principles.

Page 20: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

5

Figure (1.1): Hypothesis Model

1.6 Research Scope

The research targeted contracting companies in Gaza Strip.

The research targeted the construction experts who work in contracting

companies.

The research based on quantitative analysis using the results of questionnaire.

1.7 Research Structure

The thesis consists of five chapters as follows:

Chapter (1) Introduction: This chapter contains a general introduction to the

subject of the thesis. It describes research background, statement of the problem,

research aim and objectives, research questions, hypothesis, scope and research

structure.

Chapter (2) Literature review: This chapter introduces a general view on wastes

and its types in construction industry, the evolution of lean concept, developing of

lean construction and its techniques, and the applicability of transparency; benefits,

challenges, and success factors, also the previous studies in this field.

Page 21: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

6

Chapter (3) Methodology: This chapter describes the detailed adopted methodology

of research including the primary research framework for the study, details of

research period, location, population, and sample size. The questionnaire design was

detailed including the modifications and reviews done through experts' consultation.

Chapter (4) Data Discussion and Results: This chapter presents the analysis of

obtained data and discusses them in details. It includes quantitative analysis for each

section in the questionnaire, as well as the summary framework of the results.

Chapter (5) Conclusions: This chapter summarizes outcomes of the research under

each objective through the findings of the analyzed collected questionnaires, and

provides conclusions of the research.

References

Appendixes

Page 22: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

Chapter 2

Literature Review

Page 23: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

7

Chapter 2: Literature Review

This chapter presents a literature review of relevant areas under investigation in

this research work. The chapter begins with a brief view about construction wastes.

Then, literature of Lean concept, history, definition, and approaches were reviewed.

Afterward, visual management is presented as a lean approach that plays a significant

role in transparency of construction projects. An important focus of the literature

review is to understand the principle of transparency, also to integrate the principle

with lean construction, and why it is important for improving construction

transparency specifically in Gaza Strip as well as previous research work in this

context.

2.1 Wastes

The common sense understanding of waste is anything has no value. According to

the new production philosophy (LC), waste should be understood as any inefficiency

that results in the use of equipment, materials, labor, or capital in larger quantities

than those considered as necessary in the production of a building. Waste includes

both the incidence of material losses and the execution of unnecessary work, which

generates additional costs but do not add value to the product( Koskela, 1992).

Another simple way to define waste is "that which can be eliminated without

reducing customer value". It can be activities, resources, rules, etc (Polat & Ballard,

2004).Similarly, Alarcon (1997) defined waste as "Anything different from the

absolute minimum amount of resources of materials, equipment and manpower,

necessary to add value to the product". More precisely, waste is the expenditure of

effort or the using-up of resources without producing value (Howell et al., 2004).

Hence, in general, any losses generate direct or indirect costs but do not add value to

the product can be called „„waste‟‟, so that waste is measured in terms of costs; other

types of waste are related to the efficiency of the processes, equipment or personnel

are more difficult to be measured because the optimal efficiency is not always known

(Alarcón, 1997).

Page 24: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

8

Accordingly, based on the above definition, wastes are also called Non value adding

activities, so Non-value adding activities are those activities; time, resource, or space

consuming, but do not add value to the product. In contrast, value adding activities

are those activities which convert materials and/or information to produce the end

product (Alarcón, 1997).

2.1.1 Wastes in Construction Industry

Not only does waste have an impact on the efficiency of the construction industry

but also on the overall state of the economy of the country (Polat & Ballard,

2004).Furthermore, construction material waste has proved to have a negative impact

on the national economy and on the environment(Garas, Anis, & El Gammal, 2001).

Several studies from various countries have emphasized that wastes in construction

industry represent relatively large percentage of production cost. Faniran and Caban

(1998) informed that construction industry is a major generator of waste. As well as

Ekanyake and Ofori (2000) who reported that construction sector is generating

unacceptable levels of material waste. Construction activity generates an enormous

amount of waste (Teo & Loosemore, 2001).According to Lean Construction

Institute, the time waste in construction projects is 57 per cent; the following Figure

(2.1)shows the percentages of time waste in manufacturing and construction (Aziz &

Hafez, 2013).

Figure (2.1): Waste percentages of time (Aziz & Hafez, 2013)

Page 25: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

9

A case study of construction site in Sweden revealed through interviews, time study,

and observations that only 43% of work is value adding and gives value to the

customer, and the value-added work was approximately 44% of the workers' time.

This has financial implications not only on each individual project but also on the

industry as a whole and the entire national economy (Arleroth & Kristensson, 2011).

Taiichi Ohno, the mastermind of the Toyota Production System (Lean Production),

formed the seven wastes model in his book. These seven wastes were devised in the

context of production, and listed in this order; overproduction, time on hand,

transportation, processing itself, stock on hand, movement, and making defective

products (Ohno, 1988).

Koskela et al., (2013) argued that, ohno's list of wastes should be conceptually

compatible with construction, and empirically justified (i.e. focusing on the most

significant wastes). Such a list would be instrumental in creating awareness on the

major waste types occurring in construction, as well as mobilizing action towards

stemming, reducing and eliminating them. Also, many researchers have added

various types of waste to Ohno's model. These types of wastes were found to be

useful addition in practice; however, the wastes model is usually mentioned in its

origin seven types. At the 7th conference of IGLC in 1990, (Lee, Diekmann, Songer,

& Brown, 1999) proposed the following construction wastes:

1. Defects

2. Over-production

3. Unnecessary Processing

4. Unnecessary People Moves

5. Unnecessary Movement of Material

6. Waiting

7. Inventories

8. Designing Something that Does Not Meet the Client‟s Needs

Page 26: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

10

Ohno (1988) argued that the elimination of seven wastes will reduce the cost of

production, thus increasing profit.

2.1.2 Wastes in Gaza Strip

Waste has been recognized as a major problem in the construction industry in

Gaza Strip, and the level of material waste is higher than the nominal figures due to

managerial problems(Al-Moghany, 2006).

Al-Moghany identified the main waste causes in Gaza Strip construction industry,

and determined the level of waste within the sector through eighty questionnaires

received from construction firms operating in Gaza Strip. It was reported that the

main causes of material waste are: reworks that don't comply with drawings and

specifications, rework due to workers‟ mistakes, conversion waste from cutting

uneconomical shapes, ordering of materials that do not fulfill project requirements

defined on design documents, and waiting for replacement, inappropriate storage

leading to damage or deterioration, use of incorrect materials that require

replacement, poor workmanship, burglary, theft and vandalism and lack of workers

or tradesmen or subcontractors‟ skill.

While the main causes of time waste are: reworks that don't comply to drawings and

specifications, lack of materials(closure), rework due to workers‟ mistakes, effects of

social and political conditions, owner‟s poor communication with the construction

parties and government authorities, equipment frequent breaking down, slow in

making decisions, ambiguities, mistakes, and inconsistencies in drawings and using

untrained labors.

The above study in Gaza strip revealed that poor communication is one of the direct

causes to time waste in construction industry. The first main cause of both time and

material wastes in Gaza Strip is rework that do not comply with drawings and

specifications, which is highly related to poor communication between project's

parties; engineers, contractor and workers.

The model of the root causes of rework declares that leadership and communications

is one of the five main sources of rework (Fayek et al., 2003). Another study of the

Page 27: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

11

root causes of rework recommended firms to improve communication among owner,

designers and constructors to create a guiding coalition, and a shared objective and

mutual trust (McDonald & Leed, 2015).

Furthermore, a survey of 277 Chinese construction industries revealed that project

communication management is one of the main eleven rework factors.

Communication provides a significant means of exchanging information between

project managers and other stakeholders, also important for the contractor to

coordinate effectively with the owner to avoid misunderstandings or conflicts. The

study recommended enhancing project communication efficiency to reduce rework

caused by communication mistakes, and regular meetings should be beneficial for

information sharing and updating to reduce the possibility of rework (Ye et al.,

2014).

2.2 Lean Philosophy

2.2.1 Evolution of Lean Concept

The New Production philosophy or Toyota Production System (TPS) was created

in 1950'sby Engineer Taiichi Ohno in order to enhance productivity of the Japanese

company Toyota. Engineer Ohno, the father of the New Production System,

published his book "Toyota Production System" in 1978 to explain the new system

and his experiences. Afterward the name was changed into “Lean Production” by

Womack, Jones and Roos (1990) in the U.S as the previous name seemed unsuitable.

The core of the new production philosophy is in the observation that there are two

kinds of activities in all systems; conversions and flows. While all activities expend

cost and consume time, only conversion activities add value in the process.

Traditional managerial principles treat all activities as conversion activities though

they are all considered as value-adding activities, therefore flow processes have not

been controlled or improved in an orderly fashion. This led to complex, uncertain

and confused flow processes, expansion of non-value-adding activities, and reduction

of output value (Koskela et al., 2002).

Page 28: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

12

Thus, flow activities "wastes or no value added" should be eliminated or reduced to

minimum, whereas conversion activities "value adding activities" should be made

more efficient in the production system, which is the basic idea of lean thinking. The

outstanding success of this new management system in car manufacturing induced

others to adapt "Lean Thinking" at new fields like services, administration, product

development, and construction industry.

Koskela (1992) who leaded the adaption of Lean Thinking principles for

Construction industry, reported that "The conception of the new production

philosophy has evolved through three stages: it has been viewed as a tool (like

kanban or quality circles), as a manufacturing method (like JIT) and as a general

management philosophy (referred to, for example, as world class manufacturing).

Further, the theoretical and conceptual understanding of the new production

philosophy is still incomplete."

However, Lean Thinking is still growing and diffusing today all over the world and

many researchers work on adapting and developing techniques of lean production at

various fields and on different levels of practices.

2.2.2 Lean Definition

The underlying idea of LEAN concept is to minimize process wastes in order to

increase the value of results, however there is no unified definition for this

management approach and there is apparent controversy on the meaning since the

concept is used to refer to a phenomenon on several levels of applications, and it is

not clear where to place the boundaries between related approaches. Koskela and

Vrijhoef (2000) refer this to the newness of the field as it has not reached a degree of

maturity yet.

The idea of Toyota production system, the origin of lean concept, is the elimination

of inventories and other waste through small lot production, reduced set-up times,

semiautonomous machines, co-operation with suppliers, and other techniques (Ohno,

1988). Hence, Lean could be simply defined as a way to design production systems

to minimize waste of materials, time, and effort in order to generate the maximum

possible amount of value ( Koskela et al., 2002)

Page 29: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

13

Likewise, Lean Thinking concept is a way to do more and more with less and less;

less human effort, less equipment, less time and less space while coming closer and

closer to provide customers with exactly what they want (Womac & Jones, 1996).

The term “New production philosophy” refers to an evolving set of methodologies,

techniques and tools, the genesis of which was in the Japanese Just in Time (JIT) and

Total Quality Control (TQC) efforts in car manufacturing. Several alternative names

are presently used to refer to this philosophy; lean production, JIT/TQC, world class

manufacturing, time based competition (Koskela, 1992).

The two pillars of the TPS; JIT and Jidoka, are focused on creating transparency in

information so that the process participants have access to the important information

that they need to answer the six fundamental questions in a workplace which are

what, how many, who, when, how and where (Galsworth, 2005). The roof of the TPS

house represents the goals of an organization: best quality, lowest cost, shortest lead-

time (Brady, 2014).

2.2.3 Lean Principles

There are five fundamental principles for lean thinking, which have to be

followed step by step to achieve the goal of Lean, increase the value and minimize

wastes, and to gain the maximum benefit. Koskela et al. (2002)reported that there is

ample evidence that through the following principles, the efficiency of flow

processes can be considerably and rapidly improved.

1. Value: Specify value is the starting point for the application of Lean

Thinking, determining the main characteristics of the product from

customer‟s own definition and needs, and identify the value of activities

which generate value to the end product.

2. The Value Stream: Identify the value stream by elimination of everything,

which does not generate value to the end product. This means, stop the

production when something is going wrong and change it immediately.

Wastes or non-value adding activities should be eliminated or minimized to

the minimum value.

Page 30: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

14

3. Flow: Ensure that there is a continuous flow in the process by focusing on the

entire supply chain; reducing variability and irregularity so that material and

information may move in a predictable way within the supply chain. So that

focus has to be on the process and not at the end product. However, the flow

will never get optimal until customer value is specified, and the value stream

is identified.

4. Pull: Use pull in the process instead of push which means produce exactly

what the customer wants at the time the customer needs it. The idea is to

reduce unnecessary production and to use the management tool „„Just In

Time‟‟ that keeps inventory at a minimum.

5. Perfection: Strive constantly for perfection and continuous improvement in

the processes. Deliver a product which lives up to customer‟s needs and

expectations within the agreed time schedule and in a perfect condition

without mistakes and defects. The only way to do so is by having a close

communication with the customer/client as well as managers, and employees.

Simply, perfection principle means work continuously on the first four

principles to get better and better.

(WOMAK, 2003) and (Aziz & Hafez, 2013)

2.2.4 Controversy on Lean Approaches

Originally, lean thinking practices have been developed in the production context;

however, it extended far beyond the production sphere. Lean concept has widened

from tools and method at car manufacturing into management philosophy, and this

evolution involved developing various approaches and techniques to describe a range

of practices within the idea of Lean. Boundaries between these approaches are not

always clear and fairly often there is an overlapping among the main idea underlying

them ( Santos, 1999).

"New concepts emerged and the content of old concepts changed. The same concept

is used to refer to a phenomenon on several levels of abstraction. It is not clear

where to place the boundaries between related concepts."( Koskela, 1992)

Page 31: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

15

Koskela referred the majority of approaches on two historically important terms; Just

in Time (JIT) and Total Quality Control (TQC), as many new concepts have surfaced

from JIT and TQC efforts. These approaches have been rapidly elaborated and

extended, starting a life of their own e.g. Total Productive Maintenance (TPM),

Employee involvement, Continuous improvement, Benchmarking, Time based

competition, Concurrent engineering, Visual management, Re-engineering,

Lean production, and world class manufacturing.

Consequently, there is no consensus in the literature on whether Lean Production

ideas can be used to fully describe the new production management paradigm as

many researchers argue that the mass production paradigm has been replaced by a

wide range of solutions, applicable to different contexts, which cannot be brought

down to Lean Production model (Formoso et al., 2002). Furthermore, the field is still

young and in constant evolution. Therefore, it is difficult to present a coherent clear

overview of the ideas and techniques of the new production philosophy.

2.2.5 Implementation of Lean Concept

All over the world, many companies have made effort to adopt lean practices on

various levels. Even though there are numerous examples of successful

implementation of lean philosophy; there are also examples of failures and false

starts due to emotional and conceptual barriers of implementation.

Ashton et al. (1990) argued that many managers derive their perceived knowledge

from their position in the organization and they fear that their actual lack of

knowledge would be exposed. Also, there are conceptual barriers related to the

difficulty of abandoning the conventional management system concerning organizing

and controlling companies( Koskela et al., 2002). So researchers in different fields

have been working hard to formulate models of new philosophy and develop

techniques to help in implementing lean ideas.

Aziz and Hafez (2013) argued that lean implementation begins with leadership

commitment and is sustained with a culture of continuous improvement. When the

principles are applied properly; dramatic improvements in safety, quality, and

efficiency can be achieved at the project level.

Page 32: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

16

Implementation of Lean concept may be started with different levels of ambition. It

is a multidimensional change and learning process, which can be launched by

picking up just a few principles and techniques. If these are successfully

institutionalized, adoption of further principles more easily accepted.

A road map for Lean Implementation mentioned the "4P of lean way" in which

fourteen principles of implementation organized in four categories. (Ballard et al.,

2007)

1. Philosophy: the foundation of lean,

2. Process: application of lean tools,

3. People/Partners: developing internal and external people, and

4. Problem Solving: the evolution to lean enterprise through continuous

improvement.

Figure (2.2): „„4P‟‟ of the lean way (Ballard et al., 2007)

Page 33: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

17

Koskela (1992) organized four key factors that have to be balanced in implementing

the new philosophy. He reported that lack of balance among these four factors leads

usually to a dead end. The following is a brief about the four key factors of success

implementation as presented in Koskela framework.

1. Management commitment

Leadership is requisite to realize a fundamental shift of philosophy, with the goal

of improving every activity in the organization. Without an active initiative from the

management, change will stop at all natural barriers. Management must understand

and internalize the new philosophy and create an environment which is conducive to

change. As Deming (1986) says, there must be constancy of purpose.

2. Focus on measurable and actionable improvement

The focus should be on actionable and measurable improvement, rather than just

on developing capabilities. Originally in JIT, the overarching goal was to reduce or

eliminate inventories. However, reduction of inventories uncovers all problems.

Cycle time, space and variability also have to be used as drivers. Especially cycle

time provides an excellent, easy to understand driver, which can be improved

continually.

3. Involvement

Employee involvement happens naturally, when organizational hierarchies are

dismantled, and the new organization is formed with self-directed teams, responsible

for control and improvement of their process (Stewart, 1992). On the other hand,

involvement can be stimulated through problem solving teams. However employee

involvement is necessary, but not sufficient for realizing the full potential of

continuous improvement since Shingo (1988) and Imai (1986) stress that

management and staff specialists have a dominant role in targeting and realizing the

improvement.

Page 34: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

18

4. Learning

Implementation requires a substantial amount of learning and there are three

stages of learning; firstly, learning should be directed at principles, tools and

techniques of process improvement. The second source of learning is the empirical

learning and using pilot projects for testing new ideas on a limited scale so that

formal reviews of progress and experiences are useful. The last phase of learning is

made up by external information, which can be tapped through benchmarking.

2.3 Lean Construction

2.3.1 Adopt Lean to Construction Industry

After having the "production" characteristics, lean concept has taken some steps

to adapt into construction industry which has sought a new foundation for

construction project management. Traditionally, construction is viewed and modeled

only as a series of conversion activities so called value-adding activities while waste

activities such as waiting, storing inventory, moving material, and inspection are not

generally modeled by Critical Path Models (CPM) or other control tools. Thus,

construction could realize dramatic improvements simply by identifying and

eliminating non value-adding activities. So that actual construction should be viewed

as flow processes consisting of both waste and conversion activities, not just

conversion processes. Concisely, exploratory studies concluded that construction

should adopt the new production philosophy ( Koskela, 1992).

Koskela is the first researcher who studied the applicability of lean concept in

construction in 1992 after the great gains of lean in manufacturing. It was introduced

in his seminal report(Koskela, 1992). He also hosted the first conference of the

International Group for Lean Construction (IGLC) in Espoo, Finland in 1993

whereas a group of researchers at the conference adopted the name “Lean

Construction” ( Tezel et al., 2008). The International Group for Lean Construction

(IGLC) and Lean Construction Institute (LCI) are the most notable organizations

have been working for the development of the lean thinking in the construction

industry.

Page 35: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

19

Nowadays lean construction holds differences in the interpretations of the approach,

and there is a lack of clarity surrounding the concept of lean due to differences in the

environment and processes between lean manufacturing and lean construction,

concurrently their techniques share many common elements. There are two slightly

differing interpretations of Lean Construction; one interpretation views lean

construction as adapting and applying lean production methods and tools to

construction sector. In contrast, the other interpretation views lean production as a

theoretical inspiration for the formulation of a new, theory-based methodology for

construction, called lean construction. The later interpretation has been dominant in

the work of the IGLC(Koskela et al., 2002).

In manufacturing, a considerable number of specific principles and techniques have

been developed for process improvement. To a perhaps considerable extent, they are

also usable in construction. IGLC has led research on the application of lean

techniques and has provided tools for operational planning and control, supply,

visualization, and continuous improvement. Lean construction techniques are gaining

popularity, however many tools and elements are still in an embryonic state (Salem

et al., 2006).

2.3.2 Lean Construction Definition

Koskela et al., (2002) defined Lean Construction “a way to design production

systems to minimize waste of materials, time, and effort in order to generate the

maximum possible amount of value”. (Yahya & Mohamad, 2011)proposed that

“Lean Construction is about managing and improving the construction process to

profitability deliver what the customer needs by eliminating waste in the construction

flow due to construction contract, specification and agreement between client and

other parties by using the right principle, resources and measure to deliver things

right first time”. Macomber and Howell(2003) stated that Lean Construction

management should be understood as a series of conversations between parties

involved and their plans therefore may be seen as promises or commitments made by

the participants to each other, the principles of making and keeping reliable promises

and point at the importance of the person making a promise being also capable of

fulfilling it.

Page 36: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

20

However, there is no existing definition is yet satisfactory to describe lean

construction in a rigorously testable method. This is a major obstacle to the

successful deployment of lean construction especially when the industry does not

have a standard benchmark of “what a lean site looks like”( Leong, Ward, &Koskela,

2015).Whilst this is not an excuse for sticking to the old routines, and construction

companies should not wait for a consolidation of construction specific

implementation methodology but take the change steps since notable gains may be

achieved in most organizations even by well-directed initial efforts (Koskela et al.,

2002).

2.3.3 Lean Construction Principles

Koskela (1992), the mastermind of LC, proposed eleven principles or criteria for

practicing the new production philosophy to improve the flow process in various

fields, the following heuristic principles was evolved as an implementation guideline:

1. Reduce the share of non-value-adding activities.

2. Increase output value through systematic consideration of customer

requirements.

3. Reduce variability.

4. Reduce the cycle time.

5. Simplify by minimizing the number of steps, parts and linkages.

6. Increase output flexibility.

7. Increase process transparency.

8. Focus control on the complete process.

9. Build continuous improvement into the process.

10. Balance flow improvement with conversion improvement.

11. Benchmark.

Page 37: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

21

Thereafter, Koskela and Vrijhoef (2000)proposed the T.F.V approach for a wider

understanding of construction and to improve its performance in which the new

production management paradigm has been conceptualized in three complementary

ways; Transformation, Flow, and Value generation "T.F.V theory of production".

They argued that the current practice in construction heavily emphasizes the

transformation view and should be expanded to cover the other two views as well.

The principles of T.F.V approach are shown in Table (2.1) from (Tezel et al., 2008).

Table (2.1): T.F.V theory of production

Concept

P R I N C I P L E S

Conversion (Transformation)

Flow Value

Decomposition:

The transformation Process can

be decomposed into sub

processes which are also

transformation processes.

Cost minimization:

The Cost of total process can be

minimized by minimizing the

cost of each sub process.

Buffering:

It is advantageous to insulate the

production process from external

environment through physical

and organizational buffering.

Value:

The value of the output of a

process is associated with the

cost of inputs to that Process.

Reduce the share of non-

value adding activities:

Try to eliminate the reasons of

waste that were defined by

Shingo Womack and Jones.

Reduce the lead time:

Basically, eliminating non-

value activities will cause a

reduction in the lead times.

Reduce variability:

Variability increases the lead

time.

Simplify:

Reduce the number of

components in a product or the

number of steps and linkages

in a material and/or

information flow.

Flexibility: Increase mix

flexibility volume.

Requirements Capture:

Ensure that all customer

requirements, both explicit and

latent, have been captured.

Requirement flow-down:

Ensure that relevant customer

requirements are available in all

phases of production, and that

they are not lost when

progressively transformed into

design solutions, production

plans and products.

Comprehensive requirements:

Ensure that customer

requirements have a bearing on

all deliverables for all roles of

customer.

Source: (Tezel et al., 2008)

2.3.4 Implementation of Lean Construction

LC implementation effort can be divided into three different stages, with

increasing degree of sophistication. Stage one focuses on waste elimination from

technical and operational perspective. The second stage focuses on eliminating

adversarial relationships and enhancing cooperative relationships and teamwork

among supply chain actors. The essential parts are cooperation, long term framework

agreements, workshops, and facilitator. The third stage identified is the most

Page 38: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

22

sophisticated, involving a structural change of project governance in which essential

parts are: Information technology, pre-fabrication, last planner, bottom-up activities

and emphasis on individuals, a rethink of design and construction, decreased

competitive forces, long-term contracts, training at all staff levels, and a system

perspective of both processed and product (Green & May, 2005).

Also, Eriksson (2010)studied how to increase the understanding of implementing

various aspects of Lean Thinking in construction projects and grouped these various

aspects of lean into six core elements: waste reduction, Process focus in production

planning and control, End costumer focus, Continuous improvement, Cooperative

relationships, and System Perspectives. Ross and Associates (2004) mentioned LC

elements in different order as follows: LC six core drivers are waste elimination,

process control, flexibility, optimization, people utilization, continuous and efficient

improvement, and value to customer.

In practice, every organization in construction already can initially apply the new

production philosophy. Getting started is often the toughest problem. It might be

wise to adopt a proven, even if narrow, methodology for getting started, also it is

important to select and systematically use appropriate principles, techniques and

tools. There are successful experiences in implementing lean construction have been

achieved. For example, Conte & Gransberg (2001) examined the principles used in

applying lean construction by over 20 construction companies in Brazil as they

succeeded in implementing lean construction principles.

2.3.5 Lean Construction Techniques

In manufacturing, a considerable number of specific principles and techniques

have been developed for process improvement. To a perhaps considerable extent,

they are also usable in construction. Implementation of LC may be started with

different levels of ambition. It is a multidimensional change and learning process,

which can be launched by picking up a few principles and techniques to be

implemented successfully and gain profits so that waiting for a consolidation of

construction specific implementation methodology is no excuse for sticking to the

old routines.

Page 39: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

23

Salem et al. (2005) reported that lean construction is composed of these techniques;

Concurrent Engineering, Last planner, Daily huddle meetings, The Kanban System,

Plan Conditions and Work Environment in the Construction Industry, Quality

Management Tools, and Visual Inspection.

Salem et al. (2005) proposed a new lean assessment tool to quantify the results of

lean implementations. The assessment tool evaluates six lean construction elements

including: Last Planner; increased visualization; huddle meetings; first-run studies;

five S‟s; and fail safe for quality. Meanwhile, the impact of lean on sustainability

was observed and discussed. He tested the effectiveness of some lean construction

tools, in particular, those tools that can be applied in medium size construction firms.

The effectiveness of the lean construction tools was evaluated through the lean

implementation measurement standard and performance criteria. It was found that

last planner, increased visualization, daily huddle meetings, and first-run studies

achieved more effective outcomes than expected. However, the results of

implementation of 5S process and fail safe for quality did not meet the expectations

of the tool champions and the research team. It was found that there is a need for

behavioral changes and training for effective use of lean tools. Most of the lean

construction tools, selected for the project, are either ready to use or are

recommended with some modifications.

Also, Salem et al. (2006) studied the transformation of lean manufacturing

techniques into LC through four scopes illustrated in the following Table (2.2).

Page 40: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

24

Table (2.2): Tools of Lean Construction

Source: (Salem et al., 2006)

2.4 The principle of Transparency

2.4.1 Definition of Transparency

The principle of transparency is a core element of Lean Production, the lack of

transparency on construction sites appears to contribute to the fact that production

systems in construction often operate well below their full potential (Formoso et al.,

2002). He defined transparency as “the ability of a production process (or its parts) to

communicate with people”.

Criteria/Change Requirements Technique Scop

Pull approach

Quality

Knowledge

Communication

Relation with other tools

Reverse phase

Scheduling

Six-week look-ahead

Weekly work plan

Reasons for variance

PPC Charts

Last Planner Flow

variability

Actions on the job site

Team effort

Knowledge

Communication

Relation with other tools

Cheak for quality

Cheak for Safety

Fail safe for

quality

Process

variability

Actions on the job site

Team effort

Knowledge

Communication

Relation with other tools

Sort

Straighten

standardize

Shine

Sustain

Five S's

Transparency Visualization

Team effort

Knowledge

Communication

Relation with other tools

Commitment charts

Safety signs

Mobile Signs

Project milestiones

PPC Charts

Increased

visualization

Time spent

Review work to be done

Issues covered

Communication

Relation with other tools

All foreman meeting

Start of the day meeting Huddle meetings

Continuous

improvement Actions on the job site

Team effort

Knowledge

Communication

Relation with other tools

Plan

Do

Check

Act

First-run studies

Page 41: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

25

It is needed to make the main process flows visible and comprehensible from start

to finish by measuring and public displaying of information (Koskela & Vrijhoef,

2000). The "process" represents the flow of materials from the delivery of raw

materials to the end product ( Koskela, 1992).

Other researchers have described transparency as way to provide people with a clear

understanding of different aspects of the current system performance and status,

giving them feedback on performed activities and helping in making decisions,

letting them recognize interdependencies and as a result, enabling higher levels of

improvements(Bauch, 2004). Transparency provides insights into matters that are

relevant for all parties involved in a common process who with the right information,

can make well-founded decisions with regard to the transactions that they agree on

with one another (Nijhof et al., 2009).

In a traditional work environment, control and knowledge tends to be centralized and

managers tend to know more about the process than operators however transparency

means a separation of the information network and the hierarchical structure of order

giving (Greif, 1991). The goal is thus to substitute self control rather than formal

control (Brady, 2014).

The principle of transparency represents a substantial change in the production

management of construction since it aims to transform the traditional “silent”

processes into ones that communicate in an active manner (Oliveira et al., 2012).

If process transparency is successfully implemented, most problems, abnormalities,

and types of waste that exist can be easily recognized in order to allow remedial

measures to be taken(Igarashi, 1991). While lack of process transparency increases

the propensity to err, reduces the visibility of errors, and diminishes motivation for

improvement. Thus, it is an objective to make the main flow of operations from start

to finish visible and comprehensible to all employees for facilitation of improvement

and control.

It can be concluded that a key characteristic of transparent processes is that they

radiate relevant information in a physical way, facilitating communication, decision-

Page 42: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

26

making and promoting self-management. With the transparency of processes, trust

among parties is built and value is generated (Brady, 2014).A process reaches

excellent in terms of transparency when everyone, even those with relatively

little technical knowledge, understands the process without asking (Santos,

1999).

2.4.2 Transparency within Lean Construction

Transparency is a key lean principle as Increasing Process Transparency is the

seventh principle of lean construction by (Koskela, 1992) which mentioned at section

(2.3.3) in this chapter. In Lean construction theory, insufficient process transparency

increases the chance for errors, reduces the visibility of errors, and decreases

motivation for improvement. Processes that are directly observable, standardized,

and measured can help prevent this lack of transparency (Koskela & Vrijhoef, 2000).

(Koskela, 1992)discussed the notion of increasing transparency principle and

presented some ideas on how to create transparency in the construction process, he

proposed six practical approaches to increase process transparency include the

following:

Establishing basic housekeeping to eliminate clutter: the method of 5-S7

Making the process directly observable through appropriate layout and

signage

Rendering invisible attributes of the process visible through measurements

Embodying process information in work areas, tools, containers, materials

and information systems

Utilizing visual controls to enable any person to immediately recognize

standards and deviations from them

Reducing the interdependence of production units (focused factories

Salem et al. (2006) identified transparency as one of the main four scope of LC, and

specified the techniques of LC that achieve each scope. They reported that Five S's

Page 43: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

27

(5S) and Increased Visualization are the LC tools that increase the process

transparency in construction projects. As shown in Table (2.2) at section (2.3.5) in

this chapter.

Salem et al. (2006) reported the requirements of 5S tool are; Sort, Straighten,

Standardize, Shine, and Sustain, while the requirements of Increased Visualization

tool are; Commitment Charts, Safety Signs, Mobile Signs, Project milestones, and

PPC charts). Also, both (Galsworth, 1997)and (Igarashi, 1991) emphasized the use

of 5S as a well-known method for keeping a clean and orderly workplace, originally

developed in Japan.

Even though(Salem et al., 2006) identified Huddle Meetings tool under the

Continuous Improvement Scope, the researcher concluded from the in-depth

readings that Huddle Meetings tool is also enhance the transparency of the project,

since the all foreman meeting and Start of the day meeting definitely strengthen the

communication and disseminate information.

2.4.3 Visual Management Approach

Limited researches of Lean Construction Management in Gaza addressed the

primary meaning of lean construction aiming generally to increase process value and

reduce wastes using a number of practical LC tools. While lean construction

management has been branched into many approaches each addresses a specific goal

at project management in a holistic view and within lean context; such as Just in

Time (JIT), Total Quality Management (TQM), Re-engineering, Total Productive

Maintenance (TPM), Time Based Competition, Concurrent Engineering, and Visual

Management. Visual Management is the lean approach which focuses on the

transparency of construction projects. Therefore, this research work highlighted

Visual Management as a technique of transparency within LC.

Visual management is not well known within the construction industry; however, the

importance of visualization is well recognized (Tjell &Sijtsema, 2015). "As the work

environment becomes more and more complex, the need for connecting human

efforts with processes and the organization‟s strategic goals become more important.

Visual management and its elements offer this link through transparency" (Koskela

Page 44: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

28

& Vrijhoef, 2000). According to the T.F.V. approach, transparency is an important

aspect of production flow and it is realized through visual management.

Definition of VM

Visual Management (VM) can be defined as a management system that attempts to

improve organizational performance through connecting and aligning organizational

vision, core values, goals and culture with other management systems, work

processes, workplace elements, and stakeholders, by means of stimuli, which directly

address one or more of the five human senses; sight, hearing, feeling, smell and taste.

These stimuli render transparency through providing immediately necessary quality

information which helps people make sense of the organizational context at a glance

(Liff and Posey, 2004).

Tjell and Sijtsema (2015) defines VM as a system that enables the employees to

better understand their role and contribution in relation to both their own

organizational values and costumer needs. Visual management aims at creating an

information field from which people can immediately pull information when they

need it (Greif, 1991). Visual management influences, directs, limits and guarantees

human behavior (Galsworth, 1997).

Tezel et al., (2008) views VM as a communication system that tries to eliminate the

short-comings of the classical organizational communication model. It provides

necessary, true, relevant, immediate answers to the questions of people at work, so

that eliminate their dependence on other identities for information.

The above understanding helps people attribute themselves to the organization

through strengthened awareness. People can understand what the right way to do a

task is, what kind of impacts their efforts create on the organizational performance,

what performance measures are used to assess their efforts, where the correct places

of the materials, equipment and the machinery are, what skills the people in the

organization possess, and many more, by merely looking around, just at a glance. So

that normal and abnormal conditions should be distinguished by anyone, even in

experienced or newly hired employee (Tezel et al., 2008).

Page 45: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

29

Functions of VM

Visual Management is a highly practical approach with numerous visual solutions for

different management practices. The general understanding of VM mainly

concentrated on its transparency and/or discipline functions, particularly in the lean

production literature. (Tezel et al., 2009) argued that a complete understanding of the

term is necessary for the unified exploitation of these functions so that he identified

nine functions from different resources and resulted in taxonomy of VM functions;

transparency, discipline, continuous improvement, job facilitation, on the job-

training, creating shared ownership, management by facts, simplification and

unification (Tezel et al., 2009). VM functions are illustrated in details in Table (2.3).

Table (2.3): Functions of Visual Management

Function Definition Alternative Practice

Transparency

The ability of production process (or its

Parts) to communicate with People

(Formoso et al, 2002).

Information held in people's

minds and on the shelves

Discipline Making a habit of properly maintaining

correct procedures (Hirano, 1995).

Warning, scolding, inflicting

Punishments, dismissing etc.

Continuous

Improvement

An organization-wide Process of focused

and sustained incremental innovation

(Bessant and Francis, 1999).

Static organization or big

improvement leaps through

considerable investment

Job Facilitation

Conscious attempt to physically and/or

mentally ease people's efforts on routine,

already known tasks by offering various

visual adis*.

Expecting people to perform

well at their jobs without

providing them any aids.

On-the-Job

Training

Learning from experience (Mincer,

1962) or integrating working with

learning (Sumner el al., 1999)

Conventional training

practices or offering no

training.

Creating Shared

Ownership

A feeling of possessiveness and being

psychologically tied to an object

(material or immaterial) (Pierce et al., 2001)

Managements dictation for

change efforts, vision and culture creation

Managements by

facts

Use of facts and data based on statistics

(Gunasekaran et al., 1998)

Managements by subjective

judgment or vague terms

Simplification

Constant efforts on monitoring,

processing, visualizing and distributing

system wide information for individuals

and terms*.

Expecting people to monitor,

process and understand the

complex system wide

information on their own.

Unification

Partly removing the four main

boundaries (vertical, horizontal, external

and geographic) (Ashkenas, 1995) and

creating empathy within an organization

through effective information sharing*.

Fragmentation or " this is not

my job" behavior

Source: (Galsworth, 1997).

Page 46: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

30

Visual Systems (Visual Workplaces)

Visual Management is realized by visual systems that consist of one or more visual

elements to achieve visual workplace structured with information giving, signaling,

limiting or guaranteeing to allow communicate with “doers”, so that places become

self-explanatory, self-ordering, self-regulating and self-improving (Galsworth,

1997).This visual place which speaks the language of lean production means that

what is supposed to happen does happen, on time, every time, day and

night(Galsworth, 2004).

Visual control systems can be gradually implemented by dividing it in clusters,

named by (Galsworth, 1997)as mini-systems. There are sub-sets of visual devices

that work together to create an information field for people in order to pull the

necessary information at a glance by merely looking around (Greif, 1991). A number

of mini-systems (Visual elements) can be chosen for the initial stages of

implementation, when it is necessary to convince people about the benefits of

process transparency. These mini-systems (Visual elements) are consciously

designed to structure human behavior with different power index depends on the

extent to which the message they send is likely to be obeyed and the potential risk or

loss if we decide to ignore it. Visual elements, in ascending order of their power

indexes as reported in (Galsworth, 1997) and (Tezel et al., 2008), are as follows:

Visual Indicator: Gives only information. It only tells and tries to influence. The

human control of disobedience is high. The consequence of disobedience is minimal.

The commonly used visual indicators in a lean environment are team boards,

departmental boards, charts, logs, photos, films, electronic visual models, value

stream maps etc.

Visual Signal: Signals and grabs your attention with visual stimuli. It expects people

to listen and directs their behavior. The human control of disobedience is moderate.

The consequence of disobedience may be high. In the lean environment, quality

control tools such as the andon and autonomation can be good examples for the

visual signal. The andon signals visually and audibly to call a team leader in case of

an abnormality in a line or at a workstation. When a machine stopped, it is a direct

Page 47: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

31

and effective visual signal for action. The culture of stopping production is the

strength of lean production.

Visual Control: Controls and limits human response in terms of height, size,

quantity, volume, weight, width, length and breadth. Human control of disobedience

is almost none. Generally it integrates the message into the physical environment,

leaving people not many options for response. Bordering, outlining, marking, color-

coding, the safety, the production, and the maintenance kanban (signaling cards) are

some of the tools utilized for the visual control in lean production.

Visual Guarantee: Guarantees and allows the correct response only. No intentional

or unintentional errors. Human control of disobedience is none. It adds high

discipline. All the information one needs is built through mechanically or

electronically into the machine, material or environment itself (Poka-Yoke devices –

Zero Quality Control).

(Galsworth, 2004)proposed a hierarchical framework to model the visual workplace

that can be seen in the following Figure (2.3).

Figure (2.3): The Model of Visual Work place (Galsworth, 2004)

Page 48: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

32

2.4.4 Benefits of Increasing Process Transparency

"There is a need for increased transparency in construction to deal with the

uncertainty that exists, to better understand the complicated relationship between

activities and interfaces, thus anticipating and resolving problems earlier"(Brady,

2014)

Klotz (2008) studied the effect of process transparency on the project cost, several

note worthy implications are derived from this study; Stakeholders delivering

sustainable building projects should understand the value of process transparency;

the majority of costs related to a lack of process transparency appeared during the

construction phase of project delivery and could have been avoided during design;

efforts to enhance process transparency represent a fraction of the costs related to

rework and other costs resulting from a lack of process transparency; delay costs

make up a significant proportion of costs related to a lack of process transparency;

and cost impacts result from a lack of process transparency both between stakeholder

groups and also within these groups.

Facilitate a holistic view of the entire process and to implement flow: In order to

observe the construction process as a flow of activities and to achieve a holistic view

of the overall process, a high capability of handling vast amounts of information is

required. In order to overcome the difficulties associated with this additional

information, production activities in construction must become more transparent. The

application of the principle of transparency is a key concept for making the flow

model viable (Santos et al., 1998).

Reduce time waste: There is a strong link between the incidence of non-value

adding activities and information deficits in the workplace. Instead of carrying out

value adding activities, very often people spend precious time searching, wandering,

or waiting for the tools, materials, and information they need in order to do their

work (Galsworth, 1997). In workplaces where the layout changes frequently, it is

necessary to provide effective location information so that everyone identifies

workstations and pathways easily (Greif, 1991).

Page 49: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

33

Enhance control process: The amount of information displayed at the workplace

has strong influence on the effectiveness of the production planning and control

process(Formoso et al., 2002). Control is simplified, reducing the propensity to errors

and most certainly increasing the visibility of errors (Koskela, 1992).

Defects become visible: If process transparency is successfully implemented, most

problems, abnormalities, and types of waste that exist can be easily recognized in

order to allow remedial measures to be taken(Igarashi, 1991).

Support continuous improvement: In order to identify higher levels of

improvements and understand what effect those improvements have on the overall

process, it is necessary to make the process and information flow between the

different interfaces transparent(Brady, 2014).Visual communication also tends to

increase the involvement of workers in continuous improvement efforts, since it

allows rapid comprehension of and response to problems(Igarashi, 1991).

Build trust and motivate process participants: construction companies usually

have few visual mechanisms to inspire, instruct or motivate workers to carry out their

jobs more effectively, efficiently and safely ( Santos et al., 1998). Process

transparency has a very important impact on motivation. In the absence of facts,

assumptions are all too pervasive. The more scarce information becomes, the fewer

employees trust each other. A sense of disempowerment may follow, leading people

to start worrying about making mistakes (Galsworth, 1997).

A support principle: that enables other LC principles to be effectively implemented

(Formoso et al., 2002).

The practical impacts resulting from transparency on a working environment can be

summarized in the following manner: simplification and increased coherence

indecision making, stimulation of informal contact between the different

hierarchical positions, contributions towards introducing decentralization policies,

assistance in extending workers‟ involvement and management autonomy, increased

efficiency in production programming, simplification of the production control

systems, quicker understanding and response to problems, and finally, greater

Page 50: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

34

motivation among workers towards improving being able to visualize errors (de

Oliveira et al., 2012).

2.4.5 Challenges of Increasing Process Transparency

(Formoso et al., 2002) studied the applicability of process transparency and

identified barriers for its implementations in construction based on a literature

review, and on six exploratory case studies carried out in Brazil and England. The

study indicated that it is feasible and worthwhile to apply the principle of

transparency in construction sites and can bring direct benefits for the performance

of production systems. However, some difficulties related to the implementation of

visual systems are inherent to construction sites or problems in management.

Changeable work environment as site layout modified several times

throughout the project. This may demand to update and reallocate the

necessary set of visual devices, especially location addresses and borders.

Large place of work site where large numbers of crews spread out and move

continuously.

Lack of knowledge as managers are not aware of process transparency

benefits.

Low level of participation of workers in improvement process has negative

impact on transparency.

Poor degree of transparency in construction sites contribute for operating below the

full potential of production system; precious time wasted in searching…etc as well as

wastage and unneeded materials obstruct pathways and reduce process visibility.

2.4.6 Success Factors to Increase Process Transparency

It is necessary to establish strong management, structured and systematic plan to

implement visual systems as well as training and hands-on experience in order to

make managers fully knowledgeable about benefits of transparency principle and its

impact on production system (Formoso et al., 2002).

Page 51: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

35

Although visualization programs can support process improvements in terms of

reducing inventories and waste, an opposite cause-effect relationship also exists. If

production pans are vague and large inventories are kept, it is very likely that the

production system will have many hidden problems and waste. In this situation, even

if visual devices are used, some problems will still be difficult to be identified.

Therefore, it is necessary to implement some basic improvements in production

systems, such as forcing the reduction of inventories to some extent, and tightening

production plans, in order to increase the positive impact of visual systems (Igarashi,

1991).

It is also important to consider the two-way influence between transparency and

process variability. So that reducing process variability also facilitates the

implementation of visual control systems, as well as drawing visual mechanism is

necessary to inspire or motivate workers to carry out their jobs efficiency and

effectively (Formoso et al., 2002).

Page 52: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

36

Summary

Poor communication was recognized as a main cause of time and material wastes in

construction industry of Gaza Strip; so that transparency in construction projects

should be enhanced as a way to communicate with people in the system, provide

them a clear understanding of different aspects of performance and status, and

enabling higher levels of improvements. Koskela (1992) who adopted Lean Thinking

into Construction industry defined Lean Construction as a way to design production

systems to minimize waste of materials, time, and effort in order to generate the

maximum possible amount of value. Also, he reported eleven criteria of LC;

Increasing Process Transparency is one of these main criteria.

Increasing Process Transparency allows great benefits to construction industry; its

reduce time waste, enhance control process, support continuous improvement, build

trust and motivate process participants, and defects become visible. However, there

are many factors supposed to be achieved formerly in order to enable the success of

transparency principle such as; strong management, structured and systematic plans,

fully knowledgeable managers, reduction of inventories to some extent, and reducing

process variability. On the other hand, changeable work environment, large place of

work site, lack of managers' knowledge, and low level of participation of workers in

improvement process, are all main challenges facing transparency applicability.

5S's, Huddle Meetings, and Increased Visualization are LC tools that support

transparency in construction projects, as well as, Visual Management approach

which enhance transparency in the process. Therefore, this research focused on those

techniques, and related its factors and aspects to study the applicability in

construction industry in GS.

Page 53: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

Chapter 3

Methodology

Page 54: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

37

Chapter 3: Methodology

This research was designed to investigate the applicability of increasing

transparency principle within lean construction approach in Gaza Strip. This chapter

describes the methodology that was used in this research and was selected to achieve

the research aims and objectives. The adopted methodology involved the following

techniques; research design, research population, questionnaire design, statistical

data analysis, content validity and pilot study.

3.1 Research Design

The research followed the analytical/descriptive approach in addition to the

statistical analysis. The data were collected from the primary and secondary

resources. The secondary resources include the use of books, journals, statistics and

web pages. The primary data were collected using a questionnaire that was

developed specifically for this research purpose. Many of measurement tools

“questionnaires” used by other researchers were adapted, translated, combined and

modified to fit the purpose of this research ended up in developing the research

questionnaire. The researcher designed the research by seven main steps as described

below and shown in Figure (3.1).

First step: Theme identification (Problem definition)

It was initiated to define the problem, set the objectives and develop the research

plan.

Second step: Literature review

Dozens of published articles were reviewed from different international journals in

order to study various topics needed for this research; evolution of lean principle,

lean construction adoption besides its techniques, and the principle of increasing

transparency as well as the visual management approach. Literature review study

produced the deriving of 19 factors of 4 chosen lean construction tools that achieve

the transparency, as well as 6 factors of increasing transparency principle.

Page 55: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

38

Also 12 benefits, 7 success factors and 6 challenges were derived and collected from

research articles.

Third step: Questionnaire development

The pilot study includes two parts; the first part was undertaken by consulting 5

experts, academic doctors, to pre-test the survey and subsequently modified before a

final version was produced. The second part was accomplished by making analysis

trial using some of the population sample for validation before the main survey. The

questionnaire was modified based on the results of the pilot study so that the final list

of questions was adopted to be used for the study.

Fourth step: The Field survey

This research targeted contracting companies work in construction field in Gaza Strip

in order to examine their transparency practices, and the applicability of increasing

transparency principle in construction projects. In order to obtain reliable and

representative quantitative data, questionnaires were distributed to engineers work in

contracting companies at various positions (Company director, project manager, site

engineer, office engineer) as they know the best in this regard. Moreover, the

targeted companies are from different governorates, nature of works, sizes and years

of experiences.

Fifth step: Results and discussion

Data collected and then analyzed using statistical software, Statistical Package for

Social Science (SPSS 24). Specialized expert in SPSS and statistical analysis assist

the researcher to analyze and extract results from the program.

Sixth step: Conclusion and recommendations

This phase included the conclusion and recommendations of this research.

Seventh step: documentation

The final phase of the research included editing the final text, formatting, spelling

and grammatical review.

Page 56: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

39

3.2 Research Period

The study started in January 2016 after the proposal was approved. The literature

review completed at the end of September 2016. The validity testing, piloting and

questionnaire distribution and collection completed at the end of April 2017. The

analysis, discussion, conclusion and recommendation were completed in August

2017.

3.3 Research Location

The research was conducted in the five governorates; North, Gaza, Middle, Khan

Younis, and Rafah in Gaza Strip, Palestine.

3.4 Research Population

This part explains sample elements, size, and sampling procedures.

Topic Selection

Literature Review

Theme

identification

Define the

Problem

Establish aim

and objectives

Develop

Research Plan

Field Survey

Results and Data

Analysis

Conclusion &

Recommendation

Questionnaires Design

Thesis Proposal

Literature Review

Pilot Questionnaires

Questionnaires Validity

Questionnaires

Reliability

Figure (3.1): Flowchart of research methodology

Page 57: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

40

3.4.1 Sample Elements

The research sample elements consist of construction engineers who can defined

in this study as; civil or architectural engineers who are company directors, project

managers, site engineers or office engineers and work at contracting companies in

construction projects in Gaza Strip.

3.4.2 Sample Size

Study sample is a subset of population selected to participate in a research study

and its size refers to the number of the elements included in a study, that can be

individuals, groups or organizations (Tezel, Koskela, & Tzortzopoulos, 2010). The

aim of determining an adequate sample size is to estimate the population prevalence

with a good precision (Naing, Winn, & Rusli, 2006). It is less costly and less time to

collect data from a sample rather than collect it from all population.

However, the selected sample may not adequately represent the population and the

obtained results cannot be generalized (Marczyk et al., 2005). The principles of

statistical sampling that guarantee representative sample are used for the sake of

speed and economy (Fellows & Liu, 2008). Several factors can influence the size of

the required sample for a study, including the purpose of the study, population size,

sample sizes used in similar studies, the risk of selecting a “bad” sample, and the

allowable sampling error and resource constraints (Israel, 2013). A statistical

calculation approach has been used in this study to calculate the required sample

size.

Israel (2013) reported that, many researchers commonly increased the sample size

about 10% to 30%, to compensate for persons that the researcher is unable to contact

and for nonresponsive. Thus, the number of distributed questionnaires is larger than

the number required for a desired level of precision and confidence.

3.4.3 Sampling Procedure

A sample design “sampling procedure” refers to the procedure or the technique

that researcher may adopt in selecting items of the sample (Kothari, 2004).

Page 58: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

41

A convenience sampling was used in this research which is a type of no

probability sampling as respondents are sampled simply because of their convenient

accessibility and proximity to the researcher.170 copies of the questionnaires were

distributed to the targeted elements, while only 130 copies were returned from

respondents and completed for quantitative analysis since many of targeted elements

had no enough time to response. So that the total returned percent is nearly 76.5%

which is acceptable.

3.5 Questionnaire Design

A significant amount of work has already been done on LC tools, items of

increasing transparency principle, its benefits, success factors and challenges.

According to the review of literature related to LC and transparency, a well designed

questionnaire was developed. After consulting, modifying and reviewing by the

supervisor and experts, the final version of the questionnaire was established and

ready for distribution. The questionnaire was designed in both English and Arabic

languages in order to facilitate the understanding of content for the concerned

population sample. The questionnaire consisted of multiple choice (close-ended)

questions. Close-ended questions are more difficult to design than open-ended

questions; however they allow much more efficient data collection, processing and

analysis (Bourque, 2003). The rating scale (0-10) was used for data measurement in

which 0 is the lowest point and 10 is the highest point.

Table (3.1): Rating Scale for data measurement

Item Strongly Disagree

Strongly

agree

Scale 0 1 2 3 4 5 6 7 8 9 10

The researcher utilized the following procedures to develop the questionnaire:

The questionnaire was designed by the researcher, and was reviewed and

modified by the research's supervisor.

Page 59: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

42

The modified copy was given to a number of 5 academic referees from

different universities.

The questionnaire was then modified based on the referee's comments.

Next, a pilot study sample of 30 questionnaires was distributed to help test

the validity and reliability of the questionnaire; this provides a trial for the

questionnaire, which involves testing the wordings of questions, and

identifying ambiguous questions.

Based on the pilot phase findings, it was concluded that the questionnaire is

ready to be distributed as a final copy.

The first page in the questionnaire was a cover letter that explained the study

purpose, aim and the information security. While the questionnaire body divided into

five parts;

1. Organizational background of respondent.

This part aimed to give information about the position and years of

experiences of the respondent as well as the contracting company; its

location, size, years of experiences, and work field.

2. Evaluate factors of increasing transparency concept in Gaza Strip.

Increasing transparency concept has six main factors proposed by Koskela,

the master mind of LC, and agreed by many researchers. Therefore, this part

aimed to evaluate the current status of applying these factors in Gaza Strip as

well as the views of respondent's on the importance of these factors.

3. Evaluate LC tools for improving transparency.

Lean Construction approach involves many application tools, this part

examined factors of four main tools of LC that serve and assist in achieving

transparency; the degree of application in the current situation as well as the

importance of these tools and factors from the view of contracting companies

in Gaza Strip.

4. Investigate the effect of increasing transparency on application of LC

principles.

Lean Construction, also, has eleven criteria proposed by Koskela, this part

examined the two direction relationship between lean construction and

Page 60: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

43

transparency principle. The respondents gave their views on the importance

of transparency to facilitate the application of LC criteria.

5. Evaluate benefits, success factors and challenges of applying the concept of

increasing transparency.

The last but not least, this part studied benefits, success factors of

transparency and challenges facing the applicability of transparency principle

in Gaza Strip.

3.6 Questionnaire References

Part II: Evaluation of the current practices of transparency in

construction

Six practical approaches to increase process transparency (Transparency Principles)

proposed by Koskela (1992), the mastermind of Lean Construction.

Part III: Investigate the applicability of LC tools for transparency

This part involved four of lean construction tools that enhance transparency process;

each tool has many factors from different resources. The reference of each factor is

shown in the following Table (3.2).

Table (3.2): References of LC tools in the questionnaire

No. Lean Construction Tools Reference

1.

Seiri/Sort: Throw away all rubbish and unrelated materials, and

make sure that all broken stuff is in a special place. (No good and

bad stuff set together)

(Chi, 2011)

2.

Seiton/Straighten: Tools and materials were piled in a regular

pattern in the site store, and keep the orderliness of the store

content.

( Salem, et al., 2006)

3. Place devices and tools close to work areas in the site. ( Salem et al., 2006)

4. Place materials in the work place with consideration of safety and

crane movement. ( Salem et al., 2006)

5. Each subcontractor takes responsibility of tools and orneriness of

his work area. ( Salem et al., 2006)

6. Seiso/Shine: Hire sufficient numbers of cleaners who maintain the

cleanliness of the workplace permanently and continuously. Researcher

Page 61: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

44

No. Lean Construction Tools Reference

7. Everyone should be a janitor in the workplace as everyone cleans

his area after finishing the activity. (Nazir, 2012)

8.

Seiketsu/Standardize: Standardize the way of maintaining

cleanliness, and design a checklist to apply all standards of

cleanliness and required tidiness.

(Chi, 2011)

( Salem et al., 2006)

9. Shitsuke/Sustain: Maintain all previous practices daily throughout

the project and make it a way of life. "Commitment" ( Salem et al., 2006)

10.

Conducting a workshop for all employees to sign on a commitment

to comply with all safety and security requirements, and attach the

pledge to the caravan wall.

Researcher

11. Use colorful signage, especially for the application of security and

safety guidelines. (Salem et al., 2006)

12. Use billboards to explain the implementation of project stages and

the delivery dates. (Salem et al., 2006)

13. Calculate Plan Percent Complete (PPC) periodically and attach

results charts on the caravan walls. (Salem et al., 2006)

14. Weekly meeting of all foremen; to discuss the weekly plan and all

issues and potential problems. (Salem et al., 2006)

15. A quick day-to-day meeting of the project staff to discuss the work

carried out the day before and what is planned for the current day. (Salem et al., 2006)

16. Give information about the activities to affect workers' behavior

(without obliging). Ex: boards, charts, logs, photos, maps etc.

( Galsworth, 2004) and

(Tezel et al., 2008)

17. Grab workers' attention visually to give them a guide and obligate

them to follow. Ex: light boards and safety signage.

( Galsworth, 2004) and

(Tezel et al., 2008)

18.

Control workers' behaviors physically by determining how to work

correctly in compulsory way. Example: Set a border defines the

area of work.

( Galsworth, 2004) and

(Tezel et al., 2008)

19. Control processes electronically or mechanically to guarantee the

right response with zero risk.

( Galsworth, 2004) and

(Tezel et al., 2008)

Part IV:Investigate the effect of increasing transparency on LC

principles.

The eleven principles of lean construction were proposed by (Koskela, 1992).

Part V: Evaluate benefits, success factors and challenges of applying

the concept of increasing transparency.

The following tables (3.3), (3.4), and (3.5) show references of benefits, success

factors, and challenges respectively.

Page 62: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

45

Table (3.3): References of Benefits in the questionnaire

No. The Benefits Reference

1.

Save time spent in searching, wandering, or waiting

for the tools, materials, and information needed to do

work.

(Galsworth, 1997) and (Formoso et

al., 2002)

2. Increase the efficiency of workers as reduce wastage

in efforts. (Santos et al., 1998)

3. Increase the effectiveness of the production planning

and control process. (Formoso et al., 2002)

4. Increase the visibility of errors (Defects are more

visible and easier to recognize)

( Koskela, 1992) and (Formoso et al.,

2002) and (Igarashi, 1991)

5. Reduce the propensity to errors. ( Koskela, 1992) and (Formoso et al.,

2002)

6. Facilitate a holistic view of the entire process and to

implement flow. (Brady, 2014).

7. Build trust and motivation of participants. (Brady, 2014).

8. Support and involve workers at continuous

improvement. (Brady, 2014).

9. Stimulation of informal contact between the different

hierarchical positions. (Oliveira et al., 2012)

10. Contributions towards introducing decentralization

policies. (Oliveira et al., 2012)

11. Simplification of the production control systems. (Oliveira et al., 2012)

12. Reduce reworks that don't comply with drawings and

specifications.

Table (3.4): References of Success Factors in the questionnaire

No. Success Factors Reference

1. Establish strong management, structured and systematic plan

to implement visual systems. (Formoso et al., 2002)

2. Establish a visual mechanism to inspire or motivate workers

to carry out their jobs efficiency and effectively. (Formoso et al., 2002)

3.

Training and hands-on experience in order to make managers

fully knowledgeable about benefits of transparency principle

and its impact on production system.

(Formoso et al., 2002)

4. Forcing the reduction of inventories to some extent. (Igarashi, 1991) and

(Formoso et al., 2002)

5. Tightening production plans. (Igarashi, 1991) and

(Formoso et al., 2002)

6. Reducing process variability to facilitate the implementation

of visual control systems. (Formoso et al., 2002)

Page 63: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

46

Table (3.5): References of Challenges in the questionnaire

No. The Challenges Reference

1. Misunderstanding of Lean systems approach as

organizations tend to confuse “Lean thinking” with the

application of a tool or a set of tools in practice.

(Liker, 2004)

2. Lack of knowledge as managers are not aware of process

transparency benefits.

(Formoso et al., 2002)

3. Restrict to traditional conversion model and manager's fear

to changes into unknown approach to them.

(Brady, 2014).

4. Difficulties in communication in construction. (Brady, 2014).

5. Changeable work environment as site layout modified

several times throughout the project.

(Formoso et al., 2002)

6. Large place of work site where large numbers of crews

spread out and move continuously.

(Formoso et al., 2002)

7. Low level of participation of workers in improvement

process.

(Formoso et al., 2002)

Refer to Appendix I and Appendix II for the final questionnaire design in English and

Arabic respectively.

3.7 Questionnaire Content Validity

The content validity of the questionnaire was conducted through the supervisor

review in order to assure that the content is consistent with the research objectives,

and evaluate whether the questions reflect the research problem or not. Besides that,

5professional engineers have academic background reviewed the questionnaire and

provided valuable notes to improve its validity so that their comments were taken

into consideration. Each expert got a copy of the questionnaire for revision, each

expert developed his own notes for modification and some notes were confirmed by

more than one expert. Each note was carefully considered in preparing the final

questionnaire. Table (3.6) shows in details notes gathered from experts.

Page 64: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

47

Table (3.6): Notes gathered from the consultants

No. Specialization Notes gathered from experts

Expert A PhD Construction Engineering,

University of Cambridge, UK.

- Add examples for transparency factors to

allow more understanding. (Done)

- Many notes involved wording of the

questions. (Done)

- Suggested to put the company profile section

at the end of the questionnaire. (Ignored)

Expert B PhD Construction Engineering,

UK

- Many notes involved wording of the

questions. (Done)

- Summarize some questions and delete

unnecessary sentences. (Done)

Expert C

M.Sc. Water Engineering

Management, Brunel

University, UK.

- Rearrange sections of questionnaire and make

the section of transparency factors the second

section after company profile, so that allow

the respondent to understand the approach

well before assessing the benefits and

challenges. (Done)

Expert D

M.Sc. Construction

Management, Islamic

University of Gaza, Palestine

- Make separate section for the effect of LC

tools on transparency rather than merging it

with success factors. (Done)

- Merge many factors in one question as they

could have the same meaning. (Done)

Expert E PhD Statistics, Islamic

University of Gaza, Palestine.

- Change the measuring scale from (low,

medium or high) to point's scale from 0 to10

for more accurate results. (Done)

- Rebuilding of questionnaire based on the new

understanding of hypothesis and relations

between questionnaire sections. (Done)

3.8 Pilot Study

In order to test the appropriateness, validity and reliability of the questionnaire

before committing to the complete sample population, a pilot study for the

questionnaire was conducted. It provides a trial run for the questionnaire, which

involves testing the wordings of question, identifying ambiguous questions, testing

the techniques that used to collect data, and measuring the effectiveness of standard

deviation to respondents. The questionnaire was conducted to limited group of the

targeted population by distributing the questionnaire conveniently to 30 respondents

selected randomly.

Page 65: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

48

After the researcher collected the 30 questionnaire data analyzed using SPSS (24) in

order to test the validity and the reliability of the questionnaire. The validity tested

using Pearson correlation coefficient for both criterion and structural validity of the

questionnaire. However, the reliability tested using Cronbach‟s Alpha Coefficient.

3.8.1 Questionnaire Validity

Validity refers to the degree to which an instrument measures what it is supposed

to be measuring. Validity has a number of different aspects and assessment

approaches. Statistical validity is used to evaluate instrument validity, which include

internal validity and structure validity.

3.8.1.1 Internal Validity

Internal validity of the questionnaire is the first statistical test that used to test the

validity of the questionnaire. It is measured by a scouting sample, which consisted of

30 questionnaires through measuring the correlation coefficients between each item

in one field and the whole field.

Table (3.7) clarifies the correlation coefficient for each item of the "Transparency

Factors" and the total of the section. The p-values (Sig.) are less than 0.05, so the

correlation coefficients of this section are significant at α = 0.05, so it can be said

that items of this section are consistent and valid to be measure what it was set for.

Table (3.7): Correlation coefficient of each item of "Transparency Factors" and the

total of this section

No. Item

Degree of application Degree of importance

Correlation

Coefficient

P-Value

(Sig.)

Correlation

Coefficient

P-Value

(Sig.)

1.

Reducing the interdependence of

project activities in time,

materials, and work area.

.386 0.008 .601 0.000

2.

Utilizing visual devices to

immediately recognize mistakes

and problems. Ex. Andon

system: light board to notify the

management to any problem

immediately as lacks in

materials.

.518 0.000 .792 0.000

Page 66: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

49

No. Item

Degree of application Degree of importance

Correlation

Coefficient

P-Value

(Sig.)

Correlation

Coefficient

P-Value

(Sig.)

3.

Making the process visible and

observable by appropriate site

layout, visible fencing, signage

for safety equipment location,

good lighting.

.732 0.000 .384 0.008

4.

Incorporating information in the

work place about project

activities by display boards,

statistics, or videos.

.623 0.000 .725 0.000

5.

Establishing basic housekeeping

to eliminate clutter, maintaining

orderly and clean workplace.

.701 0.000 .429 0.003

6.

Using measurements to reveal

the work quality and efficiency.

Ex: Measurements for

performance indicators,

completion and delay

percentage.

.629 0.000 .366 0.011

The following Table (3.8) clarifies the correlation coefficient for each item of the

"Lean Construction Tools" and the total of the section. The p-values (Sig.) are less

than 0.05, so the correlation coefficients of this section are significant at α = 0.05, so

it can be said that the items of this section are consistent and valid to measure what it

was set for.

Table (3.8): Correlation coefficient of "Lean Construction Tools" items and its total

No. Item

Degree of application Degree of

importance

Correlation

Coefficient

P-

Value

(Sig.)

Correlation

Coefficient

P-

Value

(Sig.)

Applying 5 S tool (Sort – Straighten – Shine – Standardize - Sustain(

1.

Seiri/Sort: Throw away all rubbish and

unrelated materials, and make sure that all

broken stuff is in a special place. (No good

and bad stuff set together)

.687 0.000 .767 0.000

2.

Seiton/Straighten: Tools and materials were

piled in a regular pattern in the site store, and

keep the orderliness of the store content.

.781 0.000 .799 0.000

3. Place devices and tools close to work areas in

the site. .642 0.000 .684 0.000

4. Place materials in the work place with

consideration of safety and crane movement. .684 0.000 .664 0.000

Page 67: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

50

5. Each subcontractor takes responsibility of

tools and orneriness of his work area. .576 0.000 .595 0.000

6.

Seiso/Shine: Hire sufficient numbers of

cleaners who maintain the cleanliness of the

workplace permanently and continuously.

.769 0.000 .878 0.000

7.

Everyone should be a janitor in the

workplace as everyone cleans his area after

finishing the activity.

.705 0.000 .849 0.000

8.

Seiketsu/Standardize: Standardize the way of

maintaining cleanliness, and design a

checklist to apply all standards of cleanliness

and required tidiness.

.566 0.000 .474 0.001

9.

Shitsuke/Sustain: Maintain all previous

practices daily throughout the project and

make it a way of life. "Commitment"

.718 0.000 .679 0.000

Applying Increased Visualization tool

10.

Conducting a workshop for all employees to

sign on a commitment to comply with all

safety and security requirements, and attach

the pledge to the caravan wall.

.802 0.000 .834 0.000

11. Use colorful signage, especially for the

application of security and safety guidelines. .781 0.000 .727 0.000

12. Use billboards to explain the implementation

of project stages and the delivery dates. .842 0.000 .717 0.000

13.

Calculate Plan Percent Complete (PPC)

periodically and attach results charts on the

caravan walls.

.655 0.000 .693 0.000

Applying Huddle Meeting tool

14.

Weekly meeting of all foremen; to discuss

the weekly plan and all issues and potential

problems.

.867 0.000 .918 0.000

15.

A quick day-to-day meeting of the project

staff to discuss the work carried out the day

before and what is planned for the current

day.

.877 0.000 .913 0.000

Applying Visual Management

16.

Give information about the activities to affect

workers' behavior (without obliging). Ex:

boards, charts, logs, photos, maps etc.

.850 0.000 .787 0.000

17.

Grab workers' attention visually to give them

a guide and obligate them to follow. Ex: light

boards and safety signage.

.872 0.000 .855 0.000

18.

Control workers' behaviors physically by

determining how to work correctly in

compulsory way. Example: Set a border

defines the area of work.

.606 0.000 .725 0.000

19.

Control processes electronically or

mechanically to guarantee the right response

with zero risk.

.823 0.000 .670 0.000

Page 68: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

51

The following table (3.9) clarifies the correlation coefficient for each item of the "LC

Principles" and the total of the section. The p-values (Sig.) are less than 0.05, so the

correlation coefficients of this section are significant at α = 0.05, so it can be said that

the items of this section are consistent and valid to be measure what it was set for.

Table 3.9: Correlation coefficient of each item of "LC Principles" and its total

No. Item

Pearson

Correlation

Coefficient

P-Value

(Sig.)

1. Reduce of non-value-adding activities. .716 0.000

2. Increase output value through systematic

consideration of customer requirements. .666 0.000

3. Reduce project variability. .342 0.015

4. Reduce project cycle time. .712 0.000

5. Simplify by minimizing the number of steps,

parts and linkages between activities. .740 0.000

6. Increase flexibility in work and output. .752 0.000

7. Focus control on the complete process. .731 0.000

8. Build continuous improvement into the

process. .741 0.000

9. Balance flow improvement with conversion

improvement. .688 0.000

10. Conduct reference studies, and lesson learnt

(Benchmarking) .702 0.000

The following table (3.10) clarifies the correlation coefficient for each item of the

"The Benefits" and the total of the section. The p-values (Sig.) are less than 0.05, so

the correlation coefficients of this field are significant at α = 0.05, so it can be said

that the items of this field are consistent and valid to be measure what it was set for.

Table (3.10): Correlation coefficient of each item of "The Benefits" and its total

No. Item

Pearson

Correlation

Coefficient

P-Value

(Sig.)

1.

Save time spent in searching, wandering, or waiting

for the tools, materials, and information needed to do

work.

.563 0.000

2. Increase the efficiency of workers as reduce wastage

in efforts. .586 0.000

Page 69: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

52

3. Increase the effectiveness of the production planning

and control process. .699 0.000

4. Increase the visibility of errors (Defects are more

visible and easier to recognize) .578 0.000

5. Reduce the propensity to errors. .620 0.000

6. Facilitate a holistic view of the entire process and to

implement flow. .749 0.000

7. Build trust and motivation of participants. .707 0.000

8. Support and involve workers at continuous

improvement. .753 0.000

9. Stimulation of informal contact between the different

hierarchical positions. .497 0.001

10. Contributions towards introducing decentralization

policies. .475 0.001

11. Simplification of the production control systems. .425 0.000

12. Reduce reworks that don't comply with drawings and

specifications. .556 0.000

The following table (3.11) clarifies the correlation coefficient for each item of the

"SuccessFactors"and the total of the section. The p-values (Sig.) are less than 0.05,

so the correlation coefficients of this section are significant at α = 0.05, so it can be

said that the items of this field are consistent and valid to be measure what it was set

for.

Table (3.11): Correlation coefficient of each item of "Success Factors" and its total

No. Item

Pearson

Correlation

Coefficient

P-Value

(Sig.)

1. Establish strong management, structured and systematic

plan to implement visual systems. .673 0.000

2. Establish a visual mechanism to inspire or motivate workers

to carry out their jobs efficiency and effectively. .814 0.000

3.

Training and hands-on experience in order to make

managers fully knowledgeable about benefits of

transparency principle and its impact on production system.

.826 0.000

4. Forcing the reduction of inventories to some extent. .505 0.000

5. Tightening production plans. .590 0.000

6. Reducing process variability to facilitate the implementation

of visual control systems. .838 0.000

Page 70: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

53

The following table (3.12) clarifies the correlation coefficient for each item of the

"The Challenges" and the total of the section. The p-values (Sig.) are less than 0.05,

so the correlation coefficients are significant at α = 0.05, so it can be said that the

items of this section are consistent and valid to be measure what it was set for.

Table (3.12): Correlation coefficient of each item of "The Challenges" and its total

No. Item

Pearson

Correlation

Coefficient

P-Value

(Sig.)

1.

Misunderstanding of Lean systems approach as organizations

tend to confuse “Lean thinking” with the application of tools

in practice.

.671 0.000

2. Lack of knowledge as managers are not aware of transparency

benefits. .726 0.000

3. Restrict to traditional conversion model and manager's fear to

changes into unknown approach to them. .708 0.000

4. Difficulties in communication in construction. .667 0.000

5. Changeable work environment as site layout modified several

times throughout the project. .796 0.000

6. Large place of work site where large numbers of crews spread

out and move continuously. .731 0.000

7. Low level of participation of workers in improvement

process. .464 0.001

3.8.1.2 Structure Validity

Structure validity is the second statistical test that used to test the validity of the

questionnaire structure by testing the validity of each section and the validity of the

whole questionnaire. It measures the correlation coefficient between one section and

all section of the questionnaire that have the same level of liker scale.

Table (3.13) clarifies the correlation coefficient for each section and the whole

questionnaire. The p-values (Sig.) are less than 0.05, so the correlation coefficients of

all sections are significant at α = 0.05, so it can be said that all the questionnaire

sections are valid to be measured what it was set for to achieve the main aim of the

study.

Page 71: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

54

Table (3.13): Correlation coefficient of each field and the whole of questionnaire

No. Field

Pearson

Correlation

Coefficient

P-Value

(Sig.)

1. Transparency Factors- Degree of application .603 0.000

2. Transparency Factors- Degree of importance .666 0.000

3. Applying 5 S tool (Sort – Straighten – Shine –

Standardize Sustain(- Degree of application .917 0.000

4. Applying Increased Visualization tool-

Degree of application .858 0.000

5. Applying Huddle Meeting tool- Degree of

application .779 0.000

6. Applying Visual Management- Degree of application .882 0.000

7. Lean Construction Tools - Degree of application .779 0.000

8. Applying 5 S tool (Sort – Straighten – Shine –

Standardize Sustain(- Degree of importance .942 0.000

9. Applying Increased Visualization tool- Degree of

importance .746 0.000

10. Applying Huddle Meeting tool- Degree of

importance .644 0.000

11. Applying Visual Management- Degree of importance .814 0.000

12. Lean Construction Tools - Degree of importance .727 0.000

13. LC Principles .693 0.000

14. The Benefits .832 0.000

15. Success Factors .748 0.000

16. The Challenges .706 0.000

3.8.2 Questionnaire Reliability

The reliability of an instrument is the degree of consistency which measures the

attribute; it is supposed to be measuring (George and Mallery, 2006). The less

variation the instrument produces in repeated measurements of an attribute, the

higher its reliability. Reliability can be equated with the stability, consistency, or

dependability of a measuring tool. The test is repeated to the same sample of people

on two occasions and then compares the scores obtained by computing a reliability

coefficient (George and Mallery, 2006). To insure the reliability of the questionnaire,

Cronbach‟s Coefficient Alpha should be applied.

Page 72: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

55

Cronbach’s Coefficient Alpha

Cronbach‟s alpha (George D. and Mallery P, 2006) is designed as a measure of

internal consistency. The normal range of Cronbach‟s coefficient alpha value

between 0.0 and + 1.0, and the higher values reflects a higher degree of internal

consistency. The Cronbach‟s coefficient alpha was calculated for each section of the

questionnaire.

Table (3.14) shows values of Cronbach's Alpha for each section of the questionnaire

and the entire questionnaire. For the questionnaire sections, values of Cronbach's

Alpha were in the range from 0.583 and 0.919. This range is considered high; the

result ensures the reliability of each field of the questionnaire. Cronbach's Alpha

equals 0.949 for the entire questionnaire which indicates an excellent reliability of

the entire questionnaire.

Table (3.14): Cronbach's Alpha for each field of the questionnaire

No. Field Cronbach's Alpha

1. Transparency Factors- Degree of application 0.638

2. Transparency Factors- Degree of importance 0.583

3. Lean Construction Tools - Degree of application 0.919

4. Lean Construction Tools - Degree of importance 0.915

5. LC Principles 0.872

6. The Benefits 0.828

7. Success Factors 0.802

8. The Challenges 0.804

9. All items of the questionnaire 0.949

Therefore, it can be said that the researcher proved that the questionnaire was valid,

reliable, and ready for distribution for the population sample.

3.8.3 Questionnaire Normality

Table (3.15) shows results for Kolmogorov-Smirnov test of normality. The p-

value for each variable is greater than 0.05 level of significance, and then the

distributions for these variables are normally distributed. Consequently, parametric

tests should be used to perform the statistical data analysis.

Page 73: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

56

Table (3.15): Kolmogorov-Smirnov test

Field Kolmogorov-Smirnov

Statistic P-value

Transparency Factors- Degree of application 0.676 0.750

Transparency Factors- Degree of importance 0.563 0.909

Lean Construction Tools - Degree of application 0.434 0.992

Lean Construction Tools - Degree of importance 0.866 0.441

LC Principles 0.870 0.435

The Benefits 0.564 0.909

Success Factors 0.844 0.474

The Challenges 0.800 0.544

All items of the questionnaire 0.464 0.983

3.9 Statistical Analysis Tools

The researcher used data analysis both qualitative and quantitative data analysis

methods in this research. The Data analysis made utilizing (SPSS 24). The researcher

utilized the following statistical tools:

1. Kolmogorov-Smirnov test of normality.

2. Pearson correlation coefficient for Validity.

3. Cronbach's Alpha for Reliability Statistics.

4. Frequency and Descriptive analysis.

5. One-sample T test.

6. Independent Samples T-test.

7. Analysis of Variance.

Summary

This chapter described in detail the adopted methodology of research. It included

the primary research framework for the study, details of research period, location,

population, and sample size. The questionnaire design was detailed including the

modifications and reviews done through experts' consultation. Quantitative data

analysis techniques, which include validity tests, reliability test, normality test and

Pearson correlation analysis, were designed to be applied by the instrument of SPSS

and explained in details.

Page 74: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

57

Chapter 4

Results and Data

Analysis

Page 75: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

58

Chapter 4: Data Analysis and Results

This chapter includes analysis and discussion of the results that have been

collected from field surveys. Data was analyzed using SPSS including descriptive

and inferential statistical tools. In this study, total of a hundred and thirty

questionnaires respondents from the study sample were considered. This chapter

includes quantitative analysis of questionnaire field survey for each section in the

questionnaire.

4.1 Data Analysis of Questionnaire Sections

4.1.1 Organizational Background of Respondent

This section designed to understand the background of respondents and

contracting companies, in order to study the impact of company profile on their

transparency practices. Table (4.1) shows the classification of contracting companies.

Table (4.2): Classification of Contracting Company

Work field First Class Second Class Third Class

N % N % N %

Building 95 74.8 23 18.1 9 7.1

Roads 63 56.3 28 25.0 21 18.8

Water and Sewer 64 57.1 28 25.0 20 17.9

Electro-mechanic 55 50.0 29 26.4 26 23.6

Results in Table (4.2) shows that majority of respondents (83.1%) are site engineers

and project managers who work in the field and have good experiences in practical

construction. About half of respondents have experience years from 5 to less than 10

years while 22.3% have less than 5 years experiences.

Most of companies who filled the questionnaires are from Gaza and the South

governorates; however the response level from Middle Area and the North

governorates were the least. Two-thirds of companies have experiences 10 years and

more, one-fifth of them have experiences 5 to less than 10 years while others have

less than 5 years experiences. So that the responds have good variety to examine the

Page 76: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

59

effect of experience years on transparency practices. The same at the size of

companies (number of employees, number of projects, and annual budget); results

distributed on different categories so that allowed diverse in respondents.

Table (4.2): Organizational background of respondent (N=130)

No. Organizational background of respondent Frequency Percent

1.

Job title

Company director 8 6.2

Project manager 40 30.8

Site engineer 68 52.3

Office engineer 14 10.8

2.

Years of respondent experience

Less than 5 years 29 22.3

5 – less than 10 years 64 49.2

10 – less than 20 years 33 25.4

20 years, and above 4 3.1

3.

The place of company office

(Governorate)

The South 31 23.8

The Middle area 9 6.9

Gaza 83 63.8

The North 7 5.4

4.

Years of company experience

Less than 5 years 23 17.7

5 – less than 10 years 24 18.5

10 – less than 20 years 39 30.0

20 years, and above 44 33.8

5.

Number of permanent employees

Less than 5 employees 13 10.0

5 - 10 employees 47 36.2

11 - 20 employees 43 33.1

Over 20 employees 27 20.8

6.

Number of projects implemented

in the last 5 years

Less than 10 projects 34 26.2

10 – 20 projects 54 41.5

21 - 30 projects 16 12.3

Over 30 projects 26 20.0

7.

Annual average value of projects

in the last 5 years

(U.S. $)

Less than 1 M 17 13.1

1 M – less than 5 M 45 34.6

5 M - less than 10 M$ 36 27.7

10 M, and over 32 24.6

8. The respondent degree of

knowledge of LC approach, and

familiarity with the concept and

tools

High 20 15.4

Medium 71 54.6

poor 30 23.1

None 9 6.9

Page 77: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

60

Last question at Organizational background aimed to test the general knowledge of

respondents to lean construction approach. Figure (4.1) show the respondents

percentages on the degree of knowledge of LC approach, and familiarity with the

concept and tools.

Figure (4.1): Familiarity of respondents to LC Approach

4.1.2 Transparency Factors

This section of questionnaire aimed to evaluate factors of increasing transparency

concept to investigate the current condition of transparency practices in construction

projects in Gaza Strip and the contracting company's attitude toward the principle.

Respondents scored the degree of application of the six transparency factors in

construction projects. Obtained results show that the mean value of the

“Transparency Factors- Degree of application” equals 6.11 (61.08%), Test-value =

8.09, and P-value =0.000 which is smaller than the level of significance 0.05 .

The sign of the test is positive, so the mean of this field is significantly greater than

the hypothesized value 5.It was concluded that the respondents agreed to the section

“Transparency Factors- Degree of application”.

The factor no.5 (Establishing basic housekeeping to eliminate clutter, maintaining

orderly and clean workplace) obtained the highest degree of application which is

0

10

20

30

40

50

60

High Medium poor None

Pe

rce

nta

ge (%

)

Familiarity of Respondents to LC Approach

Page 78: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

61

72.17%, and factor no.3 (Making the process visible and observable) get the second

degree, while the factor no.2 (Utilizing visual devices to immediately recognize

mistakes and problems) obtained the lowest degree of application that is 44.88%.

Ranking of the transparency factors, in terms of the degree of current application,

shows in the following Table (4.3).

Table (4.3): Means and Test values for “Transparency Factors- Degree of

application”

No. Item

Degree of application

Mean (%) Test

value

P-

value Rank

1.

Reducing the interdependence of project

activities in time, materials, and work

area.

6.10 60.97 5.73 0.000 4

2.

Utilizing visual devices to immediately

recognize mistakes and problems. Ex.

Andon system: light board to notify the

management to any problem immediately

as lacks in materials.

4.49 44.88 -2.06 0.021 6

3.

Making the process visible and

observable by appropriate site layout,

visible fencing, signage for safety

equipment location, good lighting.

6.90 68.99 9.17 0.000 2

4.

Incorporating information in the work

place about project activities by display

boards, statistics, or videos.

5.17 51.71 0.71 0.239 5

5.

Establishing basic housekeeping to

eliminate clutter, maintaining orderly and

clean workplace.

7.22 72.17 12.33 0.000 1

6.

Using measurements to reveal the work

quality and efficiency. Ex: Measurements

for performance indicators, completion

and delay percentage.

6.67 66.74 8.54 0.000 3

All items of the field. 6.11 61.08 8.09 0.000

Also, respondents evaluated "Transparency Factors- Degree of importance" to find

out their views on the importance of increasing transparency principle in

construction. The mean of this field equals 7.81 (78.14%), Test-value = 23.26, and P-

value=0.000 which is smaller than the level of significance 0.05 .

Page 79: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

62

The sign of the test is positive, so the mean of this field is significantly greater than

the hypothesized value 5. It was concluded that the respondents agreed to field of

"Transparency Factors- Degree of importance".

The factor no.5 (Establishing basic housekeeping to eliminate clutter, maintaining

orderly and clean workplace) obtained the highest degree of importance that is

88.06%, and factor no.3 (Making the process visible and observable) get the second

degree while the factor no.3 (Utilizing visual devices to immediately recognize

mistakes and problems) obtained the lowest degree of importance that is 69.76%.

Ranking of transparency factors in terms of importance is shown in the following

Table (4.4).

Table (4.4): Means and Test values “Transparency Factors - Degree of importance”

No. Item

Degree of importance

Mea

n (%)

Test

value

P-

value

Ran

k

1. Reducing the interdependence of project

activities in time, materials, and work area. 7.31 73.06 12.79 0.000 4

2.

Utilizing visual devices to immediately

recognize mistakes and problems. Ex. Andon

system: light board to notify the management to

any problem immediately as lacks in materials.

6.98 69.76 9.39 0.000 6

3.

Making the process visible and observable by

appropriate site layout, visible fencing, signage

for safety equipment location, good lighting.

8.26 82.64 18.27 0.000 2

4.

Incorporating information in the work place

about project activities by display boards,

statistics, or videos.

7.20 71.95 10.69 0.000 5

5.

Establishing basic housekeeping to eliminate

clutter, maintaining orderly and clean

workplace.

8.81 88.06 30.09 0.000 1

6.

Using measurements to reveal the work quality

and efficiency. Ex: Measurements for

performance indicators, completion and delay

percentage.

8.24 82.40 18.74 0.000 3

All items of the field 7.81 78.14 23.26 0.000

From the previous results, it was noticed that ranking of transparency factors in terms

of importance and current application is the same which means the contracting

companies have a concern to apply what they believe in its importance for project

management.

Page 80: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

63

However, figure (4.2) shows that the importance of all transparency factors were

given higher degrees than its current application, which means the respondents

believe that the transparency principle still needs to be enhanced in construction

projects.

Figure (4.2): Degrees of Importance and Application of Transparency Factors

4.1.3 Lean Construction Tools

This section of questionnaire aimed to evaluate LC tools for improving

transparency. Respondents scored degrees of application and importance of LC tools

for increasing transparency principle in construction projects.

Applying 5S tool (Sort – Straighten – Shine – Standardize–Sustain)

For the degree of application; the mean of the field "Applying 5S tool" equals 6.70

(67.04%), Test-value = 11.66, and P-value=0.000 which is smaller than the level of

significance 0.05 . The sign of the test is positive, so the mean of this field is

significantly greater than the hypothesized value 5.It was concluded that the

respondents agreed to the field. Detailed results are shown in table (4.5).

For the degree of importance; the mean of the field “Applying 5 S tool" equals 8.29

(82.91%), Test-value = 29.41, and P-value=0.000 which is smaller than the level of

significance 0.05 .

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6

Pe

rce

nta

ge (%

)

No. of Transparency Factors

Degree of Importance

Degree of Application

Page 81: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

64

The sign of the test is positive, so the mean of this field is significantly greater than

the hypothesized value 5. It was concluded that the respondents agreed to the field.

Detailed results are shown in Table (4.6).

As shown in Figure (4.3); 5S tool involves five factors, "Straighten" and "Sort"

factors obtained highest degree of application while "Standardize" obtained the

lowest degree of application in the construction companies in Gaza Strip. On the

other hand, "Straighten" and "Sustain" factors obtained the highest degree of

importance while the factor "Standardize" obtained the lowest degree of importance

however it is still significant (77.75%).

Figure (4.3): Degrees of Importance and Application of "5S tool" Factors

Applying Increased Visualization tool

For the degree of application as shown in table (4.5); the mean of the field

“Applying Increased Visualization tool” equals 6.06 (60.61%), Test-value = 5.25,

and P-value=0.000 which is smaller than the level of significance 0.05 . The sign

of the test is positive, so the mean of this field is significantly greater than the

hypothesized value 5.It was concluded that the respondents agreed to the field.

0

10

20

30

40

50

60

70

80

90

Sort Straighten Shine Standardize Sustain

Per

cen

tage

(%)

Factors of 5S tool

Degree of Importance

Degree of Application

Page 82: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

65

The item (Use billboards to explain the implementation of project stages and the

delivery dates) obtained the highest degree of application that is 65.74%, while the

item (Conducting a workshop for all employees to sign on a commitment to comply

with all safety and security requirements, and attach the pledge to the caravan wall)

obtained the lowest degree of application that was 50.16%.

For the degree of importance as shown in Table (4.6); the mean of the field

“Applying Increased Visualization tool” equals 8.22 (82.23%), Test-value = 25.22,

and P-value=0.000 which is smaller than the level of significance 0.05 . The sign

of the test is positive, so the mean of this field is significantly greater than the

hypothesized value 5.It was concluded that the respondents agreed to the field.

The item (Use colorful signage, especially for the application of security and safety

guidelines) obtained the highest degree of importance that is 86.90%, while the item

(Calculate Plan Percent Complete –PPC- periodically and attach results charts on the

caravan walls) obtained the lowest degree of importance that is 79.22%.

Applying Huddle Meeting tool

For the degree of application as shown in Table (4.5); the mean of the field

“Applying Huddle Meeting tool” equals 6.23 (62.29%), Test-value = 5.19, and P-

value=0.000 which is smaller than the level of significance 0.05 . The sign of the

test is positive, so the mean of this field is significantly greater than the hypothesized

value 5.It was concluded that the respondents agreed to the field.

For the degree of importance as shown in Table (4.6); the mean of the field

“Applying Huddle Meeting tool” equals 8.33 (83.26%), Test-value = 19.86, and P-

value=0.000 which is smaller than the level of significance 0.05 . The sign of the

test is positive, so the mean of this field is significantly greater than the hypothesized

value 5.It was concluded that the respondents agreed to the field.

As shown in Figure (4.5); "Weekly meeting of all foremen" was given a higher

degree of application but less degree of importance than the "Quick day-to-day

meeting". Generally, degrees of importance are higher than degrees of application,

Page 83: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

66

indicating that respondents believe that applying huddle meetings need to be

enhanced in construction projects.

Figure (4.4): Degrees of Importance and Application of Huddle Meetings

Applying Visual Management

For the degree of application as shown in Table (4.5); the mean of the field

“Applying Visual Management” equals 5.36 (53.60%), Test-value = 1.86, and P-

value=0.032 which is smaller than the level of significance 0.05 . The sign of the

test is positive, so the mean of this field is significantly greater than the hypothesized

value 5.It was concluded that the respondents agreed to the field.

The item (Control workers' behaviors physically by determining how to work

correctly in compulsory way) obtained the highest degree of application that is

64.19%, while the item (Give information about the activities to affect workers'

behavior) obtained the lowest degree of approval that was 47.75%.

For the degree of importance as shown in Table (4.6); the mean of the field

“Applying Visual Management” equals 7.28 (72.77%), Test-value = 15.12, and P-

value=0.000 which is smaller than the level of significance 0.05 . The sign of the

test is positive, so the mean of this field is significantly greater than the hypothesized

value 5.It was concluded that the respondents agreed to the field.

82.71 83.8

62.64 61.94

0

10

20

30

40

50

60

70

80

90

100

Weekly meeting Daily meeting

Pe

rce

nta

ge (%

)

Degree of Importance

Degree of Application

Page 84: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

67

The item (Control workers' behaviors physically by determining how to work

correctly in compulsory way) obtained the highest degree of importance that is

76.74%, while the item (Control processes electronically or mechanically to

guarantee the right response with zero risk) obtained the lowest degree of importance

that is 69.69%.

Table (4.5): Means and Test value “Lean Construction Tools-Degree of application”

No. Item

Degree of application

Mean (%) Test

value

P-

value

Factors

Rank

Tools

Rank

1.

Sort: Throw away all rubbish and unrelated

materials, and make sure that all broken stuff is

in a special place.

7.12 71.24 10.42 0.000 4

2.

Straighten: Tools and materials were piled in a

regular pattern in the site store, and keep the

orderliness of the store content.

6.93 69.30 9.74 0.000 5

3. Place devices and tools close to work areas in

the site. 7.38 73.80 14.74 0.000 1

4. Place materials in the work place with

consideration of safety and crane movement. 7.36 73.57 14.78 0.000 2

5. Each subcontractor takes responsibility of tools

and orneriness of his work area. 7.26 72.56 13.14 0.000 3

6.

Seiso/Shine: Hire sufficient numbers of

cleaners who maintain the cleanliness of the

workplace permanently and continuously.

6.09 60.93 4.73 0.000 7

7. Everyone should be a janitor in the workplace

and cleans his area after finishing the activity. 5.98 59.84 4.51 0.000 8

8.

Standardize: Standardize the way of

maintaining cleanliness, and design a checklist

to apply all standards of cleanliness and

required tidiness.

5.74 57.36 3.06 0.001 9

9.

Sustain: Maintain all previous practices daily

throughout the project and make it a way of

life. "Commitment"

6.47 64.73 7.17 0.000 6

Total of Applying 5 S tool 6.70 67.04 11.66 0.000 1

10.

Conducting a workshop for all employees to

sign on a commitment to comply with all safety

and security requirements, and attach the

pledge to the caravan wall.

5.02 50.16 0.06 0.477 4

11. Use colorful signage, especially for the

application of security and safety guidelines. 6.38 63.80 5.29 0.000 2

12. Use billboards to explain the implementation of

project stages and the delivery dates. 6.57 65.74 6.24 0.000 1

13. Calculate Plan Percent Complete periodically

and attach results charts on the caravan walls. 6.16 61.55 4.53 0.000 3

Total of Applying Increased Visualization tool 6.06 60.61 5.25 0.000 3

Page 85: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

68

No. Item

Degree of application

Mean (%) Test

value

P-

value

Factors

Rank

Tools

Rank

14.

Weekly meeting of all foremen; to discuss the

weekly plan and all issues and potential

problems.

6.26 62.64 4.92 0.000 1

15.

A quick day-to-day meeting of the project staff

to discuss the work carried out the day before

and what is planned for the current day.

6.19 61.94 4.45 0.000 2

Total of Applying Huddle Meeting tool 6.23 62.29 5.19 0.000 2

16.

Give information about the activities to affect

workers' behavior (without obliging). Ex:

boards, charts, logs, photos, maps etc.

4.78 47.75 -0.91 0.182 4

17.

Grab workers' attention visually to give them a

guide and obligate them to follow. Ex: light

boards and safety signage.

4.91 49.07 -0.37 0.357 3

18.

Control workers' behaviors physically by

determining how to work correctly in

compulsory way. Example: Set a border defines

the area of work.

6.42 64.19 6.25 0.000 1

19.

Control processes electronically or

mechanically to guarantee the right response

with zero risk.

5.32 53.20 1.29 0.099 2

Total of Applying Visual Management 5.36 53.60 1.86 0.032 4

All items of the field 6.24 62.36 7.92 0.000

Table (4.6): Means and Test value “Lean Construction Tools-Degree of Importance”

No Item

Degree of importance

Mean (%) Test

value

P-

value

Factors

Rank

Tools

Rank

1. Sort: Throw away all rubbish and unrelated

materials. 8.32 83.18 18.73 0.000 5

2.

Straighten: Tools and materials were piled in

a regular pattern in the site store, and keep

the orderliness of the store content.

8.26 82.64 18.55 0.000 6

3. Place devices and tools close to work areas

in the site. 8.50 85.04 27.09 0.000 2

4. Place materials in the work place with

consideration of safety and crane movement. 8.73 87.29 28.06 0.000 1

5. Each subcontractor takes responsibility of

tools and orneriness of his work area. 8.45 84.50 24.94 0.000 3

6.

Shine: Hire sufficient numbers of cleaners

who maintain the cleanliness of the

workplace permanently and continuously.

7.96 79.61 16.36 0.000 8

7.

Everyone should be a janitor in the

workplace and cleans his area after finishing

the activity.

8.17 81.71 21.00 0.000 7

Page 86: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

69

No Item

Degree of importance

Mean (%) Test

value

P-

value

Factors

Rank

Tools

Rank

8.

Standardize: Standardize the way of

maintaining cleanliness, and design a

checklist to apply all standards of cleanliness

and required tidiness.

7.78 77.75 14.83 0.000 9

9.

Sustain: Maintain all previous practices daily

throughout the project and make it a way of

life. "Commitment"

8.44 84.42 24.35 0.000 4

Total of Applying 5 S tool 8.29 82.91 29.41 0.000 2

10.

Conducting a workshop for all employees to

sign on a commitment to comply with all

safety and security requirements, and attach

the pledge to the caravan wall.

8.06 80.64 14.14 0.000 3

11. Use colorful signage, especially for the

application of security and safety guidelines. 8.69 86.90 24.08 0.000 1

12. Use billboards to explain the implementation

of project stages and the delivery dates. 8.19 81.94 19.93 0.000 2

13.

Calculate Plan Percent Complete (PPC)

periodically and attach results charts on the

caravan walls.

7.92 79.22 16.54 0.000 4

Total of Applying Increased Visualization

tool 8.22 82.23 25.22 0.000

3

14.

Weekly meeting of all foremen; to discuss

the weekly plan and all issues and potential

problems.

8.27 82.71 17.34 0.000 2

15.

A quick day-to-day meeting of the project

staff to discuss the work carried out the day

before and what is planned for the current

day.

8.38 83.80 19.04 0.000 1

Total of Applying Huddle Meeting tool 8.33 83.26 19.86 0.000 1

16.

Give information about the activities to

affect workers' behavior (without obliging).

Ex: boards, charts, logs, photos, maps etc.

7.21 72.09 12.76 0.000 3

17.

Grab workers' attention visually to give them

a guide and obligate them to follow. Ex:

light boards and safety signage.

7.23 72.33 11.61 0.000 2

18.

Control workers' behaviors physically by

determining how to work correctly in

compulsory way. Example: Set a border

defines the area of work.

7.67 76.74 13.10 0.000 1

19.

Control processes electronically or

mechanically to guarantee the right response

with zero risk.

6.97 69.69 9.20 0.000 4

Total of Applying Visual Management 7.28 72.77 15.12 0.000 4

All items of the field 8.07 80.66 28.59 0.000

Page 87: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

70

Comparing Results of LC tools

5-S tool obtained the highest degree of application in construction projects in Gaza

Strip (67.04%), while Visual Management tool obtained the least degree of

application (53.6%). On the other hand, degrees of importance are significantly

higher than degrees of application with highest point (83.26%) for Huddle meeting

tool and least point (72.77%) for Visual Management tool. The following Figure

(4.5) shows the degrees of application and importance for lean construction tools.

Figure (4.5): Degrees of Importance and Application for "LC Tools"

4.1.4 Transparency Effect on LC Principles

Increasing Transparency is one of LC eleven criteria proposed by Koskela and

agreed by many researchers; these criteria have a comprehensive interrelationship.

This section of questionnaire aimed to investigate the effect of increasing

transparency principle on the application of other LC principles and examined the

two direction relationship between lean construction approach and transparency

principle. Respondents gave their views on the importance of increasing transparency

to facilitate the application of LC criteria.

As shown in Table (4.7), the mean of the field “Effect of increasing transparency on

application of LC principles” equals 7.53 (75.27%), Test-value = 23.90, and P-

82.91 82.23 83.26

72.7767.04

60.61 62.29

53.6

0

10

20

30

40

50

60

70

80

90

100

5-S Increased Visualization

Huddle Meeting

Visual Management

Per

cen

tage

(%)

Degree of Importance

Degree of Application

Page 88: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

71

value=0.000 which is smaller than the level of significance 0.05 . The sign of the

test is positive, so the mean of this field is significantly greater than the hypothesized

value 5. It was concluded that the respondents agreed to the field.

Results of different items at this section slightly change and range from 71.88%

(lowest point) to 78.31% (highest point) which indicates the respondents believe that

increasing transparency has a significant effect on the application of all LC

principles. Ranking of LC criteria according to the effect of transparency principle on

its application is shown in the following Table (4.7).

Table (4.7): Means and Test values for “Effect of Transparency on LC Principles”

No. Item Mean (%) Test

value P-value Rank

1. Reduce of non-value-adding activities. 7.19 71.88 11.90 0.000 10

2. Increase output value through systematic

consideration of customer requirements. 7.83 78.31 17.80 0.000 1

3. Reduce project variability. 7.38 73.85 14.78 0.000 8

4. Reduce project cycle time. 7.45 74.46 14.90 0.000 7

5.

Simplify by minimizing the number of

steps, parts and linkages between

activities.

7.72 77.15 17.31 0.000 3

6. Increase flexibility in work and output. 7.48 74.85 16.32 0.000 6

7. Focus control on the complete process. 7.79 77.92 17.29 0.000 2

8. Build continuous improvement into the

process. 7.58 75.85 16.11 0.000 5

9. Balance flow improvement with

conversion improvement. 7.22 72.17 13.84 0.000 9

10. Conduct reference studies, and lesson

learnt (Benchmarking) 7.60 76.00 14.58 0.000 4

All items of the field 7.53 75.27 23.90 0.000

4.1.5 Benefits of Transparency

From results shown in Table (4.8), the mean of the field “Benefits of

transparency” equals 7.55 (75.49%), Test-value = 24.03, and P-value=0.000 which is

smaller than the level of significance 0.05 . The sign of the test is positive, so the

mean of this field is significantly greater than the hypothesized value 5.It was

concluded that the respondents agreed to this field.

Page 89: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

72

The benefits of transparency which obtained highest degree are; Increase the

effectiveness of the production planning and control process / Increase the efficiency

of workers since reduce wastage in efforts / Save time spent in searching, wandering,

or waiting for the tools, materials, and information needed to do work / Build trust

and motivation of participants. On the other hand, these two benefits obtained the

lowest degree; Contributions towards introducing decentralization policies/

Stimulation of informal contact between the different hierarchical positions.

Table (4.8): Means and Test values for “Benefits of Transparency”

No. Item Mean (%) Test

value P-value Rank

1.

Save time spent in searching, wandering,

or waiting for the tools, materials, and

information needed to do work.

7.94 79.38 17.71 0.000 3

2. Increase the efficiency of workers since

reduce wastage in efforts. 7.95 79.46 19.98 0.000 2

3. Increase the effectiveness of the

production planning and control process. 7.95 79.54 18.90 0.000 1

4. Increase the visibility of errors (Defects

are more visible and easier to recognize) 7.35 73.54 11.83 0.000 9

5. Reduce the propensity to errors. 7.75 77.54 17.12 0.000 5

6. Facilitate a holistic view of the entire

process and to implement flow. 7.68 76.85 15.61 0.000 6

7. Build trust and motivation of

participants. 7.92 79.15 20.78 0.000 4

8. Support and involve workers at

continuous improvement. 7.55 75.46 15.27 0.000 8

9. Stimulation of informal contact between

the different hierarchical positions. 6.87 68.69 8.82 0.000 11

10. Contributions towards introducing

decentralization policies. 6.76 67.62 7.80 0.000 12

11. Simplification of the production control

systems. 7.29 72.92 11.62 0.000 10

12. Reduce reworks that don't comply with

drawings and specifications. 7.58 75.77 13.01 0.000 7

All items of the field 7.55 75.49 24.03 0.000

4.1.6 Success Factors of Transparency

The mean of the field “Success Factors of Transparency” equals 7.80 (78.00%),

Test-value = 26.13, and P-value=0.000 which is smaller than the level of significance

0.05 .

Page 90: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

73

The sign of the test is positive, so the mean of this field is significantly greater

than the hypothesized value 5.It was concluded that respondents agreed to the field.

Results of this field are shown in Table (4.9).

Respondents found that “Establish strong management, structured and systematic

plan to implement visual systems” and "Training and hands-on experience in order to

make managers fully knowledgeable about benefits of transparency principle and its

impact on production system" are the most important success factors for increasing

transparency in construction projects. On the other hand, “Forcing the reduction of

inventories to some extent” is the least important success factor, however it is still a

significant item for increasing transparency (70.85%).

Table (4.9): Means and Test values for “Success Factors of Transparency”

No. Item Mean (%) Test

value P-value Rank

1.

Establish strong management, structured

and systematic plan to implement visual

systems.

8.80 88.00 30.01 0.000 1

2.

Establish a visual mechanism to inspire or

motivate workers to carry out their jobs

efficiency and effectively.

7.84 78.38 15.94 0.000 3

3.

Training and hands-on experience in order

to make managers fully knowledgeable

about benefits of transparency principle

and its impact on production system.

7.97 79.69 18.55 0.000 2

4. Forcing the reduction of inventories to

some extent. 7.08 70.85 12.87 0.000 6

5. Tightening production plans. 7.66 76.62 17.25 0.000 4

6.

Reducing process variability to facilitate

the implementation of visual control

systems.

7.45 74.46 12.85 0.000 5

All items of the field 7.80 78.00 26.13 0.000

4.1.7 Challenges of Transparency

The mean of the field “Challenges of Transparency” equals 7.14 (71.42%), Test-

value = 17.60, and P-value=0.000 which is smaller than the level of significance

0.05 . The sign of the test is positive, so the mean of this field is significantly

greater than the hypothesized value 5. We conclude that the respondents agreed to

this field.

Page 91: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

74

Table (4.10) shows that itemsNo.1 and No.2; Misunderstanding of Lean systems

approach as organizations tend to confuse Lean thinking with the application of a

tool or a set of tools in practice / Lack of knowledge as managers are not aware of

process transparency benefits, are the biggest challenges facing the transparency

principle (78% and 76.69%, respectively) . While items No.4 and No.5; Difficulties

in communication in construction / Changeable work environment as site layout

modified several times throughout the project, are the least important challenges

facing the transparency principle however they are still significant (65.08% and

66.85%, respectively)

Table (4.10): Means and Test values for “Challenges of Transparency”

No. Item Mean (%) Test

value P-value Rank

1.

Misunderstanding of Lean systems approach

as organizations tend to confuse “Lean

thinking” with the application of a tool or a set

of tools in practice.

7.80 78.00 16.47 0.000 1

2. Lack of knowledge as managers are not aware

of process transparency benefits. 7.67 76.69 16.73 0.000 2

3.

Restrict to traditional conversion model and

manager's fear to changes into unknown

approach to them.

7.15 71.54 10.32 0.000 4

4. Difficulties in communication in construction. 6.51 65.08 7.24 0.000 7

5. Changeable work environment as site layout

modified several times throughout the project. 6.68 66.85 7.95 0.000 6

6. Large place of work site where large numbers

of crews spread out and move continuously. 6.95 69.54 9.69 0.000 5

7. Low level of participation of workers in

improvement process. 7.22 72.23 12.84 0.000 3

Total of all items of the field 7.14 71.42 17.60 0.000

Page 92: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

75

4.2 Test of Research Hypothesis

Hypothesis Model

Hypothesis (1)

There are statistically significant differences attributed to the profile of contracting

company at α ≤0.05 between the averages of respondents' views on the subject of

increasing transparency concept within LC in Gaza Strip.

Job title:

Table (4.11) shows that the p-value (Sig.) is greater than the level of significance

= 0.05 for each field, then there is insignificant difference among the respondents

toward each field due to job title. It was concluded that the personal characteristics‟

job title has no effect on each field. Therefore, job title does not affect the

applicability of increasing transparency principle in construction projects in Gaza

Strip.

Page 93: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

76

Table (4.11): ANOVA test of the fields and their p-values for "Job title"

No. Field

Means Test

Value Sig.

Company

director

Project

manager

Site

engineer

Office

engineer

1. Transparency Factors –

Degree of application 6.00 6.60 5.91 5.71 2.065 0.108

2. Transparency Factors –

Degree of importance 7.06 8.22 7.73 7.49 2.394 0.072

3. Lean Construction Tools

– Degree of application 6.20 6.46 6.09 6.33 0.388 0.762

4. Lean Construction Tools

– Degree of importance 7.31 8.29 8.04 7.98 1.517 0.213

5. Effect of Transparency

on LC Principles 7.42 7.78 7.38 7.59 0.920 0.433

6. Benefits of Transparency 6.89 7.70 7.49 7.79 1.258 0.292

7. Success Factors of

Transparency 7.75 8.14 7.56 8.02 2.096 0.104

8. Challenges of

Transparency 6.13 7.24 7.12 7.54 1.924 0.129

All items of the questionnaire 6.83 7.51 7.14 7.31 1.576 0.199

Years of experience:

Table (4.12) shows that the p-value (Sig.) is smaller than the level of significance

= 0.05 for the field “Challenges of Transparency”, then there is a significant

difference among the respondents toward this field due to years of experience. It was

concluded that years of experience has an effect on this field. Figure (4.6) shows that

5 to less than 10 years of experiences have the highest mean.

Figure (4.6): Means of "Challenges of Transparency" due to "Years of experience"

62

64

66

68

70

72

74

76

< 5 yrs 5 to < 10 yrs 10 to < 20 yrs >= 20 yrs

Per

cen

tage

(%)

Page 94: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

77

For the other fields, the p-value (Sig.) is greater than the level of significance =

0.05, then there is insignificant difference among the respondents toward these fields

due to years of experience. It was concluded that years of experience has no effect on

these fields.

Table (4.12): ANOVA test of the fields and their p-values for years of experience

No. Field

Means

Test

Value Sig. Less

than 5

years

5 – less

than 10

years

10 – less

than 20

years

20 years

and

above

1. Transparency Factors –

Degree of application 5.99 6.20 5.94 6.88 0.578 0.630

2. Transparency Factors –

Degree of importance 7.58 7.99 7.80 6.88 1.260 0.291

3. Lean Construction Tools

– Degree of application 5.91 6.34 6.30 6.47 0.425 0.735

4. Lean Construction Tools

– Degree of importance 7.87 8.17 8.20 6.70 2.303 0.080

5. Effect of Transparency

on LC Principles 7.56 7.50 7.60 7.10 0.219 0.883

6. Benefits of Transparency 7.33 7.62 7.66 7.13 0.635 0.594

7. Success Factors of

Transparency 7.63 7.76 7.91 8.75 1.123 0.343

8. Challenges of

Transparency 6.92 7.49 6.71 6.79 2.820 0.042

All items of questionnaire 7.07 7.34 7.30 6.93 0.577 0.631

The place of company office:

Table (4.13) shows that the p-value (Sig.) is smaller than the level of significance

= 0.05 for the field “Lean Construction Tools - Degree of application”, then there

is a significant difference among the respondents toward this field due to the place of

company office. We conclude that the place of company office has an effect on this

field.

Page 95: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

78

Figure (4.7): Means of "Lean Construction Tools - Degree of application" due to"

place of company office"

For the other fields, the p-value (Sig.) is greater than the level of significance =

0.05, then there is insignificant difference among the respondents toward these fields

due to the place of company office. It was concluded that the place of company

office has no effect on the other fields.

Table (4.13): ANOVA test of the fields and p-values for the place of company office

No. Field

Means

Test

Value Sig. The

South

The

Middle

area

Gaza The

North

1. Transparency Factors-

Degree of application 6.18 7.13 5.92 6.62 2.000 0.117

2. Transparency Factors-

Degree of importance 7.78 7.78 7.82 7.88 0.013 0.998

3. Lean Construction Tools -

Degree of application 6.56 7.55 5.88 7.29 4.225 0.007

4. Lean Construction Tools -

Degree of importance 8.16 8.36 8.00 8.01 0.301 0.825

5. Effect of Transparency on

LC Principles 7.57 7.31 7.46 8.41 1.475 0.224

6. Benefits of Transparency 7.47 7.72 7.52 7.96 0.383 0.765

7. Success Factors of

Transparency 7.63 7.65 7.84 8.31 0.660 0.578

8. Challenges of Transparency 7.23 7.27 7.09 7.24 0.123 0.947

All items of the questionnaire 7.35 7.69 7.13 7.74 1.568 0.200

0

10

20

30

40

50

60

70

80

The South The Middle area Gaza The North

Pe

rce

nta

ge (%

)

Page 96: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

79

Years of company experience:

Table (4.14) shows that the p-value (Sig.) is greater than the level of significance

= 0.05 for each field, then there is insignificant difference among the respondents

toward each field due to years of company experience. We conclude that the years of

experience has no effect on each field.

Table (4.14): ANOVA test of the fields and p-values for years of company experience

No. Field

Means

Test

Value Sig. Less

than 5

years

5 – less

than 10

years

10 – less

than 20

years

20

years,

and

above

1. Transparency Factors-

Degree of application 6.15 6.66 6.09 5.80 1.609 0.191

2. Transparency Factors-

Degree of importance 7.98 7.89 7.94 7.58 0.661 0.578

3. Lean Construction Tools -

Degree of application 6.25 6.33 6.36 6.06 0.222 0.881

4. Lean Construction Tools -

Degree of importance 8.08 8.10 8.20 7.91 0.384 0.765

5. Effect of Transparency on

LC Principles 7.80 7.46 7.66 7.30 1.091 0.356

6. Benefits of Transparency 7.39 7.80 7.71 7.35 1.073 0.363

7. Success Factors of

Transparency 7.72 7.83 7.87 7.77 0.083 0.969

8. Challenges of Transparency 6.86 6.96 7.45 7.12 1.090 0.356

All items of the questionnaire 7.27 7.35 7.40 7.06 0.857 0.466

Page 97: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

80

Number of permanent employees:

Table (4.15) shows that the p-value (Sig.) is greater than the level of significance

= 0.05 for each field, then there is insignificant difference among the respondents

toward each field due to number of permanent employees. It was concluded that the

number of permanent employees has no effect on each field.

Table (4.15): ANOVA test and p-values for number of permanent employees

No. Field

Means

Test

Value Sig. Less than

5

employees

5 - 10

employees

11 - 20

employees

Over 20

employees

1.

Transparency

Factors- Degree of

application

6.14 5.93 6.22 6.22 0.327 0.805

2.

Transparency

Factors- Degree of

importance

7.62 8.03 7.79 7.58 0.732 0.535

3.

Lean Construction

Tools - Degree of

application

6.65 5.79 6.41 6.53 1.624 0.187

4.

Lean Construction

Tools - Degree of

importance

8.25 8.07 8.12 7.89 0.299 0.826

5.

Effect of

Transparency on

LC Principles

7.59 7.35 7.87 7.26 1.992 0.119

6. Benefits of

Transparency 7.98 7.58 7.60 7.21 1.288 0.281

7. Success Factors of

Transparency 7.64 7.91 7.76 7.75 0.220 0.882

8. Challenges of

Transparency 7.12 7.26 7.04 7.10 0.202 0.895

All items of the

questionnaire 7.44 7.13 7.36 7.20 0.531 0.661

Page 98: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

81

Number of projects implemented in the last 5 years:

Table (4.16) shows that the p-value (Sig.) is greater than the level of significance

= 0.05 for each field, then there is insignificant difference among the respondents

toward each field due to number of projects implemented in the last 5 years. It was

concluded that the number of projects implemented in the last 5 years has no effect

on each field.

Table (4.16): ANOVA test of the fields and their p-values for number of projects

implemented in the last 5 years

No. Field

Means Test

Value Sig. Less than 10

projects

10 – 20

projects

21 - 30

projects

Over 30

projects

1. Transparency Factors-

Degree of application 6.07 6.07 6.71 5.87 1.024 0.385

2. Transparency Factors-

Degree of importance 7.93 7.76 7.75 7.81 0.109 0.955

3. Lean Construction Tools -

Degree of application 5.87 6.02 7.08 6.63 2.452 0.066

4. Lean Construction Tools -

Degree of importance 7.81 8.03 8.29 8.33 1.096 0.353

5. Effect of Transparency on

LC Principles 7.35 7.35 7.87 7.92 2.026 0.114

6. Benefits of Transparency 7.44 7.55 7.83 7.53 0.380 0.768

7. Success Factors of

Transparency 7.68 7.77 8.23 7.74 0.787 0.503

8. Challenges of

Transparency 7.03 7.15 7.63 6.97 0.857 0.465

All items of the questionnaire 7.15 7.69 7.42 1.695 0.171

Annual average value of projects in the last 5 years:

Table (4.17) shows that the p-value (Sig.) is smaller than the level of significance

= 0.05 for the fields “Benefits and Challenges of Transparency”, then there is a

significant difference among the respondents toward these fields due to annual

average value of projects in the last 5 years. It was concluded that the personal

characteristics‟ annual average value of projects in the last 5 years has an effect on

these fields.

Page 99: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

82

Figure (4.8): Means "Benefits of Transparency" due to "Annual average of projects"

Figure (4.9): Means of "Challenges of Transparency" due to "Annual average value

of projects"

For the other fields, the p-value (Sig.) is greater than the level of significance =

0.05, then there is insignificant difference among the respondents toward these fields

due to annual average value of projects in the last 5 years. It was concluded that the

personal characteristics‟ annual average value of projects in the last 5 years has no

effect on the other fields.

66

68

70

72

74

76

78

80

< 1 M$ 1 M to < 5 M$ 5 M to < 10 M$ >= 10 M$

Per

cen

tage

(%)

0

10

20

30

40

50

60

70

80

< 1 M$ 1 M to < 5 M$ 5 M to < 10 M$ >= 10 M$

Per

cen

tage

(%)

Page 100: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

83

Table (4.17): ANOVA test of the fields and their p-values for annual average value of

projects in the last 5 years

No. Field

Means

Test

Value Sig. Less

than 1

M

1 M –

less

than 5

M

5 M -

less

than 10

M$

10 M,

and

over

1. Transparency Factors-

Degree of application 5.40 5.98 6.17 6.60 2.478 0.064

2. Transparency Factors-

Degree of importance 7.57 7.69 7.65 8.30 1.835 0.144

3. Lean Construction Tools -

Degree of application 5.47 6.31 6.07 6.71 1.994 0.118

4. Lean Construction Tools -

Degree of importance 7.78 7.94 7.96 8.51 2.019 0.115

5. Effect of Transparency on

LC Principles 7.84 7.32 7.32 7.88 2.102 0.103

6. Benefits of Transparency 7.13 7.50 7.54 7.86 1.434 0.236

7. Success Factors of

Transparency 7.24 7.67 7.83 8.24 2.927 0.036

8. Challenges of Transparency 5.83 7.42 7.04 7.56 7.774 0.000

All items of the questionnaire 6.79 7.22 7.12 7.69 3.381 0.020

Hypothesis (2)

There is statistically significant positive relationship at α ≤ 0.05 between the existing

status of applying transparency factors and existing status of applying lean

construction tools supporting transparency principle in GS.

The correlation coefficient between the existing status of applying transparency

factors and existing status of applying lean construction tools supporting

transparency principle in GS equals 0.694 and the p-value (Sig.) equals 0.000 less

than 0.05, so the correlation coefficient is statistically significant at α = 0.05. It was

concluded that there exists a significant relationship between the existing status of

applying transparency factors and existing status of applying lean construction tools

supporting transparency principle in GS.

Page 101: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

84

Hypothesis (3)

There is statistically significant positive relationship at α ≤ 0.05 between importance

of transparency factors and importance of lean construction tools supporting

transparency principle.

The correlation coefficient between importance of transparency factors and

importance of lean construction tools supporting transparency principle equals 0.697

and the p-value (Sig.) equals 0.000is less than 0.05, so the correlation coefficient is

statistically significant at α = 0.05. It was concluded that there exists a significant

relationship between importance of transparency factors and importance of lean

construction tools supporting transparency principle.

Hypothesis (4)

There is statistically significant positive relationship at α ≤ 0.05 between importance

of increasing transparency factors and benefits of increasing transparency principle.

The correlation coefficient between importance of increasing transparency factors

and benefits of increasing transparency principle equals 0.397 and the p-value (Sig.)

equals 0.000is less than 0.05, so the correlation coefficient is statistically significant

at α = 0.05. It was concluded that there exists a significant relationship between

importance of increasing transparency factors and benefits of increasing transparency

principle.

Hypothesis (5)

There is statistically significant positive relationship at α ≤ 0.05 between importance

of lean construction tools supporting transparency principle and benefits of

increasing transparency principle.

The correlation coefficient between importance of lean construction tools

supporting transparency principle and benefits of increasing transparency principle

equals 0.545 and the p-value (Sig.) equals 0.000is less than 0.05, so the correlation

coefficient is statistically significant at α = 0.05. It was concluded that there exists a

Page 102: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

85

significant relationship between importance of lean construction tools supporting

transparency principle and benefits of increasing transparency principle.

Hypothesis (6)

There is statistically significant positive relationship at α ≤ 0.05 between importance

of lean construction tools supporting transparency principle and the effect of

transparency on lean construction principles.

The correlation coefficient between importance of lean construction tools

supporting transparency principle and the effect of transparency on lean construction

principles equals 0.540 and the p-value (Sig.) equals 0.000is less than 0.05, so the

correlation coefficient is statistically significant at α = 0.05. It was concluded that

there exists a significant relationship between importance of lean construction tools

supporting transparency principle and the effect of transparency on lean construction

principles.

Hypothesis (7)

There is statistically significant positive relationship at α ≤ 0.05 between benefits of

increasing transparency principle and the effect of transparency on the lean

construction principles.

The correlation coefficient between benefits of increasing transparency principle

and the effect of transparency on the lean construction principles equals 0.586 and

the p-value (Sig.) equals 0.000is less than 0.05, so the correlation coefficient is

statistically significant at α = 0.05. It was concluded that there is exist a significant

relationship between benefits of increasing transparency principle and the effect of

transparency on the lean construction principles.

Hypothesis (8)

There is statistically significant positive relationship at α ≤ 0.05 between benefits of

increasing transparency and success factors supporting the application of the

concept.

Page 103: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

86

The correlation coefficient between benefits of increasing transparency and

success factors supporting the application of the concept equals 0.557 and the p-

value (Sig.) equals 0.000is less than 0.05, so the correlation coefficient is statistically

significant at α = 0.05. It was concluded that there exists a significant relationship

between benefits of increasing transparency and success factors supporting the

application of the concept.

Summary

Analysis of results showed that, generally, the company profile does not have a

significant effect on the applicability of transparency principle, few items showed

little influence but it is very limited and inconsiderable.

Results showed that several factors of transparency principle are applied well in

construction projects in Gaza Strip while some of them are still weak and need to be

enhanced since the results of means values range from 44.88% to 72.17%. The same

for the application of LC tools that supporting transparency, results range from

53.60% to 67.04%, which are relatively weak values and need to be enhanced. On

the other hand, all factors of transparency principles and LC tools are considered to

be important from respondents' viewpoint since the means are all above 69%. Also,

degrees of importance for all factors are higher than degrees of application, therefore

transparency principle needs to be increased and enhanced in construction projects in

Gaza Strip within lean construction tools.

There is a significant effect of Increasing Transparency principle on applying other

principles of LC whereas all means values are above 71%. Thus, there is a reciprocal

relationship between transparency principle and lean construction.

Results showed that transparency has worthy advantages from respondents'

viewpoint since the total mean of benefits is 75.49%, however there are also

considerable challenges facing the application of transparency principle (Total means

= 75%). Furthermore, there are many factors need to be applied well to allow the

success of increasing transparency principle, respondents gave these success factors

75.49% importance.

Page 104: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

Chapter 5

Conclusion

Page 105: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

87

Chapter 5: Conclusion

This chapter summarizes the objectives and outcomes of the research and

provides conclusions of the research. In achieving the aim of the research, three main

objectives have been outlined and achieved through the findings of the analyzed

collected questionnaires. These objectives are related to the research questions that

were developed to increase knowledge and familiarity with the subject. The

outcomes were found as follows:

5.1 Outcomes Related to Objective One

"To evaluate the current status and general perceptions of

transparency practices in construction industry of Gaza Strip"

This research studied the transparency concept within lean construction approach

in Gaza Strip so that it was necessary to evaluate the current status of transparency

practices in construction industry and the general perceptions of contracting

companies on the applicability of this concept. Therefore, the conducted survey

investigated the degree of application of transparency factors and lean construction

tools that support the transparency. Results showed that factors of transparency

principle are applied in construction projects in Gaza Strip however they are still

weak and need to be enhanced since the results of means values range from 44.88%

to 72.17%.

Contracting companies in Gaza Strip do some efforts to apply factors of

transparency; Establishing the basic housekeeping in the workplace, Make the

process visible and observable by appropriate site layout, and Using measurements

to reveal the work quality and efficiency. While the following three factors of

transparency obtained low degrees of application and less than 60% means;

Reducing the interdependence of project activities in time, materials, and work area,

Incorporating information in the work place about project activities, and Utilizing

visual devices to immediately recognize mistakes and problems.

Likewise the application of LC tools that supporting transparency, results range from

53.60% to 67.04%, which are relatively weak values and need to be enhanced.

Page 106: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

88

Results of LC tools are correspond to results of transparency factors since the 5-S

tool (Sort – Straighten – Shine – Standardize–Sustain) obtained highest degree of

application, while Visual Management tool obtained the lowest degree of application.

On the other hand, all factors of transparency principles and LC tools are considered

to be important from respondents' viewpoint since the means of all factors are about

70% or above. Respondents gave these factors higher degrees of importance;

Establishing the basic housekeeping in the workplace, Make the process visible and

observable by appropriate site layout, and Using measurements to reveal the work

quality and efficiency.

It was found that degrees of importance of all factors are higher than degrees of

application, therefore it was concluded that transparency principle needs to be

increased and enhanced in construction projects in Gaza Strip. Further, results

showed that there is a relationship between the importance and the application of

transparency factors indicating that contracting companies have a concern to apply

what they believe in its importance for projects management.

5.2 Outcomes Related to Objective Two

"To identify benefits, challenges and success factors supporting the

implementation of transparency principle"

Lists of benefits, challenges, and success factors were gathered from literature

reviews and various researches, and then the questionnaire tool was used to

investigate views of contracting companies on these lists regarding transparency

principle in Gaza Strip.

Results analysis of 12 benefits of transparency showed that transparency has worthy

advantages from respondents' viewpoint since the total mean of benefits is 75.49%.

Increase the effectiveness of the production planning and control process, Increase

the efficiency of workers since reduce wastage in efforts, Save time spent in

searching, wandering, or waiting for the tools, materials, and information needed to

do work, and Build trust and motivation of participants, are the most agreed benefits

by respondents and all about 80% mean value, which indicates that respondents are

Page 107: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

89

well aware on the benefits of increasing transparency in construction projects in

Gaza Strip.

However, Stimulation of informal contact between the different hierarchical

positions, and Contributions towards introducing decentralization policies, are the

least agreed benefits of transparency that less than 70% mean values.

On another level, respondents approved that Increasing Transparency principle

significantly influences the applicability of other LC principles whereas all means

values regarding the effect of transparency on LC principles are above 71%. Thus,

there is a reciprocal relationship between transparency principle and lean

construction.

However, there are many factors should be applied properly in construction projects

to allow the success of increasing transparency principle; respondents gave these

success factors 75.49% importance. Results found that Establish strong

management, structured and systematic plan to implement visual systems, Training

and hands-on experience in order to make managers fully knowledgeable about

benefits of transparency principle and its impact on production system, and Establish

a visual mechanism to motivate workers to carry out their jobs efficiency and

effectively, are the most important success factors for increasing transparency in

construction projects in Gaza Strip.

Furthermore, results showed that there are considerable challenges facing the

application of transparency principle, total means of all 7 listed challenges equals

75%. Misunderstandings of Lean systems approach, Lack of knowledge as managers

are not aware of process transparency benefits, Low level of workers participation in

improvement process, and Restrict to traditional conversion, are the most approved

challenges facing the application of transparency principle with means values above

70%.

The obtained results of success factors and challenges indicated that projects

management in Gaza Strip should be supported by managers with higher knowledge

and better understand of transparency principle, its techniques and importance.

Page 108: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

90

Project managers need to understand benefits of the new managements approach to

convince its applicability. Consequently, it was concluded that building capacities of

project managers is a crucial issue to allow increasing transparency in construction

projects in Gaza Strip.

These results are harmonized with the conduction obtained by (Ismaiel, 2013)who

studied the applicability of Lean Construction in the Gaza Strip Construction

Industry, and he found that team work and leadership management are the main

factors affect the applicability of lean construction principles in the Gaza strip.

5.3 Outcomes Related to Objective Three

"To investigate the proper Lean tools/techniques those enhance

transparency in Gaza Strip"

Previous literatures and published articles were reviewed from different

international journals in order to study lean construction, its techniques and tools. It

was found that there are four main tools that support increasing transparency

principle; 5-S, Increased Visualization, Huddle Meeting, and Visual Management.

The conducted survey was used to investigate the most proper techniques needed for

construction projects in Gaza Strip; respondents gave the most importance degrees to

Huddle Meeting, 5-S, Increased Visualization respectively, at means values above

82%. It was concluded that construction projects in Gaza Strip need to be enhanced

regarding the communication between different parties, and pay more attention to the

tidiness and orderings of work place.

While Visual Management tool obtained the least importance degrees at means value

72.77%. It was concluded that preferred simple tools preferable on tricky techniques

in construction projects in Gaza Strip.

5.3 Research contribution to previous studies

This research aimed to enhance transparency of construction projects throughout

lean construction approach, explore the present transparency practices in

construction projects, and identify the proper LC tools that enhance transparency in

Gaza Strip. An extensive review of literature was conducted to achieve this aim.

Page 109: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

91

Generally, there are limited studies researched on lean construction approach while

there is no any researches study the principle of increasing transparency in Gaza

Strip. Further, the field of study is relatively recent approach therefore there are

limited researches on worldwide. In this research, the applicability of increasing

transparency principle within lean construction approach was examined.

Most previous studies investigated the applicability of lean construction approach or

specific tools of LC in generally, without focusing on transparency principle and its

different aspects. Also previous studies did not investigate the relationship between

increasing transparency principle and other LC principles. In this research the

relation between increasing transparency principle and other LC principles was

investigated.

Different instruments were conducted by previous studies such as case studies and

brain storming in the field of study, however there is no any researches used the tool

of questionnaire to study the applicability of increasing transparency principle in

construction projects so that the questionnaire of this research was built originally for

the purpose of this research drawing on literatures and case studies.

The outcomes of this research can be used to enhance projects success by give

attention to the mentioned factors, tools, and conclusions.

5.4 Research value

Construction projects in Gaza Strip are characterized by low productivity, errors,

poor co-ordination, bad reputation, high accident rates, insufficient quality and

overruns in cost and schedule (Yahia, 2004). Furthermore, wastes have been

recognized as a major problem in construction industry in Gaza Strip, and the level

of material waste is fairly high and higher than the nominal figures due to managerial

problems (Al-Moghany, 2006). Therefore, this research can be used to promote the

knowledge of lean construction as a new innovative management approach, and to

enhance projects ability to face challenges and problems through applying the

increasing transparency principle, this work reveals an important concept and paves

the path for future research.

Page 110: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

92

Therefore, transparency concept within lean construction was spotlighted in this

research to add valuable contribution to construction industry and to enhance the

sector's performance. Also, this research is considered the milestone for applying

transparency concept and to start paying more attention to lean construction approach

in Gaza Strip. It is concerned with construction professionals and project managers

work in contracting firms to optimize the success of construction projects. It is hoped

that the obtained factors and tools in this study to be applied and examined

practically in construction projects in Gaza Strip.

Furthermore, this research will be added value to the current body of knowledge

about Increasing Transparency principle all over the world. Rarely researchers

studied this principle within lean construction, so that this research is considered as

one of these limited researches that study the applicability of transparency principle

in construction industry. Moreover, it is the first study that contributes significantly

to increase transparency within LC in Palestine. This study can provide a

documentation of reference for researchers who are interested in this field.

Page 111: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

References

Page 112: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

93

References

Al-Moghany, S. (2006). Managing and minimizing construction waste in Gaza

Strip. M.Sc. Thesis, Islamic University of Gaza, Palestin.

Alarcón, L. (1997).Lean construction.Catholic University of Chile,

Santiago.Book: CRC Press.

Arleroth, J., & Kristensson, H. (2011). Waste in Lean Construction–A case study

of construction site and the development of a Lean Construction Tool. M.Sc.

Thesis, Chelmers University of Technology, Gothenburg, Sweden.

Aziz, R. F., & Hafez, S. M. (2013). Applying lean thinking in construction and

performance improvement. Alexandria Engineering Journal, 52(4), 679-695.

Ballard, G., Kim, Y., Jang, J., & Liu, M. (2007). Roadmap for lean

implementation at the project level. Research report: Construction Industry

Institute.

Ballard, G., Koskela, L., Howell, G., & Zabelle, T. (2001). Production system

design in construction. Paper presented at the Annual Conference of the

International Group for Lean Construction, Singapore.

Bauch, C. (2004).Lean product development: making waste transparent. Diploma

Thesis: TUM & MIT.

Bourque, L. (2003). How to conduct self-administered and mail surveys.

University of California at Los Angeles, USA. Book(Vol. 3): Sage.

Brady, D. A. (2014). Using visual management to improve transparency in

planning and control in construction. PhD Thesis, University of Salford.

Chi, H. (2011). 5S implementation in Wan Cheng Industry Manufacturing

Factory in Taiwan. M.Sc. Thesis, University of Wisconsin-Stout.

Conte, A. S. I., & Gransberg, D. (2001). Lean construction: From theory to

practice. AACE International Transactions, CS101.

Oliveira, T. R., Costa, D. B., Ilse, N., & Thomas, R. (2012). Transparency in

Construction Sites. Proceedings of the 20th Annual Conference of the

International Group for Lean Construction, San Diego, USA

Deming, W. (1986).Out of the Crisis. Book.Massachusetts Institute of

Technology Press, Cambridge.

Page 113: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

94

Santos, A. (1999). Application of flow principles in the production management

of construction sites. University of Salford.

Santos, A., Powell, J., Sharp, J., & Formoso, C. (1998). Principle of transparency

applied in construction. Paper presented at the Process Of the Annual

Conference (IGLC-6), Brazil.

Enshassi, A., & Abu Zaiter, M. (2014). Implementation of Lean Tools on Safety

in Construction Projects in Palestine. Paper presented at the 22nd annual

conference Proceedings IGLC, Oslo, Norway.

Enshassi, A., Mohamed, S., & Abushaban, S. (2009). Factors affecting the

performance of construction projects in the Gaza strip. Journal of Civil

Engineering and Management, 15(3), 269-280.

Eriksson, P. (2010). Improving construction supply chain collaboration and

performance: a lean construction pilot project. Supply Chain Management:

An International Journal, 15(5).

Faniran, O., & Caban, G. (1998). Minimizing waste on construction project sites.

Engineering, construction and architectural management. 5(2), 182-188.

Australia: MCB UP Ltd.

Fayek, A. R., Dissanayake, M., & Campero, O. (2003). Measuring and

classifying construction field rework: A pilot study. Research Rep.

Fellows, R. F., & Liu, A. M. (2008). Research methods for construction: John

Wiley & Sons.

Formoso, C. T., Santos, A. D., &Powell, J. A. (2002). An exploratory study on

the applicability of process transparency in construction sites. Journal of

construction Research, 3(01).

Galsworth, G. (2004). The value of vision: the language of lean production is

self-ordering and self-improving. Industrial engineer, 36(8), 44-50.

Galsworth, G. (2005). Visual workplace: visual thinking. Visual-Lean Enterprise

Press, Portland.

Galsworth, G. D. (1997). Visual systems: harnessing the power of the visual

workplace: American Management Association.

Garas, G. L., Anis, A. R., & El Gammal, A. (2001). Materials waste in the

Egyptian construction industry. Proceedings IGLC-9, Singapore.

Page 114: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

95

Green, S. D., & May, S. C. (2005). Lean construction: arenas of enactment,

models of diffusion and the meaning of „leanness‟. Building Research &

Information, 33(6).

Greif, M. (1991). The visual factory: building participation through shared

information: CRC Press.

Howell, G., Macomber, H., Koskela, L., & Draper, J. (2004). Leadership and

project management: time for a shift from Fayol to Flores. Paper presented at

the Proceedings of the 12th Annual Conference of the International Group for

Lean Construction (IGLC-12).

Igarashi, R. (1991). The big picture. Visual control systems. Productivity Press,

Cambridge.

Ismaiel, M. I. A. (2013). The Applicability of Lean Construction in the Gaza

Strip Construction Industry. The Islamic University-Gaza.

Klotz, L. (2008). Process transparency for sustainable building delivery. (PhD),

The Pennsylvania State University.

Koskela, L. (1992). Book. Application of the new production philosophy to

construction: Stanford University.

Koskela, L., Bølviken, T., & Rooke, J. (2013). Which are the wastes of

construction? Paper presented at the Proceedings for the 21st Annual

Conference of the International Group for Lean Construction.

Koskela, L., Howell, G., Ballard, G., & Tommelein, I. (2002). The foundations of

lean construction. Design and construction: Building in value, 211-226.

Koskela, L., & Vrijhoef, R. (2000). The Prevalent Theory of Construction a

Hindrance for Innovation. Paper presented at the Proceedings for 8th Annual

Conference of the International Group for Lean Construction, Brighton, UK.

Kothari, C. R. (2004). Book. Research methodology: Methods and techniques:

New Age International. 2nd

Edition: New Age.

Lee, S.-H., Diekmann, J. E., Songer, A. D., & Brown, H. (1999). Identifying

waste: applications of construction process analysis. Paper presented at the

Proceedings of the Seventh Annual Conference of the International Group for

Lean Construction. Berkeley, USA.

Liff, S., & Posey, P. A. (2004). Seeing is believing: how the new art of visual

management can boost performance throughout your organization:

AMACOM Div American Mgmt Assn.

Page 115: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

96

Macomber, H., & Howell, G. (2003). Foundations of Lean Construction:

Linguistic Action. Paper presented at the IGLC.

Marczyk, G., DeMatteo, D., & Festinger, D. (2005). Essentials of research design

and methodology: John Wiley & Sons Inc.

Masaaki Imai, K. (1986). The Key to Japan's Competitive Success: New York,

NY: Random House.

Naing, L., Winn, T., & Rusli, B. (2006). Practical issues in calculating the sample

size for prevalence studies. Archives of orofacial Sciences.

Nijhof, A., Graafland, J., & de Kuijer, O. (2009). Exploration of an agenda for

transparency in the construction industry. Construction Innovation.

Ohno, T. (1988). Toyota production system: beyond large-scale production: crc

Press.

Polat, G., & Ballard, G. (2004). Waste in Turkish construction: need for lean

construction techniques. Paper presented at the Proceedings of the 12th

Annual Conference of the International Group for Lean Construction IGLC-

12, August, Denmark.

Russell, M. M., Liu, M., Howell, G., & Hsiang, S. M. (2014). Case studies of the

allocation and reduction of time buffer through use of the last planner system.

Journal of Construction Engineering and Management, 141(2), 04014068.

Salem, O., Solomon, J., Genaidy, A., & Luegring, M. (2005). Site

implementation and assessment of lean construction techniques. Lean

Construction Journal, 2(2).

Salem, O., Solomon, J., Genaidy, A., & Minkarah, I. (2006). Lean Construction:

From Theory to Implementation. Journal of management in engineering,

22(4).

Salem, O., Solomon, J., Genaidy, A., & Minkarah, I. (2006). Lean construction:

From theory to implementation. Journal of management in engineering,

22(4).

Shingo, S. (1988). Non-stock production: the Shingo system of continuous

improvement: CRC Press.

Sjögren Leong, M., Ward, S., & Koskela, L. (2015). Towards an Operational

Definition of Lean Construction Onsite: IGLC. net.

Stewart, T. A. (1992). The search for the organization of tomorrow. Fortune,

125(10), 92.

Page 116: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

97

Teo, M., & Loosemore, M. (2001). A theory of waste behaviour in the

construction industry. Construction Management & Economics, 19(7).

Tezel, A., Koskela, L., & Tzortzopoulos, P. (2008). Visual management in lean

construction. Conference Paper at 8th International Built and Human

Environment Research : Czech Technical University, Prague

Tezel, B., Koskela, L., & Tzortzopoulos, P. (2009). The functions of visual

management. Conference Paper, University of Salford, Manchester.

Tezel, B., Koskela, L., & Tzortzopoulos, P. (2010). Visual management in

construction: Study report on Brazilian cases. University of Salford,

Manchester.

Tjell, J., & Bosch-Sijtsema, P. M. (2015). Visual Management in Mid-sized

Construction Design Projects. Procedia Economics and Finance, 21, 193-200.

Womac, J., & Jones, D. (1996). Lean thinking: New York: Simon and Schuster.

Womack, J. P., Jones, D. T., & Roos, D. (1990). Book. Machine that changed the

world: Simon and Schuster.

Womak, J. Jones, Daniel. (2003) Book. Lean thinking: Free Press.

Yahia, A. (2004). Time Schedule Preparation By Predicting Production

RateUsing Simulation. M.Sc. Thesis, Islamic University of Gaza, Palestine.

Yahya, M. A., & Mohamad, M. I. (2011). Review on lean principles for rapid

construction. Jurnal Teknologi, 54.

Ye, G., Jin, Z., Xia, B., & Skitmore, M. (2014). Analyzing causes for reworks in

construction projects in China. Journal of management in engineering, 31(6).

Page 117: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

98

Appendixes

Page 118: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

99

Appendix (I): The Questionnaire "English"

Questionnaire about:

The Applicability of Increasing Transparency Principle within Lean Construction in

Gaza Strip

Dear participant:

We thank you for contribution in some of your time and effort to participate in the

filling of this questionnaire, which aim to improve and enhance the awareness and

understanding about the applicability of lean construction and transparency

practices in the Gaza Strip’s construction industry. Your contribution in the filling of

this questionnaire is for the purpose of obtaining the master degree in Construction

Management, Islamic University of Gaza therefore the information will be

contributed for the purpose of scientific research only, while ensuring full

confidentiality.

Lean Construction (LC) is a new culture of management of projects in construction

industry that means eliminating all wastes and non-added value activities of the

construction project through all phases in order to get a profitable delivery. This

research is studying LC tools which improve transparency of construction projects.

Transparency means a separation of the information network and the hierarchical

structure of order giving. A process reaches excellent in terms of transparency when

everyone, even those with relatively little technical knowledge, understands the

process without asking.

The questionnaire consists of five parts:

1. Organizational background of respondent.

2. Evaluate factors of increasing transparency concept in Gaza Strip

construction projects.

3. Evaluate LC tools for improving transparency.

4. Investigate the effect of increasing transparency on application of LC

principles.

5. Evaluate benefits, success factors and challenges of applying the concept of

increasing transparency.

Researcher: Anas M. Abu daqqa

Supervisor: Dr. Khaled Hallaq

Page 119: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

100

Part I: Organizational background of respondent

1. Job title:

Company director Project manager Site engineer Office engineer

2. Years of respondent experience:

Less than 5 years 5–less than 10 years 10–less than 20 years

20 years, and above

3. The place of company office, which governorate:

The South The Middle area Gaza The North

4. Years of company experience:

Less than 5 years 5–less than 10 years 10–less than 20 years

20 years, and above

5. Number of permanent employees:

Less than 5 5 - 10 employees 11 - 20 Over 20

6. Number of projects implemented in the last 5 years:

Less than 10 10 – 20 projects 21 - 30 projects Over 30 projects

7. Annual average value of projects in the last 5 years (U.S. $):

Less than 1 M 1 M – less than 5 M 5 M - less 10 M$ 10 M, and over

8. Company Classification:

Classification Nature of Work

First Class Second Class

Third Class

Building

Roads

Water and Sewer

Electro-mechanic

9. The respondent degree of knowledge of LC approach, and familiarity with the concept and tools:

High Medium poor None

Part II: Evaluate factors of increasing transparency concept in Gaza Strip

construction projects

The following factors in the table represent the factors of transparency in the

construction projects. Please choose degree of application of these factors in the

work field, in which the 10 is the highest degree and the factor is always applied,

the degree gradually decrease to 0 as the factor is not applied at all.

Page 120: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

101

Please choose degree of importance of each factor in order to improve the

transparency of construction projects in Gaza Strip in which 10 is the highest

importance, and gradually decrease to 0 as the factor has no importance.

No. Transparency Factors Degree of Applying (0 - 10)

Degree of Importance (0 - 10)

1. Reducing the interdependence of project activities in time, materials, and work area.

2.

Utilizing visual devices to immediately recognize mistakes and problems. Ex. Andon system: light board to notify the management to any problem immediately as lacks in materials.

3. Making the process visible and observable by appropriate site layout, visible fencing, signage for safety equipment location, good lighting.

4. Incorporating information in the work place about project activities by display boards, statistics, or videos.

5. Establishing basic housekeeping to eliminate clutter, maintaining orderly and clean workplace.

6. Using measurements to reveal the work quality and efficiency. Ex: Measurements for performance indicators, completion and delay percentage.

Part III: Evaluate LC tools for increasing transparency.

The following factors in the table represent lean construction tools that increase

transparency. Please choose degree of application of these tools in the work field,

in which the 10 is the highest degree and the tool is always applied, the degree

gradually decrease to 0 as the tool is not applied at all.

Please choose degree of importance of each tool in order to increase transparency

of construction projects in Gaza Strip in which 10 is the highest importance, and

gradually decrease to 0 as the tool has no importance.

Page 121: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

102

No. Lean Construction Tools Degree of Applying (0 - 10)

Degree importance (0 - 10)

Applying 5 S tool (Sort – Straighten – Shine – Standardize Sustain(

1. Seiri/Sort: Throw away all rubbish and unrelated materials, and make sure that all broken stuff is in a special place. (No good and bad stuff set together)

2. Seiton/Straighten: Tools and materials were piled in a regular pattern in the site store, and keep the orderliness of the store content.

3. Place devices and tools close to work areas in the site.

4. Place materials in the work place with consideration of safety and crane movement.

5. Each subcontractor takes responsibility of tools and orneriness of his work area.

6. Seiso/Shine: Hire sufficient numbers of cleaners who maintain the cleanliness of the workplace permanently and continuously.

7. Everyone should be a janitor in the workplace as everyone cleans his area after finishing the activity.

8.

Seiketsu/Standardize: Standardize the way of maintaining cleanliness, and design a checklist to apply all standards of cleanliness and required tidiness.

9. Shitsuke/Sustain: Maintain all previous practices daily throughout the project and make it a way of life. "Commitment"

Applying Increased Visualization tool

10.

Conducting a workshop for all employees to sign on a commitment to comply with all safety and security requirements, and attach the pledge to the caravan wall.

11. Use colorful signage, especially for the application of security and safety guidelines.

12. Usebillboardsto explain the implementation of project stages and the delivery dates.

13. Calculate Plan Percent Complete (PPC) periodically and attachresults charts on the caravan walls.

Page 122: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

103

Applying Huddle Meeting tool

14. Weekly meeting of all foremen; to discuss the weekly plan and all issues and potential problems.

15. A quick day-to-day meeting of the project staff to discuss the work carried out the day before and what is planned for the current day.

Applying Visual Management

16. Give information about the activities to affect workers' behavior (without obliging). Ex: boards, charts, logs, photos, maps etc.

17. Grab workers' attention visually to give them a guide and obligate them to follow. Ex: light boards and safety signage.

18. Control workers' behaviors physically by determining how to work correctly in compulsory way. Example: Set a border defines the area of work.

19. Control processes electronically or mechanically to guarantee the right response with zero risk.

Part IV: Investigate the effect of increasing transparency on LC principles. The following table shows lean construction principles. Please choose degree of

effect of increasing projects transparency on supporting and facilitating the

application of these principles, in which 10 is the highest effect, and gradually

decrease to 0 as there is no effect.

Degree of Applying (0 - 10)

LC Principles No.

Reduce of non-value-adding activities. 1.

Increase output value through systematic consideration of customer requirements. 2.

Reduce project variability. 3.

Reduce project cycle time. 4.

Simplify by minimizing the number of steps, parts and linkages between activities.

5.

Increase flexibility in work and output. 6.

Page 123: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

104

Degree of Applying (0 - 10)

LC Principles No.

Focus control on the complete process. 7.

Build continuous improvement into the process. 8.

Balance flow improvement with conversion improvement. 9.

Conduct reference studies, and lesson learnt (Benchmarking) 10.

Part V: Evaluate benefits, success factors and challenges of applying the concept of increasing transparency. The following is a list of benefits of increasing projects transparency. In your

experience, please choose the degree of your consent for each mentioned benefit,

in which 10 is totally agree and gradually decrease to 0 as you do not agree at all.

No. The Benefits Degree of consent (0 - 10)

1. Save time spent in searching, wandering, or waiting for the tools, materials, and information needed to do work.

2. Increase the efficiency of workers as reduce wastage in efforts.

3. Increase the effectiveness of the production planning and control process.

4. Increase the visibility of errors (Defects are more visible and easier to recognize)

5. Reduce the propensity to errors.

6. Facilitate a holistic view of the entire process and to implement flow.

7. Build trust and motivation of participants.

8. Support and involve workers at continuous improvement.

9. Stimulation of informal contact between the different hierarchical positions.

10. Contributions towards introducing decentralization policies.

11. Simplification of the production control systems.

12. Reduce reworks that don't comply with drawings and specifications.

Page 124: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

105

The following is success factors for applying transparency in Gaza Strip. In your

experience, choose the degree of your consent for each mentioned success factors,

in which 10 is totally agree and gradually decrease to 0 as you do not agree at all.

No. Success Factors Degree of consent (0 - 10)

1. Establish strong management, structured and systematic plan to implement visual systems.

2. Establish a visual mechanism to inspire or motivate workers to carry out their jobs efficiency and effectively.

3. Training and hands-on experience in order to make managers fully knowledgeable about benefits of transparency principle and its impact on production system.

4. Forcing the reduction of inventories to some extent.

5. Tightening production plans.

6. Reducing process variability to facilitate the implementation of visual control systems.

The following is a list of challenges facing the application of increasing projects

transparency in Gaza Strip. In your experience, please choose the degree of your

consent for each mentioned challenges, in which 10 is totally agree and gradually

decrease to 0 as you do not agree at all.

No. The Challenges Degree

of consent (0 - 10)

1. Misunderstanding of Lean systems approach as organizations tend to confuse “Lean thinking” with the application of a tool or a set of tools in practice.

2. Lack of knowledge as managers are not aware of process transparency benefits.

3. Restrict to traditional conversion model and manager's fear to changes into unknown approach to them.

4. Difficulties in communication in construction.

5. Changeable work environment as site layout modified several times throughout the project.

6. Large place of work site where large numbers of crews spread out and move continuously.

7. Low level of participation of workers in improvement process.

Thanks for cooperation.

Page 125: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

106

Appendix (II): The Questionnaire "Arabic"

:إستببت حىل

دراست يذي لببهت تطبك يبذأ سبدة انشفبفت ف إطبر االشبء انز ف لطبع غشة

The Applicability of Increasing Transparency Principle within Lean Construction in

Gaza Strip

اغال ػ١ى سؽخ هللا ،، / اغبدح اىشا

شىش ى غبزى ف لزى عذو زؼجئخ ز االعزجبخ؛ از رذف ئ دساعخ ذ شفبف١خ اشبس٠غ

زا ٠شع ؽؼشارى رؼجئخ . االشبئ١خ ف لطبع غضح، ػا رؾغ١ اشفبف١خ خالي ظ االشبء اش

اإلعزجبخ ثذلخ طي ئ ازبئظ اشعح ز اذساعخ، وب أ اؼبد از عف رم ثزوشب

. عزغزخذ ألغشاع اجؾش اؼ فمؾ

ظ ؽذ٠ش غج١اب ف غبي اداسح اشبس٠غ ٠ذف ا رم١ و١خ : Lean Construction))االشبء اش

ر ازشو١ض ف زا اجؾش . افبلذ ف الذ ااد اطبلخ اجشش٠خ ب٠إد ا رم١ رىفخ اششع االشبئ

ػ أداد االشبء اش از رخذ شفبف١خ اشبس٠غ االشبئ١خ ؽ١ش رؼزجش ص٠بدح اشفبف١خ أؽذ أ أذاف

. االشبء اش، از رإد ا رم١ و١خ افبلذ ثبشبس٠غ االشبئ١خ

رف١ش شجىخ اؼبد اخبطخ ثبششع ثؾ١ش رى زبؽخ غ١غ، : (Transparency)اشفبف١خ

رؾغ١ ازاط ث١ ع١غ االؽشاف راد اؼاللخ ثبششع؛ زغ١ ؼشفخ أبو اخطأ رم١ افبلذ

رؼزجش اؼ١خ االشبئ١خ شفبفخ ػذب ٠غزط١غ اغ١غ ؽز ر اخجشح . ؼشفخ اػغ افبلذ ف لغ اؼ

. اؾذدح ف خؾ ع١ش األشطخ اظشح األ لغ اؼ

أعضاء؛ خغخرزى ز االعزجبخ

. ؼبد ػبخ ػ ششوخ امبالد اذط ذخ اج١ببد: اغضء األي

. ف اشبس٠غ االشبئ١خ ف لطبع غضحػا رؾغ١ اشفبف١خدساعخ : اغضء اضب

. رم١١ أداد االشبء اش ابعجخ زطج١ك اشفبف١خ ف اشبس٠غ االشبئ١خ:اغضء اضبش

.رأص١ش رطج١ك جذأ ص٠بدح اشفبف١خ ػ جبدب االشبء اش: اغضء اشاثغ

.رم١١ فائذ ػا اغبػ ازؾذ٠بد ف رطج١ك جذأ ص٠بدح اشفبف١خ: اغض اخبظ

أظ ع أث دلخ : اجبؽش

خبذ اؾالق . د: اششف

2017اثش٠

.شبوش٠ ى ؽغ رؼبى

Page 126: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

107

(√ )٠شع اخز١بس اإلعبثخ ابعجخ ثػغ ئشبسح: يؼهىيبث ػبيت حىل شزكت انمبوالث ويذخم انبببث: أوالال

: انس انىظف نهشخص انجب .1

ذ٠ش اششوخ ذ٠ش ششع ذط لغ ذط ىزت

: ػذد سىاث انخبزة انخبصت ببنشخص انجب .2

عاد 5أل 5 - 10أل

عاد

10 - عخ 20أل 20فأوضش عخ

يكب يمز انشزكت .3

اؾبفظبد

اغث١خ

اؾبفظخ اعط ؾبفظخ غضح اؾبفظخ اشب١خ

: ػذد سىاث انخبزة انخبصت ببنشزكت .4

عاد 5أل 5 - 10أل

عاد

10 - عخ 20أل 20عخ فأوضش

: ػذد انىظف انذائ ف انشزكت .5

5أل

ظف١

5 -10 ظف 11 -20 ظف 20أوضش

ظف : ػذد انشبرغ انت تى تفذهب خالل انخس سىاث انبضت .6

10أل

شبس٠غ

10 -20 ششع 21 -30 ششع 30أوضش

ششع : (ببنذوالر األيزك)انؼذل انسى نمت انشبرغ انت تى تفذهب خالل انخس سىاث انبضت .7

١ 1أل 1 - ١ 5أل 5 أل - ١

10 ١

10١ فأوضش

:تصف شزكت انمبوالث .8

صبضخ صب١خ أ ازظ١ف / ؽج١ؼخ اؼ

يبب

طزق ويىاصالث

يب ويجبر

كهزويكبك

: ، وػه درات ببنفهىو واألدواثLean Construction يؼزفت بهج االشبء انز أيتهك .9

ثذسعخ ػب١خ ثذسعخ زعطخ ثذسعخ ػؼ١فخ ثذسعخ ؼذخ

انشفبفت ف انشبرغ االشبئت تحس دراست ػىايم : ببال

اششوخ درجت تطبكاؼا اشفمخ ثبغذي ازب رض ػا اشفبف١خ ثبشبس٠غ االشبئ١خ، ثشعبء اخز١بس

ؽ١ش 0 أػ دسعخ رض رطج١ك اؼب دبا، رم اذسعخ ثبزذس٠ظ ا 10ز اؼا ف االغ ؽ١ش

و ػب زؾغ١ شفبف١خ اشبس٠غ االشبئ١خ ثمطبع غضح درجت أهتوب شع اخز١بس /ال٠ز رطج١ك اؼب ثزبربا

. ١خرؼذ األؽ١ش 0 رض أ١خ ػب١خ، رم ثبزذس٠ظ ا 10ؽ١ش

Page 127: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

108

ػىايم انشفبفت نزلىا

درجت

انتطبك

(10 – 0)

درجت

األهت

(10 – 0)

. رم١ اإلػزبد٠خ ث١ أشطخ اششع ف الذ ااد ىب اؼ .1

2. بدسان األخطبء إلاعزخذا أداد ازؾى اشئ اؽخ : اشبو عش٠ؼا

.اإلداسح ثغشػخ ػ أ خ ٠ؼشل اؼ ومض اادرج١ اؼئ١خ ي

3.

خالي(ف١ض٠بئ١با )عؼ أظخ أشطخ اششع شئ١خ اػؾخ

ػغ خبسؽخ لغ، : ازخط١ؾ ابعت لغ اعزخذا االفزبد

ألبو، ع١بط شئ ؽي الغ ٠غؼ ثشؤ٠خ الغ رػؾبالفزبد

. اخبسط، اػبءح وبف١خ ف و صا٠ب الغ

4. خالي ؽي أشطخ اششع رغغ١ذ رؼ١ ؼبد ف ىب اؼ

. ؽبد ػشع، اؽظبئ١بد، ف١ذ٠بد ؽي اششع األشطخ افزح

رشر١ت رظ١ف لغ اؼ ثبعزشاس، اؾشص ػ اصاخ افػ .5

. اىب

6. إششاد األداء : ضبي. اعزخذا امب١٠ظ ىشف ػ وفبءح عدح اؼ

Performance Indicators ،ل١بط غجخ اإلغبص ازأخ١ش.

تمى أدواث االشبء انز انبسبت نتطبك انشفبفت ف انشبرغ االشبئت : بنلبال

اششوخ دسعخ رطج١كف١ب ٠ لبئخ ثأداد االشبء اش از رؾمك شفبف١خ اشبس٠غ االشبئ١خ، ثشعبء اخز١بس

ؽ١ش ال٠ز 0 أػ دسعخ رض رطج١ك األداح دبا، رم اذسعخ ثبزذس٠ظ ا 10ز األداد ف االغ ؽ١ش

رض 10شفبف١خ ؽ١ش أع رطج١ك جذأ ص٠بدحاي و أداح دسعخ أ١خوب شع اخز١بس/ رطج١ك اي أداح ثزبربا

. رؼذ األ١خ ؽ١ش 0أ١خ ػب١خ، رم ثبزذس٠ظ ا

أدواث االشبء انز انزلى

درجت

انتطبك

(10 – 0)

درجت

األهت

(10 – 0)

S ( Sort – Straighten – Shine – Standardize Sustain ) 5: تطبيق أداة

1. ػشس٠خ ثبلغ، ازأوذ ايازخض امبخ و ااد غ١ش : ػهت انفزس

افظ ث١ ) أ ع١غ األداد اؼطثخ عدح ف ىب خظض ب

.(ااد االصخ غ١ش االصخ

2. اؾفبظ ، رغ١غ ااد األداد ف طبد٠مؼ ظ ؼ١:ػهت انتزتب

.ػ رشر١ت خض

3. ػغ األعضح األداد ف أبوب اظؾ١ؾخ لش٠جاب أبو اعزخذاب ف

. الغ

4. شاػبح ؽشوخ اؼبي ػا اغالخ األب ػذ رشر١ت رظ١ األداد

. األعضح ثبلغ

5. ٠ؼ و مبي ثبؽ ػ رشر١ت أدار رؾ غئ١خ اظب ف اطمخ

. اخبطخ ثؼ ف الغ

6. رظ١ف ػذد وبف ػبي اظبفخ ؾفبظ ػ اظبفخ ثشى : ػهت انتظف

. دائ غزش

Page 128: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

109

أدواث االشبء انز انزلى

درجت

انتطبك

(10 – 0)

درجت

األهت

(10 – 0)

اىب ٠ؼ و شخض ػ ظبفخ ار ، ثظبفخ الغازب ع١غ اؼب١ .7

. ثغشد االزبء اشبؽ

8.

رظ١ رط ٠ؾز ػ ؼبد أعبع١خ ػ و شبؽ ف و : وضغ انؼبز

زطج١ك و ؼب١٠ش اظبفخ ازشر١ت checklistلغ اؼ لبئخ رذل١ك

.اطثخ

9.

االؼجبؽ اؾفبظ ػ ع١غ ابسعبد اغبثمخ ١٠با د امطبع : االستذايت

. ؽاي فزشح اششع ف ع١غ أؾبء الغ، عؼب أعة ؼزذ ف اؼ

"ازضا"

Increased Visualizationتطبيق أداة

10. رل١غ ع١غ اؼب١ خالي سشخ ػ ػ رؼذ ثبالزضا ثىبفخ زطجبربغالخ

.األب، رؼ١ك ازؼذ ػ وشفبخ الغ

خ عبرثخ الزجب خبطخ ثزطج١ك اسشبداد األ - زمخ-اعزخذا الفزبد .11

.اغالخ

.رؼ١ك ؽبد خبطخ ثشاؽ رف١ز اششع ، اػ١ذ ازغ١ اطثخ .12

13. ثشى دس رؼ١ك خططبد ازبئظ (PPC) ؽغبة غجخ االغبص خطؾ

.ػ وشفبخ الغ

The Huddle Meetingتطبيق أداة

14. اعزبع أعجػ غ١غ شالج اؼبي؛ بلشخ اخطخ األعجػ١خ ع١غ امؼب٠ب

.اشبو اؾزخ

15. بلشخ األػبي اغضح ثب١ اغبثك، ب ٠ عش٠غ طبل اششع؛اعزبع

١ اؾب خطؾ ي

Visual Managementتطبيق الادارة املرئية

16. دو )رمذ٠ ؼبد شئ١خ ؽي األشطخ زأص١ش ػ رظشفبد اؼب١ ثبلغ

. (انشاو

. ؽبد، سع ث١ب١خ، طس، خشائؾ: ضبي

17. ٠ظبي ؼخ خالي اظد أ اظسح العزة ازجب اؼب١

. الفزبد اغالخ االب، اؼئ١خاؽبد: ضبي. انشايهى بهبوؼ١خ

18. رؾذ٠ذ ؽش٠مخ اؼ اظؾ١ؾخ ثشى اضا ةفشبئالب ثزظشفبد اؼب١ انتحكى

.ػغ ع١بط ٠ؾذد غبي اؾشوخ: ضبي. ال غبي ؾ١بد ػ

19. ؼب اؼ اظؾ١ؼ ثذ أ انكتزوبال أو يكبكبال ازؾى ثغ١ش اؼ١بد

.غجخ خطأ

تأ ز تطبك يبذأ سبدة انشفبفت ػه يببدئ االشبء انز: رابؼبال

ص٠بدح اشفبف١خ ف دػ رغ١ رطج١ك اجبدب رأص١ش دسعخ االشبء اش، ثشعبء اخز١بس جبدبف١ب ٠ لبئخ

ؽ١ش ٠ؼذ رأص١ش ص٠بدح اشفبف١خ ف دػ رطج١ك 0، رم اذسعخ ثبزذس٠ظ ا رأص١ش أػ دسعخ 10 ؽ١ش ازب١خ

.اجذأ

Page 129: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

110

انتأ زدرجت يببدئ االشبء انزانزلى

(10 – 0)

.ياؾذ عد أشطخ ال رؼ١ف ل١خ ؼ .1

ص٠بدح ل١خ عدح اخشط ابئ ششع خالي دساعخ غخ زطجبد .2

. طبؽت اؼ

.عثبششازغ١ش رم١ اززثزة .3

.رم١ دسح اششع اض١خ .4

.رجغ١ؾ اب خالي رم١ ػذد اخطاد أعضاء اشاثؾ ث١ األشطخ .5

. ص٠بدح اشخ ثبؼ اخشعبد .6

. ازؾى اىب اشوض ثبششع وى .7

. ػ رؾغ١بد غزشح ثبششع .8

. رؾم١ك ازاص ث١ ازؾغ١بد ازذفمخ ازؾغ١بد ازؾ١٠خ .9

.اعشاء دساعبد شعؼ١خ، االعزفبدح اخجشح ازشاوخ .10

تمى فىائذ وػىايم انجبح وانتحذبث ف تطبك يبذأ سبدة انشفبفت : خبيسبال

ػ و فبئذح افمزىدسعخ ثشعبء اخز١بس خالي خجشرى ، خ فائذ ص٠بدح شفبف١خ اشبس٠غف١ب ٠ لبب

.غ١ش افك اجزخ0 دسعخ ، رم ثبزذس٠ظ اافمخ أػ دسعخ 10ؽ١ش زوسح

انفــىائـــــــذانزلى يىافمتكىدرجت

(10 – 0)

رف١ش الذ از ٠ؼ١غ ف اغإاي اجؾش ازظبس األداد ااد اؼبد .1

. االصخ م١ب ثبؼ

. ص٠بدح وفبءح اؼبي ار أب رؾذ ذس اغد .2

. ص٠بدح فؼب١خ ػ١خ ازخط١ؾ اشالجخ، ازؾى ثشى أفؼ ثبششع .3

. ص٠بدح ػػ األخطبء، ار رظجؼ ػ١ة اؼ أوضش اىشبفبا غخ ادساوب .4

. رم١ ١ اؼب١ ؾ اخطأ .5

. رغ١ سؤ٠خ شبخ ؼ١خ ثأوب رف١ز األشطخ ثزذفك ٠غش .6

. ثبء اضمخ اذافؼ١خ ذ ع١غ اؼب١ .7

دػ ئششان ع١غ اؼب١ ف ازط٠ش اغزش ؼ، ار رظجؼ ػ١خ ازط٠ش .8

. عبؼخ رخض اى

. اش١خ اخزفخاالغرؾف١ض االرظبي غ١ش اشع ث١ .9

.الشوض٠خاغببد ف رطج١ك ع١بعبد .10

.اشالجخأظخ رغ١ رجغ١ؾ .11

. طبثك خططبد ااطفبداي٠م اػبدح اؼ اغ١ش .12

Page 130: The Applicability of Increasing Transparency Principle ... · Wastes have been recognized as a major problem in construction industry in Gaza Strip, and the level of material waste

111

و ػب ٠غب ف رطج١ك جذأ اشفبف١خ أهت درجت ، ثشعبء اخز١بس خ ػا غبػ ض٠بدح اشفبف١خف١ب ٠ لبب

.رؼذ أ١خ ؽ١ش 0 دسعخ ، رم ثبزذس٠ظ اأ١خ أػ دسعخ 10ؽ١ش

ػــىايـــــم انـجـــــبحانزلى درجت األهت

(10 – 0)

. عد ئداسح ل٠خ، خطخ ظخ غ١خ زطج١ك األظخ اشئ١خ ف الغ .1

. ئشبء آ١خ شئ١خ اػؾخ إلب رؾف١ض اؼب١ ػ رف١ز ظبئف ثىفبءح فؼب١خ .2

3. ازذس٠ت اؼ رجبدي اخجشاد زضم١ف اذساء ثضا٠ب جذأ اشفبف١خ أصش ػ غبػ

. اششع

. رخف١غ و١بد ااد ف اخبص ا ؽذ ب .4

. ػغؾ خطخ اؼ زى راد أشطخ ؾذدح فؼبخ .5

. رم١ ازغ١١شاد ف خش٠طخ الغ لذس اغزطبع زغ١ رف١ز أظخ ازؾى اشئ١خ .6

، ثشعبء اخز١بس خ ازؾذ٠بد از لذ راع رطج١ك ص٠بدح اشفبف١خ ف اشبس٠غ االشبئ١خ ثمطبع غضحف١ب ٠ لبب

.رؼذ األ١خ ؽ١ش 0، رم ثبزذس٠ظ ا أ١خ أػ دسعخ 10ؽ١ش و ػب أهتدرجت

درجت األهت انتحــذــــــبثانزلى

(10 – 0)

(10 – 0) 1. ػؼف اؼشفخ ثظ االشبء اش أصش ػ لطبع االشبءاد، ع اششوبد

.ثبجبدب األداد

. افائذ اؾم١م١خ زطج١ك جذأ اشفبف١خ ف اشبس٠غاؼشفخ ةػذ .2

. ازم١ذ ثبرط ازم١ذ الداسح ، اخف ازغ١١ش ظ اداس عذ٠ذ .3

.طؼثبد االرظبي ازاط ث١ اؼب١ ف طبػخ االشبء ثشى ػب .4

. ؽج١ؼخ ث١ئخ اؼ ازغ١شح، ار ٠زغ١ش شى الغ ػذح شاد خالي رف١ز اششع .5

6. عد أػذاد وج١شح اطال اؼبخ اخزفخ رزشش رزؾشن ثشى غزش ف غبؽخ

. اعؼخ

. اخفبع غز شبسوخ اؼب١ ف ػ١خ ازط٠ش .7

لحسن تعاونكم ،،شكرا