Upload
lucas-haynes
View
18
Download
0
Embed Size (px)
DESCRIPTION
The Assessment. SEA as part of a Strategic Sustainability Assessment Carried out between February 2004 and March 2006 by consultants but working closely with plan authors Challenge of assessing high-level strategic and detailed sub-regional policies. The Assessment. Three main phases of work - PowerPoint PPT Presentation
Citation preview
The Assessment
SEA as part of a Strategic Sustainability Assessment
Carried out between February 2004 and March 2006 by consultants but working closely with plan authors
Challenge of assessing high-level strategic and detailed sub-regional policies
The Assessment
Three main phases of workPhase 1: Deciding the scopePhase 2: Assessment of possible development
strategy optionsPhase 3: Assessment of the draft RSS policies
Note – the following slides provide “snapshots” of approaches used, not a full overview of the process
The Assessment – Phase 1
Deciding the scopeDecision to develop a small number of
Assessment objectives, reflecting strategic nature of plan
Development of guidance to enable organisations with local knowledge to compile sub-regional baseline information
The Assessment – Phase 1
Assessment frameworkOnly 6 high level objectives
Particularly relevant to SEA
The Assessment – Phase 1
Reasons for and benefits of small number of objectivesEmphasised issues at level the RSS can
influenceAimed to provide balance between enabling
manageable assessment, and providing sufficient detail to identify important issues
Enabled “2-tier” assessment: 1) strategic / high level and 2) more specific detailed questions
The Assessment – Phase 1
Assessment frameworkMore detailed criteria / questions to draw out
effects
The Assessment – Phase 1
Development of guidance for the collection of baseline at the sub-regional levelOpportunity taken to draw on existing sub-
regional expertiseThrough use of guidance each sub-region
collated baseline and conducted initial assessment
Role of consultants:Provided guidance on approach / framework for assessmentMeetings with each sub-regionReview and commentary on each sub-region’s workBringing reports together and harmonising
The Assessment – Phase 2
Development and assessment of alternative strategiesConsidered a range of housing and economic growth
scenariosConsidered different spatial development optionsAlternatives considered in assessment:
Growth at existing urban areas (previous strategy)More concentrated growth in smaller number of areasMore dispersed growthOne or more “new” townsGoing with past trendsPlus need to consider lower and higher housing growth
The Assessment – Phase 2
Assessment of alternative strategies
The Assessment – Phase 3
Assessment of Draft RSS policiesRegular communication, commentaries and
presentationsRegional Spatial Planning and Transport GroupSSA (including SEA) Steering Group
Challenge of assessing policy at both very strategic and detailed sub-regional levels
Use of maps in assessment
The Assessment – Phase 3
Regular communication and use of steering groupsA “steering group” was set up – provided advice as well as
some assessment inputComprised broad range of representatives (e.g.
Environment Agency, Local Authorities, Non Governmental Organisations)
Enabled informal discussions of assessment challenges and procedural issues
SEA teamSteering group
The Assessment – Phase 3
Strategic policy and detailed sub-regional assessmentFor strategic policies
Individual assessment matrices completed and recommendations made for each strategic policy
For the sub-regionsDetailed sub-regional studies undertakenSub-regional authorities completed initial assessments based
on guidanceFinal assessment drew on these initial assessments and
used constraint mapping to consider implications of the proposed locations of change
The Assessment – Phase 3
Maps used in sub-regional assessmentIdentified location of proposed development and
existing constraints (e.g. conservation areas, flood risks )
The Assessment
How it influenced the Draft RSSInformed the assessment of sub-regions by local
stakeholders, ensuring “ownership”Provided guidance on alternative strategiesReviewed early drafts of policies / strategyLed to specific changes to policies
Lessons learnt
Things that worked wellProcess ensured that authors and those who will
implement plan had “buy in” to SEA and saw its value
Regular meetings and 2-way communication with plan authors – e.g. use of steering groups
Use of existing sources of baseline information to help identify effects – maps were very useful
Lessons learnt
Things that worked less wellAssessment was
sometimes constrained by too short time-frames
Process was modified during assessment which added time and complexity
Ensure sufficient time is available – overestimate if in doubt!
Build in flexibility and seek broad agreement in method at outset
To find out more
Link to more information on the RSS and Assessment
http://www.southwest-ra.gov.uk/ And follow links to RSS
SA Report is at:
http://www.southwest-ra.gov.uk/media/SWRA/RSS%20Documents/Final%20Draft/ssamainreport1.pdf