THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims Manager, Europe/Latin America

THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

Embed Size (px)

Citation preview

Page 1: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND

REINSURERS BEFORE A LARGE LOSS OCCURRENCE

12th September - Istanbul

Georg Feierabend, Property Claims Manager, Europe/Latin America

Page 2: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

First steps before the Occurrence

1. Review Corporate Catastrophe Plan

Establish employee internal teams and duties

Identify and prepare alternate place to conduct business

Data base back ups

Review employee personal contingency plans

2. Secure Portfolio Information

List of probable loss by CRESTA Zone

Aggregates by risk

3. Local and International Adjuster Teams Selection

Establish Rates

Secure Agreements and Service Providers Contracts

Prepare uniformed forms and instructions as to the construction costs and unitary prices

Secure list of Approved Experts

Inspect high exposure risks

The insurer

The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence 2

Page 3: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

Critical Issues

1. Shortage of experienced licensed Adjusters

2. Shortage of resources to handle BI claims

3. Insufficiency of Insured’s information

4. Inadequate Insured's business recovery plans

5. Lack of employees recovery plans

The insurer

The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence 3

Page 4: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

4

Preparation before an occurrence (1/2)

The reinsurer shall:

Work out together with the cedent NatCat contingency

plans that can be adapted for the individual local

application

Check the capabilities of loss adjuster companies,

recommend loss adjusters and restoration companies

with proven expertise and good reputation (regional as

well as international background and network).

Carry out inspections together with the cedent to learn

about quality standards of the local risks and work out

improvement strategies, if necessary

The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence

The reinsurer

Page 5: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

5

Preparation before an occurrence (2/2)

Cooperation with the loss adjuster and the insurer to optimize the reporting.

Munich Re is interested in detailed reports about large single losses.

For smaller losses, it is necessary to provide bordereaux showing all affected risks and

every single loss amount.

For complex losses and losses on facultative risks, the involvement of the reinsurer is

generally necessary and shall be initiated by the client.

The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence

The reinsurer

Page 6: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

6

After the occurrence

The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence

The reinsurer

The reinsurer establishes reserves and submits advance payments

according to loss estimates of the insurers, confirmed by statistical models

of natural perils experts of the reinsurer.

Models of insurers and reinsurers/brokers should be aligned in close

cooperation before loss occurrences to avoid large discrepancies in case

of an event.

MunichRe offers local support with claims manager(s) and/or accounting

personnel to improve and accelerate the cooperation between insurer,

reinsurer, loss adjuster and insured.

Page 7: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

7

Preparation phase– coordination of activities between parties involved

No. Insurer Insurer Reinsurer AdjusterVolum. anal.

expert

Accounting expert

Restoration company

Insured

1 Identify Cat scenarios and areas of risks that may be affected X   X X   X  

2 Elaborate own business continuity plan X   X        

3 Review general policy terms X ●          

4 Issue policies and properly inform insureds on scope of cover and limits X            

5 Inspect the risks and draw up loss prevention recommendations X ●         X

6 Agree collaboration with adjusters, experts and restoration companies X X X X X X  

7 Obtain individual contingency plans for adjusters, experts and restoration companies X   X X X X  

8 Obtain individual contingency plans from adjusters, experts and restoration companies X   X   X    

9 Inform loss adjusters and accounting experts on scope of covers and limits X X X        

10 Agree on method of reporting X   X X   X  

11 Prepare check lists X X          

12 Establish funds for dealing with losses immediately X X          

13Annual meeting: to update contingency plans with all parties involved (for hurricane scenarios, before the start of the hurricane season)

X   X     X  

X = involved party; ● = Optional The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence

Page 8: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

8

Actions following the NatCat occurrence coordination of activities between parties involved

No. Insurer Insurer Reinsurer AdjusterVolum. anal.

expert

Accounting expert

Restoration company

Insured

1Organize an emergency meeting to coordinate concrete activities when a hurricane is imminent or in the immediate aftermath of a cat event

X ● X X X X

2 Quantification of staff needs X X X X X

3 Assign specific works and tasks X X X X X

4 Instruct/engage adjusters, experts and restoration companies X ● X X X X

5 Inform again loss adjusters and accounting experts on scope of covers and limits X X X

6 Coordinate travel to the disaster area X X X

7 Coordinate lodging and service offices X X X X

8Purchase / hire of generating equipment and fuel, including operating and servicing personnel

X X X

9 Coordinate mobilisation of restoration equipment and materials X

10 Mobilisation to the disaster area X X X X

11 Obtain accommodation / food / drink in the disaster area X X X

12 Mobilisation of equipment and material X X

13 Set up provisional / temporary offices, workshops for restoration work X X X

14 Hire sheds to carry out the restoration work and keep the salvaged goods X X X

15 Inspect the risks affected / agree on measures to minimise damage X ● X X X X

16 Start restoration work asap X X X

17 Estimate of total damage X X X X

X = involved party; ● = Optional The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence

Page 9: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

9

Loss Adjusting– coordination of activities between parties involved

No. Insurer Insurer Reinsurer AdjusterVolum. anal.

expert

Accounting expert

Restoration company

Insured

1Carry out survey, evaluation and documentation of individual losses together with the Insured’s representatives

X ● X X X X

2 Clearly separate direct damage from improvements or normal maintenance works X X X X

3 Draw up correct basis for unit prices and labour X X X

4 Estimate real cost of indemnifiable repairs and fix property damage reserves X X X

5 Coordinate repair and replacement work X X

6 Obtain financial data on the operation affected X X X

7 Estimate repair times and establish LOP reserves X X X

8 Recommend advanced payments where appropriate X

9 Advanced payments where appropriate X X

10 Verify appropriate execution of repair / replacement work affected X X X X

11 Obtain and verify invoices for repair / replacement X X

12 Quantification and sale of salvage X X

13 Final report on property damage X

14 Obtain accounting data on all of the property affected X X X

15 Verify that operations are resumed after completion of repairs

16 Final indemnity payment X

17 Final indemnity payment X X

18Draw up recommendations to avoid similar / identical losses in the future or at least minimize them as far as possible

X X X

X = involved party; ● = Optional The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence

Page 10: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

NatCat Claims Management

Individualmajor claims

Mass Claims: Very large

numberof small /

medium sizeclaims

Two different groups of claims that have to be tackled using different strategies

Residential risks Commercial / industrial risks

10The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence

Page 11: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

Experienced Example

27FChile

27 Feb. 2010

Earthquake of magnitude

8.8 Richter

+

tsunami

Casualties: ~ 500

Insured loss: US$ 8bn

Munich Re reserve:

US$ 1.1bn

The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence 11

Page 12: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

12

Munich Re …

installed a task force in Santiago 5 days after the event

contacted the cedents immediately and offered quick support in form of advanced

payments

agreed with cedents efficient processes, for e.g. adjusting massive numbers of

small claims

showed continuous local presence for the whole year 2010 with claims managers

actively participating in loss surveys

consulted the cedents in selecting loss adjusters or forensic accountants for

large, complex claims

conducted claims reviews at the claims dept. of ceding companies

collaborated with the local association of insurers for drafting lessons learnt

The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence

Page 13: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

13

The Chilean Insurance Market in the immediate aftermath of the event

Weakness of the infrastructure in the affected area aggravated the situation

- Utilities (electricity, water, telephones/communication network incl. cell phones)

interrupted for several days

- Damaged roads, fallen bridges, i.e. difficult access

- Hotel capacities largely reduced

Curfew limited the mobility during the initial weeks

Employees of industrial companies did not go to work for several days in order to

stay with their families.

Lack of manpower and of construction material retarded the beginning of loss

minimisation measures and of repair works.

The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence

Page 14: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

14

Problems related to the loss adjusting process

Chilean law allows adjustment only to locally authorised loss adjusting companies

Chilean law requires full settlement of claims affecting private lines within a

timeframe of 3 months from the date of the loss notification. Enforcement by the

Superintendencia de Valores y Seguros, Chile (SVS)

Mass losses at private buildings/apartments (mortgage insurance)

- Multiple loss notifications from the insured, the broker or the bank

- One building/several owners/different insurance policies

- Difficulties to decide on demolition vs. repair

Large industrial risks: Lack of clarity of certain insurance policies, i.e. on sums

insured for business interruption

Uncertainties regarding preliminary loss estimates, in particular with business

interruption claims

“Public Adjusters” who work for the insured and raise expectation of higher

indemnificationsThe cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence

Page 15: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

15

Role of the Loss Adjusters

Number of loss notifications superseded by far the initially available capacity of

local loss adjusters

For the adjustment of large, complex losses some of the local loss adjusters had

to require the help of their own or affiliated international organisations as well as

forensic accountants expert in business interruption losses

After 4 – 6 weeks the loss adjusters managed to drastically increase their

capacity in terms of manpower, office space, office equipment and could start to

work efficiently

Due to the very large number of claims the loss adjusters could not comply

entirely with the SVS requirements. They had to demand for and obtained a

general postponement of the compulsory time limit of 3 months for claims

settlement.

By the end of 2010 the vast majority of the householders claims could be settled

The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence

Page 16: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

16

Total 31 Aug. 2010 28 Feb. 2011

Paid indemnification: USD 2.190 bn USD 4.656 bn

Commercial / Industrial 31 Aug. 2010 28 Feb. 2011

Number of claims notifications: 31,866 31,811

Liquidated claims: 16,970 28,294

Closed claims (paid or to be paid): 8,793 15,666

Not indemnifiable (e.g. below deductibles): 7,298 12,152

Paid indemnification: USD 3.365 bn

Homeowners 31 Aug. 2010 28 Feb. 2011

Number of claims notifications: 190,199 189,491

Liquidated claims: 156,242 188,478

Closed claims (paid or to be paid): 105,694 125,904

Not indemnifiable (e.g. below deductibles): 46,336 62,574

Paid indemnification: USD 1.291 bn

Statistics

The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence

Page 17: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

Mass Claims - Impact of Deductibles

Regulations in Chile

Deductibles are regulated for residential and commercial risks as follows:

• Residential risks: 1% of sum insured, min. UF 25 (approx. USD 1.000)

• Commercial risks: 2% of sum insured, min. UF 50 (approx. USD 2.000)

Consequences

Homeowners started complaining against the height of the deductibles and

this turned out to be a political issue. The Superintendency (SVS) asked the

insurance industry to withdraw the deductibles.

The insurance industry did not accept and explained why deductibles are

absolutely needed in case of NatCat.

17The co-operation of insurers, loss adjusters and reinsurers before a large loss occurrence

Page 18: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

0 25 50 750

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

Claims below deductible (22.000)

Number of Claims vs. Deductible [UF]

Mass Claims – Residential Risks Portfolio (example)Number of Claims

Deductible [UF]

Num

ber

of c

laim

s

UF 1 = approx. USD 40

The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence 18

Page 19: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

19

0 25 50 750

20,000,000

40,000,000

60,000,000

80,000,000

100,000,000

120,000,000

140,000,000

Deductible [UF]

Indemnity 100% [USD] vs Deductible [UF]

UF 1 = approx. USD 40

Claims below deductible (ca. USD 28 m)

Mass Claims – Residential Risks Portfolio (example)Amount of Indemnity

The cooperation of insurers, loss adjusters and reinsurers before a large loss occurrence

Page 20: THE COOPERATION OF INSURERS, LOSS ADJUSTERS AND REINSURERS BEFORE A LARGE LOSS OCCURRENCE 12 th September - Istanbul Georg Feierabend, Property Claims

Georg Feierabend

THANK YOU FOR YOUR ATTENTIONLET’S WORK TOGETHER!