Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
Report No. CTI-UCD-2-94
The Deep Patch
Technique for
Landslide Repair
Bassam M. Helwany Colorado Transportation Institute 4201 East Arkansas Avenue Denver, CO 80222
Final Report October, 1994
in cooperation with the Irtment of Transportation ighway Administration
Technical Report Documentation Page
1. Report No. 2. Government Accession No.
CTI-UCD-2-94
4. Title and Subtitle
The Deep Patch Technique for Landslide Repair
7. Author(s)
Dr. M. Bassam Helwany
9. Performing Organization Name and Address
Colorado Transportation Institute
4201 East Arkansas Avenue
Denver, CO 80222
12. Sponsoring Agency Name and Address
Colorado Department of Transportation
4201 East Arkansas Avenue
Denver, CO 80222
15. SuppJementaIy Notes
3. Recipient's Catalog No.
S. Report Date
October, 1994
6. Performing Organization Code
8. Performing Organization Rpt.No.
10. Work Unit No. (TRAIS)
11. Contract or Grant No.
93-482
13. Type of Rpt. and Period Covered
Final Report
14. Sponsoring Agency Code
270.01
Prepared in Cooperation with the U.S. Department of Transportation and the U.S. Forest
Service
16. Abstract
This report describes the laboratory testing of the "USFS deep patch" technique and a cn modification of this technique for repairing landslides with geosynthetic reinforcement. The technique involves replacing sections of roadway lost due to landslides on top of a geosyntheticaUy-reinforced embankment. The cn modification involves replacing the reinforced slope with a geosynthetically-reinforced retaining wall with a truncated base. Both techniques rely on the cantilevering ability of the reinforced mass to limit the load on the foundation with a high slide potential.
The testing was done in a plane-strain device, (8 feet high, 16 feet long, and 3 feet wide) with a floor that can be lowered down to simulate the loss of support due to additional sliding of the foundation. Both road base fill and shredded tire till were tested.
The tests with road base showed that (1) both the USFS and CI'I repair reduced effectively the adverse effects of local landsliding on the highway pavement by preventing crack propagation; (2) the USFS repair increased the stability of the repaired slope, which was in progressive failure, by reducing the stresses exerted on it; and (3) the cn repair produced substantially greater stresses on its foundation due to the truncated base of the reinforced mass. These higher stress of the cn method will probably aggravate the stability of the slope which was in the state of progressive failure before repair. The en method, however, provides a wider base for pavement reconstruction. Tests with shredded tires found that excessive deformation makes them unsuitable for either repair technique.
17. Key Words
geosynthetic, landslide
reinforcement, shredded tires
19.5ecurity Classif. (report)
None
ZO.security Classif. (page)
None
i
18. Distribution Statement
No Restriction
21. No. of Pages 22. Price
118
11
PREFACE
This Research Project was sponsored by the Colorado Transportation
Institute (CTI). Professor Jonathan Wu from the University of Colorado at
Denver was the Principal Investigator. Mr. Robert Barrett, a physical
science researcher I scientist III from the Colorado Department of
Transportation (CDOT) and the geotechnical research manager of CTI, was
.the General Manager of this project. Mr. John B. Gilmore, the chief
geologist of CDOT, Mr. Shan-Tai Yeh, a senior geotechnical engineer at
CDOT, and Dr. Trevor Wang, a bridge design engineer at cnOT have all
been involved in making this project successful.
iii
tv
TABLB OF CONTENTS
LIST OF TABLES
LIST OF FIGURES
CHAPTER
1. INTRODUCTION ......................•..........•........... 1
2. THE UNITED STATES FOREST SERVICE DEEP PATCH TECHNI QUE. . . . . . . . . . . . . . . . . . . . . . . . • . . . . . . . . . . . . . . • . . . . . . . . 4
2.1 THE DEEP PATCH TEST APPARATUS ....................... 4
2.2 CONSTRUCTION AND LOADING SEQUENCE ................... 6
2.3 TEST MA.TERI.ALS ....•................................. 8
2.3.1 THE GEOSYNTHETIC REINFORCEMENT ...•........ 8
2.3.2 THE GRAVELLY SAND ...........•............ I0
2.4 INSTRUMENTATION ..................................•. 11
2.4.1 TWO-COMPONENT LOAD CELL ....•............. 1l
2.4.2 HIGH ELONGATION STRAIN GAGE •............. 14
2.4.3 LUBRICATED LATEX GRID SYSTEM ..........••• 15
2.4.4 DI.AL INDICATOR .............•...........•• 16
2.5 RESULTS AND DISCUSSION OF RESULTS ................•. 17
2.6 SUMMARY AND CONCLUDING REMARKS .........•.......••.. 19
3. THE CTI DEEP PATCH TECHNIQUE ............................ 21
3 . 1 INTRODUCTION ....................................... 21
3.2 CONSTRUCTION AND LOADING SEQUENCE .................. 22
3.3 TEST MA.TERI.ALS ..................................... 24
3.3.1 THE GEOSYNTHETIC REINFORCEMENT .........•. 24
v
3.3.2 THE GRAVELLY SAND ........................ 24
3.4 INSTRUMENTATION .................................... 24
3.5 RESULTS AND DISCUSSION OF RESULTS .................. 25
3.6 THE CTI DEEP PATCH TECHNIQUE IN SILVERTHORNE ....... 27
3.7 SUMMARY AND CONCLUDING REMARKS ..................... 28
4 . THE CTI DEEP PATCH TECHNIQUE WITH SHREDDED TIRE .. AS BACKFILL ......................................... ;. .... 29
4 . 1 INTRODUCTION ....................................... 29
4.2 CONSTRUCTION AND LOADING SEQUENCE ............•..... 30
4.3 TEST MATERIALS ..................................... 30
4.3.1 THE GEOSYNTHETIC REINFORCEMENT ........... 30
4.3.2 THE SHREDDED TIRE ........................ 31
4 . 4 INSTRUMENTATION .................................... 33
4.5 RESULTS AND DISCUSSION OF RESULTS .................. 34
4.6 SUMMARY AND CONCLUDING REMARKS ..................... 35
5. SUMMARY AND CONCLUSIONS ................................. 37
5.1 SUMMARY ................................................................................... 37
5.2 CONCLUSIONS ........................................ 39
vi
List o~ Tables
Table 2.1 Magnitude and Duration of Drop Increments ........... 7
Table 2.2 Some Properties of the Geosynthetic Reinforcement ... S
vii
viii
Figure 1.1
Figure 1.2
Figure 2.1
Figure 2.2
Figure 2.3
Figure 2.4
Figure 2.5
Figure 2.6
Figure 2.7
Figure 2.8
Figure 2.9
Figure 2.10
Figure 2.11
Figure 2.12
Figure 2.13(a)
Figure 2.13(b)
Figure 2.14
Figure 2.15
List o~ Figure.
Schematic Diagram of the USFS Deep Patch Technique ................................................................. 42
Schematic Diagram of the CTI Deep Patch Technique .......................................................................... 43
The Deep Patch Test Apparatus ................. 44
The Front Crank which Operates the Front Two Jacks ...........•............•.•.... 45
The Back Crank which Operates the Front Two Jacks ..•...•....•...•.•.•........... 46
The Moveable Part of the Bottom Panel at 11 inch-Drop ............................... 47
The Vibratory Plate Compactor ..............•.. 48
Schematic Diagram of the Uniaxial Load-Deformation Apparatus .•........•......... 49
The Uniaxial Load-Deformation Test ............ 50
Steel Mold for Epoxy Application on the Two Ends of the Geotextile Specimen .....•. 51
Assembly of Steel Mold for Epoxy Application on the Two Ends of the Geotextile Specimen ....•..•..•...........•.... 52
Load-Deformation Behavior of the Geotextile Reinforcement ....••.......•........ 53
Grain Size Distribution Curve of the Gravelly Sand ............................. 54
Compaction Curve of the Gravelly Sand ......... 55
Triaxial Compression Test Results for the Gravelly Sand ............................. 56
Triaxial Compression Test Results for the Gravelly Sand ............................. 57
Instrumentation of the USFS Deep Patch Test ... 58
Schematic Diagram of the Two-Component Load Cell ................ .. .................... 59
ix
Figure 2.16
Figure 2.17
Figure 2.18
Figure 2.19
Figure 2.20
Figure 2.21
Figure 2.22
Figure 2.23
Figure 2.24
Figure 2.25
Figure 2.26
Figure 2.27
Figure 2.28
Figure 2.29
Figure 2.30
Figure 2.31
Figure 2.32
Figure 2.33
Figure 2.34
Instrumentation of the Two-Component Load Cell ..................................... 60
Steel Box for Load Cell Protection .•....•..•.. 61
The Load Cell Inside the Protective Steel Box .................................................................................... 62
Normal Stress Calibration of Load Cell .......• 63
Normal Stress Calibration Curves for Load Cell .............•......................•..... 64
Shear Stress Calibration of Load Cell ......... 65
Shear Stress Calibration Curves for Load Cell .......................................................................... 66
In-Soil Calibration of Load Cell .•............ 67
Strain Gage Mounting Method .......•............ 68
Strain Gage Covered with Protective Mixture . . . 69
Strain Gage Calibration in the Uniaxial Load-Deformation Test ..............••••.••.... 70
Calibration Curve for Strain Gage .......•..... 71
Environmental and Mechanical Protection of Strain Gages Using a Layer of Neoprene Rubber ................................................................................ 72
Geotextile Layer Instrumented with Strain Gages .................................................................................. 73
Lubricated Side-Wall Grid System (close-up) ... 74
Lubricated Side-Wall Grid System •..••...•..... 75
Displacement Field of the Backfill in the Unreinforced USFS Deep Patch Test .........•..... 76
The Crack Corresponding to 11 inch-Drop in the Unreinforced USFS Deep Patch Test ......... 77
Displacement Field of the Backfill in the Reinforced USFS Deep Patch Test ............... 78
Figure 2.35(a) Comparison of Crack Propagation in the Two Tests at 2 inch-Drop .......................... 79
Figure 2.35(b) Comparison of Crack Propagation in the Two Tests at 5 inch-Drop .......................... 80
x
Figure 2.35(c) Comparison of Crack Propagation in the Two Tests at 8 inch-Drop .......................... 81
Figure 2.35(d) Comparison of Crack Propagation in the Two
Figure 2.36
Figure 2.37
Figure 2.38
Tests at 11 inch-Drop .........•.........•....• 82
Comparison of Crack Propagation in the Two Tests ............................................................ 83
Distribution of Normal Stresses along the Bottom Panel in the Unreinforced USFS Deep Patch Test ...............•.................... 84
Distribution of Normal Stresses along the Bottom Panel in the Reinforced USFS Deep Patch Test .••.......•....•.......•.•.......••• 85
Figure 2.39(a) Distribution of Strain along the Geosyn-thetic Reinforcement Layer 1 in the Reinforced USFS Deep Patch Test ..........•.........••.... 86
Figure 2.39(b) Distribution of Strain along the Geosyn-thetic Reinforcement Layer 3 in the Reinforced USFS Deep Patch Test ......•.•......••......... 87
Figure 2.39(c) Distribution of Strain along the Geosyn-
Figure 3.1
Figure 3.2
Figure 3.3
Figure 3.4
Figure 3.5
Figure 3.6
Figure 3.7(a)
Figu~e 3.7(b)
thetic Reinforcement Layer 5 in the Reinforced USFS Deep Patch Test .....................•.... 88
Schematic Diagram of the CTI Deep Patch Test .• 89
The CTI Deep Patch Test at End of Construc-tion ........................................................... 90
Instrumentation of the CTI Deep Patch Test .... 91
Displacement Field of the Backfill in the CTI Deep Patch Test with Road Base Backfill ... 92
The Deformed Face of the CTI Deep Patch Test with Road Base Backfill after Removing the Berm ............................................................ 93
Distribution of Normal Stresses along the Bottom Panel in the CTI Deep Patch Test with Road Base Backfill ............................ 94
Distribution of Strain along the Geosynthetic Reinforcement Layer 2 in the CTI Deep Patch Test with Road Base Backfill .................. 95
Distribution of Strain along the Geosynthetic Reinforcement Layer 2 in the CTI Deep Patch Test with Road Base Backfill •.........•....... 96
xi
Figure 3.7(c) Distribution of Strain along the Geosynthetic Reinforcement Layer 6 in the CTI Deep Patch Test with Road Base Backfill •........•••...•.• 97
Figure 3.8
Figure 3.9
Figure 3.10
Figure 3.11
Figure 4.1
Figure 4.2
Figure 4.3
Figure 4.4
Figure 4.5
Figure 4.6
Configuration of the CTI Deep Patch in Silverthorne .................................. 98
Construction Procedure of the CTI Deep Patch in Silverthorne ...........................•... 99
Construction of the CTI Deep Patch in Silverthorne ......................•.......... 100
Construction of the CTI Deep Patch in Silverthorne ..•..•....••..............•..•..• 101
Schematic Diagram of the One-Dimensional Compression Test for Shredded Tire •.......•.. l02
The Load History of the One-Dimensional Compression Test on Shredded Tire ....•. .. .... l03
Stress-Strain Behavior of the Shredded Tire under One-Dimensional Compression ....•...••.. l04
Creep Behavior of Shredded Tire under a Constant Stress of 6.3 psi (arithmetic) ••.... 105
Creep Behavior of Shredded Tire under a Constant Stress of 6.3 psi (semi-logarithmic) ..............................•.. 106
Displacement Field of the CTI Deep Patch Test with Shredded Tire Backfill •.••........• 107
xii
CHAPTER 1
INTRODUCTION
The United States Forest Service (USFS) is currently using a new method
for landslide repair named "the USFS deep patch technique". The USFS deep patch
technique involves the removal of the top portion (5-6 feet-high) of the small-scale
sliding slope under a highway pavement and rebuilding that portion with the use
of horizontal layers of geosynthetic inclusions.
The USFS deep patch technique is illustrated in Figure 1.1. Figure 1.1 (a)
depicts a cross-section of a typical highway in a mountain region. Part of the
natural slope, which consists of inherently strong soil, is cut to allow for the
highway. The loose soil from the cutis used to fill, without compaction, the lower
part of the slope to form an extension to the existing foundation.
Due to the seasonal increase of pore water pressure in the soil combined with
soil creep and other factors, the fill part of the highway foundation may develop
a local landslide causing undesirable settlement in the highway pavement as shown
1
in Figure 1.1(a). The upper portion of the local landslide is removed and rebuilt,
as shown in Figure 1.1 (b) , utilizing horizontal layers of geosynthetic
reinforcement.
This study was aimed at investigating the effectiveness of the USFS deep
patch technique in (1) reducing the adverse effects of local landslides on highway
pavement and (2) increasing the stability of the repaired slope by reducing applied
normal stresses exerted on top.· The investigation was accomplished by devising
a large-scale apparatus, as shown in Figure 1.1 ( c), in which the USFS deep patch
technique can be closely simulated. Two large-scale deep patch tests were con
ducted. The first test, termed "the USFS unreinforced test", used a compacted
backfill without geosynthetic reinforcement, whereas the second test, termed "the
USFS reinforced test", used the same soil for backfill as the USFS unreinforced
test along with five equally-spaced horizontal layers of geosynthetic reinforcement.
Another deep patch technique, evolved from the USFS deep patch technique,
was also investigated. This technique, named the CTI (Colorado Transportation
Institute) deep patch technique, was suggested by Professor Zhenghuan Liao from
Chongqing University (P. R. of China). In the CTI deep patch technique the top
portion (5-6 feet-high) of the small-scale sliding slope under a highway pavement
is removed and then rebuilt in the form of a geosynthetic-reinforced soil "retaining
2
wall" with a reversed angle as shown in Figure 1.2.
There are two advantages of using the CTI deep patch technique. The first
advantage is the tolerance of the CTI deep patch to any subsequent settlement of
the repaired slope. If there is a tendency of further settlement in the repaired
slope, the geosynthetic-reinforced portion of the CTI deep patch will separate from
the repaired slope causing no distress in the highway pavement. The second
advantage of using the CTI deep patch technique is its ability to widen the highway
of an average of 4 feet as shown in Figure 1.2. Two CTI deep patch tests were
conducted using two different backfill materials. Road base class 1 backfill was
used in the first CTI deep patch test. On the other hand, shredded tire backfill,
which weighs approximately 1/3 of the road base backfill, was used in the second
CTI deep patch test.
3
CHAPTER 2
THE UNITED STATES FOREST SERVICE DEEP PATCH TECHNIQUE
2.1 THE DEEP PATCH TEST APPARATUS
A plane strain apparatus, within which the deep patch tests were conducted,
was devised and constructed. The state of plane strain, as defined in engineering
mechanics, is the state which occurs in structures that are not free to expand in
the direction perpendicular to the plane of the applied loads. If the applied loads
lie in the x-z plane (x is horizontal and z is vertical), then the displacement in the
y-direction is zero.
The apparatus, shown in Figures 1.1 (c) and 2.1, measures 8 feet high, 16
feet deep and 3 feet wide. The apparatus has two side panels, one back panel, and
a bottom panel. The bottom panel consists of two parts: a stationary 7 feet-long
part and a moveable 9 feet-long part. The moveable part is held:in place by four
jacks at its four corners as shown in Figure 2.1. The front two jacks can be
lowered simultaneously by the use of one crank. shown in Figure 2.2. The back two
4
jacks can also be lowered simultaneously by the use of another crank shown in
Figure 2 . 3. This arrangement allows the moveable panel to be lowered at the front
and at the back simultaneously in a uniform motion. Moreover, this arrangement
allows the moveable panel to be lowered at an angle. The 'moveable part can be
vertically lowered in a uniform manner about 1 foot. Figure 2.4 shows the moveable
panel at 1 foot drop.
~he side panels were constructed with 0 . 5 inch -thick transparent plexiglass
as shown in Figure 2.1. The back panel was made of a 0.75 inch-thick plywood.
The bottom of the testing apparatus was a rough surface created by gluing coarse
aggregate to its steel plate floor. The treated surface was covered with a 2 inch
thick layer of Ottawa sand before placing the first layer of geosynthetic sheet.
The side and back panels were heavily reinforced with 0.2 inch thick, 4.0 inches
by 2.0 inches rectangular steel tubing with center-to-center spacing of 2 feet
horizontal and 2 feet vertical. After the backfill was emplaced, the moveable part
of the bottom panel was gradually lowered to simulate progressive local landslide
such as the one shown in Figure 1.l(a) .
To insure plane strain condition for the deep patch backfill throughout the
test, the following three measures were taken:
(a) The test apparatus was made very rigid. The lateral deformation of the side
5
walls will be'negligible.
(b) The adhesion between the backfill and the side panel was minimized so that
the shear stress induced on the side walls became negligible. This was
accomplished by creating a lubrication layer between the side wall and
backfill. The lubrication layer consists of a 0.02 mm thick latex membrane
and a thin layer of silicone grease. This procedure has been used
extensively by Tatsuoka at the University of Tokyo and Wu at the University
of Colorado at Denver. The friction angle between the lubrication layer and
p1exig1ass as determined by direct shear test is less than one (1) degree
(Tatsuoka, et aI., 1984).
(c) The backfill was very uniform across the width of the deep patch test so that
there was practically no variations in terms of the geometry and the material
along the width of the wall.
2.2 CONSTRUCTION AND LOADING SEQUENCE
- Road base (class 1) backfill was placed in 6 inch -thick lifts to construct a 1 : 1 • 25
slope. Each lift was uniformly compacted using a vibratory plate compactor,
shown in Figure 2.5, in a consistent pattern. The relative compaction of the
backfill soil was approximately 98%. Upon completing the placement of two layers
6
of soil (12 inches-thick), a sheet of geosynthetic reinforcement was placed
horizontally.
- Upon reaching the full height of 6 feet, three 6 inch-thick layers of the same
backfill material, without reinforcement, were placed and compacted on the top
surface of the backfill as surcharge.
- Ten uniform drop increments of the moveable part of the bottom panel were
performed at a rate of 1 inch/minute. A waiting period followed each increment
to allow for taking measurements. Table 2.1 gives the magnitude and the
duration (drop time + waiting period) of each increment.
Table 2.1 Magnitude and Duration of Drop Increments
Increment Magnitude Duration (inches) (minutes)
1 0.2 5 2 0.2 5 3 0.2 5 4 0.4 20 5 0.5 ·5 6 0.5 20 7 1.0 20 8 2.0 20 9 3.0 20 10 3.0 20
7
2.3 TEST MATERIALS
2.3.1 THE GEOSYNTHETIC REINFORCEMENT
The reinforcement used in the tests was a nonwoven heat-bonded polypropylene
geotextile. Some of its index properties provided by the manufacturer are
presented in Table 2.2.
Table 2.2 Some Properties of the Geosynthetic Reinforcement
Unit weight (ASTM D-3776) Grab tensile (ASTM D-4632) Elongation at break. (ASTM D-4632) Modulus at 10% elongation (ASTM D-4632) A.D.S. (ASTM D-4751) Permittivity (ASTM D-4491) Coefficient of permeability Nominal thickness
60 %
1.93 N/m2 890 N
4.45 KN 0.101 mm
O.l/sec 1.99x10-4 cm/sec 0.508 mm
To evaluate the load-extension behavior of the geosynthetic reinforcement a
uniaxial load -deformation apparatus was devised and constructed. The apparatus,
schematically shown in Figure 2.6, consists of two steel clamps which can be rigidly
attached to the jaws of a MTS-810 machine as shown in Figure 2.7. The clamps
were set to accommodate a 30 cm (1 ft)-wide and 2.54 cm (1 inch)-long geotextile
sample (the aspect ratio of 12 to suppress "necking" of the geotextile sample). To
insure uniform straining, the geotextile sample was reinforced at its top and bottom
8
with a 0.6 cm (0.25 inch) -thick layer of high strength epoxy as shown in Figure
2.6.
To insure test accuracy and repeatability, the uniaxial load -deformation
apparatus was designed and constructed carefully taking the following measures
into consideration:
- The apparatus was made very rigid to avoid bending and rotation.
- The two clamps were precisely made parallel to each other, i. e., the initial
distance between the clamps (equal to the length of the geotextile sample) can
be preset, for example, to a uniform distance of 2.54 cm (1 inch).
- The geotextile sample was reinforced with a thick layer of high strength epoxy
at its top and bottom. A precision -made steel mold, shown in Figures 2.8 and
2.9, was used for that purpose.
Numerous load -deformation tests were performed on identical geotextile samples
under identical conditions. The repeatability of the test was excellent even under
different loading conditions such as uniaxial tension under constant strain rate,
creep, relaxation, and recovery (Helwany and Wu, 1994).
The uniaxial load-deformation behavior of the geotextile used in all deep patch
tests, tested at a constant strain rate of 1% per minute, is shown in Figure 2.10.
9
The results shown in the Figure were obtained by testing a geotextile specimen of
30 cm (12 inches) in width and 2.54 cm (1 inch) in gage length. The test was
performed without pressure confinement on the geotextile specimen. Previous tests
?f this geotextile have indicated that the load -extension behavior of the geotextile
is not affected by confining pressure up to about 300 KPa (Wu, 1991).
2.3.2 THE GRAVELLY SAND
The soil used in the gravelly sand backfill test was a brown gravelly sand
classified as A-1-B (Road Base class 1) with the grain size distribution curve
s~own in Figure 2.11 (Cu=15. 7 and Cc=O. 77). The specific gravity of the soil was
2.63. The optimum water content of the soil was 10.2% and the maximum dry
density was 19.84 KN/m3 (126.3 pcf).
The compaction curve of the backfill soil is shown in Figure 2.12. The in-situ
water content of the backfill soil in all deep patch tests was approximately 8.5%.
The corresponding dry density was approximately 19.8 KN 1m3 (126.0 pcf) with a
relative compaction of approximately 99%.
Three CD triaxial compression tests were performed on the gravelly sand at
three confining pressures: 103 KPa, 207 KPa and 310 KPa (15 psi, 30 psi and 45
psi). The gravelly sand was compacted to achieve a dry density of approximately
10
•
19.8 KN/m3 (126.0 pcf) at 8.5% water content (similar to the in-situ condition in the
deep patch tests). The results of the CD tests are shown in Figure 2.13.
2.4 INSTRUMENTATION
All tests were instrumented to measure their behavior during construction and
upon dropping the moveable part of the bottom panel. A number of different
instruments were used to monitor the performance of the tests. They were two-
component load cell, high-elongation strain gage, lubricated latex grid and dial
indicator. Figure 2.14 illustrates the location of instrumentation in the USFS deep
patch tests. Instruments were read by a MEGADAC 2200C data acquistion system.
2.4.1 Two-Component Load Cell
Six two-component load cells capable of measuring normal and shear stresses at
the same point were installed along the bottom panel to monitor the stresses exerted
to it by the backfill. These load cells have been used successfully by Tatsuoka and
his colleagues at the University of Tokyo (Huang and Tatsuoka, 1990) and by Wu
(1992b). A unique feature of the load cell is that there is a very little coupling
between the forces registered in the two orthogonal directions, i. e. , there is very
little coupling between the normal and shear stresses.
11
A schematic diagram of the load cell is shown in Figure 2.15(a). In the figure,
the normal stress applied to the load cell will cause stress concentration at the top
(and bottom) of the horizontal cavities. On the other hand, the shear stress
applied to the load cell will caus,e stress concentration at the top (and bottom) of
the vertical cavities. Four strain gages arranged in full bridge configuration are
set in stress concentration regions resulting from the application of normal stress.
Another four strain gages arranged in full bridge configuration are set in stress
concentration regions resulting from the application of shear stress as shown in
Figure 2.15(a). The method of wiring the full bridge configuration is shown in
Figure 2.15(b). Figure 2.16 shows a fully-instrumented load cell.
The method of mounting the load cell on the bottom panel is shown in Figure
2.15(c). To insure realistic and accurate measurements of normal and shear
stresses exerted to the bottom panel by the backfill, the exposed surface of the
load cell has to be even with the inner surface of the bottom panel as shown in the
figure. The load cell was secured inside a 1. 25 cm (0.5 inch)-thick steel box,
shown in Figures 2.17 and 2.18, which was placed inside the bottom panel as shown
in Figure 2.15(c).
To calibrate the load cell for normal stress, the load cell was horizontally
positioned on a flat rigid surface and a vertical dead weight was applied to its top
12
surface in small in~rements as shown in Figure 2.19. The calibration curve of
normal stresses for load cells 1, 2, 3 and 4 is shown in Figure 2.20. It is noted
from the figure that the response of the load cell to applied normal stresses is
linear.
To calibrate the load cell for shear stress, the load cell was vertically positioned
on a flat rigid surface and a vertical dead weight was applied in small increments
in the shear direction (parallel to the top surface of the load cell), using a special
frame shown in Figure 2.21. The calibration curve of shear stresses for load cells
1, 2, 3 and 4 is shown in Figure 2. 22. It is noted from the figure that the response
of the load cell to applied shear stresses is linear.
The load cells were further calibrated for normal stresses using a different
method. In this method a 30 em-thick layer of Ottawa sand confined inside a
plexiglass cylinder was placed on top of the load cell. A dead weight was applied
to the top of the Ottawa sand as shown iIi Figure 2.23. The normal stress
calibration factor of the load cell obtained from this method was 10-20% less than the
normal stress calibration factor of the load cell obtained from the previously
described calibration method. This was attributed to soil arching. It is to be
noted that the adhesion between Ottawa sand and the inner surface of the
plexiglass cylinder was minimized so that the shear stress induced on the inner
13
surface of the cylinder became negligible. This was achieved by creating a
lubrication layer between the inner surface and the sand similar to the one used
earlier in the plane strain loading facility.
2.4.2 High Elongation Strain Gage
High elongation strain gages were mounted along the length of the geotextile
sheets to measure tensile strains induced in the geosynthetic reinforcement. The
mounting method suggested by Billiard and Wu (Billiard, 1989; Billiard and Wu,
1991) for strain gage on "extensible" materials was employed. In this method the
strain gage is glued to the geotextile sheet only at the two extremities of the gage
as shown in Figure 2.24.
The strain gages were covered with a protective mixture made of wax and
petroleum jelly as shown in Figure 2.25. This was necessary to protect strain
gages from soil moisture. This procedure has been successfully used by Helwany
(1993) in a fully saturated clay.
The wax and petroleum jelly protective mixture was very flexible yet nearly
impermeable. To evaluate this procedure, five strain gages were mounted on a 30.0
cm (12 inch) by 5.08 cm (2 inch) geotextile specimen and covered with the
protective mixture. The specimen was then strained using the uniaxial tension test
14
apparatus (described previously). The gage factor calculated from the calibration
curves was nearly identical to that calculated frorp. the curves' for strain gages
without the protective mixture. Figure 2.26 illustrates the uniaxial tension test for
strain gage calibration (without the protective mixture). The calibration curve of
the strain gages (without the protective mixture) is shown in Figure 2.27.
The mounting procedure of a strain gage on the geotextile sheet involves gluin.g
the two extremities of the strain gage to the geotextile using high strength epoxy
(5-ton clear epoxy). The epoxy is left to cure for at least 8 hours, thereafter: a
0.6 cm (0.25 inch) -thick layer of the protective mixture is used to cover the strain
gage and its terminal. Another 0.6 cm (0. 25 inch) -thick layer of the protective
mixture is used to cover the strain gage and its terminal from the opposite side of
the geotextile to provide complete protection against the moisture seeping through
the geotextile. For further environmental and mechanical protection a layer of
Neoprene rubber was used on top of the protective mixture as shown in Figure
2.28. Figure 2.29 shows a geotextile layer instrumented with five strain gages
being placed in the test apparatus.
2.4.3 Lubricated Latex Grid System
A lubricated latex grid system was established on the side wall to measure the
15
internal movement of the slope. The lubricated side-wall grid system has been
used successfully by Wu (1992b) to measure the internal movement of the backfill
in full-scale retaining walls such as the Denver Test Walls. The lubricated side
wall grid system consists of a 0.02 mm thick latex membrane and a thin layer of
silicone grease. A grid, with a vertical spacing of 7.5 cm (3 inch) and horizontal
spacing of 7.5 cm (3 inch) , was sketched on the latex membrane as shown in Figure
2.30. The friction angle between the lubrication layer and plexiglass as determined
by direct shear test is less than one (1) degree (Tatsuoka, et al., 1984),
therefore, the deformation of the lubricated side-wall grid will reflect very closely
the deformation of the backfill. Figure 2.31 illustrates the lubricated latex grid
system of the USFS deep patch test at the end of construction.
2 .4.4 Dial Indicator
Four dial indicators were used to measure the movement of the moveable part of
the bottom panel.
16
2.5 RESULTS AND DISCUSSION OF RESULTS
The displacement of the slope, the bottom panel, and the top surface in the USFS
unreinforced test, as measured by the lubricated latex grid, is shown in Figure
2.32. A near vertical crack emanating from a point on the slope nearly above the
inner end of the moveable part of the bottom panel is shown in the figure. The
crack started with the first drop of 0.2 inch and propagated throughout the test
due to further drops of the moveable part of the bottom panel. The depth of the
crack was approximately 70 inches and its width was approximately 12 inches due
to the 11 inch drop in the moveable part of the bottom panel (see Figure 2.33).
In contrast, the deformation behavior of the backfill in the USFS reinforced test
was much more favorable than the one in the USFS unreinforced test. Several small
cracks, shown in Figure 2.34, were detected in the beginning of the USFS
reinforced test, however, their propagation was very limited due to the soil
reinforcement. The deepest crack measured about 10 inches (deep) due to the 11
inch drop in the moveable part of the bottom panel. A detailed comparison of crack
propagation of the two tests for different drops of the moveable part of the bottom
panel is shown in Figure 2.35
A comparison between the crack in the USFS unreinforced test and the largest
17
crack in the USFS reinforced test is shown in Figure 2.36. The crack in the
unreinforced case was at least 8 times deeper than the one in the reinforced case.
The measured normal stress distribution in the USFS unreinforced test along the
bottom panel is depicted in Figure 2.37. It is to be noted from the figure that the
normal stress has substantially increased with the increase of drop of the moveable
part of the bottom panel in load cell #5 (located at 70 inches from the back panel,
close to the moveable part of the bottom panel). On the other hand, the normal
stress in load cell #4 (located at 97 inches from the back panel) decreased with
increasing the drop until the drop of 3 inches was reached. Thereafter, the normal
stress in load cell #4 drastically increased with increasing the drop. This is may
be attributed to the total separation of the backfill, due to the aforementioned
vertical crack, into two soil masses located above the moveable and the stationary
parts of the bottom panel.
The measured normal stress distribution in the USFS reinforced test along the
bottom panel is depicted in Figure 2.38. A substantial reduction in normal stress
is measured along the moveable part of the bottom panel as shown in the figure.
The sudden increase in normal stress in load cell #4, noted in the USFS
unreinforced test, is not encountere~ in the USFS reinforced test. Obviously, the
geosynthetic reinforcement was able to absorb the tension crack which occurred
18
in the USFS unreinforced test preventing the total separation of the soil into two
masses.
The measured strain distribution along the geosynthetic layers 1, 3 and 5 located
at elevations 1,3 and 5 feet are shown in Figures 2.39(a), 2.39(b), and 2.39(c),
respectively. The maximum strain of approximately 4%, corresponding to 8 inches
drop of the moveable part of the bottom panel, was observed nearly in the center
of the geosynthetic layer 1. Unfortunately, the three central strain gages in this
layer were lost after the 8 inch -drop due to excessive straining.
At 8 inch-drop, the maximum strain of approximately 2.4% was observed in the
geosynthetic layer 3. Again, the strain gage located at 115 inches from the back
panel was lost due to excessive straining when the drop exceeded 8 inches.
Relatively smaller strains were observed in the geosynthetic layer 5. The
maximum strain of approximately 1.0% was measured in the strain gage located at
72.7 inch from the back panel.
2.6 SUMMARY AND CONCLUDING REMARKS
To investigate the effectiveness of the .USFS deep patch technique for landslide
repair, a large-scale laboratory test apparatus was devised and constructed. Two
slopes, one unreinforced and one reinforced with geosynthetic inclusions, were
19
constructed inside the apparatus in plane strain condition. The moveable part of
the bottom panel of the apparatus was gradually dropped to simulate progressive
local landslide. The response of each slope to the drop was carefully monitored.
The tests results showed that the unreinforced slope suffered a severe distress
throughout the test. A large vertical crack initiated in the beginning of the USFS
unreinforced test and propagated throughout the test to the extent that the slope
was virtually separated into two parts. On the other hand, the reinforced slope
remained intact throughout the test with the exception of the few cracks initiated
in the beginning of the test but were suppressed by the geosynthetic
reinforcements.
The stresses exerted on the moveable part of the bottom panel in the USFS
reinforced test were substantially smaller than those in the USFS unreinforced
test. This reduction in stresses will enhance the stability of the slope which was
in the state of progressive failure before the USFS deep patch repair.
This investigation showed that (1) the USFS deep patch repair reduced
effectively the adverse effects of local landslides on highway pavement by
preventing crack propagation, and (2) the USFS deep patch increased the
stability of the repaired slope, which was in progressive failure, by reducing the
stresses exerted to it.
20
CHAPTER 3
THE CTI DEEP PATCH TECHNIQUE
3.1 INTRODUCTION
A new deep patch technique, evolved from the USFS deep patch technique, is
investigated in this Chapter. The new technique, named the CTI (Colorado
Transportation Institute) deep patch technique, was suggested by Professor
Zhenghuan Liao from Chongqing University (P. R. of China). In the CTI deep
patch technique the top portion (5-6 feet-high) of the small-scale sliding slope
under a highway pavement is removed and then rebuilt in the form of a
geosynthetic-reinforced soil "retaining wall" with a reversed angle as shown in
Figures 1. 2 and 3.1.
There are two advantages of using the CTI deep patch technique. The first
advantage is the tolerance of the geosynthetic-reinforced portion of the CTI deep
patch to any subsequent settlement of the repaired slope. If there is a tendency
of further settlement in the repaired slope, the geosynthetic-reinforced portion of
21
the CTI deep patch will separate from the repaired slope causing no distress in the
highway pavement. The second advantage of using the CTI deep patch technique
is its ability to widen the highway of an average of 4 feet as shown in Figure 1.2.
Two CTI deep patch tests were conducted using two different backfill materials.
Road base class 1 backfill was used in the first CTI deep patch test (described in
this Chapter). On the other hand, shredded tire backfill, which weighs
approximately 1/3 of the road base backfill, was used in the second CTI deep patch
test (described in Chapter 4).
3.2 CONSTRUCTION AND LOADING SEQUENCE
- Road base (class 1) backfill was used (without compaction) to construct a 4 ft
high berm on top of the 3 inch-thick sand layer (which was placed on top of the
bottom panel) as shown in Figure 3.1. The front face of the berm has the slope
of 1 (vertical): 1 .25 (horizontal). The inner face of the berm has the slope of
2.25:1.
- A long sheet of geosynthetic reinforcement (long enough to wrap around the soil
layer, i.e., the length of the sheet =2 x length of the soil layer + the height of
the soil layer) was positioned on top of the 3 inch-thick sand layer. The excess
22
length of the sheet was positioned on top of the berm.
- Road base (class 1) backfill was placed on top of the geosynthetic reinforcement
in 6 inch-thick lifts to construct the geosynthetic-reinforced portion of the CTI
deep patch. Each lift was uniformly compacted using a vibratory plate compactor
in a consistent pattern. The relative compaction of the backfill soil was
approximately 98%. Upon completing the placement of two layers of soil (total
thickness of 12 inches), the excess length of the geosynthetic reinforcement
layer was wrapped around on top of the compacted soil.
- The above procedure was · repeated until reaching the height of 4 feet.
Thereafter, the geosynthetic-reinforced portion of the CTI deep patch was
constructed vertically until the height of 7 feet was reached, as shown in
Figures 3.1 and 3. 2, using an L-shaped form made of plywood.
- Ten uniform drop increments of the moveable part of the bottom panel were
performed at a rate of 1 inch/minute. A waiting period followed each increment
to allow for taking measurements. Table 2.1 gives the magnitude and the
duration (drop time + waiting period) of each increment.
23
3.3 TEST MATERIALS
3.3.1 THE GEOSYNTHETIC REINFORCEMENT
The reinforcement used in the tests was a nonwoven heat-bonded polypropylene
geotextile. The reinforcement was described in Section 2.3.1 .
3.3.2 THE GRAVELLY SAND
The soil used in this test was a brown gravelly sand classified as A-1-B (Road
Base class 1). The soil was described in Section 2.3.2.
3.4 INSTRUMENTATION
The CTI deep patch tests were instrumented to measure their behavior during
construction and upon dropping the moveable part of the bottom panel. A number
of different instruments were used to monitor the performance of the tests. They
were two-component load cell, high-elongation strain gage, lubricated latex grid
and dial indicator. Figure 3.3 illustrates the location of instrumentation in the CTI
deep patch tests. A detailed description of instrumentation was given in Section
2.4.
24
3.5 RESULTS AND DISCUSSION OF RESULTS
The displacement of the CTI deep patch and the bottom panel, as measured by
the lubricated latex grid, is shown in Figure 3.4. It is noted from the figure that
the vertical part of the face of the CTI deep patch remains vertical (with very
limited lateral displacement) throughout the test. The maximum settlements of 7
and 16 inches were measured at the top of the wall corresponding, respectively,
to the 5 and 11 inches drop in the moveable part of the bottom panel. Figure 3.5
shows the CTI deep patch after removing the berm which followed the 11 inch drop
of the moveable part of the bottom panel. A gab between the bottom of the
structure and the moveable part of the bottom panel is to be noted in the figure.
A vertical crack emanating from a point on the top of the CTI deep patch near
the back panel is shown in the Figure 3.4. The crack started with the first drop
of. 0.2 inch and propagated throughout the test due to further drops of the
moveable part of the bottom panel. The depth of the crack was approximately 7 ft
and its width was approximately 1 inch due to the 11 inch drop in the moveable part
of the bottom panel.
The measured normal stress dis,tribution in the CTI test along the bottom panel
is depicted in Figure 3.6. It is to be noted from the figure that the normal stress
has substantially increased with the increase of drop of the moveable part of the
25
bottom panel in load cell #2- (located at 70 inches from the back panel, close to the
moveable part of the bottom panel). On the other hand, the normal stress in load
cell #1 (located at 97 inches from the back panel) decreased (as expected) with
increasing the drop of the moveable part of the bottom panel. The maximum stress
of approximately 12.0 psi was measured after berm removal (following the 11 inch
drop in the moveable part of the bottom panel) .
It is to be noted that the initial stresses measured in the CTI deep patch test are
higher than the initial stresses measured in the USFS unreinforced test (Figure
2.37). This is obviously due to the odd shape of the CTI deep patch.
The measured strain distribution along the geosyntl1etic layers 2, 4 and 6 located
at elevations 2, 4 and 6 feet are shown in Figures 3. 7(a), 3. 7(b), and 3. 7(c),
respectively. The maximum -strain of approximately 1.2%, corresponding to 11
inches drop of the moveable part of the bottom panel, was observed near the edge
of geosynthetic layer 2. At 11 inch-drop, the maximum strain of approximately
0.7% was observed in geosynthetic layer 4, whereas the maximum strain of
approximately 1% was observed in geosynthetic layer 6. A substantial increase in
measured strains corresponding to the removal of the berm is noted in the figures.
It is to be noted that the strains measured in the CTI deep patch test are smaller
than those measured in the reinforced USFS deep patch test.
26
3.6 THE CTI DEEP PATCH TECHNIQUE IN SILVERTHORNE
The newly developed CTI deep patch technique was used to repair a landslide
within the city of Silverthorne-Colorado in October, 1993. The cost of traditional
repair for the landslide could have easily exceeded $100,000, whereas the estimated
cost of the CTI deep patch technique was less than $15,000. This tremendous
reduction in cost could result in repairs to many present and future landslides
around Colorado that would go un-repaired or that would cost tremendous amount
of money with traditional technologies of landslide repair.
Figure 3.8 illustrates the configuration of the CTI deep patch in the Silverthorne
site. Six layers of compacted soil with geogrid reinforcement were used. The
construction procedure is very similar to the one described in Section 3.2. The
construction procedure, shown in Figure 3.9, involves making a 6 ft-deep cut in
the existing highway. The cut width was about 10 ft which was well beyond the
slip surface of the landslide. The geogrid reinforcement was then positioned on top
of the existing soil and on top of the berm which was constructed beforehand. A
1 ft-thick layer of soil was placed and compacted and the geogrid reinforcement was
wrapped around it. This was repeated until reaching the total height of 6 ft.
Figures 3.10 and 3.11 show the CTI deep patch during construction in
Silverthorne.
27
3.7 SUMMARY AND CONCLUDING REMARKS
To investigate the effectiveness of the CTI deep patch technique for landslide
repair, a large-scale plane strain laboratory test was conducted. The moveable
part of the bottom panel of the plane stain apparatus was gradually dropped to
simulate progressive local landslide. The response of the CTI deep patch to the
drop was carefully monitored.
The test results showed that the CTI deep patch remained intact throughout the
test with the exception of the tolerable crack near the back panel which initiated
in the beginning of the test and propagated throughout the test. However, the
stresses exerted to the bottom panel in the CTI deep patch test were substantially
greater than those in the USFS unreinforced test. This increase in normal
stresses, due to the odd shape of the CTI deep patch, will probably aggravate the
stability of the slope which was in the state of progressive failure before the CTI
deep patch repair.
28
CHAPTER 4
THE CTI DEEP PATCH TECHNIQUE WITH SHREDDED TIRE
AS BACKFILL
4.1 INTRODUCTION
Chapter 3 described the CTI deep patch technique which evolved from the USFS
deep patch technique. In the CTI deep patch technique the top portion (5-6 feet
high) of the small-scale sliding slope under a highway pavement is removed and
then rebuilt in the form of a geosynthetic-reinforced soil "retaining wall" with a
reversed angle as shown in Figures 1.2 and 3.1.
Two CTI deep patch tests were conducted using two different backfill materials.
Chapter 3 described, in detail, the first CTI test which involved the use of Road
base class 1 as backfill. In this Chapter, the second CTI test with shredded tire
as backfill is described. The unit weight of the" compacted" shredded tire backfill
used in this test is approximately 1/3 of the unit weight of the road base backfill
used in the first test.
29
4.2 CONSTRUCTION AND LOADING SEQUENCE
- Road base (class 1) backfill was used (without compaction) to construct a 4 ft
high berm on top of the 3 inch-thick sand layer (which was placed on top of the
bottom panel) as shown in Figure 3.1. The front face of the berm has the slope
of 1 (vertical): 1.25 (horizontal). The inner face of the berm has the slope of
1:2.25.
- A sheet of geosynthetic reinforcement (long enough to wrap around the backfill
layer, i.e., the length of the sheet =2 x length of the backfill layer + the height
of the backfill layer ) was positioned on top of the 3 inch -thick sand layer. The
excess length of the sheet was positioned on top of the berm.
- Shredded tire backfill was placed on top of the geosynthetic reinforcement in 12
inch-thick lifts to construct the geosynthetic-reinforced portion of the CTI deep
patch as shown in Figure 3.1. Each lift was uniformly compacted by simply
"stepping" on top in a reasonably consistent pattern. The unit weight of the
shredded tire backfill was approximately 40 pcf. Upon completing the placement
of a layer of shredded tire, the excess length of the geosynthetic reinforcement
layer was wrapped around it.
- The above procedure was repeated until reaching the height of 4 feet.
Thereafter, the geosynthetic-reinforced portion of the CTI deep patch was
30
constructed (vertically) with compacted road base as backfill . The height of the
vertical portion, with road base backfill, was 3 feet.
- Ten uniform drop increments of the moveable part of the bottom panel were
performed at a rate of 1 inch/minute. A waiting period followed each increment
to allow for taking measurements. Table 2.1 gives the magnitude and the
duration (drop time + waiting period) of each increment .
4.3 TEST MATERIALS
4.3.1 THE GEOSYNTHETIC REINFORCEMENT
The reinforcement used in the test was a nonwoven heat-bonded polypropylene
geotextile. The reinforcement was described in Section 2.3.1.
4.3.2 THE SHREDDED TIRE
The backfill material used in this test was a coarse shredded tire, with its
average grain size (chip length) of 4 to 6 inches.
A one-dimensional compression test was performed on the shredded tire prepared
at 6.3 KN / m3 (40 pcf) density. The one-dimensional compression test apparatus,
shown in Figure 4.1, consisted of a 0.5 inch-thick, 20 inch-diameter and 20 inch
high steel cylinder. The steel cylinder had one close end (the bottom end) made
31
of a 0.5 inch-thick steel plate. The inner surface of the steel cylinder was lined
with a thin layer of plexiglass. A lubrication layer made of a thin layer silicon
grease and a latex membrane was used to minimize friction between the shredded
tire and the lining plexiglass . After the shredded tire was placed in the cylinder,
a circular 0.5 inch-thick steel cover (with a diameter slightly smaller than the
diameter of the cylinder) was positioned on top. A vertical load was applied to the
steel cover using an MTS-810 machine.
The load history of the one-dimensional compression test is shown in Figure
4. 2 . As shown in the figure, the load history consists of three stages. The first
stage is a controlled load stage at a load rate of approximately 150 lb/minute which
correspond to a stress rate of 0.6 psi/minute. The second stage is a constant load
stage (creep), in which the applied load of 1500 lb (which correspond to a 6.3 psi
stress) was kept constant for 300 minutes. The third stage is a unload stage at a
unload rate of approximately 150 lb/minute (0.6 psi/minute).
The stress-strain behavior of the shredded tire under one-dimensional
compression is shown in Figure 4.3. The stress-strain behavior of the shredded
tire in the controlled load stage is nearly linear with a slight upward concavity.
Assuming a linear behavior during loading, a constant Constrained Modulus of
approximately 56.0 psi for shredded tire is estimated from the figure. Additional
32
modulus, such as Poisson's ratio, is needed to completely characterize the elastic
behavior of this material.
During the constant load stage, a significant creep can be noted in Figure 4.3.
The creep strain which occurred during the 300 minutes-period was approximately
15% of the total axial strain. Figures 4.4 and 4.5 show in arithmetic and semi
logarithmic planes, respectively, the creep behavior of shredded tire under a
constant stress of 6.3 psi.
At the end of the unload stage, as shown in Figure 4.3, most of the axi8J. strain
was recovered. Only 2% to 3% axial strain of the 12.5% total axial strain
(corresponding to 6.3 psi normal stress) was not recovered (plastic strain). Since
the applied normal stress of 6.3 psi in the one-dimensional compression test is
comparable to the maximum compaction stress normally used in the field, it is
obvious from the figure that most of the strain will be recovered as the compaction
factory is removed. Therefore, it can be concluded that ·the static compaction of
shredded tire is ineffective.
4.4 INSTRUMENTATION
The CTI deep patch test with shredded tire was instrumented to measure its
behavior during construction and upon dropping the moveable part of the bottom
33
panel. A number of different instruments were used to monitor the performance
of the tests. They were two-component load cell, lubricated latex grid and dial
indicator. A detailed description of instrumentation was given in Section 2.4.
4.5 RESULTS AND DISCUSSION OF RESULTS
The displacement of the CTI deep patch and the bottom panel, as measured by
the lubricated latex grid, is shown in Figure 4.6. It is noted from the figure that
the face of the CTI deep patch suffers excessive vertical and lateral displacements
throughout the test. The maximum settlements of 8 and 18 inches were measured
at the top of the wall corresponding, respectively, to the 5 and 11 inches drop in
the moveable part of the bottom panel. Lateral displacements in excess of 12 inches
were measured corresponding to the 11 inch drop of the moveable part of the
bottom panel.
A vertical crack emanating from a point on the top of the CTI deep patch near
the back panel is shown in the Figure 4.6. The crack started with the first drop
of 0.2 inch and propagated throughout the test due to further drops of the
moveable part of the bottom panel. The depth of the crack was approximately 7 ft
and its width was approximately 7 inches due to the 11 inch drop in the moveable
part of the bottom panel. It is noted from the figure that the whole structure seems
34
to be rotating clockwise with further drops in the moveable part of the bottom
panel. This rotation did not cease even after the maximum drop of 11 inches was
reached. The excessive movements and the large crack in the backfill render the
CTI deep patch technique with shredded tire as backfill unapplicable.
4.6 SUMMARY AND CONCLUDING REMARKS
To investigate the effectiveness of the CTI deep patch technique (with shredded
tire as backfill) for landslide repair, a large-scale plane strain laboratory test was
conducted. The moveable part of the bottom panel of the plane stain apparatus was
gradually dropped to simulate progressive local landslide . The response of the CTI
deep patch to the drop was carefully monitored.
The test results showed that the CTI deep patch with shredded tire backfill
suffered excessive movements throughout the test. A large crack near the back
panel initiated in the beginning of the test and propagated throughout the test.
The depth of the crack was approximately 7 ft and its width was approximately 7
inches due to the 11 inch drop in the moveable part of the 1:;lottom panel. The whole
structure seems to be rotating clockwise with further drops in the moveable part
of the bottom panel. This rotation did not cease even after the maximum drop of
11 inches was reached. The excessive movements and the large crack in the
35
backfill render the CTI deep patch technique with shredded tire as backfill
unapplicable.
36
CHAPTER 5
SUMMARY AND CONCLUSIONS
5.1 SUMMARY
The USFS deep patch technique involves the removal of the top portion (5-6
feet-high) of the small-scale sliding slope under a highway pavement and
rebuilding that portion with the use of horizontal layers of geosynthetic inclusions.
This study was aimed at investigating the effectiveness of the USFS deep patch
technique in (1) reducing the adverse effects of local landslides on highway
pavement and (2) increasing the stability of the repaired slope by reducing applied
normal stresses exerted to its top. The investigation was accomplished by devising
a large-scale apparatus in which the USFS deep patch technique can be closely
simulated. Two USFS large-scale deep patch te'sts were conducted. The first test,
termed "the USFS unreinforced test", used a compacted backfill without
geosynthetic reinforcement, whereas the second test, termed "the USFS reinforced
test", used the same soil for backfill as the USFS unreinforced test along with five
37
equally-spaced horizontal Iayers of geosynthetic reinforcement.
Another deep patch technique, evolved from the USFS deep patch technique,
was also investigated. This technique, named the CTI (Colorado Transportation
Institute) deep patch technique, was suggested by Professor ZhenghuanLiao from
Chongqing University (P. R. of China). In the CTI deep patch technique the top
portion (5-6 feet-high) of the small-scale sliding slope under a highway pavement
is removed and then rebuilt in the form of a geosynthetic-reinforced soil "retaining
wall" with a reversed angle.
There are two advantages of using the CTI deep patch technique. The first
advantage is the tolerance of the CTI deep patch to any subsequent settlement of.
the repaired slope. If there is a tendency of further settlement in the repaired
slope, the geosynthetic-reinforced portion of the CTI deep patch will separate from
the repaired slope causing no distress in the highway pavement. The second
advantage of using the CTI deep patch technique is its ability to widen the highway
of an average of 4 feet.
Two CTI deep patch tests were conducted using two different backfill materials.
Road base class 1 backfill was used in the first CTI deep patch test, and shredded
tire backfill, which weighs approximately 1/3 of the road base backfill, was used
in the second CTI deep patch test.
38
5.2 CONCLUSIONS
The USFS deep patch tests results showed that the unreinforced slope suffered
a severe distress throughout the test. A large vertical crack initiated in the
beginning of the USFS unreinforced test and propagated throughout the test to the
extent that the slope was virtually separated into two parts. On the other hand,
the reinforced slope remained intact throughout the test with the exception of the
few cracks initiated in the beginning of the test but were suppressed by the
geosynthetic reinforcements.
The stresses exerted on the moveable part of the bottom panel in the USFS
reinforced test were substantially smaller than those in the USFS unreinforced
test. This reduction in stresses will enhance the stability of the slope which was
in the state of progressive failure before the USFS deep patch repair.
This USFS tests results showed that (1) the USFS deep patch repair reduced
effectively the adverse effects of local landslides on highway pavement by
preventing crack propagation, and (2) the USFS deep patch increased the
stability of the repaired slope, which was in progressive failure, by reducing the
stresses exerted to it.
The CTI deep patch test (with road base as backfill) results showed that the CTI
deep patch remained intact throughout the test with the exception of the tolerable
39
crack near the back panel which initiated in the beginning of the test and
propagated throughout the test. However, the stresses exerted to the bottom
panel in the CTI deep patch test were substantially greater than those in the USFS
unreinforced test. This increase in normal stresses, due to the odd shape of the
CTI deep patch, will probably aggravate the stability of the slope which was in the
state of progressive failure before the CTI deep patch repair.
The CTI deep patch test (with shredded tire as backfill) results showed that the
CTI deep patch suffered excessive movements throughout the test. A large crack
near the back panel initiated in the beginning of the test and propagated
excessively throughout the test. The depth of the crack was approximately 7 ft
and its width was approximately 7 inches due to the 11 inch drop in the moveable
part of the bottom panel. The whole structure seems to be rotating clockwise with
further drops in the moveable part of the bottom panel. This rotation did not cease
even after the maximum drop of 11 inches was reached. The excessive movements
and the large crack in the backfill render the CTI deep patch technique, with
shredded tire as backfill, unapplicable.
40
REFERENCES
Billiard, J. W. 1989. Performance of a Large Scale Fabric Wall During Load Test. M.S. Thesis, University of Colorado at Denver.
Billiard, J. W. and Wu, J. T. H. (1991). "Load Test of A Large-Scale GeotextileReinforced Retaining Wall. " Proceedings of Geosynthetics '91 Conference, Atlanta, Georgia, pp. 537-548
Helwany, M. B. (1993). "The Long-Term Behavior of Geosynthetic-Reinforced Soil Structures." Ph.D. Thesis, University of Colorado at Boulder.
Helwany, M. B. and Wu, J. T. H. (1994)."In-Confinement Creep Characteristics of Geotextiles." To be submitted to ASTM Geotechnical Testing Journal.
Huang, C. C. and Tatsuoka, F. (1990). " Bearing Capacity of Reinforced Horizontal Sandy Ground." Geotextiles and Geomembranes, Vol. 9, pp. 51-82.
Tatsuoka, F., Molenkamp, F., Torti, T. and Hino, T. (1984). "Behavior of Lubrication Layers of Platens in Element Tests." Soils and Foundations, vol. 24, No.1, pp. 113-128.
Wu, J. T. H. (1991). "Measuring Inherent Load-Extension Properties of Geotextiles for Design of Geosynthetic-reinforced Structures. " ASTM Geotechnical Testing Journal, Vol. 14, No.2, June 1991, pp. 157-165.
Wu, J. T. H. (1992a). "Predicting Performance of the Denver Walls: General Report." Geosynthetic-Reinforced Soil Retaining Walls, Wu (editor), Balkema Publisher, pp. 3-20.
Wu, J. T. H. (1992b). "Construction and Instrumentation of the Denver Walls." Geosynthetic-Reinforced Soil Retaining Walls, Wu (editor) , Balkema Publisher, pp. 21-30.
41
8 ft
"" ... ........ ............
(c)
SURCHARGE
......... fa) .... , \
' ... ''''''''
" , , , -, ... , \ ,
\ ,
(b)
, ... ... , , , ,
" , ... ,
.....
PAVEMENT
OCAL~SUDE 40-50 ft
... , , " FILL .....
..... .... ..... , ...... ..... ....... ..........
GEOSYNTHETIC
~ ____ ~~~~~~~ O~CEMENT
PANEL
Figure 1.1 Schematic Diagram of the USFS Deep Patch Technique
42
8ft
SURCHARGE
, , , ,
HIGHWAY PA VEMENr
, .. , , ,
GEOSYNTHETIC
~ __ -=~~~~ruaNFORCE~ . /
, , , .. , ..... ..... .....
..... ' .....
7 ft ----.1~* .. If---- 9 ft -.....lI_~ 3 ft DROPPING PANEL
Figure 1.2 Schematic Diagram of the CTI Deep Patch Technique
43
Figure 2. 1 The Deep Patch Test Awaratus
44
Fig~ 2.2 The Front Cranl.: which Oper-c.tes the Front Th.,0\l Jacks
45
:':""igu:-e The Back Crank whi.::h Opera:es Front Two Jacks
--
48
tension ... --_.
1.· stationary clamps
2. cover clamps ./ ./ ~2
3. bolt /1 / // r /3
4. geosynthetic reinforcement ./' ./' ./' ./' V J' 0
5. epoxy-reinforced ends of geosynthetic reinforcement
of:>, 1.0
1
5
4
5
1
T I / tension
Figure 2.6 Schematic Diagram of the Uniaxial Load-Deformation Apparatus
Fig'.!:"e 2.7 Th~ 'Uni2xjal Load-Deformation Test
5 (
[) I
I '
Figurf~ ? R Stee:l Mold fur Epoxy A ppli cation on the Two Hnds of the Geotextile Specimen
tn t»
Figure 2.9 Assembly of Steel Mold for Epoxy Application on the Two Rnds of the Ueotextile Specimen
1.00
0.90
0.80
0.70
I/) 0.60 c. ~ - 0.50 '0
as 0
0.40 ...J
0.30
0.20
0.10
0.00 0.00 0.04 0.08 0.12 0.16 0.20
Strain
Figure 2.10 Load-Deformation Behavior of the Geotextile Reinforcement
53
100
90
80
70 "-CD c:: 60 -- 50 c:: CD 0 ... 40 CD Q.
30
20
10
0 0.001 0.01
: ::: t . ···11 . "'11
: : ::::":
: : :::=i. · . : :1:: · . ~1::~
v······ .... -.. . · ..... . ······v· · . .... . · . .... . · . .... . · . .... . · . .... .
· . ::¥: · .7::: ·······A····· · . ..... . ..... . · . ..... . ..... . · . ..... . ..... . · . ...... . ...... . ....... . ...... .
0.1 . 1 10
grain diameter, mm
100
Figure 2.11 Grain Size Distribution Curve of the Gravelly Sand
54
130
126 -0 Q.
- 122 .r:. C)
CD ~ -c: 118 :::s >. ~
~
114
11 0 I..--..L._"""'----'""---'-_-'-_""--..L._ ....... _'----'
5 6 7 8 9 10 11 12 13 14 15
water content, %
Figure 2.12 . Compaction Curve of the Gravelly Sand
55
111 0\
C\l c:
" ..tI
'" > Q)
"'0 -jd
E Cl
11l
120
l01ZJ
B0
S0
40
20
Figure 2. 1 3 (a) -------.. ----
Triaxial ,Compression Test Results for the Gravelly Sand
UI feb 1994 1S~4Sz 15
I' 1 T-· --- ---T I -"-- -'---l
• I I
-_ ... ---L------I
__ . __ ... ___ .. -'-_____ 1 ______ 1-_._._.___ ___ ~ II Ji i I .----- ----.- -... ----... ----.... ~----.-.... '---'---' --~
I . ~ . t ~- .~~t-----+---J.-.
--~-.-- ----- ·---.. ·-t--·-----I I I I o 1i---J'---____ ... --l ___ .. ___ L ___ 1 _ L __ l "
B 2 LEGEND
4 B B 10 12 14 18 19 ·20
SYM~OL SPi~IMEN Ax 1 a 1 St r a: in - ~ x 32
l * 33 rea.ture Sample 1 Class. symbol ROAD BASE COMPACTED
Liquid " mft Plasttc l ty Index Spectflc gravIty 2.60 Project UCD Depth ft. Test Type CD
- ------ . ~---- .. --.--. ---------~.-.-.--------------------. --------------_._--_._---.. _-------------_ .... _----
U1 -.J
...:
Q) m
I~
l~ E :J -0 >
-- ~ ----.-------. - - ._-- -~ --~---------. __ .------.-._--- ------.. _- --- _._-_..-----.. --. --- ---.... --... --~.--- -. ---'---- -""--- -.... --.---.~.- ... _----. --.,-- ------- ----------
Figure 2.13(b) Triaxial Compression Test Results for the Gravelly Sand
10 Feb 1994 15:54:29
Volume Plot Pore Pressure Plot
10
9
9
7
6
5
4
3
2
1
0 0
-----r--- '- '- --l---T----<--·--1·-.. ·----- ---- ----- .--- -._.- "--l--i----.. ------+-- --- ----- .-.--- ----- ---1-- 1--
~_~i~~.tj~_ ~--_.=~~~=-'-=~j~~-.j~:--I.---l-L------L---J.-------L~---_i--
I
.-.-- -- ··------1-----·-- -.-_.- ----.-.1---~ ~
-=[:=:~ =~~:.:·I·=:-~ --~:±=_= ~= ~=t=-~~= ~- - - ~
2 4 B B 10 12 14 16 18 20
Axia l Strain - Y.
LEGEND
.9
.9 N C ... "\ .7 .a
.6 ., L :::J .5 ~
" ., L a. .4 ., L 0 .3 a.
" ~ .2 Q)
" x w
• 1
I!J I!J 2 4 6 B 10 12 14 16 18
Ax 1 a 1 Str a 1 n - Y.
212
SYMBOL SPECIMEN o 31 X 32 * 33 Feature
L f qu f d 1 f m f t Project UCD
Samp l e 1 Class . symbo l ROAD BASE Plastfcity I ndex Specific gravIty 2.S0
Depth ft. Test Type CD
COMPACTED
__ ... , ..... -_ ....... _ ...... _. __ ... · ...... ___ 0-· ...... _. ____ . _______ ._ .. ,_. __ ... ____ ,. .......... _______ ..---_ ..... ~_. ____ • __ .. _. ____ ._ .. __ • __ .... __ ., .... _-.-... ___ .. ______ .... ___ .•. _ ... _. ___ • __ ...... __ .... ____ • _______ •• _____ • __ ... _ __.. ". _________ ..
U1 co
SURCHARGE
. l~~~:.. 3 ~ ----lJr-- -"7't:.--- - &1.- - - - 8--- __
--- --- ------ - -- ____ ~ I - ____ - ----- -. -----
_~c:y_eE -~A- _____ A- - ---- -8- - - - - -8- - - - - -b-- - --
6 high-elongation strain gage
~ two-component load cell
. 2 displacement dial gages
@ lubricated latex grid
-- ---- --- .----- ----- - - - - -. - -- -----. - -- -- --- - -----
layer 1 A A ___ A -------i::z-------~--------------M-------M---- ~
6 5 4 3 2
Figure 2.14 Instrumentation of the USFS Deep Patch Test
t.n \0
1
input
c ' 'd ' , , .!:zz::1 tz:z:: , " , " , , ,
f
t1 c I I d
:t:?~ I I I I
shear stress 3
output
4 <:==:>
Full Bridge
2 (b)
(a )
c
normal stress
4
d b - - I J - 1
2
3
-a
liLtli
Bottom panel
normal
stress ~ c::=.=n
shear stress
perpendicular to paper'
steel container
Vertical Cross-Section of the Bottom Panel
( C)
Figure 2.15 Schematic Diagram of the Two-Component Load Cell
61
.-" < -.
1100
1000
0 900
:: 0 800 + cell # 1 > 0 ... u 700 E t:. cell # 2 CD 600 CD c:
500 0 cell # 3 CIS .c 0 CD 400 CD + cell # 4 CIS
300 !:: 0 >
200
100
0 0 3 6 9 12 15
Normal Stress, psi
Figure 2.20 Normal Stress Calibration Curves for Load Cell
64
Figure 2.21 Snear SLress Calibration of Load ee:l
55
5000 r------------,
tI.I 4000 -0 + cell # 1 > 0 ... . 2 E 3000 t- celi # 2 CD 0) C 0 cell # 3 «I
.J:: 0 2000
CD cell # 4 0) +
as !:: 0 > 1000
o 4 8 12 16 20
Shear Stress, psi
Figure 2.22 Shear Stress Calibration Curves for Load Cell
66
.sa
69
;S .~
~ > c U
.5
70
30
27
24
I/) 21 -0_ >1/) 18 01J (j C .- as E I/) 15 = • 0 .... CD,c
I-' ~t:. 12 !:: 0 > 9
6
3
0
calibration curves for strain gages
+
+
0 4 8 12 16 20
strain. %
Figure 2.27 Calibration Curve for Strain Gage
gages 1. 2 3 and 4
".J 1'0
l::'iigure 2.28 Environmental and Mechanical Protection of Strain Gages Using a layer of Neoprene :Rubber
Figure 2.29 Geotextile Layer Instn::mented \\ith Strain Gages-
- ., . -
I 1
i4
I
-1 I
•
75
-..J C'\
w/o Reinforcement
surcharge ~ crack
5432 1
Legend 1 end of construction 2 2.0"drop 3 5.0"drop 4 8.0"drop 5 11.0"drop
Figure 2.32 Displacement Field of the Backfill in the Unreinforced USFS Deep Patch Test
--I >,.,
Figure 2.33 The Crack Corrt'sponding to 11 inch · Drop in the Unreinforced USPS Deep Patch Test
-...J 0)
wI Reinforcement
crack (5)
surcharge
crack (5)
---------------------------------
-------------------------------------~~,
______ ~ Reinforcement ------------- - --- ----- - - - -- ---
Legend 1 end of construction 2 2.0"drop 3 5.0"drop 4 8.0"drop 5 11.0"drop
---------- - - ------- ---- --------- - - - -------- ~-~-"...
------------------------------------------------~~~~ 54321
Figure 2.34 Displacement Field of the Backfill in the Reinforced USFS Deep Patch Test
" 1.0
SURCHARGE
Figure 2.35(a)
"' "'. "', "" , ,
" , , ""'.... 2.0 INCH DROP ,
"""', , , " , , , , ,
" " ",
Comparison of Crack Propagation in the Two Tests at 2 inch-Drop
"
co o
SURCHARGE
Figure 2.35(b)
5.0 INCH DROP
Comparison of Crack Propagation in the Two Tests at 5 inch-Drop
co I-'
SURCHARGE
Figure 2.35(c)
8.0 INCH DROP
Comparison of Crack Propagation in the Two Tests at 8 inch-Drop
co to.)
SURCHARGE
Figure 2.35(d)
11.0 INCH DROP
Comparison of Crack Propagation in the Two Tests at 11 inch-Drop
crack propagation
+ wlo reinf. A w/reinf.
100
90
80 In CD .c 70 0 r::
~ 60
0 as 50 ... 0 -0 40 .c -C) 30 r::
CD
20
10
0 0.00 2.20 4.40 6.60 8.80 11.00
settlement, inches
Figure 2.36 Comparison of Crack Propagation in the Two Tests
83
normal stress, w/o reinforcement
7
6 + end of construction
5 6 1 inch tn c.. drop iii
4 tn 0 2 inch Ql ~ -tn
ca 3 E
+ 3 inch ~
0 c:
2 • 8 inch
1 • 11 inch
0 0 28 56 84 112 140 168 196
distance from back, inches
Figure 2.37 Distribution of Nonnal Stresses along the Bottom Panel in the Unreinforced USFS Deep Patch Test
84
normal stress, wI reinforcement
7
6 + end of
construction 5
(/) A 1 inch a.. 1/)-
4 I/)
GI
drop
0 2 inch ... -I/)
~ 3 E + 3 inch ... 0 c
2 • 8 inch
1 • 11 inch
0 0 28 56 84 112 140 168 196
distance from back, inches
Figure 2.38 Distribution of Nonnal Stresses along the Bottom Panel in the Reinforced USFS Deep Patch Test
85
4
3
'#. c 2 tIS .... -II)
1
0 0
Figure 2.39(a)
+ end of strain distribution in layer 1 construction
t. .2" drop
0 .4"
+ .6"
• 1.0"
• 1.5"
v 2.0"
<> 3.0"
c 5.0"
.. 8.0"
• • 11.0"
27 54 81 108 135 162
distance from back, inches
Distribution of Strain along the Geosynthetic Reinforcement Layer 1 in the Reinforced USFS Deep Patch Test
86
+ end of
strain distribution in layer 3 construction IJ. .2" drop
4 r-------------------------------~ 0 .4"
3
-c cu 2 .... -(f.J
1
o
Figure 2.39(b)
+ .6"
4 1.0"
• 1.5"
v 2.0"
0 3.0"
0 5.0"
• B.O"
• 11.0"
23 46 69 92 115 138
distance from back, inches
Distribution of Strain along the Geosynthetic Reinforcement Layer 3 in the Reinforced USFS Deep Patch Test
87
4.00
3.20
'#. 2.40
c tIJ .... -(/)
1.60
0.80
0.00 0.00
Figure 2.39(c)
+ end of strain distribution in layer 5 construction
11 .2" drop
0 .4"
+ .6"
A 1.0"
• 1.5"
v 2.0"
<> 3.0"
0 5.0"
y 8.0"
• 11.0"
18.17 36.33 54.50 72.67 90.83 109.00
distance from back, inches
Distribution of Strain along the Geosynthetic Reinforcement Layer 5 in the Reinforced USFS Deep Patch Test
88
L GEOSYNTHETIC REINFORCEMENT
(X) t-\C ~
....... / ,"" t,12.25 1.25~ I /1 .".-5 A N D i
-7 FT. I 1.5 FT. I 7.5 FT.
Figure 3.1 Schematic Diagram of the CTI Deep Patch Test
Figure 3.2 Tna en Deep Patzh Test at End of Construttior:
90
10 ,....
!-I-!- 1-1-!-
4
I
layer 6 A A A A A L.J. L...J. -~ L...J. L...J.
layer 4 A A A A J\ L...J. ~ ~ ~ ~
7 layer 2 A A A A A
~ ~ ~ ~
~7 2.25
-1
3 2 1 / ..---. ...
l
Figure 3.3 Instrumentation of the CTI Deep Patch Test
-.. ..
6 high-elongation strain gage
~ two-component load cell
. 2 displacement dial gages
.x grid
1 ~ 1.25~
U)
I\l
~ LL .......
5" drop
11" drop
Displacement Scale
12"
- =='- = = == = ==::..=. = ==~======= == ====-===_1
7FT 9FT
Figure 3.4 Displacement Field of the Backfill in the CTIDeep Patch Test with Road Base Backfill
"
Figure 3.5 The Deformed Face c: tlJe eTr Deep Patch Test with Roa.d B.:se Backfill after Removing the Berm
Figure 3.6 Distribution of Normal Stresses along the Bottom Panel in the en Deep Patch Test with Road Base Backfill
94
strain distribution in layer 1
2 ~--------------------------------~
~ -c 1
CIS ... -f/)
oL---~~~~~~~~--~ 40 56 72 88 104 120
distance from back, inches
. + end of construction
1" drop
o 2" drop
+ 3" drop
4 8" drop
• 11" drop
v after berm removal
Figure 3.7(a) Distribution of Strain along the Geosynthetic Reinforcement Layer 2 in the en Deep Patch Test with Road Base Backfill
95
strain distribution in layer 2
2.00 ,..--------------------,
1.60
'#. 1.20
c:: 'iii .... -{I) 0.80
0.40
0.00 40 56 72 88 104 120
distance from back, inches
+
0
+
..
•
v
end of construction
1" drop
2" drop
3" drop
8" drop
11" drop
after berm removal
Figure 3.7(b) Distribution of Strain along the Geosynthetic Reinforcement Layer 2 in the en Deep Patch Test with Road Base Eackfl11
96
+ end of
strain distribution in layer 3 co nstructi on
A 1 n drop
2.00
0 2" drop
1.60
+ 3" drop
"$. 1.20
c: 4 8" drop cu ... -0
0.80
• 11" drop
0.40 v after berm
removal
0.00 40 56 72 88 104 120
distance from back, inches
Figure 3.7(c) Distribution of Strain along the Geosynthetic Reinforcement layer 6 in the eTI Deep Patch Test with Road Base Backfill
97
"> <XI
I 3ft
SILVERTHORNE, COLORADO October 26, 1993
Guardrail
II .... -' ... , ... .. .. .. -.------; .... ~
u 6 ft
..... - " ..
10-12 % slope
/--2 ft -I" 7 ft ..,
Figure 3.8 Configuration of the CTI Deep Patch in Silverthorne
\0 \0
CONSTRUCTION
6ft
1 berm
Figure 3.9 Construction Procedure of the CTI Deep Patch in Silverthorne
o C"-l
II
detailed section
aPPliedloadf
Diameter = 18 inch .
(1) steel container (2) plexiglass liner (3) silicone grease (4) latex membrane
£J.gure 4.1 Schematic Diagram of the One-Dimensional Compression Test for Shredded Tire
102
.... rrl ~
.n rrl ~ ... ~ rrl
.... = 8 ... 0 I::
7
r··· "!*..: • 'p.
6
5
4-
: 3:
2'
1
0 0 50 100 150 200 250 300 350
time. minutes
Figure 4.2 The Load History of the One-Dimensional Compression Test on Shredded Tire
103
.... 171 j:l,
ci 171 ~ ~ ... 171 ... CIS
S ~ 0 I::
10
9
8
7
6
5
4
.' 3
2
1
0 0 2 4 6 8 10 12 14
axial strain, %
:Figure 4.3 Stress-Strain Behavior of the Shredded Tire under One-Dimensional Compression
104
!;oI!
a .... ell ~ ~ I'll -CIS .... ~ ell
12.8
12.6
12.4-
12.2
12
11.8: . ,
11.6
11.4-
11.2
11 0 50 . 100 150 200 250 300
time, minutes
Figure 4.4 Creep Behavior of Shredded Tire under a Constant Stress of 6.3 psi (arithmetic)
105
~
d .... ell
'"' ~ en -ell .... >< C\l
12.8
12.6
12.4
12.2 .., /"
,/ 12 . ..-.--'-.--_.-.....
. .. ..
11.8
11.6
11.4
11.2 10-1 100 101 102 103
time, minutes
Figure 4.5 Creep· Behavior of Shredded Tire under a Constant Stress of 6.3 psi (semi-logarithmic) . -
106
...... a ...:I
"
5 inch drop 11 inch drop
r--------------------~ -- .... - ... _--I Road Base - ___ _ , '-r Road Base ------------Road Base ---------------
-----------Shredded Tire
Shredded Tire
Shredded Tire
--Shredded Tire
\ , , J
'\
I
I Displacement Scale
12"
------------------- --------- --- ------- -- -- - -- - - - - - - - - - - - - - - - -- - - - - --
Figure 4.6 Displacement Field of the CTI Deep Patch Test with Shredded Tire Backfill