Upload
evelyn-robbins
View
217
Download
3
Tags:
Embed Size (px)
Citation preview
The Detector Safety System
for LHC Experiments
The DSS Team – IT/COJCOP Review, 11 March 2002
11 March 2003The Detector Safety System for LHC Experiments 2/17
Introduction
Experimental Safety LHC Experimental Needs The DSS
Functional Requirements Design and Architecture of the
Prototype Conclusions and Planning
11 March 2003The Detector Safety System for LHC Experiments 3/17
Sensors for• temperature (equipment, ambient air, water),
• humidity,• water-flow,
• sniffers,• watchdog signals of the sub-detectors
monitor the state of the equipment.
There are dedicated sensors for the different safety and control systems.
The LHC experiments and their sites, e.g.• (sub-)detectors,
• gas systems,• magnets,
• power distribution,• racks and crates
will be the equipment to be acted uponby the control and safety systems.
Technical Services provide power, water, gas (general services) and distribute them to the different locations (experiment services).
The DSS complements CSS and DCS:
“The DSS is a system to safeguard the experiment.As such, it acts to prevent damage to the experimental
equipment when a serious fault situation is detected (e.g. temperature too high, water leak, bad detector status…), inside
or outside of the detector…”
The Detector Control System (DCS) is responsible for the overall monitoring and control of the detector.
It might take corrective action to maintain normal operation.All DCS sub-systems are interconnected.
monitor
control
General services: power, water, gas
Experiment services:power, water, gas
Experiment: sub-detectors, racks, crates
In 2001, the experiments have realized, that some safety aspects are
not covered by the CSS and DCS.
The DSS was born.Level 3Level 3 Level 1Level 1Level 2Level 2
Experiment’s DCS
The DSS is embedded in the Experiment’s DCS.Alarm conditions are exchanged with the CSS (hardwired).
Sensors Sensors Sensors
3 Levels of Experiment Safety
DCSsub-system C
DCSsub-system B
DCSsub-system ACSS
CSAM,CSE,etc.DSS
The safety for personnel is ensured by the CERN Safety System (CSS).
It has its own sensors.
Water LeakSmoke,
Gas Leak
Hardware LayerHardware Layer
Supervisory LayerSupervisory Layer
Trip
11 March 2003The Detector Safety System for LHC Experiments 4/17
The DSS functional requirements have been evaluated by the four LHC experiments in a joint WG, and are described in the document CERN-JCOP-2002-012:
http://cern.ch/proj-lhcdss/images/DSSFRD_20020425.pdf
“A Detector Safety System for the LHC Experiments – Functional Requirements Document”
The WG was chaired by Philippe Gavillet.
The DSS Functional Requirements
11 March 2003The Detector Safety System for LHC Experiments 5/17
Scope and Goal:An Optimization Challenge
The DSS should… Protect experimental equipment Improve the experiment’s efficiency by…
preventing situations leading to level-3-alarms(these might lead to 2-3 weeks downtime)
decreasing downtime due to failures Not cost too much
DSS can be considered as an “insurance policy”
11 March 2003The Detector Safety System for LHC Experiments 6/17
Constraints for the DSS
Easy integration… into the controls system of the experiment of sub-detector safety systems of external information (GCS, CSS, …)
Adaptability… since the DSS is a common solution
proposed for all four experiments. to different needs of the four experiments to evolving experimental environments
11 March 2003The Detector Safety System for LHC Experiments 7/17
LHC Experimental Needs
200 to 800 inputs to be monitored
sensors located in several buildings
(caverns & surface) several 100 outputs
Geographicallydistributed system
11 March 2003The Detector Safety System for LHC Experiments 8/17
The DSS must be a standalone system and be…
highly reliable highly available as simple and robust as possible re-configurable by the GLIMOS’s and
experiment experts self-checking for consistency
The DSS Functional Requirements
11 March 2003The Detector Safety System for LHC Experiments 9/17
The Prototyping Phase
A DSS prototype is currently being developed by the DSS Team
(1.5 FTE from IT and 1.0 FTE from EP) to meet the defined requirements
will be a “proof-of-concept”The DSS Advisory Board, consisting of
representatives from all four experiments, site safety experts and the DSS Team is overseeing the prototyping phase.
A review in May 2003 will verify that the design meets the requirements. This will allow for a series production.
11 March 2003The Detector Safety System for LHC Experiments 10/17
After discussions in the DSS Advisory Board, the Front-End will…
be based on PLC technology have its own sensors and actuators check and filter the input sensors be on safe power (CERN safe power plus own
UPS’s) will always react immediately and automatically
on fault conditions indicated by the sensors
DSS Front-End Architecture
11 March 2003The Detector Safety System for LHC Experiments 11/17
The DSS User Interface (Back-End) will… be based on PVSS and the JCOP Framework monitor and configure the Front-End allow a configuration of the relations between
sensor values, fault situations and the actions performed in these cases (the “Alarm/Action Matrix”)
define user access rights through a controlled scheme
provide the user with comprehensible displays log alarm states, warnings, and related information
DSS Back-End Architecture
11 March 2003The Detector Safety System for LHC Experiments 12/17
Redundancy:
• up to the level of I/O interfaces
• backup if failure of a PS, a CPU, a Profibus
• Modules have high MTBF (low failure rates).
• optical link between CPUs
• step-by-step comparison between CPU processes
OPC server:
• gateway to the Back-End
• data distribution via an OPC server
• redundant in the Front-End communication
Front-End (cont’d):
• Siemens S7-300
• capable of handling the number of channels (inputs and outputs) as
required
• located near sensors (<200m)
• I/O interfaces hot-swappable
• inputs and outputs use “positive safety”External crate:
ET 200Mredundant PS
Profibus adapterI/O interfaces
Front-End:
• uses a Siemens S7-400 station
• implementation and processing of the Alarm/Action Matrix
• monitors the DSS system itself
CPU crate:redundant PS
CPU 414-4HEthernet adapter
(CP 443-1)
DSS Architecture
Back End:
• PVSS user interface for displays and logging
• modification of the Alarm/Action MatrixProfibus
DSS COM
OPCServer
Oracle DB & PVSS
CERN LAN
11 March 2003The Detector Safety System for LHC Experiments 13/17
PLC:
Input: Sensors
cycle time
The Alarm/Action Matrix
The PLC loop: PLCs continuously monitor the
sensors e.g. temperatures, water flow,
sub-detector status
Output: Action(e.g. switching off power)
T>TthresT>TthresT>Tthres
Input values are compared to defined thresholds.
Several conditions can be logically combined. Their fulfillment will produce an alarm.
Alarms will trigger defined actions. Actions are on a coarse level (e.g.
cutting power to a complete sub-detector).
ANDAlarm
End-of-Loop
11 March 2003The Detector Safety System for LHC Experiments 14/17
Conclusion
The design of the Detector Safety System, arrived at in consultation with the DSS Advisory Board, will consist of… Front-End:
Siemens S7-400 redundant PLC hardware STEP7 development environment PC based OPC server acting as a gateway
Back-End: A PC based system with a PVSS user interface,
using the JCOP Framework Oracle Database connection for data and configuration
logging
11 March 2003The Detector Safety System for LHC Experiments 15/17
Planning OverviewTask Status Target Date
Front End software Operational June 2003
Back End software In progress June 2003
Installation, commissioning and test of the complete prototype
In progress April 2003
System Review May 2003
Final tests of the revised prototype May/June 2003
*Preliminary version of the DSS
Installation / commissioning for CMS Summer 2003
Operational DSS for CMS* 01/09/2003
Installation / commissioning for LHCb Autumn/Fall 2003
Operational DSS for LHCb* 20/11/2003
Operational DSS for ALICE / ATLAS 2004
11 March 2003The Detector Safety System for LHC Experiments 16/17
Status
Hardware development The PLC hardware has been installed in the lab. The complete system is now being commissioned. Survey of useful temperature sensors (ambient
air & water), humidity sensors, etc. has started.
Software development The DSS database has been defined. A first implementation of the Front-End software
has been done. PVSS Back-End interface implementation is
underway.
A prototype DSS system will be ready forthe review in May 2003.
11 March 2003The Detector Safety System for LHC Experiments 17/17
Where to find more Information?
All documents and DSS presentations can be found on the DSS site
http://cern.ch/proj-lhcdss/
Or visit us in our laboratory: 14/3-030Contact: [email protected] (74841)