Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Transportation Report
Oatman Restoration Project Page 1
Project Basic Information
The Oatman Restoration Project is located on the Silver Lake Ranger District of the Fremont-
Winema National Forests. The project area encompasses approximately 36,252 acres of land, of
which 26,341 acres are National Forest Service (NFS) land. The legal location of the project
area includes all and/or portions of the following Townships (T), Ranges (R), and Sections
(Sec.):
T27S R12E, Sec.34 & 35; T27S R13E, Sec.8, 17-22, 27-32;
T28S R11E, Sec. 24-25, & 36; T28S R12E, Sec. 1&2, 11-15, 19-35;
T28S R13E, Sec. 18 &19; T29S R11E, Sec.1;
T29S R12E, Sec. 2-12, 15-21, 29-32; T30S R12E, Sec. 5-7.
The Oatman project area includes portions of four sub-watersheds (Bear Creek, Buck Creek,
Oatman Flat, and Timothy Creek). The Oatman project area also includes Fremont Forest Plan
Management Areas (MA) 1, 2, 3, 5, 6, 9, 12, 14 and 15 (Table 1).
Table 1. Oatman project Forest Plan MAs and total acres (approximate) in project area.
MA Description Project Area Acres % NFS Lands in
Project Area
1 Mule Deer Winter Range 11,912 45%
2 Bald Eagle Management 1,743 7%
5 Timber & Range Production 14,866 56%
6 Scenic Viewshed 1,891 7%
9 Semiprimitive Non-Motorized 200 0.1%
12 Utility & Transportation Corridors 6.5 miles n/a
14 Old-Growth 945 4%
15 Habitat & Water Quality 889 3%
Background/History
Although there is very little documentation of when the roads were built within the Oatman
project area boundary road building began on both the Fremont and Winema National Forests
primarily due to the increased demands for timber products in the late 1940’s. It was at this time
Congress began to appropriate dollars for road building, and many of the mainline roads were
constructed by the Bureau of Public Roads, now known as the Federal Highway Administration.
Historically, the Fremont National Forest has emphasized timber management, and road building
continued to expand from 1960 through 1990 in response to timber management. In the late
1990’s road construction began decreasing, and the emphasis now is to decrease the number of
miles of National Forest System (NFS) roads requiring long-term maintenance, as well as to
decommission NFS roads no longer needed for resource management purposes.
Current Condition
The transportation system in the project area exceeds desired road densities and may not best
meet the land management objectives. The condition of the transportation system located within
the boundaries of the Oatman Restoration Project area has been created due to actions related to
fire, restoration, allotment management, timber harvest, road maintenance activities and
recreational use. The road system may not be the most effective or efficient road system for land
and recreation management. Not all system roads have been field validated, therefore,
Transportation Report
Oatman Restoration Project Page 2
discrepancies may exist. Additionally, Best Management Practices (BMP) for the maintenance
of the designed drainage features has not been fully implemented to the roads and water
crossings. Resource damage on these roads may potentially be occurring.
The Forest Supervisor of the Fremont-Winema National Forests formed an Interdisciplinary
Team to develop a Forest-level roads analysis in 2000 for the Winema and 2002 for the Fremont.
The Forest Roads Analysis Team produced a forest roads analysis report and transportation atlas
documenting the interdisciplinary recommendation process. The process targeted Maintenance
Level 3, 4 and 5 roads. These roads are maintained for low clearance vehicle access with the
highest level of travel comfort at Level 5. These roads form the main or “backbone” road system
for the Fremont-Winema National Forests. Where appropriate, recommendations were made for
future actions on this system that would reduce risks of unacceptable environmental disturbance,
increase the benefits provided by these roads, and prioritize funding allocations for maintenance
and reconstruction. Maintenance Level 1 and 2 roads were not part of this analysis, and neither
was consideration to decommission roads.
Within the Oatman project area there are approximately 147 miles of NFS roads, of which 142
miles are on NFS lands. The Forest Service has easement on 6 miles of road that cross on
Private land within the Oatman project area. Refer to Map Attachment A: Current Condition –
Transportation, for current road locations.
Maintenance level standards (FSH 770109, 63.32) are used to describe the current level at which
a road is being maintained. Maintenance level status, describes the existing condition of the
road. There are three road Maintenance Levels (ML) within the Oatman Project area. They are
described as follows:
Maintenance Level 1 (ML1) (STATUS = Existing), are considered closed roads and are
placed in storage between intermittent uses, these roads prohibit traffic and are not shown on
Motor Vehicle Use Maps (MVUM).
Maintenance Level 1 (ML1) (STATUS = Decommissioned) are physically
decommissioned/obliterated roads that are no longer included in total NFS system road miles
or road densities. They are only maintained in forest system roads database for historical
documentation. These roads are not shown on Motor Vehicle Use Maps (MVUM).
Maintenance Level 2 (ML2) are roads maintained for use by high clearance vehicles.
Maintenance Level 3 (ML3) are roads maintained for travel in standard passenger car. These
roads are normally lower speed, single lane with turnouts.
Table 2, summarizes the current NFS road maintenance levels within the Oatman Project area.
Table 2 – Current Operational Road Maintenance Levels
Road Maintenance Level
Current
Condition
(Miles) Comments
ML 3 8 Maintained for passenger cars
Transportation Report
Oatman Restoration Project Page 3
ML 2 61
High clearance vehicles only, not all road
miles are accessible, field inventory found
some of these roads blocked or obliterated.
ML 2 – (FS Easement ) 1 Currently part of NFS road system
ML 1 (Closed) 68
Not all roads found, some may have been
obliterated or naturally reclaimed.
ML 1 (Closed – FS Easement) 5 Currently part of NFS road system
ML 1 (Status: Decommission) 9
After field inventory, several roads were
found, and are currently accessible.
TOTALS 152
All Fremont-Winema NF system roads have been addressed in the Fremont-Winema National
Forests Environmental Assessment for Motorized Travel Management Decision (Travel
Management Decision), signed July 8, 2010. The Travel Management Decision determines
which roads, trails, and areas will be available for motorized use, season of use, and class of
vehicles. Table 3 summarizes the current motor vehicle use and season of use allowed in the
Oatman Project area. Refer to Map Attachment A: Current Condition – Travel Management.
Table 3– Current Motorized Road Opportunities by Vehicle Class
Vehicle Class
Open Yearlong
(Miles)
Seasonally Open
4/1 - 11/30
(Miles)
Roads Open to All Vehicles 33 37
Roads Open to Highway Legal Vehicles Only 0 0.3
Trails Open to Motor Vehicles 50 Inches or Less in Width 0 0
Trails Open to All Motorized Vehicles 0 0
Motorized Access to Dispersed Camping (MADC)
50 miles total available, seasonal restrictions
will apply within Deer Winter Range closure.
There are approximately 2.3 miles of non-system roads currently accessible by motorized
vehicles of various size classes. The Travel Management Decision considers all travel by
motorized vehicles on non- designated roads and trails to be cross-country travel. Cross-country
travel is not allowed under the Travel Management Decision, except when authorized through a
permit or contract.
Approximately 142 miles of NFS system roads are on 41.3 square miles of NFS lands within the
Oatman Project analysis area. Total NFS road density on NFS land exceeds the Forest Plan’s
objective of 2.5 miles per square mile. Table 4 provides a summary of total and open road
densities within the subwatershed within the project boundary.
Table 4: Current Forest Service Road Densities by Subwatershed (NFS Land).
Subwatershed Total Road Density* Open Road Density**
Bear Creek 3.8 2.0
Buck Creek 1.7 0.5
Oatman Flat 2.4 1.1
Timothy Creek 2.4 1.6
Transportation Report
Oatman Restoration Project Page 4
Total NFS Land 3.2 1.7
* Road Density Calculation = miles of road / square miles of land base
** Open Road Density Calculation includes ML 2 and ML 3 roads only
Data Collection/Methodology/Analysis
Data collection on the road systems within the project area was done in preparation for this
analysis. The majority of the field data collected was done during the summer of 2012. Field
data collected included whether roads existed and if they did, were the roads open or closed, how
they were closed, and if accessible by car, high clearance vehicle or off-road type vehicle. Roads
surveyed were also assessed for maintenance, construction or re-construction needs. Data
collection included locating and inventory of undocumented roads and type of use occurring on
these roads, it was also documented if these roads could be useable for project treatments. Field
data collection was a compilation of information from various Forest Service personnel utilizing
the roads as well as Engineering personnel. Not all roads were fully inventoried due limited
personnel and funding for reconnaissance.
Corporate GIS spatial layers were also utilized in developing current conditions. These layers
were clipped to the project area boundaries and attributed with field information. These layers
were later used in travel analysis, and the development of a road management and access strategy
for the Oatman project area. Other resource considerations were utilized in determining allowed
motorized access on National Forest Service roads.
The Paisley/Silver Lake District Ranger directed that a project level travel analysis be conducted
for the Oatman Project area. The following disciplines participated in this analysis:
Engineering Timber/Silviculture Fisheries Hydrology
Cultural/Historical Range Wildlife Fire/Fuels
Recreation Botany Planning
This group met two times to review roads. Road management recommendations for each road
within the project area included whether to keep roads in existing condition, to close, to
decommission, or change road maintenance level. Road recommendations were based on
resource specific evaluation criteria found in Oatman Travel Analysis document located in the
project record.
Specific road management recommendations made by the Travel Analysis Team are also
displayed in the Oatman Travel Analysis document. The results of this analysis are
recommendations to close approximately 38 miles, and decommission approximately 52 miles of
NFS roads. The recommendations were approved by the Silver Lake District Ranger and are
included in all action alternatives.
Regulatory Framework
Fremont National Forest Land and Resource Management Plan (LRMP or Forest Plan),
(USDA, Forest Service 1989 as amended)
The Forest Plan provides direction regarding resource management activities and establishes
management standards and guidelines. In regards to road management the plan states:
Transportation Report
Oatman Restoration Project Page 5
The Forest Plan sets as a goal, “a safe and economical transportation system providing
efficient access for the movement of people and materials” (page 51).
“The transportation system will serve long-term multiple resources…(with)…the minimum
system necessary to provide access for the activities authorized under management area
direction. ” (p.116)
Overall density for roaded areas of the Forest will not exceed 2.5 miles per square mile
(p.116).
“All system roads will be operated and maintained to protect the resources, perpetuate the
intended road management objective, and promote safety.” (p. 116)
These protective measures are achieved by limiting activities according to road maintenance
level standards and limiting access on closed roads. The requirement that all seasonal and special
vehicle designation outlined in the current Travel Management Decision shall remain in effect,
works to protect other resource management areas. The safety of the transportation system is
retained through maintaining current standards.
National Forest Management Act (NFSMA) (1976)
The National Forest Management Act provides direction in regards to changes in the Forest Plan
that may affect permits. In regards to road use and off-road use implemented under the Fremont-
Winema National Forests Motorized Travel Management Environmental Assessment (2010), the
following statement directs changes to be made to contract activities when land management
plans (i.e. Forest Plans) are revised:
"(i) Resource plans and permits, contracts, and other instruments for the use and occupancy
of National Forest System lands shall be consistent with the land management plans. Those
resource plans and permits, contracts, and other such instruments currently in existence shall
be revised as soon as practicable to be made consistent with such plans. When land
management plans are revised, resource plans and permits, contracts, and other instruments,
when necessary, shall be revised as soon as practicable. Any revision in present or future
permits, contracts, and other instruments made pursuant to this section shall be subject to
valid existing rights. (pg. 6)
The Oatman Restoration Project Environmental Assessment is in compliance with the National
Forest Management Act by reviewing all regulatory frameworks that affect the transportation
system. The inclusion of new land management plans allows for permits and contracts to remain
current with evolving current conditions.
Fremont-Winema National Forests Motorized Travel Management Environmental
Assessment (EA), (USDA, Forest Service 2010)
As a requirement of the Travel Management Rule (2005) (36 CFR Parts 212, 251, 261, and 295),
the Forests completed an EA to determine which roads, trails, and areas will be available for
Transportation Report
Oatman Restoration Project Page 6
motorized use, the season of use, and class of motorized vehicles. Cross-country motorized
travel was prohibited, other than for some limited exceptions:
Motor vehicle use that is specifically authorized under a written authorization issued under
Federal law or regulations. This includes such items as special use permits, access to private
property, personal use firewood permits, timber sale contracts, and range allotment. Use of
National Forest System roads and areas would be regulated by conditions listed in the
permits authorizing the use. (p.14)
Requiring that any travel off designated motor vehicle use routes (undocumented roads) must be
permitted use or contract use for projects in the Oatman Project area complies with the Fremont-
Winema National Forests Motorized Travel Management Environmental Assessment.
Alternatives Analyzed in Detail
Three alternatives have been developed and analyzed in detail. Consideration of a “No Action”
alternative has been given through effects analysis comparing/contrasting the actions considered
with the current conditions and expected future conditions should actions not be implemented as
disclosed in Chapter 3 (FSH 1909.15, Chapter 40: 36CFR220.7(b)(2)(ii). The range of
alternatives developed has been deemed reasonable based upon the range of public comments
received and the direction set by 40 CFR 1505.1(e).
Alternative 1 – No Action
Alternative 1 serves as a baseline for evaluation other alternatives during the effects analysis for
proposed actions. Current activities, such as permitted grazing, dispersed recreation use, fire
protection, personal use firewood cutting, invasive plant treatments, public safety, and scheduled
road maintenance within the project area would continue. The existing land and resource
conditions would be otherwise unaffected, except through natural occurrences and processes.
Alternative 1 does not propose any new ground disturbing activities. Therefore, no timber
harvest, wildlife habitat enhancements, riparian and meadow enhancements, or fuels reduction
activities would occur on NFS lands within the project area as a result of this alternative. The
transportation system would not be refined as a result of Alternative 1. No roads would be
reconstructed, nor would any roads be identified for closure or decommissioning. Refer to Map
Appendix A, for a depiction of the existing transportation system.
Direct & Indirect Effects
Under Alternative 1, only routine maintenance and repair of existing road facilities would occur.
As in the recent past, there would be occasional opportunities to replace or upgrade road/stream
crossings and improve road surface drainage as funding allowed.
There would be no comprehensive management activities to recondition and maintain road
systems within the Oatman Project area. This would likely result in continued general
deterioration of road conditions. Potentially this could include vegetation encroachment,
cutbank and fill slope failure and culvert failure. No temporary roads would be constructed or
decommissioned.
Transportation Report
Oatman Restoration Project Page 7
None of the road management recommendations found in the Oatman Roads Analysis Report
would be implemented. Road densities within the projects area’s subwatersheds would remain
high and would not move towards achieving Forest Plan objectives.
Alternative 2 – Proposed Action
The IDT developed the proposed action utilizing information and data gathered from the project
area and with direction from the Deciding Officials.
Forest Plan Amendments
The proposed actions identified under Alternative 2 would need two Fremont Forest Plan
amendments.
Forest Plan Amendment #40
The Fremont Forest Plan would be amended to allow the cutting and removal of conifers greater
than 21 inches diameter at breast height (dbh) in the Oatman project area. The project area will
be exempted from the Eastside Screens because there is a need to remove some conifers greater
than 21inches dbh, excluding five-needle pine species. Approximately 6,500 acres of meadows
and other non-forest vegetation have encroaching conifers that need to be removed to restore the
desired condition and remove seed sources to reduce future encroachment. There is also a need
to remove some conifers greater than 21 inches dbh, excluding five-needle pine species, in the
approximately 21,334 acres of commercial thinning treatments to improve stand health and
achieve the desired watershed resiliency to drought. Specific cutting and retention criteria
provide for promoting forest health and vigor while retaining trees with desired characteristics
for wildlife habitat.
Forest Plan Amendment #41
The Fremont Forest Plan would be amended to use a commercial contract (timber sale or
stewardship) in the Oatman project area as a tool to accomplish thinning treatments in
“dedicated” pine and pine-associated stands, to develop sustainable conditions that would benefit
old growth habitat. Up to approximately 1,249 acres of ponderosa pine-associated old growth
would be thinned. Treatments would be focused on maintaining or promoting late and old
structural conditions, while creating resilient forest conditions.
Silvicultural Treatments
Proposed silvicultural activities within the project area would occur on approximately 14,000
acres. These acres include the following activities:
Approximately 12,177 acres of timber harvest treatments;
Approximately 1,827 acres of plantation thinning;
All treatments will require the use of existing NFS system roads, and some identified existing
non-system roads for access and commercial haul. Approximately 5 miles of temporary road
construction is proposed for harvest access.
Fuels Treatments
Prescribed fire treatments would be utilized to reduce fuel loads on approximately 26,455 acres
of the project area. These methods would include, where appropriate, fire application methods
including, but not limited to, underburning and/or pile burning. Fuels treatments would require
Transportation Report
Oatman Restoration Project Page 8
the use of existing NFS system roads and existing non-system roads for access and
implementation.
Snag Retention Units
Approximately 1,120 acres of snag retention units have been identified to meet both current and
future snag habitat levels, and to provide dispersion across the project area. In these units no
direct harvest activities are proposed. Prescribed fire backing/creeping-in would be permitted.
The use of existing NFS system roads and existing non-system roads would be necessary for
implementation of treatments for wildlife habitat.
Old Growth Habitat Improvements for Wildlife To improve late and old structural stand composition, approximately 1,249 acres of sub-
merchantable and merchantable thinning would be implemented to provide improved habitat for
wildlife and species historically present. The use of existing NFS system roads and existing
non-system roads would be necessary for implementation of treatments for wildlife habitat.
Mountain Mahogany, Aspen, and Black Cottonwood Restoration To improve these habitats, sub-merchantable and merchantable thinning would be permitted as
well as prescribed fire. The use of existing NFS system roads and existing non-system roads
would be necessary for implementation of treatments for wildlife habitat.
Riparian Habitat Conservation Area (RHCA) Restoration
Approximately 1,472 acres of manual thinning from below as well as prescribed fire is
proposed for RHCAs. When identified, headcut and incised channels would be repaired. If fill
material is needed for these restoration efforts, fill material could come from decommissioned
roads or reshaping of the flood plain. The use of existing NFS system roads and existing non-
system roads would be necessary for implementation of treatments for wildlife habitat.
Meadow Restoration To remove encroaching conifers and shrubs, approximately 1,846 acres of meadows would
experience sub-merchantable and merchantable thinning through hand-felling. Prescribed fire
would be permitted via backing/creeping (no direct ignition) into the meadows as well. The use
of existing NFS system roads and existing non-system roads would be necessary for
implementation of treatments for wildlife habitat.
Deer Migration Corridors Within these areas, the same treatments as described under RHCAs and mountain mahogany
stands would occur here. Where cover retention is necessary, removing conifers up to 10 inches
in dbh would occur. The use of existing NFS system roads and existing non-system roads
would be necessary for implementation of treatments for wildlife habitat.
Wildlife Forage Openings Approximately 10 openings within coniferous forest, each up to 5 acres in size, would be
created. Hand-seeding of native grasses, shrubs, and forbs would be an option if monitoring
indicates the need. The use of existing NFS system roads and existing non-system roads would
be necessary for implementation of treatments for wildlife habitat.
Transportation Report
Oatman Restoration Project Page 9
Spring Restoration Five springs have been identified within the project area. Restoration activities would include
removing, through hand-felling, all conifers so the conifer edge is 100 feet from the spring edge.
The use of existing NFS system roads and existing non-system roads would be necessary for
implementation of treatments for wildlife habitat.
Shrub Vegetation Treatments Approximately 2,080 acres of shrub vegetation with no timber overstory, would receive
prescribed fire only. In these areas, up to 500 acres of bitterbrush in MA 1 (mule deer winter
range) to encourage sprouting of new growth would occur. The use of existing NFS system
roads and existing non-system roads would be necessary for implementation of treatments for
wildlife habitat.
Botanical and Cultural Site Protection
In Antelope Flat, up to four new troughs maybe installed to divert livestock use from a pond area
and disperse livestock use throughout the Flat. The area of disturbance for each trough could be
up to 350 square feet. Approximately 3.5 miles of polyethylene pipe would need to be installed
to connect the system. The use of existing NFS system roads would be necessary for
implementation of treatments for wildlife habitat.
Transportation System Refinement
The project area is accessed using NFS roads. The Forest Service has easement on 6 miles of
road that cross on Private land within the Oatman project area. A transportation analysis of the
system roads on NFS lands within the project area was completed on February 7, 2013, based on
the analysis and recommendations for travel management by the Oatman IDT, Table 5
summarizes the proposed travel management strategy for the roads within the Oatman project
area: (A complete road by road listing can be located in the Oatman Travel Analysis document
located in the Oatman project files.)
Table 5 – Summary of Proposed Road Maintenance Level Changes, (See Map Attachment
B – Proposed Transportation and Maintenance Levels and Attachment F – Oatman Project
Travel Analysis Recommendations)
Road Maintenance
Level Categories
Current
Condition
(Miles)
Proposed
(Miles) Comments
ML 3 8 8 No change, arterial road
ML 2 61 49 Includes 2.0 miles of existing non-system road miles converted to ML 2
ML 2 – FS
Easement 1 1 Roads on private currently open to the public under the easement.
ML 1 (Closed) 68 38 Includes 0.3 miles of existing non-system road miles converted to ML 1
ML 1 – FS
Easement 5 6 1 mile of new easement, 5 miles of existing easement added to NFS.
ML 1 *(Status:
Decommission) 9 52
Not all miles will need to be mechanically decommissioned,
approximately 27 miles are either naturally reclaimed, on private land
with no easement, or the road prism could not be found.
TOTALS 152 154
The recommended miles more accurately reflect road miles to be
managed within project area.
Transportation Report
Oatman Restoration Project Page 10
* Status signifies roads have been decommissioned; they are not removed from the forest road database unless on
private land and FS has no easement. These miles are not included when calculating total road miles or road
density.
Approximately 90 miles of road proposed for closure or decommissioning are needed for project
treatments, these roads will closed or decommissioned following completion of work. Road
closure is performed by constructing barricades of rock, earth berms or logs, or a combination of
any of these near the beginning of a road. Closure materials are usually acquired onsite, if
possible. Drainage structures are assessed for functionality, and are maintained prior to closure.
Culverts may be removed and replaced with a drivable ford as a method of putting the road into
storage. All roads identified for decommissioning may be used as a source of material (e.g. soil,
rock, large wood) for restoration projects, including, but not limited to, stream and meadow
restoration projects. All material would come from the existing road prism, and the road bed
would be fully decommissioned as part of the restoration project (i.e. all drainage structures
would be removed and the road be contoured to meet surrounding natural conditions).
Additionally, user created and/or undocumented roads to be decommissioned may be used as a
fill source. When deemed appropriate by the interdisciplinary team, closed roads (ML1) may be
used as a source of material for meadow and stream restoration projects, however these roads
would not be obliterated or re-contoured, these roads would remain in a state of storage for
future use. Closed roads are designated as “Operational Maintenance Level 1” in the Forest
transportation system database following their implementation and placed into storage for later
project use.
There are 52 miles of road proposed for decommission and/or removal from NFS inventory.
Several miles will require little to no mechanical work to accomplish this. This is due to some
roads have become naturally reclaimed, some inventoried NFS roads are on private land and
there are no easements, and some roads were previously decommissioned but not documented in
forest road database. Road decommissioning effectively removes the road from vehicular
access and is meant to allow full re-vegetation and hydrologic function of the roadway’s
footprint on the land. Road decommissioning can be a collection of actions ranging from surface
scarification to a complete re-contouring of the road prism back to a natural slope. In all, road
decommissioning, road approaches are blocked or obliterated, drainage structures are removed
and their sites rehabilitated. Typically, re-vegetation is accomplished through natural seeding.
Material from a decommissioned road maybe used for meadow and stream restoration projects.
Following implementation, decommissioned roads are designated as “Decommissioned” under
the “Route Status” attribute for the subject road in the Forest transportation system database.
Historical data for each road continues to reside within the database.
Road Activities Related to Project Treatments
A field review to determine construction, reconstruction and maintenance needs for roads to be
utilized by the project’s vegetation treatments was conducted in the summer of 2012, in
conjunction with the road system inventory. See Attachment D for a current road by road listing
of potential maintenance and reconstruction needs identified. There are approximately 113 miles
of NFS roads identified in Attachment D for potential timber sale log haul within the Oatman
project. Approximately 52.7 miles are ML 1, 52.6 miles are ML2, and 8 miles are ML 3.
Typically ML 1 roads will be opened using timber sale road maintenance specifications to make
roads serviceable. ML 2 roads will need pre-haul maintenance as these roads normally do not
Transportation Report
Oatman Restoration Project Page 11
receive routine road maintenance. ML 3 roads typically do not receive pre-haul maintenance,
however it could be an option. All roads will be maintained during the life of the timber sale,
using timber sale road maintenance specifications.
Approximately 5 miles of new temporary road construction have been identified for harvest
access. Temporary roads would be built to the lowest possible standard to facilitate timber
removal. All temporary roads are proposed for decommissioning following completion of
harvest activities, and would not add to the long term road system density.
Approximately 2.3 miles of non-systems roads were inventoried during the 2012 field review of
the project area. As recommended through Travel Analysis for this project, 2.0 miles would be
converted to a ML2 NFS road and 0.3 miles would be converted to an ML1 NFS road.
Approximately 1.1 miles of new road easement is needed. It has been identified that road
2804263 is not under easement, it is needed to access NFS land and NFS roads in T28S R12E
Sec. 32 SE & Sec. 33 SW, and T29S R12E Sec.4 NW & Sec.5 NE, without these easements
treatment acres would be reduced. All roads currently exist and would require maintenance prior
to haul. After treatments, the road would be physically closed at NFS boundary. The beginning
and ending milepost location for the road is from road 2804038 to junction with road
2804093(NFS boundary). Easement roads are typically treated as NFS roads, which add to the
total NFS miles.
Road Construction/Reconstruction
No new permanent road construction is proposed by this project. Road reconstruction activities
are usually performed prior to timber haul and are designed to bring adverse road conditions up
to haul and environmental standards. Roads are reassessed as part of the preparation for timber
harvest; if additional re-construction needs are identified they are included in the project work.
Reconstruction activities may include drainage improvement (i.e. constructing new drain
dips/water bars, installing larger/new culverts, constructing rock fords), large quantity surfacing
addition/replacement, subgrade or base rock reconstruction, heavy roadside brushing, clearing of
saplings that have grown into the road, large quantity cut bank slump removal and large scale
erosion control such as rip rap placement.
During the field review (summer 2012), approximately 24 miles of reconstruction was identified
for Oatman project roads (Attachment D), much of this consists machine brushing and clearing
trees ( less than 10” DBH), drain dips, culvert replacement and/or ford construction.
Approximately 3-4 miles of road prism will need reconstructed for travel, location of and extent
of this work will be identified during project field preparation, and in conjunction with road
preparations for haul.
Road Maintenance
Road maintenance activities for a timber sale are performed during three general timeframes
within the life span of the sale: pre-haul, during haul, and post haul.
Pre-haul road maintenance prepares the project road system for heavy truck traffic related to
the sale.
Transportation Report
Oatman Restoration Project Page 12
During haul maintenance sustains optimum road conditions favorable to continued haul
activity.
Post haul maintenance ensures that road elements within the sale area and on the haul routes
within the National Forest are returned to their full operational maintenance level standards.
Timber sale road maintenance activities generally consist of surface blading, ditch pulling, light
to medium roadside brushing, danger tree felling, culvert cleaning, small quantity cut bank slump
removal, spot surfacing addition/replacement and maintenance of existing drainage structures
(i.e. water bars, drain dips). For ML 1 roads this may include barrier removal, temporarily
replacing culverts and re-shaping fords, brushing and clearing. Treatment related road
maintenance may take place on all forest roads.
Direct & Indirect Effects
The transportation system located within the boundaries of the project area was analyzed
individually for direct and indirect effects. The timeframe, for which the effects to the
transportation system were analyzed, is the expected to be the duration of time for completion on
all projects (5 – 10 years). These boundaries were selected because it provides the most
immediate effects from the transportation actions which would occur from the proposed
management activities. The analyses of effects to the transportation system are defined as both
short and long term. Short term for this analysis is the end of one field season and the beginning
of the next. Long term is the duration of time until completion of projects (up to 10 years). The
direct and indirect effects of the Oatman Project have been analyzed to determine if there would
be any effect to road management objectives, road maintenance standards and motorized vehicle
use.
Measurement Indicators The possible effects of the proposed alternatives on the transportation resource within the
Oatman Project area are discussed quantitatively using the indicators below. In Table 6, the No
Action Alternative is equivalent to the Current Conditions.
Table 6: Measurement Indicators
Measurement Indicator
Current
Condition
All Action
Alternatives
Oatman Project Area Roads: (All Ownerships)
Total NFS road miles (excluding decommissioned roads) 143 102
Total miles of open NFS road 70 58
Miles of ML 3 – Open to passenger cars 8 8
Miles of ML 2 – Open to high clearance vehicles 62 50
Miles of ML 1 – Closed to motorized vehicles 73 44
Miles of ML 1 - Status Decommissioned 9 52
Oatman Project Area Roads: ( NFS Lands Only)
Total NFS road miles (excluding decommissioned roads) 138 95
Total miles of open NFS road 69 57
Miles of ML 3 – Open to passenger cars 8 8
Miles of ML 2 – Open to high clearance vehicles 61 49
Miles of ML 1 – Closed to motorized vehicles 69 38
Miles of ML 1 - Status Decommissioned 9 52
Transportation Report
Oatman Restoration Project Page 13
Measurement Indicator
Current
Condition
All Action
Alternatives
Road Maintenance / Reconstruction
NFS road miles to be reconstructed for project use 0 24
NFS road miles to be maintained 8 113
ML 1 road miles to be opened for project use 0 46
Existing Non-System Roads
Total miles of existing non-system roads 2.3 2.3
Miles of existing non-system roads added to NFS inventory as ML2 0 2.0
Miles of existing non-system roads added to NFS inventory as ML1 0 0.3
Miles of existing non-system roads used for MADC access 0.2 0.2
Motorized Vehicle Use Designations
Miles of road closed to public use 78 90
Miles of road open to Highway Legal Motor Vehicles Only, YEARLONG 0 0
Miles of road open to Highway Legal Motor Vehicles Only, SEASONAL
4/1 – 11/30 0.3 0.3
Miles of road Open to All Motor Vehicles Only, YEARLONG 33 23
Miles of road Open to All Motor Vehicles Only, SEASONAL 4/1 – 11/30 37 35
Trails Open to All Motor Vehicles 0 0
Miles of Motorized Access to dispersed Camping (MADC) 50 50
NFS Land Road Density by Subwatershed (Miles/Sq. Mile)
Total Road /
Open Road
Total Road /
Open Road
Bear Creek 3.8 /2.0 2.6/1.4
Buck Creek 1.7/0.5 1.3/0.5
Oatman Flat 2.4/1.1 1.8/1.3
Timothy Creek 2.4/1.6 2.0/1.2
Total NFS land 3.2/1.7 2.3/1.4
Effects Common to All Action Alternatives
Implementation of the recommendations made under the Oatman Restoration Project Travel
Analysis. The report proposes reducing the closed roads through decommissioning. Additional
refinement to open road miles and decommissioning of open road miles aided in the reduction of
overall road miles. Proposals to change ML designations between ML 2 – 3 allow designations
to better align with current use and road management objectives. The reduction in closed road
miles due to decommissioning and ML changes aids in the reduction of resource damage, and
removes roads no longer needed. Table 6 summarizes the changes to the road maintenance
levels and reduction in NFS system roads. Maintaining the roads at their existing ML would
continue to misallocate resources and misrepresent accessibility conditions on the landscape. As
such, there would be beneficial direct and indirect effects anticipated to road management
objectives and road maintenance standards by these changes to MLs.
The closing and decommissioning of approximately 90 miles of system roads would reduce
administrative and public access to National Forest lands. However, these changes would bring
the current road densities closer to achieving Fremont Forest Plan direction to reduce overall
road densities on NFS land, and within the affected sub-watersheds to closer to the 2.5 miles per
square mile. Despite reductions, no negative direct or indirect effects are anticipated from road
closures or decommissioning, as there would still be approximately 58 miles of open road within
Transportation Report
Oatman Restoration Project Page 14
the project area. Access to some specific locations would change, but overall accessibility within
the project area remains similar. Road densities following full implementation of the road
management recommendations are shown in the Table 6.
This alternative proposes using approximately 113 miles of system road for log haul.
Approximately 53 miles of ML 1, 53 miles of ML 2, and 8 miles of ML3 roads have been
identified for haul. Road maintenance and reconstruction activities would be performed to bring
road to safe haul standards. Road maintenance and reconstruction activities are designed to
effectively drain storm waters from existing roadways, maintain or replace culverts, blade out
washboard roads, and mitigate roadside hazards. Although routine road maintenance occurs on
ML 3 roads, this may be the only opportunity for a substantial period of time, to perform road
maintenance on ML 1 and 2 roads in this area. This road maintenance would effectively reduce
sediment delivery to streams and lower the potential risk of culvert and fill failures both during,
and for a number of years following, project treatments. As such, there are beneficial direct and
indirect effects expected from maintenance of the 113 miles of road for log haul.
Approximately 1.1 miles of new road easement will be needed to gain access into treatment areas
proposed; these miles would be added to the NFS system roads inventory as a ML 1. This road
currently exists and would require maintenance prior to haul. After harvest, these 1.1 miles of
road would be closed. Road maintenance for haul may be the only opportunity for a substantial
period of time for portions of this road to receive maintenance. Like ML 1 and ML 2 roads,
maintenance on this easement road would be expected to provide beneficial effects.
The Oatman Roads Analysis report recommends a refinement in the NFS road system that would
create changes to the Fremont-Winema NFs Motor Vehicle Use Map (MVUM). Approximately
2.3 miles of non-systems roads were inventoried during the 2012 field review of the project area.
As recommended through Travel Analysis for this project, 2.0 miles would be converted to a
ML2 NFS road and 0.3 miles would be converted to an ML1 NFS road. Like ML 1 and 2 roads,
maintenance on these non-system roads would be expected to provide beneficial direct and
indirect effects.
The refinement of the NFS road system and reduction in closed road miles would create changes
to the Fremont-Winema NFS’s Motor Vehicle Use Map (MVUM) (Map Attachment C). A total
reduction of 12 miles of roads open to all motorized vehicles is proposed through closing or
decommissioning to provide for reductions in resource damage found to be occurring because of
motorized access or to remove overgrown or inaccessible roads found during field reviews.
There are no expected direct or indirect effects to road management objectives, road maintenance
standards, or motorized vehicle use resulting from the construction of approximately 5 miles of
temporary roads. Temporary roads would be created for use of implementation of the proposed
actions and would be obliterated after use.
Alternative 3 Alternative 3 was designed to address the issues identified through the scoping process while
meeting the need for action, as described in Chapter 1. Alternative 3 is identical to Alternative 2
except that cutting ponderosa pine greater than 21 inches dbh would not be permitted.
Transportation Report
Oatman Restoration Project Page 15
Alternative 3 would still require a project specific Forest Plan amendment to allow cutting white
fir and lodgepole pine greater than 12 inches dbh. The amendment would be identical to Forest
Plan Amendment #40 under Alternative 2, except that is would exclude ponderosa pine.
Direct and Indirect Effects Even with the difference between Alternative 2 and Alternative 3, the proposed acres of
disturbance are the same for Alternative 3 as in Alternative 2. Therefore, the direct and indirect
effects of Alternative 3 are identical to those addressed under Alternative 2.
Cumulative Effects of Alternative 2 and 3
Cumulative effects are defined as the impact on the environment which results from the
incremental impact of the action when added to other past, present, or reasonably foreseeable
future actions. In order to understand the contribution of past actions to the cumulative effects of
the proposed action and alternatives, this analysis relies on current environmental conditions as a
proxy for the impacts of past actions. Existing conditions reflect the accumulated impact of all
prior human actions and natural events that have affected the environment and might contribute
to cumulative effects. The spatial bound for cumulative effects analysis is the sub-watersheds
that overlap the Oatman Project area, and the temporal bounds are 30 years. Past, present, and
reasonably foreseeable activities include but not limited to livestock grazing, road construction
and maintenance, invasive plant management, and continued land management such as
commercial and non-commercial thinning, fuels treatments and fire.
Access to livestock grazing, recreation, and firewood gathering do not impact road conditions
because very little use occurs under wet spring conditions and the otherwise low use (as evident
by the amount of brushed in roads) has minimal effect on the road system. These ongoing
actions will have no measureable cumulative effects to road conditions with the proposed
actions. Public safety on the roads available for motorized use would be improved by the road
maintenance for the commercial sale activities.
Project Design Criteria
Best Management Practices (BMPs) would be incorporated into project design and
implementation (USDA Forest Service, 2012), utilizing Fremont-Winema BMP site
specific guidelines for roads (see Attachment E).
Road closure in this project would include the construction of rock barricades, earth or
log berms, or a combination of any of these near the beginning of a road. Closure
materials would be acquired on site, when possible.
Road decommissioning would range from surface scarification to a complete re-
contouring of the road prism back to a natural slope.
In all road decommissioning, drainage structures would be removed and their sites
rehabilitated according to BMPs.
Typically, re-vegetation of decommissioned roads is accomplished through natural
seeding, however hand seeding of native species could occur if natural regeneration is not
meeting resource objectives.
A closure device (e.g., berm) should be used when decommissioning any portion of a
system road, except when the road is currently overgrown with vegetation and is already
impassable to motorized vehicles.
Transportation Report
Oatman Restoration Project Page 16
Wherever practical, a closure device should be placed at the entrance of a network of
roads rather than closing each individual segment.
All temporary roads will be obliterated, using the same design criteria utilized to
decommission existing system roads.
All closed roads, which are to remain as ML1, and are opened to access treatment areas
would be closed upon completion of operations.
Fill material from decommissioned roads maybe used as fill material for headcut and
incised channel restoration efforts.
References
National Forest Management Act (NFSMA) (1976)
USDA Forest Service. 1989. Fremont National Forest Land and Resource Management Plan
(LRMP).
USDA Forest Service. 2010. Fremont-Winema National Forests Motorized Travel Management
Project.
USDA Forest Service. 2012. National Best Management Practices for Water Quality
Management on National Forest System Lands, Volume 1: National Core BMP Technical
Guide. FS-990a.
Transportation Report
Oatman Restoration Project Page 17
Attachment E
ROAD SYSTEM BMPS
R-2. Erosion Control Plan
Objective: To limit and mitigate erosion and sedimentation through effective planning prior to
initiation of road construction activities and through effective contract administration during
construction.
Explanation: Land disturbing activities, such as road construction, usually result in short term
erosion. By effectively planning for erosion control, sedimentation can be minimized. Prior to
starting work, the Contractor submits a general plan which sets forth erosion control measures to
be used. Operations cannot begin until the Forest Service has given written approval of the plan.
The plan recognizes the mitigation measures required in the contract. All contracts specify that
operations be scheduled and conducted to minimize erosion.
Implementation and Responsibility: Mitigative measures are developed by design engineers,
using an interdisciplinary approach; the measures are reflected in the contract's specifications and
provisions.
Erosion control is required by contract provisions common to road construction. The Erosion
Control Plan is implemented by the Purchaser on timber sale contracts or Contractor on Public
Works Projects.
This practice is commonly applied to road construction or timber sales, but should be extended to
apply to road construction for mining, recreation, special uses, and other roadwork on the Forest.
Monitoring: Contract packet review, prework meetings, and operating plans along with tests,
measurements, and observations by the COR or ER and watershed specialists. Also see Forest
Plan monitoring plan.
R-3. Timing of Construction (Reconstruction) Activities
Objective: To minimize erosion by conducting road construction operations during minimal
runoff periods.
Explanation: Since erosion and sedimentation are directly related to runoff, scheduling
operations during periods when the probabilities for rain and runoff are low is an essential
element of effective erosion control. Contractors are to schedule and conduct operations to
minimize erosion and sedimentation. Equipment shall not be operated when ground conditions
are such that excessive damage will result. Such conditions are identified by the COR or ER
with the assistance of watershed specialists as needed.
In addition, it is important to keep erosion control work as current as practicable with on-going
operations during anticipated runoff periods. Construction of drainage facilities and performance
Transportation Report
Oatman Restoration Project Page 18
of other contract work which contribute to the control of erosion and sedimentation shall be
carried out in conjunction with earthwork operations, or as soon thereafter as practicable. The
Contractor should limit the amount of area not graded to drain at any one time, and should install
permanent drainage structures as soon as practical.
Implementation and Responsibility: Mitigative measures are developed by design engineers,
using an interdisciplinary approach and are incorporated into the contracts.
Contracted projects are implemented by the Contractor or Purchaser. Compliance with plans,
specifications, and the operating plan is determined with tests, measurements, and observations
by the COR or ER through inspection.
Monitoring: Road construction review process. Also see Forest Plan monitoring plan.
R-5. Road Slope and Waste Area Stabilization (Preventive)
Objective: To minimize soil erosion from cut slopes, fill slopes, and waste areas.
Explanation: Depending on various factors such as slope angle, soil type, climate, and proximity
to waterways, many fill slopes, some cut slopes, and waste areas will require vegetative and/or
physical restraint measures to provide for adequate surface soil stability. The level of
stabilization effort needed must be determined on a case-by-case basis by appropriate personnel.
Vegetation measures include the seeding of herbaceous species (grass, legumes, or browse
species), or the planting of brush and trees. Vegetative measures may include fertilization and
mulching to ensure success.
Physical restraint measures may include, but are not limited to grading, ditches, scattering
vegetative debris, erosion nets, terraces, side drains, blankets, mats, riprapping, mulch, tackifiers,
pavement, and soil seals.
Implementation and Responsibility: Vegetative measures can improve the effectiveness of
physical restraint measures, but may not be effective and complete by themselves for the first
several seasons.
Physical restraint and vegetative surface stabilization measures will be periodically inspected, as
necessary, to determine effectiveness. In some cases, additional work may be needed to ensure
that the vegetative or mechanical surface stabilization measures continue to function as intended.
Initial project location, mitigative measures, and management requirements and needs are
normally developed during the environmental analysis process, using an interdisciplinary
approach. These requirements and needs are translated into contract provisions and
specifications.
Transportation Report
Oatman Restoration Project Page 19
Monitoring: Forest Service work leaders, road inspectors, and their supervisors monitor work
accomplishment and effectiveness, to help ensure that design standards, project plan constraints,
and mitigative measures are met. Watershed specialists assist in implementation and
effectiveness evaluations. Also see Forest Plan monitoring plan.
R-6. Dispersion of Subsurface Drainage Associated with Roads
Objective: To minimize the possibilities of roadbed and cut or fill slope failure and the
subsequent production of sediment.
Explanation: Roadways may change the subsurface drainage characteristics of a hillside. Since
changes to normal areas and interruption of subsurface flows increase the risk of instability, it is
sometimes necessary to provide special drainage (subsurface) to avoid saturation of the subgrade
and slopes to reduce subsequent slope failure. The following are some dispersion methods
which can be used:
a. pipe underdrains
b. horizontal drains
c. stabilization trenches
d. drainage blankets or rock drains
e. ditches
Dispersal of collected water should be accomplished in an area capable of withstanding
increased flows. On most soils, energy dissipators need to be placed at pipe outlets. This is a
preventive practice.
Implementation and Responsibility: Locatable wet areas and areas with underground flows are
designed with appropriate mitigative measures to provide subsurface drainage. Locating such
areas may involve geologists, engineers, soil scientists, and hydrologists.
Contracted projects are implemented by the Contractor or timber sale Purchaser. Compliance
with project plan and specifications requirements, and operating plans is determined with tests,
measurements, and observations by the COR or ER. Additional sites found during construction,
or necessary changes to known sites, are designed in the same manner as the original sites.
Monitoring: Plan-in-hand review, design review, and road construction review process. Also
see Forest Plan monitoring plan.
R-7. Control of Surface Road Drainage Associated with Roads
Objective: -To minimize the erosive effects of water concentrated by road drainage features.
-To disperse runoff from or through the road.
-To minimize the sediment generated from the road.
Transportation Report
Oatman Restoration Project Page 20
Explanation: A number of measures can be used, alone or in combination, to minimize possible
detrimental effects of surface drainage. Culverts or bridges are normally placed at all natural
drainages crossed by roads. Ditches, cross drains, water bars, dips, and grade sags are used to
take water off the roadbed surface.
Methods used to reduce erosion may include such things as energy dissipators, aprons,
downspouts, gabions, debris racks, and armoring ditches and drain inlets and outlets. Soil
stabilization can help reduce sedimentation by reducing the effects of erosion on borrow and
waste areas, on fill slopes, and on roadbeds.
Dispersal of runoff from roads can be accomplished by rolling the grade, insloping with cross
drains, outsloping, crowning, installation of water spreading ditches, contour trenching, etc.
Dispersal of runoff can reduce peak downstream flows and keep water in its natural drainage
area.
Sediment travel can be reduced by installing measures such as sediment filters, settling ponds,
and contour trenches.
Implementation and Responsibility: Soil erosion classification, parent rock, steepness of side
slopes, soil type, and road grades are used to assist in project location, design criteria, and
mitigative measures used by designers for surface drainage. The data is determined using an
interdisciplinary approach during the environmental analysis and road design process, and then
placed in contracts.
Contracted projects are implemented by the Contractor or Purchaser. Compliance with plans,
specifications, and operating plans is determined with tests, measurements, and observations by
the Forest Service COR or ER.
Monitoring: Tag-line review, design review, and road construction review process. Watershed
specialists assist with implementation and effectiveness evaluations. Also see Forest Plan
monitoring plan.
R-9. Timely Erosion Control Measures on Incomplete Roads and Stream Crossing
Projects
Objective: To minimize erosion of and sedimentation from disturbed ground on incomplete
projects.
Explanation: The best drainage design can be ineffective if projects are incomplete at the end of
the dry season. Affected areas can include roads, waste areas, tractor trails, skid trails, landings,
fills, streamcrossings, and bridge excavations. Preventive measures include:
a. Removal of temporary culverts, culvert plugs, diversion dams or elevated streamcrossing
causeways;
Transportation Report
Oatman Restoration Project Page 21
b. Installation of temporary culverts, side drains, flumes, cross drains, diversion ditches, energy
dissipators, dips, sediment basins, berms, debris racks or other facilities needed to control
erosion;
c. Removal of debris, obstructions, and spoil material from channels and floodplains;
d. Grass seeding, placement of hay bales, and mulching.
Implementation and Responsibility: Protective measures must be applied to all areas of
disturbed, erosion-prone, unprotected ground. When conditions permit operations outside of the
dry season, erosion control measures must be kept current with ground disturbance, to the extent
that the affected area can be rapidly "closed," if weather conditions deteriorate. Areas should not
be abandoned for the winter with remedial measures incomplete.
Project mitigative measures and location are developed and documented during the
environmental analysis process using an interdisciplinary approach.
Contracted projects are implemented by the Contractor or Purchaser. Compliance with project
plan criteria, contract specifications, and operating plans is determined with tests, measurements,
and observations by the COR or ER.
Monitoring: Road construction review process and observation during and after project
completion. Also see Forest Plan monitoring plan.
R-11. Control of Sidecast Material
Objective: To minimize sediment production originating from sidecast material during road
construction or maintenance.
Explanation: Unconsolidated sidecast material can be difficult to stabilize and is susceptible to
erosion, settling, and mass instability. Site-specific limits or controls for sidecasting
uncompacted material should be developed through interdisciplinary input. Sidecasting is not an
acceptable embankment placement alternative in areas where it will adversely affect water
quality. Road widths on full bench ground should not include any width on side cast material
without prior approval of the COR or ER.
Waste areas should be located where excess material can be deposited and stabilized. The
location and provisions for disposal of waste materials are included in construction contracts.
During road maintenance operations, the deposition of sidecast material shall be done where it
will not weaken stabilized slopes. Disposal of slide debris shall be done only at designated waste
areas where deposited material can be stabilized or approved for sidecast placement, which may
include the road surface and fill slopes.
Implementation and Responsibility: Mitigative measures are developed through the
environmental analysis and road design process, using an interdisciplinary approach, and are
included in the project specifications, drawings, or guidelines.
Transportation Report
Oatman Restoration Project Page 22
Contracted projects are implemented by the Contractor or timber sale operator. Compliance with
project criteria, contract specifications, and operating plans is determined with tests,
measurements, and observations by the COR, ER, or maintenance engineer.
Contracts and guidelines address slide and slump repair, surface blading, and the placement of
waste road material to reduce sidecasting.
Monitoring: Road design review, progress review during construction, and maintenance activity
reviews. Also see Forest Plan monitoring plan.
R-12. Control of Construction in Streamside Management Units
Objective: To reduce the adverse effects of sediment from nearby roads on slope stability,
vegetation, and aquatic resources along a designated stream zone by:
a. Acting as an effective filter for sediment generated by erosion from road fills, dust drift,and
oil traces;
b. Maintaining shade, riparian habitat (aquatic and terrestrial), and channel stabilizing effects;
c. Maintaining the floodplain in an undisturbed condition.
Explanation: Except at designated stream crossings, road fills, waste areas and other
embankments must be kept at a distance from nearby streams. Factors such as stream class,
channel stability, sideslope, ground cover, and soil stability are taken into account in developing
riparian and streamside management unit widths. It is vital to stabilize fill slopes and control
water runoff to minimize the movement of sediment into streamside management units.
Stream classes and streamside management unit widths are determined by an interdisciplinary
process involving hydrologists, fisheries biologists, and other specialists as required.
Implementation and Responsibility: Project location and mitigative measures are developed by
the interdisciplinary team. Specifications are inserted into the contract by design engineers.
Contracted projects are implemented by the Contractor or Purchaser. Compliance with
environmental criteria, contract specifications, and operating plans is determined with tests,
measurements, and observations by the COR or ER.
Monitoring: NEPA field review process, tag line review, design review, and progress review
during construction. Also see Forest Plan monitoring plan.
R-13. Diversion of Flows Around Construction Sites
Objective: - To ensure that all stream diversions are carefully planned.
Transportation Report
Oatman Restoration Project Page 23
- To minimize downstream sedimentation.
- To restore stream channels to their natural grade, condition and alignment as soon
as possible.
Explanation: Flow must sometimes be guided or piped around streamside project sites. Typical
examples are bridge and dam construction, or large culvert installation. Flow in stream courses
will be diverted if the Forest Service deems it necessary due to expected sediment production
during construction. Such a diverted flow shall be restored to the natural streamcourse as soon as
practicable and, in any event, prior to normal periods of precipitation runoff.
Implementation and Responsibility: This practice is required by contract provisions. The
planning and design process will identify where diversions are required, and the design will
include mitigative measures to protect fishery values and other downstream uses. The planning
process may include consultation with other Federal, State, or local agencies and private parties
to ensure that all factors are considered.
Project location, bypass design, and mitigative measures are identified in the design and planning
process to meet project criteria.
Contracted projects are implemented by the Contractor or Purchaser. Compliance with project
criteria, contract specifications and operating plans is determined with tests, measurements, and
observations by the COR or ER.
Monitoring: Progress review during construction and road construction review process. Also
see Forest Plan monitoring plan.
R-14. Bridge and Culvert Installation and Protection of Fisheries
Objective: To minimize sedimentation and turbidity resulting from excavation for in-channel
structures.
Explanation: Excavation is a common requirement for the installation of bridges, culverts and
minor streamside structures such as weirs, check dams, or riprapping. Waste material developed
in such operations should neither obstruct the streamcourse (including natural floodplains) nor
the efficiency of the associated structures. Some preventive and corrective measures are:
a. Excavated materials shall be kept out of live streams unless they are designed to be
placed there. (i.e. riprap, etc.)
b. Sediment producing materials will not be left within reach of anticipated flood flows.
c. It is sometimes necessary to divert flowing water around work sites to minimize erosion
and downstream sedimentation.
Transportation Report
Oatman Restoration Project Page 24
d. When needed, bypass and access roads shall be suitably located with plans made for their
subsequent obliteration and stabilization.
For streams designated as important fisheries by Forest Service fisheries biologists, culverts will
be installed only during flow periods specified in the project plan. Normally, this work would
occur during minimum flow periods when water could be more easily diverted; work would not
be allowed during salmonid fish spawning periods or before eggs have hatched and fingerlings
have emerged from the gravel. Downstream sediment basins may be necessary to mitigate
impacts on low flows.
Implementation and Responsibility: Project location and mitigative measures are developed
during the road design process to meet the project criteria, using an interdisciplinary approach
when deamed necessary.
Contracted projects are implemented by the Contractor or Purchaser. Compliance with project
criteria and the operating plan is determined with tests, measurements, and observations by the
Forest Service COR or ER through inspection.
Monitoring: NEPA field review process, plan in hand review, design review, progress review
during construction and road construction review process. Also see Forest Plan monitoring plan.
R-18. Maintenance of Roads
Objective: To maintain roads in a manner which provides for water quality protection by
controlling the placement of waste material, keeping drainage facilities open, and by repairing
ruts and failures to reduce sedimentation and erosion.
Explanation: Roads normally deteriorate because of use and weather impacts. This deterioration
can be reduced through adequate maintenance or restriction of use. All system roads will be
maintained to at least the basic custodial care required to maintain drainage, protect the road
investment, and minimize damage to adjacent land and resources. This level is the normal
prescription for roads that are closed to traffic. Higher levels of maintenance may be chosen to
reflect greater use or resource protection. Additional maintenance measures could include
resurfacing, outsloping, clearing debris from ditches and cross drains, restoration of ditches, and
spot rocking.
Annually, the Forest Service determines the maintenance needs of each road. Roads to be
maintained by commercial users are considered. The process to accomplish maintenance
activities are budgeted and contracted or scheduled for force account work. The Forest Service
may collect deposits for commercial use to facilitate road maintenance and to equitably assess
maintenance cost of each user.
Implementation and Responsibility: The work is controlled by maintenance engineers who
prioritize work to fit the budget and develop a road maintenance plan. Maintenance levels for
each road are documented in road management objectives. Maintenance on timber sale roads is
Transportation Report
Oatman Restoration Project Page 25
a Contractor responsibility commensurate with their use. On roads not maintained by active
timber sales, the work is accomplished with Forest Service crews or by contract. Compliance
with the contract provisions is determined with tests, measurements, and observations by the
COR or ER.
Monitoring: Timber Sale road package or Public Works Contract review and on the ground
review of road maintenance practices on the Forest. Also see Forest Plan monitoring plan.
R-19. Road Surface Treatment to Prevent Loss of Materials
Objective: To minimize the erosion of road surface materials and consequently reduce the
likelihood of sediment production from those areas.
Explanation: Unconsolidated road surface material is susceptible to erosion during periods of
precipitation. Likewise, dust derived from road use may settle onto adjacent water bodies.
Road surface treatments include grading, watering, dust oiling, penetration oiling, sealing,
aggregate surfacing, chip-sealing, or paving, depending on traffic, soils, geology, road design
standards, the road objectives,and available funding.
Implementation and Responsibility: Project location and mitigative measures are developed by
the design or maintenance engineer to meet project criteria.
Contracted projects are implemented by the Contractor or Purchaser. Compliance with project
criteria, contract specifications, and operating plans is determined with tests, measurements, and
observations by the COR or ER.
Monitoring: Road construction review process. Also see Forest Plan monitoring plan.
R-20. Traffic Control During Wet Periods
Objective: -To reduce road surface damage and rutting of roads.
-To lessen sediment washing from damaged road surfaces.
Explanation: The unrestricted use of roads during wet weather can result in rutting and churning
of the road surfaces. Runoff from such damaged road surfaces carries a high sediment load. The
damage and maintenance cycle for roads that are frequently used in winter can create a disturbed
road surface that is a continuing sediment source.
Roads involving more than casual use during wet periods shall have a stable surface and
sufficient drainage to allow such use with a minimum of resource impact. Rocking, oiling,
paving, and armoring are measures that may be necessary to protect the road surface and reduce
material degradation. In many cases, use can be discouraged, but not eliminated. Where winter
field operations are planned, roads may need to be upgraded, use restricted to low ground
Transportation Report
Oatman Restoration Project Page 26
pressure vehicles, or maintenance intensified to handle the traffic without creating excessive
erosion and damage to the road surfaces.
Implementation and Responsibility: Project-associated implementation procedures can be
eNFSorced by Forest Service personnel. Hauling activity can be controlled by the Sale
Administrator or maintenance ER within active timber sales. The decision for restricted use is
based on local weather, soil moisture conditions, and road damage criteria.
Mitigative measures are developed by engineers using an interdisciplinary approach as
necessary. Contracted projects are implemented by the Contractor or Purchaser. Compliance
with plans, specifications, and operating plans is determined with tests, measurements, and
observations by the Forest Service COR or ER.
Monitoring: Timber Sale road package or Public Works Contract review, and forest road
management inspection trips. Also see Forest Plan monitoring plan.
R-21. Snow Removal Controls to Avoid Resource Damage
Objective: To minimize the impact of melt water on road surfaces and embankments and to
consequently reduce the probability of sediment production resulting from snow removal
operations.
Explanation: This is a preventive measure used to protect resources and indirectly to protect
water quality. Forest roads are sometimes used during the winter for a variety of reasons. For
such roads, the following measures are employed to meet the objectives of this practice:
a. The Contractor or permittee is responsible for snow removal in a manner which will
protect roads and adjacent resources.
b. Rocking or other special surfacing and drainage measures may be necessary, before the
operator is allowed to use the roads.
c. Snow berms shall be removed or breached to avoid accumulation or channelization of
melt water on the road and prevent water concentration on erosive slopes or soils. If the
road surface is damaged, the Contractor or permittee shall replace lost surface material
with similar quality material and repair structures damaged in blading operations, unless
otherwise agreed to in writing.
Implementation and Responsibility: Project location and mitigative measures are developed by
the maintenance engineer and District resource assistant.
Contracted projects are implemented by the Contractor or Purchaser. Compliance with
developed criteria and the operating plan is determined with tests, measurements, and
observations by the COR, ER or maintenance engineer.
Transportation Report
Oatman Restoration Project Page 27
Monitoring: Forest road management inspection trips; see implementation section for tracking.
Also see Forest Plan monitoring plan.
R-23. Obliteration of Temporary Roads and Landings
Objective: To reduce sediment and restore productivity of the land at the completion of intended
use.
Explanation: Temporary roads are constructed for a specific short-term purpose, such as, ski
area development roads and logging spurs on a timber sale. In order to prevent continued low
level casual use, such roads and landings are obliterated at the completion of their intended use.
Due to the location, grades, and drainage are often inadequate for long-term use and
maintenance. Temporary roads that are allowed to remain in use beyond their prescribed time are
subject to continued, uncorrected damage, and they can become chronic sediment sources.
Effective obliteration is generally achieved through a combination of these measures:
a. Temporary culverts and bridges removed and natural drainage coNFSiguration
reestablished.
b. Road surface deep ripped.
c. Sideslopes reshaped and stabilized.
d. Road effectively drained and blocked.
e. Road returned to resource production through revegetation (grass, browse, or trees).
The National Forest Management Act requires that all temporary roads be returned to resource
production within ten years.
Implementation and Responsibility: Obliteration of the road to the level that it is blocked to
vehicular traffic, culverts and bridges removed, and the roadway stabilized is required by the
TSC. Further revegetation needs are addressed in Sale Area Improvement Plans to achieve
resource production above that required for stabilization of the road bed surface.
Temporary road location and stabilization measures are determined by the Sale Administrator by
agreement with the Purchaser. The sale administrator may request the advice of a watershed
specialist in determining the most appropriate location and stabilization measures required.
Forest Service crew leaders and supervisors are responsible for ensuring that other temporary
roads built for force account projects meet design standards and project EA criteria. Temporary
roads built on Forest Service administered lands through special use permits or easements are
subject to the same obliteration requirements as temporary roads on timber sales. District
Rangers or their representatives are responsible for assuring the obliteration of such roads is
accomplished.
Monitoring: Post-sale reviews by the Sale Administrator. Also see Forest Plan monitoring plan.