Upload
anjali-gurejani
View
217
Download
0
Embed Size (px)
Citation preview
7/30/2019 The IIS University
1/15
The IIS UniversityCOST ACCOUNTING PROJECT
PROCESS COSTING
Submitted to
Mr. Ashish
Khandelwal
Submitted by-
Anjali Gurejani
Anukrati Gupta
Harshika Gupta
BBM Sec A Sem VI
7/30/2019 The IIS University
2/15
Process Costing : Meaning
Process costing is the method used in industriesin which raw materials passes through variousprocesses to be converted into finished goods.Example include chemical, flour and glassmanufacturing.
It computes the average cost per unit by dividingthe costs or production for a particular period bythe number of units produced during the period.
According to Weldon,Process costing is a method of costing used to ascertain the cost ofproduct at each process, operation or stage of manufacture.
7/30/2019 The IIS University
3/15
Characteristics
Homogeneous unitspass through aseries of similarprocesses.
Each unit in eachprocess receives asimilar dose ofmanufacturing
costs. Manufacturing costs
are accumulated fora process for a
given period of time.
7/30/2019 The IIS University
4/15
Direct material
Direct labour
Overheads
Direct material
Direct labour
Overheads
Direct material
Direct labourOverheads
Process 1
Process
2
Process 3
Finishedgoods
7/30/2019 The IIS University
5/15
7/30/2019 The IIS University
6/15
Elements of Process Costing
Direct material
Added at the beginning, during, and/or at
the end of process
Direct laborAdded throughout the process
Overhead
Added throughout the process Based on direct labor
Based on other, multiple cost drivers
7/30/2019 The IIS University
7/15
Accounting for Process
Costing Costs are accumulated by each process Each process maintains its process
account The process account is debited with the
costs incurred and credited with goodscompleted and transferred to otherprocess account
When the goods are completed, they will
be transferred to finished goods account When the goods are sold, the amount
will be transferred to the cost of goodssold account
7/30/2019 The IIS University
8/15
7/30/2019 The IIS University
9/159
Joyce Ltd. operates a factory involving two production
Processes. The output of process 1 is transferred to process
2. The information of production for January 2005 is as
follows:
Cost for Process 1
Materials: 3000 units at Rs 5 per unit
Labour Rs 2400
Cost for Process 2
Materials: 2000 unit at Rs 8 per unit
Labour Rs 1680
No opening and closing work in progress
Output for January 2005
Process 1: 2300 units
Process 2 4000 units
7/30/2019 The IIS University
10/1510
General overhead, for January 2005 amounted to Rs7140,
are absorbed into the process cost at a rate of 375% of
direct labour costs in process 1 and 496.4% of direct labour
cost in process 2.
The normal output of process 1 and process 2 is 80% and
90% of input respectively
Waste matters from process 1 and sold for Rs4 per unitand those from process 2 for Rs6 per unit
Prepare Process Accounts for
(a) Process 1
(b) Process 2
(c) Abnormal loss
(d) Abnormal gain
7/30/2019 The IIS University
11/1511
Process 1 account
Units Rs Units Rs
Labour 2400
Materials 3000 15000
(Rs5 *3000)
Overhead 9000
(2400*375%)
Process 2
(Rs10*2300) 2300 23000
Abnormal loss
(Rs10 *100) 100 1000
3000 26400 3000 26400
Scrap: normal loss
(4*600) 600 2400
Cost per unit
= Normal cost
Normal output
= Rs26400-Rs2400
3000-600
= Rs10 per unit
7/30/2019 The IIS University
12/1512
Process 2 account
Units Rs Units Rs
Labour 1680
Materials 2000 16000
Overhead 8340
(1680*469.4%)
Finished goods
(Rs12*4000) 4000 48000
Abnormal gain
(Rs 12 *130) 130 1560
4300 49020
Scrap: normal loss
(Rs 6*430) 430 2580
Cost per unit
= = Rs 49020- Rs 2580
4300-430
= Rs 12 per unit
Process 1 2300 23000
4430 50580 4430
7/30/2019 The IIS University
13/1513
Abnormal loss account
Units Rs Units Rs
Process 1 100 1000 Scrap 100 400
Profit and loss 600
100 1000 100 1000
Abnormal Gain account
Units Rs Units Rs
Process 2 130 1560Scrap: value of
abnormal gain 130 780
Profit and loss 780
130 1560 130 1560
Loss on scrap value due to abnormal gain
7/30/2019 The IIS University
14/15
Interpretation
In Process 1, the cost per unit incurred is Rs 10per unit. Out of 3000 units that were input , only2300 units were transferred to Process 2 . The
rest 600 were normal wastage and 100 wereabnormal.
In Process 2, the cost per unit incurred is Rs 12and there is a gain of 130 units in the process.
After both the processes it was inferred thatabnormal gain was Rs 1560 (130 x 12) and thetotal abnormal loss was of Rs.1000.
It is shown that Rs 600 were credited into P&La/c and Rs 780 were debited in the same.
7/30/2019 The IIS University
15/15
Thank you!!!!!!