The implementation of a performance management system
Robert Jan Feijen - SPC director - Coentunnel Company
Session II - 12 October,2015
Content
• Coentunnel: DBFM Project
• What is a Performance Management Sytem?
• How does it work?
• Added value solution
2/
Coentunnel: DBFM Project • 2008-2014
– Design & Build Coentunnel system
– Maintenance during construction phase
• 2014-2037
– Operate Coentunnel system for 24 years
3
Coentunnel: DBFM Project (2)
• Coentunnel is an Availability Payment DBFM contract
• Activities o Renovation of the first Coentunnel
o Construction of the second Coentunnel and the connections to the A8 and A10 motorways
o Reconstruction of the Coenplein motorway junction
o Construction and renovation of 36 fly-overs and bridges
4/
What is Performance Management System?
• Performance Measurement System (PMS) calculates the net availability payment per quarter
• Within DBFM contracts, evidence for performance provided by contractor (concessionaire)
• Represent the state of physical assets outside, in an automated software system that calculates Availability Correction
• The Electronic Data Processing (EDP)-certified system is web-based and therefore 24/7 accessible (also for the government)
5/
Example of failure mechanism
6/
Failure Definition 01-a:
Requirement 01-a fails when Two consecutive Matrixboards fail.
OK
Requirement 01-a:
Matrixboards need to guide road users
as desired by Traffic Management
Office
NOK FD 01A NOK
Failure Definition 01-a:
Requirement 01-a fails when Three
consecutive Matrixboards fail.
PMS behind the scenes
7/
Storage Unit
Data transformation Storage
Validation Authentication Interventions Library Editor
Manual input Unit Inspections & findings
(Relatics)
Interface TTTI Status messages and
measurement (OPC server)
Business logics
calculation
Invoice Invoice
Invoice
Processing Unit
PMS behind the scenes (manual input)
8/
Inspection registration manual input
(example with real data)
Information from
maintenance and inspection
plan
Is inspection a follow-up on
a failure notification?
Timestamp and result of
inspection: NOK
PMS behind the scenes (automated input)
9/
Automated failure message from TTI stored in database
Add relationship
PMS CCY – 2.2
PMS behind the scenes (filter & registration)
10/
• Sending relevant date to processing unit
• Processing Unit: determines financial consequences of data, given the contractual requirements
Lane Starting time Ending time Type ReasonDocument TTR Time budget Waiting time Incident
Special
circumstance
T11S03R1H 2014-07-18 14:36 2014-07-18 14:36 Virtual no no
BK23.1: Unintented functioning
VeVa0 360 no
2014-07-18
14:36:07.541 VeVa.Alarmlockabsent = 1no no
2014-07-18
14:36:08.505 VeVa.Alarmlockabsent = 0no no
Lane Starting time Ending time Type Reason Document TTR Time budget Waiting time Incident Special circumstance
PMS behind the scenes (Calculation)
11/
• Data is used to automatically calculate Periodic Availability Correction
• Manual adjustments possible (fully traceable)
Date From To Location AC BW Multiplier Weight Factor Norm Lane closure Headlane Exception
PMS behind the scenes (invoice)
12/
• Quarterly reliable, accountable invoice
Maximum Availability Payment (MAP) 10.000.000,-
Relative Value (1/S)
O&M Violation Adjustment
Bonus Percentage (BP%) %
Correction Percentage (CP%) %
Performance Correction (PC) - 2.000,-
Unavailability Correction (UC)
Net Availablity Payment (NAP) 9.998.000,-
Taxes (…%)
Total amount (incl. taxes)
Added value solution
• Continuous insight in performance
• No disputes with clients about the (non)performance
• Lower inspection cost (lower life cycle cost)
• First day of new quarter invoice, quick payment of quarterly invoices (for 24 years)
13/
Questions