The KM3NeT Preparatory Phase Project
Objectives
Current membership and funding
The Preparatory Phase project
KM3NeT Meeting, Pylos, April 16, 2007
Uli KatzUniv. Erlangen
KM3NeT meeting, Pylos, 16.04.07 U. Katz: The KM3NeT Prepratory Phase 2
KM3NeT Objectives
Observe high-energy cosmic neutrinos- Opens new window to the most violent processes in the universe- Key objective of astroparticle physics- Convergence towards two major neutrino telescopes covering the full sky:
Mediterranean Sea:
Lake Baikal:
KM3NeTANTARES
NEMONESTOR
Antarctica: AMANDA IceCube
Baikal experiment
?
Provide infrastructure for long-term deep-sea measurements- Highly interesting for marine biologists, geologists and geophysicists,
environmental scientists, oceanographers, ….- Strong links to the EMSO project.
KM3NeT meeting, Pylos, 16.04.07 U. Katz: The KM3NeT Prepratory Phase 3
3-year FP6 Design Study, Feb. 2006 – Jan. 2009, 9 M€ from EU, overall budget ~20 M€
Participants: 30 Particle/Astroparticle institutes + 7 Sea science/technology institutes
Main Deliverables- Conceptual Design Report (fall 2007)- Technical Design Report (early 2009)
The KM3NeT Design Study
} from 9 EU countries:
CYP
IT
FR GE GR IRL
NL ES UK
KM3NeT meeting, Pylos, 16.04.07 U. Katz: The KM3NeT Prepratory Phase 4
Technological/scientific:- ANTARES:
5 lines in operation, continuous data taking, first ’s Completion (12 lines) expected by January 2008
- NEMO: Prototype modules (junction box, 5-storey tower) deployed and connected, data taking ongoing
- NESTOR: DOE proposal with Berkeley
(GRBs with 4-floor tower + autonomous lines)
Strategic/political:- ESFRI:
KM3NeT included in ESFRI roadmap (Sept. 2006) ESFRI has initiated top-down political process (national prioritization, expressions of interest) Strong support for KM3NeT in several countries
Recent Progress
KM3NeT meeting, Pylos, 16.04.07 U. Katz: The KM3NeT Prepratory Phase 5
Pilot projects:- ANTARES (cap. investment only) 20.1 M€
• FR, GER, IT, NL, ES funding agencies 14.5 M€• France: Regional sources 1.9 M€• FEDER/France 3.7 M€
- NEMO ( IT, cap. investment only) 17.0 M€• IT funding agencies 10.9 M€• FEDER/Italy 6.1 M€
- NESTOR (GR, cap. investment only) 8.0 M€• Greek government 6.5 M€• FEDER/Peloponnese 1.5 M€
_______
45.1 M€
KM3NeT (cap. + pers.) ca. 11.0 Mۥ CY, FR, GER, GR, IRL, IT, NL, ES, UK
funding agencies and other sources • +9 M€ from EU
Current National/Regional Funding
KM3NeT meeting, Pylos, 16.04.07 U. Katz: The KM3NeT Prepratory Phase 6
ERDF funds may be a major source of KM3NeT construction money
- ERDF and FP7 run concurrently (2007-2013)
- KM3NeT candidate sites are target-1/target-2 regions
Political coordination needed
- Cross-coordination between ESFRI, EU DG Research (FP7), EU DG Regio (ERDF) and national authorities to promote research infrastructures
- Avoid conflicting boundary conditions in both programs
- Support for the concept of spending regional funds locally, but in the framework of pan-European projects
The situation must be clarified very soon!
Structural Funds (slide taken from ESFRI talk)
KM3NeT meeting, Pylos, 16.04.07 U. Katz: The KM3NeT Prepratory Phase 7
Top-down call, restricted to ESFRI projects
Objective: Pave the way to construction of ESFRI RIs
- Political and financial convergence
- Legal / governance structure
- Strategic preparation (centers of excellence, user needs, data dissemination etc.)
- Technical work (must not be the core of the proposal)
Financial framework:
- 135 M€ for 30-35 projects ~4 M€ / project on average
- A frame of 1-7 M€ is mentioned in the Guide for Applicants
Deadline: May 2, 2007, 17:00 Brussels time
The Preparatory Phase Instrument
KM3NeT meeting, Pylos, 16.04.07 U. Katz: The KM3NeT Prepratory Phase 8
Application in preparation(time very tight due to overlap with 1st-year Design Study report)
Current list of Work Packages:WPA Management of the PP projectWPB Political convergenceWPC Legal, governance, financial engineering and site issues WPD Strategic issues and international networkingWPE Marine and environmental agencies and networkingWPF Industrial production of telescope componentsWPG International partnerships for auxiliary vesselsWPH Industrial production of deep sea components and partnership for deep sea infrastructures WPI Telescope pre-production and production modelWPJ Data handling and dissemination
Cornerstone data:- Requested amount from EU: ca. 6.5 M€ (~40% technical)- 3-year project, ca. 1/2008-12/201
The KM3NeT Preparatory Phase (PP) Proposal
KM3NeT meeting, Pylos, 16.04.07 U. Katz: The KM3NeT Prepratory Phase 9
WPA: Management of the PP project- Contractual, reporting, communication work, meetings, etc.- Special situation: Cross-coordination with Design Study necessary,
use of common resources (web portal etc.)
WPB: Political convergence
- Involve stakeholders, initiate a forum for political and financial negotiations, provide input to negotiations
- Accompany and foster political negotiations on site(s), funding, legal and governance issues, etc.
- Objective: (draft) Memorandum of Understanding, set of commitments
WPC: Legal, governance, financial engineering and site issues
- Governance model, management structure and legal entity for construction and operation
- Assessment of funding sources and related legal constructs
- Site aspects related to these issues
The KM3NeT PP Work Packages (1)
KM3NeT meeting, Pylos, 16.04.07 U. Katz: The KM3NeT Prepratory Phase 10
WPD: Strategic issues and international networking- Questions related to science, distributed infrastructures, technological
issues, expandability
- Assess options of international partnerships WPE: Marine and environmental agencies and networks
- Integration with global systems, e.g. GOOS and ESONET/EMSO- Integration with local national systems, marine and environmental
agencies and networks- Use of marine/environmental data, environmental impact of installation- Operation/exploration of funding options (national FAs, ERDF, EIB, …)
and their interrelation WPF: Industrial production of telescope components
- Vertical cables, connectors, glass spheres, industrial resources,…- Goal: Be ready for tenders once the money is available
WPG: Industrial partnerships for auxiliary vessels - Buying, building, chartering and operation of ships and other surface
vessels
The KM3NeT PP Work Packages (2)
KM3NeT meeting, Pylos, 16.04.07 U. Katz: The KM3NeT Prepratory Phase 11
WPH: Industrial production of deep sea components and partnership for deep sea infrastructures- buying/chartering of ROVs/AUVs
- horizontal cables, JB, … WPI: Telescope pre-production and production model
- Project planning, production preparation, resource allocation,local infrastructures
- Preproduction and production model
- Prototyping, test stands
- QA/QC WPJ: Data handling and dissemination
- Rules and formats of data publication and data access, multi-messenger aspects
- User needs, scientific relations to APP community
- Granting of observation time, public outreach
- Computing and GRID, virtual control room
The KM3NeT PP Work Packages (4)
KM3NeT meeting, Pylos, 16.04.07 U. Katz: The KM3NeT Prepratory Phase 12
Budget allocation (preliminary)
WPA Management INFN 350 350WPB Political convergence FR/GR/IT 300 300WPC Legal, governance,
financial, site issues GR/FR 1200 1200
WPD Strategic issues international networking FR/GR 700 100 100 500
WPE Marine/environmental Aberdeen 500 200 300WPF Telescope components CEA 500 100 150 250WPG Auxiliary vessels GR 500 100 150 250WPH Deep-sea components INFN 500 100 150 250WPI Preproduction and
production FOM 1300 100 200 1000
WPJ Data Erlangen 700 100 100 500Sum 6550 350 1100 2350 2750
Budget (k€)total man. coor. supp. tech.Coord.
KM3NeT meeting, Pylos, 16.04.07 U. Katz: The KM3NeT Prepratory Phase 13
Status- WP structure, tasks, rough budget allocation (ok)
- Involvement of funding agencies / governmental authorities (ok)
- Distribution of responsibilities between partners (ok)
- Distribution of budget between partners (not really)
- Administrative part (started)
- Writing of proposal (well …) Prospects
- If we are successful extremely important milestone towards KM3NeT realisation we must do it! please be prepared to provide input (fast!)
- A start of construction in 2010/11 may be in reach.
- All depends on the successful completion of the Design Study.
Status & Outlook