The major causes of quality failures in the Malaysian building construction
industry
Hamzah Abdul-Rahmana, Samiaah M. Hassen Al-Tmeemy
b , Zakaria Harun
c, Mei Ye, Kho
d
a Research & Innovation, University of Malaya, 50603 Kuala Lumpur, Malaysia b Ministry of Higher Education -Technical Institute-Baquba-Iraq
c Faculty of Engineering, University of Malaya, 50603 Kuala Lumpur, Malaysia
d Faculty of Built Environment, University of Malaya, 50603 Kuala Lumpur, Malaysia
Abstract
The paper aims to investigate the causes of quality failures in the construction of buildings. A survey was
conducted to collect data from a random sample of building companies in Malaysia. Statistical analyses
based on Chi-Square and on Relative Importance Index techniques were used to determine the
significance of the findings and the relative importance of the failure causes. Among 15 causes of quality
failures, the most frequent causes are “insufficient skill levels”, “inadequate reviews of the design
and engineering drawings”, and “lack of site layout studies”. To overcome these failures, an
influence diagram is developed, which attributes quality failures to the lack of implementation of cost of
control activities. The outcome of this study clearly shows the importance of understanding the reasons of
quality failures to employ remedial actions that can prevent recurrence of errors. Furthermore, this study
provides managers with adequate justification to spend for cost of control activities and to launch various
quality improvement initiatives.
Keywords: Cost of quality, quality failure, building construction, cost of control, Relative Important
Index
1. Introduction
Successful companies must deliver projects on time and within budget; as well as meet
specifications while managing project risks (Raymond and Bergeron 2008). Achieving project
objectives and completing project within pre-defined time, cost and quality constraints is not an
2
easy task in the construction of buildings (Al-Tmeemy et al. 2011). During construction,
contractors are often required to re-work portions of the project due to unacceptable quality
(Kakitahi et al. 2011; Hwang et al. 2009). Quality is evident in the amount of re-work and in the
overall expenditures of a project (Garrett and Teizer 2009). Quality failure can occur during any
stage of the construction process (Ede 2011). These conditions have led studies and practitioners to
rethink models and frameworks that consider the cost of quality failure as not only a performance
measure in the manufacturing plant or for a specific process, but also for an entire supply chain (Castillo-
Villar et al. 2012a 2012b).
Regardless of time occurrence, the impact of quality failure can erase the projected benefits of
development programmes (Kakitahi et al. 2011; Ede 2011). However, many companies are not
aware of the cost that quality failure can incur, and the real harm it can cause, because these costs
are not properly assessed (Selles et al. 2008). Consequently, quality failures continue to occur
during construction process, while some are repeated in several projects (Selles et al. 2008; Love
et al. 2008; Mitropoulos and Nichita 2010). Therefore, understanding the underlying causes of
these failures and developing strategies to eliminate or to mitigate their occurrence are important
to increase the probability of achieving the project objectives.
The first step in reducing the occurrences of quality failure is to study its causes and to develop
subsequent effective prevention strategies (Love et al. 2008; Yates and Lockley 2002). For this
purpose, this paper provides a deeper understanding of the causes of quality failures in
construction projects in Malaysia. A literature review was conducted to identify the possible
causes of quality failures, which were then associated with the lack implementation of cost of
control (COC) activities. The findings of this research significantly contribute to the
understanding of the necessity of COC activities. This understanding particularly helps people
3
involved in the construction process to obtain a true picture of the impact of implementation of
COC activities and directs efforts to mitigate quality failures.
2. Relationship Between Quality Failure and Cost of Control Activities
Improving quality in the construction industry is necessary (Tam et al. 2008). This need for an
improved overall project quality drives the implementation of quality control programs (Love and
Edwards 2004). Effective quality management is a critical factor in the successful management
of construction projects (Achi et al. 2007). Prior literature reports that poor quality management
system connotes that uncoordinated information gathering, reporting, and project management,
thereby necessitating multiple processing of information (Love and Irani 2003). Ultimately,
wasted time; unnecessary costs; increased errors; reworking and non- conformity become
inevitable in the construction process (Love and Irani 2003; Abdul-Rahman 1995; Alwi et al.
2001; Smallwood and Rossouw 2008). Thus, investigating and gathering information onquality
costs are essential (Selles et al. 2008). Unnecessary costs due to failures can be eliminated with a
small investment in prevention and timely inspection (Kazaz et al. 2005). Controlling quality
costs can lead to the reduction in building cost and time for error or failure correction. Higher
savings can therefore be derived from reducing failure and minimizing defects. In other words,
cost of quality (COQ) represents a powerful tool that translates the implications of poor quality,
reflects activities of a quality program, and translates quality improvement efforts into a monetary
language for managers (Castillo-Villar et al. 2012a).
Quality costs are associated with two categories of quality-related activities, namely, control and
failure activities (Hansen and Mowen 2006). Control activities consist of prevention and
appraisal activities. Prevention activities are performed to avoid production of nonconforming
units (Morse and Poston 1987). Prevention activities eliminate the initial occurrence of defects by
4
assuring the meeting of the standards of organizational quality and customer satisfaction.
Prevention investments seek to realize this purpose by supporting activities, such as quality
program management; training and education; quality promotion; process capability studies;
failure mode and effect analysis; quality function deployment; designing of experiments;
designing for the manufacturing, market research; internal and external customer surveys; quality
planning; supplier certification programs; preventive maintenance; and the creation of cross-
functional design teams (Angel and Chandra 2001).
Appraisal activities determine the actual level of quality achieved, which is relative to the desired
levels of customer satisfaction and to organizational quality standards (Gilmore 1990). Appraisal
activities extract nonconforming units before reach the customer (Morse and Poston 1987). These
activities include inspection, testing and supplier surveillance internal audits and review of
completed work (Gray 1995). Appraisal activities are done after failures occur and not before.
Failure activities are performed because of poor quality existence (Juran and Gryna 1980; Juran
1951). Costs due to failure are either internal or external. Internal failure costs are incurred when
defective goods are identified while still in the factory and before they are shipped to customers
(Morse 1993). Examples of internal failure costs are associated with scraps, re-working, equipment
downtime, re-testing, and the time spent in identifying the appropriate corrective action. External
failure costs are incurred when nonconforming products are shipped to customers (Morse and
Poston 1987). These costs cover include attending to complaints adjustment; receipt and
replacement of defective product, warranty charges, and payments made to customers to
compensate for the inconvenience. (Angel and Chandra 2001).
The combination of prevention and appraisal costs composes COC (Hansen and Mowen 2006).
The Construction Industry Institute (CII) defines eight types of COC that cover COC activities
5
(Love and Irani 2003; Willis and Willis 1996). These activities include: quality systems; supplier
qualification; personnel qualification, testing and training; Expediting; constructability review;
operability, safety, and value review; examinations, internal; and examinations, external, as
shown in Table 1.
Table 1: Cost of Control Activities
Activities Description
Quality System Developing quality improvement programs, standards and goals,
data collection, analysis and reporting, indoctrination, and training
Personnel Qualification, Testing, and Training Testing personnel„s ability to perform work according to specified
standards, craft certification, and training for quality
assurance/control activities.
Supplier Qualification Evaluating the ability of suppliers, vendors, contractors, and
subcontractors to perform capably, as well as developing a
certification system and compiling rating scores to measure
supplier performance.
Expediting Activities prior to delivery to ensure on-schedule delivery of all
purchased materials, equipment, services, and third-party
engineering information.
Operability, Safety, and Value Review Determining if the design is in compliance with client, industry,
and government requirements in terms of operability, safety, value
engineering, safety analysis, process hazards, operability reviews,
value engineering studies, and so on.
Constructability Review
Activities to ensure that the most efficient design and planned
construction methods are used to maximize the chance of building
perfect facilities, construction site layout studies, de-watering
studies, prefabrication studies, and so on.
Examinations, Internal Reviewing, checking, inspecting, testing and observing
services/product internally in the organization; reviewing designs,
drafting and documentation, soil testing, concrete testing, hydro-
testing piping, and so on.
Examinations, External Reviewing, checking, inspecting, testing and observing
products/services produced externally by others; inspection of
material/equipment received, vendor document reviews, and so on.
3. Causes of Quality Failures
Previous literature on construction management mentions various terms for quality failure. These
terms include re-work (Love and Edwards 2004; Love et al. 2004), nonconform (Abdul-Rahman
1995), defects (Josephson and Hammarlund 1999; Sommerville 2007), quality lapses
6
(Sommerville 2007), snags (Sommerville and McCosh 2006); quality failures (Barber et al.
2000), quality indices (Apostolopoulos and Pasialis 2008), and failure incidents (Barber et al.
2000) that are often usedbut have a tendency to vary. Regardless of the term used, quality
failures lead to re-working and additional time for the correction process. Otherwise, the quality
of the project is affected (Mitropoulos and Nichita 2010; Imbeah and Guikema 2009).
Several researchers have investigated the causes of quality failures. Feld and Carper (1997)
claimed that either technical or procedural causes trigger failures. Feld and Carper (1997)
classified the causes of failure into seven categories, which are: fundamental concept; site
selection and development; programming; design; construction; materials; and operation.
Similarly, Imbeah and Guikema (2009) referred to failures as results of technical and managerial
inadequacies..
A survey carried out by Yates and Lockley (2002) exposed 29 causes of construction failures.
These causes are summarized as follows: unqualified labour, poor review of on drawings,
financial pressures, inadequate inspection methods, improper safety and value review, poor
constructability review, poor reviewing, checking, inspecting, testing and observation,
ineffective communication, and poor decision making.
Love and Edwards (2004) identified a number of factors impede the construction quality of
buildings, which leads to reworking, as lack of understanding of end-user requirements, poor
contract documentation and low consultant fees, incompetent standard of workmanship, lack of
focus on quality and inadequate supervision and inspection. Josephson and Hammarlund (1999)
attributed these factors to knowledge, information, motivation, stress, and risk. Willis and Willis
(1996) observed that the causes of major deviations are designer error, vendor error, and change
of designer.
7
The above literature clearly reveals that most causes can be attributed to the poor implemention
of COC activities (Table 1) . Several researchers claimed that the implementation of COC
activities, such as design reviews; inspection; and training is the first step to minimize the
potential impact of quality failures (Love et al. 2008; Yates and Lockley 2002; Love and Li
2000). In addition, the proper implementation of a quality management system assures the
logical and progressive sequence of work, which prevents or mitigats delays during construction
(Abdul-Rahman et al. 2006).
4. Methodology
To investigate the perception of the contractors and managers about the causes of quality
failures, a cross sectional survey was conducted to collect data from a random sample of building
companies in Kuala Lumpur. The targeted respondents for this study were drawn from the
Construction Industry Development Board Malaysia (CIDB) (2008) registered list of contractors
categorized under Class G6 (tendering capacity of 10 million Ringgit Malaysia) and Class G7
(tendering capacity of more than 10 million Ringgit Malaysia). Kuala Lumpur was chosen as the
sampling city since it comprises the largest number of registered Class G7 and G6 contractors.
To choose the sample for this research, the stratified sampling method was used to divide the
sampling frame into two groups; G6 and G7 contractors. This method yields precise estimation
more than those produced by simple random sampling; particularly, when the sampling frame is
available in the form of a list (Kothari 2004). Furthermore it is simple and convenient (Pedhazur
and Schmelkin 1991).
According to CIDB (2008) statistics, there were 1329 active contractors of grade G6 and G7 in
Kuala Lumpur. Of this total, 1196 contractors are involved in building construction, which
represented the population of this study. This population comprises 193 (16%) contractors of G6,
8
and 1003 (84%) contractors of G7.
Table 2: Sampling Frame
The sample size was 594 contractors of grade G6 and G7 operating in Kuala Lumpur. The
sampling frame was structured in such a way that it represents the population and included all
companies that have a chance to be selected. As shown in Table 2. The sample was selected
according to the proportion of each group in the population (Adams and Brace 2006; Czaja and
Blair 2005). Therefore, the sample contained 95 contractors G6 and 499 contractors G7, as
shown in Table 2.
The collected data was analyzed using the Relative Importance Index (RII), which is successfully
used in the previous researches (Alwi and Hampson 2003; Assaf and Al-Hejji 2006; Chan and
Kumaraswamy 1997; Kometa et al. 1994). The relative importance index (RII) and Chi-Squared
test (X2) were computed using the following equations:
(1)
∑
(2)
Grade Population Percentage Sample size Interval
G6 193 16% 95 2
G7 1003 84% 499 2
Total 1196 1005 594
9
RII was used to determine the relative importance of the factors, where ai= constant expressing
the weight of the ith
response, xi = level of the response given as a percentage of the total
responses for each factor, A = highest weight, N = total number of respondents. In order to
examine the significance of the findings, the equation 4 was used, where Oi = an observed
frequency, Ei = an expected (theoretical) frequency, asserted by the null hypothesis, i = response
category index, n = number of response category index.
5. Questionnaire Development
A survey is conducted to obtain maximum information at minimal cost (Ader et al. 2008). The
questionnaire has a range of structured questions and can be self-administered. Moreover, the
questionnaire can be sent to a large number of respondents at a relatively lower cost. However,
the success of the survey depends on the cooperation of the respondents (Adams and Brace
2006). To achieve a high success rate of the survey, prior meetings were held with a group of
experts to evaluate and to enhance the quality of the survey items and contents of the survey.
According to Ader et al. (2008), four to five experts can adequately assess the survey items. The
questionnaire in the present study was vetted by experts, who consisted of two academicians and
three project managers with more than 20 years of working experience in the building
construction industry.
The initial copy v of the questionnaire was used in a pilot study prior to the main conduct of the
survey. This pilot study is important in evaluating the questionnaire in terms of its clarity and its
comprehensibility as well as its suitability for the chosen sector. According to Ader et al. (2008),
a pilot survey provides feedback on errors, identifies problems that may arise, and measures the,
willingness of the respondents to participate in the survey. In addition, a pilot questionnaire is a
commonly used and successful approach in situations when the subject of the survey is not
10
widely known (Wong and Aspinwall 2005). Twenty (20) construction companies that are listed
under Classes G6 and G7 of the CIDB database were selected for this purpose. The results of the
pilot survey provided information that enhanced the final version of the questionnaire; hence some
questions were revised or rephrased based on the feedback. Specific issues that were raised prompted
some changes to the sentence structure and word usage for more clarity on the intended purpose of
the questions being asked.
The questionnaire was divided into two parts. The first part was to gather general respondent's
demographics characteristics (e.g. educational level, age, experience, and occupation) of the
participating companies. The second part was to investigate the benefits and barriers of adopting
quality cost system to measure and track quality costs data.
6. Research Findings and Discussion
6.1 Response Rate
Of the 594 questionnaires dispatched to the selected sample, 153 were satisfactorily completed,
making the total response rate 25.7%, which is acceptable according to Akintoye (2000) and
Dulaimi et al. (2003). Both, Akintoye (2000) and Dulaimi et al. (2003), have stated that the
normal response rate in the construction industry for postal questionnaires is within the range of
20–30%.
6.2 General Respondents’ Demographics Characteristics
Frequency distribution is conducted to show four main profiles namely: educational level, age,
occupation, and period of experience as shown in Table 3. The General Respondents‟
Demographics (GRD) revealed that the majority of the respondents (90.2%) were holding a
Bachelor's degree as shown in Table 3. The highest frequency of respondents (40.5%) was
11
registered by the age group between (40 – 49) years, whereas the least percentage (6.5%)
corresponded to the age group between (50- 60+) years. Where respondents are divided
according to occupation, managers form the largest number of respondents (55.6%). And of
which 96.1% had more than (10) years experience. However, the majority of the total
respondents (39.2%) fell into the group having working experience between 20-24 years.
Table 3: Descriptive Statistics of some General Respondent Demographic (GRD)
GRD Groups Frequency Percent Cumulative
Percent
Diploma 0 0 0
Educational
Bachelor 138 90.2 90.2
Master 13 8.5 98.7
PhD 2 1.3 100
Age
20-29 yrs 12 7.8 7.8
30-39 yrs 59 38.6 46.4
40-49 yrs 62 40.5 86.9
50-59 yrs 10 6.5 93.5
60 + yrs 10 6.5 100
Occupation
Quantity Survey 5 3.3 3.3
Project(construction) Engineer 5 3.3 6.5
Quality Assurance/Quality
Control 7 4.6 11.1
Resident/ site Engineer 41 26.8 37.9
Manager 85 55.6 93.5
Director 10 6.5 100
Experience
5 - 9 yrs 6 3.9 3.9
10 - 14 yrs 37 24.2 28.1
15 - 19 yrs 25 16.3 44.4
20 - 24 yrs 60 39.2 83.7
25 + yrs 25 16.3 100
6.3 The Causes of the Quality Failures
The respondents were asked to provide their opinions toward the listed causes on a 5-point Likert
scale where 1 = never, 2 = rarely, 3 = sometimes, 4= often, 5= always. Table 4 shows that the
most frequent causes of quality failure was “Insufficient skill levels” with RII=0.79.
12
The respondents declared that the most frequent cause of quality failure is “insufficient skill
levels” with RII=0.79. This result indicates that the Malaysian construction industry often faces the
problem of inadequate skill levels among its workers. . The lack of labor skills can be attributed to
two possible reasons. First, contractors mostly consider ethical practices rather than education and
training. Ethical practices are not easy to perform, while the development of skills in the construction
sector takes a long time. Construction work encompasses a diverse range of specialized skills to perform a
number of functions, which leads to the difficulty. Second, contractors do not fully understand the
implications of a shortage of skilled labor to the ability of the company to compete in the global market.
Table 4: The causes of the quality failures
Questions Choices Frequency Percent Cumulative
Percent
RII P-value
Poor quality improvements
programs
never 0 0 0 χ
2 =107.0
P=0.000
rarely 4 2.6 2.6 sometimes 84 54.9 57.5 0.70
often 52 34 91.5
Always 13 8.5 100
Poor document control
never 1 0.7 0.7 χ
2 =268.4
P=0.000
rarely 23 15 15.7 sometimes 110 71.9 87.6 0.60
often 16 10.5 98 Always 3 2 100
Lack of training
never 1 0.7 0.7 χ
2=139.1
P=0.000
rarely 12 7.8 8.5 sometimes 63 41.2 49.7 0.69
often 69 54.1 94.8 Always 8 5.2 100
Poor selection of suppliers,
vendors and sub-contractors
never 0 0 0 χ
2 =42.6
P=0.000
rarely 13 8.5 8.5 sometimes 72 47.1 55.6 0.67
often 68 44.4 100 Always 0 0 -
Insufficient skill levels
never 0 0 0 χ
2 =128.7
P=0.000
rarely 0 0 0
sometimes 22 14.4 14.4 0.79
often 117 76.5 90.8 Always 14 9.2 100
never 28 18.3 18.3 Delayed purchased material rarely 65 42.5 60.8 χ
2 =79.8
sometimes 44 28.8 89.5 0.47 P=0.000 often 13 8.5 98
Always 3 2 100
13
Table 4: The causes of the quality failures (contd.)
never 0 0 0 Unclear or incomplete rarely 39 25.5 25.5 χ
2 =10.9
construction drawings and sometimes 70 45.8 71.2 0.61 P=0.004
specifications often 44 28.8 100
Always 0 0 -
never 0 0 0 rarely 0 0 0 χ
2 =21.2
Lack of site layout studies sometimes 48 31.4 31.4 0.74 P=0.000
often 105 68.6 100
Always 0 0 0
never 0 0 0
rarely 5 3.3 3.3 χ
2 =174.3
P=0.000
Constructability problems sometimes 105 68.6 71.9 0.66 P=0.000
often 38 24.8 96.7
Always 5 3.3 100
never 37 24.2 24.2 Poor safety program rarely 74 48.4 72.5 χ
2 =55.3
sometimes 32 20.9 93.5 0.42 P=0.000
often 10 6.5 100 Always 0 0 100
never 1 0.7 0.7 Inadequate operability rarely 20 13.1 13.7 χ
2 =119.0
review and value sometimes 57 37.3 51.0 0.68 P=0.000
engineering studies often 68 44.4 95.4 Always 7 4.6 100
never 0 0 0 Improper soil analysis
andparations
rarely 52 34 34 χ2 =43.7
sometimes 63 41.2 75.2 0.60 P=0.000
often 27 17.6 92.8 Always 11 7.2 100
never 0 0 0 Inadequate reviews of the rarely 0 0 0 χ
2 =39.6
design and sometimes 59 38.6 38.6 0.74 P=0.000
engineering drawings often 78 51 89.5 Always 16 10.5 100
never 4 2.6 2.6 Poor checking, rarely 22 14.4 17.0 χ
2 =182.2
inspecting and sometimes 96 62.7 79.7 0.65 P=0.000
testing internally often 21 13.7 93.5 Always 10 6.5 100
never 72 47.1 47.1 Poor checking, rarely 68 44.4 91.5 χ
2 =42.6
inspecting and sometimes 13 8.5 100 0.39 P=0.000 testing externally often 0 0 100
Always 0 0 100
The second identified cause of quality problems is “inadequate reviews of the design and
engineering drawings” with RII of 0.74. The review of design is an important step in the lifecycle
of a project because it evaluates the adequacy of design requirements to identify problems. The
14
problems discovered during construction are usually more costly to correct and more likely to cause
delay. However, several contractors conduct inadequate reviews because they either feel they already
know enough to prohibit any design review or because of limited time. Moreover, the client rarely
requires the contractor to provide a comprehensive design review.
Surprisingly, the “lack of site layout studies” ranks third with RII of 0.74. Previous studies
mentioned that site layout studies focused on space management and on the manner in which
construction plans are formed, safety is ensured, and resources are utilized (Hendrickson 2000;
Ning et al. 2011; Osman et al. 2003; Tam et al. 2002). These studies acknowledged the role of
construction site planning in improving both efficiency and safety during the construction
process. Hence site layout planning has a higher impact on quality than other reasons, such as
improvement programs; training; selection of suppliers; and so on. This result indicates the
importance of site layout management in the large building projects, which are crowded and chaotic job
sites.
Table 4 shows the ranking of the other identified causes from fourth to fifteenth based on their RII.
The rankings are: poor quality improvement programs (RII = 0.70); lack of training (RII= 0.69);
inadequate operability review and value engineering studies (RII= 0.68); poor selection of
suppliers, vendors and sub-contractors (RII= 0.67); constructability problems (RII= 0.66); poor
checking, inspecting, and testing internally (RII=0.65); unclear or incompleteness construction
drawings and specifications (RII= 0.61); improper soil analysis (RII= 0.60); poor document
control (RII= 0.60); delayed purchased (RII= 0.47); poor safety program (RII= 0.42); and poor
checking, inspecting and testing externally (RII= 0.39). The result shows a strong correlation
value at 0.01 level of significance. This finding suggests that the sample is truly random and the
population had no observed differences.
15
The above causes of quality failures can be attributed to the lack of implementation of COC
activities. The implementation of eight activities of COC, as shown in Figure 1, can ultimately, reduce
or prevent quality failures. For example, to deal with the problem of insufficient skills, the
contractor should test the ability of the personnel to perform work according to specified standards,
ensure personnel qualifications, and conduct trainings for quality assurance/control activities. Almost all
instances of nonconformity can be avoided either by timely inspections or by the use of more experienced
and skilled employees (Abdul-Rahman et al., 1996).
To overcome the problem of “inadequate reviews of the design and engineering drawings”, a
design review must be planned and performed during the early stages of a project. The early review
can determine if the design complies with the client requests, industry standards, and government
requirements in terms of operability, safety, value engineering, process hazards, and so on. These
activities provide managers with visibility to empower effectively employees. In addition, managers
can immediately recognize existing or emerging problems, make corrections, and adjust resource
allocations. Besides, these activities can prevent or reduce other quality failures such as poor safety
program, inadequate operability, and improper site analysis, as shown in Figure 1.
The constructability review copes with the problems of “lack of site layout studies”, “unclear or
incomplete construction drawings and specifications”, and “constructability problems”. The
constructability review comprises all activities that necessary to ensure the efficiency of the design and
the accuracy of studies on construction site layout, dewatering studies, pre-fabrication, and so on.
16
Figure 1: The causes of quality failure and cost of control activities
7. Conclusion
The present study aimed at identifying the possible causes of quality failures experienced by
managers and contractors of building projects in Malaysia. Results show that the most frequent
17
cause of quality failures is “insufficient skill levels”. Additional evidence from this study
suggests that the conduct of training programs improves knowledge and skills of employees.
Quality assurance/control activities, such as training programs, can mitigate the skill shortages
among the existing workforce and ultimately reduce quality failures. Therefore, the management of
quality costs and implementation of COC activities can prevent or eliminate all quality failures.
Findings indicate that failure costs and the causes of failures should essentially be monitored. The
level of awareness and sensitivity on the importance of COQ among managers and those involved in
the construction process should be increased. As a result, managers potentially become more confident
in implementing COC activities to minimize quality failures.
The limitation of this research is that the sample consisted only of Classes G6 and G7 contractors
in Kuala Lumpur.Therefore, the results obtained may not be representative of the Malaysian
construction population or of the situation worldwide. However, the findings from this study can
be considered as acceptable indicators and a fair representation of the situation in the Malaysian
construction industry.
For further studies, the sequences of quality failures may be examined more deeply based on time
and cost overrun. This investigation will raise awareness regarding the significance of quality
costs and equip managers with knowledge and confidence on where to best utilize their resources.
8. References
Abdul-Rahman H. (1995). The cost of non-conformance during a highway project: A case
study. Construction Management and Economics, 13(1):23-32.
Abdul-Rahman H., Berawi M. A., Berawi A. R., Mohamed O., Othman M., Yahya I. A.
(2006). Delay Mitigation in the Malaysian Construction Industry. Journal of
Construction Engineering and Management, 132(2):125-133.
Abdul-Rahman H., Thompson P. A., Whyte I. L. (1996). Capturing the cost of non-
conformance on construction sites: An application of the quality cost matrix.
International Journal of Quality & Reliability Management, 13(1):48-60.
18
Achi F. O., Onukwube H. N., Oluwaseyi M A. (2007). An assessment of quality management
of building projects in Nigeria. The construction and building research conference of
the Royal Institution of Chartered Surveyors, Atlanta USA.
Adams K., Brace I. (2006). An introduction to market & social research: planning & using
research tools & techniques Kogan Page Ltd, London, United Kingdom edition.
Ader H. J., Mellenbergh G. J., Hand D. J. (2008). Advising on research methods: A
consultant's companion, Johannes van Kessel Publishing, Huizen, The Netherlands.
Akintoye A. (2000). Analysis of factors influencing project cost estimating practice.
Construction Management and Economics, 18(1):77-89.
Al-Tmeemy S. M. H. M., Abdul-Rahman H., Harun Z. (2011). Future criteria for success of
building projects in Malaysia. International Journal of Project Management,
29(3):337-348.
Alwi S., Hampson K. (2003). Identifying the important causes of delays in building
construction projects. The 9th East Asia-Pacific Conference on Structural Engineering
and Construction Bali, Indonesia.
Alwi S., Keith H., Sherif M. (2001). Effect of quality supervision on rework in the
Indonesian context. Asia Pacific Building and Construction Management Journal,
6(1):2-6.
Angel L. C., Chandra M. J. (2001). Performance implications of investments in continuous
quality improvement International Journal of Operations & Production Management,
21(1/2):108-125.
Apostolopoulos C. A., Pasialis V. P. (2008). Use of quality indices in comparison of
corroded technical steel bars B500c and S500s on their mechanical performance basis.
Construction and Building Materials, 22(12):2325–2334.
Assaf S. A., Al-Hejji S. (2006). Causes of delay in large construction projects. International
Journal of Project Management, 24(4):349-357.
Barber P., Graves A., Hall M., Sheath D., Tomkins C. (2000). Quality failure costs in civil
engineering projects. International Journal of Quality and Reliability Management,
17(4/5):479-492.
Chan D. W., Kumaraswamy M. M. (1997). A comparative study of causes of time overruns
in Hong Kong construction projects. International Journal of Project Management,
15(1):55-63.
CIDB (2008). Construction Statistics. Construction Industry Development Board Malaysia.
Czaja R., Blair J. (2005). Designing surveys: a guide to decisions and procedures, Sage
Publications, Inc. , United States of America, Second edition.
Dulaimi M. F., Ling. F. Y. Y., Bajracharya A. (2003). Organisational motivation and inter-
organisational interaction in construction innovation in Singapore. Construction
Management and Economics, 21(3):307-318.
Ede A. N. (2011). Measures to reduce the high incidence of structural failures in Nigeria.
Journal of Sustainable Development in Africa, 13(1): 153-161.
Feigenbaum A. V. (1956). Total quality control. Harvard Business Review, 34(6):93-101.
Feld J., Carper K. L. (1997). Construction failure Johan Wiley & Sons, Inc., New York, 2nd
edition.
Garrett J. W., Teizer J. (2009). Human factors analysis classification system relating to
human error awareness taxonomy in construction safety. Journal of Construction
Engineering and Management, 135(8):754-763.
19
Gilmore H. L. (1990). Continuous incremental improvement: an operations strategy for
higher quality, lower costs, and global competitiveness. SAM Advanced Management
Journal, 55(1):21-25.
Gray J. (1995). Quality costs: a report card on business. Quality Progress, 28(4):51-54.
Hansen D. R., Mowen M. M. (2006). Cost management: accounting and control Thomson,
South-Western, United State of America, Fifth edition.
Hendrickson C. (2000) Project management for construction. In. Prentice Hall, Pittsburgh, pp
Hiyassat M. A. S. (2000). Applying the ISO standards to a construction company: a case
study. International Journal of Project Management, 18(4):275-280.
Hwang B.-G., Thomas S. R., Haas C. T., Caldas C. H. (2009). Measuring the impact of
rework on construction cost performance. Journal of Construction Engineering and
Management, 135(3):187-198.
Imbeah W., Guikema S. (2009). Managing construction projects using the advanced
programmatic risk analysis and management model. Journal of Construction
Engineering and Management, 135(8):772-781.
Josephson P.-E., Hammarlund Y. (1999). The causes and costs of defects in construction: a
study of seven building projects. Automation in Construction, 8(6): 681-687.
Juran J. M. (1951). Quality Control Handbook, McGraw-Hill, New York, 3rd edition.
Juran J., Gryna F. (1980). Quality planning and analysis, McGraw-Hill, New York.
Kakitahi J. M., Landin A., Alinaitwe H. (2011). An analysis of rework in the context of
whole life costing in uganda‟s public building construction: A review of literature. 1st
Annual Advances in Geomatics Research Conference, AGRC2011, 32-43, Kampala,
Uganda.
Kazaz A., Birgonulb M. T., Ulubeylia S. (2005). Cost-based analysis of quality in developing
countries: a case study of building projects Building and Environment 40(10):1356-
1365.
Kometa S. T., Olomolaiye P. O., Harris F. C. (1994). Attributes of UK construction clients
influencing project consultants' performance. Construction Management and
Economics, 12433-443.
Kothari C. R. (2004). Research Methodology: Methods And Techniques, New Age
International, New Delhi, India, Second edition.
Love E. D. P., Li H. (2000). Quantifying the causes and costs of rework in construction.
Construction Management and Economics, 18(4):479-490.
Love P. E. D., Edwards D. J., Irani Z. (2008). Forensic project management: an exploratory
examination of the causal behavior of design-induced rework. IEEE Transactions on
Engineering Management, 55(2): 234-247.
Love P. E. D., Irani Z. (2003). A project management quality cost information system for the
construction industry. Information and Management, 40(7):649-661.
Love P. E. D., Irani Z., Edwards D. J. (2004). A rework reduction model for construction
projects. IEEE Transactions on Engineering Management, 51(4):426-440.
Love P., Edwards D. (2004). Forensic project management: The underlying causes of rework
in construction projects Civil Engineering and Environmental Systems, 21(3):207-228.
Mitropoulos P., Nichita T. (2010). Critical concerns of production control system on projects
with labor constraints: lessons from a residential case study. Journal of Management in
Engineering, 26(3):153-159.
20
Morse W. J. (1993). A handle on quality costs. CMA-the Management Accounting
Magazine, 67(1):21-24
Morse W. J., Poston K. M. (1987). Accounting for quality costs in CIM. Journal of Cost
Management, (Fall):5-11.
Ning X., Lam K.-C., Lam M. C.-K. (2011). A decision-making system for construction site
layout planning. Automation in Construction, 20(5):459-473.
Osman H. M., Georgy M. E., Ibrahim M. E. (2003). A hybrid CAD-based construction site
layout planning system using genetic algorithms. Automation in Construction, 12749 –
764.
Pedhazur E. J., Schmelkin L. P. (1991). Measurement, design, and analysis: an integrated
approach, Lawrence Erlbaum Associates Inc., Hillside, NJ.
Raymond L., Bergeron F. (2008). Project management information systems: An empirical
study of their impact on project managers and project success. International Journal of
Project Management, 26(2):213-220.
Sanad H. M., Ammar M. A., Ibrahim3 M. E. (2008). Optimal construction site layout
considering safety and environmental aspects. Journal of Construction Engineering
and Management, 134(7):536-544.
Selles M. E. S., Rubio J. A. C., Mullor J. R. (2008). Development of a quantification
proposal for hidden quality costs: Applied to the construction sector. Journal of
Construction Engineering and Management, 134(10):749-757.
Smallwood J., Rossouw J.-H. (2008). The implementation of quality management systems in
South African construction. The construction and building research conference of the
Royal Institution of Chartered Surveyors (COBRA), Dublin, Ireland.
Sommerville J. (2007). Defects and rework in new build: an analysis of the phenomenon and
drivers. Structural Survey, 25(5):391-407.
Sommerville J., McCosh J. (2006). Defects in new homes: an analysisof data on 1,696 new
UK houses. Structural Survey, 24(1):6-21.
Tam C. M., Tong T. K. L., Leung A. W. T., Chiu G. W. C. (2002). Site layout planning using
Nonstructural Fuzzy Decision Support System. Journal of Construction Engineering
and Management, 128(3):220–231.
Tam V. W. Y., Le K. N., Le H. N. (2008). Using Gaussian and Hyperbolic distributions for
quality improvement in construction: case study approach. Journal of Construction
Engineering and Management, 134(7):555-561.
Willis T. H., Willis W. D. (1996). A quality performance management system for industrial
construction engineering projects. International Journal of Quality and Reliability
Management, 13(9):38-48.
Wong K. Y., Aspinwall E. M. (2005). An empirical study of the important factors for
knowledge management adoption in the SME sector. Journal of Knowledge
Management, 9(3):64-82.
Yates J. K., Lockley E. E. (2002). Documenting and analyzing construction failures. Journal
of Construction Engineering and Management, 128(1):8-17.