12
Index Largest demineralised water plant De Vries & van de Wiel Pilot plant for the SOURCE project Condensate Polishing project On-site container treatment units NieuWater ultrapure water project GEA Westfalia to Sri Lanka RO system in a 20ft container Disc filter for the Deventer Municipality Removal of medicine residues from sewer Final nanofiltration unit on Vlieland Ball Packaging groundwater treatment Logisticon expands again 1 2 3 4 5 6 7 8 8 9 10 11 12 THE NETHERLANDS’ LARGEST DEMINERALISED WATER PLANT BUILT IN RECORD TIME Evides Industry Water has had the Netherlands’ largest demineralised water plant (DWP) built in the port of Rotterdam. It has a capacity of 1,400 m 3 /h. Whereas it would normally take 2.5 years to build a plant like DWP, this one was designed, built and commissioned within the record time of 14 months. As a result of the unique cooperation between the contracting parties on the construction team level, the water purification plant, as planned in the first phase, was started up well before the deadline. Logisticon Water Treatment and its sister company Elmon Elektro- techniek were responsible for the mechanical and electro technical installation for the DWP plant. Instructions have now also been given for the second phase of the project. Realisation in 2 phases In 2008, Evides Industry Water started with the design of a 1,400 m 3 /h demineralised water plant: the Botlek DWP. This plant will use water from the Brielse Meer (Lake Brielle), which will be desalinated using membrane filtration and ion exchange technology. Drinking water will be used as the back-up raw influent. The project was split into two phases because it had to be Process water Continued on page 2 Water regulates the temperature of the earth. About water

THE NETHERLANDS’ LARGEST DEMINERALISED WATER PLANT … · 2018. 2. 2. · The execution was based on a planning analysis, ... also, and especially, the connection between the process

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

  • IndexLargest demineralised water plant

    De Vries & van de Wiel

    Pilot plant for the SOURCE project

    Condensate Polishing project

    On-site container treatment units

    NieuWater ultrapure water project

    GEA Westfalia to Sri Lanka

    RO system in a 20ft container

    Disc fi lter for the Deventer Municipality

    Removal of medicine residues from sewer

    Final nanofi ltration unit on Vlieland

    Ball Packaging groundwater treatment

    Logisticon expands again

    1

    2

    3

    4

    5

    6

    7

    8

    8

    9

    10

    11

    12

    THE NETHERLANDS’ LARGEST DEMINERALISED WATER PLANT BUILT IN RECORD TIMEEvides Industry Water has had the Netherlands’

    largest demineralised water plant (DWP) built

    in the port of Rotterdam. It has a capacity of

    1,400 m3/h. Whereas it would normally take

    2.5 years to build a plant like DWP, this one was

    designed, built and commissioned within the

    record time of 14 months. As a result of the unique

    cooperation between the contracting parties on

    the construction team level, the water purifi cation

    plant, as planned in the fi rst phase, was started

    up well before the deadline. Lo gisticon Water

    Treatment and its sister company Elmon Elektro-

    techniek were responsible for the mechanical

    and electro technical installation for the DWP

    plant. Instructions have now also been given for

    the second phase of the project.

    Realisation in 2 phases

    In 2008, Evides Industry Water started with

    the design of a 1,400 m3/h demineralised water

    plant: the Botlek DWP.

    This plant will use water

    from the Brielse Meer

    (Lake Brielle), which will

    be desalinated using

    membrane fi ltration and

    ion exchange technology.

    Drinking water will be

    used as the back-up raw

    infl uent. The project was

    split into two phases

    because it had to be

    Process water

    Continued on page 2

    Water regulates the temperature of the earth.

    About water

  • Continued from page 1Continued from page 1

    completed within a very short time

    frame. The fi rst phase entailed the

    construction of a complete DWP plant.

    This is now producing demineralised

    water from drinking water. The second

    phase entails a unit for the pre treat-

    ment of surface water from the Brielse

    Meer which will go into operation in

    early 2010.

    The demineralised water from the DPW plant

    is distributed through the existing deminer-

    alised water net-

    work to a number

    of refi neries and

    about 15 chemical

    and petrochemical

    companies. Evides

    also supplies sof-

    tened water to

    Huntsman sepa-

    rately.

    Unique cooperation from design to delivery

    The execution was based on a planning analysis,

    the objective of which was to shorten the time

    frame taken by each process component as far

    as possible. The most important aspects are, of

    course, delivery, assembly and commissioning

    times, but also, and especially, the connection

    between the process components. An extensive

    3D design was made using as many “prefab”

    parts as possible in order to maximise control

    on the building site. This applied, for example, to

    the RO skids, but also to the polypropylene fi lter

    fronts Logisticon made in its own workshop.

    The speed of construction was only possible

    because of this unique cooperation.

    High quality demineralised water

    The demineralised water produced is of a high

    quality. The quality of water ex works (includ-

    ing 0.2 µS/cm and 30 ppb silica) is well within

    the specifi cations.

    Pump and control container for De Vries & van de WielOn the instructions of the Province of South Holland, De Vries & van de Wiel is currently decon-

    taminating two areas (Geitenwei and Schanspolder) located close to the Hollandse IJssel near

    Ouderkerk aan den IJssel in The Netherlands. The contaminated groundwater released during

    excavation must be cleaned up before it can be discharged.

    Because of the distance between the two sites, two separate water treatment plants

    had to be used. De Vries & van de Wiel has bought one of them and leases the other from

    Logisticon. Basically, they consist of 10-foot containers equipped with pumps, blowers, a

    control switch board for sand fi ltration with automatically operated valves for the fi ltration

    and backwashing of the sand fi lter. The capacity of the pumps is adjustable up to a maximum

    of 30 m³/h. The size of the sand fi lter ultimately determines the capacity of a plant. The big

    advantages of these versatile water treatment plants are that all the pumps and automatic

    valves are protected from the frost in the containers and that the capacity can easily be

    adjusted to suit any project.

    Environmental

    is distributed through the existing deminer-

  • Pump and control container for De Vries & van de Wiel

    Logisticon delivers and operates pilot plant for SOURCE projectThe Aa and Maas Water Board in The

    Netherlands initiated the develop-

    ment of a processing concept for

    reducing the emission of nitrogen,

    phosphate and medicines to the

    surface water. To this end, it cooper-

    ated with the Southern Agricultural

    and Market Gardening Organisation

    (ZLTO), the Foundation for Applied

    Water Research (STOWA) and the

    ministries of Agriculture, Nature and

    Food Quality (LNV), Housing, Spatial

    Planning and the Environment

    (VROM) and Transport, Public Works

    and Water Management (V&W). A

    project named ‘SOURCE’ was set up

    for this purpose: SimultaneOUs Reuse

    of nutrients and removal of human

    and veterinary pharmaCEuticals.

    A test plant is being tested in accord-

    ance with the SOURCE concept at

    the Land van Cuijk waste water treat-

    ment plant in Haps, The Netherlands

    for about a year. In this process,

    animal manure is pre-treated together

    with human urine (collected at a

    hospital). Subsequently, the phos-

    phate is fi xed and recovered in the

    form of granular struvite (Magnesium

    Ammonium Phosphate) using Akwa-

    dok’s NuReSys® nutrient recovery

    system and ammonia is removed

    with a low-energy biological system

    (Grontmij’s Demon®). Medi-

    cines and hormones are then

    removed from the water fl ow

    using an advanced treatment

    involving ozone and activated

    carbon fi ltration.

    In addition to producing

    a detailed design, Logisticon

    was instructed to build, lease

    and operate the plant. The job

    included detail engineering,

    building and providing technical

    support in the SOURCE project and

    executing it with an over-all measur-

    ing, data storage and management

    system with the possibility of control

    and monitoring at a distance. The

    study was given a festive launch on

    7 October 2010.

    (Grontmij’s Demon®). Medi-

    Was

    te w

    ater

  • Condensate polishing for Neste Oil at the E.on power stationThere has recently been an increase

    in the number of projects based on

    cooperation between companies

    in the Rotterdam harbour area. For

    instance the production and delivery

    of demineralised water by Evides

    Industry Water to various industries

    in the port of Rotterdam (DWP) and

    another is the Condensate Polishing

    Unit project (CTU). This last project

    entails the improvement of Neste

    Oil’s used return condensate by E.on

    for boiler feed water. The condensate

    must be stripped of oily contaminants

    primarily released during the produc-

    tion of Neste Oil’s palm oil. Other

    oils released in the processing of,

    for example, soybeans and stearine

    from palm oil must, however, also be

    taken into account.

    This plant, with a capacity of 65 m3/h

    (2x60%), will treat condensate with

    a temperature of 97 °C. The specifi -

    cations are, however, much higher,

    so that all the equipment has been

    designed to process condensate

    with a temperature of 125 °C under

    a pressure of 10 bar. The mechani-

    cal components of the plant must,

    moreover, be able to operate for

    8,760 h annually for a period of

    25 years. Operation of the plant

    may only be interrupted for planned

    stops. Two parallel activated carbon

    units have, therefore, been designed

    and built. The backwashing with

    demineralised water in these units

    is fully automatic. Logisticon also

    delivered and installed the pre-

    fi ltration, gas collectors, buffer tank

    with nitrogen blanket, fl ush tank

    and pumps, instrumentation and all

    the steel pipes and pressure pipes

    on the site. The electro technical

    installation was carried out by Elmon

    Electrotechniek, one of Logisticon’s

    sister companies. With

    this project, Logisticon

    has further expanded

    its fi eld with pressure

    driven, high tempera-

    ture water/condensate

    systems.

    and built. The backwashing with

    fi ltration, gas collectors, buffer tank

    with nitrogen blanket, fl ush tank

    and pumps, instrumentation and all

    Pro

    cess

    wat

    er

  • Env

    iron

    men

    tal

    Seen over a period of 100 years, a water molecule spends 98 years in the ocean, 20 months in the form of ice, approximately 2 weeks in lakes and rivers and less than a week in the atmosphere.

    About water

    Water treatment plant in 30-ftcontainer forOnsite NVOn the instructions of the Belgian

    company Onsite N.V., Logisticon

    has built a new groundwater treat-

    ment plant for a large in-situ soil

    remediation project which will be

    running the coming years. Because

    the treatment plant is located next

    to the client’s offi ce building, as

    many components as possible had

    to be built into an insulated container.

    The groundwater is treated by means

    of sand fi ltration (for iron removal),

    air-stripped using a plate aerator and

    polished by granulated active carbon

    fi ltration. The challenging aspect of

    this project was the high iron content

    (greater than 50 mg/l) in the ground-

    water. The capacity of the plant is

    15 m³/h and it is built into a 30-ft

    container. All the air from the plate

    aerator is cleaned with activated

    carbon. The air fi lters with activated

    carbon have been placed on top of

    the container because of the limited

    space and to facilitate the changing

    of fi lters.

  • Pro

    cess

    wat

    er Extensive chemical storage and dosing facilities for NieuWaterNieuWater B.V.’s ultra pure water

    project is unique in the water world.

    This is the fi rst time that effl uent

    (from the Emmen waste water treat-

    ment plant, The Netherlands) has

    been processed into ultra pure water

    (UPW). It is also the fi rst time so

    many complex process

    steps such as ultra

    fi ltration, biological

    active granular carbon

    fi ltration, double pass

    reverse osmosis and

    continuous de ionisation

    have all been used in

    such a project together. Because of

    the technology chosen, the use of

    chemicals is minimised. However,

    to ensure continuous supply, a com-

    prehensive chemical dosing plant

    has also been opted for. This can

    be used in the event that there is

    an un expected deterioration in the

    quality of the effl uent from the waste

    water treatment plant, if the biologi-

    cal active carbon fi ltration fails or in

    any other contingency. The point is

    that this plant will only be needed to

    bridge short periods, should problems

    arise. The continuity in supplies of

    ultra pure water to the NAM for oil

    extraction in Schoonebeek is of great

    economic importance. Logisticon

    has never before designed and built

    dosing devices for 9 different chemi-

    cals in one single project. In high

    tech water treatment of this kind,

    it is very important to monitor any

    possible contaminant strictly. The

    chemical dosing devices are housed

    in a separate building and the central

    storage and dosing devices are

    located in a separate acid and caustic

    department. As a result, a total of

    around 3 km of dosing piping had to

    be constructed.

    Double-walled piping has been

    used for safety and environmen-

    tal reasons. Particular attention has

    been paid to the couplings between

    the reinforced hoses and equipment.

    Comprehensive pressure testing

    has, of course, been carried out and

    a leak detection system has been

    installed to guarantee safety.

    This size of this plant (the largest

    storage tanks are 5 and 10 m3) is

    not its most striking

    characteristic. The chal-

    lenge lay in the hand-

    ling of small amounts

    safely (drums of up to

    30 litres) and highly

    accurate measurement

    and dosing.

  • GEA WestfaliaSeparator decanters for Biwater project in Sri LankaFor activities of Negombo Water

    Supply, a drinking water company in

    Sri Lanka, Biwater Contracting has

    been awarded a contract to the value

    of EUR 34m. The activities concern

    the design, construction and start

    up of an extension to the existing

    drinking water plant, distribution

    network and storage reservoirs. In

    turn, Biwater has instructed GEA

    Westfalia Separator Netherlands BV

    in Cuijk to deliver a complete plant

    for the dewatering of sludge.

    This plant will dewater the thickened

    sludge arising as a result of coagu-

    lation with aluminium during the

    production of drinking water. GEA

    Westfalia Separator has designed

    a complete Plug & Play container

    unit and executed its engineering

    together with Logisticon. This 30-ft

    container contains all the requisite

    equipment, including two UCD 305

    decanters, a polymer production unit,

    pumps and the entire controls. The

    unit will process approximately 5 m3

    aluminium sludge per hour.

    Biwater chose GEA Westfalia Sepa-

    rator as partner because it was able

    to supply a complete solution, includ-

    ing the possibility of testing the unit

    with sludge prior to shipment, and

    the possibility of training for the staff

    involved. Logisticon played a crucial

    role here, and this, along with the

    professional project management

    and the quality of the works, were

    the deciding factors in awarding

    the contract to GEA Westfalia and

    Lo gisticon Water Treatment.

    This project is being co-fi nanced with

    development funds from the Dutch

    government.

    Was

    te w

    ater

    I f all of the water in the world were to be put in a one litre bottle, all of the available fresh water would fit in a spoon.

    About water

  • Pro

    cess

    wat

    er

    Waste water

    Pro

    cess

    wat

    er

    Mobile reverse osmosis unit in 20-ft container

    Building a reverse osmosis

    (RO) unit with a capacity of

    100 m3/h in a mobile 20-foot

    high cube container was quite

    a challenge. It was clear that

    all the components had to fi t

    into the container, but easy

    maintenance and accessibility

    during operation were even

    more important. To this end,

    a detailed 3D design was

    required in advance. Logisticon

    has been using the software

    programme Solidworks, with a

    comprehensive library, for this

    purpose for several years now.

    Ultimately the whole container

    was given a double fl oor, doors on

    both sides and an additional wicket

    door on one side. The RO unit was

    also equipped with an automatic

    cleaning fi lter, high-fl ow cartridge

    fi lters, high pressure pump with

    frequency converter and 2 chemical

    dosing units. All the piping was

    constructed in stain-

    less steel 316L.

    In the end, two

    complete mobile

    RO containers were

    delivered to the client

    in record time.

    dosing units. All the piping was

    Waste water

    The municipality of Deventer commissioned Logisticon Water Treatment B.V. and Pannekoek

    GWW to jointly deliver an effl uent treatment plant at the waste water treatment plant in

    Deventer, The Netherlands. After a test period and a tendering procedure, the parties involved

    opted for a DynaDisc fi lter with a capacity of 600 m3/h.

    The project was the result of a waste water purifi cation agreement concluded between the

    municipality of Deventer and the Groot Salland Water Board. The purpose of this agreement

    was to reduce the Chemical Oxygen Demand (COD) in the effl uent water in question. In this

    case, the municipality of Deventer was the client and it transferred the project management

    for the realisation, management and maintenance of the fi lter after commissioning to the

    Groot Salland Water Board. The DynaDisc plant was designed to remove a total of 19,700 kg

    COD annually. This COD, consisting primarily of suspended particles, is fi ltered off at the disc

    First disc fi lter in the Netherlandsfor improving sewage effl uent

  • Was

    te w

    ater

    Was

    te w

    ater

    As yet, little of the residual medicine which ends up in waste water through urine and faeces is removed.

    The current generation of waste water treatment plants are insuffi ciently equipped to break down

    these substances in the treatment process. They can, however, be removed at various places. This can

    be realised at the district water boards’ waste water treatment plants or at the places where the medi-

    cine residues are highest, so that the effects of treatment specifi cally for this purpose are maximised.

    The concentration of medicine residues is highest at for instance hospitals and health care institutions.

    Groot Salland Water Board in Zwolle, The Netherlands has acknowledged this problem and has

    started a project to investigate how to tackle it. This is known as the SLIK project (Sanitary discharge

    at Isala Clinics) which is part of a larger European cooperation project PILLS (Pharmaceutical Inputs

    and eLimination from Local Sources).

    A process design was fi rst drawn up by Grontmij. Ultimately, Logisticon Water Treatment was

    commissioned to design in detail, build and commission the greater part of this treatment plant to-

    gether with its subcontractors Elmon Electrotechniek and MWH. The core of

    the plant consists of a new, unique low-energy Membrane Biological Reactor

    (MBR) system based on BioAir™ technology. This comprises the pumping of

    water and biological sludge through 8 mm membrane straws. This MBR plant

    is used as a component in a complete waste water treatment plant which,

    roughly speaking, consists of a pre fi ltration, biological treatment, a BioAir™-

    type MBR and a post-treatment with ozone/UV and activated carbon. The

    ultimate objective is to treat the waste water locally with a compact MBR and

    to remove the residual medicine with the post-treatment.

    Removal of medicine residues from sewage water

    commissioned to design in detail, build and commission the greater part of this treatment plant to-

    on the inside of the fi lter by means of special 10-micron fi lter fabric. The clean effl uent from the disc

    fi lter is then discharged into the IJssel by means of gravity. The suspended particles trapped in the

    fi lter are then transported back to the beginning of the waste water treatment process. Essential

    aspects of the design are that the energy consumption and the fl ow of fl ushing water returned to

    the waste water treatment plant are minimised.

    The civil activities were carried out by Pannekoek GWW, and the design and mechanical and electrical

    engineering activities by Logisticon Water Treatment B.V. The fi lter itself was supplied by Nordic

    Water Benelux.

    The disc fi lter plant was offi cially opened on 13 September 2010 by alderman Jos Pierey and

    chairman of the water board council Herman Dijk.

    The plant performs better than the requirements

    laid down.

    The disc fi lter plant was offi cially opened on 13 September 2010 by alderman Jos Pierey andThe disc fi lter plant was offi cially opened on 13 September 2010 by alderman Jos Pierey and

  • West Frisian islands ready for the future: Final nano fi ltration unit installed on VlielandVitens is responsible for the drinking

    water supplies on the West Frisian

    islands Vlieland, Terschelling, Ameland

    and Schiermonnikoog. In 2005, Vitens

    started with the expansion of treat-

    ment facilities on Terschelling by

    installing 2 Logisticon anaerobic nano

    fi ltration (NFI) plants in temporary

    accommodation. In addition to re-

    moving iron and manganese, the

    particular objectives of these units

    were to remove colour and soften

    the water. They are part of the overall

    drinking water preparation in which

    groundwater is treated, in the tra-

    ditional manner, by rapid fi ltration.

    After this temporary expansion on

    Terschelling, the defi nitive expansion

    and renovation of the production

    plant on Terschelling and two produc-

    tion plants on Ameland were tackled.

    The West Frisian islands Schiermon-

    nikoog and Vlieland followed. The

    last anaerobic nano fi ltration was de-

    livered on Vlieland early 2011. This

    last step completed the renovation

    of Vitens’ drinking water production

    plants on the West Frisian islands.

    In this project, Logisticon delivered a

    total of 8 highly specifi c NFIs, all of

    which function satisfactorily.

    A special aspect of the design of

    these anaerobic nanofi ltration plants

    is that each one has a variable capac-

    ity of between 2 and 22 m3/h, split up

    into 2 lines. Incidentally, the nanofi l-

    tration plant on Vlieland is larger than

    the others and has a variable capacity

    of 3 – 33 m3/h.

    Another special feature of these wa-

    ter treatment plants is that they are all

    automatically cleaned by a Cleaning

    In Place (CIP) unit so that anti-scalant

    no longer has to be used. The need

    for cleaning is determined in the con-

    trols by trending of the functioning

    of the plant. Each plant is a tour de

    force in terms of con-

    trols. The latter ensure

    that a minimum of

    manpower is required

    to operate and main-

    tain the plants.

    total of 8 highly specifi c NFIs, all of

    which function satisfactorily.

    A special aspect of the design of

    these anaerobic nanofi ltration plants

    is that each one has a variable capac-

    ity of between 2 and 22 m

    into 2 lines. Incidentally, the nanofi l-

    tration plant on Vlieland is larger than

    the others and has a variable capacity

    Dri

    nkin

    g w

    ater

    a co

    mp

    onen

    t of p

    roce

    ss w

    ater

  • Pro

    cess

    wat

    er

    Groundwater treatment for Ball Packaging EuropeBall Packaging Europe in Oss com-

    missioned Logisticon Water Treat-

    ment to design, build and commis-

    sion a groundwater treatment plant

    with a maximum capacity of 16 m³/h.

    Ball Packaging Europe is one of the

    biggest manufacturers of cans for

    the food industry.

    After purifi cation, the groundwater is

    used for pre-rinsing cans, as cooling

    water and as feed water for the

    RO units. The groundwater contains

    various elements including iron and

    manganese. The levels of these

    elements are reduced until they

    are equal to drinking water norms.

    Effective removal of iron and man-

    ganese is achieved using two special

    sand fi lters, connected in series.

    Moreover, the water is softened

    and intensively aerated with a plate

    aerator to remove substances such

    as CO2 and is ultimately disinfected.

    Once it has been treated, the quality

    of the water is comparable with

    softened drinking water. The ground-

    water treatment plant means that

    Ball Packaging Europe makes sub-

    stantial savings on an annual basis.

    The entire plant was built on frames,

    wired up and installed as elements in

    workshop of Logisticon in advance.

    This meant that the plant could be

    delivered and commissioned quickly

    and started up without interrupting

    production.

    The entire plant was built on frames,

    wired up and installed as elements in

    workshop of Logisticon in advance.

    This meant that the plant could be

    delivered and commissioned quickly

    and started up without interrupting

    production.

  • Colofon‘LogistiContour’ is a publication of:

    Logisticon Water Treatment b.v.

    Energieweg 2, 2964 LE

    Industrieterrein Gelkenes

    P.O. Box 38, 2964 ZG

    Groot-Ammers, The Netherlands

    Telephone: +31 (0) 184 - 60 82 60

    Fax: +31 (0) 184 - 60 82 80

    E-mail: [email protected]

    Website: www.logisticon.com

    © 2011

    Logisticon Water Treatment expanding againLogisticon has been growing steadily during

    the last few years. In 2006, it was necessary

    to expand the site by 5000 m2 and replace the

    gantry crane in order to be able to store all the

    rental equipment effi ciently. Two years later, in

    2008, the offi ce was also expanded by around

    300 m2. The next extension has also recently

    been fi nalised. The expansion of the rental

    fl eet – mainly with pilot and test plants – means

    that more frost-free storage space inside is

    required. An area of approximately 600 m2

    and a 5-ton gantry crane have, therefore, been

    added to the buildings.

    Investments have also been made in various

    pieces of production equipment. These include

    an orbital welding robot, a T-drill machine,

    welding systems for plastics for larger dia-

    meters and mobile workshops. Environmental

    factors and the improvement of working

    conditions were also looked at. The lighting

    in the workshop was replaced, resulting in an

    improvement in the light yield of 28% and an

    annual energy saving of 17,900 kWh. A large,

    new air cleaner was also installed. This con-

    tinually cleans the air in the workshop and, by

    recycling it, ensures that no warmth is lost

    during cold periods.

    It can take groundwater a complete human lifetime to move 1 kilometre.

    About water