Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
IndexLargest demineralised water plant
De Vries & van de Wiel
Pilot plant for the SOURCE project
Condensate Polishing project
On-site container treatment units
NieuWater ultrapure water project
GEA Westfalia to Sri Lanka
RO system in a 20ft container
Disc fi lter for the Deventer Municipality
Removal of medicine residues from sewer
Final nanofi ltration unit on Vlieland
Ball Packaging groundwater treatment
Logisticon expands again
1
2
3
4
5
6
7
8
8
9
10
11
12
THE NETHERLANDS’ LARGEST DEMINERALISED WATER PLANT BUILT IN RECORD TIMEEvides Industry Water has had the Netherlands’
largest demineralised water plant (DWP) built
in the port of Rotterdam. It has a capacity of
1,400 m3/h. Whereas it would normally take
2.5 years to build a plant like DWP, this one was
designed, built and commissioned within the
record time of 14 months. As a result of the unique
cooperation between the contracting parties on
the construction team level, the water purifi cation
plant, as planned in the fi rst phase, was started
up well before the deadline. Lo gisticon Water
Treatment and its sister company Elmon Elektro-
techniek were responsible for the mechanical
and electro technical installation for the DWP
plant. Instructions have now also been given for
the second phase of the project.
Realisation in 2 phases
In 2008, Evides Industry Water started with
the design of a 1,400 m3/h demineralised water
plant: the Botlek DWP.
This plant will use water
from the Brielse Meer
(Lake Brielle), which will
be desalinated using
membrane fi ltration and
ion exchange technology.
Drinking water will be
used as the back-up raw
infl uent. The project was
split into two phases
because it had to be
Process water
Continued on page 2
Water regulates the temperature of the earth.
About water
Continued from page 1Continued from page 1
completed within a very short time
frame. The fi rst phase entailed the
construction of a complete DWP plant.
This is now producing demineralised
water from drinking water. The second
phase entails a unit for the pre treat-
ment of surface water from the Brielse
Meer which will go into operation in
early 2010.
The demineralised water from the DPW plant
is distributed through the existing deminer-
alised water net-
work to a number
of refi neries and
about 15 chemical
and petrochemical
companies. Evides
also supplies sof-
tened water to
Huntsman sepa-
rately.
Unique cooperation from design to delivery
The execution was based on a planning analysis,
the objective of which was to shorten the time
frame taken by each process component as far
as possible. The most important aspects are, of
course, delivery, assembly and commissioning
times, but also, and especially, the connection
between the process components. An extensive
3D design was made using as many “prefab”
parts as possible in order to maximise control
on the building site. This applied, for example, to
the RO skids, but also to the polypropylene fi lter
fronts Logisticon made in its own workshop.
The speed of construction was only possible
because of this unique cooperation.
High quality demineralised water
The demineralised water produced is of a high
quality. The quality of water ex works (includ-
ing 0.2 µS/cm and 30 ppb silica) is well within
the specifi cations.
Pump and control container for De Vries & van de WielOn the instructions of the Province of South Holland, De Vries & van de Wiel is currently decon-
taminating two areas (Geitenwei and Schanspolder) located close to the Hollandse IJssel near
Ouderkerk aan den IJssel in The Netherlands. The contaminated groundwater released during
excavation must be cleaned up before it can be discharged.
Because of the distance between the two sites, two separate water treatment plants
had to be used. De Vries & van de Wiel has bought one of them and leases the other from
Logisticon. Basically, they consist of 10-foot containers equipped with pumps, blowers, a
control switch board for sand fi ltration with automatically operated valves for the fi ltration
and backwashing of the sand fi lter. The capacity of the pumps is adjustable up to a maximum
of 30 m³/h. The size of the sand fi lter ultimately determines the capacity of a plant. The big
advantages of these versatile water treatment plants are that all the pumps and automatic
valves are protected from the frost in the containers and that the capacity can easily be
adjusted to suit any project.
Environmental
is distributed through the existing deminer-
Pump and control container for De Vries & van de Wiel
Logisticon delivers and operates pilot plant for SOURCE projectThe Aa and Maas Water Board in The
Netherlands initiated the develop-
ment of a processing concept for
reducing the emission of nitrogen,
phosphate and medicines to the
surface water. To this end, it cooper-
ated with the Southern Agricultural
and Market Gardening Organisation
(ZLTO), the Foundation for Applied
Water Research (STOWA) and the
ministries of Agriculture, Nature and
Food Quality (LNV), Housing, Spatial
Planning and the Environment
(VROM) and Transport, Public Works
and Water Management (V&W). A
project named ‘SOURCE’ was set up
for this purpose: SimultaneOUs Reuse
of nutrients and removal of human
and veterinary pharmaCEuticals.
A test plant is being tested in accord-
ance with the SOURCE concept at
the Land van Cuijk waste water treat-
ment plant in Haps, The Netherlands
for about a year. In this process,
animal manure is pre-treated together
with human urine (collected at a
hospital). Subsequently, the phos-
phate is fi xed and recovered in the
form of granular struvite (Magnesium
Ammonium Phosphate) using Akwa-
dok’s NuReSys® nutrient recovery
system and ammonia is removed
with a low-energy biological system
(Grontmij’s Demon®). Medi-
cines and hormones are then
removed from the water fl ow
using an advanced treatment
involving ozone and activated
carbon fi ltration.
In addition to producing
a detailed design, Logisticon
was instructed to build, lease
and operate the plant. The job
included detail engineering,
building and providing technical
support in the SOURCE project and
executing it with an over-all measur-
ing, data storage and management
system with the possibility of control
and monitoring at a distance. The
study was given a festive launch on
7 October 2010.
(Grontmij’s Demon®). Medi-
Was
te w
ater
Condensate polishing for Neste Oil at the E.on power stationThere has recently been an increase
in the number of projects based on
cooperation between companies
in the Rotterdam harbour area. For
instance the production and delivery
of demineralised water by Evides
Industry Water to various industries
in the port of Rotterdam (DWP) and
another is the Condensate Polishing
Unit project (CTU). This last project
entails the improvement of Neste
Oil’s used return condensate by E.on
for boiler feed water. The condensate
must be stripped of oily contaminants
primarily released during the produc-
tion of Neste Oil’s palm oil. Other
oils released in the processing of,
for example, soybeans and stearine
from palm oil must, however, also be
taken into account.
This plant, with a capacity of 65 m3/h
(2x60%), will treat condensate with
a temperature of 97 °C. The specifi -
cations are, however, much higher,
so that all the equipment has been
designed to process condensate
with a temperature of 125 °C under
a pressure of 10 bar. The mechani-
cal components of the plant must,
moreover, be able to operate for
8,760 h annually for a period of
25 years. Operation of the plant
may only be interrupted for planned
stops. Two parallel activated carbon
units have, therefore, been designed
and built. The backwashing with
demineralised water in these units
is fully automatic. Logisticon also
delivered and installed the pre-
fi ltration, gas collectors, buffer tank
with nitrogen blanket, fl ush tank
and pumps, instrumentation and all
the steel pipes and pressure pipes
on the site. The electro technical
installation was carried out by Elmon
Electrotechniek, one of Logisticon’s
sister companies. With
this project, Logisticon
has further expanded
its fi eld with pressure
driven, high tempera-
ture water/condensate
systems.
and built. The backwashing with
fi ltration, gas collectors, buffer tank
with nitrogen blanket, fl ush tank
and pumps, instrumentation and all
Pro
cess
wat
er
Env
iron
men
tal
Seen over a period of 100 years, a water molecule spends 98 years in the ocean, 20 months in the form of ice, approximately 2 weeks in lakes and rivers and less than a week in the atmosphere.
About water
Water treatment plant in 30-ftcontainer forOnsite NVOn the instructions of the Belgian
company Onsite N.V., Logisticon
has built a new groundwater treat-
ment plant for a large in-situ soil
remediation project which will be
running the coming years. Because
the treatment plant is located next
to the client’s offi ce building, as
many components as possible had
to be built into an insulated container.
The groundwater is treated by means
of sand fi ltration (for iron removal),
air-stripped using a plate aerator and
polished by granulated active carbon
fi ltration. The challenging aspect of
this project was the high iron content
(greater than 50 mg/l) in the ground-
water. The capacity of the plant is
15 m³/h and it is built into a 30-ft
container. All the air from the plate
aerator is cleaned with activated
carbon. The air fi lters with activated
carbon have been placed on top of
the container because of the limited
space and to facilitate the changing
of fi lters.
Pro
cess
wat
er Extensive chemical storage and dosing facilities for NieuWaterNieuWater B.V.’s ultra pure water
project is unique in the water world.
This is the fi rst time that effl uent
(from the Emmen waste water treat-
ment plant, The Netherlands) has
been processed into ultra pure water
(UPW). It is also the fi rst time so
many complex process
steps such as ultra
fi ltration, biological
active granular carbon
fi ltration, double pass
reverse osmosis and
continuous de ionisation
have all been used in
such a project together. Because of
the technology chosen, the use of
chemicals is minimised. However,
to ensure continuous supply, a com-
prehensive chemical dosing plant
has also been opted for. This can
be used in the event that there is
an un expected deterioration in the
quality of the effl uent from the waste
water treatment plant, if the biologi-
cal active carbon fi ltration fails or in
any other contingency. The point is
that this plant will only be needed to
bridge short periods, should problems
arise. The continuity in supplies of
ultra pure water to the NAM for oil
extraction in Schoonebeek is of great
economic importance. Logisticon
has never before designed and built
dosing devices for 9 different chemi-
cals in one single project. In high
tech water treatment of this kind,
it is very important to monitor any
possible contaminant strictly. The
chemical dosing devices are housed
in a separate building and the central
storage and dosing devices are
located in a separate acid and caustic
department. As a result, a total of
around 3 km of dosing piping had to
be constructed.
Double-walled piping has been
used for safety and environmen-
tal reasons. Particular attention has
been paid to the couplings between
the reinforced hoses and equipment.
Comprehensive pressure testing
has, of course, been carried out and
a leak detection system has been
installed to guarantee safety.
This size of this plant (the largest
storage tanks are 5 and 10 m3) is
not its most striking
characteristic. The chal-
lenge lay in the hand-
ling of small amounts
safely (drums of up to
30 litres) and highly
accurate measurement
and dosing.
GEA WestfaliaSeparator decanters for Biwater project in Sri LankaFor activities of Negombo Water
Supply, a drinking water company in
Sri Lanka, Biwater Contracting has
been awarded a contract to the value
of EUR 34m. The activities concern
the design, construction and start
up of an extension to the existing
drinking water plant, distribution
network and storage reservoirs. In
turn, Biwater has instructed GEA
Westfalia Separator Netherlands BV
in Cuijk to deliver a complete plant
for the dewatering of sludge.
This plant will dewater the thickened
sludge arising as a result of coagu-
lation with aluminium during the
production of drinking water. GEA
Westfalia Separator has designed
a complete Plug & Play container
unit and executed its engineering
together with Logisticon. This 30-ft
container contains all the requisite
equipment, including two UCD 305
decanters, a polymer production unit,
pumps and the entire controls. The
unit will process approximately 5 m3
aluminium sludge per hour.
Biwater chose GEA Westfalia Sepa-
rator as partner because it was able
to supply a complete solution, includ-
ing the possibility of testing the unit
with sludge prior to shipment, and
the possibility of training for the staff
involved. Logisticon played a crucial
role here, and this, along with the
professional project management
and the quality of the works, were
the deciding factors in awarding
the contract to GEA Westfalia and
Lo gisticon Water Treatment.
This project is being co-fi nanced with
development funds from the Dutch
government.
Was
te w
ater
I f all of the water in the world were to be put in a one litre bottle, all of the available fresh water would fit in a spoon.
About water
Pro
cess
wat
er
Waste water
Pro
cess
wat
er
Mobile reverse osmosis unit in 20-ft container
Building a reverse osmosis
(RO) unit with a capacity of
100 m3/h in a mobile 20-foot
high cube container was quite
a challenge. It was clear that
all the components had to fi t
into the container, but easy
maintenance and accessibility
during operation were even
more important. To this end,
a detailed 3D design was
required in advance. Logisticon
has been using the software
programme Solidworks, with a
comprehensive library, for this
purpose for several years now.
Ultimately the whole container
was given a double fl oor, doors on
both sides and an additional wicket
door on one side. The RO unit was
also equipped with an automatic
cleaning fi lter, high-fl ow cartridge
fi lters, high pressure pump with
frequency converter and 2 chemical
dosing units. All the piping was
constructed in stain-
less steel 316L.
In the end, two
complete mobile
RO containers were
delivered to the client
in record time.
dosing units. All the piping was
Waste water
The municipality of Deventer commissioned Logisticon Water Treatment B.V. and Pannekoek
GWW to jointly deliver an effl uent treatment plant at the waste water treatment plant in
Deventer, The Netherlands. After a test period and a tendering procedure, the parties involved
opted for a DynaDisc fi lter with a capacity of 600 m3/h.
The project was the result of a waste water purifi cation agreement concluded between the
municipality of Deventer and the Groot Salland Water Board. The purpose of this agreement
was to reduce the Chemical Oxygen Demand (COD) in the effl uent water in question. In this
case, the municipality of Deventer was the client and it transferred the project management
for the realisation, management and maintenance of the fi lter after commissioning to the
Groot Salland Water Board. The DynaDisc plant was designed to remove a total of 19,700 kg
COD annually. This COD, consisting primarily of suspended particles, is fi ltered off at the disc
First disc fi lter in the Netherlandsfor improving sewage effl uent
Was
te w
ater
Was
te w
ater
As yet, little of the residual medicine which ends up in waste water through urine and faeces is removed.
The current generation of waste water treatment plants are insuffi ciently equipped to break down
these substances in the treatment process. They can, however, be removed at various places. This can
be realised at the district water boards’ waste water treatment plants or at the places where the medi-
cine residues are highest, so that the effects of treatment specifi cally for this purpose are maximised.
The concentration of medicine residues is highest at for instance hospitals and health care institutions.
Groot Salland Water Board in Zwolle, The Netherlands has acknowledged this problem and has
started a project to investigate how to tackle it. This is known as the SLIK project (Sanitary discharge
at Isala Clinics) which is part of a larger European cooperation project PILLS (Pharmaceutical Inputs
and eLimination from Local Sources).
A process design was fi rst drawn up by Grontmij. Ultimately, Logisticon Water Treatment was
commissioned to design in detail, build and commission the greater part of this treatment plant to-
gether with its subcontractors Elmon Electrotechniek and MWH. The core of
the plant consists of a new, unique low-energy Membrane Biological Reactor
(MBR) system based on BioAir™ technology. This comprises the pumping of
water and biological sludge through 8 mm membrane straws. This MBR plant
is used as a component in a complete waste water treatment plant which,
roughly speaking, consists of a pre fi ltration, biological treatment, a BioAir™-
type MBR and a post-treatment with ozone/UV and activated carbon. The
ultimate objective is to treat the waste water locally with a compact MBR and
to remove the residual medicine with the post-treatment.
Removal of medicine residues from sewage water
commissioned to design in detail, build and commission the greater part of this treatment plant to-
on the inside of the fi lter by means of special 10-micron fi lter fabric. The clean effl uent from the disc
fi lter is then discharged into the IJssel by means of gravity. The suspended particles trapped in the
fi lter are then transported back to the beginning of the waste water treatment process. Essential
aspects of the design are that the energy consumption and the fl ow of fl ushing water returned to
the waste water treatment plant are minimised.
The civil activities were carried out by Pannekoek GWW, and the design and mechanical and electrical
engineering activities by Logisticon Water Treatment B.V. The fi lter itself was supplied by Nordic
Water Benelux.
The disc fi lter plant was offi cially opened on 13 September 2010 by alderman Jos Pierey and
chairman of the water board council Herman Dijk.
The plant performs better than the requirements
laid down.
The disc fi lter plant was offi cially opened on 13 September 2010 by alderman Jos Pierey andThe disc fi lter plant was offi cially opened on 13 September 2010 by alderman Jos Pierey and
West Frisian islands ready for the future: Final nano fi ltration unit installed on VlielandVitens is responsible for the drinking
water supplies on the West Frisian
islands Vlieland, Terschelling, Ameland
and Schiermonnikoog. In 2005, Vitens
started with the expansion of treat-
ment facilities on Terschelling by
installing 2 Logisticon anaerobic nano
fi ltration (NFI) plants in temporary
accommodation. In addition to re-
moving iron and manganese, the
particular objectives of these units
were to remove colour and soften
the water. They are part of the overall
drinking water preparation in which
groundwater is treated, in the tra-
ditional manner, by rapid fi ltration.
After this temporary expansion on
Terschelling, the defi nitive expansion
and renovation of the production
plant on Terschelling and two produc-
tion plants on Ameland were tackled.
The West Frisian islands Schiermon-
nikoog and Vlieland followed. The
last anaerobic nano fi ltration was de-
livered on Vlieland early 2011. This
last step completed the renovation
of Vitens’ drinking water production
plants on the West Frisian islands.
In this project, Logisticon delivered a
total of 8 highly specifi c NFIs, all of
which function satisfactorily.
A special aspect of the design of
these anaerobic nanofi ltration plants
is that each one has a variable capac-
ity of between 2 and 22 m3/h, split up
into 2 lines. Incidentally, the nanofi l-
tration plant on Vlieland is larger than
the others and has a variable capacity
of 3 – 33 m3/h.
Another special feature of these wa-
ter treatment plants is that they are all
automatically cleaned by a Cleaning
In Place (CIP) unit so that anti-scalant
no longer has to be used. The need
for cleaning is determined in the con-
trols by trending of the functioning
of the plant. Each plant is a tour de
force in terms of con-
trols. The latter ensure
that a minimum of
manpower is required
to operate and main-
tain the plants.
total of 8 highly specifi c NFIs, all of
which function satisfactorily.
A special aspect of the design of
these anaerobic nanofi ltration plants
is that each one has a variable capac-
ity of between 2 and 22 m
into 2 lines. Incidentally, the nanofi l-
tration plant on Vlieland is larger than
the others and has a variable capacity
Dri
nkin
g w
ater
a co
mp
onen
t of p
roce
ss w
ater
Pro
cess
wat
er
Groundwater treatment for Ball Packaging EuropeBall Packaging Europe in Oss com-
missioned Logisticon Water Treat-
ment to design, build and commis-
sion a groundwater treatment plant
with a maximum capacity of 16 m³/h.
Ball Packaging Europe is one of the
biggest manufacturers of cans for
the food industry.
After purifi cation, the groundwater is
used for pre-rinsing cans, as cooling
water and as feed water for the
RO units. The groundwater contains
various elements including iron and
manganese. The levels of these
elements are reduced until they
are equal to drinking water norms.
Effective removal of iron and man-
ganese is achieved using two special
sand fi lters, connected in series.
Moreover, the water is softened
and intensively aerated with a plate
aerator to remove substances such
as CO2 and is ultimately disinfected.
Once it has been treated, the quality
of the water is comparable with
softened drinking water. The ground-
water treatment plant means that
Ball Packaging Europe makes sub-
stantial savings on an annual basis.
The entire plant was built on frames,
wired up and installed as elements in
workshop of Logisticon in advance.
This meant that the plant could be
delivered and commissioned quickly
and started up without interrupting
production.
The entire plant was built on frames,
wired up and installed as elements in
workshop of Logisticon in advance.
This meant that the plant could be
delivered and commissioned quickly
and started up without interrupting
production.
Colofon‘LogistiContour’ is a publication of:
Logisticon Water Treatment b.v.
Energieweg 2, 2964 LE
Industrieterrein Gelkenes
P.O. Box 38, 2964 ZG
Groot-Ammers, The Netherlands
Telephone: +31 (0) 184 - 60 82 60
Fax: +31 (0) 184 - 60 82 80
E-mail: [email protected]
Website: www.logisticon.com
© 2011
Logisticon Water Treatment expanding againLogisticon has been growing steadily during
the last few years. In 2006, it was necessary
to expand the site by 5000 m2 and replace the
gantry crane in order to be able to store all the
rental equipment effi ciently. Two years later, in
2008, the offi ce was also expanded by around
300 m2. The next extension has also recently
been fi nalised. The expansion of the rental
fl eet – mainly with pilot and test plants – means
that more frost-free storage space inside is
required. An area of approximately 600 m2
and a 5-ton gantry crane have, therefore, been
added to the buildings.
Investments have also been made in various
pieces of production equipment. These include
an orbital welding robot, a T-drill machine,
welding systems for plastics for larger dia-
meters and mobile workshops. Environmental
factors and the improvement of working
conditions were also looked at. The lighting
in the workshop was replaced, resulting in an
improvement in the light yield of 28% and an
annual energy saving of 17,900 kWh. A large,
new air cleaner was also installed. This con-
tinually cleans the air in the workshop and, by
recycling it, ensures that no warmth is lost
during cold periods.
It can take groundwater a complete human lifetime to move 1 kilometre.
About water