Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
The Nordic Capacity Calculation Methodology (CCM) project
CCM Stakeholder Forum – Stockholm
8 February - 2017
Agenda
1. Coffee (9.00 – 9.30)
2. Welcome, objective and agenda (9.30 - 9.45), Trond Jensen (Statnett)
3. NordREG presentation (9.45 - 10.15), Johan Roupe (EI)
4. Nordic CCM project and timeline (10.15 - 10.30), Trond Jensen (Statnett)
5. Coffee (10.30 - 10.50)
6. Nordic FB and CNTC methodologies (10.50 - 11.30), Nils Flaten Ræder (Statnett) and Heini Ruohosenmaa (Fingrid)
7. Market results (11.30 - 12.00), Mårten Bergman (Svk)
8. First round of questions and answers (12.00 - 12.30)
9. Lunch (12.30 - 13.30)
10. Market information platform and market information tool (13.30 - 14.00), Mårten Bergman (Svk)
11. CCM proposal process (14.00 - 14.30), Ulrik Møller (Edk)
12. Coffee break (14.30 - 15.00)
13. Second round of questions and answers (15.00 - 16.30)
Agenda
1. Coffee (9.00 – 9.30)
2. Welcome, objective and agenda (9.30 - 9.45), Trond Jensen (Statnett)
3. NordREG presentation (9.45 - 10.15), Johan Roupe (EI)
4. Nordic CCM project and timeline (10.15 - 10.30), Trond Jensen (Statnett)
5. Coffee (10.30 - 10.50)
6. Nordic FB and CNTC methodologies (10.50 - 11.30), Nils Flaten Ræder (Statnett) and Heini Ruohosenmaa (Fingrid)
7. Market results (11.30 - 12.00), Mårten Bergman (Svk)
8. First round of questions and answers (12.00 - 12.30)
9. Lunch (12.30 - 13.30)
10. Market information platform and market information tool (13.30 - 14.00), Mårten Bergman (Svk)
11. CCM proposal process (14.00 - 14.30), Ulrik Møller (Edk)
12. Coffee break (14.30 - 15.00)
13. Second round of questions and answers (15.00 - 16.30)
Main deliveries of the Nordic CCM project
A CCM for the Day Ahead (DA) and Intraday (ID) ID market in accordance to Guideline on Capacity Allocation and Congestion Management (CACM) The methodology is to be used by the industrialized Capacity Calculation (CC) tool to be developed
by the Regional Security Centre (RSC) Either a Flow Based or a Coordinated Net Transfer Capacity (CNTC) methodology Prototype Capacity Calculation tool(s) to test the methodology on real market data Market simulations and parallel runs
Management of the National Regulatory Agencies (NRA) CCM proposal process Consultation document (Supporting document) Stakeholder consultation NRA proposal for CCM (Legal document)
Support the RSC with "Domain expertise" in the tooling phase Capacity Calculation (CC) experts Specify domain requirements for the RSCs CC tool
Organizational structure
Work Group 1 CCM Methodology
FB & CNTC
Convener: Nils Ræder
Work Group 3 Welfare Economics
Convener: Mårten
Bergman
Steering committee One member from each TSO
Convener: Søren Dupond Kristensen
Work Group 4 CCM Proposal
Convener: Ulrik Møller
Convener team Project Manager: Trond Jensen
Regional Group Nordic (RGN)
Operational Reference Group
Convener: Jan Hystad
Work Group 2 CCM Methodology
CNTC Convener: Heini Ruohosenmaa
IT-Support
Convener: Martin Julander
Market Steering Group (MSG)
Agenda
1. Coffee (9.00 – 9.30)
2. Welcome, objective and agenda (9.30 - 9.45), Trond Jensen (Statnett)
3. NordREG presentation (9.45 - 10.15), Johan Roupe (EI)
4. Nordic CCM project and timeline (10.15 - 10.30), Trond Jensen (Statnett)
5. Coffee (10.30 - 10.50)
6. Nordic FB and CNTC methodologies (10.50 - 11.30), Nils Flaten Ræder (Statnett) and Heini Ruohosenmaa (Fingrid)
7. Market results (11.30 - 12.00), Mårten Bergman (Svk)
8. First round of questions and answers (12.00 - 12.30)
9. Lunch (12.30 - 13.30)
10. Market information platform and market information tool (13.30 - 14.00), Mårten Bergman (Svk)
11. CCM proposal process (14.00 - 14.30), Ulrik Møller (Edk)
12. Coffee break (14.30 - 15.00)
13. Second round of questions and answers (15.00 - 16.30)
Agenda
1. Coffee (9.00 – 9.30)
2. Welcome, objective and agenda (9.30 - 9.45), Trond Jensen (Statnett)
3. NordREG presentation (9.45 - 10.15), Johan Roupe (EI)
4. Nordic CCM project and timeline (10.15 - 10.30), Trond Jensen (Statnett)
5. Coffee (10.30 - 10.50)
6. Nordic FB and CNTC methodologies (10.50 - 11.30), Nils Flaten Ræder (Statnett) and Heini Ruohosenmaa (Fingrid)
7. Market results (11.30 - 12.00), Mårten Bergman (Svk)
8. First round of questions and answers (12.00 - 12.30)
9. Lunch (12.30 - 13.30)
10. Market information platform and market information tool (13.30 - 14.00), Mårten Bergman (Svk)
11. CCM proposal process (14.00 - 14.30), Ulrik Møller (Edk)
12. Coffee break (14.30 - 15.00)
13. Second round of questions and answers (15.00 - 16.30)
A brief history of the Nordic CCM project
Prefeasibility study
Feasibility study
Pre-implementation phase
Project development Model studies Market assessments Work shops Methodology and technical requirements for a Nordic FB
Prototype development FB capacity calculation and market simulation experiments Stakeholder communication
Capacity calculation and market simulations Welfare analyses Infrastructure development (IT platforms) Stakeholder processes CCM proposal process CNTC development DA → DA and ID
Nordic Flow Based Project Nordic CCM Project SN Flow Based Project
Asses the FB concept Asses literature & practice Develop ideas
2012 2013 2014 2015 2016 2017 2010/2011
Internal TSO phase External communication → Stakeholder Forums → Stakeholder Group →News letters →Info platform
FB experiments FB Capacity Calculation and market simulations
CNTC Calculation and simulations
Today
18 Sept. CCM
proposal
High Level Status
WP Convener Status
Project Management
team
Trond Jensen
Stakeholder and NRA communication (Stakeholder Group, Forums and information platform, News Letters)
IT infrastructure (Secure FTP, CCM server) Link to other projects (Common Grid Model Project, Regional Security Centre project)
Work Group 1
Nils Ræder
FB and CNTC methodologies are developed FB and CNTC prototype tools are developed (CNTC not fully adjusted yet) Intraday CNTC Methodology is being developed FB capacity calculation and market simulation is ongoing CNTC capacity calculation and market simulation is ongoing
Work Group 2
Heini Ruohosenmaa
Alternative CNTC methodology and prototype tools is in development
Work Group 3
Mårten Bergman DA market welfare analyses FB vs NTC is ongoing DA market welfare analyses FB vs CNTC is ongoing
Work Group 4
Ulrik Møller
CCM proposal Currently working on a supporting document Planning for the internal TSO consultation Preparing for the market consultation Legal proposal document to be done later in the process
High-Level CCM Project Roadmap
Today
2016 2017 2018 2019 2020
Q3: Nordic DA CCM operationalized
Q4: Go-live ID CCM
Cap calc & Market sim. Jan 16 – Dec 17
Develop operational procedures
Q1/18 – Q3/19
Develop operational tools and go-live Intraday Q3/18 – Q3/20
Public parallel runs Q1/18 – Q4/19
CCM proposal Oct 16 – Sept 17
Sept 18: Submission of CCM proposal to NRAs
Q1-Q2: Go-live DA CCM
CC
M P
roje
ct
Rel
ate
d A
ctiv
itie
s
2017 – 2019 RSC develops industrialized DA tool
CGM D-2
Q1 18 – Q4 18 CGM ID Q1 19 – Q4 20 RSC develops industrialized ID tool
Each TSO develops CNE process Q1/17 – Q4/17
March 18: NRA Decision
2016 – Dec 17
Agenda
1. Coffee (9.00 – 9.30)
2. Welcome, objective and agenda (9.30 - 9.45), Trond Jensen (Statnett)
3. NordREG presentation (9.45 - 10.15), Johan Roupe (EI)
4. Nordic CCM project and timeline (10.15 - 10.30), Trond Jensen (Statnett)
5. Coffee (10.30 - 10.50)
6. Nordic FB and CNTC methodologies (10.50 - 11.30), Nils Flaten Ræder (Statnett) and Heini Ruohosenmaa (Fingrid)
7. Market results (11.30 - 12.00), Mårten Bergman (Svk)
8. First round of questions and answers (12.00 - 12.30)
9. Lunch (12.30 - 13.30)
10. Market information platform and market information tool (13.30 - 14.00), Mårten Bergman (Svk)
11. CCM proposal process (14.00 - 14.30), Ulrik Møller (Edk)
12. Coffee break (14.30 - 15.00)
13. Second round of questions and answers (15.00 - 16.30)
Agenda
1. Coffee (9.00 – 9.30)
2. Welcome, objective and agenda (9.30 - 9.45), Trond Jensen (Statnett)
3. NordREG presentation (9.45 - 10.15), Johan Roupe (EI)
4. Nordic CCM project and timeline (10.15 - 10.30), Trond Jensen (Statnett)
5. Coffee (10.30 - 10.50)
6. Nordic FB and CNTC methodologies (10.50 - 11.30), Nils Flaten Ræder (Statnett) and Heini Ruohosenmaa (Fingrid)
7. Market results (11.30 - 12.00), Mårten Bergman (Svk)
8. First round of questions and answers (12.00 - 12.30)
9. Lunch (12.30 - 13.30)
10. Market information platform and market information tool (13.30 - 14.00), Mårten Bergman (Svk)
11. CCM proposal process (14.00 - 14.30), Ulrik Møller (Edk)
12. Coffee break (14.30 - 15.00)
13. Second round of questions and answers (15.00 - 16.30)
Why capacity restrictions?
The electrical grid has a limited capacity for transporting power
Try transferring too much power, and the system is at risk of collapse
Capacity restrictions are necessary to ensure stable electricity supply with high quality
Capacity restrictions are only one of the tools employed by the TSOs to ensure operational security
Capacity calculation?
A detailed model of the electricity system, with forecasted system state and information on transmission constraints
Simplified transmission constraints that can be used by the electricity market
Only essential information is preserved, the amount and complexity of information is greatly reduced
Capacity calculation
process
Scope of the Capacity Calculation Methodology
FB
CNTC
• Common grid model (CGM) of the electricity system with forecasted system state
• Grid constraints • Available remedial actions
• Simplification of grid model
• Calculation of available capacity
• Reliability margins • Generator shift keys
Scope of CCM
Input from the TSOs
The CCM covers capacities for both the day-ahead and intraday market
The market capacities can be formulated as either flow-based parameters (FB) or coordinated net transmission capacities (CNTC)
Both FB and CNTC must respect the same underlying grid constraints, much of the calculation can be common to both approaches
The calculation process will consider updated forecasts until the last possible moment
To power exchanges for price calculations
OR
The Common Grid Model
Defined in CACM: ‘common grid model’ means a Union-wide
data set agreed between various TSOs describing the main characteristic of the power system (generation, loads and grid topology) and rules for changing these characteristics during the capacity calculation process
The CGM is built up of the TSOs' Individual Grid Models: 'individual grid model’ means a data set
describing power system characteristics (generation, load and grid topology) and related rules to change these characteristics during capacity calculation, prepared by the responsible TSOs, to be merged with other individual grid model components in order to create the common grid model
Simplifications made in the capacity calculation
Nodes aggregated into bidding zones Almost all load and generation have a unique impact
on the flows in the transmission system The difference in impact is not considered by the
market coupling All market parties in the same area are considered to
have equal impacts Each node have weigh according to the generation
shift keys (GSK)
A
C
B
The bidding zone contain numerous nodes
Linearization of interdependencies in the modelled electricity system There are complex relationships between the net
position of the bidding zones, and the loading of a transmission constraint
A more simplified approximation is found This linearization is required by the price
calculation algorithms
Export position of a bidding zone
Loading of a transmission constraint
Flow-based or
Coordinated net transmission capacity
The TSOs will provide either FB or CNTC to each of the day-ahead and intraday markets
Both FB and CNTC are sets of linear transmission constraints provided by the TSOs to the day-ahead and intraday markets Both FB and CNTC are based on the same input data
The requirements that all relevant transmission constraints shall be respected is the same
Both require the model of the electricity system to be simplified
Mathematically speaking the difference between the approaches is small
FB considers all bidding zones to be interconnected, and provides the market with information on transit flows CNTC treats all bidding zone borders as independent conduits for commercial exchange
Transit flows Contract paths vs physical paths
0.7 % 0.7 %
24 %
24 %
0 %
0.7 %
20 %
8 %
56 %
24 %
12 %
0.1 %
0.1 % 12 %
Power exchange between two bidding zones will follow all available paths in the grid
Much of the power will pass through other bidding zones – these are transit flows
The presence of transit flows means that a trade between two bidding zones will impact all transmission constraints in the region
The maximum commercial exchange that can be allowed between two bidding zones is therefore dependent on all other commercial exchanges in the region
Example market capacities
Flow-based
Transmission constraint
Available margin Impact from A Impact from B Impact from C
A -> B 1000 MW 33 % - 33 % 0
B -> C 1000 MW 33 % 67 % 0
A -> C 1000 MW 67 % 33 % 0
A
C
B
67 %
33 %
Coordinated net transmission capacities
Border Max exchange
A -> B 750 MW
B -> C 750 MW
A -> C 750 MW
Generation
Load
Simple system with three bidding zones
These are the power transfer distribution factors (PTDF)
The PTDF describe the interdependency between border flows
DK
1-D
E
DK
1-S
E3
DK
1-N
O2
DK
1-D
K2
DK
2-D
E
DK
2-S
E4
FIN
-EE
FIN
-SE
3
FIN
-NO
4
FIN
-SE
1
NO
1-N
O2
NO
1-N
O3
NO
1-N
O5
NO
1-S
E3
NO
2-N
L
NO
2-N
O5
NO
3-N
O4
NO
3-N
O5
NO
3-S
E2
NO
4-S
E1
NO
4-S
E2
SE
1-S
E2
SE
2-S
E3
SE
3-S
E4
SE
4-D
E
SE
4-L
T
SE
4-P
L
DK1-DE 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK1-SE3 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK1-NO2 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK1-DK2 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK2-DE 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK2-SE4 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FIN-EE 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FIN-SE3 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FIN-NO4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FIN-SE1 0 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
NO1-NO2 0 0 0 0 0 0 0 0 0 0 0.9 0 0.2 0 0 0.7 0 0.2 0 0 0 0 0 0 0 0 0
NO1-NO3 0 0 0 0 0 0 0 0 0.1 0 0 0.4 0.1 0.2 0 0 0.2 0.4 0.2 0.1 0.1 0 0 0 0 0 0
NO1-NO5 0 0 0 0 0 0 0 0 0 0 0.1 0 0.8 0 0 0.6 0 0.7 0 0 0 0 0 0 0 0 0
NO1-SE3 0 0 0 0 0 0 0 0 0.1 0 0 0.6 0 0.8 0 0 0.2 0.6 0.2 0.1 0.1 0 0 0 0 0 0
NO2-NL 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0
NO2-NO5 0 0 0 0 0 0 0 0 0 0 0.1 0 0.2 0 0 0.3 0 0.2 0 0 0 0 0 0 0 0 0
NO3-NO4 0 0 0 0 0 0 0 0 0.2 0 0 0.1 0 0 0 0 0.5 0.1 0.2 0.2 0.3 0.1 0 0 0 0 0
NO3-NO5 0 0 0 0 0 0 0 0 0 0 0 0 0.1 0 0 0.1 0 0.1 0 0 0 0 0 0 0 0 0
NO3-SE2 0 0 0 0 0 0 0 0 0.2 0 0 0.4 0 0.1 0 0 0.4 0.4 0.6 0.2 0.2 0.1 0 0 0 0 0
NO4-SE1 0 0 0 0 0 0 0 0 0.6 0 0 0.1 0 0 0 0 0.4 0.1 0.1 0.6 0.5 0.1 0 0 0 0 0
NO4-SE2 0 0 0 0 0 0 0 0 0.1 0 0 0.1 0 0 0 0 0.1 0.1 0.1 0.1 0.2 0 0 0 0 0 0
SE1-SE2 0 0 0 0 0 0 0 0 0.4 0 0 0.1 0 0 0 0 0.5 0.1 0.1 0.3 0.6 0.9 0 0 0 0 0
SE2-SE3 0 0 0 0 0 0 0 0 0.1 0 0 0.6 0 0.2 0 0 0.2 0.6 0.2 0.1 0.1 0 1 0 0 0 0
SE3-SE4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0
SE4-DE 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0
SE4-LT 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0
SE4-PL 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1
Commercial exchange between areas …
… im
pac
t o
n s
ched
ule
d f
low
The table show how a commercial exchange between two areas – production in one and consumption in the other – create flows on the bidding zone borders
The checkered area shows that the Norwegian and Swedish grids are highly interconnected
Any trades that would change the net positions in these areas create transit flows on multiple borders
There is not a one-to-one relationship between commercial exchange and power flow
The interdependencies between the bidding zone borders are not considered in CNTC
DK
1-D
E
DK
1-S
E3
DK
1-N
O2
DK
1-D
K2
DK
2-D
E
DK
2-S
E4
FIN
-EE
FIN
-SE
3
FIN
-NO
4
FIN
-SE
1
NO
1-N
O2
NO
1-N
O3
NO
1-N
O5
NO
1-S
E3
NO
2-N
L
NO
2-N
O5
NO
3-N
O4
NO
3-N
O5
NO
3-S
E2
NO
4-S
E1
NO
4-S
E2
SE
1-S
E2
SE
2-S
E3
SE
3-S
E4
SE
4-D
E
SE
4-L
T
SE
4-P
L
DK1-DE 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK1-SE3 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK1-NO2 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK1-DK2 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK2-DE 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK2-SE4 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FIN-EE 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FIN-SE3 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FIN-NO4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FIN-SE1 0 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
NO1-NO2 0 0 0 0 0 0 0 0 0 0 0.9 0 0.2 0 0 0.7 0 0.2 0 0 0 0 0 0 0 0 0
NO1-NO3 0 0 0 0 0 0 0 0 0.1 0 0 0.4 0.1 0.2 0 0 0.2 0.4 0.2 0.1 0.1 0 0 0 0 0 0
NO1-NO5 0 0 0 0 0 0 0 0 0 0 0.1 0 0.8 0 0 0.6 0 0.7 0 0 0 0 0 0 0 0 0
NO1-SE3 0 0 0 0 0 0 0 0 0.1 0 0 0.6 0 0.8 0 0 0.2 0.6 0.2 0.1 0.1 0 0 0 0 0 0
NO2-NL 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0
NO2-NO5 0 0 0 0 0 0 0 0 0 0 0.1 0 0.2 0 0 0.3 0 0.2 0 0 0 0 0 0 0 0 0
NO3-NO4 0 0 0 0 0 0 0 0 0.2 0 0 0.1 0 0 0 0 0.5 0.1 0.2 0.2 0.3 0.1 0 0 0 0 0
NO3-NO5 0 0 0 0 0 0 0 0 0 0 0 0 0.1 0 0 0.1 0 0.1 0 0 0 0 0 0 0 0 0
NO3-SE2 0 0 0 0 0 0 0 0 0.2 0 0 0.4 0 0.1 0 0 0.4 0.4 0.6 0.2 0.2 0.1 0 0 0 0 0
NO4-SE1 0 0 0 0 0 0 0 0 0.6 0 0 0.1 0 0 0 0 0.4 0.1 0.1 0.6 0.5 0.1 0 0 0 0 0
NO4-SE2 0 0 0 0 0 0 0 0 0.1 0 0 0.1 0 0 0 0 0.1 0.1 0.1 0.1 0.2 0 0 0 0 0 0
SE1-SE2 0 0 0 0 0 0 0 0 0.4 0 0 0.1 0 0 0 0 0.5 0.1 0.1 0.3 0.6 0.9 0 0 0 0 0
SE2-SE3 0 0 0 0 0 0 0 0 0.1 0 0 0.6 0 0.2 0 0 0.2 0.6 0.2 0.1 0.1 0 1 0 0 0 0
SE3-SE4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0
SE4-DE 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0
SE4-LT 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0
SE4-PL 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1
Commercial exchange between areas …
… im
pac
t o
n s
ched
ule
d f
low
DK
1-D
E
DK
1-S
E3
DK
1-N
O2
DK
1-D
K2
DK
2-D
E
DK
2-S
E4
FIN
-EE
FIN
-SE
3
FIN
-NO
4
FIN
-SE
1
NO
1-N
O2
NO
1-N
O3
NO
1-N
O5
NO
1-S
E3
NO
2-N
L
NO
2-N
O5
NO
3-N
O4
NO
3-N
O5
NO
3-S
E2
NO
4-S
E1
NO
4-S
E2
SE
1-S
E2
SE
2-S
E3
SE
3-S
E4
SE
4-D
E
SE
4-L
T
SE
4-P
L
DK1-DE 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK1-SE3 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK1-NO2 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK1-DK2 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK2-DE 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DK2-SE4 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FIN-EE 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FIN-SE3 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FIN-NO4 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FIN-SE1 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
NO1-NO2 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
NO1-NO3 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
NO1-NO5 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0
NO1-SE3 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0
NO2-NL 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0
NO2-NO5 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0
NO3-NO4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0
NO3-NO5 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0
NO3-SE2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0
NO4-SE1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0
NO4-SE2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0
SE1-SE2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0
SE2-SE3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0
SE3-SE4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0
SE4-DE 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0
SE4-LT 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0
SE4-PL 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1
Commercial exchange between areas …
… im
pac
t o
n s
che
du
led
flo
w Flow-based CNTC
More or less capacity with FB compared to CNTC?
The aim of the capacity calculation is to provide capacities that create the best possible dispatch All loads covered
Minimizing production costs
Avoiding risks to operational security
FB is a more flexible approach compared to CNTC The "solution space" for FB can form almost any shape
The "solution space" for CNTC is limited by the requirement that all bidding zone borders are considered independently
Export position
of area A
- 400
- 300
- 200
- 100
0
100
200
300
400
- 400 - 300 - 200 100 200 300 400 - 100 0
Export position
of area B
Black line: real limit of system security
Forecasted system state
More or less capacity with FB compared to CNTC?
The aim of the capacity calculation is to provide capacities that create the best possible dispatch All loads covered
Minimizing production costs
Avoiding risks to operational security
FB is a more flexible approach compared to CNTC The "solution space" for FB can form almost any shape
The "solution space" for CNTC is limited by the requirement that all bidding zone borders are considered independently
Export position
of area A
FB
- 400
- 300
- 200
- 100
0
100
200
300
400
- 400 - 300 - 200 100 200 300 400 - 100 0
Export position
of area B
Forecasted system state
Black line: real limit of system security
More or less capacity with FB compared to CNTC?
The aim of the capacity calculation is to provide capacities that create the best possible dispatch All loads covered
Minimizing production costs
Avoiding risks to operational security
FB is a more flexible approach compared to CNTC The "solution space" for FB can form almost any shape
The "solution space" for CNTC is limited by the requirement that all bidding zone borders are considered independently
Export position
of area A
FB
CNTC
- 400
- 300
- 200
- 100
0
100
200
300
400
- 400 - 300 - 200 100 200 300 400 - 100 0
Export position
of area B
Forecasted system state
Black line: real limit of system security
Are internal grid constraints limiting cross-border trade?
Few grid constraints are at the geographic border
The location of grid constraints determined by the total system state: grid topology, loads and generation We don't want to change the bidding zone configuration hour-by-hour
Constraints inside bidding areas mainly affected by cross-border trade
FB doesn't "move" the congestions at all, the PTDFs provide accurate information on how each area impact the constraints
CNTC makes a choice on which cross-border trades can be allocated the capacity of the constraint, constraint still mainly affected by cross border trade
Grid constraints not highly affected by cross border trade not included in capacity calculation
Constraints instead handled by costly remedial actions
(Non-costly remedial actions already included in the capacity calculation)
Can we have FB day-ahead and CNTC intraday?
The planned continuous intraday market cannot use FB initially
There will be a new capacity calculation for the intraday market Based on an updated common grid model
Not only the "remainder" from the day-ahead market as today
The concern is that there will be limited capacity available for intraday FB is a more flexible approach
The FB net positions from day-ahead may put the system in a "corner" where it's there's limited options to create secure CNTCs
This is due to more capacity being made available for the day-ahead market
Reasons/options that mitigate this risk: Reduced uncertainty at the intraday stage
TSOs can expand the CNTC space where it's unlikely to be used will free up initial capacity without significant impact on operational security
CNTC can be continuously recalculated
Export position
of area A
FB
CNTC
- 400
- 300
- 200
- 100
0
100
200
300
400
- 400 - 300 - 200 100 200 300 400 - 100 0
Export position
of area B
Result of the day-ahead market
Reduced uncertainty in the intraday time-frame
Export position
of area A
FB
CNTC
- 400
- 300
- 200
- 100
0
100
200
300
400
- 400 - 300 - 200 100 200 300 400 - 100 0
Export position
of area B
Reduced uncertainty means there may be more capacity available initially
TSOs can expand the CNTC space where it's likely to be used, free up initial capacity
CNTC can be continuously recalculated, making new capacity available in the desired direction
Discard grid constraints unlikely to be binding in the market outcome
Export position
of area A
FB
CNTC
- 400
- 300
- 200
- 100
0
100
200
300
400
- 400 - 300 - 200 100 200 300 400 - 100 0
Export position
of area B
Reduced uncertainty means there may be more capacity available initially
TSOs can expand the CNTC space where it's likely to be used, free up initial capacity
CNTC can be continuously recalculated, making new capacity available in the desired direction
Continuous recalculation of CNTC
Export position
of area A
FB
CNTC
- 400
- 300
- 200
- 100
0
100
200
300
400
- 400 - 300 - 200 100 200 300 400 - 100 0
Export position
of area B
Reduced uncertainty means there may be more capacity available initially
TSOs can expand the CNTC space where it's likely to be used, free up initial capacity
CNTC can be continuously recalculated, making new capacity available in the desired direction
Impact on price forecasts and bids
No impact on bid format
Bids still specified by volume and price per area in all markets
More hour-to-hour variation in available capacity
Both FB and CNTC will better reflect the constantly varying state of the power system compared to current NTC
FB will provide information on available capacity in a new format
PTDF and RAM contain much more information than NTC/CNTC
May impact the tools and methods used for predicting future prices
FB will provide more, but smaller price differences
Prices not caused by congested borders, instead caused by congested grid constraints
All areas receive a price relative to the area's specific impact on the grid constraints
Flow-based
Available margin Area A Area B Area C
A -> B 1000 33 % - 33 % 0
B -> C 1000 33 % 67 % 0
A -> C 1000 67 % 33 % 0
Coordinated net transmission capacity
Max exchange
A -> B 750 MW
B -> C 750 MW
A -> C 750 MW
Prototype capacity calculation and market simulations
The Nordic CCM project have developed a set of prototype tools for coordinated capacity calculation We are currently calculating flow-based parameters, and doing market
simulations
CNTC market simulations just starting, but the CNTC method needs refinements on the rules for efficiently sharing capacity on the borders
Data quality remains an issue Mostly related to the prototype common grid model which is created
specifically for this use
Quality will improve as soon as the real common grid model is in place
Market simulations are conducted using the same algorithm and bid lists used for the day-ahead market
Calculation of maximum exchanges on bidding zone borders
Aim to automate TTC calculations
Calculations based on basic AC load flow and dynamic simulations
Method and tool to calculate maximum exchanges has been developed and tested using SE1-FI border as an example
Tool calculates maximum technical capacities for import and export directions individually bidding zone border by border taking into account following items GSKs Contingencies Operational security limits
The same calculation approach can be used to calculate Fmax values in the FB approach, and cross-zonal capacities in the CNTC
Capacity calculation tool
Input data
CGM GSKs Contingencies
and other rules
Operational security limits (thermal limits, voltage limits, frequency and damping limits)
Load flow analysis Dynamic stability
analysis Maximum cross-zonal
capacity
Other steps in CNTC calculation process
adjusting maximum power exchange using remedial actions
applying rules for avoiding undue discrimination between internal and cross-zonal exchanges
applying rules for efficiently sharing power flow capabilities of different CNEs among different bidding zone borders
taking into account reliability margin and previously allocated cross-zonal capacity
cross-zonal capacities to be given to the market
Agenda
1. Coffee (9.00 – 9.30)
2. Welcome, objective and agenda (9.30 - 9.45), Trond Jensen (Statnett)
3. NordREG presentation (9.45 - 10.15), Johan Roupe (EI)
4. Nordic CCM project and timeline (10.15 - 10.30), Trond Jensen (Statnett)
5. Coffee (10.30 - 10.50)
6. Nordic FB and CNTC methodologies (10.50 - 11.30), Nils Flaten Ræder (Statnett) and Heini Ruohosenmaa (Fingrid)
7. Market results (11.30 - 12.00), Mårten Bergman (Svk)
8. First round of questions and answers (12.00 - 12.30)
9. Lunch (12.30 - 13.30)
10. Market information platform and market information tool (13.30 - 14.00), Mårten Bergman (Svk)
11. CCM proposal process (14.00 - 14.30), Ulrik Møller (Edk)
12. Coffee break (14.30 - 15.00)
13. Second round of questions and answers (15.00 - 16.30)
Disclaimers
Prototype tools/process
Prototype tools have been used for the simulations
Flow Reliability Margins (FRM) are not included
Some known difficulties with the Danish CNE definitions in the first half of 2016
Although operators are consulted in the review stage, they are not personally involved in the FB capacity calculation process yet
Some of the hours (~6 %) in the FB results lacks FB parameters these hours are replaced with NTC values
Prototype Common grid model
The grid models used are not yet the target models. Indeed those are in the process of being implemented. The quality of the grid models is the best we can have at this moment in time; they do not allow for dynamic analysis and detailed voltage/reactive power analysis though.
Merging software for creating the CGM from the IGMs evolves over time. Improvements made for the later weeks have not been applied for the earlier ones
Market simulations
The market simulations are done in the European Power Exchanges’ Simulation Facility by using historical order books
Limited to the Central Northern European market
Critical Network Element (CNE) selection (review and possible removal of non-significantly impacted CNEs) has not been implemented at this stage yet
Objective function of the Price coupling Euphemia
Same price coupling algorithm in both FB and NTC
MAX Welfare =
Subject to constraints
Consumer surplus Producer surplus Congestion revenue
Example of an exchange from a low price area to a high price area
Welfare economic results for Weeks 2-5, 7-8, 14-17, 41-46
-7,000
-5,000
-3,000
-1,000
1,000
3,000
5,000
7,000
-80
-60
-40
-20
0
20
40
60
80
Nordic
Tota
l [kE
UR
]
SEW
per
Sta
keh
old
er [
MEU
R]
Nordic socio-economic welfare , FB compared to NTC
Congestion rent Producer surplus Consumer surplus Total
-1,200-1,000-800-600-400-20002004006008001,0001,200
-40
-30
-20
-10
0
10
20
30
40
2 3 4 5 7 8 14 15 16 17 41 42 43 44 45 46
Tota
l [kE
UR
]
SEW
per
Sta
keh
old
er [
MEU
R] Nordic socio-economic welfare per week, FB compared to NTC
Congestion rent Producer surplus Consumer surplus Total
On an annualized basis the welfare in FB is 12 M€ larger than in NTC
Average prices in all Nordic bidding zones
0
5
10
15
20
25
30
35
40
Nordic DK1 DK2 FIN NO1 NO2 NO3 NO4 NO5 SE1 SE2 SE3 SE4
Average prices in the bidding zones
NTC
FB
-0,4
0,1
-0,5 -0,4 -0,4
0,8
-1,2
-0,3
0,5
-0,9 -0,9 -0,7
-0,5
-1,5
-1,0
-0,5
0,0
0,5
1,0
Nordic DK1 DK2 FIN NO1 NO2 NO3 NO4 NO5 SE1 SE2 SE3 SE4
Difference FB-NTC
Nordic net position per week 2-5, 7-8, 14-17, 41-46 and average
Average Nordic net position (GWh)
-300
-200
-100
0
100
200
300
400
500
2 3 4 5 7 8 14 15 16 17 41 42 43 44 45 46
Net Position, [GWh/week]
NTC FB
136
137
138
139
140
141
142
143
144
145
NTC FB
Economic gain VS grid overloads
The figure shows how the hourly FB results compare to the NTC market outcome
The horizontal axis show the impact on expected grid overloads
The vertical axis show the socio-economic impact
The TSO choice of which CNEs to include in the market coupling will determine the balance between better grid security, and improved economic outcome
Results in this quadrant have both better economic results and lower grid overloads in FB than in NTC
Results in this quadrant have both worse economic results and larger grid overloads in FB than in NTC
FB vs CNTC vs NTC: single hour from week 42
Welfare compared to NTC (k€) CNTC 17 FB 20
Agenda
1. Coffee (9.00 – 9.30)
2. Welcome, objective and agenda (9.30 - 9.45), Trond Jensen (Statnett)
3. NordREG presentation (9.45 - 10.15), Johan Roupe (EI)
4. Nordic CCM project and timeline (10.15 - 10.30), Trond Jensen (Statnett)
5. Coffee (10.30 - 10.50)
6. Nordic FB and CNTC methodologies (10.50 - 11.30), Nils Flaten Ræder (Statnett) and Heini Ruohosenmaa (Fingrid)
7. Market results (11.30 - 12.00), Mårten Bergman (Svk)
8. First round of questions and answers (12.00 - 12.30)
9. Lunch (12.30 - 13.30)
10. Market information platform and market information tool (13.30 - 14.00), Mårten Bergman (Svk)
11. CCM proposal process (14.00 - 14.30), Ulrik Møller (Edk)
12. Coffee break (14.30 - 15.00)
13. Second round of questions and answers (15.00 - 16.30)
Agenda
1. Coffee (9.00 – 9.30)
2. Welcome, objective and agenda (9.30 - 9.45), Trond Jensen (Statnett)
3. NordREG presentation (9.45 - 10.15), Johan Roupe (EI)
4. Nordic CCM project and timeline (10.15 - 10.30), Trond Jensen (Statnett)
5. Coffee (10.30 - 10.50)
6. Nordic FB and CNTC methodologies (10.50 - 11.30), Nils Flaten Ræder (Statnett) and Heini Ruohosenmaa (Fingrid)
7. Market results (11.30 - 12.00), Mårten Bergman (Svk)
8. First round of questions and answers (12.00 - 12.30)
9. Lunch (12.30 - 13.30)
10. Market information platform and market information tool (13.30 - 14.00), Mårten Bergman (Svk)
11. CCM proposal process (14.00 - 14.30), Ulrik Møller (Edk)
12. Coffee break (14.30 - 15.00)
13. Second round of questions and answers (15.00 - 16.30)
Agenda
1. Coffee (9.00 – 9.30)
2. Welcome, objective and agenda (9.30 - 9.45), Trond Jensen (Statnett)
3. NordREG presentation (9.45 - 10.15), Johan Roupe (EI)
4. Nordic CCM project and timeline (10.15 - 10.30), Trond Jensen (Statnett)
5. Coffee (10.30 - 10.50)
6. Nordic FB and CNTC methodologies (10.50 - 11.30), Nils Flaten Ræder (Statnett) and Heini Ruohosenmaa (Fingrid)
7. Market results (11.30 - 12.00), Mårten Bergman (Svk)
8. First round of questions and answers (12.00 - 12.30)
9. Lunch (12.30 - 13.30)
10. Market information platform and market information tool (13.30 - 14.00), Mårten Bergman (Svk)
11. CCM proposal process (14.00 - 14.30), Ulrik Møller (Edk)
12. Coffee break (14.30 - 15.00)
13. Second round of questions and answers (15.00 - 16.30)
Agenda
1. Coffee (9.00 – 9.30)
2. Welcome, objective and agenda (9.30 - 9.45), Trond Jensen (Statnett)
3. NordREG presentation (9.45 - 10.15), Johan Roupe (EI)
4. Nordic CCM project and timeline (10.15 - 10.30), Trond Jensen (Statnett)
5. Coffee (10.30 - 10.50)
6. Nordic FB and CNTC methodologies (10.50 - 11.30), Nils Flaten Ræder (Statnett) and Heini Ruohosenmaa (Fingrid)
7. Market results (11.30 - 12.00), Mårten Bergman (Svk)
8. First round of questions and answers (12.00 - 12.30)
9. Lunch (12.30 - 13.30)
10. Market information platform and market information tool (13.30 - 14.00), Mårten Bergman (Svk)
11. CCM proposal process (14.00 - 14.30), Ulrik Møller (Edk)
12. Coffee break (14.30 - 15.00)
13. Second round of questions and answers (15.00 - 16.30)
Interfaces – External Stakeholders
Stakeholder Group Group with nominated members from industry and NRAs Detailed discussions and exchanges
Stakeholder Forum Open for all stakeholders
Broader information forums
Stakeholder Newsletter 1 issued in 2016
4 issues/year from 2017
Stakeholder Information Platform Web platform for information exchange Open for all stakeholders
Interactive discussion forum
Information Platform
Stakeholder Information Platform Web platform for information exchange
Open for all stakeholders
Interactive discussion forum
To gain access: Send mail to: [email protected]
Subject: User registration NCCM SH info platform
Content:
Name, E-mail & Telephone
The Nordic Capacity Calculation Methodology (CCM) project
Stakeholder Information Tool CCM Stakeholder Forum – Stockholm
8 February 2017
Stakeholder Tool
Tool for examining the effect on flows/possible net positions from PTDFs
CNEs are fully anonymized – randomized numbering
This is a first draft – comments/suggestions are welcome
Stakeholder tool
GUI - Test feasible net positions
cells that can be editted
the white cells indicate the Nordic synchronous area; the grey cells the DK1 synchronous area
the orange texts indicate that the cell value is computed from another. Indeed, this is applied for DC cables: the power injected on one side is emitted at the other
A check on the power balance in each synchronous area is performed;
GUI - Test feasible net positions If the net positions, that you entered, fit within the FB domain, the message that 'Transmission system not congested' appears. Otherwise, the message 'Transmission system congested' appears in red.
The net position, that you entered, appears in the Nordic map in bold. Above this value, the maximum net position (feasible within the FB domain) is shown. Below this value the min net position (feasible within the FB domain) is shown.
The border flows (according to the FB model), resulting from the net positions that you entered, are shown in the map.
FB parameters
the net positions that you filled in on the 'GUI'
the flows induced on the CNEs (PTDF matrix * net positions)
is the CNE congested? Or in other words: is the resulting flow larger than the RAM ( remaining available margin, the flow that is allowed to be used by the market transactions)?
the PTDF factors of the CNEs
Min/Max Net Positions & Border Flows
The tool includes information on Min/Max Net Position per bidding zone Not simultaneously feasible
The border flows (according to the FB model), resulting from the net positions that you entered, are computed. Those values are presented in the 'GUI'
Agenda
1. Coffee (9.00 – 9.30)
2. Welcome, objective and agenda (9.30 - 9.45), Trond Jensen (Statnett)
3. NordREG presentation (9.45 - 10.15), Johan Roupe (EI)
4. Nordic CCM project and timeline (10.15 - 10.30), Trond Jensen (Statnett)
5. Coffee (10.30 - 10.50)
6. Nordic FB and CNTC methodologies (10.50 - 11.30), Nils Flaten Ræder (Statnett) and Heini Ruohosenmaa (Fingrid)
7. Market results (11.30 - 12.00), Mårten Bergman (Svk)
8. First round of questions and answers (12.00 - 12.30)
9. Lunch (12.30 - 13.30)
10. Market information platform and market information tool (13.30 - 14.00), Mårten Bergman (Svk)
11. CCM proposal process (14.00 - 14.30), Ulrik Møller (Edk)
12. Coffee break (14.30 - 15.00)
13. Second round of questions and answers (15.00 - 16.30)
Timeline for the NRA proposal
2017
Today
Sep Nov 2017 Mar May Jul Sep
Stakeholder Forum
Feb 8
Workshop (Stakeholder Forum)
Apr 19
Stakeholder Forum
Sep 7
Submission of final CCM proposal to NRAs
Sep 18
Sep 1 - Feb 21 Develop supporting document
Feb 22 - Mar 28 Internal TSO consultation and approval of proposed CCM
Apr 3 - May 15 Public consultation
Apr 3 - Jun 30Develop the legal CCM proposal (legally-binding
document)
Jul 3 - Aug 18 Internal TSO consultation
Aug 21 - Sep 18Finalization of the CCM
proposal
Jul 1 - Aug 15 Holiday period
Comparison FB/CNTC/NTC
Art 9.9. Proposed timeline for implementation
Art 9.9 Description of the expected impact on the objective
Art 21.1.C Methodology for validation of Cross Zonal capacity
Art 21.2 Frequency for updating ID capacity
Content of the supporting document and the CCM proposal
Art 21 Legal document: The proposal for a CCM shall (at least) include
Art 21.1.A Methodologies for the calculation of input to the CC
Methodologies for: i. Determine Reliability Margins ii. Determine Operational Security Limits ii. Determine Contingencies ii. Determine Allocation Constraints iii. Determine GSK iv. Determine Remedial Actions to be used
Art 21.1.B Description of the applied CCM
A Mathematical description of the i. Applied CCM with different inputs v. FB: The calculation of PTDFs and RAMs Rules for: ii. Avoiding undue discrimination iii. Previously allocated Cross Zonal capacity iv. Applying Remedial Actions to adjust flow on CNEs vi. CNTC: Calculating Cross Zonal capacity and efficiently sharing CNE cap on Bidding Zone Borders vii. Efficiently sharing CNE cap on different CCRs when relevant
Supporting document: Proposed methodology and impact assessment
21.1.A Methodologies for the calculation of input to the CC
21.1.B Description of the applied CCM
Art 21.1.C Methodology for validation of
Cross Zonal capacity
Art 21.2 Frequency for updating ID capacity
Art 21.3 Fall-back procedure
Art 9.9 Proposed timeline for implementation
Art 9.9 Description of the expected impact
on the objective
Description of the alternative CCM
Art 21.3 Fall-back procedure
Impacts on other markets
Bidding zone delimitation
Non-intuitive flows
Congestion Income Distribution (if FB)
Transparency
Long-term investment decisions
Agenda
1. Coffee (9.00 – 9.30)
2. Welcome, objective and agenda (9.30 - 9.45), Trond Jensen (Statnett)
3. NordREG presentation (9.45 - 10.15), Johan Roupe (EI)
4. Nordic CCM project and timeline (10.15 - 10.30), Trond Jensen (Statnett)
5. Coffee (10.30 - 10.50)
6. Nordic FB and CNTC methodologies (10.50 - 11.30), Nils Flaten Ræder (Statnett) and Heini Ruohosenmaa (Fingrid)
7. Market results (11.30 - 12.00), Mårten Bergman (Svk)
8. First round of questions and answers (12.00 - 12.30)
9. Lunch (12.30 - 13.30)
10. Market information platform and market information tool (13.30 - 14.00), Mårten Bergman (Svk)
11. CCM proposal process (14.00 - 14.30), Ulrik Møller (Edk)
12. Coffee break (14.30 - 15.00)
13. Second round of questions and answers (15.00 - 16.30)
Agenda
1. Coffee (9.00 – 9.30)
2. Welcome, objective and agenda (9.30 - 9.45), Trond Jensen (Statnett)
3. NordREG presentation (9.45 - 10.15), Johan Roupe (EI)
4. Nordic CCM project and timeline (10.15 - 10.30), Trond Jensen (Statnett)
5. Coffee (10.30 - 10.50)
6. Nordic FB and CNTC methodologies (10.50 - 11.30), Nils Flaten Ræder (Statnett) and Heini Ruohosenmaa (Fingrid)
7. Market results (11.30 - 12.00), Mårten Bergman (Svk)
8. First round of questions and answers (12.00 - 12.30)
9. Lunch (12.30 - 13.30)
10. Market information platform and market information tool (13.30 - 14.00), Mårten Bergman (Svk)
11. CCM proposal process (14.00 - 14.30), Ulrik Møller (Edk)
12. Coffee break (14.30 - 15.00)
13. Second round of questions and answers (15.00 - 16.30)
FB vs NTC: single hour from week 41
The Nordic welfare is 3k€ better in FB than in NTC
The total market welfare is 7k€ better in FB than in NTC
For the week as a whole Nordic gain is 600k€, and the market wide gain is 1M€