  • The SDRGC Imagery Subcommittee presents

    The San Diego Sub-Regional Imagery Acquisition ProjectStatus and Next StepsJune 24, 2008

  • Imagery Subcommittee IntroductionsWendy Flynn, City of EncinitasMettja Kuna, City of San MarcosKarl Von Schlieder, City of CarlsbadSue Carnevale, SANDAGGrace Chung, SANDAG

  • Imagery Subcommittee AssistanceCheryl Mason, SANDAG Service BureauDrew Decker, USGSPaul Hardwick, SDSURF and SDRGCBarbara Kent, CALTRANS and SDRGCPat Landrum, CALTRANS

  • Brief History of Past Sub-Regional Imagery Projects2001 effort led by San Diego County Water AuthorityMethods: Traditional photogrammetry; film-based photography.Deliverables: 6 orthos, 2 ft. contours.Administration: Separate contracts.

    2004 effort led by Chula VistaMethods: Traditional photogrammetry; film-based photography.Deliverables: 6 orthos, 2 ft. contours.Administration: One joint contract.

    2005 effort led by the City of San DiegoMethods: LiDAR; film-based photography.Deliverables: 3 orthos, 2 ft. contours, LiDAR generated terrain model.Administration: Separate contracts.

  • Project Background and Current StatusProject Specifications and Requirements

    Current Caveats and Assumptions

    Imagery Subcommittee Efforts To-Date

  • Project Specifications4" digital true-color orthophotos, Delivered in 2000x3000 ft GeoTIFF tiles covering an agency's selected area of interest, Captured with a digital matrix array camera, With positional accuracy to be sufficient for producing 1 = 100 ft scale planimetric mapping (ASPRS Class 1Accuracy Standards for Large Scale Maps), Delivered in CA Stateplane coordinates NAD83, 1993 HARN adjustment, Vertical datum NAVD88, and color-balanced across the entire project area. These are not true orthos and may contain an acceptable amount of building lean.

  • 4 resolution true-color digital imagery example

  • Project RequirementsA high resolution terrain model covering the entire project area is required for this project.

    Agencies who already have an existing high resolution terrain model (e.g. LiDAR) can submit their DTM to the select vendor for use in the project.

    Agencies who do not have an existing high resolution terrain model will need to acquire one for their AOI as part of this project in order to rectify the imagery to the required positional accuracy specs.

  • Current Terrain Date Merrick 2005 LIDAR Coverage

  • Current Caveats and AssumptionsVendors can merge high resolution DTMs in different formats to arrive at a uniform surface to produce orthorectified imagery within the required positional accuracy specs.

    Vendors can produce on-the-fly autocorrelated terrain models in areas where no terrain models exist for image orthorectification, but the process may not meet the required positional accuracy specs or be of sufficient quality to generate 2-foot contours.

    Agencies who need terrain data may opt to use the autocorrelated terrain method at a lower cost, or have the selected vendor create a more accurate terrain model for better orthorectification at a higher cost. The latter option would include the terrain data as a deliverable.

    Does SD Countys existing control monumentation cover the project area? Is it accurate enough? Will vendor set up panels for ground control? Are these required for digital imagery acquisition?

  • Imagery Subcommittee Efforts To-DateSeveral meetings conducted.

    Agencies contacted to select tiles.

    Tile selections map created. Some agencies still need to select their tiles.

    First draft of RFP completed.

    Matrix developed to understand partner agency needs and possible constraints. Some agencies still need to fill out the matrix.

    SANDAG approached to act as Administrative lead.

  • Partner Agency Feedback To-DateThese Agencies Are IN (e.g. No Constraints at this time):Airport Authority, Carlsbad, Coronado, Encinitas, Imperial Beach, Oceanside, Poway

    These Agencies Have Constraints (DTM, Cost, and/or Admin):Borrego Water District, Chula Vista, County Water Authority, Escondido, San Marcos, SDG&E, Sweetwater, USFWS, Vallecitos Water District

    These Agencies Have Not Yet Completed the Matrix:Centre City Development, City of San Diego, Del Mar, National City, Navy, Port District, Santee, Solana Beach, Vista, Wild Animal Park These Agencies Have Decided Not to Participate:CALTRANS, County of San Diego, El Cajon, La Mesa, Lemon Grove, LWWD, NCTD, OMWD, SANDAG, Valley Center MWD

  • Thanks for your time and attention.SDRGC Imagery Subcommittee