Upload
crystal-johns
View
222
Download
3
Embed Size (px)
Citation preview
THE SOUTH WESTERN RAILWAY
Twickenham Station Platform Improvements
29th January 2014 - Twickenham Stadium
THE SOUTH WESTERN RAILWAY
Agenda
• Overview of scheme• Construction methodology• Programme• Next steps
THE SOUTH WESTERN RAILWAY
Context
• Key commuter station and supporting events at the stadium • Subject to final agreement the following combined multiple
funding sources have been indentified; – National Stations Improvement Programmes – Network Rail Discretionary Fund – Network Rail Renewals funding – Greater London Authority
• Separation of the platform level works to support the Rugby World Cup
• Solum works to progress separately and are not part of this package
THE SOUTH WESTERN RAILWAY
Platform level work scope
• Replacement platform buildings • New lining for canopies • Replacement events day footbridge • Platform resurfacing • New platform edge copers• Stair lifts (existing staircases)• Platform 2 widening to 3m • Repair & paint public footbridge• General paint/refurbishment • New canopies London End • St Marys terrace stairwell upgrade
THE SOUTH WESTERN RAILWAY
New platform level facilities
Brute route ramp modified for passenger access/egress
Existing access from platform 19 to 20
Possible extra access from platform 19 to 20
THE SOUTH WESTERN RAILWAY
Public Footbridge and New Events Bridge
Brute route ramp modified for passenger access/egress
Existing access from platform 19 to 20
Possible extra access from platform 19 to 20
THE SOUTH WESTERN RAILWAY
Construction Methodology • Maximises use of ‘abnormal’ possessions to minimise ‘out of
hours’ working i.e. Week 9 replacement coper works is equivalent of 6 weeks of weekday nights
• Co-ordinate as many of the ‘noisy’ & ‘dusty’ activities i.e. removal of structures into the three ‘abnormal’ possessions
• Use of acoustic screens to contain plant noise• Use of mains power to supply site accommodation – saves need
for 24/7 generator• Wet cutting of materials to suppress dust• Full encapsulation of Public Footbridge so works can be
completed in daytime hours
THE SOUTH WESTERN RAILWAY
Programme• January – February 2014
– Permitted development notification of works falling under Part 17 of the General Permitted Development Order” and “Request for Prior Approval for works falling under Part 11 of the General Permitted Development Order
– Removal of tree and de-vegetation works • March – April 2014
– Set up site– New events footbridge enabling works
• May 2014 - Key possession 75 Hours 24th-26th May 2014 – Bridge delivered to site – car park closed from 21st May– Removal of existing events footbridge – Lift in new events footbridge – New platform copers at country end – Scaffold & encapsulation to public footbridge and commence repairs– Open new secondary footbridge 27th May
• June – August 2014 Key 51 hour possession 7th-8th June – New platform copers at London end– Removal of platform 2/3 building– Construct new platform 2/3 building– Platform 2/3 canopy works
THE SOUTH WESTERN RAILWAY
Programme• September – December 2014
– Key 52 hour possession 20th -21st September • Remove scaffold encapsulation to public footbridge• Removal of platform 4/5 building• Platform resurfacing 2/3
– Public foot bridge reopens 22nd September– Platform 4/5 works 22nd September to 19th December
• Construct platform new building • Platform canopy works • Platform resurfacing 4/5
• April – July 2015– World cup final preparation
• Painting and final preparation for World Cup