Upload
morris-edwards
View
216
Download
2
Tags:
Embed Size (px)
Citation preview
The Stripping Foil Test Stand in the Linac4 Transfer Line
R. Noulibos, P. van Trappen, W. WeteringsCERN, European Organization for Nuclear Research, CH-1211 Geneva 23, Switzerland
3The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Stripping Foil Test StandA stripping foil test stand will be installed in the Linac4 transfer line allowing tests with a 160 MeV H− Linac4 commissioning beam:
• Testing from 2015, prior to final PSB installation (>2018)• The foil changing mechanism as well as the interlocking
functions can be assessed;• Gain experience with these very fragile foils;• Test different foil materials and thicknesses;• Evaluate the lifetime of the foils and foil holders;• Measure the stripping efficiency and emittance growth of
the beam through the stripping foil.
01/09/2014W. Weterings
4The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
BCT + BLM BCT
Profile Monitors Stripping Foil Test Stand Location
SourceDTLCCDTLPIMSDump
3 MeV50 MeV100 MeV160 MeV
Linac4 Layout
01/09/2014W. Weterings
Layout & Instrumentation
• Stripping efficiency is measured by current decrease between cross-calibrated Beam Current Transformers (BCT) and by taking the electrical signal from the foil holder.
• Emittance growth is estimated using Secondary Electron Monitor (SEM) profile.
• The upstream defocusing quadrupole (QD) is used to vary the beam size.
Transfer Line to PSBTransfer Lineto PSB
QF QD
5The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Test possibilities• Stripping efficiency by measuring the BCT current before and
after the foil (resolution of 0.1 mA).• Beam losses at the level of few 109 protons are expected for
1014 H− nominal intensity from L4.• A rough estimate of the emittance growth through the stripping
foil could be obtained by using the SEM profile grids.• The PSB injection worst failure scenario can be simulated by
hitting the foil with a 400 µs pulse and minimum beam size.• Many mechanical cycles and movement of the foil, with and
without beam to test rigidity of different types of foils.• The BTV system will be tested, including correct filters selection
for beam measurements over a large range of beam intensities as well as the Foil – BTV screen interference interlock.
01/09/2014W. Weterings
6The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Foil Handling Mechanism
01/09/2014W. Weterings
Stepping motor
Magneticcoupling
Mirrors andOptical Filters
Radiation HardCamera
Foil Changer Beam ObservationSystem (BTV) with
Screen in BeamRear View
Showing mirror
7The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Foil Handling Mechanism
01/09/2014W. Weterings
Stepping motor
Magneticcoupling
Mirrors andOptical Filters
Radiation HardCamera
Foil Changer
Beam
Beam ObservationSystem (BTV) withScreen Retracted
Rear ViewShowing mirror
8The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Foil Handling Mechanism
01/09/2014W. Weterings
Stepping motor
Magneticcoupling
Mirrors andOptical Filters
Radiation HardCamera
Beam ObservationSystem (BTV) withScreen retracted
Foil ChangerVacuumChamber
9The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Foil Handling Mechanism
01/09/2014W. Weterings
Final configuration to be installed in Linac4 transfer line (L4T)
sector 1.1
10The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Configuration L4T sector 1.1
01/09/2014W. Weterings
To optimise intervention time and avoid foil damage due to differential pressure, the system is installed in a dedicated vacuum sector.
VacuumValve
VacuumValve
Beam Current Transformer (BCT)
Stripping Foil Test Stand
Beam
W. Weterings11
The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Tunnel Location
01/09/2014
W. Weterings12
The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Tunnel Location
01/09/2014
Technology Department Blanc assembly – Required Space
~ 7 meter
~ 4
mete
r
Create the restricted environment with concrete blocks and/or wood panels
‘Mock-up’ dipoles in case BHZ are not available
Technology Department Blanc assembly – Minimum Space
~ 4 meter
~ 5
mete
r
‘Mock-up’dipoles ends
Create the restricted environment with concrete blocks and/or wood panels
W. Weterings15
The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Mock-Up building 355
01/09/2014
W. Weterings16
The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Mock-Up building 355
01/09/2014
W. Weterings17
The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Mock-Up building 355
01/09/2014
W. Weterings18
The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Mock-Up building 355
01/09/2014
W. Weterings19
The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Mock-Up building 355
01/09/2014
W. Weterings20
The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Mock-Up building 355
01/09/2014
21The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
STR mechanism prototype status
16/12/2014
R. Noulibos
- All parts manufactured and modified- Ready for 2nd assembly and tests
1104 mm Prototype progression 541.5 mm Foil Loader progression
- Most of parts manufactured - Ready for assembly and tests
January 2015
Courtesy of Remi GUEYDAN
- Prototype 1104mm has been completely dismantled
- Modifications have been done after tests
- Assembly has started for new tests in January 2015
22The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
Study of Magnetic coupling replacement
16/12/2014
R. Noulibos
Magnetic coupling
Present Drive
Length : 80mmOutside diameter : 35mm
LHC BTVMechanism
Drive Study (in progress)
Length : 80mmOutside diameter : 35mm
Goal: overcome lack of precision due to magnetic drive
LHC BTVMechanism
23The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
L4 STR test stand & HST Status
16/12/2014
R. Noulibos
STR for
Test Stand
STR for HST
_ All manufacturing drawings are all produced_ A few drawings to control
24The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
STR test stand & HST Tanks
16/12/2014
R. Noulibos
With new shape for Inconel Chambers
_ Machining finished
_ Electron beam welding 1st week of January
_ Deadline : Dec. 2014 but…. dedicated milling machine breakdown 4 weeks
25The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
STR test stand & HST tanks
16/12/2014
R. Noulibos
Flanges still to be machined
26The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
STR test stand & HST Loaders
16/12/2014
R. Noulibos
_ Delivery of loader parts: 2nd week of January
_ Assembly ready for tests: 1st week of February
_ BI Mechanisms Delivery ?
Linac 4 Planning
• Commissioning phases contain• RF Conditioning• Connection of the beam line (vacuum , survey)• Hardware Tests (power converters, magnets)• LLRF calibrating• Beam Commissioning
2014-11-17 EDMS 1437718 J. Coupard EN-MEF 27
Installation Commissioning50 MeV
Commissioning100 MeV
Commissioning160 MeV
Reliability Run
Half Sector Test
5 months 4 weeks 5 weeks3 months 3 months
YETSReady for 50 MeV protons
28The Stripping Foil Test Stand in theLinac4 Transfer Line
INTDS2014
STR Planning Jan 2015 :
• Tests of 1104mm band prototype improvements for precision• Assembly of Test stand & HST short loaders (541mm band)
Feb - Mar 2015 : • Lab tests with short loaders in L4 Test Stand vacuum tank
Apr 2015 : • Lab tests with BI instrumentation mechanism in L4 Test Stand
May 2015 : • Installation of STR Test Stand in Linac 4
Jun-Jul 2015 : • Lab tests with short loaders in L4 HST vacuum tank
Aug-Sep 2015 : • Installation of STR HST in Linac 4
Jan-Feb 2016 : • Tests of STR HST in Linac 4
16/12/2014
R. Noulibos