107
1 THE UNITED REPUBLIC OF TANZANIA MINISTRY OF FINANCE PUBLIC FINANCIAL MANAGEMENT REFORM PROGRAMME (PFMRP PHASE IV) MID YEAR PROGRESS REPORT FOR FY 2013/14 (PERIOD: JULY DECEMBER 2013) CONTACT: Permanent Secretary Ministry of Finance P.O. Box 9111 Dar es Salaam June, 2014

THE UNITED REPUBLIC OF TANZANIA MINISTRY OF FINANCE · 2015. 8. 13. · 1 THE UNITED REPUBLIC OF TANZANIA MINISTRY OF FINANCE PUBLIC FINANCIAL MANAGEMENT REFORM PROGRAMME (PFMRP PHASE

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

  • 1

    THE UNITED REPUBLIC OF TANZANIA

    MINISTRY OF FINANCE

    PUBLIC FINANCIAL MANAGEMENT REFORM PROGRAMME

    (PFMRP PHASE IV)

    MID – YEAR PROGRESS REPORT FOR FY 2013/14

    (PERIOD: JULY – DECEMBER 2013)

    CONTACT:

    Permanent Secretary

    Ministry of Finance

    P.O. Box 9111

    Dar es Salaam

    June, 2014

  • 2

    TABLE OF CONTENTS

    LIST OF ABBREVIATIONS ................................................................................................................................ 3

    Executive Summary................................................................................................................................................ 5

    Chapter 1.0 BACKGROUND AND INTRODUCTION........................................................................................ 7

    Chapter 2.0 PROGRESS ON IMPLEMENTATION OF PLANNED ACTIVITIES .......................................... 11

    Chapter 3.0 BUDGET EXECUTION .................................................................................................................. 25

    Chapter 4.0 CHALLENGES AND RECOMMENDATIONS FOR NEXT PERIOD ...................................... 31

    Annexes:

    a) Annex 1: Detailed assessment of milestone status as at Dec 2013 based on M&E Framework for

    2012 – 2017..................................................................................... 32

    b) Annex 2: Fund use by milestone for the mid-year 2013/2014 ................................... 62

    c) Annex 3: Procurement progress report for the mid-year 2013/2014.......................... 101

  • 3

    LIST OF ABBREVIATIONS

    AG Attorney General

    CAG Controller and Auditor General

    FY Financial Year

    ICT Information & Communication Technology

    IPSAs International Public Sector Accounting Standards

    LAAC Local Authority Accounts Committee

    LGAs Local Government Authorities

    JSC Joint Steering Committee

    KRA Key Result Area

    MDAs Ministries, Departments and Agencies

    M&E Monitoring and Evaluation

    MIS Management Information System

    MKUKUTA Mkakati wa Kukuza Uchumi na Kupunguza Umaskini Tanzania

    MoF Ministry of Finance

    MTEF Medium Term Expenditure Framework

    PAC Public Accounts Committee

    PEFA Public Expenditure Framework for Assessment

    PFMRP Public Financial Management Reform Programme

    PMU Procurement Management Unit

    PMIS Procurement Management Information System

    PMORALG Prime Minister’s Office Regional Administration and Local Government

    PO-PC President’s Office – Planning Commission

    PO- PSM President’s Office – Public Service Management

    RSs Regional Secretariat’s

    SMTB Secretary for Ministerial Tender Board

    TRA Tanzania Revenue Authority

    TRMIS Treasury Registrar Management Information System

    TWG Technical Working Group

  • 4

    EXECUTIVE SUMMARY

    This report covers the period of first half of the FY 2013/14 in the second year of PFMRP Phase IV

    implementation which was launched in June 2012. PFMRP Phase IV complements efforts to realize

    national policy objectives stated in Tanzania Development Vision 2025, Five Year Development Plan

    (FYDP) 2011/12-2015/16 and MKUKUTA/MKUZA II by ensuring achievement of the following:

    (i) Economic growth and poverty reduction achieved through policy-based budget management and

    resource mobilization and allocation, improved fiscal discipline and sustainable budget

    balance;

    (ii) Service delivery improvement through the introduction of result-based management, program

    based budgets, accountability and performance audits;

    (iii) Good governance through improved transparency, accountability and efficient controls.

    PFMRP IV is designed to be an enabler towards enhancing revenue mobilization; improving planning

    and budgeting; ensuring transparency, accountability, efficiency and effectiveness in the use of

    resources and implementation will be through five Key Results Areas which are: Revenue management;

    Budget and Planning; Budget execution, Transparency and Accountability; Budget Control and

    Oversight; and Change management, Program Monitoring and Communication. Table 1.1 gives a

    summary of the KRA overview.

    The approved budget for FY 2013/14 is Tshs. 46,398,324,415 out of which Tshs. 2,730,783,800 are

    Project funds, Tshs. 22,557,295,000 local Government contribution and Tshs.21, 110,245,615 Basket

    Funds. As at Dec 2013, a total of Tshs.14,073,082,040 was released out of which Tshs. 3,000,415,000

    from GoT; Tshs.961,301,040 from Project fund and Tshs. 10,111,366,000 from Basket Fund. Actual

    expenditure and commitment as at 31st December, 2013 amounted to Tshs. 15,124,212,175 being 107%

    of the fund released1. Expenditure by source was GoT Tshs. 9,591,295,774 equivalent to 68% of the

    released funds; Project Tshs. 509,910,857 being 3.6% of the released funds and Basket Fund Tshs.

    5,023,005,545 being 36% of the released funds.

    1 Expenditure and Commitment include commitment of GoT for construction NAO Headquarters in Dodoma three years ago

    and the full amount is yet to be released.

  • 5

    On the part of procurement, on 31st December, 2013 total procurement amounted to Tshs.

    19,378,000,000 equivalent to 73% of the total planned procurements, all at different stages of

    procurement process. Postponed procurement activities amounted to Tshs. 1,175,000,000 which

    includes Tshs. 950,000,000 and Tshs. 225,000,000 which were planned to be used to procure

    communication network equipment and software for integration of systems respectively. NAO is

    implementing construction works for regional offices in Dodoma, Rukwa; Mara and Iringa the total

    budgeted amount was Tshs. 13,650,000,000. Activities estimated to costs Tshs. 6,031,080,000

    representing 25% of the total estimated had not been initiated. Most of them will be procured in the

    second half of the financial year. Detailed procurement progress report is displayed under Annex 3.

    The programme recorded fairly satisfactory progress whereby 28 milestones (out of 153) were

    achieved while 101 milestones were on track and 24 milestones (16%) recorded no progress. Key

    achievements during the period include submission of draft bills (VAT and Tax Administration) to

    Cabinet secretariat; draft of national procurement policy draft; installation of asset management

    software; capacity building for internal audit as well as external audit functions (NAOT); modification

    of server room at MOF to prepare for ICT integration and finalization of action plan for streamlining

    and rationalizing the national processes and systems for intergovernmental transfers to LGAs.

    Though it is not a milestone under PFMRPIV M&E framework, one of the most notable achievements

    of the period was the undertaking and finalization of PEFA covering Central Government. The report

    revealed steady improvement in PFM systems since the 2010 PEFA assessment with a significant

    influence from PFMRP implementation. Out of 31 PIs, 12 ratings improved, 5 are in process of

    improving, 9 PIs have not changed and 2 have fallen. Weaknesses revealed in the PEFA exercise

    resulted into fine-tuning of the PFMRPIV M&E framework which was one of the key objectives of the

    Sept 2013 Joint Supervision Mission. New milestones were identified; others were merged while others

    were improved to make them more “SMART”.

    Report Layout

    This report comprises of four chapters: Chapter one provides background information and introduction; Chapter

    two covers progress on implementation of the planned activities for six months (July–December) 2013; Chapter

    three reports the budget execution and Chapter four highlights on challenges and recommendations for next

    period of implementation. Annex 1 give detailed assessment of milestone status as at the end of December, 2013

    based on M&E Framework for 2012 – 2017; annex 2 gives a detailed of financial status per component as of

    December 2013 and 3: Procurement Progress report for the period ended December, 2013.

  • 6

    CHAPTER ONE

    INTRODUCTION

    1.0 Introduction

    PFMRP Phase IV which was launched in June 2012 complements efforts to achieve national policy

    objectives stated in Tanzania Development Vision 2025, Five Year Development Plan (FYDP) 2011/12-

    2015/16 and MKUKUTA/MKUZA II by ensuring achievement of the following:

    (i) Economic growth and poverty reduction achieved through policy-based budget

    management and resource mobilization and allocation, improved fiscal discipline and

    sustainable budget balance;

    (ii) Service delivery improvement through the introduction of result-based management,

    program based budgets, accountability and performance audits;

    (iii) Good governance through improved transparency, accountability and efficient controls.

    PFMRP IV is designed to be an enabler towards enhancing revenue mobilization, improving planning

    and budgeting; ensuring transparency; accountability; efficiency and effectiveness in the use of

    resources and implementation will be through five Key Results Areas which are: Revenue management;

    Budget and Planning; Budget execution, Transparency and Accountability; Budget Control and

    Oversight; and Change management, Program Monitoring and Communication. Table 1.1 gives a

    summary of KRA overview.

    The Public Financial Management Reform Program is implemented in line with the on-going reforms in

    the Public Sector which aim at improved performance, efficiency and effectiveness in service delivery

    for sustainable economic growth. In doing so, PFMRP IV will address interventions which will be:

    i. Comprehensive to include the various key reform activities in the PFM systems as well as the

    cross-cutting issues related to capacity building, improving infrastructure for service delivery,

    and reviewing the institutional policy and regulatory frameworks;

    ii. Captured in a well defined Monitoring and Evaluation framework, sequenced to manage

    priorities and ensure a more accurate cash forecasting and achievement of results;

    iii. Linked and inter-dependent with clear demarcation of responsibilities and accountability;

  • 7

    iv. Better standardized and automated systems to ensure attainment of desired results in financial

    recording and reporting;

    v. Well managed, with effective institutional arrangement to support implementation of the

    programme;

    vi. Focused, aiming at supporting agencies and initiatives which are likely to have a great cross

    cutting impact on the PFM system.

    Table 1.1 KRA and components overview

    Key Result Area (KRA) Major Component,

    Department and KRA-

    TWG

    KRA 1: Revenue Management

    Leader: CPAD

    Focus: improving revenue forecasting and resources mobilization and

    reviewing & streamlining existing revenue policies, laws and regulations.

    The intervention aims at developing appropriate model for revenue

    forecasting to improve cash flow forecasting to spending units. Also the

    KRA will continue to improve external resource management, review

    retention schemes and enhance capacity for managing public investments.

    1. CPAD – MoF

    2. TR - MoF

    3. PMO-RALG

    4. External Finance -

    MoF

    5. MDAs

    KRA 2:Planning and Budgeting

    Leader: BC

    Focus: improving macro-fiscal policy, planning, MTEF credibility,

    enhancing budget classification by adopting GFS 2001 and CoFoG

    standards, facilitate program based budgeting, broadening the scope of the

    chart of accounts, enhancing monitoring, reporting and accountability and

    review of the Medium Term Strategic Planning & Budgeting Manual

    (MTSPBM) to enable the national development planning and budgeting

    system to articulate national policy priority targets with the desired

    institutional results.

    1. CB – MoF

    2. CPAD – MoF

    3. PMO-RALG

  • 8

    KRA 3: Budget Execution, Transparency and Accountability

    Leader: ACCGEN

    Focus: achieving greater predictability of resources to spending units;

    strengthening capacity on procurement, cash and debt management; and

    improving the scope and quality of financial recording and reporting

    1. PPRA

    2. PPPD

    3. ACCGEN - MoF

    4. CPAD - MoF

    5. DGAM - MoF

    KRA 4: Budget Control and Oversight

    Leader: IAG

    Focus: strengthening capacity on audit functions (internal and external) as

    well as oversight function of the Parliament. The interventions involves

    providing technical guidance and capacity building to MDAs and LGAs in

    the areas of internal audit and to facilitate timely independent external

    examination of financial and performance auditing and report to the public

    1. IAG - MoF

    2. NAO (and

    Parliament PACs)

    3. TR

    KRA 5:Change Management Programme Monitoring and

    Communication

    Leader: DPD

    Focus: cross cutting issues including capacity building on change

    management, Monitoring and Evaluation, stakeholders’ communication,

    coordination and leadership for efficient and effective programme

    implementation.

    1. DFMIS - MoF

    2. GCU - MoF

    3. DPD – MoF

    4. PMO – RALG

    5. ACGEN - MoF

    6. DAHRM - MoF

    7. Zanzibar

  • 9

    CHAPTER TWO

    PROGRESS ON IMPLEMENTATION OF PLANNED ACTIVITIES

    There is notable progress with regard to some milestones, but the report also highlights some delays in

    implementation in other milestones and reveals that other milestones remain at risk for implementation

    if remedial action is not taken.

    2.1 Highlights on Targets/Outputs and Implementation Status of Milestones as per M&E

    Framework

    The number of assessed milestones has been reduced because some milestones have been merged, a few

    new milestones have been created, the implementation of which will commence during FY 2014/15. The

    number of milestones has been reduced from 167 to 153. Thus, the review was done on the 153

    milestones budgeted for implementation in FY 2013/14 showed that, 28 milestones (18%) had been

    achieved. However, 101 milestones (66%) recorded a satisfactory implementation progress (on track)

    while 9 milestones (6%) are pending, 13 milestones (9%) delayed in implementation and 2 (1%) are at

    risk. Pending and delayed milestones were dependent on the accomplishment of other milestones. For

    milestones reliant on diagnostic work/studies, the formulations of action plans for the implementation of

    the recommendations are an example for delayed progress. Status of implementation of milestones per

    KRA as at 31st December, 2013 is displayed in Table 1 below and the detailed information on each

    milestone is outlined in Annex 1. Progress toward achieving the output under each KRA is presented in

    the next part.

    Table 1: Cumulative Milestone Status for FY 2013/14

    KRA Achieved On Track Pending Delayed At Risk Total

    KRA 1 - 17 1 - 1 19

    KRA 2 2 8 5 3 - 18

    KRA 3 9 30 - - 1 40

    KRA 4 8 25 2 2 - 37

    KRA 5 9 21 1 8 - 39

    TOTAL 28 101 9 13 2 153

    Percentage 18 66 6 9 1 100

  • 10

    KRA 1 Revenue Management:

    Objective: Strengthened systems, processes and procedures for improving the operational capability of

    the revenue collection by June 2016.

    Output 1.2: The Government improves efficiency in domestic revenue mobilization both at the policy

    and the administration levels by updating legal instruments towards international best practices.

    Achievements include:

    i. A draft of Tax Administration Bill has been submitted to the cabinet for approval. It is expected

    that Cabinet approval and Attorney General Verification will be done in time for the draft Act to

    be submitted to parliament.

    ii. The first draft of new TR Bill has been submitted to Cabinet Secretariat for an initial review.

    Implementation Status of Milestones as Per M&E Result Framework

    The implementation status on the 19 milestones was fairly satisfactory of which 17 (89.4%) were on

    track with 1 pending and 1 at risk.

    Figure 1 below depicts schematic presentation of KRA 1 status as at June, 2013.

    89.40%

    5.30% 5.30%

    Fig 1: KRA 1 Milestone Status

    Achieved

    On Track

    Pending

    Delayed

    At Risk

    A milestone assessed to be at risk is the Bill for an act to amend the Local Government Finances Act No.

    9 of 1982 (Milestone 1.3.7). The delayed milestones are 1.1.1 and 1.1.2 which were merged to form a

    new milestone on undertaking a study to identify ways of improving tax revenue forecast and action

    plan by June 2014.

  • 11

    The table below highlights the mid-year expenditure in KRA 1.

    Component Name

    Sources

    of

    Fund

    Approved Budget Fund Released Total Commitment

    and Expenditure

    % of

    expenditure

    against fund

    released

    % of

    expenditure

    against budget

    1 2 3 4 7 9 10

    POLICY

    ANALYSIS DEPARTMENT

    GoT 100,000,000 53,700,000 52,700,000 98% 53%

    BF 228,000,000 86,000,000 86,000,000 100% 38%

    Project 56,597,600 - - 0%

    TOTAL FOR

    COMPONENT

    384,597,600 139,700,000 138,700,000 99% 36%

    MINISTRY OF NATURAL

    RESOURCES

    AND TOURISM

    BF

    162,250,000 90,000,000 28,027,000

    31% 17%

    TOTAL FOR

    COMPONENT

    162,250,000 90,000,000 28,027,000 31% 17%

    EXTERNAL

    FINANCE

    GoT 100,000,000 - - 0%

    BF 379,060,000 162,060,000 158,658,980 98% 42%

    Project 25,000,000 0%

    TOTAL FOR

    COMPONENT

    504,060,000 162,060,000 158,658,980 98% 31%

    PMO-RALG GoT - - -

    BF 600,930,000 435,430,000 77,652,500 18% 13%

    TOTAL FOR

    COMPONENT

    600,930,000 435,430,000 77,652,500 18% 13%

    TOTAL KRA 1 1,651,837,600 827,190,000 403,038,480 49% 24%

    KRA 2 Budgeting and planning

    Objective: Strengthened capacity of planning and budget management, including results and program

    based budgeting, within MoF, MDAs and LGAs by June 2016.

    Output 2.1: Strengthened capacity of MDAs, RSs and LGAs in implementing program based

    budgeting by June 2016. Achievements include:

    i. The Chart of accounts has been modified to accommodate Program Based Budgeting (PBB) and

    the .

    ii. Training for MDAs will be done after third quarter with LGAs to be decided after review of the

    action plan.

    Output 2.2: Increased effective utilization of Planning and budgeting tools by 2016. Achievements

    include:

  • 12

    i. The PER process has been strongly revitalized, the PER Group has continued to conduct regular

    meetings on the on-going 5 studies and an annual dissemination workshop is planned to be done

    in October 2014.

    ii. Training for MDAs on Prioritization and Planning and on the new budget cycle was carried out.

    Implementation Status of Milestones as Per M&E Result Framework

    During the period under review, 2 milestones (11%) were achieved, 8 milestones (44%) were on track, 5

    milestones (28%) were pending and 3 milestones (17%) delayed in implementation. Figure 2 below

    depicts the schematic presentation for KRA 2 status as at December, 2013.

    11%

    44%28%

    17%

    Fig 2: KRA 2 Milestone Status

    Achieved

    On Track

    Pending

    Delayed

    The milestones delayed are those related to action plan for budget legal framework and MTSPBM.

  • 13

    The table below highlights the mid-year expenditure in KRA 2.

    Component Name

    Sources

    of

    Fund

    Approved Budget Fund Released Total Commitment

    and Expenditure

    % of

    expenditure

    against fund

    released

    % of

    expenditure

    against budget

    1 2 3 4 7 9 10

    GOVERNMENT

    BUDGET

    DIVISION

    GoT 1,500,000,000 525,390,000 - 0% 0%

    BF 470,400,000 343,600,000 -

    0% 0%

    TOTAL FOR

    COMPONENT

    1,970,400,000 868,990,000 - 0% 0%

    PMO-RALG GoT - - -

    BF 44,000,000 44,000,000 - 0% 0%

    TOTAL FOR

    COMPONENT

    44,000,000 44,000,000 - 0% 0%

    TOTAL KRA 2 2,014,400,000 912,990,000 - 0% 0%

    KRA 3: Budget Execution, Accountability and Transparency

    Objective: Improved utilization of public resources in a more effective, efficient and transparent manner

    by June 2016

    Output 3.1: Improved public procurement performance by PEs by 2015. Achievements include:

    i. 120 PEs were audited and the results indicated the compliance level of 64%.

    ii. PPA 2011 has been disseminated to 85 Board of Directors and 189 Accounting officers of

    Public Entities.

    iii. A survey to update database on unit costs for common activities in construction works

    undertaken in 7 regions.

    iv. PMIS is in fully functional in 364 PEs with 699 registered users.

    Output 3.2: Strengthened public sector procurement by June 2015. Achievements include:

    i. Verification and update of the database for 1,109 Public Procurement and Supplies Staff (now

    includes Tanga, Morogoro and Lake Zone).

    ii. Draft of the National procurement policy is in place and the stakeholders’ inputs in the draft

    National Procurement Policy.

    Output 3.3: Strengthened capacity of MDAs, RSs and LGAs in Cash management by 2015.

    Achievements include:

    i. 163 LGA are operating 7 bank accounts.

    ii. 271 staff from MDAs trained on cash management.

  • 14

    Output 3.5: Improved integrity and content of government financial statements and the migration from

    IPSAS cash to IPSAS accrual accounting for all government accounts is progressing in accordance with

    plans. Achievements include:

    i. Action plan for migration towards IPSAS Accrual accounting is under implementation with the

    opening balances for the financial year 2012/2013 for all MDAs established in order to facilitate

    the implementation of IPAS Accrual;

    ii. 250 accountants from MDAs and Regions were trained on migration to IPSAS Accrual.

    iii. PFA has been reviewed by stakeholders and awaits to be tabled to Parliament for enactment.

    Output 3.6: Improved accountability in management of Government Assets for supporting migration to

    IPSAS Accrual. Achievements include:

    i. An interim report for valuation of Government assets in 34 MDAs and RSs is available for

    discussion;

    ii. Asset management software is installed and tested while training of 40 staff will be undertaken

    in fourth quarter of FY 2013/14.

    Implementation Status of Milestones as per M&E Result Framework

    Out of 40 assessed milestones in KRA 3, achievement was realized in 9 (22.5%) milestones, which

    include finalization of National procurement policy draft, the preparation and issuing of public

    procurement regulations. Satisfactory progress (on track) was recorded in 30 (75%) milestones and

    1(2.5%) milestone was at risk.

    Figure 3 below depicts the schematic presentation for KRA 3 status as at December, 2013.

  • 15

    22.50%

    75%

    2.50%

    Fig 3: KRA 3 Milestone Status

    Achieved

    On Track

    Pending

    Delayed

    At Risk

    The table below shows the expenditure in KRA 3 as at December 2013

    Component Name

    Sources

    of

    Fund

    Approved Budget Fund Released Total Commitment

    and Expenditure

    % of

    expenditure

    against fund

    released

    % of

    expenditure

    against budget

    1 2 3 4 7 9 10

    ACCOUNTANT

    GENERAL DEPARTMENT

    GoT 400,000,000 - - 0%

    BF 4,355,547,615 1,947,250,000 1,250,607,908

    64% 29%

    TOTAL FOR

    COMPONENT

    4,755,547,615 1,947,250,000 1,250,607,908 64% 26%

    GOVERNEMNT ASSET

    MANAGEMENT

    DIVISION

    GoT 500,000,000 120,000,000 - 0% 0%

    BF

    2,010,000,000 1,490,500,000 155,476,647

    10% 8%

    TOTAL FOR

    COMPONENT

    2,510,000,000 1,610,500,000 155,476,647 10% 6%

    PUBLIC

    PROCUREMENT

    POLICY DIVISION

    GoT 100,000,000 30,000,000 - 0% 0%

    BF 776,000,000 505,000,000 118,368,683

    23% 15%

    TOTAL FOR

    COMPONENT

    876,000,000 535,000,000 118,368,683 22% 14%

    POLICY ANALYSIS

    DEPARTMENT

    GoT - - -

    BF 800,000,000 - -

    0%

    TOTAL FOR

    COMPONENT

    800,000,000 - - 0%

    TOTAL KRA 3 8,941,547,615 4,092,750,000 1,524,453,238 37% 17%

  • 16

    KRA 4: Budget Control and Oversight

    Objective: Improved adherence and enforcing of MDAs and LGAs to financial internal controls, rules,

    laws, regulations and audit recommendations by June 2016

    Output 4.1: Increased coverage and quality of the internal audit functions by 2016. Achievements

    include:

    i. Internal Audit manual/guidelines, standards and quality assurance improvement programme in

    line with International Standards developed.

    ii. A consultant is already engaged for conducting technical audits for 70 projects.

    iii. Survey to identify weaknesses of MDAs audit committees was conducted.

    iv. Training on roles of internal auditors for 226 stakeholders (Mayors, Council Chairpersons and

    Internal Audit) was conducted.

    v. Training on roles of internal auditors to 114 audit committees’ chairpersons was conducted.

    Output 4.2: Strengthened External audit functions by 2016. Achievements include:

    i. 12 NAOT offices have been connected with WAN.

    ii. The study on two of five Team Mate modules is completed. The activation of the Two of the five

    Team Mate modules will be conducted.

    iii. The Citizen Audit report for 5 General Audit Reports in Kiswahili language has been prepared

    internally and printed.

    Implementation Status of Milestones as per M&E Result Framework

    During the period, 8 milestones (21.6%) were achieved, 25 milestones (67.6%) were on track, 2 (5.4%)

    pending and 2 (5.4%) milestones delayed.

    Figure 4 below depict milestone status for KRA 4 by December, 2013.

  • 17

    21.60%

    67.60%

    5.40% 5.40%

    Fig 4: KRA 4 Milestone Status

    Achieved

    On Track

    Pending

    Delayed

    The table below shows the expenditure in KRA 4 as of December 2013

    Component

    Name

    Sources

    of Fund Approved Budget Fund Released

    Total Commitment

    and Expenditure

    % of

    expenditure

    against fund

    released

    % of

    expenditure

    against budget

    1 2 3 4 7 9 10

    INTERNAL

    AUDITOR GENERAL

    DIVISION

    GoT 750,000,000 105,000,000 105,000,000 100% 14%

    BF 1,589,000,000 844,810,000 576,103,000

    68% 36%

    TOTAL FOR

    COMPONENT

    2,339,000,000 949,810,000 681,103,000 72% 29%

    NATIONAL

    AUDIT OFFICE2

    GoT 15,250,000,000 1,334,375,000 9,058,462,305 679% 59%

    BF 2,422,000,000 786,075,000 786,075,000 100% 32%

    TOTAL FOR

    COMPONENT

    17,672,000,000 2,120,450,000 9,844,537,305 464% 56%

    PPRA

    GoT 950,000,000 151,000,000 33,140,151 22% 3%

    BF 1,117,188,000 343,906,000 333,191,391 97% 30%

    Project 2,616,895,000 961,301,040 509,910,857 53% 19%

    TOTAL FOR

    COMPONENT

    4,684,083,000 1,456,207,040 876,242,399 60% 19%

    TREASURY

    REGISTRAR

    GoT 600,000,000 70,000,000 69,333,949 99% 12%

    BF 1,028,800,000 758,100,000 309,707,699 41% 30%

    TOTAL FOR

    COMPONENT

    1,628,800,000 828,100,000 379,041,648 46% 23%

    TOTAL KRA 4 26,323,883,000 5,354,567,040 11,780,924,352 220% 45%

    2 The commitment shown is for the construction of Dodoma office building which is designated to be NAOT Head quarters.

    The construction contract was signed some three years ago with the value of TShs. 15bn. The constructors have finished

    their work and the building is expected to be handed over in June, so far the committed amount need to be paid and the

    Government is yet to release the full amount

  • 18

    KRA 5 – Change Management, Programme Monitoring and Communication

    Objective: Improved management practices with increased accountability and leadership to better

    manage performance of PFMRP.

    Output 5.2: Utilization of EPICOR modules increased from seven to ten. Achievement includes:

    i. 381 end users trained on EPICOR new version (9.05).

    Output 5.3: All software development and module upgrades are coordinated with the overarching plans

    for ICT integration. Achievements include:

    i. The MoF server room has been modified to manage acquisition of software and development.

    Output 5.4: Improved communication and public access to key fiscal information to stakeholders.

    Achievements include:

    i. The final draft of communication strategy has been submitted to the MoF Head of Departments

    for comments.

    Output 5.5: Coordination and Standardization of PFM Training Achieved. Achievements include:

    A PFM training mapping exercise finalized and the draft report is under discussion.

    Output 5.12: National systems and processes for intergovernmental transfers to LGAs streamlined and

    rationalized. Achievements include:

    The finalization of action plan for streamlining and rationalizing the national processes and

    systems for intergovernmental transfers to LGAs. Implementation of some actions in the short

    term started in FY 2013/14 and others will be included in FY 2014/15.

    133 LGAs are all operating its accounts by using Epicor 9.05

    Implementation Status of Milestones as per M&E Result Framework

    In KRA 5, achievement recorded in 9 milestones (23.1%), 21 milestones (53.8%) recorded a satisfactory

    progress, 1 milestone (2.6%) was pending and 8 (20.5%) milestones delayed for implementation.

    Figure 5 below depicts the schematic presentation for KRA 5 status as at December, 2013.

  • 19

    23.10%

    53.80%

    2.60%

    20.50%

    Fig 5: KRA 5 Milestone Status

    Achieved

    On Track

    Pending

    Delayed

    The table below shows the expenditure in KRA 5 as at December 2013

    Component Name

    Sources

    of

    Fund

    Approved Budget Fund Released Total Commitment

    and Expenditure

    % of

    expenditure

    against fund

    released

    % of

    expenditure

    against budget

    1 2 3 4 7 9 10

    FINANCIAL

    INFORMATION

    MANAGEMENT SYSTEM

    GoT 750,000,000 230,000,000 46,749,369 20% 6%

    BF

    1,744,000,000 325,000,000 92,480,038 28% 5%

    TOTAL FOR COMPONENT 2,494,000,000 555,000,000 139,229,407 25% 6%

    PMO-RALG GoT - - -

    BF 786,270,000 79,610,000 - 0% 0%

    TOTAL FOR COMPONENT 786,270,000 79,610,000 - 0% 0%

    ADMNISTARTION

    DEPARTMENT

    GoT 200,000,000 140,000,000 27,660,000 20% 14%

    BF 207,000,000 90,000,000 10,000,000 11% 5%

    TOTAL FOR COMPONENT 407,000,000 230,000,000 37,660,000 16% 9%

    GOVERNEMNT

    COMMUNICATION

    UNIT

    GoT 300,000,000 64,900,000 22,200,000 34% 7%

    BF 323,500,000 262,725,000 116,600,230 44% 36%

    TOTAL FOR COMPONENT 623,500,000 327,625,000 138,800,230 42% 22%

    PLANNING

    DEPARTMENT

    GoT 1,057,295,000 176,050,000 176,050,000 100% 17%

    BF 1,566,300,000 1,217,300,000 924,056,469 76% 59%

    Project 32,291,200 - - 0%

    TOTAL FOR COMPONENT 2,655,886,200 1,393,350,000 1,100,106,469 79% 41%

    ZANZIBAR BF 500,000,000 300,000,000 - 0% 0%

    TOTAL FOR COMPONENT 500,000,000 300,000,000 - 0% 0%

    TOTAL KRA 5 7,466,656,200 2,885,585,000 1,415,796,106 49% 19%

  • 20

    CHAPTER THREE

    BUDGET EXECUTION

    3.1 Funds Disbursement and Release

    The approved budget for FY 2013/14 is Tshs. 46,398,324,415 out of which Tshs. 2,730,783,800 are

    Project funds, Tshs. 22,557,295,000 Government funds and Tshs. 21,110,245,615 are Basket funds. Out

    of the committed funds (Tshs.16,217,888,000), Basket fund donors disbursed Tshs. 14,463,386,303.

    Basket Funds and the status of disbursements is shown in table 3.1 below.

    Table 3.1: Basket Funds Disbursement by Development Partners for July-December 2013/14

    DPs Commitment Actual Disbursement Difference

    DP

    DPs Local

    Currency

    Amount in

    (US )

    Amount in

    (Tshs.) Date

    Amount

    USD Amount in Tshs.

    Amount

    USD

    Amount in

    Tshs.

    DANIDA DKK 11,876,870 2,064,200 3,302,720,000 22.07.2013 1,896,844 3,041,608,322

    167,356

    261,111,678

    KFW EUR 600,000 777,180 1,243,488,000 28.07.2013 787,863 1,263,818,917

    (10,683)

    (20,330,917)

    Canada CAD 2,024,903 1,975,900 3,161,440,000 18.10.2013 1,927,897 3,075,987,846

    48,003

    85,452,154

    DFID GBP 2,661,463 4,023,600 6,437,760,000 30.08.2013 3,097,702 4,968,188,168

    925,898

    1,469,571,832

    Ireland EUR 1,000,000 1,295,300 2,072,480,000 05.09.2013 1,318,300 2,113,783,049

    (23,000)

    (41,303,049)

    Sub

    Total 10,136,180 16,217,888,000 9,028,606 14,463,386,303

    1,107,574

    1,754,501,697

    3.2 Fund flows

    The available Basket funds in the holding account was Tshs. 21,274,239,543 out of which Tshs.

    1,661,787,834 was opening balance, Tshs. 5,149,065,406 was unspent balance returned by components

    and Tshs. 14,463,386,303 was disbursement by DPs. The amount released to components was Tshs.

    10,111,366,000 as detailed in table 3.2.

  • 21

    Table 3.2 Movement in Holding Account with the Bank of Tanzania from July-December 2013/14

    PFMRP BASKET FUND HOLDING ACCOUNT No. 9931206081

    Date Description

    Amount in

    USD Amount in Tshs.

    01.07.2013 (a) Opening Balance 1,042,082 1,661,787,834

    Add Inflows

    Returned Unspent Balances

    02.08.2013 Vote 21 (Budget & External Finance)

    341,401 550,460,000

    02.08.2013 Zanzibar

    303,506 491,674,075

    16.08.2013 Vote 50

    500,962 811,377,873

    11.09.2013 Vote 50 1,241,685 2,011,145,137

    11.09.2013 Vote 21 (CPAD)

    81,555 132,108,150

    04.12.2013 Vote 23 (ACGEN)

    11,202 18,060,747

    16.12.2013 Vote 23 (ACGEN)

    395,709 637,530,598

    20.12.2013 Vote 50

    310,050 496,708,825

    (b) Unspent Balance Total 3,186,069 5,149,065,406

    DP Releases

    22.07.2013 Denmark 1,896,844 3,041,608,322

    28.07.2013 KfW

    787,863 1,263,818,917

    30.08.2013 DFID 3,097,702 4,968,188,168

    08.09.2013 Ireland 1,318,300 2,113,783,049

    18.10.2013 CIDA 1,927,897 3,075,987,846

    (c) DP Release Total 9,028,606 14,463,386,303

    Funds Available (a+b+c) 13,256,757 21,274,239,543

    Less Outflows `

    23.08.2013 Accountant General

    546,902 877,025,000

    23.08.2013 PMO-RALG

    220,077 352,920,000

    23.08.2013 Vote 7,21 and 50 2,008,144 3,220,308,000

    04.09.2013 NAOT

    490,277 786,075,000

    23.10.2013 Ministry of Natural Resources and Tourism 90,000,000

  • 22

    56,426

    26.11.2013 Vote 7,21 and 50 2,194,386 3,508,693,000

    26.11.2013 Accountant General

    669,334 1,070,225,000

    12.12.2013 PMO-RALG

    129,170 206,120,000

    Amount Transferred to Exchequer 6,314,716 10,111,366,000

    Balance in The Holding Account as at 31 December,2013 6,942,041 11,076,199,184

    Note: Holding Account Balance have been translated at Tshs. 1,595.5248 per US $ at 31 December 2013

    3.3 Actual Expenditure and Commitment

    During the reporting period, actual expenditure and commitment amounted to Tshs. 15,124,212,175

    equivalent to 107% of the total funds released. Actual expenditure and commitment by source was GoT

    Tshs. 9,591,295,774 equivalent to 320% of the released funds3; Project Tshs. 509,910,857 (53%) and

    Basket Funds Tshs. 5,023,005,545 equivalent to 50% of the released funds. Table 3.3 below is the

    summary of overall funds release against actual expenditure for July 2013 to December 2013 while table

    3.4 shows the summary breakdown by component recipients.

    Table 3.3: PFMRP IV Summary of Fund Release and Actual Expenditure and Commitment for July-

    December 2013/14

    SOURCE OF FUNDS

    APPROVED

    BUDGET

    CUMMULATIVE

    RELEASE

    CUMMULATIVE

    EXPENDITURE

    AND

    COMMITMENT

    % ON

    RELEASE

    GOT 22,557,295,000 3,000,415,000 9,591,295,7744 320%

    PROJECT 21,110,245,615 10,111,366,000 5,023,005,545 50%

    BF 2,730,783,800 961,301,040 509,910,857 53%

    GRAND TOTAL 46,398,324,415 13,399,074,040 15,031,732,138 117%

    3 The over expenditure and commitments is caused by NAO see Note 1& 2

    4 The over expenditure and commitments is caused by NAO see Note 1 & 2

  • 23

    Table 3.4: PFMRP IV Fund Release against Expenditure and Commitment by component for FY 2012/13

    Component Name

    Sources

    of

    Fund

    Approved Budget Fund Released Expenditure to

    date

    Commitments to

    Date

    Total

    Commitment and

    Expenditure

    Fund Balance Budget Balance

    % of

    expenditure

    against budget

    1 2 3 4 5 6 7 8 9 10

    POLICY

    ANALYSIS

    DEPARTMENT

    GoT 100,000,000 53,700,000 52,700,000 - 52,700,000 1,000,000 46,300,000 53%

    BF 1,028,000,000 86,000,000 86,000,000 - 86,000,000 - 942,000,000 8%

    Project 56,597,600 - - - - - 56,597,600 0%

    TOTAL FOR COMPONENT 1,184,597,600 139,700,000 138,700,000 - 138,700,000 1,000,000 1,044,897,600 12%

    MINISTRY OF

    NATURAL

    RESOURCES AND

    TOURISM

    BF 162,250,000 90,000,000 28,027,000 - 28,027,000 61,973,000 72,250,000 17%

    TOTAL FOR COMPONENT 162,250,000 90,000,000 28,027,000 - 28,027,000 61,973,000 72,250,000 17%

    EXTERNAL

    FINANCE

    GoT 100,000,000 - - - - - 100,000,000 0%

    BF 379,060,000 162,060,000 85,398,980 73,260,000 158,658,980 3,401,020 217,000,000 42%

    Project 25,000,000 25,000,000 0%

    TOTAL FOR COMPONENT 504,060,000 162,060,000 85,398,980 73,260,000 158,658,980 3,401,020 342,000,000 31%

    BF 1,431,200,000 559,040,000 77,652,500 - 77,652,500 481,387,500 872,160,000 5%

    TOTAL FOR COMPONENT 1,431,200,000 559,040,000 77,652,500 - 77,652,500 481,387,500 872,160,000 5%

    GOVERNMENT

    BUDGET

    DIVISION

    GoT 1,500,000,000 525,390,000 - - - 525,390,000 974,610,000 0%

    BF 470,400,000 343,600,000 - - - 343,600,000 126,800,000 0%

    TOTAL FOR COMPONENT 1,970,400,000 868,990,000 - - - 868,990,000 1,101,410,000 0%

    Component Name

    Sources

    of

    Fund

    Approved Budget Fund Released Expenditure to

    date

    Commitments to

    Date

    Total

    Commitment and

    Expenditure

    Fund Balance Budget Balance

    % of

    expenditure

    against budget

    1 2 3 4 5 6 7 8 9 10

    ACCOUNTANT

    GENERAL

    DEPARTMENT

    GoT 400,000,000 - - - - - 400,000,000 0%

    BF 4,355,547,615 1,947,250,000 850,607,908 - 1,250,607,908 - 2,408,297,615 29%

    TOTAL FOR COMPONENT 4,755,547,615 1,947,250,000 850,607,908 - 1,250,607,908 - 2,808,297,615 26%

    PPRA

    GoT 950,000,000 151,000,000 - 33,140,151 33,140,151 117,859,849 799,000,000 3%

    BF 1,117,188,000 343,906,000 59,401,380 273,790,011 333,191,391 10,714,609 773,282,000 30%

    Project 2,616,895,000 961,301,040 509,910,857 - 509,910,857 451,390,183 1,655,593,960 19%

    TOTAL FOR COMPONENT 4,684,083,000 1,502,699,040 569,312,237 306,930,162 876,242,399 626,456,641 3,181,383,960 19%

    GOVERNEMNT

    ASSET

    MANAGEMENT

    DIVISION

    GoT 500,000,000 120,000,000 - - - 120,000,000 380,000,000 0%

    BF 2,010,000,000 1,490,500,000 155,476,647 - 155,476,647 1,335,023,353 519,500,000 8%

  • 24

    TOTAL FOR COMPONENT 2,510,000,000 1,215,000,000 155,476,647 - 155,476,647 1,059,523,353 1,295,000,000 6%

    PUBLIC

    PROCUREMENT

    POLICY DIVISION

    GoT 100,000,000 30,000,000 - - - 30,000,000 70,000,000 0%

    BF 776,000,000 505,000,000 93,878,308 24,490,375 118,368,683 386,631,317 271,000,000 15%

    TOTAL FOR COMPONENT 876,000,000 535,000,000 93,878,308 24,490,375 118,368,683 416,631,317 341,000,000 14%

    INTERNAL

    AUDITOR

    GENERAL

    DIVISION

    GoT 750,000,000 105,000,000 105,000,000 - 105,000,000 - 645,000,000 14%

    BF 1,589,000,000 844,810,000 481,633,000 94,470,000 576,103,000 268,707,000 744,190,000 36%

    TOTAL FOR COMPONENT

    2,339,000,000

    949,810,000

    586,633,000

    94,470,000

    681,103,000

    268,707,000

    1,389,190,000

    29%

    NATIONAL AUDIT

    OFFICE

    GoT 15,250,000,000 1,334,375,000 1,312,036,182

    7,746,426,1235 9,058,462,305 (7,724,087,305) 13,915,625,000 59%

    BF 2,422,000,000 786,075,000 786,075,000 - 786,075,000 - 1,635,925,000

    32%

    TOTAL FOR COMPONENT 17,672,000,000 2,120,450,000 2,098,111,182 7,746,426,123 9,844,537,305 (7,724,087,305) 15,551,550,000 56%

    TREASURY

    REGISTRAR

    GoT 600,000,000 70,000,000 69,333,949 - 69,333,949 666,051 530,000,000 12%

    BF 1,028,800,000 758,100,000 309,707,699 - 309,707,699 448,392,301 270,700,000 30%

    TOTAL FOR COMPONENT 1,628,800,000 828,100,000 379,041,648 - 379,041,648 449,058,352 800,700,000 23%

    FINANCIAL

    INFORMATION

    MANAGEMENT

    SYSTEM

    GoT 750,000,000 230,000,000 46,749,369 - 46,749,369 183,250,631 520,000,000 6%

    BF 1,744,000,000 325,000,000 84,534,038 7,946,000 92,480,038 232,519,962 1,419,000,000 5%

    TOTAL FOR COMPONENT 2,494,000,000 555,000,000 131,283,407 7,946,000 139,229,407 415,770,593 1,939,000,000 6%

    ADMNISTARTION

    DEPARTMENT

    GoT 200,000,000 140,000,000 27,660,000 - 27,660,000 112,340,000 60,000,000 14%

    BF 207,000,000 90,000,000 10,000,000 - 10,000,000 80,000,000 117,000,000 5%

    TOTAL FOR COMPONENT 407,000,000 230,000,000 37,660,000 - 37,660,000 192,340,000 177,000,000 9%

    GOVERNEMNT

    COMMUNICATION

    UNIT

    GoT 300,000,000 64,900,000 22,200,000 - 22,200,000 42,700,000 235,100,000 7%

    BF 323,500,000 262,725,000 116,600,230 - 116,600,230 146,124,770 60,775,000 36%

    TOTAL FOR COMPONENT 623,500,000 327,625,000 138,800,230 - 138,800,230 188,824,770 295,875,000 22%

    PLANNING

    DEPARTMENT

    GoT 1,057,295,000 176,050,000 176,050,000 - 176,050,000 - 881,245,000 17%

    BF 1,566,300,000 1,217,300,000 238,928,184 685,128,285 924,056,469 293,243,531 349,000,000 59%

    Project 32,291,200 - - - - - 32,291,200

    5 The commitment shown is for the construction of Dodoma office building which is designated to be NAOT Head quarters. The construction contract was

    signed some three years ago with the value of TShs. 15bn. The constructors have finished their work and the building is expected to be handed over in June, so

    far the committed amount need to be paid and the Government is yet to release the full amount

  • 25

    TOTAL FOR COMPONENT 2,655,886,200 1,393,350,000 414,978,184 685,128,285 1,100,106,469 293,243,531 1,262,536,200 41%

    ZANZIBAR

    BF 500,000,000 300,000,000 - - - 300,000,000 200,000,000 0%

    TOTAL FOR COMPONENT 500,000,000 300,000,000 - - - 300,000,000 200,000,000 0%

    TOTAL FOR PROGRAM 46,398,324,415 14,073,082,040 5,785,561,230 8,938,650,945 15,124,212,175 (1,747,772,228) 32,243,644,775 33%

    TOTAL BY

    SOURCE

    GoT 22,557,295,000 3,000,415,000 1,811,729,499 7,779,566,274 9,591,295,774 (6,590,880,774) 19,556,880,000 43%

    BF 21,110,245,615 10,111,366,000 3,463,920,874 1,159,084,671 5,023,005,545 4,391,718,363 10,998,879,615 24%

    Project 2,730,783,800 961,301,040 509,910,857 - 509,910,857 451,390,183 1,769,482,760 19%

    TOTAL FOR PROGRAM 46,398,324,415 14,073,082,040 5,785,561,230 8,938,650,945 15,124,212,175 (1,747,772,228) 32,325,242,375 33%

  • 26

    CHAPTER FOUR

    CHALLENGES AND RECOMMENDATIONS

    During the period, program implementation encountered challenges including:

    (i) Late submission of reports from some components: The delay in submission of reports

    from some components is one of challenges the Secretariat has been facing. The

    components do not submit reports timely, which results in delays in the finalisation of a

    consolidated report for sharing with stakeholders.

    (ii) Lack of M&E Specialist: The delay in having in place the Monitoring and evaluation

    specialist for the programme contributed to the inadequate follow-up of M&E framework

    and reporting. The M&E Specialist was recruited at the end of reporting period.

    (iii)Delays in ToRs/procurement approval process: There are some cases in which

    components provide incomplete or unsatisfactory information in the draft ToRs for

    recruitment of services/programme inputs. This has resulted in significant delays in DPs

    granting “no objection” to the undertaking of some activities impacting on milestone

    progress.

    (iv) Lack of GoT disbursements: DPs have expressed concern over the low level of

    disbursement from the GoT side. As at Dec 2013, this represented only 13% of the funds

    committed. This affected a number of components in undertaking their activities.

    Recommendations

    (i) Component managers have to appoint officers who will be responsible for preparing and

    submitting the report timely to PFMRP secretariat. These officers will work with the

    M&E specialist to ensure reporting is according to best practice.

    (ii) The components should ensure that comprehensive Terms of Reference are submitted to

    the secretariat in good time to allow for the due procurement process from no objection

    stage to actual steps required by procurement regulations.

    (iii)The recently agreed quarterly financial and procurement reporting should facilitate the

    stakeholders to discuss and seek remedial solutions for red flags and challenges identified

    during the quarter.

  • 27

    Annex 1

    PFMRP MID-YEAR REPORT FOR FY 2013/14

    PFMRP IV M&E RESULT FRAMEWORK 2012 – 2017

    STATUS AS AT 30TH

    DECEMBER 2013

    CODE: MILE STONE DESCRIPTIONS STATUS

    (State

    whether

    Achieved, On

    track,

    Delayed

    Pending, At

    Risk)

    COMMENTS ON THE STATUS RESPONSIBLE

    COMPONENT

    KRA 1: Revenue Management

    Output 1.1: Improved quality of forecasting of fiscal aggregates for three years on a rolling basis

    1.1.1 Undertake a study to identify ways of

    improving tax revenue forecast and action

    plan by June 2014

    Pending The study is yet to be conducted. There is need to

    develop capacity development plan to have trainers

    (ToT) who are well equipped on revenue forecasting

    PAD

    1.1.2 A team of trainers in revenue forecasting

    developed by June 2014 (The milestone to be

    reviewed in line with recommendation from

    the study)

    On track A study/training to 15 staff on macroeconomic

    diagnostic was conducted in December 2013. The

    received funds in Q3 will be used to conduct more

    traning. If training is done appropriately, the ToT can

    train MDAs.

    PAD

  • 28

    Output 1.2:The Government improves efficiency in domestic revenue mobilization both at the policy and the administration levels by

    updating legal instruments towards international best practices

    1.2.1 The study on Non Tax Revenue (NTR) -

    “Integration and Harmonization of Revenue

    Collection Systems” completed by November

    2013.

    On track Draft report of the study has been circulated to

    stakeholders for comments and inputs. Stakeholders

    workshop held in Dec 2013 and comments shared

    with the consultant. Final report due in April 2014.

    PAD

    1.2.2 Action plan to implement the

    recommendations from review of non-tax

    collection developed by June 2014

    On track The action plan will be developed once the study is

    finalized. To be included in FY2014/15 so that

    stakeholders are called to work on action plan. There

    is also a possibility to draw on DPs who can assist

    with action plan workshop so that it is finalized

    before June 2014.

    PAD

    1.2.3 Costed action plan incorporated in FY

    2015/16 for implementation

    Pending This milestone depends on the completion of

    milestone 1.2.2

    PAD

    1.2.4 Submission of a bill to Parliament to enact

    Tax Administration Act for the purpose of

    establishing a common tax procedure among

    different taxes collected by Tanzania revenue

    authority (TRA) by February 2014

    On track The Tax Administration Bill drafted and submitted to

    Attorney General’s Office for vetting. Now waiting

    for Parliament for approval hopefully in next budget

    session. Harmonizing of tax procedures due to EAC

    commitments.

    PAD

    1.2.5 Review laws, rules and regulations for local

    government revenue system to improve LGA

    own sources in line with best practice by

    June, 2016

    On track

    Stakeholders meeting to review local government

    finance Act No 7,8 and 9 of 1982 and urban

    rating Act has been done.

    Preparation of Cabinet Bill of an Act to amend

    the Local Government Finance Act No. 7, 8 and 9

    of 1982 and submit to the cabinet are scheduled

    PMO-RALG

  • 29

    to be implemented in FY 2014/15

    1.2.6 Take policy action to improve revenue

    mobilization from natural resource sectors by

    June, 2014

    On track Review of antiquity entrance fee is completed

    Review of Forest loyalty charges for forest

    product has been done and new charges are in use

    Review of photographic tourism regulation is in

    final stage

    Collection of tourism development levy started

    (TRA collected on behalf of MNRT)

    MNRT

    1.2.7 Computerized revenue collection to at least

    50% from MNRT by June 2016

    On track The Ministry has developed and started using

    Tourism Hunting Management System, Photographic

    Tourism Management System & Tourism Business

    Registration and Licensing System. Training on

    Tourism Business Registration and Licensing System

    has been done to 21 users of the system.

    MNRT

    1.2.8 Review the current system of tax exemptions

    with the value-added Tax (VAT) regime and

    amend the VAT Act with a view to be in line

    with international best practices by November

    2014

    On track

    The Cabinet paper for the VAT Act is being prepared

    with support from IMF consultant. The draft cabinet

    paper will be shared to stakeholders for comments.

    Draft concept submitted to Cabinet in Dodoma and it

    now approved. Estimated to bring in more revenue

    (about TZS1.1 trillion per year). Balance of activity

    to be shared in FY2014/15. PAD to share roadmap

    PAD

    Output 1.3: Strengthened capacity of local government authorities to collect revenue by 2015

  • 30

    1.3.1 Completed assessment and evaluation of

    revenue potential for major sources of

    revenue to all LGAs by June 2014

    On track The assessment and evaluation is completed and draft

    report will be shared to stakeholders in the next

    quarter

    PMO-RALG

    1.3.2 Local Authorities Tax administration teaching

    and practice modules established and TOT

    completed for all finance management staff at

    the regional levels by June 2014

    On track The milestone was planned to be implemented using

    Local funding. Fund for this milestone was not

    released. The milestone dismissed.

    PMO-RALG

    1.3.3 PMO - RALG staff and Finance Management

    Officers at RS are trained in tax revenue

    plans and budgets to spearhead LGAs tax

    reviews and reforms, June 2014

    On track The ToR has been prepared and submitted to DPs for

    no objection. Request. The training will be conducted

    upon approval from the DPs.

    PMO-RALG

    1.3.4 Four (4) revenue accountants, 3 Council

    management team members and 1 FMO from

    each LGA and RS are trained on own source

    revenue management in every two years.

    On Track The milestone planned activities scheduled to be

    implemented in FY 2014/15.

    PMO-RALG

    1.3.5 Establishment of known and clear revenue

    data base by each source of revenue, presence

    of trained personnel and a clear follow up

    arrangement at PMORALG and RS levels by

    June, 2015

    On track The milestone is planned to be implemented during

    FY 2014/15, I-tax revenue database to be

    implemented.

    PMO-RALG

    1.3.6 Completed study on the effectiveness,

    relevancy and sufficiency of the provisions of

    the Local Government Finances Act No. 9 by

    June, 2014

    On track The Finances Act No.9 was reviewed and areas to be

    amended were identified and a report is in place. The

    report is to be shared with other stakeholders.

    Stakeholders meetings will be carried in FY 2014/15.

    PMO-RALG

    1.3.7 A bill for an act to amend the Local

    Government Finances Act No.9 of 1982 is

    finalized and submitted to the Cabinet by June

    At risk The milestone will be implemented in F Y 2014/15. PMO-RALG

  • 31

    2014

    Output 1.4: Increase of Donor funding that flows through the exchequer system by 2016

    1.4.1 National framework for managing

    development cooperation (Development

    Cooperation Framework, DCF) reviewed,

    disseminated and put in operation by March

    2014

    On track Development Cooperation Framework (DCF) final

    draft is already shared with Government stakeholders

    and DP’s. DP’s comments are waited to be

    incorporated.

    EFD

    1.4.2 Revised AMP user guideline clearly

    communicated to both parties by December

    2014

    On track AMP user guidelines to be shared with stakeholders.

    Training of EFD staff on AMP New Version awaiting

    release of funds.

    EFD

    1.4.3 Analysis of the trends of the direct project

    fund portfolio disbursed via exchequer system

    published and shared annually by June 2015

    On Track Collection and compilation of data have been done,

    the analysis of which is expected to be undertaken in

    the fourth quarter of FY 2013/14.

    EFD

    KRA 2: Planning and Budgeting:

    Output 2.1: Strengthened capacity of MDAs, RSs and LGAs in implementing program based budgeting by June 2016.

    2.1.1 All Sub programs, program objectives and

    performance indicators defined by December

    2014

    Delayed Programs Based Budgeting (PBB) template

    developed and MOF organized a working session end

    of August 2013 with 8 pilot Ministries (Ministry of

    Finance, Water, Works, Transports, Education,

    Health, Community Development and Agriculture).

    The assignment to MDAs was to convey FY 13/14

    budget into PBB format. Another session will be

    conducted in third quarter in this FY.

    GBD

    2.1.2 Chart of Accounts modified to accommodate Achieved Chart of accounts has been modified to accommodate GBD

  • 32

    program based budgeting by Aug 2013 PBB.

    2.1.3 MTEF reviewed to make program based

    budget compatible by September 2016

    On track The reviewed MTEF will build on the existing one.

    MDAs and LGAs have been informed on the coming

    change, preparation began. It was agreed to move the

    timeline for all MDAs and LGAs to be compatible to

    September 2016 with continuous follow-up of the

    roll-out. The MTEF will partly be reviewed in the

    fourth quarter of FY 2013/14.

    GBD

    2.1.4 Progress on the PBB Action plan

    implementation annually

    Delayed The activities lagging behind will be dealt with in the

    FY 2013/14

    GBD

    2.1.5 Completed phased training for all MDAs and

    RSs by September 2016

    On track Existing PBB Action Plan will be reviewed after the

    third quarter working session with pilot Ministries. It

    will include a Policy paper in order for the Cabinet to

    formally authorize the use of PBB. PBB will be

    implemented in stepwise fashion starting with a

    number of Pilot ministries and then move to other

    MDAs, regions and LGAs. All MDAs and LGAs to

    be compatible by September 2016. The training to

    selected MDAs will be conducted after the review.

    GBD

    2.1.6 Completed phased training for all LGAs by

    September 2016

    Pending The pilot for MDAs is still ongoing. The training for

    LGAs will be decided at a later stage.

    GBD

    Output 2.2:Increased effective utilization of Planning and budgeting tools by 2016

    2.2.1 MTSPBM reviewed by June 2013 Delayed It is not done yet as it requires a joint work with the

    Planning Commissioner. However, initial timeline

    won’t be met as MTSPBM is planned to be reviewed

    this financial year (2013/2014).

    GBD

  • 33

    2.2.2 Sixty MDAs, 21 RSs and 133 LGAs trained

    in MTSPBM by June 2014

    On track However, completion may be delayed as MoF is only

    at the stage of developing a Training Budget Manual.

    GBD

    2.2.3 Reviewed MTSPBM to be applied during FY

    2013/14

    Pending To be applied in FY 2014/15 GBD

    2.2.4 Annexes to budget book volume II for

    Executive Agencies completed by June 2014

    On track This milestone will be partially achieved by timeline,

    as only some of the 133 public agencies will be

    covered by June 2014. It will be included in the PBB

    Action Plan; the level of detail required for these

    annexes is still under discussion. MoF plans to

    organize training on MTEF to public agencies.

    GBD

    2.2.5 Action plan on implementation of

    recommendations on budget legal framework

    completed by June 2013

    The milestone to be shifted to Planning

    Division and CB to share the AFRITEC

    report with Planning Division.

    Delayed Mainly due to external constraints. Review of the

    Public Finance Act is under process but the new

    Constitution is likely to further delay it. The Local

    Government Finance Act will also need to be

    changed, as it currently doesn’t include IFMS. The

    PPP Act will also be changed. In parallel, the

    Parliamentary Budget Committee is pushing to have

    a separate Budget Act.

    GBD

    2.2.6 At least 10 PER Main Dialogue meetings held

    by June 2016

    On track The PER process has been strongly revitalized since

    June 2012. The PER Champion Group has had

    regular meetings on the on-going 5 studies and an

    annual dissemination workshop is planned for

    beginning of October 2014.

    GBD

    2.2.7 Phased training to MDAs, RSs and LGAs

    Budget Committees on resources

    prioritization and planning

    On track Training for MDAs on Prioritization and Planning

    was carried out and also MDAs were oriented to the

    New budget cycle for their comments and

    GBD

  • 34

    implementation

    Output 2.3: Strengthened capacity of LGAs for MTEF preparation by 2015

    2.3.1 Proposal for budget information to be

    included in the Budget guideline to be

    submitted to National Budget Guideline

    committee by October annually.

    Achieved The process of collecting, scrutinizing and submitting

    all LGAs own source budget information to National

    Budget guideline Committee has successful been

    done.

    PMO-RALG

    2.3.2 Recommendations of various studies on

    LGAs budget allocation formula reviewed by

    June 2014

    On track ToR developed and shared to stakeholders, it will be

    carried in the third and fourth quarters of FY

    2013/14. The no objection was granted.

    PMO-RALG

    2.3.3 Agreement on improvement of LGAs budget

    allocation formulas among the sector Ministry

    (PMORALG, MOF, PO-PSM and Sectors)

    completed by June 2014

    Pending Pending achievement of 2.3.2. PMO-RALG

    2.3.4 All LGAs budget allocation formulae

    reviewed by June, 2014

    Pending Pending achievement of 2.3.3 PMO-RALG

    2.3.5 All reviewed LGAs budget allocation

    formulae applied in the budget preparation

    during 2014/15 for the FY 2015/16 budget.

    Pending Pending achievement of 2.3.4 and the activity is

    planned to be conducted in the FY 2014/15.

    PMO-RALG

    2.3.6 Monitoring arrangements are in place for

    measuring deviations in actual releases

    against all formula-based allocations to LGAs

    by June 2015.

    Pending Pending achievement of above milestones PMO-RALG

    Output 2.4: Quality and comprehensiveness of budget documentation as well as public access to key fiscal information

    KRA 3: Budget Execution, Transparency and Accountability

  • 35

    Output 3.1 Strengthened public sector procurement by June 2015

    3.1.1 Action Plan for implementing Public

    Procurement Act is developed by December

    2014

    On track Regulations for implementing PPA, 2011 have been

    approved for use from December, 2013. Action plan

    for implementing the Act will be developed in

    collaboration with other key stakeholders in the

    fourth quarter of FY 2013/14.

    PPRA

    3.1.2 New public procurement regulations prepared

    and issued by June 2013

    Achieved Regulations prepared, signed and gazetted PPD

    3.1.3 Procurement training needs assessment

    exercise completed by Dec 2014

    On track ToRs for TNA in MDAs developed and shared to

    stakeholders for comment.

    PPD

    3.1.4 [300] procurement staff trained on public

    procurement by June 2017 as per TNA.

    On track It will be done after completion of TNA exercise. It

    was agreed that the number and type of training will

    be revisited depending on the findings and

    recommendations of the TNA. There may be need to

    prepare for training modules given the TNA

    recommendations.

    PPD

    3.1.5 Strategy to develop Procurement Management

    Unit (PMU) structures in Public Sector by

    June 2015

    On track Stakeholders’ meeting (compromised Head of PMUs)

    was held to provide comments on proposed PMU

    structure. At the moment the PPD is incorporating

    comments provided by stakeholders and will be

    presented to DAHRM for further actions.

    PPD

    3.1.6 Procurement and supplies staff database

    maintained and updated by December, 2015

    On track Data base information for 1,109 Public Procurement

    and Supplies Staff have been verified (in Tanga,

    Morogoro and Mwanza region) and updated.

    PPD

  • 36

    3.1.7 National procurement policy draft is finalized

    by Dec 2014

    Achieved Draft National Public Procurement Policy finalized

    and submitted to PS MOF for further actions.

    PPD

    3.1.8 Stakeholders’ comments incorporated by

    June, 2013

    Achieved Stakeholders’ meeting conducted and comments

    incorporated in the draft National Procurement

    Policy.

    PPD

    3.1.9 PPDs' office and staff capacity enhanced by

    June, 2017

    On Track PPD

    3.1.10 -

    3.1.17

    The following milestones are related to the

    final national procurement policy:

    20 members of PPD staff equipped with

    skills on public policy formulation,

    implementation and evaluation by June,

    2013

    National procurement policy developed and

    shared by December, 2014

    National procurement policy (NPP) strategy

    developed and implemented by June 2015

    Printing and uploading the NPP on the

    website by June, 2015

    National procurement policy and

    procurement law synchronized by June,

    2015

    Monitoring the implementation of the

    National procurement policy by June, 2015

    Evaluation and feedback of the

    implementation of the National procurement

    On track

    On track

    On track

    Eight PPD staff capacity enhanced with skills on

    public policy formulation, implementation and

    evaluation. The training for another 8 PPD Staff is

    scheduled in the fourth quarter.

    The fund re-allocation request for implementing the

    said milestone was submitted, a response is awaited.

    Will be done after completion of the National Public

    Procurement Policy. The 2014 onwards targets for

    the national procurement policy are all on track –

    targets within reach.

    PPD

  • 37

    policy by June, 2016

    1000 Stakeholders acquainted with the

    National procurement Policy by June, 2016

    Output 3.2: Strengthened capacity of MDAs Rs and LGAs in Cash Management by 2015

    3.2.1 600 staff of MDAs and LGAs Trained on cash

    Management using standardized materials by

    June 30 2015

    ( Milestones to be reviewed and aligned after

    the East AFRITAC recommendations on Cash

    and Banking Arrangement Mission)

    On track 271 staff from MDAs trained on cash Management.

    100 staff from MDAs will be trained in cash

    management on the third quarter of FY 2013/14

    ACGEN

    3.2.2 Six bank accounts operated by each LGA by

    December, 2013

    Achieved Each LGA is now operating with six bank accounts ACGEN

    Output 3.3: Strengthened public debt management capacity by 2015

    3.3.1 The agreed actions arising from the Feb. 2012

    World Bank debt management report shared

    with key stakeholders by July 31, 2012

    Achieved The report has been shared and it is available in the

    Ministry of Finance website

    PAD

    3.3.2 Debt management policy developed and

    shared by June 2014

    On track

    With technical support from the World Bank and the

    East African MEFMI, MOF conducted a debt

    sustainability analysis (DSA) in September 2013,

    which covers both domestic and external debt. The

    DSA report will be published by March 2014.

    PAD

  • 38

    3.3.3 Capacity of 50 Public Debt Management Staff

    enhanced to undertake DSA on external,

    domestic debt and contingent liabilities by

    June 2014

    On track

    Despite funds not being available, capacity continues

    adhoc basis (such as secondment of GoT to MEFIM

    on risk management and another to WB HQ) while

    waiting for administrative measures to be completed

    on the approval of DMO structure. The structure

    would include a middle office - MO (PAD), front

    office -FO (BoT) and Back Office- BO (ACGEN)

    PAD, ACCGEN

    3.3.4 Reviewed Government Loans, Guarantees

    and Grants Act submitted to the Cabinet by

    June 2014

    On track

    Review in progress. The Government Loans,

    Guarantee and Grants Act, No.30 Cap. 134 (R.E

    2004) reviewed; and the medium Term Debt Strategy

    reviewed too.

    PAD

    3.3.5 Debt Management department established by

    June 2016.

    On track

    Establishment of DMO office is awaiting approval

    from PO-PSM

    PAD

    Output 3.4: Improved Integrity and content of government financial statements and migration from IPSAS cash Basis to

    IPSAS accrual is progressing in accordance with the plans.

    3.4.1 Completed review of the IPSAS guideline

    issued by PMORALG in 2008/09 to

    accommodate the recent IPSAS updates by

    June 2013

    At risk The milestone is not clear to ACCGEN

    ACGEN

    3.4.2 Training to MDAs, RSs and LGAs accounting

    officers to develop awareness on IPSAS

    Accrual by June 2014

    On track 320 people (chief accountants from MDAs, Public

    Accounts Committee (PAC) members and staff from

    foreign embassies) have been trained. 172 accounting

    officers are expected to be trained in fourth quarter of

    FY 2013/14.

    ACGEN

  • 39

    3.4.3 Capacity building to 250 staffs from MDAs,

    RSs and embassies to enhance skills in IPSAS

    Accrual by 2014.

    Achieved 250 staff from MDAs and Embassies were trained in

    IPSAS accrual.

    ACCGEN

    3.4.4 Public Finance Act. of 2001 and regulations

    reviewed to address migration to IPSAS

    accrual by 2016

    On track The work is in progress. The Public Finance Act has

    been reviewed by stakeholders. It is waiting to be

    tabled to the Parliament for enactment.

    ACGEN

    3.4.5 Consolidated template of financial statements

    to include MDAs, Rs, LGAs, Controlled

    entities and GBEs developed by June 2016

    On track Currently the template of financial statement of

    MDAs and RS has been completed. The rest of

    entities will be taken on board as per the road map.

    ACGEN

    3.4.6 250 government accountants in MDAs /LGAs

    trained in IPSAS accrual and accrual

    modules for Epicor by September 2013

    Achieved Training was conducted on IPSAS Accrual basis to

    MDAs, RS & Embassies accountants.

    ACGEN

    3.4.7 Plan for migration towards IPSAS Accrual

    accounting is completed by December 2013.

    Achieved The 5 year road map is in place and often upgraded to

    be fully compliant to IPSAS.

    ACGEN

    3.4.8 Plan is approved for execution and

    stakeholder information sessions have been

    completed by January 2014

    Achieved The plan has been approved and is in use. Awareness

    been done to some of the stakeholders (e.g. PAC

    members). Other groups will follow

    ACGEN

    3.4.9 All legislative and policy supports have been

    identified by 31st Dec.2014

    On track Some of the legislative and policy supports have been

    identified such as accounting policy, PFA,

    Accounting manual, LGF act and TR act. The

    committee is still collecting opinions from various

    stakeholders

    ACGEN

  • 40

    3.4.10 Milestones for the transition have been

    identified and approved (E.g. Public Finance

    Act of 2001 and Regulations) amendments by

    October 2014

    On track Pending the completion of milestone 3.4.5 (Review

    of PFA and its Regulations) Some milestones have

    been identified

    ACGEN

    3.4.11 Consolidated accounts with IPSAS Accrual

    by June 2017

    On track Chart of accounts in use by LGAs has been reviewed;

    the harmonization to integrate with central

    government chart of accounts process is on-going, the

    process is planned to be completed in March 2014.

    Preparation and communication of reporting

    templates for consolidation is completed.

    ACGEN

    3.4.12 ACGEN to compile and produce financial

    statements disaggregated on the basis of

    economic classification and by sectors

    Output 3.5: Improve accountability in management of Government asset management for supporting migration to IPSAS

    Accrual

    3.5.1 Uploading of 70 additional MDAs in

    EPICOR by June 2017

    On track Currently, 35 MDAs and RS already uploaded in

    SAGE and it is anticipated that more 7 MDAs will be

    uploaded in SAGE for FY 2013/14.

    GAMD

    3.5.2 Asset Management (tracking) software

    installed, tested and users are trained on use

    of software by June 2014

    On track Assets management (tracking) software installed and

    tested, it is planned that at the end of June 2014, 40

    staff will be trained on the same.

    GAMD

    3.5.3 GAM capacity enhanced on asset

    management function by June 2016

    On Track 40 staff scheduled to attend training by June 2014. GAMD

    3.5.4 Asset Management Policy prepared and

    submitted by June 2015

    On Track Contract has been awarded and ongoing. The

    consultant has submitted an inception report and

    feedback provided by the client will be incorporated

    for submission of an interim report.

    GAMD

  • 41

    3.5.5 Valuation of Government assets in 34 MDAs

    and RSs completed by June 2017

    On Track A consultant has submitted an interim report and

    feedback provided by the client will be incorporated

    by the submission of draft final report.

    GAMD

    KRA 4: Budget Control and Oversight

    Output 4.1: Increased coverage and quality of the internal audit functions by 2016

    4.1.1 Operational plan developed and approved by

    June, 2013

    Achieved Operation Plan for 5 year 2013 – 2017 approved and

    disseminated to all Internal Audit Units.

    IAG

    4.1.2 Internal Audit manual/guidelines, standards

    and quality assurance improvement

    programme in line with International

    Standards will be in place by June, 2013

    Achieved a) The manual was prepared. Consultant is

    incorporating comments from stakeholders.

    b) Quality assurance and improvement program

    procedures (QAIP) manual was prepared,

    approved and disseminated.

    c) Consultant for preparing Audit Committees

    guidelines selected.

    d) Manuals for LGAs and MDAs have been

    reviewed by consultants (August 2012) to ensure

    consistency with the International Practice

    Framework (IPPF), training has been provided on

    IPPF and inception report was produced for

    guidelines on quality assurance. Stakeholders’

    consultation conducted.

    IAG

    4.1.5 Effective IAU and audit committee

    established and internal auditors conduct

    compliance audit and evaluate effectiveness

    of internal control in MDAs and LGAs by

    June 2016

    On Track a) Data base of internal auditors and members of

    audit committees established. Training on

    business processes of EPICOR for 38 internal

    auditors in MDAs was conducted and 20 internal

    auditors undertook professional courses (CIA,

    CFE and CPA).

    b) To date awareness workshop on roles of internal

    IAG

  • 42

    auditors for 351 stakeholders (Mayors, Council

    Chairpersons and Internal Audit) conducted.

    c) Training on roles of internal auditors to 264 audit

    committees’ chairpersons conducted.

    4.1.6 The Pilot stage of Computerized Audit will be

    finalized by June 2014

    On track -Procurement of audit software is at tendering stage.

    -Training will be conducted after procurement of

    audit software

    IAG

    4.1.7 Computerized Audit in place by June 2016.

    Pending IAG

    4.1.8 Technical Audits are conducted for 70

    Projects by 2016

    On track Technical Audits for 8 projects will be conducted in

    quarter three of FY 2013/14.

    4.1.10 550 internal auditors and other stakeholders

    trained in risk management process and risk

    based audit by June, 2016.

    On track a) 121 stakeholders have been trained on risk based

    management process.

    b) 138 internal auditors staff from MDAs and LGAs

    have been trained in risk based audit.

    c) IAGD is underway to hire a consultant to develop

    a risk management M&E framework

    IAG

    Output 4.2: Strengthened External audit functions by 2016

    4.2.1 The committee report on needs of legal

    amendments (existing laws) to contribute

    towards reaching level 3 submitted to the

    attorney General and awareness programs

    conducted by December 2012

    NEW MILESTONE:

    Maintain and enhance independence of CAG

    by 2016 (Issues related to New Constitution,

    AFROSAI-E)

    Achieved An AFROSAI-E team elevated NAOT to level 3 of

    AFROSAI-E capability model in early 2013. The

    ambition is now to move towards level 4. As such, a

    report on need to revise the Laws and Policies was

    submitted to the Attorney General’s Office for action,

    however with the ongoing Constitutional review, the

    amendment of various laws will follow after the new

    Constitution. NAOT submitted to the Constitutional

    Review committee NAOT views on Articles related

    to NAOT meanwhile addressing Independence of the

    NAOT

  • 43

    CAG.

    4.2.2 100% of auditors are moved from auditee

    premises to NAO offices by 2015

    On track Construction of Dodoma and Rukwa on going,

    Dodoma (80%), Rukwa (50%). Procurement process

    for identification a Consultant to supervise

    construction of two office buildings in Iringa and

    Mara regions is in final stage.

    NAOT

    4.2.3 300 Auditors trained on Risk Based Audit

    and 200 in IT audit by 2014

    On track The milestone will be achieved in the fourth quarter

    of FY2013/14 as the plan is to train 300 auditors on

    Risk Based Audit and 200 in IT audit.

    NAOT

    4.2.4 Two Value for Money audit reports to be

    produced each year by NAO staff without

    technical assistance from external consultant

    by 2014.

    Achieved More than 5 performance audits p.a. are being carried

    out using internal coaching, providing a base to build

    on.

    NAOT

    4.2.5 600 Auditors trained on international

    standards of auditing and full adoption of

    International Audit Standards by June 2016

    Achieved 300 Auditors trained on international standards of

    auditing and full adoption of International Audit

    Standards.

    NAOT

    4.2.6 Closing of books of accounts for Parastatals

    harmonized and audit modalities agreed by

    2014.

    On track Forum with 176 CEOs of Public bodies to discuss on

    harmonization of closing of books of accounts and

    round table with Board of Directors of Parastatals

    was conducted. Decision to harmonize closing of

    books of accounts needs time and more discussion at

    technical level. A follow up will be held on the fourth

    quarter of FY 2013/14.

    NAOT

    4.2.8 Scoping study to ascertain the parameters of

    the outstanding matters Database is

    completed by November 2012

    Delayed The scoping study has been completed. Data for the

    outstanding audit recommendations has been

    collected, analysis is on- going. The analysis will be

    completed in FY 2013/14

    NAOT

  • 44

    4.2.9 Establish a database that will separate

    findings (monetary and non monetary) and

    recommendations including by age, and

    record follow up actions by December 2013.

    On track Creation of data base for tracking outstanding audit

    recommendations is ongoing. Data for last two years

    has been collected analysis including preparations of

    software requirements is ongoing

    NAOT

    4.2.10 300 Auditors trained on audit commanding

    language (ACL) and other audit based

    software by 2014

    On track 200 Auditors has been trained on ACL. The office

    has created a group of IT auditors who eventually

    will form IT audit unit.

    NAOT

    4.2.11 NAO Headquarter is connected to 10

    Regional offices using WAN by 2014

    Achieved 12 NAOT offices have been connected with WAN

    fiber optics, the office is currently using intranet for

    internal communication with the help of WAN

    NAOT

    4.2.12 Two of five Team mate modules applied in

    auditing by October 2014

    On track The study on Two of five Team Mate module

    completed by internal staff. The activation of the

    Two of five Team Mate module and elementary

    training to 40 team mate champion will be conducted

    and completed by June 2014.

    N