Central Area Site Coordinator: Gordon MacDougall, [email protected] Central Area Campus Works Update Week Commencing 9 th April 2018 Law School – Old College Main Contractor – Graham Construction Activities External Works: Removal of phase 2 scaffold. Removal of next section of temporary roof. Continue roof works (phases 2 and 3), including joinery new dormer, glazing to roof lights and new sarking and leadwork. Painting of phase 3 window frames Deliveries/removals into/from Old College Quad – before 8.45am (every morning Monday – Friday) Internal Works: Ongoing M&E installation Phases 1, 2 and 3 Ongoing partitioning Phases 1, 2 and 3. Plastering and plaster repairs Painting and Decoration Refurbishment of windows and installation of new secondary glazing. Install drainage and new concrete slabs to lower ground floor (phases 2 and 3) Install oak veneered teaching walls. Install secondary steelwork for lift in main stair. Screed treads on main staircase Installing soft floor finishes in phases 1 & 2 Installation of new steel lintels to lower ground floor Phase 2 at feature stair. Location of works: Law School Project Site (northern half of Old College), South Side of Chambers Street, South Bridge, West College Street 175 Operatives on site Working Hours: Monday- Friday: 07:00-18:00 Saturday: 08:00 – 16:00

The University of Edinburgh | The University of Edinburgh - Central … · 2018. 4. 6. · Edinburgh Futures Institute – Enabling Works Main Contractor –Sir Robert McAlpine Activities

  • Upload
    others

  • View
    9

  • Download
    0

Embed Size (px)

Citation preview

Page 1: The University of Edinburgh | The University of Edinburgh - Central … · 2018. 4. 6. · Edinburgh Futures Institute – Enabling Works Main Contractor –Sir Robert McAlpine Activities

Central Area Site Coordinator: Gordon MacDougall, [email protected]

Central Area Campus Works Update Week Commencing 9th April 2018

Law School – Old College

Main Contractor – Graham Construction

Activities

External Works:

Removal of phase 2 scaffold.

Removal of next section of temporary roof.

Continue roof works (phases 2 and 3), including joinery new dormer, glazing to roof lights and new sarking and leadwork.

Painting of phase 3 window frames

Deliveries/removals into/from Old College Quad – before 8.45am (every morning Monday – Friday)

Internal Works:

Ongoing M&E installation Phases 1, 2 and 3

Ongoing partitioning Phases 1, 2 and 3.

Plastering and plaster repairs

Painting and Decoration

Refurbishment of windows and installation of new secondary glazing.

Install drainage and new concrete slabs to lower ground floor (phases 2 and 3)

Install oak veneered teaching walls.

Install secondary steelwork for lift in main stair.

Screed treads on main staircase

Installing soft floor finishes in phases 1 & 2

Installation of new steel lintels to lower ground floor Phase 2 at feature stair.

Location of works: Law School Project Site (northern half of Old College), South Side of Chambers Street, South Bridge, West College Street

175 Operatives on site

Working Hours: Monday- Friday: 07:00-18:00 Saturday: 08:00 – 16:00

Page 2: The University of Edinburgh | The University of Edinburgh - Central … · 2018. 4. 6. · Edinburgh Futures Institute – Enabling Works Main Contractor –Sir Robert McAlpine Activities

Central Area Site Coordinator: Gordon MacDougall, [email protected]

Central Area Campus Works Update Week Commencing 9th April 2018

Buccleuch Place/Meadow Lane Student Accommodation

Main Contractor – Graham Construction

Activities

Buildings 1-3 Furniture fit out Final decoration snags Final carpet installation

Location of works: Buccleuch Place and Meadow LaneLane Site

25 Operatives on site

Working Hours: Monday- Thursday : 07:00-17:30 Friday: 07:00 - 16:00 Saturday: 07:00 – 14:00

Page 3: The University of Edinburgh | The University of Edinburgh - Central … · 2018. 4. 6. · Edinburgh Futures Institute – Enabling Works Main Contractor –Sir Robert McAlpine Activities

Central Area Site Coordinator: Gordon MacDougall, [email protected]

Central Area Campus Works Update Week Commencing 9th April 2018

Data Technology Institute (DTI) Main Contractor – McLaughlin and Harvey Construction Activities

Installation of M&E services to all levels

Perimeter wall partitioning continuing to all levels.

Concrete finishing ongoing to walls and soffits throughout the building

Steel erection to courtyard elevation

Erect internal walls on levels 1,2, 3, 4 and 5

Continue plastering to internal walls

Install doors into glazed office partitions

Continue installation of raised access flooring

Install glazing to atrium screen

Continue works to existing level 4 roof

Carry out hot melt works to roof level (6)

Install granite cladding to bike pend walls

Carry out general repairs to precast cladding panels

Lifting existing road on Marshall Street ahead of landscaping works

Install timber flooring within cafe

The site’s tower crane is to be removed on Saturday 7th and Sunday 8th April. A full road closure of Potterrow will be in place during this removal. This was rescheduled for a second time due to high winds.

Location of works: DTI Site (next to the Informatics Forum and Dugald Stewart Building)

120 Operatives on site

Working Hours: Monday- Friday: 07:30-19:00 Saturday 07:30 – 15:00

Page 4: The University of Edinburgh | The University of Edinburgh - Central … · 2018. 4. 6. · Edinburgh Futures Institute – Enabling Works Main Contractor –Sir Robert McAlpine Activities

Central Area Site Coordinator: Gordon MacDougall, [email protected]

Central Area Campus Works Update Week Commencing 9th April 2018

Edinburgh Futures Institute – Enabling Works

Main Contractor – Sir Robert McAlpine

Activities

Continue with soft strip of services and materials throughout the building (zones 9-12)

Continue to remove asbestos containing materials from the building.

Continue with hand demolition of zone 4

Soft strip zones 9,10,11,12,13,14

Phase 4A scaffolding on going.

Phase 4A stone cleaning, roof and masonry works

Installation of zone 14 retention system and separation at zones 3 and 4

Scaffold alterations throughout

Clearing of demolition materials from zone 3

Gatehouse demolition works complete

Carry out temporary roof repairs and temporary weathering to multiple zones

All vehicle movements take place under the control of trained vehicle banksmen

Dry rot works ongoing (removals, treatment and replacement). Currently zones 8 and 12. Inspections in zone 10 and 11.

Dust suppression control measures are in place.

Location

of works:

Edinburgh

Futures

Institute

Site (Old

Royal

Infirmary

Build ing,

Quartermile

, Lauriston

Place)

75 Operatives on site

Working Hours: Monday- Thursday: 07:00-19:00 Friday: 07:00 – 15:30 Saturday 07:00 – 15:00

Page 5: The University of Edinburgh | The University of Edinburgh - Central … · 2018. 4. 6. · Edinburgh Futures Institute – Enabling Works Main Contractor –Sir Robert McAlpine Activities

Central Area Site Coordinator: Gordon MacDougall, [email protected]

Central Area Campus Works Update Week Commencing 9th April 2018

Appleton Tower Main Contractor – CCG Activities

Installing new staircase on ground level

Location of works: Appleton Tower

7 Operatives during the day 4 Operatives during the night

Working Hours: Monday- Friday: 07:00-17:00 Saturday – 07:00 – 15:00

Page 6: The University of Edinburgh | The University of Edinburgh - Central … · 2018. 4. 6. · Edinburgh Futures Institute – Enabling Works Main Contractor –Sir Robert McAlpine Activities

Central Area Site Coordinator: Gordon MacDougall, [email protected]

Central Area Campus Works Update Week Commencing 9th April 2018

Student Centre Enabling Works Main Contractor – Vital Energi

Activities

Civils

Reinstate the trench in Charles St. (Zone 1)

Continue the excavation in George Square (Zone 3)

Commence backfilling eastern end of George Square (Zone 3)

Pipe laying in George Square (Zone 3)

Continue the excavation in Charles St. Lane (Zone 5)

Form concrete plinth in Informatics HV room (Monday)

Lift the concrete access hatch over the basement of the Dugald Stewart Building (within the Bayes Centre site) Welding

Welding of pipework in Zone 5 Electrical

Install new transformer into basement of Informatics Forum (Thursday 12th)

The closure of the north side of George Square will remain in place until June 2018

HEATING SHUTDOWN SATURDAY 7th April Location of works: George Square – opposite the

Hugh Robson Building, Charles Street Lane (behind the Hugh Robson Building), Charles Street, George Square (north side).

36 Operatives on site

Working Hours: Monday – Thursday: 07:30 – 17:30 Friday: 07:30 – 15:30 Saturday – Sunday: 07:30 – 19:30