Upload
dangthuan
View
214
Download
0
Embed Size (px)
Citation preview
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Approval of final capital cost, True up for the period from the COD up to 31.03.14 and Approval of MYT tariff for the period from FY 2014-15 to FY 2018-19in respect of 2 X 45 MW thermal power plants of Bajaj Energy Pvt. Limited
Barkhera
Khambarkhera
Kundarki
Maqsoodapur
Utraula
Lucknow
Dated: 24th May, 2017
THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION
LUCKNOW
Petition Nos. 973 of 2014, 1036,1037,1038,1039 &1040 of 2015
1079, 1080, 1081, 1082 &1083 of 2016
FILED BY
Bajaj Energy Private Ltd (BEPL)
IN THE MATTER OF:
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 2 of 114
Table of Contents
1. FOREWORD
2. BACKGROUND
3. APPROVAL OF FINAL CAPITAL COST
4. APPROVAL OF PARAMETERS FOR DETERMINATION OF ARR
5. METHODOLOGY FOR TRUING UP
6. FINAL TRUE UP FOR FY 2011-12, FY 2012-13 AND FY 2013-14
7. MULTI YEAR TARIFF PETITION FOR FY 2014-15 TOFY 2018-19
8. TARIFF DESIGN AND APPROACH FOR DETERMINATION OF MYT
9. APPROVED MULTI YEAR TARIFF AND ARR
10. OTHER PROVISIONS
11. COMMISION’S DIRECTIVES
12. IMPLEMENTATION OF ORDER
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 3 of 114
Petition Nos.973 of 2014, 1036,1037,1038,1039 &1040 of 2015
1079, 1080, 1081, 1082 &1083 of 2016
BEFORE
THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION
LUCKNOW
Date of Public Hearing: 29.02.2016, 16.03.2016 and 16.08.2016
Date of Order: 24.05.2017
PRESENT:
1. Hon’ble Shri Desh Deepak Verma, Chairman
2. Hon’ble Shri Suresh Kumar Agarwal, Member
IN THE MATTEROF:
Approval of final capital cost, True-up for the period from the COD up to 31.03.14 and
Approval of MYT tariff for the period from FY 2014-15 to FY 2018-19 in respect of 2 X 45
MW thermal power plants of Bajaj Energy Pvt. Ltd.
BETWEEN
M/s Bajaj Energy Pvt. Ltd, B-10 Sector 3, Bajaj Bhawan, Jamnalal Bajaj Marg, Noida 201301(UP)
--------------- Petitioner
AND
Uttar Pradesh Power Corporation Ltd. (UPPCL) Shakti Bhawan, 14-Ashok Marg, Lucknow-226001 &Others
--------------- Respondent(s)
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 4 of 114
The following were present:
1. Shri Vinay Kumar Bonkuti, President, Bajaj Energy Pvt. Ltd.
2. Shri S. N. M. Tripathi, Director, Bajaj Energy Pvt. Ltd.
3. Shri Arun Garg, GM (F P&A), Bajaj Energy Pvt. Ltd.
4. Shri Anant Swaroop, VP, Bajaj Energy Pvt. Ltd.
5. Shri Amrendra, Sr. Manager, Bajaj Energy Pvt. Ltd.
6. Shri VKS, President (OM), Bajaj Energy Pvt. Ltd.
7. Shri Suth, Director, Bajaj Energy Pvt. Ltd.
8. Shri PradeepTandon, President, Bajaj Energy Pvt. Ltd.
9. Shri V. P. Srivastava, CE (PPA), UPPCL
10. Shri J. P. S. Gangwar, SE (PPA), UPPCL
11. Shri Nadeem Khan, EE, PPA, UPPCL
12. Shri VivekDikshit, EE, UPPCL
13. Shri Rajiv Srivastava, Advocate, UPPCL
14. CA Manish Garg, Consultant, UPPCL
15. Shri BhushanRastogi, Consultant, UPPCL
16. Shri Shafiullah, UPRVUP, Consumer Representative
17. Shri LaljiYadav, UPRVUP, Consumer Representative
18. Shri Rama Shankar Awasthi, Consumer Representative
19. Shri Avdhesh Kumar Verma, Chairman, UPRVUP, Consumer Representative
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 5 of 114
Order
1. FOREWORD :
1.1 The Bajaj Energy Private Limited (BEPL) filed petitions for Approval of Capital Cost and for True
up for Barkhera, Khambarkhera, Maqsoodapur, Kundarki and Utraula Thermal Power Stations for
F.Y. 2011-12 to 2013-14 on 25.08.2015. The petitions were admitted by the Commission vide
order dated 07.01.2016 The Petitioner got the details published in newspapers on 20.01.2016
and 21.01.2016. The Petitioner was also directed to put the petitions along with the relevant
documents on its website and to make available hard copies of the same for inspection by any
person during office hours at its Registered Office.
1.2 Subsequently the Petitioner filed petitions vide affidavit dated23.01.2016for determination of Multi
Year Tariff (MYT) for FY 2014-15 to FY 2018-19. The petition was admitted by the Commission
vide order dated 04.02.2016.
1.3 A Public Notice was given to the stakeholders and interested parties to give opportunity to submit
comments/ objections/ suggestions to petitions in writing directly to the Commission’s Office with
an advance copy to the Petitioner, personally or by post. The Public Notice for hearing was
published on 05.02.2016 and hearing in the matter was held in the office of the Commission on
29.02.16 at 11:30 hrs. During the hearing, the representative of the Petitioner summarized the
contents of the petitions, on which specific comments against the petitions were raised by
Respondents.
1.4 UPPCL filed comments on the petition on 06.11.2015 to which the Petitioner filed a rejoinder on
06.01.2016.UPPCL raised an objection that the agreed capital cost of the Bajaj energy plants as
on CoD was Rs. 2511.82 Crores, on which the Petitioner has claimed a significant additional
capitalization of Rs. 155 Crores after CoD. BEPL submitted that the additional capitalization of
Rs.85.21 Crores out of this Rs.155 Crores claimed in its Petitions has already been accepted as
deferred liability in the Expert Committee Report on the approval of capital cost for its plants.
1.5 UPPCL also raised objection that plant wise audited annual accounts and plant wise audited
details of deferred liabilities have not been submitted by the Petitioner to substantiate its claims of
additional capitalization.
1.6 Since there was no representation from the public; on request of Shri Rama Shankar Awasthi,
Consumer representative, the Commission allowed some additional time for filing of objections on
the Petitions and fixed a date for second public hearing on 15.03.2016 at 11:30 Hrs. However, a
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 6 of 114
corrigendum was issued later that the public hearing shall be held on 16.03.2016 instead of
15.03.2016.
1.7 Shri Awasthi also brought to the notice his written submissions filed during the Public Hearing on
Petition No. 852, 853, 854, 855, 856 & 869 of 2012. These include the following points:
1. The Commission should take up review of operating norms based on performance test report
(PG report) submitted by supplier and actual performance report since CoD.
2. The Commission should prepare benchmark study report for operating parameter for
45 MW thermal generating station before reviewing the operating parameters
3. The Commission should not amend or add this stabilization period for generating plant of 45
MW based on CFBC technology
4. CFBC technology is newer and an improved technology. Therefore in any case operating
parameter should not be more than operating parameter as decided by MPERC in M/s BLA
Power Pvt. Ltd. passed on Order dated 24.07.2012
1.8 The objections raised by the Consumer representatives in second public hearing have been
detailed in the following sections:
A. Shri Avadhesh Kumar Verma, Chairman, U.P Rajya Vidyut Upbhokta Parishad raised objection
that BEPL has uploaded the petitions and other related documents on www.bajajgroup.org
instead of Bajaj Energy Pvt. Ltd. website. He further raised objection that UPPCL had not
uploaded their expert committee report on the agreed capital cost of BEPL on the website and
that BEPL had not provided the report on the subletting of the contract by BIDCO (EPC
Contractor) to other contractors.
B. During the public hearing Shri Verma also brought to the notice his written submissions filed
during the Public Hearing on Petition No. 852, 853, 854, 855, 856 & 869 of 2012. He had
submitted that the Consumer’s interest must be taken care of by the Hon’ble Commission and
that private power producers in the State are already getting very high tariff which is evident from
the annual revenue requirements as submitted by UPPCL. The issue of such high tariff is
required to be examined thoroughly so that the reasons for difference in tariff in comparison to
State or Central sector generating plants may be ascertained. He further propounded that the
Hon’ble Commission may form a high level committee to probe the issue of higher cost power as
supplied through the MoU route by the power producers in the state of Uttar Pradesh (UP). He
added that a competent expert committee should be formed by the Hon’ble Commission to review
the actual performance of the petitioner plants and only on the basis of the report any decision
may be taken. Shri Verma, stressing again upon the already higher tariff as being paid to the
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 7 of 114
company, vehemently opposed any further allowance which may impact increase in tariff and
which would ultimately further burden the consumer of the State.
C. Shri Verma also submitted a letter of objections along with the findings of CAG report which
states the following points:
1. Faulty planning of Generation plants
2. Faulty installation of Power plant by BEPL
3. Default in informing Commission about the criteria of DPR
4. Discrepancies in Petition filed by BEPL related to power purchase
5. Consideration of wrong value of Debt and Equity
6. Consideration on increased IDC during construction period
7. Permission granted for increased rate on equity
8. Non-Monitoring of activities by GoUP
D. Shri Shafiullah, another Consumer representative, raised objection that M/s Bajaj Hindustan Ltd.
(BHL) had signed EPC contract for all the 5 projects with M/s Bajaj Infrastructure Development
Company (BIDCO) on 28.12.2009, much before the date of MoU signed between BHL and GoUP
on 22.04.2010 and the finalization of EPC contract by BHL prior to signing of MoU and PPA. This
implies that BHL has taken up the 5 thermal Power Projects (2X45 MW) at Barkhera,
Khambarkhera, Maqsoodapur, Kundarki and Utraula on their own which were subsequently
brought under MoU route by signing of MoU with the BHL on 14.01.2012. He further submitted
that the existing 5 projects of (2X45 MW) thermal Power Project at Barkhera, Khambarkhera,
Maqsoodapur, Kundarki and Utraula are said to have been installed under UP Government Co-
Generation policy, declaring these units as Co-Generation Plants installed by the Co-Generator,
BHL. Further, the Consumer representative raised objection that as per Regulation 11 of UPERC
Generation Tariff Regulations 2009, BHL was required to submit the Detailed Project Report
(DPR) of the Projects and scheduled Commercial Operation Date (CoD) etc. in respect of the
proposed Projects to the Commission. However, the Commission was not even aware of the fact
that BHL was in advance stage of the project by the time the approval for PPA was sought by
UPPCL.
E. Shri Shafiullah raised objection that while approving the PPA , the Commission had not
considered the issue of procedures for selection of BHL as developer and also the following facts:
1. The guidelines issued by GoI for Case-2 bidding in selection of BHL as developer
2. Specifications for the establishment of the Plant were not approved from the Commission
and Standard Bidding Documents (SBDs) framed by the Government of India (GoI) were
not followed. He added that higher O&M charges, fixed charges and variable charges had
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 8 of 114
been provided to the petitioner as compared to those already declared vide Schedule-1 in
UPERC Tariff Regulations dated 22.03.2010 and requested the Commission for recovery of
excess payment from the Petitioner.
F. Further he raised an objection on BEPL regarding setting up of plants without Railway siding and
requested the Commission to institute enquiry through an appropriate agency to examine the
circumstances of deciding 45 MW units with CFBC boilers as an IPP utility and locating the same
at forlorn places of Bajaj Sugar Factories without any Railway siding.
G. Shri Shafiullah submitted that the Expert Committees had practically not carried out any check of
the Capital Cost and did not verify the details related to IDC. He further submitted that the Expert
Committee appointed by the Commission did not examine the detailed cost structures and relied
on the figures indicated by UPPCL, thereby reducing the cost by Rs.13.85 Crore.
H. Shri Shafiullah requested the Commission to determine the correct capital cost of the 5 projects
of BEPL through some other outside agency.
I. Shri Avdhesh Kumar Verma, requested the Commission to hold another Public hearing in this
matter.
J. On the above submissions made by the Consumer representatives, Shri S.N.M.Tripathi, Director,
BEPL submitted that the softcopies of the petition and other documents were easily available on
their group company’s website. However, if the Commission thinks that it should be on their
generating company’s website, then they have no problem in uploading the documents on that
website. Further he submitted that the projects were conceived under GoUP Energy Policy on
coal based power generation to meet the gap in demand. The projects have undisputed status of
IPP and have started operations in record time. He requested the Commission to approve their
final tariff.
K. Subsequent to the public hearing, BEPL vide letter dated 12.05.2016 submitted their response to
the observations made by Consumer representative Shri Shafiullah. The submissions are given in
the following:
1. The Petitioner submitted that the observations by Consumer representative pertaining to
recommendations of the operating parameters of Bajaj Thermal Power Plant are not the
subject matter of the petition of BEPL in the current instance.
2. The Petitioner submitted that in the Petition, the observations/ submissions are made
against UPPCL and Expert Committee appointed by Hon’ble Commission and BEPL is not
the respondent intended.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 9 of 114
3. The Petitioner further submitted that the determination of operating parameters for 45MW
IPP units was disposed of by the Hon’ble Commission vide order dated 27.07.2011 after
due diligence and based on submission and deliberations of all stakeholders in public
hearing. The Consumer representative had opportunity to file objection during that time. To
raise objection now after five years seems to harass the associated parties and the Hon’ble
Commission.
4. The Petitioner further submitted that the Hon’ble Commission had decided to fix
parameters of 45MW separately by an order and by necessary amendments in the
regulations as the same were not described in UPERC (Terms and Conditions of
Generation tariff, 2009).
5. The Petitioner submitted that the Hon’ble Commission had followed the due procedure and
had invited comments from all stakeholders on its discussion papers after uploading it on
its website on 24.02.2011 and also copies of the same were forwarded to CEA, CERC and
other regulatory commissions and other stakeholders.
6. The Petitioner also submitted that prior to passing the order dated 27.07.2011, Hon’ble
Commission had reviewed all aspects in details including available benchmarks,
precedence by that time, contention related to category of plant (viz. CPP or IPP or Co-
gen) SHR, O&M, APC etc. and had also sought clarifications and details from CEA, CERC
and also held public hearing before final determination of operating parameters.
7. The Petitioner further submitted that the Hon’ble Commission had also appointed an Expert
Committee to review operating parameters after one year of continuous successful
operation. The Committee after review of data and on ground verification had
recommended the operating parameters.
L. The Petitioner vide letter dated 17.03.2016 informed the Commission that the petitions and other
related documents had been uploaded on the website of Bajaj Energy Private Limited.
M. The issues raised by Consumer representatives can be broadly classified in three categories
namely increase in quantum in PPA from 90% to 100% of the power, operating parameters and
capital cost. Regarding the increase in quantum, the Commission vide its Order on Petition Nos.
662, 663, 664, 665, 666, 689 and 701 of 2010 dated 07.12.2010 read with Order on Petition Nos.
662, 663, 664, 665, 666, 689 and 701 of 2010 dated 18.11.2010 approved the purchase of 90 %
of the power from each of the aforementioned power stations. Subsequently the Commission in
its Order on Petition Nos. 830, 833, 838, 839, 840, 842, 845, 859 of 2012 and 897 of 2013 dated
03.11.2014 approved the revised quantity of 100% power in case of the power stations of BEPL
after due diligence, considerations and public hearings.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 10 of 114
N. In the matter of determination of operating parameters for 45MW IPP units, the Commission has
taken a view vide order dated 27.07.2011 after due diligence and based on submission and
deliberations of all stakeholders in public hearing. The Commission notified the UPERC (Terms
and Conditions of Generation Tariff Regulations) (First Amendment Regulations) 2012 which
firmed up the operating parameters for thermal power plants with installed capacity up to 50 MW.
The Commission had issued an order dated 31.03.2014 on the petition filed by BEPL on review of
parameters determined for 45 MW capacity coal based generating plant based on CFBC
technology. In line with the directions in the aforesaid Order an expert Committee comprising of
Shri N. B. Mathur, Retired General Manager (Engg.), BHEL and Shri Rajiv Goyal, Retired Chief
Engineer, UPRVUNL was constituted for verifying the operational data of the IPP plants of the
Petitioner and propose the normative values for operating parameters like-Station Heat Rate and
Auxiliary Power Consumption. The matter of operational parameters considered for the true up
period FY 2011-12 to FY 2013-14 has been dealt with in detail in Section 4 of this Order. Further
operating parameters for the MYT Control Period FY 2014-15 and FY 2018-19 have been
considered as per the norms specified in the UPERC (Terms and Conditions of Generation Tariff
Regulations) 2014.
O. As per directions of the Commission, UPPCL had appointed a Committee for verification of the
actual incurred capital costs of the thermal power plants. The Committee after due audit and
verification process had recommended a capital cost of Rs. 2535.13 Crore to UPPCL in its report
dated 12.05.2014 as against an incurred cost of Rs. 2569.80 Crore submitted by BEPL. UPPCL
and BEPL after further deliberation had submitted a mutually agreed cost of Rs. 2511.82 Crore
before the Commission vide letter dated 10.10.2014.
P. For verification and prudence check of capital cost, an Expert Committee comprising Shri V. K.
Garg, Ex-Chairman, JERC and Shri P.K. Agarwal, Ex Director (Technical) UPRVUNL was
constituted by the Commission. The Committee submitted its report on 29.06.2015 in which it has
verified the Capital Cost of Rs. 2497.97 Crore. The matter of capital expenditure additional capital
expenditure has been dealt with in detail in Section 3 of this Order.
Q. The Commission conducted the third hearing on the subject petition on 16.08.2016.
R. Vide order dated 19.08.2016, the Commission had directed UPPCL, Shri A.K. Verma and Shri
R.S. Awasthi to provide written objections/ comments to the petitioner within fifteen days of the
hearing which was conducted on 16.08.2016 and the Petitioner was directed to submit responses
to these objections/ comments within the next 10 days.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 11 of 114
S. Shri Shafiullah filed objections before the Hon’ble Commission as rejoinder on 17.08.2016, which
are given in the following sections and has prayed before the Commission for appropriate action
1. Shri Shafiullah raised objection that M/s Bajaj Hindustan had started construction of the 5
nos. of 2x45 MW Plants in the year 2009 as Captive Power Plants and had already placed
the orders for Supply, Erection, Testing Commissioning and Operation of BTG for one year
on 26.12.2009 and finalized all the contracts through BIDCO during the year 2009. The
objector alleged that these Plants have not been designed and constructed under the MoU
dated 22.04.2010 and accordingly are deemed to be Captive Plants for which the Hon’ble
Commission has issued MYT Regulations in 2010 and in 2015. The Plants of BEPL fall in
the category of Captive Plant and hence the exercise for sanction of exclusive tariff for
these Plants is unlawful.
2. Shri Shafiullah mentioned that State Bank of India (SBI) while arranging the loan for the
Projects had prepared a DPR and had also determined the Capital Cost, Energy Cost and
the Tariff for 10 years for the recovery period of loan. As per the report of SBI, the total tariff
was Rs.2.93/kWh and with this the Bank had projected a return of 16% RoE and some
surplus amount besides the recovery of loan with interest, IWC cost of consumables and
the liability of taxes. He mentioned that the quoted DPR is available in public domain in
internet and has requested the Hon’ble Commission to take reference of the same before
sanction of exorbitantly higher tariff of Rs 6.82/kWh excluding Taxes.
3. Shri Shafiullah raised objection that BIDCO was appointed by BHL as Project Management
Company and not as EPC contractor through any bidding process as mentioned by BEPL
in their Petitions and therefore there has been absolutely no financial control over pricing of
the Project.
4. He further mentioned that the BTG suppliers have given guaranteed GSHR and Auxiliary
Consumptions with stringent Liquidated Clauses and accordingly the Operating Parameters
approved in favour of BEPL need to be modified in line with the terms and conditions of the
BTG contracts.
5. He submitted that from the available coal dispatch record of Coal India Limited, BEPL had
received 90.3% of their FSA quantity against their PLF of 69.8% and hence the claim that
coal was procured from the open market is not true as submitted by the Petitioner. He
requested the Hon’ble Commission to restrain UPPCL from approving such energy
charges.
6. He mentioned that the revised GoUP Power Policy had authorized only for increase in
capacity of Co-generation/ Captive Plants up to 100 MW and had allowed use of Coal/Gas
as Fuel and Ground Water and for IPP it had been permitted upto units of 250 MW and
above. Therefore all actions taken to declare these 2x45 MW Plants as IPP are unlawful.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 12 of 114
7. Shri Shafiullah objected that the RoE admissible for these Plants as per CERC regulations
is 15.5% and therefore the considerations of 0.5% incentive for these plants is unlawful.
8. Shri Shafiullah mentioned that GoUP Power Policy has authorized UPERC to determine
the tariff for these Plants, which cannot be extrapolated as power for declaring these plants
as IPP. The UPERC has already determined the tariff for such plants and the same ought
to be applicable to these plants of BEPL also.
9. Shri Shafiullah mentioned that the fee submitted by the Petitioner along with the Petition is
not as per latest revised fee regulations notified vide notification no. 429/24 dated
27.04.2010. He requested that the Petition should not be accepted for hearing without the
submission of requisite fee by the Petitioner.
10. Shri Shafiullah mentioned that the amount of additional capital cost of Rs. 112.38 Cr
mentioned in Petition No. 1079 to 1083 by the Petitioner has not been detailed either in
Petition or in Annexures and hence are arbitrarily assumed figures and hence should not
be admissible.
11. Shri Shafiullah also submitted that the start date of project given in Form 5E is not correct
as application for coal linkage, orders for supply of boilers, contract for civil works were
placed before the date mentioned in Form 5E. He requested that the earliest possible date
should be considered as the date for start of project.
12. Shri Shafiullah mentioned that the amount of equity shown in Form-6 of Petition no. 1079 to
1083 is not correct as in the report prepared by SBI, the equity is given as 25%.
13. Also, he mentioned that the amount of Capital shown in Form-5D of the Petition no. 1079 to
1083 are arbitrary and different from that submitted by UPPCL and as claimed by BEPL.
14. He mentioned that the Petitions submitted by the Petitioner neither contain the Common
Loan Agreement (CLA) nor the amount and dates of drawdown and BEPL has calculated
the interest at SBI PL rates which is normally higher than the CLA rates. Hence neither the
IDC nor interest on long term loan can be ascertained.
15. Further, Shri Shafiullah mentioned that as per the report prepared by SBI, the cost of the
project was Rs. 2320 Cr and the RoI on the loan is 11.5% as against 14% and 13.83%
claimed by BEPL.
16. Shri Shafiullah claimed that the capital cost figures mentioned in the SBI report are based
on actual work order values and include head wise scope of work. He objected that both
UPPCL and the Expert Committee appointed by the Hon’ble Commission for prudence
check did not take reference of the SBI report nor the costs were analyzed from value of
work orders. He mentioned that the Committee followed Reductio ad Absurdum technique
of reducing some amounts from the cost data of BEPL.
17. He further mentioned that the cost of Boilers and Generators mentioned in SBI report taken
from work orders is Rs. 949.53 Crore as against the amount of Rs. 1119.45Crore assumed
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 13 of 114
by BEPL and certified by UPPCL which is arbitrary and inflated. Similarly, the total cost of
overhead charges, margin money, cost of BOP (Mechanical and Electrical) switchyard etc.
as claimed by Petitioner are inflated from that considered by SBI in its report.
18. Shri Shafiullah requested the Hon’ble Commission to ensure that the Generator does not
get undue opportunity to recover more tariff by way of manipulating the fuel price and GCV.
19. Shri Shafiullah further mentioned that there are error in the fixed cost calculations in
Hon’ble Commission’s order dated 20.05.2013 which resulted in passing of higher tariff. He
further objected that higher tariff was calculated by wrongful consideration of Equity and
Return of Equity.
20. Shri Shafiullah requested the Commission to examine the tariff as the determined tariff has
been calculated even with reduction in capital cost in petition no. 1036 to 1040. He
specifically highlighted the amounts considered for AAD in Maqsoodapur, Increase in
Interest of Working Capital etc. He also alleged that BEPL has not provided any data of
coal prices and GCV in any of the Petition which amounts to irregularity.
21. He further mentioned that, as per ARR 2016-17 of UPPCL, the average power purchase
rate from NTPC plants is around Rs. 3.47/kWh and as per SBI report it is Rs. 3.25/kwh.
Therefore the tariff calculated for BEPL is fallacious.
22. Shri Shafiullah objected that there has been an unusual trend of prices of Coal and SFO as
mentioned in the petition which needs scrutiny. He has supported his objection by providing
comparable prices from other plants and based on rates taken in SBI report.
23. Shri Shafiullah mentioned that operating norms for all type/ sizes were already available in
GoI notification of 1999 but reference of the same was not included by the Commission in
their discussion paper. For finalization of operating norms for 45MW units.
24. Shri Shafiullah also requested the Commission for amending the GSHR and Auxiliary
consumption of the plant
25. Shri Shafiullah also requested the Commission for consideration of O&M charges at 2.5%
of the capital cost which was initially proposed in the discussion paper and as per GoI
notification of 1999.
26. Shri Shafiullah mentioned that the Hon’ble Commission in its order dated 11.06.2010 had
declared the plants of BEPL as increasing capacity of captive plants being established in
accordance with revised GoUP Power Policy dated 24.12.2009. Since the Commission has
already declared tariff for all captive power plants vide Schedule 1 of its CNCE Regulations
dated 22.03.2010, the same should also be applicable to BEPL and no separate tariff
calculation should be carried out. He further mentioned that the Hon’ble Commission has
further revised the CNCE regulations on 20.01.2015 and has declared for the MYT period
2014-15 to 2018-19 and same should be applicable for BEPL plants also.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 14 of 114
27. Shri Shafiullah also mentioned that the declaration of the BEPL plants as IPP is also
fallacious as the revised Power Policy of GoUP 24.12.2009 permits IPP only with units of
250 MW and above and for plants operated by coal for capacity up to 100MW as increase
in capacity of captive plant. Hence the 5 nos. of BEPL plants with 2x45MW capacity should
be considered under increase in capacity of captive plants and CNCE Tariff should be
applicable.
28. Shri Shafiullah requested the Commission to use power provided under Electricity Act 2003
regarding enforcing Commercial Principles, Economy, and Efficient and Optimum use of
resources to reduce the burden on the consumers and take action against profiteering.
T. On 22.08.2016, Shri R.S. Awasthi filed an application requesting copies of (i) enclosures of Shri
V.K. Garg, Committee (ii) enclosures of Shri Rajeev Goyal and Shri N.B. Mathur Committee (iii)
Unit wise financial statement. The copies of the enclosures were handed over to Shri R. S.
Awasthi on 05.10.2016 except unit wise financial statement which was not available with the
Commission.
U. Shri A.K. Verma vide letter dated 30.08.2016 filed written objections before the Commission
which are given below
1. He mentioned that due to incorrect consideration of auxiliary consumption, higher tariff has
been determined. Upto March 2013, Bajaj got a benefit of Rs. 115 Crore and in the next 24
years, the benefit accrued will be Rs. 2464 Crore.
2. The submitted capital cost of Rs. 2511 along with Rs. 155 of Additional Capitalisation
submitted by Bajaj is not correct. CAG in its report has highlighted many irregularities which
the expert committee appointed by the Commission should look into.
3. He requested the Commission to investigate the type of works awarded to BIDCO by BEPL
as BIDCO is a concern company of the Bajaj group. He objected that BIDCO was offered
works at higher rates by BEPL which subsequently were awarded by BIDCO to other
companies for execution.
4. He highlighted that the tariff of Rs. 6.82/kWh determined for Bajaj Energy is very high which
is increasing the electricity bills of the consumer wherein cheaper power is available in
power agencies.
5. He requested that his interim objection may be sent to BEPL and UPPCL for their reply.
The Commission vide letter UPERC/Secy/D(G)/2016-976 dated September 2016 had
forwarded the same to BEPL and UPPCL for their replies.
V. Shri. R. S. Awasthi filed written objections vide letter dated 15.09.2016 which are given as under
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 15 of 114
1. Shri Awasthi mentioned that BEPL has not provided required documents to the Committee
for prudence check of operational parameters and capital cost and requested the
Commission to not accept the Committee recommendations. He requested the
Commission to disallow an amount of Rs. 262.95 Crore as BEPL has not submitted
requisite documents before the expert Committee.
2. He submitted that there is large scale irregularity and deviations from standard bidding
procedure in awarding contract to group concern BIDCO as EPC contractor. He requested
the Commission to constitute a high power committee/ independent agency for verification
of actual capital cost, enquiry on bidding process and to determine amounts routed to
group concern.
3. He objected that payment terms were changed in LOA to favor BIDCO and thereby
BHL/BEPL paid excess amount as initial advance. He requested the Commission to not
allow IDC on the excess initial advance.
4. Shri Awasthi requested the Commission to direct BEPL to clarify whether BIDCO was
appointed as EPC or PMC contractor.
5. Shri Awasthi requested the Commission to examine the actual COD date of each unit from
test certificates as prescribed in article 6.3.1 of PPA as there are irregularities in the dates
mentioned in various committee reports.
6. Shri Awasthi requested the Commission to issue specific directions to all the Committees
for submitting detailed expenditure of around Rs. 438 Crore with supporting documents
before the Commission and also to clarify in which year the expenditure has been incurred
and whether BEPL has capitalized that amount in its books or not. He mentioned that the
Commission should not allow the expenditure until details are clarified.
7. He objected that the claim of Rs. 13.94 Crore towards land claimed by BEPL should be
disallowed
8. He requested the Commission to verify the cost of spares amounting to Rs. 63.50 Cr
claimed by BEPL in capital cost whereas the same should have been included under O&M
head in case purchased before the cutoff date. Also Commission should verify if the spares
were part of the total cost of OEM supplier as the original list was not available for review.
9. Shri Awasthi mentioned that the available 132 KV transmission line is inadequate to
evacuate power from the plant when running in full load due to capacity constraints and
hence has requested the Commission to look into the issue.
10. Shri Awasthi requested the Commission to verify the amounts deducted by BEPL under
Liquidated Damages from BTG/BOP suppliers/ contractors through sister concern due to
delay of supply or non-completion of work on time. He mentioned that such deductions
should not be considered in the amount claimed by BEPL.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 16 of 114
11. He requested the Commission to verify the pre-operative expenses amount of Rs. 65.28
Crore which has been claimed by BEPL
12. He mentioned that as per details available and shareholding pattern, both the companies
BEPL and BIDCO are related parties and requested the Commission to investigate the
accounts of BIDCO and pending enquiry, to restrict tariff to 80% of approved capital cost.
13. He requested the Commission to direct UPPCL and BEPL to submit details of energy
scheduled, coal procurement/ consumption records, secondary oil consumption and in-
house energy consumption.
14. He requested the Commission to disallow higher GSHR, Auxiliary consumption and
Secondary Fuel Oil Consumption and fix the norms as per actuals.
15. He requested the Commission to not accept the recommendation of the Committee for
additional SHR of 100 kCal/kWh during the stabilization period.
16. He mentioned that BEPL has failed to submit technical specifications of BTG as supplied
by OEM and performance test reports to the Committee due to which the Committee had to
rely on whatever information was available. He requested the Commission that till
submission of all documents, the parameters should not be approved.
17. Shri Awasthi also requested the Commission to stop payment for both the Committees due
to nonperformance of their duties.
18. The Commission vide letter UPERC/Secy/D(G)/2016-1164 dated 05.10.2016 had
forwarded the copy of interim objection letter of Shri R. S. Awasthi to BEPL and UPPCL for
their reply.
W. UPPCL vide affidavit dated 02.11.2016 has submitted their replies on the comments/
observations of the Consumer representatives. UPPCL submitted the following
1. That the mandate of section 64 (3) of the Electricity Act, 2003 is restricted to “considering
all suggestions and objections received from the public…” Inputs from Consumer
representatives do not confer upon them the right to get their views made a part and parcel
of the tariff determination process.
2. That the Consumer representatives may not be allowed to arrogate to themselves and at
best can point out a specific violation of Section 61 of the Act, in a tariff determination
exercise undertaken by a Commission. UPPCL objected that the Consumer
representatives have not spared the sanctity attached with the functioning of the
Commission by being critical about the decisions taken by the Commission on various
aspects.
3. UPPCL further mentioned that from the comments of the Consumer representatives, it
appears that they are seeking to get the entire process reversed.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 17 of 114
4. UPPCL strongly denies any wrong doing on its part as alleged in the comments of the
Consumer representatives and mentioned that it has always complied with all directions
and orders of the Commission.
5. UPPCL further stated that the role assigned to them as licensee under provisions of
Section 61 of the Electricity Act, 2003 is of much higher order than the claims made by the
Consumer representatives and therefore is not willing to cede to the observations made by
the Consumer representatives.
X. In reply to the suggestions/ comments of the Shri R. S. Awasthi, BEPL filed their responses
before the Commission vide affidavit dated 06.03.2017. BEPL submitted the following:
1. BEPL submitted that the expert committee report related with determination of Operating
Parameters was already disposed of by Hon’ble commission earlier. Also the information
memorandum was prepared for the limited purpose of fund raising only and the same
should also be referred only where relevant.
2. BEPL in their submission also mentioned that many of the objections raised by the
Consumer representative has already been settled by the Hon’ble Commission.
3. BEPL mentioned that it had provided all relevant documents as sought by the referred
Committee for Prudence check of Capital Cost. Further, the report(s) were submitted by
Expert committee to the Hon’ble Commission directly and hence BEPL is not in a position
to comment regarding the sufficiency of documents referred by Expert Committee based on
which report was prepared.
4. BEPL further mentioned that the bidding procedure adopted was already reviewed and
thoroughly scrutinized by Expert committee appointed for the purposes. Subsequently such
observations were submitted before Hon’ble Commission. BEPL reiterated that it had
strictly followed standard commercial procedures for bidding and applied reasonable
prudence considering magnitude and size of project and in optimum interest of time and
cost involved. Regarding the contention related with steel consumption, Expert Committee
had already reviewed thoroughly all aspects related with design, engineering, BOQ,
consumption etc. and has found it satisfactory. So any contention of public representative
based on his presumptive approach was baseless and is not tenable.
5. BEPL had invited prospective bidders and gave full opportunity to reach at minimum
competitive price. After various round of negotiations, BIDCO emerged as lowest bidder.
Further, to reduce contract price, payment terms were re-casted further. Such justifications
were also appraised by Expert Committees and were found satisfactory in line with
industrial practice.
6. BEPL mentioned that it does not want to comment on the concerns raised by learned
Consumer representative pertaining to the functioning, procedure adopted and prudence of
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 18 of 114
Expert Committees. It further mentioned that the Consumer representative by requesting
for constitution of another high power Committee is trying to create unnecessary hindrance
and delay in the instant tariff petition.
7. With respect to the concern for IDC, the Expert Committee appointed by UPPCL, has
already addressed this issue in its report and recommended for disallow the part of IDC
pertaining to initial advance payment to BIDCO. Hence, the request of Consumer
Representative in this regard is not relevant is already settled.
8. BEPL submitted that it had appointed M/s BIDCO as EPC Contractor and scope of same
also included services as Project Coordination and Management consultancy services
apart from Supplies, Civil Construction, Erection etc. This aspect was also duly addressed
in detailed reviewed by Expert Committees.
9. With regards to determination of COD, BEPL submitted that the Article 6.3.1 of the Power
Purchase Agreement (PPA) duly prescribed the method and procedure to determine COD.
Accordingly, COD was determined and considered based on Certificate of Independent
Engineer duly appointed by UPPCL. The issued certificate was duly endorsed and
communicated as COD to BEPL by UPPCL. Such declared COD was put on record as
COD for respective station for all purposes and question of any doubt in this regard is
baseless and not tenable.
10. BEPL submitted that M/s BHL had entered into a MoU with GoUP to implement 450 MW
TPP which was later with due permission of GoUP, assigned in favor of the SPV M/s BEPL.
BHL, being promoter, initially incurred the expenditure and which was subsequently
transferred on assignment and accordingly, the same was considered as a part of capital
cost. This was appraised in detail by Expert Committees and found to be in order. The
Expert Committees had also reviewed and scrutinized all related supporting documents,
financial statements in detail. Hence, the request of the Consumer representative to form
another Committee appears as intent of causing hurdle and delay in the tariff
determination.
11. BEPL submitted that the Capital Cost of Rs. 2511 Crore is mutually agreed and the Cost of
Land is not included as part of agreed capital cost. The concern of the representative in this
regard is already settled in the agreed cost and hence is not tenable.
12. BEPL submitted that the mandatory spares supplied by OEM with the main equipment
were fast consuming items required for plant stabilization during the warranty period of two
years and cannot be considered distinctly as initial spares as provisioned in the Regulation.
These spares are different from the critical spares which are required as backup for usage
in the medium and long term. The Regulation 17 of UPERC Regulations 2009 and 2014,
after taking an overall view on the aforesaid and having considered the requirement of
medium and long term delivery provides to procure initial spares subject to ceiling of 2.5%
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 19 of 114
of capital cost and accordingly the initial spares of Rs.63.50 crore have been considered.
BEPL has claimed initial spares within ambit of the Regulations and the Expert Committees
have found it in order after reviewing it in detail.
13. BEPL further submitted that the concern raised by the consumer representative regarding
viability of evacuation of BEPL TPP in conjunction with Cogen Power Plants through
existing 132 KV substations was baseless, misconceived and irrelevant. Since almost the
last five years, power is being evacuated uninterruptedly and in full capacity through the
existing 132 KV Transmission System.
14. BEPL stated that there was no delay in the supply/ commissioning by OEMs or EPC
contractor, hence the question of LD does not arise. All the guaranteed operating
parameters were also duly demonstrated in Performance Guarantee (PG) Test to the
satisfaction of all concerned. Hence, the concern raised are baseless and not tenable.
15. With regards to the concern raised for pre-operative expenditure, the Expert Committee
had reviewed the same and found satisfactory. Further, UPPCL has also disallowed the
part of miscellaneous fixed assets cost which was consented by BEPL. Hence the concern
of the representative is denied.
16. BEPL further submitted that the contentions of the Consumer representative pertaining to
relation between the BEPL and the EPC contractor are baseless. Both the organizations
operate under distinct professional management and all transactions were carried out at
arm’s length basis and based on merits. Transparent bidding procedure was adopted while
awarding the EPC Contract. Such concerns although settled has now been raised by the
representative only to cause unnecessary hindrance and delay in determination of tariff.
17. BEPL stated that the IPP’s were established under UP Government Energy Policy 2009
and 100% of its saleable energy is to be procured by the State nominated agency. Hence
concerned of the representative regarding fixed cost issue is misconceived and baseless.
Also, regarding the concern on competitiveness of variable cost and submission of
documents, BEPL clarified that the energy supplied is being scheduled by SLDC as per
competitive variable charges within the ambit of merit order and the relevant records with
regard to energy scheduled, coal procurement, coal consumption, auxiliary consumption,
secondary oil etc. are being regularly submitted to UPPCL with monthly billing for their due
verification.
18. With regards to the concern of the Consumer representative on the Committee’s findings
and recommendations in absence of design data from the manufacturers, BEPL reiterated
that the manufacturers design data is mentioned in the joint PG Test report of boilers and
turbines and were made available to the Committee.
19. BEPL further reiterated that the current petition is for determination of Capital cost and
Tariff and not for determination/ review of Operating Parameters. The Technical Committee
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 20 of 114
appointed for the purposes had reviewed all aspects related with the consumption of
Secondary Fuel Oil on materiality basis and found the same to be satisfactory and within
ambit of allowed Normative Parameters.
20. With regards to the relaxation provided in SHR during stabilization, the Hon’ble
Commission had considered the same after due diligence by a Technical Committee and
based on Committee’s recommendations. Hence the concern is already settled.
21. With regards to the concerns of the Consumer representative on the reports of two Expert
Committees, one for verification of capital cost and another for prudence check of operating
parameters appointed by Hon’ble Commission, BEPL does not wish to comment on the
same.
22. BEPL reiterated that the objections/ observations of the learned representative are
baseless, misconceived, misleading, not tenable and irrelevant to the petition under
consideration before the Hon’ble commission and liable to be rejected.
Y. In reply to the suggestions/ comments of Shri Avdhesh Kumar Verma, BEPL filed their responses
before the Commission vide affidavit dated 12.04.2017. BEPL submitted the following:
1. BEPL mentioned that the learned Consumer representative had referred to the CAG report
submitted before the UP Government and filed objections based on it. BEPL submitted that
current petition is for determination of capital cost and for determination of tariff and the
Hon’ble Commission has exercised its prudence procedurally as defined in the
Regulations. Hence the concerns raised at this stage by referring to the CAG report are not
relevant to the Petition.
2. BEPL submitted that the contention of the Consumer representative with regards to
mutually agreed capital cost and additional capitalization is misconceived. The agreed
capital cost has been arrived after due scrutiny of the relevant documents by the Expert
Committee nominated by UPPCL. The Expert Committee appointed by the Hon’ble
Commission had also submitted their findings before the Hon’ble Commission. BEPL
further submitted that the additional capitalization of Rs. 155 Cr for expenditure incurred up
to the cutoff date has been claimed as per the ambit of the Regulations.
3. BEPL further submitted that the concern of the Consumer representative alleging
irregularities in awarding EPC contract to BIDCO is denied. BEPL reiterated that all
transactions were carried out in strict compliance of standard industrial practices and in
transparent manner. The Entire bidding process was also scrutinized in detail by various
Expert Committee and no irregularities were observed in bidding and award pricing. The
allegations are baseless and denied.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 21 of 114
4. With regards to the allegation of high energy charges, BEPL has not submitted any
comment on the same.
Z. Summary and Conclusion by the Commission
The Commission has provided ample opportunities to all the stakeholders to file their
comments and responses regarding the subject Petition. The Commission has considered
and reviewed the submissions/ comments and recommendations of all the stakeholders
and hereby summarizes its views in the following sections
1. Status as an IPP
The Commission has already dealt upon this matter in the order dated 18.11.2010 and
thereby doesn’t find it necessary to again clarify on the matter in the current Petition.
The status of the power plant as IPP has been considered as per the prevalent policies.
2. Detailed Project Report
The Petitioner has not submitted the detailed project reports even after directions from
the Commission. However, the Commission does not see it as a deterrent in the
process of finalizing the tariff as per the Regulations.
3. Capital cost
While approving the final capital cost of the project, the Commission has exercised due
prudence and has considered recommendations of the Expert Committees and the
agreed capital cost of the Petitioner and the Respondent. The Commission has dealt
with the approval of capital cost of the project in a detailed manner in Section 3 of this
order.
4. Operating norms
The Commission has dealt with topic of operating norms in the order dated 31.03.2014.
Also the norms for determination of tariff have been approved as per the relevant
UPERC Generation Tariff Regulations. The Commission has also considered the
recommendations of the nominated Expert Committee for approval of GSHR and
Auxiliary norms for 45 MW thermal power plant of the Petitioner. However, the norms
have been dealt in detail in Section 4 of this order.
5. Additional RoE
The Commission has approved additional RoE of 0.5% in line with its order dated
09.07.2014 and the applicable Regulations.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 22 of 114
6. Fixed Cost
The Commission has determined the fixed cost for the period under True-up and MYT
as per the provisions of the relevant Generation Tariff Regulations and after due
prudence check of the submissions of the Petitioner. During the scrutiny of the Petition,
the Commission had directed the Petitioner to submit additional information in support
of their claims. The Commission has proceeded with the tariff determination of the
thermal power project only after thorough review of the submission of the Petitioner.
7. Variable cost
The variable cost shall be considered as per the norms provided in the Generation
Tariff Regulations.
8. EPC Contract
The Committees nominated by the Commission and by UPPCL for verification and
prudence check of the Capital cost had dealt with the subject topic.
The Expert Committee nominated by UPPCL under section 5 of its report had
mentioned its key observations after evaluating the EPC vendor selection process. The
Committee concluded by mentioning the following
“11) Considering the aforementioned documents and findings highlighted above in Para
1 to 10 above, we have come to the conclusion that the EPC Vendor Selection Process
was not consistent with the standard bidding practices and scope for bias/ errors may
have existed in the process.
12) In the background, we are of the opinion that Company could have adopted a more
detailed exercise in selection of the EPC Contactor.”
The Expert Committee nominated by the Commission in its report had mentioned that
while during verification of the capital cost, the Committee had reviewed various project
related agreements and also mentioned the reasons for increase in value of the EPC
contract
“The Committee also reviewed various Project Contractual Arrangements comprising of
Contract for Engineering services and Project Management awarded to SIJCON,
Contract for Design Engineering services awarded to Powertech Engineering Pvt. Ltd.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 23 of 114
and TPSC (India) Pvt. Ltd., EPC Contract awarded to BIDCO, etc. The Committee also
reviewed scope of work of other sub-contractors including LOA...”
…
The BEPL has demonstrated that the EPC contract on BIDCO was placed based on
the initial drawings, which was prepared by SIJCON, consultant of BEPL and have
been provided to the Committee.
Subsequent to the award of EPC contract, when detailed engineering was done during
project implementation, the drawings and engineering, particularly in CHP area and TG
Area was found to be deficient. …The detailed drawings which have been implemented
at the project sites prepared by M/s. Powertec Engineering Private Limited were also
provided to the Committee.
BEPL has stated that this led to a considerable change, in the scope of the EPC
Contract with BIDCO. This change, along with other changes, in the scope of the EPC
works (as detailed in the Lenders Engineer Report and Section 7.1 of the UPPCL
Expert Committee
Report) lead to a Supplementary Contract for EPC works with BIDCO for Rs 220.05
crores.”
After reviewing the reports of both the Expert Committees, the Commission is of the
opinion that the subject has been dealt with in detail. However, the Commission is
concerned about inability of the Petitioner to adopt a transparent process of
standardized two part process of international competitive bidding for award of EPC
contract. Award of large contracts for such projects should always be undertaken
through a transparent competitive bidding.
9. Filing of Tariff petition
During the review of the Petitions, the Commission had observed a number of
discrepancies in the tariff petition filed by the Petitioner. The Commission had also
directed the petitioner to submit additional/ missing information, bills etc., which was
submitted by the Petitioner in due course.
The Commission is proceeding with its order only after review and due prudence of the
Petitioner’s submission.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 24 of 114
10. Comparative cost of power
The Consumer representatives have highlighted in their submissions that the tariff
calculated for BEPL is on a higher side in respect to the tariffs other generating
stations. The Commission acknowledges the concern of the Public Respondent and
would like to reiterate that the interest of the consumer is paramount and the
Commission considers the same while approving the tariff of the Petitioner.
11. CAG Report
The Consumer representatives have highlighted about the audit and findings by CAG.
The Commission would like to mention that any such findings of CAG having an impact
on tariff will be considered in the subsequent orders of the Commission.
2. BACKGROUND:
(i) Bajaj Energy Private Limited (hereinafter ‘BEPL’ or the ‘Petitioner’) promoted by Bajaj Hindustan
Limited (hereinafter ‘BHL’), has set up 450 MW coal fired Thermal Power Plants subsequent to an
Memorandum of Understanding (hereinafter ‘MoU’) between Government of Uttar Pradesh
(hereinafter ‘GoUP’) and BHL under GoUP Energy Policy 2009.
(ii) In terms of the MoU, the Petitioner has set up 2x45 MW units of coal fired power plants at
Barkhera (District: Pilibhit), Khambarkhera (District: Lakhimpuri Kheri), Maqsoodapur (District:
Shahjahanpur), Kundarki (District: Gonda), Utraula (District: Balrampur), of Uttar Pradesh
(hereinafter collectively referred to as the ‘Thermal Power Project’).
(iii) The Petitioner and the Respondent had entered into a Power Purchase Agreement (hereinafter
‘PPA’) on 10.12.2010 for purchase of 90 % of the power from each of the aforementioned power
stations pursuant to approval of the Commission vide its Order on Petition Nos. 662, 663, 664,
665, 666, 689 and 701 of 2010 dated 07.12.2010 read with Order dated 18.11.2010.
(iv) Subsequently, GoUP vide its Order No-456 dated 26.05.2011 approved for purchase of 100%
power by the State Nominated Agency namely U.P. Power Corporation Limited (hereinafter
‘UPPCL’). Accordingly, the Petitioner entered into a Supplementary Power Purchase Agreement
(hereinafter ‘SPPA’) dated 15.06.2011 with the Respondent for the sale of 100 % saleable power
generated from the Power Stations to the respondent at the power purchase rates to be
determined by the Hon’ble Commission.
(v) The Hon’ble Commission in its Order on Petition Nos. 830, 833, 838, 839, 840, 842, 845, 859 of
2012 and 897 of 2013 dated 03.11.2014 approved the revised quantity of 100% power in case of
the Bajaj Energy Private Limited.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 25 of 114
(vi) The Petitioner filed for grant of provisional tariff based on the estimated capital cost of Rs. 2,564
crore before the Hon’ble Commission vide Petition Nos. 763, 764, 765, 766 and 767 of 2011. The
Hon’ble Commission vide its order dated 22.12.2011 allowed provisional tariff computed at 95%
of the then incurred capital expenditure of Rs. 2,307 crore.
(vii) Subsequently, the Petitioner filed petition nos. 825 to 829 of 2012 for Approval of capital cost and
determination of tariff for 2 x 45 MW coal based Thermal Power Stations situated at Barkhera,
Khambarkhera, Maqsoodapur, Kundarki and Utraula.
(viii) Since the agreed Capital Cost was not submitted, the Commission reiterated vide order dated
20.05.2013 that UPPCL and BEPL will have to arrive on agreed capital cost without further delay.
In the aforesaid order, the Commission, regarding the capital cost of MoU route projects stated:
“Since there are many power projects for procurement of power for the Discoms under MoU with
the GoUP and under PPA with UPPCL, it is necessary to evolve the mode so that the intent of the
Act and the Regulations may not be misunderstood. The reluctance shown by UPPCL in this
matter, which has caused enough delay in initiating the process for prudence check of capital
cost and subsequent determination of tariff by the Commission, hammer the requirement of
making the agreed cost as an essential part of PPA.
Therefore, it is directed that for all MoU Route projects which are under PPA with UPPCL, the agreed
ceiling capital cost shall be brought to the Commission for approval and the approved cost shall
be a part of PPA. The actual capital cost, if it is equal to the approved ceiling capital cost, shall
form the basis for prudence check and determination of tariff by the Commission. If the actual
cost is lower, then the lower cost would be taken and if it is higher, then the additional cost would
first be verified and agreed by UPPCL/GoUP and then shall be taken up by the Commission for
consideration and approval. The necessary changes to remove the ambiguity in the Regulations
shall be made accordingly.”
However, the Commission allowed plant wise revised provisional fixed charges in the order dated
20.05.2013 based on submissions of the parties. Subsequently after submission of agreed
Capital Cost, BEPL was directed to file the petitions for determination of final tariff afresh.
(ix) Accordingly, after the commissioning of the plants, the Petitioner has filed petitions for approval of
final capital cost as on COD, determination of final tariff, approval of additional capitalization and
true up for the period from COD to 31.03.14. In petition no. 973 of 2014, BEPL submitted that the
incurred capital cost of Rs.2569.80 Crore has been scrutinized by UPPCL and both have arrived
on an agreed project cost of Rs. 2511.82 Crore.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 26 of 114
(x) For reviewing the operating norms of the IPP plants of the Petitioner and proposing the normative
values for operating parameters an Expert Committee comprising Shri N. B. Mathur, Retired
General Manager (Engg.), BHEL and Shri Rajiv Goyal, Retired Chief Engineer, UPRVUNL was
constituted. The Committee submitted its report and the same was uploaded on the
Commission’s website.
(xi) The Commission constituted another Expert Committee comprising Shri V. K. Garg, Ex-
Chairman, JERC and Shri P.K. Agarwal, Ex Director (Technical) UPRVUNL for verification and
prudence check of the Capital Cost of the Project. The Committee submitted its report on
29.06.2015 in which it has verified the Capital Cost of Rs. 2497.97 Crore. The Commission
uploaded the report of the Expert Committee on its website.
(xii) On scrutinizing the petition, the Commission observed a number of discrepancies in the
submissions made by the Petitioner and issued first discrepancy note dated 07.10.2015 directing
the Petitioner to submit the additional/missing information, which was submitted by the Petitioner
on 29.10.2015. However, on the basis of scrutiny the additional submission made by the
Petitioner, it was observed that actual sample primary fuel bills had not been submitted by the
Petitioner for calculation of Energy Charge Rate (ECR), hence an additional discrepancy note
dated 06.11.2015 was issued wherein the Petitioner was directed to submit additional
clarifications/ information. The Petitioner submitted its response to the discrepancy note
on16.11.2015.
(xiii) The Commission admitted the true up petitions on 07.01.2016 subject to submission of all the
information to the satisfaction of the Commission, in replies to deficiency notes raised by the
Commission in the process.
(xiv) Subsequently the MYT petition was filed by the petitioner on 19.01.2016 and the same was
admitted on 04.02.2016 and a combined public hearing was fixed on 29.02.2016 instead of
09.02.2016.The Public hearings were further continued on 16.03.2016 and 16.08.2016.
3. APPROVAL OF FINAL CAPITAL COST
(i) The Petitioner had earlier filed for grant of provisional tariff based on the estimated capital cost of
Rs. 2,564 Crore on October 2011. The Commission had allowed provisional tariff computed at
95% of the then incurred capital expenditure of Rs. 2,307 Crore. The Commission had also
directed the Petitioner to submit actual project completion cost to UPPCL for verification, who in
turn, was required to submit the agreed costs to the Commission based on which final tariff shall
be filed by BEPL as per the provisions of the Electricity Act, 2003 and UPERC (Terms and
Conditions of Generation Tariff) Regulations, 2009.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 27 of 114
(ii) Subsequently, in September 2012, after the COD of all the power stations, BEPL submitted
before the Hon’ble Commission petitions for approval of final tariff based on actually incurred
capital costs (totaling Rs.2569.80 crore for all five power stations) up to COD bearing Petition
Nos. 825, 826, 827, 828 and 829 of 2012 ,in respect of each power station,
(iii) As the capital cost was not finalized, the Commission disposed of the aforementioned petitions
by an Order dated 20.05.2013 provisionally allowing 95% of claimed annual fixed costs agreed by
UPPCL and reiterating its earlier directive to UPPCL to submit agreed capital costs of BEPL
stations after due verification.
(iv) First Proviso under Regulation 17 of the Generation Tariff Regulations 2009 specifies that
“where the Power Purchase Agreement entered into between the generating company and the
beneficiaries provides a ceiling on capital expenditure and the actual capital expenditure exceeds
such ceiling, such increase/escalations shall be decided by the Commission on case to case
basis on an application filed by the generating company”
As the project was implemented through MoU route, the PPA should have provided a ceiling
capital cost for the project which may be admitted by the Commission after prudence check, for
the purpose of determination of the final tariff. However, no ceiling towards the capital cost was
agreed in the PPA and hence the same was never brought before the Commission for approval.
Based on this, a time limit of 3 months was provided to UPPCL to complete the verification
process and submit agreed capital costs before the Commission.
(v) In view of above direction of the Commission, UPPCL appointed an independent team of
consultants to carry out the verification of capital expenditure incurred by the BEPL. Subsequently
UPPCL submitted the committee report dated 12.05.2014 to the Commission which provides the
recommended capital cost of Rs.2535.13 crores as against the proposed capital cost of
Rs. 2569.80 claimed by BEPL. Further, the UPPCL reviewed the findings and deducted some
capital costs and communicated the final mutually agreed capital cost at Rs. 2511.82 Crores to
the Commission.
(vi) Further on 09.12.2014, an Expert Committee was constituted by the Commission to conduct the
prudence check and verification of the capital cost of BEPL. The Expert Committee reviewed
various information & facts and submitted a final capital cost of Rs. 2497.97 Crores by further
reducing the mutually agreed (between UPPCL and BEPL) Capital cost by Rs.13.85 Crores on
29.06.2015.
(vii) The plant wise capital cost recommended by the Expert Committee is shown in the following
table:
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 28 of 114
(Rs.Cr.)
Name of Power Station
Project Cost submitted
by BEPL to UPPCL Expert
Committee
Project Cost
Submitted by
UPPCL Expert
Committee
Mutually agreed Project
Cost Submitted by UPPCL
Recommended Capital Cost by Expert
Committee appointed
by the Commission
Khambarkhera 510.50 503.64 499.4 497.78
Barkhera 508.23 501.43 496.6 492.41
Maqsoodapur 504.42 497.58 494.0 492.49
Kundarki 511.42 504.61 499.8 498.11
Utraula 535.23 527.87 522.0 517.18
Total 2569.80 2535.13 2511.82 2497.97
(viii) However, the petitioner filed the current Petition on the basis of mutually agreed Capital cost with
UPPCL in place of recommended capital cost by the Expert Committee appointed by the
Commission.
Commission’s View
(i) While truing up the tariff for FY 2011-12 to FY 2013-14 and for determination of MYT tariff for FY
2014-15 to FY 2018-19, the Commission has considered the Capital cost for BEPL thermal plants
as recommended by the Expert Committee as appointed by the Commission i.e. Rs. 2497.97
Crore less a deduction as mentioned in subsequent para.
(ii) During the tariff determination process, the Consumer representatives have raised various
objections regarding the procedure adopted in awarding Engineering, Procurement and
Construction (EPC) to Bajaj Infrastructure Development Company Limited (BIDCO). According to
them, as per details available in public domain and as per the shareholding pattern, both the
companies BEPL and BIDCO are related parties. Secondly, the consumer representatives have
made submissions that there were large scale irregularities in the bidding procedure for award of
contract to group company BIDCO as EPC Contractor. The Consumer representatives have also
submitted that the payment terms were modified in the LOA to favor BIDCO and thereby BEPL
paid excess amount as initial advance to their group company who was the EPC contractor.
(iii) The Expert Committee(s) nominated by UPPCL and by the Commission respectively for the
verification and prudence check of the Capital cost have also reviewed the procedures adopted
by BEPL. The Committee nominated by UPPCL after review of all the documents concluded that
the EPC Vendor Selection Process was not consistent with the standard bidding practices and
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 29 of 114
scope for bias/ errors have existed in the process. The Committee were of the opinion that BEPL
could have adopted a more detailed exercise in selection of the EPC Contactor.
(iv) The Expert Committee nominated by the Commission in its report mentioned that during
verification of the capital cost, the Committee had reviewed various project related agreements.
BEPL in response to queries of the aforesaid Committee has stated number of reasons such as
deficient drawing particularly in CHP area and TG area and high water table at plant sites as
reasons for change in scope of work which led to award of a supplementary contract for EPC to
BIDCO by BEPL.
(v) BEPL in their submission before the Commission submitted that the bidding procedure adopted
by them was reviewed and thoroughly scrutinized by the Expert committees appointed for the
purpose. BEPL submitted that it had strictly followed the standard commercial procedures for
bidding and had applied reasonable prudence considering the magnitude and size of the project.
BEPL further submitted that both the organizations are managed professionally and all the
activities were carried out at arm’s length distance. Based on the procedure adopted and in
optimum interest of time and cost involved, BIDCO was selected for executing the EPC contract.
(vi) After reviewing the submissions of all the stakeholders, the Commission is of the opinion that
BEPL has failed to adopt a transparent process for selection of EPC contractor. It is reasonable
to conclude that the procedure adopted by BEPL has not led to efficient price discovery for the
said contract. The excess cost should not be passed on to the end consumers in the form of fixed
cost of the project.
(vii) Regulation 17 of the UPERC (Terms and Conditions of Generation Tariff) Regulations, 2009
specify that:
“Note:
Scrutiny of the project cost estimates by the Commission shall be limited to the
reasonableness of the capital cost, financing plan, interest during construction, use of
efficient technology, and such other matters for determination of tariff.”
(viii) It is also important to note that Regulation 19(6) of the UPERC (Terms and Conditions of
Generation Tariff) Regulations 2014 also specify that:
“(6) Prudence Check of Capital Expenditure: The following principles shall be adopted for
prudence check of capital cost of the existing or new projects:
…………………..
(b) Provided that in cases where benchmark norms have not been specified, prudence
check may include scrutiny of the capital expenditure, financing plan, interest during
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 30 of 114
construction, incidental expenditure during construction for its reasonableness, use of
efficient technology, cost over-run and time over-run, competitive bidding for procurement
and such other matters as may be considered appropriate by the Commission for
determination of tariff:”
(ix) The Commission after carefully considering the submissions of all stakeholders as well as the
applicable Tariff Regulations has found that BEPL did not strictly observe the competitive bidding
procedure and had a leaning towards awarding the EPC contract to its group company to
promote the business interest of the group at the expense of the consumers of the State. The
Commission is of the view that non observance of a transparent bidding process raises a valid
question about the pricing of the contract. Violation of a clean business practice certainly calls for
a penal action by the Commission. At this stage when the project has been commissioned we
cannot undo the action of the past but the action of the promoter in not ensuring a fair business
practice need to be penalized. Therefore the Commission has decided to deduct 2% of the capital
cost from the recommended capital cost by the Expert Committee appointed by the Commission.
(x) The Plant wise details of the approved Capital cost of BEPL is tabulated below:
(Rs. Cr.)
S.No Name of Power Station
Capital Cost recommended by the
Expert Committee appointed by the
Commission
Capital cost Approved by the Commission after deducting 2% from the Recommended capital
cost
1 Khambarkhera 497.78 487.82
2 Barkhera 492.41 482.56
3 Maqsoodapur 492.49 482.64
4 Kundarki 498.11 488.16
5 Utraula 517.18 506.84
Total 2497.97 2448.02
Additional Capitalization
Petitioner’s Submission
(i) In respect of additional capitalization a total of Rs.155 Crore has been filed by the Petitioner
during the True up and MYT period. The plant wise details of additional capitalization as claimed
by the Petitioner have been provided in the following table:
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 31 of 114
(Rs.Cr)
(ii) These additional capitalization are for works towards Ash Disposal Area development, Coal Yard
Area development, Machinery spares and other works etc. which are necessary for the efficient
operations of the Power Station.
Commission View
(i) The Expert Committee (appointed by the Commission) for Verification and Prudence Check of the
Capital Cost of BEPL TPP on Page No.6 of its final Report has mentioned that:
“the Committee wrote a letter dated 15th March, 2015 and email dated 24th March, 2015 seeking more clarifications from BEPL on the issues of cost of land, residential colony, subordinate debt, initial spares, etc. BEPL responded to the Committee vide email dated 24th March 2015 and 30th March 2015 and informed the following: . . . Specific comment on the para in point-6 of UPPCL Affidavit: The actual cost incurred till completion of power station COD is under prudence check before your good-self. Besides this, BEPL has deferred the liability of Rs. 85.21 crore falling within the original scope of work (EPC & Non EPC) towards work in progress…..”
(ii) Further Regulation 18(1) of Generation Tariff Regulation 2009 specifies that:
“18. Additional capitalization:
(1) The following capital expenditure within the original scope of work actually incurred after the date of commercial operation and up to the cutoff date may be admitted by the Commission, subject to prudence check:
(i) Deferred liabilities;
(ii) Works deferred for execution;
(iii) Procurement of initial capital spares in the original scope of work, subject to ceiling specified in regulation 17;
(iv) Liabilities to meet award of arbitration or for compliance of the order or decree of a court; and
S.No
Name of Power Station Additional Capitalization
claimed in true up
Additional Capitalization
claimed during MYT
1 Barkhera 3.72 14.42
2 Maqsoodapur 7.06 23.46
3 Khambarkhera 19.75 30.82
4 Kundarki 8.39 20.46
5 Utraula 4.12 23.22
Total 43.04 112.38
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 32 of 114
(v) On account of change in law.
Provided that original scope of work along with estimates of expenditure shall be submitted along with the application for provisional tariff”.
Provided further that a list of the deferred liabilities and works deferred for execution shall be submitted along with the application for final tariff after the date of commercial operation of the generating station.
(iii) The Commission has undertaken a detailed review of the various submissions and technical
justification submitted by the Petitioner for approval of the additional capitalization claimed by the
Petitioner. While reviewing the submissions of the Petitioner, the Commission has considered the
recommendations of the Expert Committee Report and has been guided by the relevant
provisions in the UPERC Generation Tariff Regulations, 2009.
(iv) The Commission had directed the Petitioner to submit various other details and information as
part of additional information requirement. The Petitioner submitted the following information with
respect to the claimed additional capitalization:
Plant wise audited Capital Cost as on C.O.D
Plant wise audited Additional Capital Expenditure from C.O.D up to 31.03.2014
Plant wise audited Additional Capital Expenditure from 01.04. 2014 to 31.03.2015
Justification Report by independent agency for coal yard augmentation and Ash Dyke
Augmentation
Plant wise Year wise expenditure relating to work deferred for execution
(v) Whereas the Petitioner was directed to submit a report by an independent agency providing
technical justification on the requirement of additional capitalization, the Report submitted by the
Petitioner is certified by the same agency which undertook the Design Engineering Services for
the project.
(vi) The Petitioner has also not submitted satisfactory evidence and verifiable information with respect
to the year wise deferred liabilities relating to works/services within the original scope of work.
(vii) In light of these discrepancies, the Commission has not approved any additional capital
expenditure on account of deferred liabilities at this stage. This may be taken up at a later stage
on submission of a separate Petition with requisite information and as per applicable UPERC
Regulations.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 33 of 114
4. APPROVAL OF PARAMETERS FOR DETERMINATION OF ARR
Petitioner’s Submission
(i) The Petitioner has considered the following norms for calculation of the
Annual Fixed Charges for true up and MYT period:
Parameter Norms
Interest on loan Capital Weighted Average rate of Interest
Depreciation including Advance against Depreciation
As per Regulations(Although for the addition during the year, depreciation is calculated for full year)
Return on Equity 16%(15.5% plus 0.5% additional ROE)
Tax on ROE Prevailing Tax rate(Grossed up ROE)
Operation and Maintenance Expenses
As per Regulations
Interest on working Capital As per Regulations
Compensation Allowance Not Applicable
(ii) For calculation of the energy charges, the Petitioner has considered relaxed norms for
Stabilization period for Gross Station Heat Rate i.e. 3000 kcal/kWh and additional Auxiliary
Consumption i.e 0.5% while determining tariff for the True up period based on the UPERC order
dated 31.03.2014.
Commission Analysis
(i) The Commission has allowed the following parameters for calculation of the Capacity Charges for
BEPL plants:
Parameter Norms
Interest on loan Capital Weighted Average rate of Interest for the period
Depreciation including Advance against Depreciation
As per Regulations(Although for the addition during the year, depreciation is calculated for half year)
Return on Equity 16%(15.5% plus 0.5% additional ROE)
Tax on ROE No grossing up is allowed as per the Regulations. The tax will be separately collected in Tax Escrow Account
Operation and Maintenance Expenses
As per Regulations
Interest on working Capital As per Regulations
Compensation Allowance Not Applicable
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 34 of 114
(ii) The Commission had issued an order dated 31.03.2014 on the petition filed by BEPL on review of
parameters determined for 45 MW capacity coal based generating plant based on CFBC
technology. In Paragraph 16 and 17 of the said Order the Commission has stated that:
“The Commission opines that a committee shall be formed for the review of operating
parameters for these new MoU route generating plants. However since the petitioner has
raised the difficulty faced by them during the initial 180 days of operation of the plant, the
Commission considers that acceptable under its power to remove difficulties as per the
Regulations keeping in view the small capacities of the plants provided that the Petitioner
could establish the fact during initial 180 days it has actually incurred losses and so
requires relaxation in norms.
From the month wise summary submitted and further submitted detailed day wise
performance by the petitioner, it could be considered that the petitioner has operated
above the allowed norms. Therefore the Commission considers allowing additional
GSHR of 100kcal/kwh during the initial 180 days of operation. As far as additional
auxiliary consumption is concerned, it is observed that on many occasions it has been
around 11.5% meaning thereby that it could have been kept to this level with good
operation performance. Therefore only additional 0.5% is allowed during the initial 180
days of operation. The decision has been taken by the Commission as an exception
which shall not be taken as precedence. However, if the expert technical committee
report would not substantiate the claim of the petitioner then it would be
reimbursed along with the prevailing simple rate of interest.
(iii) Thus, in view of the above, the expert Committee comprising of Shri N. B. Mathur, Retired
General Manager (Engg.), BHEL and Shri Rajiv Goyal, Retired Chief Engineer, UPRVUNL was
constituted for verifying the operational data of the IPP plants of the Petitioner and proposing the
normative values for operating parameters like-Station Heat Rate and Auxiliary Power
Consumption. For this the data was provided by the Commission and BEPL. Based on this data,
2 plants were sampled and out of the financial year 2013-14, 2 months were selected for each
plant to verify the data.
(iv) Based on the available data from the Petitioner, the expert Committee proposed the following
operating norms for GSHR and Auxiliary Consumption:
Parameter Norms
Gross Station Heat Rate (GSHR) 2900 kcal/kwh
Auxiliary Consumption 11%
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 35 of 114
(v) The Expert Committee recommended allowance of an additional provision for GSHR and
Auxiliary Consumption during stabilization period stating the following in its report:
“CERC had made a provision of additional 100 Kcal/KwH vide their order dated
26th March 2004, which was subsequently withdrawn w.e.f. 1.04.2006. The above orders
were for units of 200 MW and above capacity – both the provisions of first providing the
relaxation then its withdrawal. But seeing the thin margin of operations in operation of
smaller units like the ones under consideration, committee is of the view that the BEPL
units could be extended this facility during the stabilization period”
(vi) Additional allowance on SHR of 100kcal /kWh and additional allowance of 0.5% of Auxiliary
consumption has been allowed during the Stabilization period i.e. 180 days after CoD of the
plants.
5. METHODOLOGY FOR DETERMINATION OF TARIFF FOR FY 2011-12 TO
FY 2013-14 :
(i) Tariff in respect of the generating stations has been determined under UPERC (Terms and
Conditions of Generation Tariff) Regulations, 2009. Some of the pre-requisites for a generating
company to file an application for determination of tariff, as provided under Regulations, are as
below:
(1) The application shall be filed for a period of 5 years as per clause - 5 of
Regulation – 2 on the basis of terms and conditions for determination of tariff
approved by the Commission in a Power Purchase Agreement.
(2) In the case of existing generating stations, the generating company shall make
an application for determination of tariff as per Appendix - I of the Regulations.
(3) In the case of generating stations under construction provisional tariff may be
determined in advance based on capital expenditure actually incurred up to the
date of making of the application, duly audited and certified by the statutory
auditors, which shall be applicable from the date of commercial operation. On
commencement of commercial operation of the plant a fresh application shall be
made by the generating company as per Appendix – I for determination of the
final tariff based on actual capital expenditure incurred up to the date of
commencement of commercial operation of the generating station. The over or
under recovery of charges on account of provisional tariff shall be subject to
retrospective adjustment along with simple interest calculated at rate equal to
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 36 of 114
short term Prime Lending Rate of State Bank of India prevailing as on 1st April of
the relevant year.
Tariff for sale of electricity from a thermal power generating station comprise of
two parts, namely,
(i) The annual capacity (fixed) charges consisting of:
(a) Interest on loan capital;
(b) Depreciation, including Advance Against Depreciation;
(c) Return on equity;
(d) Operation and maintenance expenses including insurance;
(e) Interest on working capital; and
(f) Contribution towards R&M or any compensation allowance,
whichever is permitted
(ii) The energy (variable) charges covering fuel cost.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 37 of 114
6. Final True up for FY 2011-12, FY 2012-13 & FY 2013-14
6.1.1 Final True-up Petition submitted by the BEPL:
(i) The Petitioner has filed the petition for the final true- up for FY 2011-12, FY 2012-13
and FY 2013-14 for all the generating stations based on the audited accounts.
(ii) In the Order date 22.11.2012, the Commission had allowed provisional tariff for all
the five generating stations.
(iii) Further, based on further submissions, the Commission had allowed revised
provisional tariff for all the five generating stations in the order dated 20.05.2013.
(iv) A hearing on the matter of admittance of True-up Petition was held with the
Commission on 07.01.2016 in which the True up Petition was admitted. However as
per the Regulation 5(5), of the UPERC Tariff Regulations 2009 as amended from
time to time, the true up shall be carried out along with the petition for ARR and Tariff
for the next tariff period including additional capital expenditure incurred upto
31.03.2014.
(v) Subsequently the Petitioner filed the MYT petition and accordingly admitted the
petition vide its Order dated 04.02.2016.
(vi) Based on detailed analysis of the Petitioner’s submission, the Commission’s approval
of Final true up for the years under consideration is deliberated as follows:
Section - 1: Barkhera
Section - 2: Maqsoodapur
Section - 3: Khambarkhera
Section - 4: Kundarki
Section - 5: Utraula
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 38 of 114
6.1
Section - 1
True up Tariff
For
Barkhera
Thermal Power Station
For
FY 2011-12 to 2013-14
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Approved GFA
(Rs. in Crores)
Barkhera Station FY 2011-12 FY 2012-13 FY 2013-14
As claimed by
BEPL As Approved by the UPERC
As claimed by BEPL
As Approved by the UPERC
As claimed by BEPL
As Approved by the UPERC
Op. GFA 496.61 482.56 496.61 482.56 496.61 482.56
Additions 0.00 0.00 1.39 0.00 3.72 0.00
Deletions - - - - - -
Cl. GFA 496.61 482.56 498.00 482.56 500.33 482.56
Closing Net FA 496.22 481.82 479.70 448.12 464.05 417.78
Financing:
Op. Equity 148.98 144.77 148.98 144.77 148.98 144.77
Additions 0.00 0.00 0.42 0.00 1.12 0.00
Reduction - - - - -
Cl. Equity 148.98 144.77 149.40 144.77 150.10 144.77
Op. Accu Dep 0.00 0.00 0.39 0.38 18.29 17.75
Dep. during the year 0.39 0.38 17.90 17.37 17.99 17.37
A. A. D. 0.00 0.36 16.96 16.33 17.04 12.96
Cl. Accu. Depreciation 0.39 0.38 18.29 17.75 36.28 35.12
Op. Debts 347.63 337.79 347.23 337.05 313.35 303.35
Additions 0.00 0.00 0.97 0.00 1.63 0.00
Less : Repayment 0.39 0.74 34.86 33.71 35.02 30.33
Cl. Debts 347.23 337.05 313.35 303.35 279.95 273.01
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 40 of 114
Approved Capacity (fixed) cost for FY 2011-12, FY 2012-13 and
FY 2013-14 after True up
Barkhera Power Station
FY 2011-12 FY 2012-13 FY 2013-14
(Rs Crores)
Petition Approved Diff Petition Approved Diff Petition Approved Diff
Fixed Cost
O&M Expenses 0.40 0.40 0.00 19.36 19.36 0.00 20.47 20.47 0.00
Depreciation 0.39 0.38 -0.01 17.90 17.37 -0.53 17.99 17.37 -0.61
Advance Against Depreciation
0.00 0.01 0.01 16.96 16.33 -0.63 17.04 12.96 -4.07
Interest on Loan 1.07 1.04 -0.03 45.78 44.38 -1.40 41.03 39.86 -1.17
Return on Equity 0.65 0.51 -0.15 29.88 23.16 -6.72 30.38 23.16 -7.22
Interest on Working Capital
0.34 0.33 -0.01 17.72 15.46 -2.26 16.84 14.84 -2.00
Total 2.85 2.67 -0.18 147.60 136.07 -9.27 143.74 128.66 -15.08
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 41 of 114
Comparison of Provisional and Approved Capacity (fixed) cost for FY 2011-12,
FY 2012-13 and FY 2013-14 after True up
Barkhera Power Station
2011-12 2012-13 2013-14
(Rs Crores)
Provisional Approved
Now Difference Provisional
Approved Now
Difference Provisional Approved
Now Difference
Fixed Cost
O&M Expenses 0.38 0.40 0.02 18.39 19.36 0.97 19.44 20.47 1.03
Depreciation 0.38 0.38 0.00 17.37 17.37 0.00 17.37 17.37 0.00
Advance Against Depreciation
0.00 0.01 0.01 16.42 16.33 -0.09 16.42 12.96 -3.46
Interest on Loan 1.04 1.04 0.00 44.90 44.38 -0.52 40.17 39.86 -0.31
Return on Equity 0.63 0.51 -0.13 28.97 23.16 -5.81 28.97 23.16 -5.81
Interest on Working Capital 0.22 0.33 0.11 10.51 15.46 4.95 10.63 14.84 4.22
Total Fixed Cost 2.65 2.67 0.01 136.55 136.07 -0.48 132.99 128.66 -4.33
*Provisional fixed charges as per UPERC Order dated 20.05.2013
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
6.2
Section - 2
True up Tariff
For
Maqsoodapur
Thermal Power Station
For
FY 2011-12 to 2013-14
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Approved GFA
(Rs. in Crores)
Maqsoodapur Station FY 2011-12 FY 2012-13 FY 2013-14
As claimed by
BEPL As Approved by the UPERC
As claimed by BEPL
As Approved by the UPERC
As claimed by BEPL
As Approved by the UPERC
Op. GFA 494.01 482.64 494.01 482.64 494.01 482.64
Additions 0.00 0.00 2.18 0.00 7.06 0.00
Deletions - - - - - -
Cl. GFA 494.01 482.64 496.19 482.64 501.07 482.64
Closing Net FA 493.81 482.27 478.18 448.52 465.24 418.15
Financing:
Op. Equity 148.20 144.79 148.20 144.79 148.20 144.79
Additions 0.00 0.00 0.65 0.00 2.12 0.00
Reduction - - - - - -
Cl. Equity 148.20 144.79 148.86 144.79 150.32 144.79
Op. Accu Dep 0.00 0.00 0.19 0.19 18.01 17.57
Dep. during the year 0.19 0.19 17.82 17.38 17.82 17.38
A. A. D. 5.51 0.18 16.92 16.37 16.92 13.00
Cl. Accu. Depreciation 0.19 0.19 18.01 17.57 35.83 34.94
Op. Debts 345.80 337.85 340.10 337.48 306.90 303.73
Additions 0.00 0.00 1.53 0.00 3.42 0.00
Less : Repayment 0.19 0.37 34.73 33.75 35.07 30.37
Cl. Debts 345.61 337.48 306.90 303.73 275.24 273.36
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 44 of 114
Approved Capacity (fixed) cost for FY 2011-12, FY 2012-13 and
FY 2013-14 after True up
Maqsoodapur Power Station
FY 2011-12 FY 2012-13 FY 2013-14
(Rs Crores)
Petition Approved Diff Petition Approved Diff Petition Approved Diff
Fixed Cost
O&M Expenses 0.20 0.20 0.00 19.36 19.36 0.00 20.47 20.47 0.00
Depreciation 0.19 0.19 0.00 17.82 17.38 -0.44 17.99 17.38 -0.62
Advance Against Depreciation
0.00 0.00 0.00 16.92 16.37 -0.55 17.08 13.00 -4.09
Interest on Loan 0.53 0.52 -0.01 45.60 44.44 -1.16 41.02 39.91 -1.11
Return on Equity 0.32 0.25 -0.07 29.77 23.17 -6.61 30.43 23.17 -7.26
Interest on Working Capital
0.15 0.13 -0.02 17.59 15.27 -2.32 17.00 15.03 -1.97
Total 1.40 1.30 -0.10 147.06 135.98 -11.08 143.98 128.94 -15.05
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 45 of 114
Comparison of Provisional and Approved Capacity (fixed) cost for FY 2011-12, FY 2012-13 and FY 2013-14 after True up
Maqsoodapur Power Station
2011-12 2012-13 2013-14
(Rs Crores)
Provisional Approved
Now Difference Provisional
Approved Now
Difference Provisional Approved
Now Difference
Fixed Cost
O&M Expenses 0.19 0.20 0.01 18.39 19.36 0.97 19.44 20.47 1.03
Depreciation 0.19 0.19 0.00 17.25 17.38 0.13 17.25 17.38 0.13
Advance Against Depreciation
0.00 0.00 0.00 16.29 16.37 0.08 16.29 13.00 -3.30
Interest on Loan 0.51 0.52 0.00 44.59 44.44 -0.15 39.89 39.91 0.01
Return on Equity 0.32 0.25 -0.06 28.75 23.17 -5.59 28.75 23.17 -5.59
Interest on Working Capital 0.11 0.13 0.02 10.38 15.27 4.89 10.50 15.03 4.53
Total Fixed Cost 1.32 1.30 -0.02 135.65 135.98 0.33 132.12 128.94 -3.19
*Provisional fixed charges as per UPERC Order dated 20.05.2013
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
6.3
Section - 3
True up Tariff
For
Khambarkhera
Thermal Power Station
For
FY 2011-12 to 2013-14
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Approved GFA
(Rs. in Crores)
Khambarkhera Station FY 2011-12 FY 2012-13 FY 2013-14
As claimed by
BEPL As Approved by the UPERC
As claimed by BEPL
As Approved by the UPERC
As claimed by BEPL
As Approved by the UPERC
Op. GFA 499.42 487.82 499.42 487.82 499.42 487.82
Additions 0.00 0.00 1.57 0.00 19.75 0.00
Deletions - - - - - -
Cl. GFA 499.42 487.82 500.99 487.82 519.17 487.82
Closing Net FA 498.34 485.77 481.90 451.82 481.42 421.28
Financing:
Op. Equity 149.83 146.35 149.83 146.35 149.83 146.35
Additions 0.00 0.00 0.47 0.00 5.92 0.00
Reduction - - - - - -
Cl. Equity 149.83 146.35 150.30 146.35 155.75 146.35
Op. AccuDep 0.00 0.00 1.08 1.06 19.09 18.62
Dep. during the year 1.08 1.06 18.01 17.56 18.66 17.56
A. A. D. 0.00 1.00 17.06 16.38 17.68 12.99
Cl. Accu. Depreciation 1.08 1.06 19.09 18.62 37.75 36.18
Op. Debts 349.60 341.48 348.51 339.42 314.54 305.48
Additions 0.00 0.00 1.10 0.00 12.72 0.00
Less : Repayment 1.08 2.06 35.07 33.94 36.34 30.55
Cl. Debts 348.51 339.42 314.54 305.48 290.92 274.93
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 48 of 114
Approved Capacity (fixed) cost for FY 2011-12, FY 2012-13 and
FY 2013-14 after True up
Khambarkhera Power Station
FY 2011-12 FY 2012-13 FY 2013-14
(Rs Crores)
Petition Approved Diff Petition Approved Diff Petition Approved Diff
Fixed Cost
O&M Expenses 1.10 1.10 1.10 19.36 19.36 0.00 20.47 20.47 0.00
Depreciation 1.08 1.08 1.06 18.01 17.56 -0.44 18.66 17.56 -1.10
Advance Against Depreciation
0.00 0.00 0.06 17.06 16.38 -0.68 17.68 12.99 -4.70
Interest on Loan 2.95 2.95 2.87 45.95 44.69 -1.26 41.87 40.14 -1.73
Return on Equity 1.81 1.81 1.41 30.06 23.42 -6.65 31.53 23.42 -8.11
Interest on Working Capital
0.94 0.94 0.90 17.48 15.13 -2.35 16.94 15.05 -1.89
Total 7.88 7.41 -0.47 147.92 136.54 -11.38 147.14 129.62 -17.53
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 49 of 114
Comparison of Provisional and Approved Capacity (fixed) cost for FY 2011-12, FY 2012-13 and FY 2013-14 after True up
Khambarkhera Power Station
2011-12 2012-13 2013-14
(Rs Crores)
Provisional Approved
Now Difference Provisional
Approved Now
Difference Provisional Approved
Now Difference
Fixed Cost
O&M Expenses 1.05 1.10 0.06 18.39 19.36 0.97 19.44 20.47 1.03
Depreciation 1.05 1.08 0.01 17.46 17.56 0.10 17.46 17.56 0.10
Advance Against Depreciation
0.00 0.00 0.06 16.49 16.38 -0.11 16.49 12.99 -3.50
Interest on Loan 2.86 2.95 0.01 45.00 44.69 -0.31 135.25 40.14 -95.12
Return on Equity 1.75 1.81 -0.34 29.10 23.42 -5.69 29.10 23.42 -5.69
Interest on Working Capital 0.61 0.94 0.29 10.60 15.13 4.54 10.72 15.05 4.34
Total Fixed Cost 7.32 7.41 0.09 137.04 136.54 -0.50 133.46 129.62 -3.84
*Provisional fixed charges as per UPERC Order dated 20.05.2013
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
6.4
Section - 4
True up Tariff
For
Kundarki
Thermal Power Station
For
FY 2012-13 to 2013-14
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Approved GFA
Kundarki Station FY 2012-13 FY 2013-14
As claimed by BEPL
As Approved by the UPERC
As claimed by BEPL
As Approved by the UPERC
Op. GFA 499.81 488.16 499.81 488.16
Additions 1.30 0.00 8.39 0.00
Deletions - - - -
Cl. GFA 501.11 488.16 508.20 488.16
Cl. Net FA 484.07 455.86 472.88 424.92
Financing:
Op. Equity 149.94 146.45 149.94 146.45
Additions 0.39 0.00 2.52 0.00
Reduction - - - -
Cl. Equity 150.33 146.45 152.46 146.45
Op. Accu Dep 0.00 36.59 17.04 16.61
Dep. during the year 17.04 16.61 18.28 17.57
A. A. D. 18.04 15.69 17.29 13.37
Cl. Accu. Depreciation 17.04 16.61 35.32 34.18
Op. Debts 349.87 341.71 315.70 309.41
Additions 0.91 0.00 4.96 0.00
Less : Repayment 35.08 32.30 35.57 30.94
Cl. Debts 315.70 309.41 285.09 278.47
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 52 of 114
Approved Capacity (fixed) cost for FY 2012-13 and FY 2013-14 after True up
Kundarki Power Station
FY 2012-13 FY 2013-14
(Rs Crores)
Petition Approved Diff Petition Approved Diff
Fixed Cost
O&M Expenses 18.30 18.30 0.00 20.47 20.47 0.00
Depreciation 17.04 16.61 -0.43 18.28 17.57 -0.71
Advance Against Depreciation 18.04 14.83 -3.21 17.29 13.37 -3.93
Interest on Loan 43.57 42.62 -0.95 41.54 40.65 -0.89
Return on Equity 28.42 22.15 -6.27 30.86 23.43 -7.43
Interest on Working Capital 16.75 16.30 -0.45 16.96 17.10 0.14
Total 142.11 130.80 -11.31 145.40 132.59 -12.81
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Comparison of Provisional and Approved Capacity (fixed) cost for FY 2012-13 and FY 2013-14 after True up
Kundarki Power Station
2012-13 2013-14
(Rs Crores)
Provisional Approved Now Difference Provisional Approved Now Difference
Fixed Cost
O&M Expenses 17.33 18.30 0.97 19.44 20.47 1.03
Depreciation 16.48 16.61 0.13 17.49 17.57 0.09
Advance Against Depreciation 17.53 14.83 -2.70 16.52 13.37 -3.15
Interest on Loan 42.63 42.62 -0.01 40.47 40.65 0.18
Return on Equity 27.48 22.15 -5.33 29.15 23.43 -5.72
Interest on Working Capital 9.95 16.30 6.35 10.55 17.10 6.55
Total Fixed Cost 131.35 130.80 -0.54 133.63 132.59 -1.04
*Provisional fixed charges as per UPERC Order dated 20.05.2013
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
6.5
Section - 5
True up Tariff
For
Utraula
Thermal Power Station
For
FY 2012-13 to 2013-14
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Approved GFA
Utraula Station FY 2012-13 FY 2013-14
As claimed by
BEPL As Approved by
the UPERC As claimed by
BEPL As Approved by
the UPERC
Op. GFA 521.97 506.84 521.97 506.84
Additions 1.36 0.00 4.12 0.00
Deletions - - - -
Cl. GFA 523.33 506.84 526.09 506.84
Cl. Net FA 505.67 473.59 489.50 441.44
Financing:
Op. Equity 156.59 152.05 156.59 152.05
Additions 0.41 0.00 1.24 0.00
Reduction - - - -
Cl. Equity 157.00 152.05 157.83 152.05
Op. Accu Dep 0.00 0.00 17.65 17.10
Dep. during the year 17.65 17.10 18.93 18.24
A. A. D. 18.98 16.15 17.89 13.91
Cl. Accu. Depreciation 17.65 17.10 36.59 35.34
Op. Debts 365.38 354.79 329.70 321.54
Additions 0.95 0.00 1.93 0.00
Less : Repayment 36.63 33.24 36.83 32.15
Cl. Debts 329.70 321.54 294.80 289.39
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 56 of 114
Approved Capacity (fixed) cost for FY 2012-13 and FY 2013-14 after True up
Utrauala Power Station
FY 2012-13 FY 2013-14
(Rs Crores)
Petition Approved Diff Petition Approved Diff
Fixed Cost
O&M Expenses 18.14 18.14 0.00 20.47 20.47 0.00
Depreciation 17.65 17.10 -0.56 18.93 18.24 -0.69
Advance Against Depreciation 18.98 15.13 -3.85 17.89 13.91 -3.98
Interest on Loan 45.10 43.88 -1.22 43.18 42.25 -0.94
Return on Equity 29.42 22.80 -6.63 31.95 24.33 -7.62
Interest on Working Capital 16.47 15.39 -1.07 17.08 17.25 0.18
Total 145.76 132.44 -13.32 149.50 136.45 -13.06
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 57 of 114
Comparison of Provisional and Approved Capacity (fixed) cost for FY 2012-13 and FY 2013-14 after True up
Utraula Power Station
2012-13 2013-14
(Rs Crores)
Provisional Approved Now Difference Provisional Approved Now Difference
Fixed Cost
O&M Expenses 17.18 18.14 0.96 19.44 20.47 1.03
Depreciation 17.10 17.10 0.00 18.30 18.24 -0.05
Advance Against Depreciation 18.50 15.13 -3.37 17.29 13.91 -3.38
Interest on Loan 44.23 43.88 -0.34 42.36 42.25 -0.11
Return on Equity 28.50 22.80 -5.71 30.51 24.33 -6.18
Interest on Working Capital 10.16 15.39 5.24 10.91 17.25 6.34
Total Fixed Cost 135.66 132.44 -3.22 138.80 136.45 -2.36
*Provisional fixed charges as per UPERC Order dated 20.05.2013
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 58 of 114
Summary of Fixed Cost for
FY 2011-12, FY 2012-13 and FY 2013-14 after True up
(Rs Crore)
FY 2011-12 FY 2012-13 FY 2013-14
Provisional Petition Approved Difference Provisional Petition Approved Difference Provisional Petition Approved Difference
Fixed Cost
Barkhera 2.65 2.85 2.67 -0.18 136.55 147.60 136.07 -11.53 132.99 143.74 128.66 -15.08
Maqsoodapur 1.32 1.40 1.30 -0.10 135.65 147.06 135.98 -11.08 132.12 143.98 129.94 -15.05
Khambarkhera 7.32 7.88 7.41 -0.47 137.04 147.92 136.54 -11.38 133.46 147.14 129.62 -17.53
Kundarki - - - - 131.35 142.11 130.80 -11.31 133.63 145.40 132.59 -12.81
Utraula - - - - 135.66 145.76 132.44 -13.32 138.80 149.50 136.45 -13.06
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 59 of 114
7. MULTI YEAR TARIFF PETITION FOR FY 2014-15 to 2018-19 :
(A) Generation Capacities of BEPL :
(i) The Petitioner Bajaj Energy Private Limited (hereinafter ‘BEPL’) promoted by Bajaj
Hindustan Limited (hereinafter ‘BHL’) has set up 450 MW coal fired Thermal Power Plants
subsequent to an Memorandum of Understanding (hereinafter ‘MoU’) between Government
of Uttar Pradesh (hereinafter ‘GoUP’) and BHL under GoUP Energy Policy 2009.
(ii) In terms of the MoU, the Petitioner has set up 2x45 MW units of coal fired power plants at
Barkhera (District: Pilibhit), Khambarkhera (District: Lakhimpuri Kheri), Maqsoodapur
(District: Shahjahanpur), Kundarki (District: Gonda), Utraula (District: Balrampur), of Uttar
Pradesh (hereinafter collectively referred to as the ‘Thermal Power Project’).
(iii) The Petitioner and the Respondent had entered into a Power Purchase Agreement
(hereinafter ‘PPA’) on 10.12.2010 for purchase of 90 % of the power from each of the
aforementioned power stations pursuant to approval of the Commission vide its Order on
Petition Nos. 662, 663, 664, 665, 666, 689 and 701 of 2010 dated 07.12.2010 read with
Order on Petition Nos. 662, 663, 664, 665, 666, 689 and 701 of 2010 dated 18.11.2010.
(iv) Subsequently, GoUP vide its Order No-456 dated 26.05.2011 approved for purchase of
100% power by the State Nominated Agency namely U.P. Power Corporation Limited
(hereinafter ‘UPPCL’). Accordingly, the Petitioner entered into a Supplementary Power
Purchase Agreement (hereinafter ‘SPPA’) dated 15.06.2011 with the Respondent for the
sale of 100 % saleable power generated from the Power Stations to the respondent at the
power purchase rates to be determined by the Hon’ble UPERC.
(v) The Hon’ble UPERC in its Order on Petition Nos. 830, 833, 838, 839, 840, 842, 845, 859 of
2012 and 897 of 2013 dated 03.11.2014 approved the revised quantity of 100% power in
case of the M/s Bajaj Energy Limited.
(vi) Accordingly the details of Installed Capacity of the generating stations of the Petitioner are
listed in table as below:
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 60 of 114
Generation Capacities of the BEPL
SN Thermal Power
Station Unit No.
Installed
Capacity Date of Commercial Operation
1
Barkhera
1 45 MW 24-03-2012
2 2 45 MW 24-03-2012
3
Maqsoodapur
1 45 MW 28-03-2012
4 2 45 MW 28-03-2012
5
Khambarkhera
1 45 MW 10-03-2012
6 2 45 MW 10-03-2012
7
Kundarki
1 45 MW 21-04-2012
8 2 45 MW 21-04-2012
9
Utraula
1 45 MW 24-04-2012
10 2 45 MW 24-04-2012
Total 10 450 MW
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 61 of 114
(B) ARR & Tariff submitted by BEPL :
The Multi Year Tariff (MYT) petition submitted by the Petitioner has average of tariffs and total
ARR for FY 2014-15 to FY 2018-19 for all the generating stations as indicated below:
Table 1: Average Tariff for the MYT Control Period FY14-19 as submitted by the Petitioner (Rs/kWh)
Table 2: ARR for the MYT Control Period FY14-19 as submitted by the Petitioner
(Rs Cr)
8. TARIFF DESIGN AND APPROACH FOR DETERMINATION OF MYT
The tariff is structured on the following basis:
(i) The data of GFA, Debt, Equity on 01.04.14, as approved by the Commission in the true-up of FY
2013-14 in this Tariff Order, has been considered as baseline data for calculation of tariff and
ARR for the Petitioner for the MYT period from FY 2014-15 to
FY 2018-2019.
SN BEPL FY 14 -15 FY 15 - 16 FY 16 - 17 FY 17 - 18 FY 18 - 19
1 Barkhera 6.50 6.44 6.40 6.36 6.33
2 Maqsoodapur 6.61 6.56 6.52 6.48 6.45
3 Khambarkhera 6.74 6.70 6.66 6.62 6.58
4 Kundarki 6.52 6.46 6.42 6.38 6.35
5 Utraula 6.52 6.47 6.43 6.39 6.35
SN BEPL FY 14 -15 FY 15 - 16 FY 16 - 17 FY 17 - 18 FY 18 - 19
1 Energy Sent out (MU)
2982.12 2982.12 2982.12 2982.12 2982.12
2 Fixed Charges (Rs/kWh)
2.29 2.24 2.20 2.16 2.12
3 Energy Charges (Rs/kWh)
4.29 4.29 4.29 4.29 4.29
4 Total Charges (Rs/kWh)
6.58 6.53 6.49 6.45 6.41
5 ARR (Rs Cr.) 1961.52 1945.94 1935.00 1922.95 1911.44
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 62 of 114
(ii) Return on Equity has been considered as 16.0 % as provided in the UPERC Generation Tariff
Regulations, 2014.
(iii) The rate of the interest shall be the weighted average rate of interest calculated on the basis of
actual loans at the beginning of each year and shall be adjusted based on actual loan each year
accordingly. If there is no actual loan for a particular year but normative loan is still outstanding,
the last available weighted average of interest has been considered.
(iv) The Petitioner has got its loan refinanced therefore the benefits thereof shall be shared between
the beneficiaries and generating company in the ratio of 2:1. The Commission appreciates the
efforts of the Petitioner to refinance its loans and passing of benefits to the beneficiaries in line
with Regulation 25(i) (e). However, as per Regulation 6. (4) (d), the benefits due to re-financing
of loan will be considered during true up of the generating stations. Further, the Commission has
observed that interest rates have shown a declining trend and directs the Petitioner to further re-
negotiate the interest rates for benefit of all stakeholders.
(v) Depreciation has been allowed as provided in Regulation 25 (ii) in the UPERC Generation Tariff
Regulations, 2014.
(vi) The O&M expenditure has been allowed as per the normative values provided in Regulation
25(iv) of the UPERC Generation Tariff Regulations, 2014
(vii) Working capital requirement has been allowed as per Regulation 25 (v) of the UPERC
Generation Tariff Regulations 2014. The rate of interest on working capital has been allowed
on normative basis as the Bank Rate as on 1.4.2014 or as on 1st April of the year during the
tariff period FY 2014-15 to FY 2018-19 in which the generating station or a unit thereof is
declared under commercial operation, whichever is later.
(viii) Thus the MYT for Thermal Power Stations of the Petitioner for FY 2014–2015 to
FY 2018–2019 has been worked out adopting the above elaborated methodology.
9. APPROVED MULTI YEAR TARIFF AND ARR:
Generating station wise approved MYT and ARR for FY 2014 - 15 to FY 2018 - 19 shall be as
detailed in following sections.
9.1 - Section - 1 Barkhera
9.2 - Section - 2 Maqsoodapur
9.3 - Section - 3 Khambarkhera
9.4 - Section - 4 Kundarki
9.5 - Section - 5 Utraula
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 63 of 114
9.1
Section-1
Multi Year Tariff
For
Barkhera
Thermal Power Station
For
FY 2014 - 15 to FY 2018 - 19
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 64 of 114
9.1.1 ARR and MYT as according to petition:
In the petition, the Petitioner has proposed the fixed, variable and total charges for the electricity sent out
as given in the table below:
9.1.2 ARR and MYT as determined by the Commission:
i. Capacity (Fixed) Charges:
(a) Provisions under Regulations:
For determination of components of fixed charges for MYT period of FY 2014 - 15 to
FY 2018 - 19, the Commission opines that the parameters provided under UPERC Generation
Tariff Regulations, 2014 shall be considered. Hence, the Commission has decided to allow the
components of fixed charges as below:
Components of Fixed Charge
Value Remark
Return on equity 15.50% + 0.5% = 16 % As per the Regulations and an additional return of 0.5% applicable to projects completed within specified timeline
Interest on Loans
FY15 - 13.43% FY16 - 11.76% FY17 - 11.72% FY18 – 11.67% FY19 – 11.59%
Weighted average of interest on loans for FY 2014-15 to FY 2018-19
O & M Expenses Normative As per the Regulations
Interest on working capital
13.50 % As per the Regulations
Barkhera 2014-15 2015-16 2016-17 2017-18 2018-19
Energy Sent out (MU)
596.42 596.42 596.42 596.42 596.42
Fixed Charges (Rs/kWh)
2.24 2.18 2.14 2.11 2.07
Variable Charges (Rs/kWh)
4.26 4.26 4.26 4.26 4.26
Total Charges (Rs/kWh)
6.50 6.44 6.40 6.36 6.33
ARR (Rs Cr.) 387.69 383.94 381.89 379.62 377.46
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 65 of 114
(b) Gross Fixed Assets (GFA) and its Components :
For the determination of Return on Equity, Interest on balance Loans and
Depreciation it is essential to determine the value of GFA duly supported with the
financing program and the value of NFA at the end of each financial year. Therefore,
the GFA and NFA at the end of each financial year commencing from FY 2014-15 to
FY 2018-19 has been worked out along with Equity and Debts taking base figures as
allowed in the final True-up for FY 2013-14.
Calculation of GFA & NFA including financing
(Rs Crores)
Barkhera Power Station
2014-15 2015-16 2016-17 2017-18 2018-19
Op. GFA 482.56 482.56 482.56 482.56 482.56
Additions 0.00 0.00 0.00 0.00 0.00
Deletions - - - - -
Cl. GFA 482.56 482.56 482.56 482.56 482.56
Cl. Net FA 389.69 361.59 333.50 305.40 277.31
Financing:
Op. Equity 144.77 144.77 144.77 144.77 144.77
Additions 0.00 0.00 0.00 0.00 0.00
Reduction - - - - -
Cl. Equity 144.77 144.77 144.77 144.77 144.77
Op. AccuDep 35.12 63.22 91.31 119.41 147.50
Dep. during the year
28.09 28.09 28.09 28.09 28.09
Cl. Accu. Depreciation
63.22 91.31 119.41 147.50 175.60
Op. Debts 273.01 244.92 216.82 188.73 160.63
Additions 0.00 0.00 0.00 0.00 0.00
Less : Repayment 28.09 28.09 28.09 28.09 28.09
Cl. Debts 244.92 216.82 188.73 160.63 132.54
(c) RoE, Depreciation, O&M and Interest on Loans :
On the basis of decisions of the Commission in the forgoing paragraphs and the
details of GFA, NFA and financing as indicated above the Return on Equity,
Depreciation, O&M expenditure and Interest on Loans, at the end of each financial
year of the control MYT period from FY 2014-15 to FY 2018-19, is worked out as
under:
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 66 of 114
Details of approved RoE, Depreciation, O&M and Interest on Loans (Rs Crores)
Sl.No. Particular 2014-15 2015-16 2016-17 2017-18 2018-19
1 O&M Expenses
21.51 22.86 24.30 25.83 27.46
2 Depreciation 28.09 28.09 28.09 28.09 28.09
3 Interest on Loan
34.78 27.15 23.77 20.39 16.99
4 Return on Equity
23.16 23.16 23.16 23.16 23.16
Total: 107.55 101.27 99.32 97.47 95.71
(d) Interest on Working Capital:
The amount of working Capital and Interest on working Capital for the control period of F.Y. 2014-15 to FY 2018-19 as determined by the Commission are as under:
Annual Receivables of Barkhera Power Station required for
Calculation of Working Capital: (Rs Crore)
Particulars
2014-15 2015-16 2016-17 2017-18 2018-19
Annual Capacity [Fixed] Charges
122.54 116.21 114.27 112.44 110.70
Cost of Fuel 253.20 253.98 253.98 253.98 253.98
Total Receivables 375.74 370.18 368.25 366.42 364.67
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 67 of 114
Interest on Working Capital as determined by the Commission
(Rs Crore)
SN Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
1 Cost of Coal for 60 days
41.55 42.02 42.02 42.02 42.02
2 Cost of Secondary Fuel Oil for 2 months
0.79 0.46 0.46 0.46 0.46
3 O & M for 1 month 1.79 1.91 2.03 2.15 2.29
4 Maintenance Spares @20% of O & M Exp.
4.30 4.57 4.86 5.17 5.49
5
Receivables equivalent to 2 months capacity and energy charges for sale of electricity
62.62 61.70 61.38 61.07 60.78
6 Working Capital 111.06 110.65 110.74 110.86 111.03
7 Rate of Interest 13.50% 13.50% 13.50% 13.50% 13.50%
8 I W C 14.99 14.94 14.95 14.97 14.99
(e) Capacity (Fixed) Charge per unit of Generation :
Based on above the capacity charges as claimed by Petitioner and as approved by
the Commission are tabulated herein for the MYT period of F.Y. 2014-15 to F.Y 2018-
19. Ex-bus energy sent out has been taken from the data mentioned in Section 8.1.1:
Fixed Charges as claimed and as approved by the Commission
Particulars
FY 15 FY 16
As claimed by BEPL
As determined
by the Commission
Diff. (if any) As claimed by BEPL
As determined
by the Commission
Diff. (if any)
O&M Expenses 21.51 21.51 0.00 22.86 22.86 0.00
Depreciation 29.46 28.09 -1.36 29.88 28.09 -1.78
Interest on Loan 36.16 34.78 -1.38 28.77 27.15 -1.62
Return on Equity 30.73 23.16 -7.57 31.32 23.16 -8.16
Interest on Working Capital
15.26 14.99 -0.27 15.23 14.94 -0.29
Special Allowance on Refinancing of loan
0.51 - -0.51 1.82 - -1.82
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 68 of 114
Particulars
FY 15 FY 16
As claimed by BEPL
As determined
by the Commission
Diff. (if any) As claimed by BEPL
As determined
by the Commission
Diff. (if any)
Total (Rs Cr) 133.63 122.54 -11.09 129.89 116.21 -13.68
Ex-bus Energy Sent Out (kwh)
596.42 596.42 0.00 596.42 596.42 0.00
Fixed Cost per Unit
2.24 2.05 -0.19 2.18 1.95 -0.23
Particulars
FY 17 FY 18
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
O&M Expenses 24.30 24.30 0.00 25.83 25.83 0.00
Depreciation 29.97 28.09 -1.87 29.97 28.09 -1.87
Interest on Loan 25.28 23.77 -1.52 21.67 20.39 -1.29
Return on Equity 31.41 23.16 -8.25 31.41 23.16 -8.25
Interest on Working Capital
15.24 14.95 -0.29 15.25 14.97 -0.28
Special Allowance on Refinancing of loan
1.64 - -1.64 1.45 - -1.45
Total (Rs Cr) 127.84 114.27 -13.57 125.57 112.44 -13.13
Ex-bus Energy Sent Out (kwh)
596.42 596.42 0.00 596.42 596.42 0.00
Fixed Cost per Unit
2.14 1.92 -0.23 2.11 1.89 -0.22
Particulars
FY 19
As claimed by
BEPL
As determined
by the
Commission
Difference
(if any)
O&M Expenses 27.46 27.46 0.00
Depreciation 29.97 28.09 -1.87
Interest on Loan 18.06 16.99 -1.07
Return on Equity 31.41 23.16 -8.25
Interest on Working Capital 15.26 14.99 -0.27
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 69 of 114
ii. Representative calculation of Variable Charges:
Variable charge per unit of Generation – For the purpose of calculation of
normative working capital
Based on the operation norms provided in the UPERC Generation Tariff Regulations,
2014, the variable charge per unit of generation for Barkhera Power Station for the MYT
period of F.Y. 2014-15 to F.Y 2018-19 has been arrived at. The calculation shown below
is representative of the variable cost calculation and has been used to arrive at some of
the components of normative working capital.
Variable charge per unit of generation for Barkhera Power Station
Description Unit 2014-15 2015-16 2016-17 2017-18 2018-19
Capacity MW 90.00 90.00 90.00 90.00 90.00
PAF % 85.00 85.00 85.00 85.00 85.00
Gross generation MU 670.14 670.14 670.14 670.14 670.14
Auxiliary Consumption
% 11.00 11.00 11.00 11.00 11.00
Net units sent out MU 596.42 596.42 596.42 596.42 596.42
Gross station heat rate
Kcal/kWh 2890 2890 2890 2890 2890
Specific oil consumption
ml/kWh 1.00 1.00 1.00 1.00 1.00
Calorific value of secondary fuel
KCal/Lt 10.00 10.00 10.00 10.00 10.00
Weighted average landed price of coal
Rs./Kg 4.26 4.72 4.72 4.72 4.72
Calorific value of Coal
kCal/kg 3312.52 3623.58 3623.58 3623.58 3623.58
Weighted average landed price of secondary fuel
Rs./mL 0.07 0.04 0.04 0.04 0.04
Energy charge rate (ECR)
Rs/kWh 4.25 4.26 4.26 4.26 4.26
Special Allowance on Refinancing of
loan 1.25 -1.25
Total (Rs Cr) 123.41 110.70 -12.71
Ex-bus Energy Sent Out (kwh) 596.42 596.42 0.00
Fixed Cost per Unit 2.07 1.86 -0.21
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 70 of 114
(a) Cost of alternative coal supply:
Regulation 26 (iv) of the UPERC Generation Tariff Regulations 2014 specifies the norms
for the calculation of cost of alternative coal supply:
“In case of part or full use of alternative source of fuel supply by coal based thermal
generating stations other than as agreed by the generating company and beneficiaries
in their power purchase agreement for supply of contracted power on account of
shortage of fuel or optimization of economical operation through blending, the use of
alternative source of fuel supply shall be permitted to generating station;
Provided further that the weighted average price of use of alternative source of fuel
shall not exceed 30% of base price of fuel computed as per clause (v) of this
regulation;
Provided also that where the energy charge rate based on weighted average
price of use of fuel including alternative source of fuel exceeds 30% of base
energy charge rate as approved by the Commission for that year or energy
charge rate based on weighted average price of use of fuel including alternative
sources of fuel exceeds 20% of energy charge rate based on weighted average
fuel price for the previous month, whichever is lower shall be considered and in
that event, prior consent of the beneficiary shall be taken by the generator by
serving a notice upon the beneficiary in writing not later than seven working
days in advance.
Provided that if the beneficiary does not respond to the notice given by the generator in
writing within the above stipulated time, the beneficiary shall be liable for payment of
fixed charges to generator.
Further Alternative coal supply from CIL beyond the FSA must be done through e-
auction route and for procurement of domestic open market coal and imported coal the
generating companies shall follow a transparent competitive bidding process so as to
identify a reasonable market price.
However the Commission directs that the Committee should be formed for carrying out
the above mentioned process with at least one member of the Beneficiary.
Accordingly the cost of alternative coal supply for FY 2016-17 shall not exceed the
following:
Period Maximum ECR (Rs/kWh)
01.04.2016 to 31.03.2017 5.54
The rates for the subsequent years shall be computed as per the Regulations.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 71 of 114
(b) Adjustment of Rate of Energy Charge on Account of Variation in price or
Heat Value of Fuels:
Any variation shall be adjusted on month to month basis on the basis of Gross Calorific
Value of coal or gas or liquid fuel as received and landed cost incurred by the generating
company for procurement of coal, oil, or gas or liquid fuel, as the case may be. No
separate petition needs to be filed with the Commission for fuel price adjustment. In case
of any dispute, an appropriate application in accordance with Uttar Pradesh Electricity
Regulatory Commission (Conduct of Business) Regulations 2004, as amended from time
to time or any statutory re-enactment thereof, shall be made before the Commission.
Provided further that copies of the bills and details of parameters of GCV and price of fuel
i.e. domestic coal, imported coal, e-auction coal, lignite, liquid fuel etc., details of blending
ratio of the imported coal with domestic coal, proportion of e-auction coal shall also be
displayed on the website of the generating company. The details should be available on its
website on monthly basis for a period of three months.
However, UPPCL shall verify the “As Received GCV” and landed cost of coal from
the original coal purchase bills.
BEPL shall be entitled to recover / adjust any change in fuel cost according to the
provisions set out in the relevant UPERC Generation Tariff Regulations.
iii. Summary – Capacity Charges (Cost):
The capacity charges (costs) for Barkhera Thermal Power Station for the MYT period of
FY 2014-15 to FY 2018-19 is summarized in the table below.
Fixed Cost per kWh as claimed with those as allowed by the Commission
Particulars
FY 15 FY 16
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
Fixed Cost (Rs Cr.)
133.63 122.54 -11.09 129.89 116.21 -13.68
F. C. per Unit (In Rs/kWh)
2.24 2.05 -0.19 2.18 1.95 -0.23
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 72 of 114
Particulars
FY 17 FY 18
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
Fixed Cost (Rs Cr.)
127.84 114.27 -13.57 125.57 112.44 -13.13
F. C. per Unit (In Rs/kWh)
2.14 1.92 -0.23 2.11 1.89 -0.22
Particulars
FY 19
As claimed by BEPL As determined by the
Commission Diff.
(if any)
Fixed Cost (Rs Cr.)
123.41 110.70 -12.71
F. C. per Unit (In Rs/kWh)
2.07 1.86 -0.21
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 73 of 114
9.2
Section-2
Multi Year Tariff
For
Maqsoodapur
Thermal Power Station
For
FY 2014 - 15 to FY 2018 - 19
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 74 of 114
19.2.1 ARR and MYT as according to petition:
In the petition, the Petitioner has proposed the fixed, variable and total charges for the electricity sent out
as given in the table below:
19.2.2 ARR and MYT as determined by the Commission:
i. Capacity (Fixed) Charges:
(a) Provisions under Regulations:
For determination of components of fixed charges for MYT period of FY 2014 - 15 to
FY 2018 - 19, the Commission opines that the parameters provided under UPERC
Generation Tariff Regulations, 2014shall be considered. Hence, the Commission has
decided to allow the components of fixed charges as below:
Components of Fixed Charge
Value Remark
Return on equity 15.50% + 0.5% = 16 %
As per the Regulations and an additional return of 0.5% applicable to projects completed within specified timeline
Interest on Loans
FY15 - 13.43% FY16 - 11.76% FY17 - 11.72% FY18 – 11.67% FY19 – 11.59%
Weighted average of interest on loans for FY 2014-15 to FY 2018-19
O & M Expenses Normative As per the Regulations
Interest on working capital
13.50 % As per the Regulations
Maqsoodapur 2014-15 2015-16 2016-17 2017-18 2018-19
Energy Sent out (MU)
596.42 596.42 596.42 596.42 596.42
Fixed Charges (Rs/kWh)
2.26 2.22 2.18 2.14 2.10
Variable Charges (Rs/kWh)
4.34 4.34 4.34 4.34 4.34
Total Charges (Rs/kWh)
6.60 6.56 6.52 6.48 6.45
ARR (Rs Cr.) 393.98 391.09 388.98 386.64 384.40
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 75 of 114
(b) Gross Fixed Assets (GFA) and its Components :
For the determination of Return on Equity, Interest on balance Loans and
Depreciation it is essential to determine the value of GFA duly supported with the
financing program and the value of NFA at the end of each financial year. Therefore,
the GFA and NFA at the end of each financial year commencing from FY 2014-15 to
FY 2018-19 has been worked out along with Equity and Debts taking base figures as
allowed in the final True-up for FY 2013-14.
Calculation of GFA & NFA including financing
(Rs Crores)
Maqsoodapur Power Station
2014-15 2015-16 2016-17 2017-18 2018-19
Op. GFA 482.64 482.64 482.64 482.64 482.64
Additions 0.00 0.00 0.00 0.00 0.00
Deletions - - - - -
Cl. GFA 482.64 482.64 482.64 482.64 482.64
Cl. Net FA 390.07 361.99 333.91 305.83 277.75
Financing:
Op. Equity 144.79 144.79 144.79 144.79 144.79
Additions 0.00 0.00 0.00 0.00 0.00
Reduction - - - - -
Cl. Equity 144.79 144.79 144.79 144.79 144.79
Op. AccuDep 34.94 63.02 91.10 119.18 147.26
Dep. during the year
28.08 28.08 28.08 28.08 28.08
Cl. Accu. Depreciation
63.02 91.10 119.18 147.26 175.34
Op. Debts 273.36 245.28 217.20 189.11 161.03
Additions 0.00 0.00 0.00 0.00 0.00
Less : Repayment
28.08 28.08 28.08 28.08 28.08
Cl. Debts 245.28 217.20 189.11 161.03 132.95
(c) RoE, Depreciation, O&M and Interest on Loans :
On the basis of decisions of the Commission in the forgoing paragraphs and the
details of GFA, NFA and financing as indicated above the Return on Equity,
Depreciation, O&M expenditure and Interest on Loans, at the end of each financial
year of the control MYT period from FY 2014-15 to FY 2018-19, is worked out as
under:
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 76 of 114
Details of approved RoE, Depreciation, O&M and Interest on Loans (RsCr)
Sl.No.
Particular 2014-15 2015-16 2016-17 2017-18 2018-19
1 O&M Expenses
21.51 22.86 24.30 25.83 27.46
2 Depreciation 28.08 28.08 28.08 28.08 28.08
3 Interest on Loan
34.83 27.19 23.81 20.43 17.04
4 Return on Equity
23.17 23.17 23.17 23.17 23.17
Total: 107.58 101.30 99.36 97.51 95.74
(d) Interest on Working Capital:
The amount of working Capital and Interest on working Capital for the control period of F.Y. 2014-15 to FY 2018-19 as determined by the Commission are as under:
Annual Receivables of Maqsoodapur Power Station required for
Calculation of Working Capital: (Rs Crore)
I
n
t
e
r
est on Working Capital as determined by the Commission
(Rs Crore)
SN Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
1 Cost of Coal for 60 days
42.38 40.78 40.78 40.78 40.78
2 Cost of Secondary Fuel Oil for 2 months
0.79 0.43 0.43 0.43 0.43
3 O & M for 1 month 1.79 1.91 2.03 2.15 2.29
4 Maintenance Spares @20% of O & M Exp.
4.30 4.57 4.86 5.17 5.49
5
Receivables equivalent to 2 months capacity and energy charges for sale of electricity
63.49 60.38 60.06 59.75 59.46
6 Working Capital 112.75 108.07 108.15 108.28 108.45
7 Rate of Interest 13.50% 13.50% 13.50% 13.50% 13.50%
Particulars
2014-15 2015-16 2016-17 2017-18 2018-19
Annual Capacity [Fixed] Charges
122.80 115.89 113.96 112.13 110.38
Cost of Fuel 258.12 246.40 246.40 246.40 246.40
Total Receivables 380.93 362.29 360.36 358.53 356.78
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 77 of 114
SN Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
8 I W C 15.22 14.59 14.60 14.62 14.64
(e) Capacity (Fixed) Charge per unit of Generation :
Based on above the capacity charges as claimed by Petitioner and as approved by the
Commission are tabulated herein for the MYT period of F.Y. 2014-15 to F.Y 2018-19.
Fixed Charges as claimed and as approved by the Commission
Particulars
FY 15 FY 16
As claimed by BEPL
As determined
by the Commission
Diff. (if any) As claimed by BEPL
As determined
by the Commission
Diff. (if any)
O&M Expenses 21.51 21.51 0.00 22.86 22.86 0.00
Depreciation 29.73 28.08 -1.65 30.42 28.08 -2.34
Interest on Loan 36.67 34.83 -1.85 29.55 27.19 -2.35
Return on Equity 31.05 23.17 -7.88 31.92 23.17 -8.75
Interest on Working Capital
15.51 15.22 -0.29 15.50 14.59 -0.91
Special Allowance on Refinancing of loan
0.52 - -0.52 1.87 - -1.87
Total (Rs Cr) 135.00 122.80 -12.20 132.12 115.89 -16.23
Ex-bus Energy Sent Out (kwh)
596.42 596.42 0.00 596.42 596.42 0.00
Fixed Cost per Unit
2.26 2.06 -0.20 2.22 1.94 -0.27
Particulars
FY 17 FY 18
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
As claimed by BEPL
As determined by the
Commission
Diff. (if any)
O&M Expenses 24.30 24.30 0.00 25.83 25.83 0.00
Depreciation 30.50 28.08 -2.42 30.50 28.08 -2.42
Interest on Loan 25.99 23.81 -2.18 22.31 20.43 -1.88
Return on Equity 32.01 23.17 -8.84 32.01 23.17 -8.84
Interest on Working Capital
15.51 14.60 -0.91 15.51 14.62 -0.90
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 78 of 114
Particulars
FY 17 FY 18
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
As claimed by BEPL
As determined by the
Commission
Diff. (if any)
Special Allowance on Refinancing of loan
1.69 - -1.69 1.49 - -1.49
Total (Rs Cr) 130.00 113.96 -16.04 127.66 112.13 -15.53
Ex-bus Energy Sent Out (kwh)
596.42 596.42 0.00 596.42 596.42 0.00
Fixed Cost per Unit
2.18 1.91 -0.27 2.14 1.88 -0.26
ii. Representative calculation of Variable Charges:
(a) Variable charge per unit of Generation – For the purpose of calculation of
normative working capital:
Based on the operation norms provided in the UPERC Generation Tariff Regulations,
2014, the variable charge per unit of generation for Maqsoodapur Power Station for
the MYT period of F.Y. 2014-15 to F.Y 2018-19 has been arrived at. The calculation
shown below is representative of the variable cost calculation and has been used to
arrive at some of the components of normative working capital
Particulars
FY 19
As claimed by
BEPL
As determined
by the
Commission
Difference
(if any)
O&M Expenses 27.46 27.46 0.00
Depreciation 30.50 28.08 -2.42
Interest on Loan 18.64 17.04 -1.60
Return on Equity 32.01 23.17 -8.84
Interest on Working Capital 15.53 14.64 -0.89
Special Allowance on Refinancing of
loan 1.29 - -1.29
Total (Rs Cr) 125.43 110.38 -15.04
Ex-bus Energy Sent Out (kwh) 596.42 596.42 0.00
Fixed Cost per Unit 2.10 1.85 -0.25
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 79 of 114
Variable charge per unit of generation for Maqsoodapur Power Station
Description Unit 2014-15 2015-16 2016-17 2017-18 2018-19
Capacity MW 90.00 90.00 90.00 90.00 90.00
PAF % 85 85 85 85 85
Gross generation MU 670.14 670.14 670.14 670.14 670.14
Auxiliary Consumption
% 11.00 11.00 11.00 11.00 11.00
Net units sent out MU 596.42 596.42 596.42 596.42 596.42
Gross station heat rate
Kcal/kWh 2890 2890 2890 2890 2890
Specific oil consumption
ml/kWh 1.00 1.00 1.00 1.00 1.00
Calorific value of secondary fuel
KCal/Lt 10.00 10.00 10.00 10.00 10.00
Weighted average landed price of coal
Rs./Kg 4.43 4.52 4.52 4.52 4.52
Calorific value of Coal
kCal/kg 3373.76 3575.43 3575.43 3575.43 3575.43
Weighted average landed price of secondary fuel
Rs./mL 0.07 0.04 0.04 0.04 0.04
Energy charge rate (ECR)
Rs/kWh 4.33 4.13 4.13 4.13 4.13
(b) Cost of alternative coal supply:
Regulation 26 (iv) of the UPERC Generation Tariff Regulations 2014 specifies the norms
for the calculation of cost of alternative coal supply:
“In case of part or full use of alternative source of fuel supply by coal based thermal
generating stations other than as agreed by the generating company and beneficiaries
in their power purchase agreement for supply of contracted power on account of
shortage of fuel or optimization of economical operation through blending, the use of
alternative source of fuel supply shall be permitted to generating station;
Provided further that the weighted average price of use of alternative source of fuel shall
not exceed 30% of base price of fuel computed as per clause (v) of this regulation;
Provided also that where the energy charge rate based on weighted average price
of use of fuel including alternative source of fuel exceeds 30% of base energy
charge rate as approved by the Commission for that year or energy charge rate
based on weighted average price of use of fuel including alternative sources of
fuel exceeds 20% of energy charge rate based on weighted average fuel price for
the previous month, whichever is lower shall be considered and in that event,
prior consent of the beneficiary shall be taken by the generator by serving a
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 80 of 114
notice upon the beneficiary in writing not later than seven working days in
advance.
Provided that if the beneficiary does not respond to the notice given by the generator in
writing within the above stipulated time, the beneficiary shall be liable for payment of
fixed charges to generator”
Further Alternative coal supply from CIL beyond the FSA must be done through e-
auction route and for procurement of domestic open market coal and imported coal the
generating companies shall follow a transparent competitive bidding process so as to
identify a reasonable market price.
However the Commission directs that the Committee should be formed for carrying out
the above mentioned process with at least one member of the Beneficiary.
Accordingly the cost of alternative coal supply for FY 2016-17 shall not exceed the
following:
Period Maximum ECR (Rs/kWh)
01.04.2016 to 31.03.2017 5.37
The rates for the subsequent years shall be computed as per the Regulations.
(c) Adjustment of Rate of Energy Charge on Account of Variation in price or
Heat Value of Fuels:
Any variation shall be adjusted on month to month basis on the basis of Gross Calorific
Value of coal or gas or liquid fuel as received and landed cost incurred by the generating
company for procurement of coal, oil, or gas or liquid fuel, as the case may be. No
separate petition needs to be filed with the Commission for fuel price adjustment. In case
of any dispute, an appropriate application in accordance with Uttar Pradesh Electricity
Regulatory Commission (Conduct of Business) Regulations 2004, as amended from time
to time or any statutory re-enactment thereof, shall be made before the Commission.
Provided further that copies of the bills and details of parameters of GCV and price of fuel
i.e. domestic coal, imported coal, e-auction coal, lignite, liquid fuel etc., details of blending
ratio of the imported coal with domestic coal, proportion of e-auction coal shall also be
displayed on the website of the generating company. The details should be available on its
website on monthly basis for a period of three months.
However, UPPCL shall verify the “As Received GCV” and landed cost of coal from
the original coal purchase bills.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 81 of 114
BEPL shall be entitled to recover / adjust any change in fuel cost according to the
provisions set out in the Generation Regulations.
iii. Summary Capacity Charges (Cost):
The total capacity charges (costs) for Maqsoodapur Thermal Power Station for the MYT
period of FY 2014-15 to FY 2018-19 is summarized in the table below.
Fixed Cost per kWh as claimed and as allowed by the Commission
Particulars
FY 15 FY 16
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
Fixed Cost (Rs Cr.)
135.00 122.80 -12.20 132.12 115.89 -16.23
F. C. per Unit (In Rs/kWh)
2.26 2.06 -0.20 2.22 1.94 -0.27
Particulars
FY 17 FY 18
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
Fixed Cost (Rs Cr.)
130.00 113.96 -16.04 127.66 112.13 -15.53
F. C. per Unit (In Rs/kWh)
2.18 1.91 -0.27 2.14 1.88 -0.26
Particulars
FY 19
As claimed by BEPL As determined by the
Commission Diff.
(if any)
Fixed Cost (Rs Cr.)
125.43 110.38 -15.04
F. C. per Unit (In Rs/kWh)
2.10 1.85 -0.25
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 82 of 114
9.3
Section-3
Multi Year Tariff
For
Khambarkhera
Thermal Power Station
For
FY 2014 - 15 to FY 2018 - 19
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 83 of 114
9.3.1 ARR and MYT as according to petition:
In the petition, the Petitioner has proposed the fixed, variable and total charges for the electricity sent out
as given in the table below:
9.3.2 ARR and MYT as determined by the Commission:
i. Capacity (Fixed) Charges:
(a) Provisions under Regulations:
For determination of components of fixed charges for MYT period of FY 2014 - 15 to
FY 2018 - 19, the Commission opines that the parameters provided under UPERC Generation
Tariff Regulations, 2014shall be considered. Hence, the Commission has decided to allow the
components of fixed charges as below:
Components of Fixed Charge
Value Remark
Return on equity 15.50% + 0.5% = 16 %
As per the Regulations and an additional return of 0.5% applicable to projects completed within specified timeline
Interest on Loans
FY15 - 13.43% FY16 - 11.76% FY17 - 11.72% FY18 – 11.67% FY19 – 11.59%
Weighted average of interest on loans for FY 2014-15 to FY 2018-19
O & M Expenses Normative As per the Regulations
Interest on working capital
13.50 % As per the Regulations
Khambarkhera 2014-15 2015-16 2016-17 2017-18 2018-19
Energy Sent out (MU)
596.42 596.42 596.42 596.42 596.42
Fixed Charges (Rs/kWh)
2.34 2.30 2.26 2.22 2.18
Variable Charges (Rs/kWh)
4.40 4.40 4.40 4.40 4.40
Total Charges (Rs/kWh)
6.74 6.70 6.66 6.62 6.58
ARR (Rs Cr.) 402.24 399.82 397.51 394.97 392.54
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 84 of 114
(b) Gross Fixed Assets (GFA) and its Components :
For the determination of Return on Equity, Interest on balance Loans and
Depreciation it is essential to determine the value of GFA duly supported with the
financing program and the value of NFA at the end of each financial year. Therefore,
the GFA and NFA at the end of each financial year commencing from FY 2014-15 to
FY 2018-19 has been worked out along with Equity and Debts taking base figures as
allowed in the final True-up for FY 2013-14.
Calculation of GFA & NFA including financing
(Rs Crore)
Khambarkhera Power Station
2014-15 2015-16 2016-17 2017-18 2018-19
Op. GFA 487.82 487.82 487.82 487.82 487.82
Additions 0.00 0.00 0.00 0.00 0.00
Deletions - - - - -
Cl. GFA 487.82 487.82 487.82 487.82 487.82
Cl. Net FA 392.48 363.68 334.89 306.09 277.29
Financing:
Op. Equity 146.35 146.35 146.35 146.35 146.35
Additions 0.00 0.00 0.00 0.00 0.00
Reduction - - - - -
Cl. Equity 146.35 146.35 146.35 146.35 146.35
Op. AccuDep 36.18 64.98 93.78 122.57 151.37
Dep. during the year
28.80 28.80 28.80 28.80 28.80
Cl. Accu. Depreciation
64.98 93.78 122.57 151.37 180.17
Op. Debts 274.93 246.13 217.34 188.54 159.74
Additions 0.00 0.00 0.00 0.00 0.00
Less : Repayment
28.80 28.80 28.80 28.80 28.80
Cl. Debts 246.13 217.34 188.54 159.74 130.94
(c) RoE, Depreciation, O&M and Interest on Loans :
On the basis of decisions of the Commission in the forgoing paragraphs and the
details of GFA, NFA and financing as indicated above the Return on Equity,
Depreciation, O&M expenditure and Interest on Loans, at the end of each financial
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 85 of 114
year of the control MYT period from FY 2014-15 to FY 2018-19, isworked out as
under:
Details of approved RoE, Depreciation, O&M and Interest on Loans (Rs Crore)
Sl.No. Particular 2014-15 2015-16 2016-17 2017-18 2018-19
1 O&M Expenses 21.51 22.86 24.30 25.83 27.46
2 Depreciation 28.80 28.80 28.80 28.80 28.80
3 Interest on Loan 34.99 27.25 23.78 20.32 16.85
4 Return on Equity 23.42 23.42 23.42 23.42 23.42
Total: 108.71 102.32 100.30 98.36 96.52
(d) Interest on Working Capital:
The amount of working Capital and Interest on working Capital for the control period of F.Y. 2014-15 to FY 2018-19 as determined by the Commission are as under:
Annual Receivables of Khambarkhera Power Station required for
Calculation of Working Capital: (Rs Crore)
Interest on Working Capital as determined by the Commission
(Rs Crore)
SN Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
1 Cost of Coal for 60 days
42.99 43.25 43.25 43.25 43.25
2 Cost of Secondary Fuel Oil for 2 months
0.79 0.46 0.46 0.46 0.46
3 O & M for 1 month 1.79 1.91 2.03 2.15 2.29
Particulars
2014-15 2015-16 2016-17 2017-18 2018-19
Annual Capacity [Fixed] Charges
124.13 117.63 115.61 113.69 111.87
Cost of Fuel 261.79 261.37 261.37 261.37 261.37
Total Receivables 385.92 378.99 376.98 375.06 373.23
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 86 of 114
SN Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
4 Maintenance Spares @20% of O & M Exp.
4.30 4.57 4.86 5.17 5.49
5
Receivables equivalent to 2 months capacity and energy charges for sale of electricity
64.32 63.17 62.83 62.51 62.21
6 Working Capital 114.19 113.35 113.43 113.54 113.70
7 Rate of Interest 13.50% 13.50% 13.50% 13.50% 13.50%
8 I W C 15.42 15.30 15.31 15.33 15.35
(e) Capacity (Fixed) Charge per unit of Generation :
Based on above the capacity charges as claimed by Petitioner and as approved by
the Commission are tabulated herein for the MYT period of F.Y. 2014-15 to F.Y 2018-
19.
Fixed Charges as claimed and as approved by the Commission
Particulars
FY 15 FY 16
As claimed by BEPL
As determined
by the Commission
Diff. (if any) As claimed by BEPL
As determined
by the Commission
Diff. (if any)
O&M Expenses 21.51 21.51 0.00 22.86 22.86 0.00
Depreciation 31.03 28.80 -2.23 31.93 28.80 -3.13
Interest on Loan 38.30 34.99 -3.31 31.11 27.25 -3.86
Return on Equity 32.37 23.42 -8.96 33.47 23.42 -10.06
Interest on Working Capital
15.78 15.42 -0.37 15.78 15.30 -0.48
Special Allowance on Refinancing of loan
0.54 0.00 -0.54 1.97 0.00 -1.97
Total (Rs Cr) 139.54 124.13 -15.41 137.12 117.63 -19.49
Ex-bus Energy Sent Out (kwh)
596.42 596.42 0.00 596.42 596.42 0.00
Fixed Cost per Unit
2.34 2.08 -0.26 2.30 1.97 0.33
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 87 of 114
Particulars
FY 17 FY 18
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
As claimed by BEPL
As determined by the
Commission
Diff. (if any)
O&M Expenses 24.30 24.30 0.00 25.83 25.83 0.00
Depreciation 32.01 28.80 -3.22 32.01 28.80 -3.22
Interest on Loan 27.37 23.78 -3.59 23.51 20.32 -3.19
Return on Equity 33.56 23.42 -10.15 33.56 23.42 -10.15
Interest on Working Capital
15.78 15.31 -0.47 15.79 15.33 -0.46
Special Allowance on Refinancing of loan
1.77 0.00 -1.77 1.57 0.00 -1.57
Total (Rs Cr) 134.81 115.61 -19.20 132.27 113.69 -18.58
Ex-bus Energy Sent Out (kwh)
596.42 596.42 0.00 596.42 596.42 0.00
Fixed Cost per Unit
2.26 1.94 0.32 2.22 1.91 0.31
ii. Representative calculation of Variable Charges:
(a) Variable charge per unit of Generation: For the purpose of calculation of
normative working capital
Particulars
FY 19
As claimed by
BEPL
As determined
by the
Commission
Difference
(if any)
O&M Expenses 27.46 27.46 0.00
Depreciation 32.01 28.80 -3.22
Interest on Loan 19.65 16.85 -2.81
Return on Equity 33.56 23.42 -10.15
Interest on Working Capital 15.79 15.35 -0.44
Special Allowance on Refinancing of
loan 1.36 0.00 -1.36
Total (Rs Cr) 129.84 111.87 -17.98
Ex-bus Energy Sent Out (kwh) 596.42 596.42 0.00
Fixed Cost per Unit 2.18 1.88 0.30
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 88 of 114
Based on the operation norms provided in the UPERC Generation Tariff Regulations,
2014, the variable charge per unit of generation for Khambarkhera Power Station for
the MYT period of F.Y. 2014-15 to F.Y 2018-19 has been arrived at. The calculation
shown below is representative of the variable cost calculation and has been used to
arrive at some of the components of normative working capital.
Variable charge per unit of generation for Khambarkhera Power Station
Description Unit 2014-15 2015-16 2016-17 2017-18 2018-19
Capacity MW 90.00 90.00 90.00 90.00 90.00
PAF % 85 85 85 85 85
Gross generation MU 670.14 670.14 670.14 670.14 670.14
Auxiliary Consumption
% 11.00 11.00 11.00 11.00 11.00
Net units sent out MU 596.42 596.42 596.42 596.42 596.42
Gross station heat rate
Kcal/kWh 2890 2890 2890 2890 2890
Specific oil consumption
ml/kWh 1.00 1.00 1.00 1.00 1.00
Calorific value of secondary fuel
KCal/Lt 10.00 10.00 10.00 10.00 10.00
Weighted average landed price of coal
Rs./Kg 4.42 4.85 4.85 4.85 4.85
Calorific value of Coal
kCal/kg 3318.33 3617.75 3617.75 3617.75 3617.75
Weighted average landed price of secondary fuel
Rs./mL 0.07 0.04 0.04 0.04 0.04
Energy charge rate (ECR)
Rs/kWh 4.39 4.38 4.38 4.38 4.38
(b) Cost of alternative coal supply:
Regulation 26 (iv) of the UPERC Generation Tariff Regulations 2014 specifies the norms
for the calculation of cost of alternative coal supply:
“In case of part or full use of alternative source of fuel supply by coal based thermal
generating stations other than as agreed by the generating company and beneficiaries
in their power purchase agreement for supply of contracted power on account of
shortage of fuel or optimization of economical operation through blending, the use of
alternative source of fuel supply shall be permitted to generating station;
Provided further that the weighted average price of use of alternative source of fuel
shall not exceed 30% of base price of fuel computed as per clause (v) of this
regulation;
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 89 of 114
Provided also that where the energy charge rate based on weighted average
price of use of fuel including alternative source of fuel exceeds 30% of base
energy charge rate as approved by the Commission for that year or energy
charge rate based on weighted average price of use of fuel including alternative
sources of fuel exceeds 20% of energy charge rate based on weighted average
fuel price for the previous month, whichever is lower shall be considered and in
that event, prior consent of the beneficiary shall be taken by the generator by
serving a notice upon the beneficiary in writing not later than seven working
days in advance.
Provided that if the beneficiary does not respond to the notice given by the generator
in writing within the above stipulated time, the beneficiary shall be liable for payment of
fixed charges to generator”
Further Alternative coal supply from CIL beyond the FSA must be done through e-
auction route and for procurement of domestic open market coal and imported coal
the generating companies shall follow a transparent competitive bidding process so as
to identify a reasonable market price.
However the Commission directs that the Committee should be formed for carrying
out the above mentioned process with at least one member of the Beneficiary.
Accordingly the cost of alternative coal supply for FY 2016-17 shall not exceed the
following:
Period Maximum ECR (Rs/kWh)
01.04.2016 to 31.03.2017 5.70
The rates for the subsequent years shall be computed as per the Regulations.
(c) Adjustment of Rate of Energy Charge on Account of Variation in price or
Heat Value of Fuels:
Any variation shall be adjusted on month to month basis on the basis of Gross Calorific
Value of coal or gas or liquid fuel as received and landed cost incurred by the generating
company for procurement of coal, oil, or gas or liquid fuel, as the case may be. No
separate petition needs to be filed with the Commission for fuel price adjustment. In case
of any dispute, an appropriate application in accordance with Uttar Pradesh Electricity
Regulatory Commission (Conduct of Business) Regulations 2004, as amended from time
to time or any statutory re-enactment thereof, shall be made before the Commission.
Provided further that copies of the bills and details of parameters of GCV and price of fuel
i.e. domestic coal, imported coal, e-auction coal, lignite, liquid fuel etc., details of blending
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 90 of 114
ratio of the imported coal with domestic coal, proportion of e-auction coal shall also be
displayed on the website of the generating company. The details should be available on its
website on monthly basis for a period of three months.
However, UPPCL shall verify the “As Received GCV” and landed cost of coal from
the original coal purchase bills.
BEPL shall be entitled to recover / adjust any change in fuel cost according to the
provisions set out in the Generation Regulations.
iii. Summary - Capacity Charges (Cost):
The total charges (costs) for Khambarkhera Thermal Power Station for the MYT period of
FY 2014-15 to FY 2018-19 is summarized in the table below.
Fixed Cost per kWh as claimed and as allowed by the Commission
Particulars
FY 15 FY 16
As claimed by BEPL
As determined
by the Commissio
n
Diff. (if any)
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
Fixed Cost (Rs Cr.)
139.54 124.13 -15.41 137.12 117.63 -19.49
F. C. per Unit (In Rs/kWh)
2.34 2.08 -0.26
2.30 1.97 0.33
Particulars
FY 17 FY 18
As claimed by
BEPL
As determined by the
Commission
Diff. (if any)
As claimed by BEPL
As determined by the
Commission
Diff. (if any)
Fixed Cost (Rs Cr.)
134.81 115.61 -19.20 132.27 113.69 -18.58
F. C. per Unit (In Rs/kWh)
2.26 1.94 0.32 2.22 1.91 0.31
Particulars
FY 19
As claimed by BEPL As determined by the
Commission Diff.
(if any)
Fixed Cost (Rs Cr.)
129.84 111.87 -17.98
F. C. per Unit (In Rs/kWh)
2.18 1.88 0.30
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 91 of 114
9.4
Section-4
Multi Year Tariff
For
Kundarki
Thermal Power Station
For
FY 2014 - 15 to FY 2018 - 19
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 92 of 114
9.4.1 ARR and MYT as according to petition:
In the petition, the Petitioner has proposed the fixed, variable and total charges for the electricity sent out
as given in the table below:
9.4.2 ARR and MYT as determined by the Commission:
i. Capacity (Fixed) Charges:
(a) Provisions under Regulations:
For determination of components of fixed charges for MYT period of FY 2014 - 15 to
FY 2018 - 19, the Commission opines that the parameters provided under UPERC Generation
Tariff Regulations, 2014shall be considered. Hence, the Commission has decided to allow the
components of fixed charges as below:
Components of Fixed Charge
Value Remark
Return on equity 15.50% + 0.5% = 16 %
As per the Regulations and an additional return of 0.5% applicable to projects completed within specified timeline
Interest on Loans
FY15 - 13.43% FY16 - 11.76% FY17 - 11.72% FY18 – 11.67% FY19 – 11.59%
Weighted average of interest on loans for FY 2014-15 to FY 2018-19
O & M Expenses Normative As per the Regulations
Interest on working capital
13.50 % As per the Regulations
Kundarki 2014-15 2015-16 2016-17 2017-18 2018-19
Energy Sent out (MU)
596.42 596.42 596.42 596.42 596.42
Fixed Charges (Rs/kWh)
2.28 2.22 2.19 2.15 2.11
Variable Charges (Rs/kWh)
4.24 4.24 4.24 4.24 4.24
Total Charges (Rs/kWh)
6.52 6.46 6.42 6.38 6.35
ARR (Rs Cr.) 388.62 385.34 383.18 380.81 378.54
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 93 of 114
(b) Gross Fixed Assets (GFA) and its Components :
For the determination of Return on Equity, Interest on balance Loans and
Depreciation it is essential to determine the value of GFA duly supported with the
financing program and the value of NFA at the end of each financial year. Therefore,
the GFA and NFA at the end of each financial year commencing from FY 2014-15 to
FY 2018-19 has been worked out along with Equity and Debts taking base figures as
allowed in the final True-up for FY 2013-14.
Calculation of GFA & NFA including financing
(Rs Crore)
Kundarki Power Station
2014-15 2015-16 2016-17 2017-18 2018-19
Op. GFA 488.16 488.16 488.16 488.16 488.16
Additions 0.00 0.00 0.00 0.00 0.00
Deletions - - - - -
Cl. GFA 488.16 488.16 488.16 488.16 488.16
Cl. Net FA 396.08 367.24 338.40 309.56 280.72
Financing:
Op. Equity 146.45 146.45 146.45 146.45 146.45
Additions 0.00 0.00 0.00 0.00 0.00
Reduction - - - - -
Cl. Equity 146.45 146.45 146.45 146.45 146.45
Op. AccuDep 34.18 63.02 91.86 120.70 149.54
Dep. during the year
28.84 28.84 28.84 28.84 28.84
Cl. Accu. Depreciation
63.02 91.86 120.70 149.54 178.38
Op. Debts 278.47 249.63 220.79 191.95 163.11
Additions 0.00 0.00 0.00 0.00 0.00
Less : Repayment
28.84 28.84 28.84 28.84 28.84
Cl. Debts 249.63 220.79 191.95 163.11 134.27
(c) RoE, Depreciation, O&M and Interest on Loans :
On the basis of decisions of the Commission in the forgoing paragraphs and the
details of GFA, NFA and financing as indicated above the Return on Equity,
Depreciation, O&M expenditure and Interest on Loans, at the end of each financial
year of the control MYT period from FY 2014-15 to FY 2018-19, is worked out as
under:
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 94 of 114
Details of approved RoE, Depreciation, O&M and Interest on Loans (Rs Crore)
Sl.No. Particular 2014-15 2015-16 2016-17 2017-18 2018-19
1 O&M Expenses 21.51 22.86 24.30 25.83 27.46
2 Depreciation 28.84 28.84 28.84 28.84 28.84
3 Interest on Loan 35.46 27.66 24.19 20.72 17.23
4 Return on Equity 23.43 23.43 23.43 23.43 23.43
Total: 109.24 102.79 100.76 98.82 96.96
(d) Interest on Working Capital:
The amount of working Capital and Interest on working Capital for the control period of F.Y. 2014-15 to FY 2018-19 as determined by the Commission are as under:
Annual Receivables of Kundarki Power Station required for
Calculation of Working Capital: (Rs Crore)
Interest on Working Capital as determined by the Commission
(Rs Crore)
SN Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
1 Cost of Coal for 60 days 41.32 39.78 39.78 39.78 39.78
2 Cost of Secondary Fuel Oil for 2 months
0.80 0.47 0.47 0.47 0.47
3 O & M for 1 month 1.79 1.91 2.03 2.15 2.29
4 Maintenance Spares @20% of O & M Exp.
4.30 4.57 4.86 5.17 5.49
5
Receivables equivalent to 2 months capacity and energy charges for sale of electricity
62.68 59.63 59.30 58.98 58.67
Particulars
2014-15 2015-16 2016-17 2017-18 2018-19
Annual Capacity [Fixed] Charges 124.21 117.15 115.13 113.20 111.37
Cost of Fuel 251.88 240.66 240.66 240.66 240.66
Total Receivables 376.09 357.81 355.78 353.86 352.03
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 95 of 114
SN Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
6 Working Capital 110.90 106.36 106.43 106.54 106.70
7 Rate of Interest 13.50% 13.50% 13.50% 13.50% 13.50%
8 I W C 14.97 14.36 14.37 14.38 14.40
(e) Capacity (Fixed) Charge per unit of Generation :
Based on above the capacity charges as claimed by Petitioner and as approved by
the Commission are tabulated herein for the MYT period of F.Y. 2014-15 to F.Y 2018-
19. Ex-bus energy sent out has been taken from the data mentioned in Section 8.1.1:
Fixed Charges as claimed and as approved by the Commission
Particulars
FY 15 FY 16
As claimed by BEPL
As determined
by the Commission
Diff. (if any) As claimed by
BEPL
As determined
by the Commission
Diff. (if any)
O&M Expenses 21.51 21.51 0.00 22.86 22.86 0.00
Depreciation 30.11 28.84 -1.27 30.71 28.84 -1.87
Interest on Loan 37.09 35.46 -1.63 29.75 27.66 -2.09
Return on Equity 31.39 23.43 -7.96 32.17 23.43 -8.74
Interest on Working Capital
15.25 14.97 -0.28 15.23 14.36 -0.87
Special Allowance on Refinancing of loan
0.52 0.00 -0.52 1.89 0.00 -1.89
Total (Rs Cr) 135.88 124.21 -11.67 132.60 117.15 -15.45
Ex-bus Energy Sent Out (kwh)
596.42 596.42 0.00 596.42 596.42 0.00
Fixed Cost per Unit
2.28 2.08 -0.20 2.22 1.96 -0.26
Particulars
FY 17 FY 18
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
O&M Expenses 24.30 24.30 0.00 25.83 25.83 0.00
Depreciation 30.79 28.84 -1.95 30.79 28.84 -1.95
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 96 of 114
Particulars
FY 17 FY 18
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
Interest on Loan 26.16 24.19 -1.97 22.45 22.45 20.72
Return on Equity 32.26 23.43 -8.83 32.26 32.26 23.43
Interest on Working Capital
15.24 14.37 -0.87 15.24 15.24 14.38
Special Allowance on Refinancing of loan
1.70 0.00 -1.70 1.50 1.50 0.00
Total (Rs Cr) 130.45 115.13 -15.32 128.07 113.20 -14.87
Ex-bus Energy Sent Out (kwh)
596.42 596.42 0.00 596.42 596.42 0.00
Fixed Cost per Unit
2.19 1.93 -0.26 2.15 1.90 -0.25
ii. Representative Calculation of Variable Charges:
(a) Variable charge per unit of Generation – For the purpose of calculation of
normative working capital
Based on the operation norms provided in the UPERC Generation Tariff Regulations,
2014, the variable charge per unit of generation for Kundarki Power Station for the MYT
period of F.Y. 2014-15 to F.Y 2018-19 has been arrived at. The calculation shown below
Particulars
FY 19
As claimed by BEPL
As determined by the
Commission
Difference (if any)
O&M Expenses 27.46 27.46 0.00
Depreciation 30.79 28.84 -1.95
Interest on Loan 18.74 17.23 -1.50
Return on Equity 32.26 23.43 -8.83
Interest on Working Capital 15.25 14.40 -0.85
Special Allowance on Refinancing of loan 1.30 0.00 -1.30
Total (Rs Cr) 125.80 111.37 -14.43
Ex-bus Energy Sent Out (kwh) 596.42 596.42 0.00
Fixed Cost per Unit 2.11 1.87 -0.24
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 97 of 114
is representative of the variable cost calculation and has been used to arrive at some of
the components of normative working capital.
Variable charge per unit of generation for Kundarki Power Station
Description Unit 2014-15 2015-16 2016-17 2017-18 2018-19
Capacity MW 90.00 90.00 90.00 90.00 90.00
PAF % 85 85 85 85 85
Gross generation MU 670.14 670.14 670.14 670.14 670.14
Auxiliary Consumption
% 11.00 11.00 11.00 11.00 11.00
Net units sent out MU 596.42 596.42 596.42 596.42 596.42
Gross station heat rate
Kcal/kWh 2890 2890 2890 2890 2890
Specific oil consumption
ml/kWh 1.00 1.00 1.00 1.00 1.00
Calorific value of secondary fuel
KCal/Lt 10.00 10.00 10.00 10.00 10.00
Weighted average landed price of coal
Rs./Kg 4.38 4.32 4.32 4.32 4.32
Calorific value of Coal
kCal/kg 3421.93 3502.61 3502.61 3502.61 3502.61
Weighted average landed price of secondary fuel
Rs./mL 0.07 0.04 0.04 0.04 0.04
Energy charge rate (ECR)
Rs/kWh 4.22 4.04 4.04 4.04 4.04
(b) Cost of alternative coal supply:
Regulation 26 (iv) of the UPERC Generation Tariff Regulations 2014 specifies the norms
for the calculation of cost of alternative coal supply:
“In case of part or full use of alternative source of fuel supply by coal based thermal
generating stations other than as agreed by the generating company and beneficiaries
in their power purchase agreement for supply of contracted power on account of
shortage of fuel or optimization of economical operation through blending, the use of
alternative source of fuel supply shall be permitted to generating station;
Provided further that the weighted average price of use of alternative source of fuel
shall not exceed 30% of base price of fuel computed as per clause (v) of this
regulation;
Provided also that where the energy charge rate based on weighted average
price of use of fuel including alternative source of fuel exceeds 30% of base
energy charge rate as approved by the Commission for that year or energy
charge rate based on weighted average price of use of fuel including alternative
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 98 of 114
sources of fuel exceeds 20% of energy charge rate based on weighted average
fuel price for the previous month, whichever is lower shall be considered and in
that event, prior consent of the beneficiary shall be taken by the generator by
serving a notice upon the beneficiary in writing not later than seven working
days in advance.
Provided that if the beneficiary does not respond to the notice given by the generator
in writing within the above stipulated time, the beneficiary shall be liable for payment of
fixed charges to generator”
Further Alternative coal supply from CIL beyond the FSA must be done through e-
auction route and for procurement of domestic open market coal and imported coal
the generating companies shall follow a transparent competitive bidding process so as
to identify a reasonable market price.
However the Commission directs that the Committee should be formed for carrying
out the above mentioned process with at least one member of the Beneficiary.
Accordingly the cost of alternative coal supply for FY 2016-17 shall not exceed the
following:
Period Maximum ECR (Rs/kWh)
01.04.2016 to 31.03.2017 5.25
The rates for the subsequent years shall be computed as per the Regulations.
(c) Adjustment of Rate of Energy Charge on Account of Variation in price or
Heat Value of Fuels:
Any variation shall be adjusted on month to month basis on the basis of Gross Calorific
Value of coal or gas or liquid fuel as received and landed cost incurred by the generating
company for procurement of coal, oil, or gas or liquid fuel, as the case may be. No
separate petition needs to be filed with the Commission for fuel price adjustment. In case
of any dispute, an appropriate application in accordance with Uttar Pradesh Electricity
Regulatory Commission (Conduct of Business) Regulations 2004, as amended from time
to time or any statutory re-enactment thereof, shall be made before the Commission.
Provided further that copies of the bills and details of parameters of GCV and price of fuel
i.e. domestic coal, imported coal, e-auction coal, lignite, liquid fuel etc., details of blending
ratio of the imported coal with domestic coal, proportion of e-auction coal shall also be
displayed on the website of the generating company. The details should be available on its
website on monthly basis for a period of three months.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 99 of 114
However, UPPCL shall verify the “As Received GCV” and landed cost of coal from
the original coal purchase bills.
BEPL shall be entitled to recover / adjust any change in fuel cost according to the
provisions set out in the Generation Regulations.
iii. Summary – Capacity Charges (Cost):
The capacity charges (costs) for Kundarki Thermal Power Station for the MYT period of
FY 2014-15 to FY 2018-19 is summarized in the table below.
Fixed Cost per kWh as claimed and as allowed by the Commission
Particulars
FY 15 FY 16
As claimed by BEPL
As determined
by the Commissio
n
Diff. (if any)
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
Fixed Cost (Rs Cr.)
135.88 124.21 -11.67 132.60 117.15 -15.45
F. C. per Unit (In Rs/kWh)
2.28 2.08 -0.20 2.22 1.96 -0.26
Particulars
FY 17 FY 18
As claimed by BEPL
As determined
by the Commissio
n
Diff. (if any)
As claimed by BEPL
As determined
by the Commissio
n
Diff. (if any)
Fixed Cost (Rs Cr.)
130.45 115.13 -15.32 128.07 113.20 -14.87
F. C. per Unit (In Rs/kWh)
2.19 1.93 -0.26 2.15 1.90 -0.25
Particulars
FY 19
As claimed by BEPL As determined by the
Commission Diff.
(if any)
Fixed Cost (Rs Cr.)
125.80 111.37 -14.43
F. C. per Unit (In Rs/kWh)
2.11 1.87 -0.24
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 100 of 114
9.5
Section-5
Multi Year Tariff
For
Utraula
Thermal Power Station
For
FY 2014 - 15 to FY 2018 - 19
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 101 of 114
9.5.1 ARR and MYT as according to petition:
In the petition, the Petitioner has proposed the fixed, variable and total charges for the electricity sent out
as given in the table below:
9.5.2 ARR and MYT as determined by the Commission:
i. Capacity (Fixed) Charges:
(a) Provisions under Regulations:
For determination of components of fixed charges for MYT period of FY 2014 - 15 to
FY 2018 - 19, the Commission opines that the parameters provided under UPERC Generation
Tariff Regulations, 2014shall be considered. Hence, the Commission has decided to allow the
components of fixed charges as below:
Components of Fixed Charge
Value Remark
Return on equity 15.50% + 0.5% = 16 %
As per the Regulations and an additional return of 0.5% applicable to projects completed within specified timeline
Interest on Loans
FY15 - 13.43% FY16 - 11.76% FY17 - 11.72% FY18 – 11.67% FY19 – 11.59%
Weighted average of interest on loans for FY 2014-15 to FY 2018-19
O & M Expenses Normative As per the Regulations
Interest on working capital
13.50 % As per the Regulations
Utrauala 2014-15 2015-16 2016-17 2017-18 2018-19
Energy Sent out (MU)
596.42 596.42 596.42 596.42 596.42
Fixed Charges (Rs/kWh)
2.34 2.28 2.25 2.20 2.16
Variable Charges (Rs/kWh)
4.18 4.18 4.18 4.18 4.18
Total Charges (Rs/kWh)
6.52 6.47 6.43 6.39 6.35
ARR (Rs Cr.) 388.99 385.75 383.44 380.91 378.49
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 102 of 114
(b) Gross Fixed Assets (GFA) and its Components :
For the determination of Return on Equity, Interest on balance Loans and
Depreciation it is essential to determine the value of GFA duly supported with the
financing program and the value of NFA at the end of each financial year. Therefore,
the GFA and NFA at the end of each financial year commencing from FY 2014-15 to
FY 2018-19 has been worked out along with Equity and Debts taking base figures as
allowed in the final True-up for FY 2013-14.
Calculation of GFA & NFA including financing
(Rs Crores)
Utrauala Power Station
2014-15 2015-16 2016-17 2017-18 2018-19
Op. GFA 506.84 506.84 506.84 506.84 506.84
Additions 0.00 0.00 0.00 0.00 0.00
Deletions - - - - -
Cl. GFA 506.84 506.84 506.84 506.84 506.84
Cl. Net FA 411.54 381.64 351.75 321.85 291.95
Financing:
Op. Equity 152.05 152.05 152.05 152.05 152.05
Additions 0.00 0.00 0.00 0.00 0.00
Reduction - - - - -
Cl. Equity 152.05 152.05 152.05 152.05 152.05
Op. AccuDep 35.34 65.24 95.13 125.03 154.93
Dep. during the year
29.90 29.90 29.90 29.90 29.90
Cl. Accu. Depreciation
65.24 95.13 125.03 154.93 184.83
Op. Debts 289.39 259.49 229.59 199.70 169.80
Additions 0.00 0.00 0.00 0.00 0.00
Less : Repayment
29.90 29.90 29.90 29.90 29.90
Cl. Debts 259.49 229.59 199.70 169.80 139.90
(c) RoE, Depreciation, O&M and Interest on Loans :
On the basis of decisions of the Commission in the forgoing paragraphs and the
details of GFA, NFA and financing as indicated above the Return on Equity,
Depreciation, O&M expenditure and Interest on Loans, at the end of each financial
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 103 of 114
year of the control MYT period from FY 2014-15 to FY 2018-19, isworked out as
under:
Details of approved RoE, Depreciation, O&M and Interest on Loans
(Rs Crore)
Sl.No. Particular 2014-15 2015-16 2016-17 2017-18 2018-19
1 O&M Expenses 21.51 22.86 24.30 25.83 27.46
2 Depreciation 29.90 29.90 29.90 29.90 29.90
3 Interest on Loan 36.86 28.76 25.16 21.56 17.95
4 Return on Equity 24.33 24.33 24.33 24.33 24.33
Total: 112.59 105.84 103.68 101.62 99.63
(d) Interest on Working Capital:
The amount of working Capital and Interest on working Capital for the control period of F.Y. 2014-15 to FY 2018-19 as determined by the Commission are as under:
Annual Receivables of Utraula Power Station required for
Calculation of Working Capital: (Rs Crore)
I
n
t
e
r
e
s
Interest on Working Capital as determined by the Commission
(Rs Crore)
SN Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
1 Cost of Coal for 60 days
40.79 41.41 41.41 41.41 41.41
2 Cost of Secondary Fuel Oil for 2 months
0.80 0.47 0.47 0.47 0.47
3 O & M for 1 month 1.79 1.91 2.03 2.15 2.29
4 Maintenance Spares @20% of O & M Exp.
4.30 4.57 4.86 5.17 5.49
5 Receivables equivalent to 2
62.70 61.86 61.50 61.16 60.83
Particulars
2014-15 2015-16 2016-17 2017-18 2018-19
Annual Capacity [Fixed] Charges
127.49 120.72 118.57 116.51 114.55
Cost of Fuel 248.68 250.45 250.45 250.45 250.45
Total Receivables 376.18 371.17 369.02 366.96 365.00
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 104 of 114
SN Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
months capacity and energy charges for sale of electricity
6 Working Capital 110.38 110.22 110.27 110.36 110.50
7 Rate of Interest 13.50% 13.50% 13.50% 13.50% 13.50%
8 I W C 14.90 14.88 14.89 14.90 14.92
(e) Capacity (Fixed) Charge per unit of Generation :
Based on above the capacity charges as claimed by Petitioner and as approved by
the Commission are tabulated herein for the MYT period of F.Y. 2014-15 to F.Y 2018-
19. Ex-bus energy sent out has been taken from the data mentioned in Section 8.1.1:
Fixed Charges as claimed and as approved by the Commission
Particulars
FY 15 FY 16
As claimed by BEPL
As determined
by the Commission
Diff. (if any) As claimed by
BEPL
As determined
by the Commission
Diff. (if any)
O&M Expenses 21.51 21.51 0.00 22.86 22.86 0.00
Depreciation 31.20 29.90 -1.31 31.88 29.90 -1.98
Interest on Loan 38.45 36.86 -1.60 30.92 28.76 -2.16
Return on Equity 32.56 24.33 -8.23 33.43 24.33 -9.10
Interest on Working Capital
15.19 14.90 -0.29 15.17 14.88 -0.29
Special Allowance on Refinancing of loan
0.54 0.00 -0.54 1.96 0.00 -1.96
Total (Rs Cr) 139.46 127.49 -11.97 136.22 120.72 -15.49
Ex-bus Energy Sent Out (kwh)
596.42 596.42 0.00 596.42 596.42 0.00
Fixed Cost per Unit
2.34 2.14 -0.20 2.28 2.02 -0.26
Particulars
FY 17 FY 18
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
O&M Expenses 24.30 24.30 0.00 25.83 25.83 0.00
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 105 of 114
Particulars
FY 17 FY 18
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
Depreciation 31.97 29.90 -2.07 31.97 29.90 -2.07
Interest on Loan 27.19 25.16 -2.03 23.33 21.56 -1.77
Return on Equity 33.52 24.33 -9.19 33.52 24.33 -9.19
Interest on Working Capital
15.17 14.89 -0.28 15.17 14.90 -0.27
Special Allowance on Refinancing of loan
1.76 0.00 -1.76 1.56 0.00 -1.56
Total (Rs Cr) 133.91 118.57 -15.34 131.38 116.51 -14.87
Ex-bus Energy Sent Out (kwh)
596.42 596.42 0.00 596.42 596.42 0.00
Fixed Cost per Unit
2.25 1.99 -0.26 2.20 1.95 -0.25
Particulars
FY 19
As claimed by BEPL
As determined by the
Commission
Difference (if any)
O&M Expenses 27.46 27.46 0.00
Depreciation 31.97 29.90 -2.07
Interest on Loan 19.49 17.95 -1.54
Return on Equity 33.52 24.33 -9.19
Interest on Working Capital 15.18 14.92 -0.26
Special Allowance on Refinancing of
loan 1.35 0.00 -1.35
Total (Rs Cr) 128.96 114.55 -14.41
Ex-bus Energy Sent Out (kwh) 596.42 596.42 0.00
Fixed Cost per Unit 2.16 1.92 -0.24
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 106 of 114
ii. Representative calculation of Variable Charges:
(a) Variable charge per unit of Generation: For the purpose of calculation of
normative working capital
Based on the operation norms provided in the UPERC Generation Tariff Regulations,
2014, the variable charge per unit of generation for Utraula Power Station for the MYT
period of F.Y. 2014-15 to F.Y 2018-19 has been arrived at. The calculation shown below
is representative of the variable cost calculation and has been used to arrive at some of
the components of normative working capital.
.Variable charge per unit of generation for Utraula Power Station
Description Unit 2014-15 2015-16 2016-17 2017-18 2018-19
Capacity MW 90.00 90.00 90.00 90.00 90.00
PAF % 85 85 85 85 85
Gross generation MU 670.14 670.14 670.14 670.14 670.14
Auxiliary Consumption
% 11 11 11 11 11
Net units sent out MU 596.42 596.42 596.42 596.42 596.42
Gross station heat rate
Kcal/kWh 2890 2890 2890 2890 2890
Specific oil consumption
ml/kWh 1.00 1.00 1.00 1.00 1.00
Calorific value of secondary fuel
KCal/Lt 10.00 10.00 10.00 10.00 10.00
Weighted average landed price of coal
Rs./Kg 4.27 4.41 4.41 4.41 4.41
Calorific value of Coal
kCal/kg 3375.82 3440.09 3440.09 3440.09 3440.09
Weighted average landed price of secondary fuel
Rs./mL 0.07 0.04 0.04 0.04 0.04
Energy charge rate (ECR)
Rs/kWh 4.17 4.20 4.20 4.20 4.20
(b) Cost of alternative coal supply:
Regulation 26 (iv) of the UPERC Generation Tariff Regulations 2014 specifies the norms
for the calculation of cost of alternative coal supply:
“In case of part or full use of alternative source of fuel supply by coal based thermal
generating stations other than as agreed by the generating company and beneficiaries
in their power purchase agreement for supply of contracted power on account of
shortage of fuel or optimization of economical operation through blending, the use of
alternative source of fuel supply shall be permitted to generating station;
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 107 of 114
Provided further that the weighted average price of use of alternative source of fuel
shall not exceed 30% of base price of fuel computed as per clause (v) of this
regulation;
Provided also that where the energy charge rate based on weighted average
price of use of fuel including alternative source of fuel exceeds 30% of base
energy charge rate as approved by the Commission for that year or energy
charge rate based on weighted average price of use of fuel including alternative
sources of fuel exceeds 20% of energy charge rate based on weighted average
fuel price for the previous month, whichever is lower shall be considered and in
that event, prior consent of the beneficiary shall be taken by the generator by
serving a notice upon the beneficiary in writing not later than seven working
days in advance.
Provided that if the beneficiary does not respond to the notice given by the generator
in writing within the above stipulated time, the beneficiary shall be liable for payment of
fixed charges to generator”
Further Alternative coal supply from CIL beyond the FSA must be done through e-
auction route and for procurement of domestic open market coal and imported coal
the generating companies shall follow a transparent competitive bidding process so as
to identify a reasonable market price.
However the Commission directs that the Committee should be formed for carrying
out the above mentioned process with at least one member of the Beneficiary.
Accordingly the cost of alternative coal supply for FY 2016-17 shall not exceed the
following:
Period Maximum ECR (Rs/kWh)
01.04.2016 to 31.03.2017 5.46
The rates for the subsequent years shall be computed as per the Regulations.
(c) Adjustment of Rate of Energy Charge on Account of Variation in price or
Heat Value of Fuels:
Any variation shall be adjusted on month to month basis on the basis of Gross Calorific
Value of coal or gas or liquid fuel as received and landed cost incurred by the generating
company for procurement of coal, oil, or gas or liquid fuel, as the case may be. No
separate petition needs to be filed with the Commission for fuel price adjustment. In case
of any dispute, an appropriate application in accordance with Uttar Pradesh Electricity
Regulatory Commission (Conduct of Business) Regulations 2004, as amended from time
to time or any statutory re-enactment thereof, shall be made before the Commission.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 108 of 114
Provided further that copies of the bills and details of parameters of GCV and price of fuel
i.e. domestic coal, imported coal, e-auction coal, lignite, liquid fuel etc., details of blending
ratio of the imported coal with domestic coal, proportion of e-auction coal shall also be
displayed on the website of the generating company. The details should be available on its
website on monthly basis for a period of three months.
However, UPPCL shall verify the “As Received GCV” and landed cost of coal from
the original coal purchase bills.
BEPL shall be entitled to recover / adjust any change in fuel cost according to the
provisions set out in the Generation Regulations.
iii. Summary - Capacity Charges (Cost):
The total capacity charges (costs) for Utraula Thermal Power Station for the MYT period of
FY 2014-15 to FY 2018-19 is summarized in the table below.
Cost per kWh as claimed with those as allowed by the Commission
Particulars
FY 15 FY 16
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
Fixed Cost (Rs Cr.)
139.46 127.49 -11.97 136.22 120.72 -15.49
F. C. per Unit (In Rs/kWh)
2.34 2.14 -0.20 2.28 2.02 -0.26
Particulars
FY 17 FY 18
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
As claimed by BEPL
As determined
by the Commission
Diff. (if any)
Fixed Cost (Rs Cr.)
133.91 118.57 -15.34 131.38 116.51 -14.87
F. C. per Unit (In Rs/kWh)
2.25 1.99 -0.26 2.20 1.95 -0.25
Particulars
FY 19
As claimed by BEPL As determined by the
Commission Diff.
(if any)
Fixed Cost (Rs Cr.)
128.96 114.55 -14.41
F. C. per Unit (In Rs/kWh)
2.16 1.92 -0.24
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 109 of 114
Summary of Fixed Cost for the MYT period
FY 2014-15 to FY 2018-19
F.C (Rs. Cr) F.C/ Unit (Rs./kWh)
FY 2014-15 FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19
Petition Approved Diff Petition Approved Diff Petition Approved Diff Petition Approved Diff Petition Approved Diff
Barkhera
F.C 133.63 122.54 -11.09 129.89 116.21 -13.68 127.84 114.27 -13.57 125.57 112.44 -13.13 123.41 110.70 -12.71
F.C/Unit
2.24 2.05 -0.19 2.18 1.95 -0.23 2.14 1.92 -0.23 2.11 1.89 -0.22 2.07 1.86 -0.21
Maqsoodapur
F.C 135.00 122.80 -12.20 132.12 115.89 -16.23 130 113.96 -16.04 127.66 112.13 -15.53 125.43 110.38 -15.04
F.C/Unit
2.26 2.06 -0.20 2.22 1.94 -0.27 2.18 1.91 -0.27 2.14 1.88 -0.26 2.10 1.85 -0.25
Khambarkhera
F.C 139.54 124.13 -15.41 137.12 117.63 -19.49 134.81 115.61 -19.20 132.27 113.69 -18.58 129.84 111.87 -17.98
F.C/Unit
2.34 2.08 -0.26 2.30 1.97 0.33 2.26 1.94 0.32 2.22 1.91 0.31 2.18 1.88 0.30
Kundarki
F.C 135.88 124.21 -11.67 132.60 117.15 -15.45 130.45 115.13 -15.32 128.07 113.20 -14.87 125.8 111.37 -14.43
F.C/Unit
2.28 2.08 -0.20 2.22 1.96 -0.26 2.19 1.93 -0.26 2.15 1.90 -0.25 2.11 1.87 -0.24
Utraula
F.C 139.46 127.49 -11.97 136.22 120.72 -15.49 133.91 118.57 -15.34 131.38 116.51 -14.87 128.96 114.55 -14.41
F.C/Unit
2.34 2.14 -0.20 2.28 2.02 -0.26 2.25 1.99 -0.26 2.2 1.95 -0.25 2.16 1.92 -0.24
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 110 of 114
10. OTHER PROVISIONS
(A) Recovery of Water Cess and Tax on Income etc.
In addition to the above tariff BEPL is allowed to recover the payment of statutory charges like
water cess, cost of water, payment to Pollution Control Board, rates and taxes, FBT and
Regulatory Fee paid to the Commission, on production of details of actual payments made
and duly supported with the certificate of the Statutory Auditors.
(B) Incentive :
Incentive shall be calculated according to Regulations 27 of UPERC (Terms and Conditions of
Generation tariff) Regulations, 2014. Incentive does not form a component of tariff.
(C) Billing & Payment :
Billing and Payment of Capacity Charges shall be done under provisions of Regulation 51 of
UPERC (Terms and Conditions of Generation Tariff) Regulations, 2014.
(D) Additional Capital Expenditure:
The Petitioner shall seek prior approval of the Commission before undertaking additional
capital expenditure on its generation stations.
(E) Truing up of Capital Expenditure and Tariff
(i) The Commission shall carry out true up exercise along with the tariff petition filed for the
next tariff period with respect to the Capital Expenditure incurred up to 31.03.2019, as
admitted by the Commission after prudence check at the time of truing up.
(ii) The generating company shall make an application, as per Appendix II to these
regulations, for carrying out truing up exercise in respect of the generating station or any
of its units or block of units thereof by 31.10.2019.
(iii) The generating company shall submit for the purpose of truing up, details of capital
expenditure and additional capital expenditure incurred duly audited and certified by the
auditors.
Provided the Commission may appoint a separate independent auditor who, under the
supervision of the Commission, shall undertake technical and financial audit of the
generating station at any time
(iv) The Commission shall also carry out truing up of tariff of generating stations based on
the performance of following controllable parameters:
(a) Gross Station Heat Rate;
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 111 of 114
(b) Secondary Fuel Oil Consumption;
(c) Auxiliary Energy Consumption; and
(d) Re-financing of Loan
(v) The Commission shall carry out truing up of tariff of generating stations based on the
performance of following uncontrollable parameters:
(a) Force Majeure;
(b) Change in Law; and
(c) Primary Fuel Cost
(vi) The financial gains by a generating company on account of controllable parameters
shall be shared between generating company and the beneficiaries. The financial gains
computed as per following formulae in case of generating station on account of
operational parameters contained in Regulation(4) (a) to (c) of Generation Regulation
2014 shall be shared in the ratio of 80:20 between generating company and the
beneficiaries:
Net Gain = (ECRN– ECRA) x Scheduled Generation
(vii) The financial gains and losses by a generating company on account of uncontrollable
parameters shall be passed on to beneficiaries of the generating company.
(viii) Where after the truing up the tariff recovered exceeds the tariff approved by, the
Commission under these regulations the generating company shall refund to the
beneficiaries, the excess amount so recovered along with simple interest at the rate
equal to the Bank Rate prevailing as on 1st April of the respective Year.
(ix) Where after the truing up the tariff recovered is less than the tariff approved by the
Commission under these regulations the generating company shall recover from the
beneficiaries, the under-recovered amount along with simple interest at the rate equal to
the Bank Rate, prevailing as on 1st April of the respective Year.
(x) The amount under-recovered or over-recovered, along with simple interest at the rate
equal to the Bank Rate as on 1st April of the respective Year, shall be recovered or
refunded by the, generating company, in six equal monthly installments starting within
three months from three months from the date of the tariff order issued by the
Commission after the truing up exercise
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 112 of 114
11. COMMISSION’S ADDIONAL DIRECTIVES
1. The Commission is of the view that it is essential for the project developer to adopt procedures
such that expenses are incurred in a prudent manner to achieve efficiency in costs. As the
fixed costs of the generating station is ultimately passed on to the consumers of the
distribution licensees in the state as part of the tariff, it is essential to always consider the
interest of consumers while awarding such contracts. It has also been observed that due
diligence has not been taken while awarding the EPC contracts. Therefore the Commission
hereby directs that in future, award of contract for procurement of major equipment, services
and works should be done through a transparent process involving a two part competitive bid
process so as to ensure cost efficiency and prudency. For award of major contract
packages the project developer should set up a Committee to manage the bid process.
This Committee shall also include a representative from the procurers to avoid pre and
post bid disputes.
2. The Commission has considered the submission of stakeholders that the power plants of
BEPL do not have railway siding in place for receipt of coal and that this leads to high
transportation cost of coal. This ultimately results in higher variable cost. Due to higher
variable cost, the generation most of the times does not qualify under merit order dispatch and
procurer ends up paying the fixed charges which is actually additional burden passed on to the
end consumers. The Commission is of the view that the end consumer is unnecessarily being
burdened in such a situation which is due to improper planning on the part of the Petitioner. In
view of this, the Commission considers that BEPL and UPPCL should jointly submit a plan to
rationalize the cost of primary fuel for these plants. The plan should specifically lay emphasis
on reducing the variable cost and also explore options for cheaper procurement of coal. The
plan should be submitted within six months of date of issue of this Tariff Order.
3. As per Section 86 of the Electricity Act 2003, the State Commission can determine the tariff for
various utilities in the state for generation, transmission and distribution. As a part of the tariff
determination process, the respective Petitioners are required to submit various information
and data pertaining to capital cost, operational and financial performance and fuel cost etc.
before the Commission.
Section 62 (2) of the Electricity Act 2003 empowers the Commission to seek information and
data from the entities for determination of tariff.
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 113 of 114
“The Appropriate Commission may require a licensee or a generating company to
furnish separate details, as may be specified in respect of generation, transmission and
distribution for determination of tariff.”
As per Section 2. (7) of the UPERC (Terms and Conditions of Generation Tariff) Regulations,
2014, the Petitioners are required to submit performance report to the Commission in every six
months period as per the format specified in Appendix I of the Regulations.
“(7) The generating company shall submit performance report to the Commission under
Section 10(3) (a) of the Act in the format given in Appendix I to these regulations.”
However, the required data is not submitted by the Utilities periodically before the Commission.
During filing of Petition, the Petitioner is required to submit details as per specified tariff filing
formats. It is observed that the information and data in the required formats are also not
submitted by the Petitioner which hampers and delays the tariff determination process. Many a
times wide discrepancies are observed in the submitted data. The Commission has to give
repeated directions to the Petitioner to submit the details post which it is submitted, if available
with the Petitioner. Moreover in some cases the Petitioner is unable to submit data as it has not
implemented processes to record and maintain such data or information.
During true up also, the Petitioner is required to submit the actual and audited data which forms
the basis for true-up. The inability of the Petitioner to submit the requisite information and data
as sought by the Commission can impact the tariff determination and as a result the end
consumer at large.
Hence it is important that issue is addressed and a mechanism is developed in consultation with
the Utilities, Generators, other stakeholders and the public so that the required data or
information is made available to the Commission on a periodic basis. This will also bring
uniformity transparency in the process.
4. As per the Uttar Pradesh Electricity Regulatory Commission (Compliance Audit) Regulations,
2012
“3.1 The Commission may, at any time, conduct audit of regulated entity for verifying
their compliance with the Act, Rules, Regulations made thereunder, orders and
directions issues by the Commission.”
The regulated entity means Distribution Licensee or Generation Company or Transmission Utility
or Trading Licensee or SLDC. The Commission may by order empanel Consultants/Auditors
Approval of Final Capital Cost, True up FY 12-14 and Multi Year Tariff of BEPL for FY 15-19
Page 114 of 114
required to assist the Commission in discharge of these functions on the terms and conditions as
deemed fit.
Hence, to address the non-compliance on the part of the Generation Companies in providing
data, the Commission would initiate independent audit.
12. IMPLEMENTATION OF ORDER
This order shall be reckoned to have come into effect from 01.04.2014 and shall remain
effective till 31.03.2019 for the Multi Year Tariff period of F.Y. 2014-15 to FY 2018-19. BEPL is
entitled to raise the bills as per the tariff order under provisions of UPERC (Terms &
Conditions of Generation Tariff) Regulations, 2014.
(Suresh Kumar Agarwal) (Desh Deepak Verma)
Member Chairman
Place: Lucknow
Dated: 24.05.2017