Document of The World Bank FOR OFFICIAL USE ONLY Report No: 57661-CN PROJECT APPRAISAL DOCUMENT ON A PROPOSED LOAN IN THE AMOUNT OF US$100 MILLION TO THE PEOPLE'S REPUBLIC OF CHINA FOR A SICHUAN WUDU IRRIGATED AGRICULTURE DEVELOPMENT PROJECT January 20, 2012 China and Mongolia Sustainable Development Unit Sustainable Development Department East Asia and Pacific Region This document is being made publicly available prior to Board consideration. This does not imply a presumed outcome. This document may be updated following Board consideration and the updated document will be made publicly available in accordance with the Bank’s Policy on Access to Information. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

Document of

The World Bank

FOR OFFICIAL USE ONLY

Report No: 57661-CN

PROJECT APPRAISAL DOCUMENT

ON A

PROPOSED LOAN

IN THE AMOUNT OF US$100 MILLION

TO THE

PEOPLE'S REPUBLIC OF CHINA

FOR A

SICHUAN WUDU IRRIGATED AGRICULTURE DEVELOPMENT PROJECT

January 20, 2012

China and Mongolia Sustainable Development Unit Sustainable Development Department East Asia and Pacific Region

This document is being made publicly available prior to Board consideration. This does not imply a presumed outcome. This document may be updated following Board consideration and the updated document will be made publicly available in accordance with the Bank’s Policy on Access to Information.

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

ii

CURRENCY EQUIVALENTS

(Exchange Rate Effective August 16, 2010)

Currency Unit = RMB

RMB1.00 = US$ 0.147

US$1.00 = RMB 6.80

FISCAL YEAR

July 1 – June 30

ABBREVIATIONS AND ACRONYMS

CDD

CEA

Community Driven Development

Consolidated Environmental Assessment

DRC Development and Reform Commission

DSP

DSR

Dam Safety Panel

Dam Safety Report

EG Expert Group

EIRR Economic Internal Rate of Return

FMS Financial Management Specialist

FSR Feasibility Study Report

CY Calendar Year

ICR Implementation Completion Report

MIS Management Information System

MOF Ministry of Finance

MTR Mid-Term Review

MWR Ministry of Water Resources

M&E Monitoring & Evaluation

NCB National Competitive Bidding

NDRC National Development and Reform Commission

O&M

OMS

PCs

Operation and Maintenance

Operation, Maintenance, and Surveillance

Producer Co-operatives

PIP Project Implementation Plan

PMP Pest Management Plan

PLG Project Leading Group

PMO Project Management Office

PRA Participatory Rapid Assessment

RAP Resettlement Action Plan

SIL Specific Investment Loan

SOE Statement of Expenditure

TTL Task Team Leader

WA Withdrawal Application

WUAs Water User Associations

Regional Vice President: Ms. Pamela Cox

Country Director: Mr. Klaus Rohland

Sector Managers: Mr. Paul Kriss and Mr. Vijay Jagannathan

Task Team Leader: Mr. Liping Jiang

Page 3: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

iii

CHINA

Sichuan Wudu Irrigated Agriculture Development Project

CONTENTS

I. Strategic Context ............................................................................................................... 1 A. Country Context .................................................................................................................. 1

B. Sectoral and Institutional Context ....................................................................................... 1 C. Higher Level Objectives to which the Project Contributes ................................................ 2

II. Project Development Objectives ...................................................................................... 3 A. PDO..................................................................................................................................... 3 B. Project Beneficiaries ........................................................................................................... 3

C. PDO Level Results Indicators ............................................................................................. 3

III. Project Description ........................................................................................................... 3 A. Project Components ............................................................................................................ 4 B. Project Financing ................................................................................................................ 5

IV. Implementation ................................................................................................................. 6 A. Institutional and Implementation Arrangements ................................................................ 6 B. Results Monitoring and Evaluation .................................................................................... 7 C. Sustainability....................................................................................................................... 8

V. Key Risks and Mitigation Measures ............................................................................... 8

VI. Appraisal Summary .......................................................................................................... 9 A. Economic and Financial Analysis ....................................................................................... 9 B. Technical ........................................................................................................................... 10 C. Financial Management ...................................................................................................... 10

D. Procurement ...................................................................................................................... 11 E. Social................................................................................................................................. 11 F. Environment ...................................................................................................................... 12

Annex 1. Results Framework and Monitoring ............................................................................. 14

Annex 2. Detailed Project Description ........................................................................................ 16 Annex 3. Implementation Arrangements ..................................................................................... 24

Annex 4. Operational Risk Assessment Framework (ORAF) ...................................................... 37 Annex 5. Implementation Support Plan ........................................................................................ 40

Annex 6. Team Composition ........................................................................................................ 42

Page 4: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn
Page 5: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

iv

SICHUAN WUDU IRRIGATED AGRICULTURE DEVELOPMENT PROJECT

PROJECT APPRAISAL DOCUMENT

EAST ASIA AND PACIFIC

EASCS

Date: January 20, 2012

Country Director: Klaus Rohland

Sector Director: John Roome

Sector Managers: Paul Kriss/Vijay Jagannathan

Team Leader: Liping Jiang

Project ID: P121414

Lending Instrument: SIL

Sectors: Irrigation & Drainage (60%);

Water Supply (20%); Agricultural Ext &

Research (20%)

Theme: Rural Services (100%)

EA Category: A

Project Financing Data:

Proposed terms: U.S. Dollar, variable spread loan with a maturity of 25 years, including a six-

year grace period, with level repayment on principle, and a front-end fee of 0.25% ogf the loan

amount.

[ X ] Loan [ ] Credit [ ] Grant [ ] Guarantee [ ] Other:

Source Total Amount (US$M)

Total Project Cost:

Borrower :

Total Bank Financing:

IBRD:

700.77

600.77

100.00

Ms. Wang Wei, Director IF Division I

Ministry of Finance, People's Republic of China

San Li He, Beijing 100820, China

Tel: (86-10) 68551174; Fax: (86-10) 68551125

Email: [email protected]

Mr. Zhou Lijun, Standing Deputy Director

Municipal Project Management Office

Wudu Water Diversion Management Bureau

Mianyang City, Sichuan Province, China

Tel: (86-816) 2683964; Fax: (86-816) 2689505

Email: [email protected]

Estimated Disbursements (US$M)

FY 2013 2014 2015 2016 2017 2018

Annual 5 15 15 25 30 10

Page 6: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

v

Cumulative 5 20 35 60 90 100

Project implementation period: October 2011- December 2017

Expected effectiveness date: August 31, 2012

Expected mid-term review date: December 31, 2015

Expected closing date: December 31, 2017

Does the project depart from the CAS in content or other

significant respects?

○ Yes ● No

If yes, please explain:

Does the project require any exceptions from Bank policies?

Have these been approved /endorsed (as appropriate by Bank

management?

Is approval for any policy exception sought from the Board?

○ Yes ● No

○ Yes ● No

○ Yes ● No

If yes, please explain:

Does the project meet the regional criteria for readiness for

implementation?

●Yes ○ No

If no, please explain:

Project Development objective:

The Project Development Objectives (PDOs) are to: (a) increase the coverage of irrigation

services in the Project Area in order to increase agricultural production; (b) provide water

supply, in bulk, to small rural communities and industries in the Project Area; and (c)

introduce a community-based participatory approach in the management of water facilities and

infrastructure and increase of production capacity of higher-value agro-products in the Project

Area to ensure the sustainable development of agriculture.

Project description [one-sentence summary of each component]

Component 1: Construction of Main Irrigation System (Total cost US$691.03 million, of

which Bank Financing US$97.41 million);

Component 2: Development of CDD-based On-farm Works in Demonstration Areas (Total

cost US$4.49 million, of which Bank Financing US$0.90 million); and

Component 3: Institutional Capacity Building and Project Management Support (Total cost

US$1.44 million with Bank Financing 100%)

Safeguard policies triggered?

Environmental Assessment (OP/BP 4.01)

Natural Habitats (OP/BP 4.04)

Forests (OP/BP 4.36)

Pest Management (OP 4.09)

Physical Cultural Resources (OP/BP 4.11)

Indigenous Peoples (OP/BP 4.10)

Involuntary Resettlement (OP/BP 4.12)

Safety of Dams (OP/BP 4.37)

Projects on International Waters (OP/BP 7.50)

Projects in Disputed Areas (OP/BP 7.60)

● Yes ○ No

● Yes ○ No

○ Yes ● No

●Yes ○ No

○ Yes ● No

○ Yes ● No

●Yes ○ No

● Yes ○ No

○ Yes ● No

○ Yes ● No

Page 7: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

vi

Conditions and Legal Covenants

Financing

Agreement

Reference

Description of Condition/Covenant Date Due

Project

Agreement

1) Sichuan shall maintain the organizational structure

established for the purpose of implementing the Project

(the Provincial Project Leading Group, the Municipal

Project Leading Group, and the Municipal Project

Management Office, County Project Leading Group in

each of the Project Counties and County Project

Management Office in each of the Project Counties).

Until

12/31/2017

2) Sichuan shall apply in the implementation of the Project,

the Project Implementation Plan, the RAP, the EMP, the

PMP, the annual implementation plan and the annual

dam safety action plan, all in a manner satisfactory to the

Bank. Sichuan shall not amend, suspend, or waive any

such plan or any provision thereof, without the prior

concurrence of the Bank.

Until

12/31/2017

3) Sichuan shall: (a) carry out measures satisfactory to the

Bank for improving the living standard of Displaced

Persons affected by the implementation of the Project in

accordance with the provisions of the RAP; and (b)

include appropriate and adequate provisions in the

contracts entered into for implementing the Project to

ensure the fulfillment of the requirements set out in the

EMP together with specification of sanctions to be

imposed or other measures to be taken for failure to carry

out said requirements.

Until

12/31/2017

4) Sichuan shall engage and retain the services of

independent consultants to carry out external monitoring

and reporting, on an annual basis, and shall implement

the recommended measures in a prompt and efficient

manner satisfactory to the Bank, in order to improve

compliance with the RAP.

Until

12/31/2017

5) Sichuan shall: (a) maintain the Dam Safety Panel under

terms of reference, including a time-table and adequate

budget for its activities, satisfactory to the Bank to, inter

alia, review the safety aspects of Upstream Dams,

recommend any needed safety measures, review and

provide comments on the Dam Safety Plans, and review

the design and construction of the Project Dam; and (b)

cause the Dam Safety Panel to carry out its function as

set out in its terms of reference and to provide to the

Bank and Sichuan annual reports of findings and

recommendations for any safety related measures.

Until

12/31/2017

Page 8: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

vii

6) Sichuan shall prepare and provide to the Dam Safety

Panel and the Bank the Dam Safety Plans for the Project

Dam in accordance with a timeframe related to the

progress of the design and construction of said Dam

satisfactory to the Bank. Sichuan shall implement said

Plans in a manner satisfactory to the Bank, and shall not

amend, abrogate, repeal, waive, or fail to enforce any

provisions of any such Plan without the prior concurrence

of the Bank.

Until

12/31/2017

7) Sichuan shall establish and implement satisfactory

arrangements for the periodical inspection of the

Upstream Dams and the Project Dam.

Until

12/31/2017

8) Sichuan shall monitor and evaluate the progress of the

Project and prepare Project Reports for the Project. Each

such Project Report shall cover the period of one

calendar semester, and shall be furnished to the Bank by

February 15 and August 15 each year, beginning on

August 15, 2012.

Until

12/31/2017

9) Sichuan shall, not later than June 30, 2015, review with

the Bank (mid-term review) the progress made in the

implementation of the Project, together with any

recommendation the Borrower or the Bank may have on

measures to be taken to ensure the efficient completion of

the Project and to achieve the objectives thereof.

12/31/2015

10) Sichuan shall install and operationalize for use the

Procurement and Financial Management Information

System no later than Forty-five (45) days after the

Effective Date, and thereafter apply the system in order

to monitor the entire procurement process and financial

transactions under the Project in a manner satisfactory to

the Bank.

Until

12/31/2017

11) Sichuan shall, with respect to the irrigation system

constructed under the Project, in order to ensure the

proper operation and maintenance of such system, at least

three months prior to the completion of each facility

under such system, prepare and furnish to the Bank for

review and comment a proposed operation and

maintenance plan for such facility, including institutional,

technical and financial arrangements, and, thereafter,

ensure the prompt implementation of each such plan,

taking into account the views of the Bank thereon.

Until

12/31/2017

Page 9: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

viii

12) Sichuan shall, in accordance with provisions of the

WUA Manual, take adequate steps to facilitate the

establishment of a WUA in each Project County with the

objective of securing the participation of the WUA in

carrying out on-farm works under the Project as well as

in the operation and maintenance of said works after their

completion.

Until

12/31/2017

13) Sichuan shall within four months of completing each

branch canal under the Project prepare a program, in

accordance with the irrigation development plan of

Mianyang City, satisfactory to the Bank, for extending

the community demand driven approach of carrying out

on-farm works from the demonstration areas under the

Project to other parts of the Project Area serviced by each

said canal. Sichuan shall cause Mianyang City to allocate

the required budgetary and other resources needed for

implementing said program, and to implement said

program in accordance with a timeframe and

arrangements satisfactory to the Bank.

12/31/2017

Page 10: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn
Page 11: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

1

I. Strategic Context

A. Country Context

1. China, with an annual per capita freshwater resource of about 2,160 m3, is a

water-stressed country. The severity of the problem is further worsened by the uneven

spatial and temporal distribution of these resources. Water availability in different parts

of China varies greatly due to the characteristics of its climate and topography. This

spatial disparity does not match the distribution of China’s population, arable land, and

productivity. The situation would worsen as demand increases due to population increase

and more competition for water use would put more stress on the available water

resources and on water quality. Furthermore, climate change impact is aggravating water

scarcity in China. Over the past 20 years, while main stream water flows have declined

substantially and the precipitation pattern is anticipated to be more uncertain, the uneven

spatial and temporal distribution of the precipitation will worsen the already serious water

shortage situation, especially in south-west China.

2. China’s general strategy for addressing the main development issues on water, as

indicated in its Twelfth Five-Year Plan (2011-2015) and Medium-term Plan of Water

Resources Development is to enforce strict water resources management in all water use

sectors, in addition to construction and rehabilitation of water engineering works,

particularly in irrigated agriculture. At the same time, the government strongly

emphasizes integration between increase in water use efficiency and increase in farmer

income and agricultural production. Government policy also recognizes the need for

institutional reform, including increasing farmer participation and ownership in irrigation,

and strengthening the organizations responsible for operation and maintenance (O&M).

B. Sectoral and Institutional Context

3. With China’s rapid social and economic development since 1970s, many parts of

the country are experiencing growing water scarcity. Three different types of water

scarcity can be distinguished: (a) physical scarcity occurs when there are not sufficient

water resources available to meet all water demands, including environmental flows; (b)

pollution scarcity as a result of limited available clean water for water users, and high

cost of providing safe water; and (c) economic scarcity occurs when there is a lack of

investment in water infrastructure or a lack of human, institutional and/or financial

capacity to satisfy the demand for water.

4. Experiences and lessons in China and other parts of the world suggest that the

strategic focus to address water shortage issues should be different depending on the type

of scarcity experienced and on the conditions that exist. For example, in areas with

physical scarcity, the focus should be on reducing consumptive use (evapotranspiration,

ET) while still trying to increase farmer incomes, by means of increasing the value (in

RMB Yuan) of agricultural production (and/or other uses) per unit of consumed water

(i.e. water productivity in terms of consumptive use), possibly by integrating water

Page 12: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

2

management basin-wide. For the pollution-related water shortages, the focus should be

on reducing pollution discharges into water bodies, including pollution from non-point

sources, possibly with a basin-wide participatory approach for pollution control. In areas

with economic water scarcity, engineering measures for improving the irrigation

infrastructure, combined with agronomic measures and participatory irrigation

management measures, should be promoted in the agricultural sector to increase

agricultural production and farmer incomes. In areas with mixed types of water scarcity,

all of the above measures would need to be applied.

5. Mianyang City is relatively abundant in water resources (with over 1,100 mm of

annual rainfall and the water-rich Fujiang river flowing through the City), but the project

area is very short of water for irrigated agriculture, mainly because of the relatively

uneven temporal and spatial distribution of water resources. Hence it can be considered

an area with economic scarcity.

6. Four key development issues were identified in water resources development and

utilization in the project areas: (a) main irrigation infrastructure systems and on-farm

works (lateral, sub-lateral and farm ditches) need to be constructed or rehabilitated

urgently to help agricultural production recover from the big earthquake; (b) water

shortages and frequent droughts impede agricultural development; (c) water use

efficiency and productivity are very low (water use in irrigated agriculture accounts for

66% of the total water use, and the actual consumptive use of water accounts for only

20% of the total available water resources in the City); and (d) sustainability of

constructed water infrastructure has not been ensured. Operation and Maintenance

(O&M) for both main/branch systems and on-farm works (lateral, sub-lateral and farm

ditches) needs to be improved.

7. The proposed project would support and complement the Government’s strategy

and its 12th

Five-year plan (2011-2015) in such water shortage areas to increase

agricultural production and farmer incomes with integrated measures.

C. Higher Level Objectives to which the Project Contributes

8. The proposed project is consistent with the Bank Group’s 2006-2010 Country

Partnership Strategy (CPS) for China, discussed by the Executive Directors on May 23,

2006. The proposed project would support Pillar 2 of the CPS to reduce poverty,

inequality and social exclusion, through promoting balanced urbanization, sustaining

rural livelihoods, and expanding access to basic social and infrastructure services,

particularly in the rural areas, and Pillar 3 to manage resource scarcity through

conserving water resources. It would also support the new China Country Partnership

Strategy (China CPS) for 2011-2015, under preparation.

Page 13: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

3

9. The higher level objectives to which the proposed project would contribute are:

(a) to help significantly improve livelihoods of poor farmers in the Project Area1 by

shifting the current reliance on rain-fed agriculture to irrigated agriculture; and (b) to

showcase and disseminate an innovative approach to Community Driven Development

(CDD) in the project area, which enables farmers to decide on ways to increase their

incomes, with assistance as necessary from local government.

II. Project Development Objectives

A. PDO

10. The Project Development Objectives (PDOs) are to: (a) increase the coverage of

irrigation services in the Project Area in order to increase agricultural production; (b)

provide water supply, in bulk, to small rural communities and industries in the project

area; and (c) introduce a community-based participatory approach in the management of

water facilities and infrastructure and increase of production capacity of higher-value

agro-products in the Project Area to ensure the sustainable development of agriculture.

B. Project Beneficiaries

11. The key beneficiaries of the project are about 1.35 million poor farmers (397,000

households) who will be able to receive reliable irrigation water supplies and change

from mainly dry farming to irrigated agriculture and boost their agriculture production.

Other key beneficiaries are about 1.7 million poor people in rural and small urban

communities, in addition to the industries in Mianyang City and other cities who will be

provided by water supply, in bulk, from the irrigation infrastructure for drinking and

industrial purposes.

C. PDO Level Results Indicators

12. The PDO would be monitored and evaluated during project implementation

through five PDO-level Results Indicators: (a) expanded new irrigated areas; (b)

increased annual value of agricultural production; (c) increased annual amount of

industrial and domestic water supply; (d) the number of farmers (and female farmers)

benefiting from the supplementary irrigation; and (e) the number of O&M plans prepared

and implemented by water management units for main irrigation systems and by WUAs

for on-farm irrigation systems.

III. Project Description

1 The project area refers to the irrigated area of 70,200 hectares covered by the Wudu Second-phase

Irrigation Scheme, including 60,250 hectares under Xizi Main Canal, and 9,950 hectares directly under

Wudu Reservoir.

Page 14: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

4

A. Project Components

13. The Project, which constitutes the second phase of the Wudu Scheme of the

Sichuan Province of the Borrower, consists of the following parts.

Component 1: Construction of Main Irrigation Systems1 (Total cost US$691.03 million,

of which Bank Financing US$97.41 million)

14. Construction and operation of the second phase of the Wudu Scheme to irrigate

about 70,200 hectares of land as well as to supply water to urban and rural areas, and

water to industries in the project area, and consisting of two systems:

(1) Construction of branch canals from the right and left segments of the Wudu

Reservoir to irrigate areas directly under said Reservoir.

(2) Construction of a new main irrigation system consisting of:

(a) Construction of Xizi Main Canal with a total length of about 108 km to divert

water from the Wudu Reservoir to irrigate areas under said Canal in the

Project Area and consisting of numerous structures including tunnels,

aqueducts, siphons, gates and other structures;

(b) Construction of a reservoir at Jinfeng with intake from the Xizi Canal with a

total storage capacity of 98 million cubic meters consisting of tunnels,

aqueducts, siphons, gates and other structures including an asphalt concrete

core sock-fill dam with a height of 88m and a chest length of 454.87m, an

irrigation intake and a tunnel to supply and regulate the supply of water to the

irrigation system to be constructed; and

(c) Construction of Jinlong sub-main canal and 16 branch canals consisting of

numerous structures including tunnels, aqueducts, siphons, gates and other

structures to divert water to irrigate areas covered under the Xizi Main Canal

to be constructed.

Component 2: Development of CDD-based On-farm Works in Demonstration Areas

(Total cost US$4.49 million, of which Bank Financing US$0.90 million)

15. Carrying out of on-farm development works under community demand driven

(“CDD”) approach in selected demonstration areas in the counties of Jiangyou, Zitong

and Yanting of Mianyang City covering about 766 hectares within the irrigated area

covered by the second phase of the Wudu Water Diversion and Irrigation Scheme and

consisting of:

(1) Construction of on-farm works including 1 lateral canal and 3 sub-lateral canals

with a total length of about 48 km;

(2) Establishment and development of Water Users’ Associations (WUAs) and

enhancement of producer co-operatives based on community demand driven

1 The Bank would finance the first section (23 km) of Xizi Main Canal, Jinlong sub-main canal (24 km)

and 10 branch canals (228 km). The rest of the main systems will be fully financed by government.

Page 15: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

5

approach around a lateral canal area or sub-lateral areas in each demonstration

area to organize and implement the construction, operation and maintenance of

on-farm works; and

(3) Provision of an integrated package of agricultural inputs and supporting services

in each demonstration area to small holder agricultural producers and farmer

groups to maximize the benefit of irrigated water delivered to the field and help

increase farmer’s production and income.

Component 3: Institutional Capacity Building and Project Management Support (Total

cost US$1.44 million with Bank financing 100%)

16. Provision of technical assistance for the institutional strengthening of the Project

Counties and Sichuan to implement the Project including:

(1) Capacity building through, inter alia, study tours and training;

(2) Consulting services and office equipment; and

(3) Acquisition of vehicles to provide necessary technical support for implementing

the activities under the Components 1 and 2 of the Project.

B. Project Financing

17. Lending Instrument. The Project would be financed by an IBRD Specific

Investment Loan (SIL) in the amount of US$100.00 million. The Bank Loan will be on

standard IBRD terms for a US Dollar denominated, variable spread loan (VSL) based on

six-month LIBOR, plus an additional variable spread. Commitment-linked repayment in

25 year period, including a 6 year grace period, level repayment of principal. The above

terms are consistent with the Borrower’s choice of similar Bank financed projects.

18. Project Financing. Table below summarizes the project cost by component and

by source of financing.

COST BY COMPONENT (US$ MILLION)

Project Component IBRD Beneficiaries Government Total

A. Construction of Main Systems 97.41 0.00 593.62 691.03

Xizi Main Canal 31.05 0.00 306.66 337.71

Jinfeng Reservoir 0.00 0.00 136.19 136.19

Main Branch Canals 66.37 0.00 150.77 217.14

B. CDD-based On-farm Demonstration 0.90 1.13 2.46 4.49

Construction of On-farm Works 0.75 1.13 2.30 4.18

Establishment of CDD-based WUAs 0.10 0.00 0.00 0.10

Agricultural Input and Supporting 0.04 0.00 0.17 0.21

C. Capacity Building and Management 1.44 0.00 0.00 1.44

Institutional Capacity Building 0.65 0.00 0.00 0.65

Project Management Support 0.79 0.00 0.00 0.79

Total Project Cost 99.75 1.13 596.08 696.96

Interest during Construction 0.00 0.00 3.56 3.56

Front-end Fees 0.25 0.00 0.00 0.25

Total Financing Required 100.00 1.13 599.64 700.77

Page 16: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

6

19. Additional Local Financing1. An investment program for extension of the CDD-

based on-farm demonstration program developed under the project would be prepared

and approved by the government of each of the six project counties. The county

governments and project beneficiaries would provide, through their internal investment

programs outside the project, additional financing for: (a) construction of on-farm

irrigation systems (laterals and sub-laterals and farm ditches) to fully cover the project

area after the main systems are completed under the project; (b) establishment of CDD-

based WUAs to be responsible for O&M of the completed on-farm irrigation systems;

and (c) provision of agricultural inputs and supporting services to maximize the benefits

of water delivered. Sichuan shall within four months of completing each branch canal

under the Project prepare a program, in accordance with the irrigation development plan

of Mianyang City, satisfactory to the Bank, for extending the community demand driven

approach of carrying out on-farm works from the demonstration areas under the Project

to other parts of the Project Area serviced by each said canal. Sichuan shall cause

Mianyang City to allocate the required budgetary and other resources needed for

implementing said program, and to implement said program in accordance with a

timeframe and arrangements satisfactory to the Bank.

IV. Implementation

A. Institutional and Implementation Arrangements

20. The proposed organizations for project management and implementation have

been established in Mianyang City and its three counties (Jiangyou, Zitong and Yanting).

Responsibilities for project management and implementation are briefly presented below

and the flow of funds and accountabilities for financial reporting are detailed in Annex 3.

21. Provincial Level. The Provincial Project Leading Group chaired by the Director

General or the Deputy Director General of the Sichuan Provincial Finance Department,

or his/her delegate, comprising all relevant agencies at the Provincial level and

responsible for liaising with central government agencies concerning the Project and

providing overall policy guidance.

22. Municipal Level. The Municipal Project Leading Group at the municipal level in

Mianyang City of Sichuan chaired by the Vice Mayor of Mianyang City and consisting of

members from the Municipal Finance Bureau and all other relevant agencies of the City

and responsible for overseeing the overall implementation of the Project, making decision

on key Project issues and carrying out interagency coordination at the municipal level as

1 According to the government’s internal procedures on water investment programs, for a central

government financed irrigation project, the funds from the central or provincial government should

normally be used to finance construction of main irrigation systems only (dams, main canals and branch

canals), rather than construction of on-farm irrigation systems (lateral canals, sub-lateral canals and farm

ditches). The latter should be financed by county government and beneficiaries in separate projects after

main system is completed. This project is a central government financed project and included in the Bank’s

lending program for the purpose of construction of main irrigation systems in the earthquake stricken area

of Sichuan Province.

Page 17: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

7

well as coordination with the Provincial Project Leading Group referred to in paragraph

21 above. The Municipal Project Management Office located within the Sichuan Wudu

Water Diversion Management Bureau (the Bureau) and responsible for Project

management and implementation at the municipal level as well as reporting on progress

and implementation issues to the Bureau and the Municipal Project Leading Group.

23. In addition, an Expert Group (EG), and a Dam Safety Panel (DSP) have been

established at the municipal level. The EG would provide technical support to the

Municipal PMO. The DSP will assist in ensuring that the project is implemented in

compliance with the Bank’s policy on Safety of Dams (OP 4.37) under terms of reference

acceptable to the Bank. The EG will provide guidance to the county PMOs to carry out

its responsibilities.

24. County Level. A County Project Leading Group in each of the Project Counties

responsible for Project implementation, coordination and decision making at the county

level. A County Project Management Office in each of the Project Counties located

within the respective county level bureau of the Wudu Scheme and responsible for

Project management and implementation at the respective county level as well as

reporting on progress and implementation issues to the respective County Project

Leading Group.

25. In addition, an expert group for agro-water inputs and services would be

established at the county level to provide technical guidance to development and

implementation of CDD-based WUA Demonstration Program.

B. Results Monitoring and Evaluation

26. The Municipal PMO will be responsible for designing and putting in place a

suitable M&E system, acceptable to the Bank, with a focus on measuring project

outcomes and impact. An independent institute will be contracted to prepare the general

design of the M&E system supported by the Municipal PMO, and carry out project-wide

data collection and processing according to the design supported by the county PMOs

during the period of project implementation. The institute will also consolidate data

collected and prepare periodic M&E reports as required. The M&E design and work

program are included in the Project Implementation Plan (PIP). The complete set of PDO

level result indicators (5) and intermediate result indicators (10) are included in Annex 1.

27. The Municipal PMO will also develop and set up a computer-based Procurement

and Financial Management Information System (PROMIS) which will automatically

monitor the entire procurement process and financial transactions and will cross-check

data for errors and alerts authorities in a timely way. PROMIS will also provide

consolidated data for intermediate result indicators 6, 7, 8 and 9.

28. M&E reports will be submitted to the Bank annually. A mid-term review (MTR)

report of the project will be prepared and provided to the Bank before December 31,

2015, and an implementation completion report (ICR) upon project completion.

Page 18: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

8

C. Sustainability

29. The strategic policies of GOC, as well as of the provincial, city and county

governments, support the attainment of project objectives, and all levels of government

have strong ownership of the project. The provincial government is paying close

attention to the preparation and implementation of this project. At the municipal level, the

current 12th

Five-Year Plan (2011-2015) proposes detailed measures to speed up the

development of irrigated agriculture. More recently, a number of far-reaching cropping

pattern adjustment measures have been adopted to increase farmers’ incomes with the

adoption of the production of cash crops. With project design closely aligned to these

goals, the municipal and county governments have fully committed to the extension of

the CDD-based on-farm demonstration (Component 2) to other parts of the project area

to ensure sustainability and increased agricultural productivity.

30. The project is designed to be sustainable and replicable through the establishment

of policies and regulatory and institutional frameworks for more environmentally

sustainable economic growth and resource management. These policies and frameworks

will be reviewed, approved, and issued as official documents for implementation by the

Mianyang City beyond completion of the project, and will also be extended by the

Provincial Water Resources Bureau to other parts of Sichuan Province.

V. Key Risks and Mitigation Measures

31. The proposed project is a technically straight-forward project to be implemented

by project management offices that are already established in Mianyang City; these have

rich experience in implementing similar national irrigation projects and one Bank

financed project. The overall project risk is moderate. Risks identified at the project level

are manageable and proposed mitigation measures are reflected in the project design, and

in the project implementation plan (PIP). The main risks identified to the achievement of

the PDO and the mitigation measures for these risks are summarized below:

(a) Institutional Capacity. Staff at both municipal and county PMOs lack

familiarity with the Bank requirements and procedures. Frequent training will be

provided on Bank procedures and guidelines on financial management,

procurement, and safeguards during project implementation. The project M&E

and MIS system will help the municipal and county PMOs to monitor the

operations of project assets. In addition, a comprehensive construction

programming plan has been developed which will guide the PMOs to effectively

conduct and monitor the project implementation. The project FM Manual will

provide guidance to the municipal and county level PMOs.

(b) Safeguards. These risks refer to the possible delay or failure on compliance with

the Bank policies on environment, resettlement and dam safety. To militate

against the risk of failure to comply with Bank policies on environment,

resettlement and dam safety, sufficient funds are required to be allocated in the

Page 19: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

9

annual budget for implementing the EMP, including for regular workshops and

training for compliance with Bank safeguards requirements.

(c) Additional Local financing. In order to ensure that adequate and timely

financing is provided by prefecture/county governments for on-farm works

(lateral, sub-lateral canals and farm ditches) which are not financed by the Bank,

Bank implementation support missions will work closely with the provincial and

municipal governments to confirm that the necessary additional funds are

confirmed to be available for construction of these works.

VI. Appraisal Summary

A. Economic and Financial Analysis

Economic Analysis

32. The major quantifiable benefits (on an incremental basis) of the project are

derived from: (a) the agricultural production from improved and increased irrigation

areas; (b) value of industrial uses and; (c) value of water for domestic use. The economic

analysis is conducted for the Wudu Second-phase Irrigation Scheme as a whole, covering

all the project interventions. The project ERR is estimated at 13%, and the NPV (at a

discount rate of 12%) is estimated at US$278.98 million.

33. The project would generate numerous non-quantifiable social and environmental

benefits, which are not included in the analysis. These include: (a) flooding

control/drainage function provided by the irrigation canal system (main canal and branch

canals in particular); (b) development of improved water management, social capital and

institutional capacity; and (c) the improved quality of soil and agricultural products due

to the adoption of good agricultural production practices (e.g., Integrated Pest

Management).

Financial Analysis

34. Farmers’ income. Financial analysis was conducted to gauge project impact on

farmers’ incomes, and to set the minimum water price charged for reservoir water users

to cover the O&M costs. Crop budget and farm models were formulated under “with”

and “without” project situations to gauge the financial attractiveness to farmers from: (a)

improved crop yields; (b) changed cropping pattern (shifting to higher value crop); and

(c) increase cropping intensities. The results show farmers’ income would increase

substantially (at RMB Y1, 966/household); and therefore the project is financially

attractive to the farmers.

35. Water Charges. This multi-purpose project is classified as both a national and a

provincial “key public sector investment project”, particularly for flooding control and

drinking water supply. Water prices are determined by the planning and finance agencies

of the local government. Water charges for irrigation and rural drinking water supply are

to be set at RMB0.27 Yuan/ m3 to cover only the O&M costs for the main system.

Page 20: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

10

Meanwhile, water charges for township industrial water supply are to be set at RMB0.77

Yuan/m3 to fully cover the cost.

36. Fiscal Impact. Of the total project financing of US$ 700.77 million, US$100

million would be covered by the World Bank Loan, the rest of US$600.77 million would

be covered by counterpart funding. The central government is expected to contribute

some US$285.29 million (RMBY1.940 billion) out of counterpart funding and the

balance of US$315.48 million will be met by the Provincial Government, Mianyang

Municipal Government and related county governments through annual budget

allocations. Beyond the construction period, the fiscal impact of the project will be

minimal as water charges would fully cover the O&M costs of the major infrastructure

(tertiary canals above). The rehabilitation costs of the on-farm works, as well as their

O&M costs, would be borne by the WUAs.

B. Technical

37. Qualified design institutes prepared the feasibility study and preliminary and

detailed designs for the Wudu Second-phase Irrigation Scheme. The design followed

Chinese national technical standards and benefited from the lessons learned from the

Wudu First-phase Irrigation Scheme built in 2002. It also took into account the 2008

earthquake which hit some of the project areas and the design of the scheme structures in

those areas was adjusted to resist an earthquake of magnitude of 7.0 on Richter scale.

During the design several alternatives were examined including several routes for the

Xizi Main Canal, tunnels versus aqueducts, and siphons versus aqueducts.

Environmental concerns and resettlement, as well as cost effectiveness, were considered

during the design in order to arrive at the optimal design. Detailed designs for the main,

sub-main and branch irrigation infrastructures would be prepared as soon as possible after

completing the preliminary design, while the design for the on-farm works would be

completed based on agreements reached between the PMO and the WUAs about the

priority of works to be undertaken. This process would ensure enough consultations and

interactions between the designers, PMO consultants and the WUAs. The works would

be suitably packaged to attract qualified contractors and contract management and

construction supervision would be carried out with the assistance of qualified engineers.

38. Project works are relatively complex, especially the canal systems, since they

involve construction of numerous sluice gates, tunnels, aqueducts and siphons, as these

systems lie in mountainous areas with difficult topographic terrain. However, Sichuan

Province has good experience in such construction and successfully implemented the

IDA funded Wudu First-phase Irrigation Scheme in 2002. In addition, the Wudu

Diversion Management Bureau had primary responsibility for constructing the major

Wudu Dam, which was completed in 2010.

C. Financial Management

39. Bank loan proceeds, including oversight of the Designated Account, will be

managed by Sichuan Provincial Finance Bureau (SPFB). A financial management

Page 21: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

11

capacity assessment has been conducted by the Bank and actions to strengthen financial

management capacity have been agreed with the relevant implementing agencies. The

FM assessment has concluded that with the implementation of these proposed actions, the

financial management arrangements will satisfy the Bank’s minimum requirements under

OP/BP 10.02. Annex 3 provides additional information on financial management.

D. Procurement

40. Procurement under the project would be managed by the Municipal PMO. The

procurement capacity assessment conducted by the Bank confirmed that the Municipal

PMO has adequate procurement experience and has qualified procurement staff.

However, local procurement procedures and practices differ from the Bank’s procedures

and the procurement staff as well as the officials responsible for approving procurement

need to update their knowledge about the Bank procurement procedures.;. Mitigation

measures have been agreed with the Municipal PMO. The procurement plan for both

Bank financed projects and Government funded contracts was finalized at appraisal, and

will be updated at least annually (or as required) to reflect project implementation needs.

See Annex 3 for more details.

E. Social

41. The Project will benefit 1.35 million farmers in the three northern counties of

Jiangyou, Zitong and Yanting in Sichuan Province, which are frequently affected by

drought. The beneficiary farmer communicates will directly participate in sub-project

selection and design, and implement the on-farm work with technical and financial

support from local governments. Women’s membership and participation in governance

of WUAs would be increased. The project will incorporate a CDD approach into WUA

management by integrating village councils’ roles in CDD with WUA functions in local

irrigation management.

42. Negative social impacts of the project are land acquisition and resettlement in the

three rural counties. The Bank supported project includes construction of a part of Xizi

main canal (23.19 km of 108.18 km in total) and 11 branch canals (231.15 km) that will

requisition about 4,245 mu of village land in 136 villages, of which 2,318 mu is

farmland. About 3,848 farmers in 1,063 households will be affected, of whom 990

people in 264 households will lose their houses as well. In addition, the main Wudu

Phase II program will requisition 10,037 mu (669 ha.) of land and remove 185,309 m2 of

structures that will relocate 3,525 people. 4,716 people will require restoration of their

livelihoods.

43. A Resettlement Plan (RP) for the overall Wudu Phase II resettlement has been

prepared. In addition, a RAP has been prepared for the proposed Bank project, which is

in compliance with Bank requirements. This RAP includes a section on resettlement in

the entire Wudu Phase II, as well as a due diligence report on the already completed

Wudu reservoir resettlement. The RAP has been disclosed locally and in the Bank

InfoShop.

Page 22: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

12

F. Environment

44. The Project is classified as a “Category A” project based on the type, location,

sensitivity, and scale, as well as the nature and magnitude of its potential environmental

impacts of the Wudu Second-phase Water Diversion and Xizi Irrigation Scheme and the

Wudu Reservoir. Environment Assessment (EA) reports acceptable to the Bank were

prepared in accordance with national requirements and the Bank’s OP/BP/GP 4.01. The

reports include an: (a) EA summary; (b) EA; and (c) Environmental Management Plan

(EMP). As the project triggers Bank safeguard policies on Natural Habitats, Safety of

Dams, and Pest Management, the reports on dam safety and a Pest Management Plan

(PMP) acceptable to the Bank have been prepared.

45. The EA concluded that the Project will bring significant positive impacts to the

natural and socio-economic environments. The main environmental issues of the project

are the soil erosion caused by construction activities and potential pesticides issues (if not

well managed) during the operational phase. The project has integrated mitigation

measures into the design, construction and operational phases. All Project investments

have been designed to avoid or minimize adverse impacts on the physical environment by

optimizing the canal routes, access roads routes, dam site selection, and spoil disposal

sites selection etc. Preventive and mitigation measures during the construction and the

operation phases have been prepared and are noted in the EMP and PMP. Proper

implementation of these measures can either minimize impacts to an acceptable level or

eliminate them.

46. A two-stage public consultation, including expert consultations, questionnaires,

symposia, and interviews, was conducted with the different stakeholders of the proposed

project. The majority of those consulted expressed strong support for the project, and

accepted short-term inconvenience, such as noise and dust during construction.

Information about the project was disclosed in January and September 2010. The

availability of the EA reports, and how to access to them, was announced in “Mianyang

Daily” on December 2, 2010. The EA, EMP, EA Summary, Dam Safety Report, and

PMP were disclosed at the website of different government agencies. All the

Environmental safeguard documents mentioned above were disclosed at the Bank Beijing

office website and at the Infoshop in Washington, D. C. on December 16, 2010.

47. Safety of Dams. The Project triggers Dam Safety Safeguard Policy (OP 4.37) as

the project sites are downstream of: the existing Heping Dam; the Wudu dam, which is

under construction; and the Jinfeng dam, which is to be constructed. Failure of these

upstream dams could cause extensive damage to or failure of some or all of the

investments under the Project. In addition, reservoirs formed by the Wudu and Jinfeng

dams would provide water to water users in the project area.

48. The government, as the owner of these dams, has: (a) strengthened the existing

Heping dam in 2010 through remedial works; (b) prepared Operation, Maintenance and

Page 23: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

13

Surveillance Plan (OMS) and Emergency Preparedness Plan (EPP) for the Wudu dam;

and (c) prepared draft OMS and EPP outlines for the Jinfeng dam.

49. During project implementation, the Bank, together with the Dam Safety Panel

employed by the PMO, will supervise implementation of the dam design and

construction; and review the safety status, and the O&M of these dams to ensure

compliance with the Bank’s OP 4.37, Safety of Dams.

Page 24: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

14

Annex 1. Results Framework and Monitoring SICHUAN WUDU IRRIGATED AGRICULTURE DEVELOPMENT PROJECT

Results Framework

Project Development Objective (PDO): The Project Development Objectives (PDOs) are to: (a) increase the coverage of irrigation services in the Project Area in order to

increase agricultural production; (b) provide water supply, in bulk, to small rural communities and industries in Mianyang City; and (c) introduce a community-based participatory

approach in the management of water facilities and infrastructure and increase of production capacity of higher-value agro-products in the Project Area to ensure the sustainable

development of agriculture.

PDO Level Results Indicators

Co

re

Unit of

Measure Baseline

Cumulative Target Values Frequency Data Source/

Methodology

Responsibility

for Data

Collection

Description

(indicator

definition etc.)

2012 2013 2014 2015 2016 2017

1. Increased new effective

irrigated area with the project 10,000

Mu 0.00 0.00 0.00 14.95 39.08 78.80 92.96

Once a

year

Design and

actual Data Wudu Bureau

By indepen-

dent consultant

2. Annual value of agricultural

production per mu Yuan/yr 1,450 1,450 1,450 1,650 1,750 1,850 2,060

Once a

year

Data collected

in the field Wudu Bureau

By indepen-

dent consultant

3. Annual amount of industrial

and domestic water supply

10,000

m3/yr 9,525 9,525 11,000 13,000 14,000 15,000 16,066

Once a

year

Design and

actual Data Wudu Bureau

By indepen-

dent consultant

4. Number of farmers (and

female1 farmers) benefiting from

the supplementary irrigation

10,000

Persons 0 0 0 60 80 110 135

Once a

year

Data collected

in the field Wudu Bureau

By WUAs or

villages

5. Number of O&M plans

prepared and implemented for

both main and on-farm systems

Plan 0 0 0 0 10 20 30 Twice a

year

Data collected

in the field Wudu Bureau

By indepen-

dent consultant

INTERMEDIATE RESULTS

Intermediate Result Indicators (Component One): Construction of Main Irrigation Systems

6. Length of Xizi canal completed Km 0.00 0.00 0.00 48.53 77.28 90.50 108.177 Twice a

year

Data collected

on site Wudu Bureau

By supervision

engineer

7. Length of sub-main or branch

canals completed Km 0.00 1.37 3.24 86.14 201.84 345.18 345.18

Twice a

year

Data collected

on site Wudu Bureau

By supervision

engineer

8. Height of the dam crest

completed for Jinfeng Reservoir m 0 0 0 419 440 477 477

Once a

year

Data collected

on site Wudu Bureau

By supervision

engineer

Intermediate Result Indicators (Component Two): Development of CDD-based On-farm Demonstration Areas

9. Length of lateral and sub-

lateral canals completed Km 0.00 0.00 0.00 57.40 144.28 326.57 479.57

Twice a

year

Data collected

on site Wudu Bureau

By supervision

engineer

10. Irrigation water use efficiency

increased in the irrigation area % 35 - - 80 80 80 80

Once a

year

Measured

Data Wudu Bureau

Measured in the

field

11. Annual net income of farmers

increased with water provided by Yuan/yr 2,680 - - 3,000 4,000 5,000 5,200

Once a

year

Data collected

in the field Wudu Bureau

By indepen-

dent consultant

Page 25: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

15

the project in the project areas

12. Agricultural value increased

per unit of water Yuan/m3 6.50 - - 7.00 8.00 9.00 10.70

Once a

year

Data collected

in the field Wudu Bureau

By indepen-

dent consultant

13. Increased number of female

membership for WUAs and

Producer Groups (PGs)

Person 0 35 40 50 60 70 80 Twice a

year

Data surveyed

in the field Wudu Bureau

By indepen-

dent consultant

Intermediate Result (Component Three): Institutional Capacity Building & Project Management

14. Number of PMO staff

familiarized with project concept,

approach and operational

procedures

Person 10 15 20 25 30 35 40 Twice a

year

Data surveyed

in the PMOs Wudu Bureau

By Bank SPN

Mission

15. Number of female project

staff participating in the domestic

and overseas study tours

organized by the project

Person 3 7 17 27 37 47 50 Twice a

year

Data surveyed

in the PMOs Wudu Bureau

By Bank SPN

Mission

1 The number of female farmers will be collected in addition to the total number of farmers.

Page 26: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

16

Annex 2. Detailed Project Description SICHUAN WUDU IRRIGATED AGRICULTURE DEVELOPMENT PROJECT

Project Development Objectives (PDOs)

1. The Project Development Objectives (PDOs) are to: (a) increase the coverage of

irrigation services in the Project Area in order to increase agricultural production; (b)

provide water supply, in bulk, to small rural communities and industries in the project

area; and (c) introduce a community-based participatory approach in the management of

water facilities and infrastructure and increase of production capacity of higher-value

agro-products in the Project Area to ensure the sustainable development of agriculture.

2. The key beneficiaries of the project are about 1.35 million poor farmers (397,000

households) who will be able to receive reliable irrigation water supplies and change

from mainly dry farming to irrigated agriculture and boost their agriculture production.

The other key beneficiaries are about 1.7 million poor people in rural and small urban

communities in addition to the industries in the project area who will be provided by

water supply, in bulk, from the irrigation infrastructure for drinking and industrial

purposes.

Project Components

3. The Project, which constitutes the second phase of the Wudu Scheme in Sichuan

Province, consists of the following parts:

Component 1: Construction of Main Irrigation Systems1 (Total cost US$691.03

million, of which Bank Financing US$97.41 million)

4. Construction and operation of the second phase of the Wudu Scheme to irrigate

about 70,200 hectares of land as well as to supply water to urban and rural areas, and

water to industries in the project area, and consisting of two systems:

(1) Construction of branch canals from the right and left segments of the Wudu

Reservoir to irrigate areas directly under said Reservoir; and

(2) Construction of a new main irrigation system consisting of:

(a) Construction of Xizi Main Canal with a total length of about 108 km to divert

water from the Wudu Reservoir to irrigate areas under said Canal in the

Project Area and consisting of numerous structures including tunnels,

aqueducts, siphons, gates and other structures;

(b) Construction of a reservoir at Jinfeng with intake from the Xizi Canal with a

total storage capacity of 98 million cubic meters consisting of tunnels,

1 The Bank would finance the first section (23 km) of Xizi Main Canal, Jinlong sub-main canal (24 km) and 10

branch canals (228 km). The rest of the main systems will be fully financed by government.

Page 27: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

17

aqueducts, siphons, gates and other structures including an asphalt concrete

core sock-fill dam with a height of 88m and a chest length of 454.87m, an

irrigation intake and a tunnel to supply and regulate the supply of water to the

irrigation system to be constructed; and

(c) Construction of Jinlong sub-main canal and 16 branch canals consisting of

numerous structures including tunnels, aqueducts, siphons, gates and other

structures to divert water to irrigate areas covered under the Xizi Main Canal

to be constructed.

5. Component 1 would comprise the construction of a new irrigation system to

irrigate about 70,200 ha and supply drinking water in bulk to rural and small urban

communities as well as for the industries in Mianyang City. The system will include

construction of Xizi Main Canal, Jinlong sub-main canal and 16 branch canals. The main

irrigation works of the second-phase irrigation scheme to be financed by the Bank are

shown in Table 1 to this Annex, and the works to be fully financed by government are

shown in Table 2 attached to this Annex.

6. Construction of Xizi Main Canal. The total length of the canal is 108 km. The

open section of the canal will be lined with 10 cm of concrete and there will be numerous

structures as a part of the canal including 61 tunnels with a total length of 53.7 km, 17

aqueducts with a total length of 5 km, 3 siphons with a total length of 2.8 km, 62 gates

and 208 other structures. The flow capacity of the canal would be 28.50 m3

/s at the start

of the canal and 12.50 m3

/s at the end of the canal. The Bank will finance the first

section of the canal with a length of 23 km including 9 tunnels with a total length of 6.04

km, 2 aqueducts with a total length of 1.43 km, 1 siphon with a total length of 1.17 km,

10 gates, and 64 other structures.

7. Construction of Jinlong Sub-Main Canal. The 24.24 km sub-main canal will be

financed by the Bank and includes construction of 22 tunnels with a total length of 8.74

km, 7 aqueducts with a total length of 1.1 km, 3 buried culverts with a total length of 0.54

km, 42 gates and 141 other structures.

8. Construction of 16 branch canals. The total length of the branch canals is 325

km. It would include construction of 159 tunnels with a total length of 72.42 km, 46

aqueducts with a total length of 10.50 km, 18 siphons with a total length of 9.71 km, 34

buried culverts with a total length of 3.87 km, 497 gates and 1740 other structures. The

Bank will finance construction of 10 branch canals with a total length of 228.08 km

including 111 tunnels with a total length of 50.5 km, 37 aqueducts with a total length of

6.06 km, 14 siphons with a total length of 6.26 km, 28 buried culverts with a total length

of 2.91 km, 354 gates and 1,220 other structures.

Component 2: Development of CDD-based On-farm Works in Demonstration Areas

(Total cost US$4.49 million, of which Bank Financing US$0.90 million)

9. Carrying out of on-farm development works under community demand driven

approach in selected demonstration areas in the counties of Jiangyou, Zitong and Yanting

Page 28: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

18

of Mianyang City covering about 766 hectares within the irrigated area covered by the

second phase of the Wudu Water Diversion and Irrigation Scheme, comprising:

(1) Construction of on-farm works including 1 lateral canal and 3 sub-lateral canals

with a total length of about 48 km;

(2) Establishment and development of Water Users’ Associations (WUAs) and

enhancement of Producer Co-operatives based on community demand driven

approach around a lateral canal area or sub-lateral areas in each demonstration

area to organize and implement the construction, operation and maintenance of

on-farm works; and

(3) Provision of an integrated package of agricultural inputs and supporting services

in each demonstration area to small holder agricultural producers and farmer

groups to maximize the benefit of irrigated water delivered to the field and help

increase farmer’s production and income.

10. WUA will be organized at the lateral level or sub-lateral level, consisting of

WUGs (Water User Groups) organized in the villages involved. It will organize and

implement the construction of the lateral, sub-lateral canals and farm ditches, including

“Community Participatory Procurement”, coordination of labor inputs, allocation of

water use, tasks of O&M and water fee collection, as well as interaction with water

supply institutes, e.g. in measuring water volume. WUGs will be the main bodies to

implement those tasks.

11. In addition to the annual agricultural inputs from government, Component 2

would include: (a) agro-water services and guidance provided by the expert group

established at the municipal level; (b) agro-water services and advice provided by the

expert groups established at the county level; (c) financial aid provided by farmers self-

help PGs (Producer Groups) to the pilot households for agricultural inputs and to the

poverty-stricken households that voluntarily participate in the project extension; (d)

financial aid needed for providing farmers with co-operative training and training

manuals; (e) financial aid needed for operation and maintenance of the CDD service

platform (webpage) added to the agro-information internet system; and (f) rewards for

grass-root level farmer/co-operative leaders who have made outstanding contributions to

developing CDD and helping increase farmers’ production and incomes.

Component 3: Institutional Capacity Building and Project Management Support

(Total cost US$1.44 million with Bank financing 100%)

12. Provision of technical assistance for the institutional strengthening of the Project

Counties and Sichuan to implement the Project including:

(1) Capacity building through, inter alia, study tours and training;

(2) Consulting services and office equipment; and

Page 29: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

19

(3) Acquisition of vehicles to provide necessary technical support for implementing

the activities under component 1 and 2 of the Project.

13. Component 3 would comprise support for project management including

provision of office equipment and vehicles for project supervision and quality control;

consulting services (through expert groups at the municipal and county levels) to support

the PMOs for project management and implementation; establishment of monitoring and

evaluation (M&E); Procurement and Financial Management Information System

(PROMIS); and overseas or domestic workshops, training and study tours to ensure that

the project implementation follows the international practices.

Construction of On-farm Works

14. The governments and beneficiaries would provide, through their internal

investment programs outside the project, additional financing for construction of on-farm

irrigation systems (laterals and sub-laterals and farm ditches) to fully cover the project

area after the main systems are completed under the project. As listed in Table 3, there

will be altogether 42 lateral canals to be constructed after the main systems are

completed, which include 10 lateral canals for Jiangyou County; 5 for Zitong County; 16

for Yanting County; 5 for Shehong County; 3 for Jiange County; and 3 for Nanbu

County.

15. The related county governments and project beneficiaries would also provide

additional funds (outside the project) to construct or rehabilitate farm ditches, and

establish the CDD-based WUAs to be responsible for O&M of the completed on-farm

irrigation systems; and finance agricultural inputs and supporting services to maximize

the benefit of the water delivered to the field, learning from the experience and lessons

from the three demonstration areas supported under the project.

Construction Programming

16. The schedule was developed for construction of civil works with Microsoft

Project, which was optimized to deliver water to the field to benefit farmers as early as

possible and successively section by section from upstream to downstream of the Xizi

Main Canal. Factors that were considered for construction programming include:

a) Technical capacity of local and domestic construction enterprises;

b) Availability of annual counterpart funding from all levels of governments;

c) Construction schedule for main irrigation canal systems;

d) Construction schedule for on-farm irrigation systems;

e) Project procurement schedule; and

f) Local weather conditions

17. Construction Schedule for Works to be financed by the World Bank Loan.

Milestones for construction of the works financed by the World Bank loan are shown in

Page 30: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

20

Table 4 below, while a more detailed schedule for the whole project is attached to the

Project Implementation Plan (PIP).

18. Estimated Investment for Civil Works. The total estimated investment for civil

works is US$315 million (RMB2.14 billion). The investment peak will come in 2015

when the annual investment is estimated at about US$80 million (RMB541 million),

which would require sufficient annual counterpart funding to be planned and prepared in

advance.

19. Construction Summary. The construction process would need 88 months from

October 2010 to December 2017 including some temporary engineering works to be fully

financed by the government (access and transportation roads, a diversion tunnel, and

works for power, water supply, and communication lines, etc.). Construction of civil

works financed by the World Bank would span over 76 months from October 2011 to

December 2017.

20. Critical Paths of Construction. The critical paths for construction of the project

are determined by the following three milestones: (a) November 2013 - when water

supply is expected to cover the Huanlian Sub-lateral in the CDD-based WUA

Demonstration Area in Jiangyou County; (b) March 2017 - when sections 1-6 of Xizi

Main Canal are completed, and water supply is expected to cover irrigated areas under

sections 1-6; and (c) December 2017 - when Jinfeng reservoir and sections 7-9 of Xizi

Main Canal below the reservoir are fully completed, and water supply is expected to

cover all irrigation areas under sections 7-9.

Page 31: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

21

Page 32: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

22

Page 33: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

23

Page 34: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

24

Annex 3. Implementation Arrangements SICHUAN WUDU IRRIGATED AGRICULTURE DEVELOPMENT PROJECT

A. Project Administration Mechanisms

1. Organizations for project management and implementation have been established

in Mianyang City and its three counties (Jiangyou, Zitong and Yanting). Responsibilities

for project management and implementation are summarized below and the

organizational chart for project management and implementation is shown at the end of

this Annex.

2. Provincial Level. The Provincial Project Leading Group chaired by the Director

General or the Deputy Director General of the Sichuan Provincial Finance Department,

or his/her delegate, comprising all relevant agencies at the Provincial level and

responsible for liaising with central government agencies concerning the Project and

providing overall policy guidance.

3. Municipal Level. The Municipal Project Leading Group at the municipal level in

Mianyang City of Sichuan chaired by the Vice Mayor of Mianyang City and consisting of

members from the Municipal Finance Bureau and all other relevant agencies of the City

and responsible for overseeing the overall implementation of the Project, making decision

on key Project issues and carrying out interagency coordination at the municipal level as

well as coordination with the Provincial Project Leading Group referred to in paragraph 2

above. The Municipal Project Management Office located within the Sichuan Wudu

Water Diversion Management Bureau (the Bureau) and responsible for Project

management and implementation at the municipal level as well as reporting on progress

and implementation issues to the Bureau and the Municipal Project Leading Group.

4. In addition, an Expert Group (EG), and a Dam Safety Panel (DSP) have been

established at the municipal level. The EG would provide technical support to the

Municipal PMO. The DSP will assist in ensuring that the project is implemented in

compliance with the Bank’s policy on Safety of Dams (OP 4.37) under terms of reference

acceptable to the Bank. The EG will provide guidance to the county PMOs to carry out

its responsibilities.

5. County Level. A County Project Leading Group in each of the Project Counties

responsible for Project implementation, coordination and decision making at the county

level. A County Project Management Office in each of the Project Counties located

within the respective county level bureau of the Wudu Scheme and responsible for

Project management and implementation at the respective county level as well as

reporting on progress and implementation issues to the respective County Project

Leading Group.

Page 35: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

25

6. In addition, an expert group for agro-water inputs and services would be

established at the county level to provide technical guidance to development and

implementation of CDD-based WUA Demonstration Program.

B. Financial Management

7. The FM capacity assessment identified the following principal risks: (a) not all

project financial staff has experience with Bank financed projects; (b) the CDD approach

to be used in some of the activities implemented by WUAs may bring additional risk

during project implementation; and (c) lack of timely and sufficient counterpart funds.

8. Mitigation measures agreed include: (a) an FM training plan to be prepared and

all project financial staff to be trained before and during project implementation; (b) an

FMM will be issued to standardize project FM procedures and provide guidance to

project financial staff; and (c) counterpart funds should be confirmed in the government’s

annual budget. The FM risk pre-mitigation has been assessed as “Substantial” and post-

mitigation has been assessed as “Moderate”. The FMM was finalized prior to loan

negotiations.

9. Budgeting. Each county PMO will be responsible for preparing county annual

investment plan in a standardized format to facilitate the preparation, consolidation and

monitoring of the annual plan in an effective and efficient manner. Each county PMO

will conduct a semi-annual variance analysis. Counterpart funds availability will be

reflected in the budget report.

10. Funds flow. Bank loan proceeds will flow from the Bank into the project

designated account (DA) to be set up at and managed by SPFB. SPFB will be directly

responsible for the management, maintenance and reconciliation of DA activities.

Supporting documents required for Bank disbursements will be prepared and submitted

by the respective county PMOs through MPMO and MFB for verification and

consolidation before sending to SPFB for further disbursement processing.

11. Accounting and financial reporting. The administration, accounting and

reporting of the project will be set up in accordance with Circular No.13: “Accounting

Regulations for World Bank Financed Projects” issued in January 2000 by MOF. The

standard set of project financial statements has been agreed between the Bank and MOF.

12. Each county PMO will manage, monitor and maintain project accounting records

for the county. Original supporting documents will be retained by the originating PMOs.

County PMOs, who are the lowest level for maintaining project accounts, will prepare

their own financial statements, which will then be reviewed and consolidated by MPMO

with SPFB’s assistance, before submission to the Bank for review and comment on a

regular basis. The unaudited semi-annual consolidated project financial statements will

be prepared and furnished to the Bank by MPMO as part of the Progress Report no later

than 45 days following each semester (the due dates will be August 15 and February 15).

Page 36: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

26

13. The project will utilize an integrated computerized project software package. The

task team will monitor the accounting process, especially during the initial stage, to

ensure that complete and accurate financial information will be provided in a timely

manner.

14. Internal control. The related accounting policy, procedures and regulations were

issued by MOF and an FMM has been issued to align the financial management and

disbursement requirements among PMOs.

15. Auditing. Sichuan Provincial Audit Office (SAO) has been identified as the

auditor for the project. Annual audit reports will be issued by SAO and will be due to the

Bank within 6 months after the end of each calendar year.

C. Disbursements

16. Three disbursement methods are available for the project: advance,

reimbursement and direct payment. Supporting documents required for Bank

disbursement under different disbursement methods will be documented in the

Disbursement Letter issued by the Bank.

17. One designated account (DA) in US dollar will be opened at commercial banks

acceptable to the Bank and will be managed by SPFB. The ceiling of the DA will be

determined and documented in the Disbursement Letter. The Bank loan would be

disbursed against eligible expenditures (taxes inclusive) as in the following table:

Category IBRD Financing (in US$ Million)

Amount1 of the Loan

Allocated

Percentage of Expenditures

to be financed

A. Works 98.16 -

(a) Xizi Canal- 1st Section & Branch

Canal (11 branch canals ) 97.41 84%

(b) Works for On-farm Works (1 lateral

canal and 3 sub-lateral canals) 0.75 20%

B. Goods/Equipment 0.27 100%

C. Consultancy 0.51 100%

D. Training and Workshop 0.71 100%

E. WUA Establishment Cost 0.10 100%

F. Front-end Fee 0.25 100%

Total 100.00 -

18. Retroactive financing will be applied for this project. The date of eligible

expenditures and the amount for the retroactive financing are specified in the loan

agreement.

19. On-farm Works. The construction of three sub-lateral canals will be executed by

WUAs in line with the procedures outlined in the project legal agreements, under the

technical guidance of County PMOs. County PMOs will make payments for

expenditures incurred on eligible activities as indicated in the project legal agreements.

Page 37: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

27

20. WUA Establishment Cost. Withdrawals for WUA establishment cost shall be

made: (a) only after municipal PMO has conducted inspection and issued acceptance

report for each established WUA in accordance with WUA manual; (b) based on actual

expenditures incurred for each WUA, and (c) the limit of payment for each WUA shall be

pre-agreed by the Bank.

D. Procurement

21. The procurement capacity assessment identified the principal risk as procurement

staff in the PPMO not having direct experience with Bank financed projects. Mitigation

measures include: (a) procurement training provided during project preparation, and

further training for procurement staff during project implementation; (b) a procurement

manual (PM) has been included in PIP and issued to standardize project procurement

procedures and provide guidance to project procurement staff; and (c) a procurement

agent with experience in World Bank procurement would be hired by PPMO to assist

with procurement activities. The overall risk for procurement is considered “Moderate”.

22. Procurement will be carried out by the Municipal PMO, except for community

participatory procurement, which would be carried out by the WUAs. Procurement for

the proposed project would be carried out in accordance with the World Bank’s

“Guidelines: Procurement under IBRD Loans and IDA Credits” dated May 2004 revised

in October 2006, and May 2010; and “Guidelines: Selection and Employment of

Consultants by World Bank Borrowers” dated May 2004 revised in October 2006, and

May 2010.

23. Procurement of Works. Works would include Xizi main canal, Jinlong sub-

main canal, branch canals as well as the on-farm works, including one lateral, three sub-

laterals in three demonstration areas located in the three project counties. Procurement

will be carried out using the Bank’s Standard Bidding Documents (SBD) for ICB and

Model Bidding Documents (MBD) for NCB, agreed with the Bank.

24. Procedures for Community Participation in Procurement. Construction of on-

farm works, including laterals, sub-laterals and farm ditches, office equipment and

furniture, agricultural inputs (chemicals, seedlings, young animals), facilities (animal

sheds), small equipment (for production purpose) required under Component 2:

Development of CDD-based On-farm Demonstration Areas, would be procured with

community participation. WUAs would carry out the procurement under the following

procedures, which are elaborated in WUA Manual:

(a) Local Shopping for Procurement of Works. Quotations would be obtained through

the invitation of at least three qualified contractors to submit quotations on the

basis of simplified quotation requests. Quotations should be opened at the same

time and to the extent possible in the presence of community. As a general rule,

the contractor who offers the lowest price and meets the technical requirements

Page 38: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

28

should be awarded the contract. The threshold for local shopping for civil works

is below US$100,000 per contract.

(b) Local Shopping for Procurement of Goods. Quotations would be solicited from at

least three qualified suppliers on the basis of simplified documents specifying the

goods to be procured. Quotations should be opened by the WUAs at the same

time. As a general rule, the responsive supplier who offers the lowest price

should be awarded the contract. The threshold for local shopping for goods is

below the equivalent of US$100,000 per contract.

(c) Community Force Account. Communities will mobilize their own labor and

equipment to carry out the works. Works to be constructed under force account

should have a detailed description of the works, a set of technical specifications,

and a supervision team to check quality and quantities. Payment would be made

based on pre-estimated unit costs for works against completed works, as certified

by communities.

25. Procurement of Goods. Goods would include office equipment, water measure

equipment and working vehicle. Procurement will be carried out using Bank SBD for all

ICB and Chinese Model Bidding Documents (MBD) for NCB, agreed with the Bank.

26. Selection of Consultants. Consulting services would include panel of experts,

project monitoring and evaluation, and management information system (MIS).

27. Establishment of Water User Association (WUA). A total of about

US$100,000 of Sub-grant would be provided to communities for establishing WUAs.

Withdrawals for WUA establishment cost shall be made: (a) only after municipal PMO

have both conducted inspection and issued acceptance report for each established WUA

in accordance with WUA manual; (b) based on actual expenditures incurred for each

WUA, and (c) the limit of payment for each WUA shall be pre-agreed by the Bank.

28. Training and Workshops. Detailed programs will be developed by Municipal

PMO and included in project annual work plan for Bank’s review. Expenditures incurred

in accordance with the approved detailed programs will be used as the basis for

reimbursement.

29. Procurement Plan. The Borrower has developed an overall procurement plan

and a procurement plan for retroactive financing for project implementation, which

provides the basis for procurement methods. The Plan has been reviewed and agreed at

appraisal. Contracts for retroactive financing are listed below and in the Procurement

Plan for Retroactive Financing. The procurement plan would be available in the Project’s

database and in the Bank’s external website. The Procurement Plan will be updated in

agreement with the Bank annually or as required to reflect project implementation needs

and improvements in institutional capacity.

30. Frequency of Procurement Supervision. In addition to the prior review to be

carried out by the Bank, the capacity assessment of the Implementing Agency has

recommended one procurement mission every twelve months to carry out procurement

Page 39: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

29

supervision and post review of procurement actions. The sampling ratio for procurement

post reviews will be at least 1 in 10 contracts.

31. Prior-Review Thresholds. Prior-review thresholds are indicated in the table

below.

Procurement Thresholds

Note: (a) “--“refers to no threshold; and (b) there are no contracts subject to international competition over

the first 18 months.

32. Retroactive Financing. Tables below list the civil works and consulting contracts

which are subject to retroactive financing.

Ref. No.

Description Procurement

Method

Domestic

Preference

(Yes/No)

Review

by Bank

(Prior / Post)

WYEQ-SG-XZ-01 Xizi Main Canal Section 1 Lot 1 NCB No Prior

WYEQ-SG-XZ-02 Xizi Main Canal Section 1 Lot 2 NCB No Prior

WYEQ-SG-XZ-03 Xizi Main Canal Section 1 Lot 3 NCB No Prior

WYEQ-SG-XZ-04 Xizi Main Canal Section 1 Lot 4 NCB No Prior

Ref. No. Description of Assignment Selection

Method

Review by Bank

(Prior / Post)

WYEQ-ZX-01 Management Information System CQS prior

WYEQ-ZX-02 Project Monitoring and Evaluation

including Baseline Survey CQS Prior

Prior Review

Thresholds

(US$

million)

Procurement/Selection Method Thresholds (US$ million)

ICB NCB Shopping QCBS QBS CQS

Least

Cost SSS

Goods 0.5 ≥1.0 <1.0 <0.1 Works, including

Supply and

Installation

5.0 ≥20 <20 <0.2

Community

Participation

WUA Pilot on-farm

works and goods

None None None

Local

Shopping

<0.1

Consulting Services 0.2 for firm

0.05 for

individuals

SSS: all

-- -- <0.2 -- --

Page 40: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

30

Governance and Anti-Corruption

33. The Project shall be carried out in accordance with the provisions of the Bank

Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by

IBRD Loans and IDA Credits and Grants, dated October 15, 2006 and revised in January

2011. Many projects face risks connected with procurement and financial management

due to capacity constraints within the institutions. Some of the problems include

information that is incorrectly entered into the system, delayed financial accounting and

payment to contractors, lack of counterpart funds, misuse of project funds, or other types

of fraud. To provide internal controls (to fight corruption) and reduce risks for this

project, a financial and procurement management system (PROMIS) will be used to

monitor the procurement process and financial transactions, and to cross-check data for

errors and alert authorities in a timely way when errors are detected.

Environmental and Social (including safeguards)

Environment

34. The Project is classified as a “Category A” project. Environment Assessment

(EA) reports were prepared in accordance with national requirements and the Bank’s

OP/BP/GP 4.01. The EA covered not only the Bank-financed project, but also

Government financed activities under the entire Wudu Second-phase Water Diversion

and Xizi Irrigation Scheme, including a due diligence review for the Wudu reservoir

project. The reports include: (a) an EA summary; (b) an EA; and (c) an Environmental

Management Plan (EMP). In addition to the OP4.01, the following environmental

safeguards policies are triggered: Natural Habitats, Safety of Dams, and Pest

Management. Dam safety reports and the Pest Management Plan (PMP) acceptable to the

Bank have been prepared.

35. The EA identified and assessed the Project benefits and impacts to the natural and

social environment, and concluded that the Project will bring significant positive impacts:

provide reliable, equitable and stable water supply to the irrigation areas of 1.053 million

mu (70,235.1hectares); increase agricultural yield; improve the livelihood of the farmers

in the irrigated areas; and promote benign circulation and sustainable development for the

regional economic, social and ecological environment. Negative impacts may arise

during project implementation, including limited negative impacts on soil, air, water,

acoustic environments, and solid wastes, mainly during construction. All Project

investments have been designed to avoid or minimize any adverse impacts to acceptable

levels. Preventive measures during the design, construction and operation phases were

prepared to minimize or even eliminate the negative impacts, and are noted in the EMP.

The main environmental issues of the project are the soil erosion caused by construction

activities and potential pesticides issues (if not well managed) during the operational

phase.

Page 41: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

31

36. Mitigation Measures. To enhance the environmental benefits of the project, the

project has integrated the mitigation measures into the project design, construction phase

and operational phase respectively.

37. During the design phase, the EA teams worked closely with project planners/

owners and the feasibility study teams to compare and evaluate alternatives. The EA

identified, evaluated and compared various options for dam sites, and optimal alternatives

were selected based on the avoidance of (or least adverse) social and environmental

impacts, as well as other economic, technical, and financial considerations for least cost

solutions. A “no project” scenario was also considered as an alternative. In addition, in-

depth alternative analysis was conducted for canal routes, access roads, and other

construction arrangements. As the result, the routes of the canals, access roads and other

construction arrangements were optimized by significantly shortening the length,

reducing the areas to be excavated and spoils to be disposed, reducing land acquisition,

decreasing the number of resettlement people, and with less cost.

38. An EMP was developed as a separate and stand-alone document. It includes

policy bases, applicable environmental standards, environmental management system,

mitigation measures, monitoring plans, institutional arrangements, capacity building, and

estimated costs for the mitigation measures, and monitoring programs during the

construction and operation phases. An EMP summary table, Environmental Monitoring

Plan, including the monitoring for water and soil conservation work, was also prepared

for both the Bank financed project and for Government financed investments outside the

project. Environmental monitoring reports will provide key and timely information,

especially on environmental impacts and mitigation, to the Borrower and to the Bank, to

evaluate the success of environmental management. Generic measures for environmental

management of construction were also designed as technical specifications to be included

in contracts. To compensate the loss of fishery resource of Fujiang River due to the

construction of the associated Wudu dam, appropriate mitigation measures were also

incorporated into the EMP, including ecological flow, monitoring of native fish species,

and implementation of fishery development plan during the operation phase of the Wudu

dam.

39. Public Consultation and Information Disclosure. A two-stage public

consultation, including expert consultations, questionnaires, symposia, and interviews,

was conducted with the different stakeholders. The majority of those consulted expressed

strong support for the project, and accepted short-term inconveniences, such as noise and

dust during the construction phase. Information about the project was disclosed in

January 2010 and September 2010. The availability of the EA reports, and how to access

to them, was announced in “Mianyang Daily” on December 2, 2010. The EA, EMP, EA

Summary, Dam Safety Report, and PMP were disclosed at the website of different

government agencies. All Environmental safeguard documents mentioned above were

disclosed at the Bank Beijing office website and at the Infoshop in Washington, D. C. on

December 16, 2010.

Page 42: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

32

40. Pest Management (OP4.09). The project will improve on-going integrated pest

management in Mianyang Municipality. Specifically, it will: (a) disseminate the

application of high efficiency, low toxic, low residual effect chemicals and biological

pesticides; (b) prohibit the use of high toxic, high residual effect pesticides; (c) reduce

reliance on chemical pesticides and chemical fertilizers; and (d) promote the use of non-

chemical technologies for insect and pest control. A Pest Management Plan (PMP) was

prepared for the project.

41. The PMP covers preface, major pest issues, present pesticides management

methods, pesticides management organizations and their respective responsibilities in

Mianyang Municipality, environmental, occupational and safety risk assessment,

monitoring, evaluation activities, and capacity building etc.

42. Appropriate grievance handling procedures and arrangements for monitoring

EMP, Dam safety, and PMP implementation are in place. With the mitigation measures

in design, construction and operation phase including grievance handling mechanisms

and M&E arrangements implemented mentioned above, the Bank Safeguards

requirements will be met in full.

Involuntary Resettlement (OP4.12)

43. The Bank Project would entail land acquisition and house demolition in three

counties in Mianyang Municipality, northern Sichuan Province. 136 villages in 38

townships will be impacted, of which 4,245 mu of land (in which 2,138 mu are farmland)

would be permanently requisitioned and 3,257 mu of land will be temporarily occupied.

A total of 3848 farmers in 1,063 households would be affected by the land acquisition, of

which 990 people in 264 households have to relocate due to house demolition.

44. The Bank supported project of canal construction is a small part of the Wudu

Water Diversion Project Phase II. The overall Wudu Phase II includes construction of

Jinfeng reservoir (capacity of 98 million m3.), Xizi main canal (108 km long) and 17

branch canals that are mostly domestically financed. Beside the Bank supported part, the

Wudu Phase II domestic part would requisition 10,037 mu (669 ha.) of land and remove

185,309 m2 of structures that would relocate 3,523 people. As affected by land loss, a

total of 4,716 people have to be resettled in new production arrangement entirely. In

2008, a census, socio-economic surveys, and impact investigations were carried out, In

2010, a Resettlement Plan (RP) for the overall Wudu Phase II resettlement was approved

by Sichuan Provincial Resettlement Bureau and Ministry of Water Resources.

Resettlement for the Wudu reservoir commenced in 2001 and was completed in 2010.

According to the relevant national policy and the Resettlement Plan for this reservoir

construction, the reservoir resettlement post-support subsidies were already allocated to

each of the affected persons (RMB600/person) annually, in addition to other

compensation provided before their physical relocation.

45. The RAP for the proposed Bank financed project was prepared after further

rounds of sample surveys and consultations among the villages and households to be

Page 43: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

33

affected. It includes a detailed impact inventory and socio-economic analysis, sets forth a

series of measures to mitigate and compensate the impacts as well as to rehabilitate

people’s livelihoods. RAP implementation is budgeted at RMB236.84 million. It

includes a special grievance redressing mechanism and a resettlement M&E system,

which have been established. The RAP is in conformity with OP4.12. The RAP was

disclosed at the county PMOs and the county libraries, as well as in the Bank InfoShop

before the project appraisal.

46. The RAP for the Bank project contains a section for the domestic part in the

Wudu Phase II resettlement, and includes all necessary mitigation and compensation

elements in compliance with the national laws and regulations, as well as Bank

requirements. This section evaluates the Wudu Phase II RP as having the same level of

detail as the Bank-supported project RAP, in terms of impact surveys, compensation

measures and rehabilitation approaches, based on a broad consultation with the project

affected people. This section also include a due diligence report of the Wudu Reservoir

resettlement which was completed in the end of 2010, because the Wudu Reservoir is

viewed as a linked project.

47. Internal and external monitoring and evaluation mechanisms have been

established. During implementation, progress status, outstanding issues and proposed

actions in relation to the project RAP would all be closely overseen and included in the

semi-annual monitoring reports.

48. Safety of Dams (OP4.37). The Project triggers Dam Safety Safeguard Policy

(OP 4.37) because the project sites are located downstream of: the existing Heping dam ;

the Wudu dam, which is under construction; and the Jinfeng dam, which is to be

constructed. Failure of these upstream dams could cause extensive damage to or failure

of some or all the investment under the Project; furthermore, reservoirs formed by the

dams Wudu and Jinfeng would provide water to the water users in the project area. See

Table 4 at the end of this annex for details on these dams.

49. The PMO has established a Dam Safety Panel (DSP) consisting of three

independent dam safety experts. The DSP would assist the PMO and the Bank to ensure

that the project is being implemented in compliance with the Bank's policy on safety of

dams. The DSP will: (a) inspect and evaluate the safety status of the existing Heping

dam, its appurtenance, and performance history, and review and evaluate the dam

operation and maintenance procedures; (b) provide written reports of findings and

recommendations for any remedial work or safety-related measures necessary to upgrade

the Heping dam to an acceptable standard of safety; and (c) review and evaluate the

design or ongoing construction of the Jinfeng and Wudu dams, and continue to review

and evaluate the safety status of the dams after they are completed.

50. The government, as the owner of these dams, has: (a) strengthened the existing

Heping dam with the remedial works by the end of 2010; (b) prepared Operation,

Maintenance and Surveillance Plan (OMS) and Emergency Preparedness Plan (EPP) for

the Wudu dam: and (c) prepared draft OMS and EPP outlines for the Jinfeng dam. All

Page 44: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

34

three dams were (or will be) fully financed by the government. The operators of these

dams are (or will be) state-owned institutions or bureaus.

51. The guidelines and regulations on dam safety management issued by the

government include: (a) dam safety management regulations; (b) regulations on dam

safety review; (c) guidelines on dam safety review; (d) guidelines for emergency

preparedness plan; and (e) guidelines for operation, maintenance and surveillance of

dams. During project implementation, the Bank will, together with the Dam Safety Panel

employed by the PMO, supervise the implementation of the dam design and construction;

and review the safety status, and operation and maintenance of these dams to ensure that

the Project complies with Bank OP 4.37, Safety of Dams.

Monitoring & Evaluation

52. The Municipal PMO, through its entrusted external institute, will be responsible

for designing and putting in place a suitable M&E system, satisfactory to the Bank, with

a focus on measuring project outcomes and impact. An independent institute will be

contracted to prepare the general design of the M&E system supported by the Municipal

PMO, and carry out project-wide data collection and processing according to the design

supported by the county PMOs during project implementation. The institute will also

consolidate data collected and prepare periodic M&E reports as required. The M&E

design and work program are included in the Project Implementation Plan (PIP). The

complete set of PDO level result indicators (5) and intermediate result indicators (10) are

included in Annex 1.

53. The Municipal PMO will set up a computer-based Procurement and Financial

Management Information System (PROMIS) to monitor the procurement process and

financial transactions, and will alert authorities when errors are detected. The MIS will

provide consolidated data for intermediate result indicators No. 6, 7, 8 and 9.

54. M&E reports will be submitted to the Bank annually. A mid-term review (MTR)

report of the project will be provided to the Bank before December 31, 2015, and an

implementation completion report (ICR) with 6 month after project completion in

December 31, 2017.

Page 45: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

35

List of Dams Triggering the Bank’s Safeguard Policy on Safety of Dams (OP4.37)

Serial

No.

Name

of Dam

Loca-

tion

Year of

Completion

Maximum

Height of

Dam

(m)

Types of Dams

Capacity

of

Reservoir

(million

m3)

Latest

Safety

Review

Dam

Safety

Class

Remedial

works

Next Step

Activities

Dam

Operator

Dam

Owner

1 Wudu Mian-

yang 2011 119.14 RCC 572 NA NA

New dam

under

construction

Construction

and acceptance

Wudu

Reservoir

Management

Division

Mianyang

Wudu Water

and Hydro-

power Group

Company Ltd.

2 Heping Zitong

County 1971 15

Homogeneous

earth 4.18 2008 III

Completed at

the end of

2010

Official

acceptance of

the remedial

works

Heping

Reservoir

Management

Station

Zitong County

Water

Resources

Bureau

3 Jinfeng Mian-

yang New dam 88

Asphalt

concrete core

rock-fill dam

98 NA NA NA

Prepare

Preliminary

Design Report

TBD

Mianyang

Wudu Water

and Hydro-

power Group

Company Ltd.

Page 46: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

36

Page 47: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

37

Annex 4. Operational Risk Assessment Framework (ORAF) SICHUAN WUDU IRRIGATED AGRICULTURE DEVELOPMENT PROJECT

Project Development Objective(s)

The Project Development Objectives (PDOs) are: The Project Development Objectives (PDOs) are to: (a) increase the coverage of irrigation services in the

Project Area in order to increase agricultural production; (b) provide water supply, in bulk, to small rural communities and industries in the project area;

and (c) introduce a community-based participatory approach in the management of water facilities and infrastructure and increase of production capacity of

higher-value agro-products in the Project Area to ensure the sustainable development of agriculture.

PDO Level Results Indicators:

1. Expanded new irrigated areas;

2. Increased annual agricultural production or value; 3. Increased annual amount of water supply for drinking and industrial purposes; 4. Number of farmers (and female farmers) benefiting from the supplementary irrigation; and 5. Number of O&M plans prepared and implemented for both main irrigation systems and on-farm works.

Risk Category Risk Rating Risk Description Proposed Mitigation Measures

Project Stakeholder Risks

Low Impact / Low Likelihood

All stakeholders have a strong interest in the development of irrigated agriculture in the project area.

Implementing Agency Risks

High Likelihood/Low Impact

PMO lacks experience and knowledge of Bank requirements on procurement and financial management and safeguards policies.

Taining on Bank procedures and safeguards will be provided to the PMO staff at both city and county levels during project implementation.

Project Risks

Design

High Likelihood/Low Impact

The technical design has been prepared by a competent provincial design institute, and the design is straightforward.

Plans for the construction of the on-farm system have been agreed, as also the technical alternatives to be considered to enable timely

Page 48: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

38

Risk Category Risk Rating Risk Description Proposed Mitigation Measures

The project includes CDD based WUA activities, which are relatively new to the project counties.

design, construction and financing.

Experienced CDD-based WUA experts provided intensive training, and will provide guidance during the project implementation and O&M stages.

Social and Environmental

Low

Likelihood/High Impact

Weak capacity of the PMOs to implement the agreed safeguards policy instruments (EIA/EMP, PMP, RAP, OMS, EPP, etc).

The Bank team will provide capacity building support by way of training for PMO staff in charge of environment, social/resettlement, and dam safety at municipal and county levels. The Bank team will monitor safeguards implementation regularly, including the measures on dam safety.

Program and Donor N/A N/A N/A

Delivery Quality

Low Likelihood/High Impact

Significant additional funding requirements for construction of on-farm works. Funding requirements for the O&M of the main system. Construction of complex facilities, with proper synchronization of construction activities Budget requirements for the O&M of the on-farm systems.

.

The prioritization of funding support for the

construction of on-farm system that corresponds to

the construction of the main, sub-main and branch

canal system has been agreed. Fundingarrangements

for O&M of the main system have been confirmed. MIS will be designed and set up to closely monitor contract management and operational zing of M&E system. A comprehensive

construction programming plan is in place. PMO

staff will be provided necessary training on

construction management, including on the use of

the computer software for construction management.

WUAs will implement the cost recovery system for on-farm O&M.

Page 49: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

39

Overall Risk Rating at

Preparation Overall Risk Rating During

Implementation Comments

Medium - Likelihood

Medium - Impact

The main risk is the capacity constraint of project entities, lack of financing, and coordination of construction of the on-farm irrigation systems to ensure that water can be delivered to the fields once the main irrigation systems are completed. These risks will be mitigated through institutional capacity building, careful project design, and implementation support from the Bank.

Note: Medium – Likelihood – High Likelihood/Low Impact Medium – Impact – Low Likelihood/High Impact

Page 50: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

40

Annex 5. Implementation Support Plan SICHUAN WUDU IRRIGATED AGRICULTURE DEVELOPMENT PROJECT

Implementation Strategy (IS)

1. The strategy for implementation support is based on the ORAF, where the risks

identified to achieving the project development objectives and the agreed mitigation

measures have been summarized. The strategy will be reviewed based on the periodic

assessments of the risks and the appropriateness of the mitigation measures.

2. Capacity constraints in implementing agencies. Bank implementation support

will focus on the implementation of the measures to strengthen the capacity of Sichuan

Province, Mianyang City, and the three county governments to implement the project in

accordance with Bank requirements on procurement, financial management, and

environmental and social safeguards. Specifically, the Bank team will confirm that

agreed specialist staffing (especially financial management staff) are in place, and review

on a regular basis adherence to the project procurement manual, the project financial

management manual, the EMP and the RAPs. It will also confirm that the agreed

intensive training program on project management, financial management, procurement,

and safeguards is provided to project staff, and will offer such programs on a

supplemental basis when required.

3. Delivery quality risks. The Bank team will carefully monitor the provision of

additional financing support for the construction of the on-farm system, in close

correspondence with the construction of the main, sub-main, and branch canal system. It

will review the implementation of the comprehensive construction programming plan, as

well as construction management practices. It will periodically assess the adequacy of

the cost recovery system for on-farm O&M being implemented by the WUAs, as well as

the quality of O&M of both the main system and the on-farm works. .

Implementation Support Plan (ISP)

4. In order to provide effective implementation support, the Bank team supporting

the project will be almost entirely based in Beijing. It will be supplemented by

Washington based experts when necessary, as well as national and international

consultants. The task team will conduct, on average, two full review missions each fiscal

year. In addition, specialists will make shorter visits to project sites as and when

necessary. Table below indicates expected focus of implementation support during the

different phases of the project and the skills needed.

Page 51: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

41

Main focus in terms of support to implementation

Time Focus Skills

Needed Resource Estimate

Partner

Role First twelve months

FM and disbursement

training and FM

supervision

Procurement Training

and Workshops

Safeguards Training

Project Concept and

Approach Training

FM and DS Procumbent Safeguards Agro-water Management

FM specialist

0.5 SW

Disbursement

Officer 1 SW

Procurement

Specialist 1 SW

Safeguards Specialist

2 SW

3 SW

12-60 months Financial management

&disbursement and

procurement review and

support

PROMIS application to

monitor the

procurement and

financial and

disbursement process

EMP and PMP

implementation

FM and DS Procurement Safeguards

FM specialist

1 SW annually

Disbursement

Officer 2 SWs

annually

Procurement

specialist 2 SWs

annually

Safeguards specialist

2 SWs annually

Page 52: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/274171468239670227/... · 2016-07-11 · document of the world bank for official use only report no: 57661-cn

42

Annex 6. Team Composition

SICHUAN WUDU IRRIGATED AGRICULTURE DEVELOPMENT PROJECT

World Bank staff and consultants who worked on project preparation:

Name Title Unit

Liping Jiang TTL and Sr. Irrigation Specialist EASCS

Zong-Cheng Lin Sr. Social Development Specialist EASCS

Yiren Feng Sr. Environmental Specialist EASCS

Ximing Zhang Sr. Dam Safety Specialist EASCS

Jinan Shi Sr. Procurement Specialist EASCS

Yuan Wang Procurement Specialist ESSCS

Yi Dong Sr. Financial Management Specialist EAPFM

Jun Zhao Rural Development Specialist EASCS

Zhuo Yu Disbursement Officer CTRLN

Xin Chen Sr. Program Assistant EACCF

Xuemei Guo Program Assistant EACCF

Dan Xie Team Assistant EACCF

Vel Fernandes Program Assistant EASIN

Junxue Chu Sr. Finance Officer CTRFC

Kishor Uprety Sr. Counsel LEGES

Syed I. Ahmed Lead Counsel LEGES

Xueming Liu Sr. Economist FAO/CP

Usaid L. Hanbali Sr. Irrigation Engineer Consultant

Li Ou Sr. CDD/WUA Specialist Consultant

Zhang Kaiping Sr. Agricultural Specialist Consultant

Li Zhi Construction Programmer Consultant

Abdulhamid Azad Peer Reviewer MNSWA

Paulus Van Hofwegen Peer Reviewer EASIS

IJsbrand Harko de Jong Peer Reviewer EASS1

Joop Stoutjesdijk Peer Reviewer SASDA