47
Document of The World Bank FOR OFFICIAL USE ONLY Report No: PAD3323 INTERNATIONAL DEVELOPMENT ASSOCIATION PROJECT PAPER ON A PROPOSED ADDITIONAL CREDIT IN THE AMOUNT OF (SDR 145 MILLION) (US$ 200 MILLION EQUIVALENT) TO NEPAL FOR SECOND ADDITIONAL FINANCING EARTHQUAKE HOUSING RECONSTRUCTION PROJECT December 19, 2019 Urban, Disaster Risk Management, Resilience and Land Global Practice South Asia Region This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

Document of 

The World Bank 

FOR OFFICIAL USE ONLY Report No: PAD3323  

 

INTERNATIONAL DEVELOPMENT ASSOCIATION 

PROJECT PAPER 

ON A  

PROPOSED ADDITIONAL CREDIT 

IN THE AMOUNT OF (SDR 145 MILLION)  (US$ 200 MILLION EQUIVALENT) 

TO  

NEPAL 

FOR  

SECOND ADDITIONAL FINANCING EARTHQUAKE HOUSING RECONSTRUCTION PROJECT 

 

December 19, 2019 

 

 

 

 Urban, Disaster Risk Management, Resilience and Land Global Practice 

South Asia Region 

This document has a restricted distribution and may be used by recipients only in the performance of their official duties.  Its contents may not otherwise be disclosed without World Bank authorization. 

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

 CURRENCY EQUIVALENTS  

 (Exchange Rate Effective October 31, 2019) 

 

Currency Unit  =   NPR 

 NPR 110 =  US$1 

US$ 1.37939 =  SDR 1 

 

FISCAL YEAR July 16 – July 15 

ABBREVIATIONS AND ACRONYMS 

AF  Additional Financing 

BCR  Benefit‐Cost Ratio 

Cat‐DDO  Catastrophe Deferred Draw Down Option 

CERC  Contingent Emergency Response Component 

CLPIU  Central‐Level Project Implementation Unit 

CPF  Country Partnership Framework 

CPS  Country Partnership Strategy 

CSEB  Compressed Stabilized Earth Brick 

DA  Designated Account 

DLPIU  District‐level Project Implementation Unit 

DPC  Development Policy Credit 

DRM  Disaster Risk Management 

DRRM  Disaster Risk Reduction and Management 

DTCO  District Treasury Controller’s Office 

EA  Economic Analysis 

EHDC  Earthquake Housing Damage Characteristics 

EHRP  Earthquake Housing Reconstruction Project 

ESMF  Environment and Social Management Framework 

ESMP  Environment and Social Management Plan 

FCGO  Financial Comptroller General’s Office 

FM  Financial Management 

FMIS  Financial Management Information System 

GDP  Gross Domestic Product 

GESI  Gender Equality and Social Inclusion 

GLOF  Glacial Lake Outburst Flood 

GoN  Government of Nepal 

GRM  Grievance Redressal Mechanism 

GRS  Grievance Redressal System 

HRP  Housing Reconstruction Program 

IPF  Investment Project Financing 

IRR  Internal Rate of Return 

IUFR  Interim Unaudited Financial Report 

Page 3: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

LMBIS  Line Ministry Budget Information System 

MDP  Mandatory Direct Payment 

MDTF  Multi‐Donor Trust Fund 

MIS  Management Information System 

MRT  Mandatory Rules of Thumb 

NBC  Nepal Building Code 

NLSS  Nepal Living Standards Survey 

NPV  Net Present Value 

NRA  National Reconstruction Authority 

NRB  Nepal Rastra Bank 

OAG  Office of the Auditor General 

OJT  On‐the Job Training 

OP  Operational Policy 

PDO  Project Development Objective 

PIU  Project Implementation Unit 

PMU  Project Management Unit 

PPSD  Project Procurement Strategy for Development 

POM  Project Operations Manual 

SMS  Short Messaging Service 

STA  Socio‐technical Assistance 

TA  Technical Assistance 

TABUCS  Transaction Accounting and Budget Control System 

TPMA  Third Party Monitoring Agent 

USAID  United States Agency for International Development 

WB  World Bank 

    

Regional Vice President: Hartwig Schafer 

Country Director: Idah Z. Pswarayi‐Riddihough 

Regional Director: John Roome 

Global Practice Director: Sameh Wahba 

Country Manager: Faris H. Hadad‐Zervos  

Practice Manager: Christoph Pusch 

Task Team Leader(s): Kamran Akbar, Hemang D. Karelia 

Page 4: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

Nepal  

Second Additional Financing Earthquake Housing Reconstruction Project  

TABLE OF CONTENTS   I.  BACKGROUND .................................................................................................................. 1 

II.  DESCRIPTION OF ADDITIONAL FINANCING ....................................................................... 9 

III.  KEY RISKS ....................................................................................................................... 10 

IV.  APPRAISAL SUMMARY ................................................................................................... 11 

V.  WORLD BANK GRIEVANCE REDRESS ............................................................................... 12 

VI    SUMMARY TABLE OF CHANGES ...................................................................................... 14 

VII   DETAILED CHANGE(S) ..................................................................................................... 14 

VIII. RESULTS FRAMEWORK AND MONITORING .................................................................... 17 

ANNEX 1: ECONOMIC ANALYSIS ............................................................................................ 26 

ANNEX‐2: PROCUREMENT ARRANGEMENTS ......................................................................... 29 

ANNEX‐3: FINANCIAL MANAGEMENT .................................................................................... 30 

ANNEX 4: TARGETED SUPPORT TOWARDS IMPROVING GENDER OUTCOMES ....................... 35 

   

Page 5: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

i

      

BASIC INFORMATION – PARENT (Earthquake Housing Reconstruction Project ‐ P155969)

     

Country  Product Line  Team Leader(s) 

Nepal  IBRD/IDA  Kamran Akbar 

Project ID  Financing Instrument  Resp CC  Req CC  Practice Area (Lead) 

P155969  Investment Project Financing 

SSACD (9364)  SACNP (7029)  Urban, Resilience and Land 

  Implementing Agency: National Reconstruction Authority   ADD FIN TBL1 

Is this a regionally tagged project? 

No 

Bank/IFC Collaboration    

No 

Approval Date  Closing Date Expected Guarantee Expiration Date 

Original Environmental Assessment Category 

Current EA Category 

29‐Jun‐2015  30‐Jun‐2023    Partial Assessment (B)  Partial Assessment (B) 

 

Financing & Implementation Modalities Parent 

[  ] Multiphase Programmatic Approach [MPA]  [✓] Contingent Emergency Response Component (CERC) 

[  ] Series of Projects (SOP)  [  ] Fragile State(s) 

[  ] Disbursement‐Linked Indicators (DLIs)  [  ] Small State(s) 

[  ] Financial Intermediaries (FI)  [  ] Fragile within a Non‐fragile Country 

[  ] Project‐Based Guarantee  [  ] Conflict 

[  ] Deferred Drawdown  [✓] Responding to Natural or Man‐made disaster 

[  ] Alternate Procurement Arrangements (APA) 

 Development Objective(s)  The Project Development Objective (PDO) is to restore affected houses with multi‐hazard resistant core housing units in target areas and to enhance the government's ability to improve long‐term disaster resilience.  

Page 6: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

ii

 

Ratings (from Parent ISR)     RATING_DRAFT_YES           

 

Implementation 

  07‐Dec‐2017  15‐Jun‐2018  19‐Dec‐2018  27‐Jun‐2019  27‐Sep‐2019 

Progress towards 

achievement of 

PDO MS 

 

MS  

MS  

MS  

MS  

Overall 

Implementation 

Progress (IP) MS 

 

MS  

MS  

MS  

MS  

Overall Safeguards 

Rating  MS  

MS  

MS  

MS  

MS  

Overall Risk  S  

S  

S  

S  

S  

  BASIC INFORMATION – ADDITIONAL FINANCING (Second Additional Financing Earthquake Housing Reconstruction Project ‐ P170565)  ADDFIN_TABLE 

Project ID  Project Name  Additional Financing Type Urgent Need or Capacity Constraints 

P170565  Second Additional Financing Earthquake Housing Reconstruction Project 

Scale Up  Yes 

Financing instrument  Product line  Approval Date 

Investment Project Financing 

IBRD/IDA  22‐Jan‐2020 

Projected Date of Full Disbursement 

Bank/IFC Collaboration   

30‐Jun‐2023  No 

Is this a regionally tagged project? 

No 

 

Financing & Implementation Modalities Child    

Page 7: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

iii

[  ] Series of Projects (SOP)  [  ] Fragile State(s) 

[  ] Disbursement‐Linked Indicators (DLIs)  [  ] Small State(s) 

[  ] Financial Intermediaries (FI)  [  ] Fragile within a Non‐fragile Country 

[  ] Project‐Based Guarantee  [  ] Conflict 

[  ] Deferred Drawdown  [✓] Responding to Natural or Man‐made disaster 

[  ] Alternate Procurement Arrangements (APA) 

[  ] Contingent Emergency Response Component (CERC) 

  Disbursement Summary (from Parent ISR)  

Source of Funds Net  

Commitments Total Disbursed  Remaining Balance  Disbursed 

IBRD         

 % 

IDA   500.00   385.72   112.71   

77 % 

Grants         

 % 

  PROJECT FINANCING DATA – ADDITIONAL FINANCING (Second Additional Financing Earthquake Housing Reconstruction Project ‐ P170565)

 

     

     

PROJECT FINANCING DATA (US$, Millions)  

SUMMARY‐NewFin1 

SUMMARY (Total Financing) 

  Current Financing Proposed Additional 

Financing Total Proposed 

Financing 

Total Project Cost  500.00  239.40  739.40 

Total Financing  500.00  239.40  739.40 

of which IBRD/IDA   500.00  200.00  700.00 

Financing Gap  0.00  0.00  0.00 

  DETAILSNewFinEnh1‐ Additional Financing 

World Bank Group Financing 

     International Development Association (IDA)  200.00 

          IDA Credit  200.00 

Page 8: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

iv

Non‐World Bank Group Financing 

     Counterpart Funding  39.40 

          Borrower/Recipient  39.40 

     IDA Resources (in US$, Millions) 

Credit Amount  Grant Amount  Guarantee Amount  Total Amount 

Nepal  200.00     0.00     0.00   200.00 

National PBA  200.00     0.00     0.00   200.00 

Total  200.00  0.00     0.00  200.00 

 

COMPLIANCE 

 Policy 

Does the project depart from the CPF in content or in other significant respects? 

[    ] Yes   [ ✔ ] No 

Does the project require any other Policy waiver(s)? 

[    ] Yes   [ ✔ ] No   INSTITUTIONAL DATA

 

 

Practice Area (Lead) 

Urban, Resilience and Land 

 

Contributing Practice Areas 

 

 Climate Change and Disaster Screening 

This operation has been screened for short and long‐term climate change and disaster risks 

 

PROJECT TEAM  

 Bank Staff 

Name  Role  Specialization  Unit 

Kamran Akbar Team Leader (ADM Responsible) 

  SSACD 

Page 9: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

v

Hemang D. Karelia  Team Leader  Disaster Risk Management  SSACD 

Shambhu Prasad Uprety Procurement Specialist (ADM Responsible) 

Procurement  ESARU 

Chandra Kishor Mishra  Procurement Specialist    ESARU 

Franck Bessette Financial Management Specialist (ADM Responsible) 

Financial Management  ESAG2 

Caroline Mary Sage Social Specialist (ADM Responsible) 

Social Safegaurds  SSASO 

Drona Raj Ghimire Environmental Specialist (ADM Responsible) 

  SSAE1 

Avani Dixit  Team Member  Disaster Risk Management  SSACD 

Bigyan B. Pradhan  Team Member  Operations  SACNP 

Neena Shrestha  Team Member    ESARU 

Ramesh Raj Bista  Team Member    ESARU 

Rekha Shreesh  Team Member  Social Development  SSASO 

Rupa Shrestha  Team Member    SACNP 

Sujan Bahadur Thing  Team Member    SSACD 

Sulochana Nepali  Team Member Disaster Risk Management Analyst 

SSACD 

 Extended Team 

Name  Title  Organization  Location       

 

Page 10: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 1 of 38 

 

I. BACKGROUND  

A. Introduction 

1. This  Project  Paper  seeks  approval  of  the  Executive  Directors  to  provide  an  additional  credit  in  the amount of SDR 145 million (US$200 million equivalent) to the Nepal Earthquake Housing Reconstruction Project (EHRP; Project ID: P155969; Credit Number: 5706‐NP and 6164‐NP; US$500 million equivalent). The EHRP and the  Second  Additional  Financing  contribute  to  the  Government  of  Nepal’s  (GoN)  umbrella  Housing Reconstruction  Program  (HRP)  which  aims  to  rebuild  earthquake‐resistant  core  housing  units  by  providing housing grants – divided into three tranches – to eligible beneficiaries who have enrolled in the program. The proposed second additional financing (AF2) will scale up EHRP’s support to the Government’s HRP by financing reconstruction of an additional 86,680 houses in the 32 districts affected by the 2015 earthquakes. The Project Paper does not propose any major changes to the design and activities supported by the project. 

 

2. The  original  EHRP  (US$200 million,  approved  on  June  29,  2015)  supports  resilient  reconstruction  of approximately 55,000 houses in the districts most affected by the 2015 earthquakes. An additional IDA credit of US$300 million was approved on December 15, 2017 to scale up the EHRP and help bridge the financing gap in the GoN’s HRP by supporting 96,000 additional households under the project. The EHRP adopts an owner‐driven housing  reconstruction approach  that promotes earthquake‐resistant building  techniques and materials  and aims at improving long‐term resilience through a culture of safer and sustainable housing and settlements. The project also finances (a) social, environmental and technical support mechanisms for beneficiary households; (b) training  of  artisans  and  beneficiaries;  (c)  communication  and  outreach;  (d)  supervision  and  certification  of compliance  with  construction  guidelines;  (e)  implementation  of  environmental  and  social  management framework  including  identified  safeguard  mitigation  measures;  (f)  development  of  grievance  redress mechanism; and (g) other enabling activities.  

Page 11: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 2 of 38 

3. Eligible beneficiaries receive grants of NPR 300,000 (approximately US$2,7301) each for reconstruction of their houses in compliance with approved reconstruction guidelines. Housing grants are provided in three tranches:  

a. First tranche of NPR 50,000 is paid upon signing of the Participation Agreement by an eligible beneficiary;  b. Second  tranche of NPR 150,000  is paid once  it  is established  that  the plinth has been constructed  in 

accordance with the reconstruction guidelines approved by the National Reconstruction Authority (NRA); and.  

c. Third tranche of NPR 100,000 is paid after inspection at roof‐band level upon finding it to be compliant with  the  reconstruction  guidelines.  There  is  a  provision  of  ascertaining  completion  of  house reconstruction that serves as output verification.  

 4. In view of the large scope of the housing reconstruction program, a World Bank‐administered Multi‐Donor  Trust  Fund  (MDTF)2  has  been  established  to  facilitate  the  participation  of  development  partners interested in contributing to the housing reconstruction program. This MDTF, through its $10 million Recipient‐executed grant, finances housing grants to approximately 3,200 eligible beneficiaries. Bank‐executed grants of the  MDTF  support  the  implementation  of  the  EHRP,  provision  of  technical  assistance  to  NRA,  vulnerable population  and  economic  recovery  assistance  to  women  and  Persons  with  Disabilities  and  will  continue supporting  EHRP’s  expanded  scope with  the proposed AF2.  The MDTF has  received  commitments  from  the United States Agency for International Development (USAID), United Kingdom’s Department for International Development, Switzerland, and Canada, totaling to US$34.54 million to date. Japan International Cooperation Agency is providing parallel financing of about US$100 million and the Government of India is providing US$100 million grant and US$50 million concessional credit to support GoN’s housing reconstruction program.  

5. Country  Context.  Nepal  is  one  of  the  world’s  most  disaster  and  climate  vulnerable  countries.  An estimated 80 percent of the geographic area in Nepal is at risk from multiple hazards, with the vast majority of the country’s population, inhabiting high risk areas. Its per capita income is estimated at USD 730 and about 25 percent of its population lives below the poverty line. In last 50 years (from 1971 to 2015), disasters claimed lives of 40,000 people, injured more than 75,000 and affected 3 million people. The resilient development of Nepal is seriously hindered by these disasters and climate risks. The impact of the 2015 Gorkha earthquake and its major aftershocks are estimated at 35 percent of GDP with recovery needs of about USD 7 billion. Every year, intense monsoon  rainfall  causes  floods  in many  parts  of  the  country.  The  country was  severely  affected by monsoon floods in year 2017 that impacted more than 30 districts.  So far3, this year’s monsoon floods, landslides and heavy rainfall have affected 67 districts, causing loss of 113 lives, disappearance of 34 persons and damage to 67,413 households4.  In some cases, debris from landslides blocks rivers and when released suddenly, causes disastrous inundation downstream. The increased instability and intensity of geological and climate events on top of the fragile landscape is worsening landslide risks. Nepal is also highly vulnerable to Glacial Lake outburst floods (GLOFs). Glacier thinning and retreat in the Himalayas has resulted in the inherently unstable process of formation of new glacial lakes and the enlargement of existing ones. Recent surveys indicate that many glacial lakes in the country are expanding at a considerable rate, increasing the risk of sudden outbursts. For Nepal to continue  to make progress on  its key development  indicators,  it  is critical  to  invest  in  resilient  recovery and reconstruction post‐earthquakes to avoid creating new risks and strengthen disaster preparedness and response capacity to manage the disaster risks. 

1 Exchange rate of US$1=NPR 110 has been used.  2 The MDTF includes $10 million in Recipient‐executed grant providing housing grants to beneficiaries and other Bank‐executed grants for providing technical assistance and advisory support to NRA on implementing housing reconstruction program.  3 As of July 26, 2019 4 National Emergency Operation Centre, Ministry of Home Affairs

Page 12: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 3 of 38 

6. Strategic Context of Disaster Risk Management Sector: Under the provisions of the new constitution, Disaster Risk Management (DRM) is on the list of concurrent subjects, thus all the tiers of government share authority and responsibility in this regard. In October 2017, the Disaster Risk Reduction and Management Act (DRRM Act) was enacted  to streamline  the disaster  risk management,  relief and  response  related processes across  all  line  Ministries.  The  Act  provides  a  platform  to  address  climate  and  disaster  risk  reduction  in  a systematic  manner  and  is  the  foundation  of  the  GoN’s  DRM  program.  It  mandates  the  establishment  of  a National Disaster Risk Reduction and Management Authority and Disaster Committees at the Federal, Provincial, District and Municipal levels. The Act is consistent with the Sendai Framework 2015‐2030 and its predecessor the Hyogo Framework for Action 2005‐2015 (HFA), and sets in motion the ongoing GoN’s DRM Program that aims to reduce climate and disaster risk and loss of life, livelihoods and health. The activities planned under EHRP Component 2: Disaster Risk Management Systems will directly support some elements of GoN’s DRM program and will also complement the DRM Development Policy Credit (DPC) Catastrophe Deferred Draw‐down Option (Cat‐DDO) that is under preparation.  

7. Institutional Context. Following the devasting earthquakes occurred in April 25, 2015 and May 12, 2015, Government of Nepal (GoN) established National Reconstruction Authority (NRA) in December 2015 to lead and manage recovery, rehabilitation and reconstruction of affected infrastructures. The mandates of NRA are to: reconstruct, retrofit and restore damaged infrastructure and houses in disaster resilient manner following the Build Back Better principle and with the overall aim of building resilient communities; develop opportunities for economic growth and livelihood; undertake research and studies on the science of earthquakes and their impact; and  manage  relocation  and  resettlement  of  vulnerable  and  displaced  communities.  The  NRA’s  roles  and responsibilities  include:  identifying  priorities  for  reconstruction  based  on  damage  assessments;  allocating reconstruction funds based on agreed priorities; approve plan and budget for the allocated funds; relocation and  rehabilitation;  collaborating  with  key  stakeholders;  building  implementation  capacity;  developing  and implementing programs  related  to  reconstruction  and  rehabilitation of  infrastructures  related  to  education, health, agriculture, cultural heritage and industry;  monitoring and quality control; and ensuring accountability and  transparency.  The Project  and proposed additional  financing will  complement  these  efforts  and  lay  the groundwork for a longer‐term program to strengthen disaster and climate resilience in Nepal. 

8. The project aligns with the objective of the 2014–2018 Nepal Country Partnership Strategy (CPS) 5 as well as the 2019–2023 Nepal Country Partnership Framework (CPF) 6 to address natural disaster risks in a cross‐cutting manner. The CPS and the CPF recognize Nepal’s high vulnerability to climate change and disaster risks, particularly the high earthquake risks, and commits to continue mainstreaming contingent emergency response components across its portfolio to allow the GoN to request the reallocation of project funds to support response and  reconstruction  in  the  case  of  an  adverse  natural  event.  The  project with  its  focus  on  disaster‐resistant reconstruction,  strengthening  of  the  DRM  systems,  and  inclusion  of  the  contingent  emergency  response component directly contributes to achieving the objectives of the CPS and the CPF objective 3.3 for increasing resilience to natural disasters and climate change. The project is also consistent with the World Bank’s twin goals of ending extreme poverty and promoting shared prosperity and fully aligns with the GoN’s post‐earthquake Housing Reconstruction Policy. The project objectives also align with the Sendai Framework for Disaster Risk Reduction (2015–2030) priority 4 that calls for enhancing disaster preparedness for effective response and to ‘Build Back Better’ in recovery, rehabilitation, and reconstruction. 

B. Economic and Political Context 

5 The Project is consistent with the World Bank Group Country Partnership Strategy FY14‐18 discussed by the Board on May 1, 2014 (Report 83148‐NP) 6 The Project is consistent with the World Bank Group Country Partnership Framework FY19‐23 discussed by the Board on July 10, 2018 (Report 121029‐NP) 

Page 13: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 4 of 38 

9. Over the past decade, Nepal’s economy has performed reasonably well. Real gross domestic product (GDP) growth averaged 4.9 percent (at market prices) over FY2010‐FY2019.  Although declining as a share of GDP, agriculture continues to play a significant role, contributing 1.6 percentage points to growth in FY2019. Over the same period, the service sector contributed 3.9 percentage points and industry 1.3 percentage points. Industry has grown more slowly and over the past decade. Similarly, exports continue to struggle, while imports are  fueled by remittances,  federalism, and housing construction/reconstruction. Remittances have remained stable, with its share as a percentage of GDP averaging 25 percent, supported by an increased transfer of funds through formal channels in recent years, and a depreciation of the Nepali Rupee against the US dollar. Inflation has been in single digits for most of the past decade, with the peg of the Nepalese rupee to the Indian rupee providing a nominal anchor. Fiscal balances remained sustainable owing to strong revenue growth and modest spending. Also, the federal government is now sharing revenue and transferring grants to provincial and local governments, as part of the recent reforms linked to federalism. The projected poverty headcount ratio (at the US$1.90 per person per day international poverty line) was 9.3 percent in 2018, down from 15 percent in 2010.  At a higher line of US$3.20 a day for Nepal, 41 percent of the population was poor in 2018, a 10 percentage‐point decrease from 2010. Despite the declining poverty trend, vulnerability remains high in Nepal. Almost 10 million people or close to 32 percent of the population are estimated to live between US$1.90 and US$3.20 a day (2018). Climate related shocks such as floods and earthquakes, further increase vulnerability.    

10. Data released by  the Central Bureau of Statistics  (consisting of a  revision of  the FY2018 growth rate coupled with the preliminary estimate for FY2019), show that growth has been strong.  Good monsoons together with increased commercialization of agriculture, the availability of fertilizers and seeds, and irrigation facilities helped  raise production of paddy, maize,  and wheat  to historic  highs and  increased  the  contribution of  the agriculture sector to GDP growth from 0.9 percentage points in FY2018 to 1.6 percentage points in FY2019. As a result, GDP growth increased from 6.7 percent in FY2018 to an estimated 7.1 percent in FY2019. Government revenue growth was robust (17.7 percent) in FY2019 but only 90.5 percent of the revenue target was met mainly due to lower imports, resulting in lower trade taxes. Delays in the enactment of Federal, Provincial, and Local Civil Service Acts and in the establishment of provincial civil service commissions adversely impacted the hiring of new staff at the subnational level. These delays together with the lack of technical capacity of existing staff led to an underspending of the federal budget by 18.8 percent, with recurrent and capital spending standing at 83.2 and 75.9 percent of the budgeted target, respectively.   There was also bunching of spending, with 14.4 percent  of  recurrent  and  36.5  percent  of  capital  spending  occurring  in  the  last  month  of  the  fiscal  year. Federalism has also exacerbated the challenges linked to weak budget execution with significant underspending of  provincial  budgets,  resulting  in  significant  opening  balances  of  17  percent  of  FY2020  provincial  budgets (equivalent to the provincial budget share for conditional transfers). 

11. Given good agricultural production and the existing peg to the Indian Rupee,  inflation in FY2019 (4.5 percent) remained below target (5.5 percent). Credit growth reached 19.3 percent, exceeding deposits growth, and led to a rise in the banking sector’s credit‐to‐core capital plus deposit ratio (which at 75.2 percent, remained just below the 80 percent regulatory limit). On the external side, the current account deficit remained high at 7.7 percent of GDP in FY2019, driven by a persistent trade deficit. The  latter narrowed marginally  from 37.5 percent  to  37.1  percent  of GDP  as  goods  import  growth  slowed down,  reflecting  lower  import  demand  for industrial supplies (such as cement clinker) and capital goods. The trade deficit has been financed mainly by remittances, as well as external concessional loans, and foreign reserves. 

12. A new government, backed by an unprecedented majority in Parliament, which took office on February 15, 2018 has recently completed one and half years.  This follows successful elections for all three tiers (local, state and federal) of the new state architecture defined by the 2015 constitution, marking a protracted‐but‐successful conclusion of a political transition that began with the signing of the Comprehensive Peace Agreement in November 2006.  State governments largely mirror the coalition at the center. At the sub‐national level, funds, functions and functionaries hitherto managed by the central, district and village authorities are moving to the 

Page 14: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 5 of 38 

seven  new  provinces  and  753  local  governments  for  which  new  legislation,  institutions  and  administrative procedures are being formalized as constitutionally prescribed.  Meanwhile, the central level authority is being streamlined with a focus on national policies and oversight.  This profound level of state restructuring is expected to result in improved outreach and service delivery in the medium term but is likely to take time before becoming fully operational. 

C. Current Status of the Project 

13. The EHRP is rated Moderately Satisfactory for implementation progress as well as for progress toward achieving  the Project Development Objective  (PDO).  The PDO  remains  relevant  given  the  extensive housing reconstruction needs and is achievable judging by the progress attained so far and demonstrated commitment shown by  the GoN  leadership. The EHRP and AF have already disbursed 77 percent of  the  total  credit as of November  30,  2019.  The  EHRP  is  compliant  with  key  legal  covenants,  including  auditing  and  financial management (FM) reporting requirements, though the last year’s audit report was submitted with a delay of three months. There has been satisfactory compliance on establishing a Project Management Unit (PMU) at the NRA and central and district‐level Project Implementation Units (DLPIUs). The Housing Reconstruction Program has adopted a robust system for identifying eligible beneficiaries, enrolling them into the program by signing Participation Agreements and ensuring the grant payments are transferred to the beneficiaries’ registered bank accounts upon satisfactory inspection at each stage of the multi‐hazard resistant house reconstruction. 

14. Below is a summary of progress in the project components: 

a. Component 1: Housing Reconstruction. Significant progress has been achieved under this component with accelerated disbursement of the second and third tranches of the housing grants based on satisfactory rate of compliance to safer reconstruction requirements. As of September 10, 2019, out of 680,587 beneficiaries enrolled under the GoN’s Housing Reconstruction Program in 14 most affected districts, 99 percent have received the first tranche, 81 percent have received the second tranche, and 68 percent have received the third tranche of the housing grant. While the inspection regime is fully established, the process of successful quality inspections and tranche disbursement gets delayed because of shortage of funds. The funding gap is also reflected in the lag between 1st and 2nd and 3rd tranches. The NRA has reported about 402,297 houses fully reconstructed under their program. Similar progress is observed in other 18 affected districts. Overall, about 481,056 houses  in 32 affected districts are reported to be fully reconstructed under the Housing Reconstruction  program.  Under  EHRP,  approximately  151,000  completed  houses will  be  covered  upon meeting the output verification requirements and digital documentation of the Participation Agreements with beneficiaries, first and second inspection data, and proof of payment of housing grant tranches into beneficiaries’ bank accounts.  To date,  77,789 houses have been booked under  IDA credits with 40,000 additional houses slated to be booked by mid‐December 2019. The NRA has devoted additional resources to expedite output verifications and have them validated by an M&E firm as a Third‐Party Monitoring Agent. 

b. Component 2: Disaster Risk Management Systems. The progress on this component remained slow initially with  only  29  of  200  targeted  government  officials  receiving  training,  and  no  technical  studies  for  the Disaster  Risk  Management  (DRM)  were  taken  up.  This  was  mainly  due  to  the  fact  that  the  housing reconstruction remained top priority for the NRA, coupled with the fact that Nepal was in transition from unitary form of government to a federal structure, awaiting clarity on roles and responsibilities related to the DRM activities. The Mid‐term review of the original EHRP held from July 29 to August 10, 2018, agreed to  carry  out  several  activities  under  Component  2.  This  included  a  nationwide  Structural  Integrity Assessment  (SIA) of  social  infrastructure  (schools  and health  facilities),  that will  assist  all  three  tiers of government in risk‐informed decision making in educational and health sector. The second activity agreed under this component is to build disaster risk management capacity of and transfer housing reconstruction data and systems  to  local governments. These activities were  included  in  the Project  through a Project Restructuring in early‐2019. While the action plan for transferring reconstruction data and systems along 

Page 15: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 6 of 38 

with capacity building measures has been finalized after conducting a district‐level needs assessment, the implementation of SIA has delayed. These activities aim to enhance the Government’s ability to improve long‐term disaster resilience.  

15. Overall,  the EHRP and  the EHRP MDTF have helped  set up a  sound  implementation  framework and technical regime for the GoN’s umbrella HRP with the following contributions: 

a. A comprehensive census of the earthquake‐affected areas surveying over 800,000 households to collect housing damage and socioeconomic information to determine program eligibility; 

b. A robust management information system and a multi‐tier grievance redressal system in place that has registered more than 200,000 grievances  (primarily  related to  ineligibility  to receive housing grants), with more than 98 percent cases addressed; 

c. Around 2,500 engineers, sub‐engineers, and assistant sub‐engineers deployed in the project districts to facilitate reconstruction, of which 18 percent are women; 

d. Mass awareness programs, technical trainings for masons and artisans, and communication campaigns for safer construction practices and Government‐approved design specifications; 

e. House quality  inspection  regime  to ensure earthquake‐resistant  construction at  several  construction stages and guidelines for corrective (remedial) actions; 

f. A  streamlined  fund  flow with  digital  recordkeeping  and  direct  payment  of  housing  subsidy  into  the beneficiaries’ designated bank accounts; and  

g. Strong  coalition  of  major  development  partners  toward  safer  housing  reconstruction  and  pooled resources for providing continuous sociotechnical assistance to homeowners for construction. 

16. The  lessons  learnt during  the  EHRP  implementation,  such as  the need  to  sustain  and expand  socio‐technical  assistance  to  vulnerable  beneficiaries  and  engaging  recently  formed  Local  Governments  into reconstruction have already been factored into the original Project through a restructuring and remain integral to the proposed AF2.   

17. Climate change. A detailed climate and disaster risk screening has been carried out for the project. The effects of climate change and extremes have further aggravated the disaster vulnerability in Nepal. Notre Dame‐Global  Adaptation  Initiative  (ND‐GAIN) matrix  estimates  that  Nepal  is  on  road  to  responding  effectively  to climate change, but the adaptation needs and urgency to act are greater. The projected change in flood risk hazard has remained static since 1995, implying that the country continues to face flood risks. Rapidly growing urban concentration coupled with geohazards and climate risks puts Nepal in a high‐risk position. The technical and  financial  support  extended  through  the  project  is  helping  beneficiaries  to  reconstruct  houses  in nonhazardous locations, out of harm’s way. Due to its focus on reconstructing multi‐hazard resistant housing units and strengthening the DRM systems, the EHRP was assessed to have 81.5 percent (US$163 million) climate adaptation  co‐benefit,  and  the  first  AF’s  climate  adaptation  co‐benefits  were  estimated  at  88.5  percent (US$265.6 million). Given the similar project design and higher share of the credit allocated to resilient housing construction, climate adaptation co‐benefit for the second AF is anticipated at 90 percent (US$180 million). The sociotechnical assistance and trainings provided to homeowners and artisans/masons for multi‐hazard resistant construction  techniques will  also  help  improve  the  construction  quality  in  the  longer  term  in  targeted  and neighboring areas. This will be an important co‐benefit toward building resilience to natural hazards. 

18. Gender. As specified in the results framework, the project tracks the housing reconstruction progress of women‐headed households, which is estimated to be 26% of the total beneficiaries.  In addition, out of total indirect beneficiaries of the project activities including awareness about resilient reconstruction, 50 percent are expected to be women. Beyond ensuring their participation, the project has been able to significantly contribute to improved outcomes for women in several domains. For example, the project has promoted financial literacy and  inclusion  for women.  The EHRP’s  condition of  transferring housing grants directly  into beneficiary bank accounts has facilitated opening of bank accounts for 100 percent of participating households, with 30 percent 

Page 16: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 7 of 38 

of  the bank accounts belonging  to women. The Government’s HRP also provides an additional grant of NPR 200,000 to households requiring relocation due to hazardous location, wherein NRA has enforced a mandatory policy  provision  of  joint  land  entitlement  by  both  husband  and  wife  in  such  land  purchases.  So  far,  2,157 beneficiaries  have  purchased  land.  This  provision  ensures  joint  ownership  of  not  only  land  but  also  the reconstructed houses. 

19. While  not  necessarily  funded  under  IDA  funds,  the  HRP  program  activities  contribute  significantly towards  creating  job  opportunities  for  women  in  reconstruction  and  allied  sectors.  The  GoN  and  I/NGOs encourage women’s participation in various trainings related to masonry, carpentry, electrician and plumbing, etc.  Out  of  the  recipients  of  these  construction  related  trainings,  15  percent  are  women.  A  2018  study7 conducted by a coalition of  I/NGOs on women’s  role  in  reconstruction  indicates  that  the  reconstruction has provided an opportunity for many women in terms of employment, training and increased confidence. Similarly, of the total number of engineers deployed in the field to provide technical assistance and carry‐out inspection of reconstructed houses, 18 percent are women, which is quite significant, as engineering has conventionally remained a male‐dominated discipline with about 12 percent of the licensed engineers being women8. Social mobilization, which is a key area of the reconstruction activities, is female dominated, with 80 percent of social mobilizers in rural areas being women. Still, significant gender gaps in skilled work within the construction sector persist. According to data from Nepal Living Standards Survey (NLSS) Wave 3 (2010/2011), 29 percent of male wage earners work in the construction sector, compared to only 5.6 percent of female wage earners. Female wage earners in the construction sector work fewer days than men (on average 62 versus 112 days, annually) and  earn  less  annual  income  (Nepalese  Rupees  7,800  versus  21,000).  Although  the  number  of  women  in engineering  and  technical  jobs  has  increased  during  the  implementation  of  this  large‐scale  reconstruction program, a downward trend is likely once the program concludes and associated jobs in public sector reduce. However,  with  increased  awareness  on  the  need  for  earthquake‐resistant  design  and  construction,  there remains  a  scope  of  increased  private  sector  jobs  where  the  women  engineers  and  artisans,  trained  and experienced during the earthquake reconstruction, would have opportunities.  

20. In view of the above, the proposed AF2 aims at providing targeted support  to  leverage and  improve some of the gender‐specific outcomes in view of the gender gaps in employment in the construction and allied sectors. Under the proposed AF2, targeted support will be provided to leverage and improve gender outcomes through  IDA  financing.  This  includes:  i)  ensuring  a  share  of  employment  in  socio‐technical  assistance.  For expanding socio‐technical assistance, NRA is in the process of recruiting 250 social mobilizers and 988 mobile masons where the project will ensure that at least 10 percent9 mobile masons being employed are women, at equal pay scale of male masons, to narrow the gender and pay gap in employment in the reconstruction. The NRA  has  issued  recruitment  directives  that  emphasize  the  prioritization  of  employing  women  masons  and confirm their equal pay; ii) providing tailored on‐the‐job skills development and vocational training to female staff and masons/artisans after their recruitment to improve their job prospects and earning potential and help close the gender pay gap.; and iii) ensuring a share of women elected officials and local government officials (250 out of 1,000 planned) in Disaster Risk Management and reconstruction orientation. A detailed summary of gender actions and expected outcomes is presented at Annex‐4.  

21. Citizen engagement. Citizen engagement  is  central  to  the EHRP and  the AFs because they  follow an owner‐driven housing reconstruction approach. In addition to providing door‐to‐door socio‐technical assistance directly  to  the  beneficiaries  in  earthquake‐affected  areas  for  effective  reconstruction,  a  robust  multitier Grievance Redress Mechanism (GRM) developed for the EHRP will continue to be in use for the AF2. The GRM 

7 Women in Reconstruction Research Report by Housing Recovery and Reconstruction Platform, May 2018 8 Source: Nepal Engineers’ Association (NEA) 9 This target is set based on consultations with NRA and Nepali context where participation of women in skilled masonry prior to earthquakes was very low. This target will be reviewed during implementation. 

Page 17: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 8 of 38 

has so far received more than 200,000 grievances with more than 98 percent grievances redressed as per NRA records, some of which have been addressed at the local level. The NRA also conducted an awareness campaign for program beneficiaries through Short Message Service (SMS) during May–August 2017 that reached more than 450,000 enrolled beneficiaries with regular messages to  inform them about the housing reconstruction modalities and updates. This resulted in increased use of NRA’s toll‐free line by the beneficiaries for queries and feedback. Encouraged by the positive response from the dissemination of information through SMS, NRA is again sending critical information to beneficiaries through SMS. For example, an SMS campaign was conducted in July 2019 to inform beneficiaries on the requirement of third inspection. Other mass communication tools such as FM radio, social media, and television programs are also being widely used to disseminate reconstruction related information. The federal system of governance, recently introduced in the country, empowers citizens at the local level aiming at provision of services at doorsteps of the citizens. The planned mobilization of socio‐technical assistance  teams  at  local  government  level  will  facilitate  close  engagement with  the  beneficiaries,  who  for various reasons, including vulnerability, have not yet been able to reconstruct their houses or have aborted the process in between.  

D. Rationale for Additional Financing 22. The EHRP was originally designed to address the housing reconstruction needs of about 10 percent (total 55,000) of the total beneficiary households estimated after the earthquake in the 14 most impacted districts. During the subsequent beneficiary surveys and resurveys, the number of total enrolled beneficiaries surpassed 779,000 in 32 affected districts, widening the funding gap in the GoN’s umbrella housing reconstruction program to more than US$1.2 billion. In response to the GoN’s request for scale‐up, an additional IDA credit of US$300 million was approved in December 2017 to cover 96,000 additional household beneficiaries under the EHRP. Since the EHRP’s quality assurance, accountability and FM procedures apply to the whole umbrella HRP, this scale‐up  has  seamlessly  expanded  the  scope  of  EHRP while  narrowing  the  funding  gap  in HRP.  Despite  the resource pooling from Government sources and external assistance, the NRA estimates an outstanding funding gap of US$689 million in their HRP and has sought a second round of additional financing (AF) for EHRP with a share  in  counterpart  financing. Given  the advanced stage of  reconstruction with more  than 400,000 houses completed, 170,000 houses under construction, and another 100,000 houses yet to start reconstruction, there is an urgent need for the NRA to bridge the funding gap through this second additional financing (AF2) and avoid any delays in tranche payments to eligible beneficiaries in the process of reconstruction. The proposed AF2 will support hazard‐resistant reconstruction of an additional 86,680 of participating houses; the first tranche of the housing grant to these households (approximately US$39.40 million) will be financed by GoN as counterpart funding and the AF2 will finance the second and third tranches of the housing grants. 

E. Situation of Urgent Need of Assistance or Capacity Constraints 23. The EHRP and the AF were prepared under situations of urgent need of assistance or capacity constraints (formerly OP 10.0 paragraph 12, currently applicable as “General Considerations Applicable to Paragraph 12 of Section III of the IPF Policy” ) in view of the massive impact of the 2015 earthquakes on Nepal, particularly in the rural districts with higher poverty rates and weaker service delivery and substantial support required for post‐earthquake recovery and reconstruction. The demands of the large‐scale multisector earthquake recovery have continued to strain the NRA’s management and implementation capacities and have led to lost opportunities in the  recovery  process.  The  large‐scale  devastation  caused  by  the  2017  and  2019  monsoon  flooding  and subsequent recovery process have broadened the capacity constraints among the implementing agencies. With the implementation of the 2015 constitution, Nepal has moved from unitary form of government to a federal structure.  Considering  Nepal’s  high  vulnerability  and  exposure  to  natural  disasters,  the  Constitution  has addressed the subject of DRM in several instances,10 and has devolved all aspects of DRM and climate change 

10 Article 51(g)(4), 51(g)(9), and 267(4) as well as Articles 211 and 273 of the Constitution of Nepal. 

Page 18: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 9 of 38 

adaptation  to  all  the  levels  of  government.11  The  GoN  has  also  adopted  a  ‘Disaster  Risk  Reduction  and Management Act’  in  2017. While  the  legislative  reforms  have  taken  place,  the GoN  is  yet  to  fully  establish provincial and local‐level institutions along with the approval of their respective structure, rules, and regulations. Though the NRA and the task team have initiated a number of activities under the current EHRP operations to build  capacities  of  local  governments,  it  is  felt  that  the  capacity  constraints  necessitate  increased hands‐on support  to  all  tiers  of  government.  While  Nepal’s  transition  to  federal  structure  offers  opportunities  to decentralize recovery and reconstruction and make service delivery more effective and accountable, the risks of jurisdictional overlap among the new tiers of Government, and lack of clarity and coherence between policies and devolved powers is likely to remain high during the coming few years, especially in the DRM sector. The ambiguity  regarding  the  roles  and  responsibilities  between  federal,  provincial  and  local  governments  was evident during floods and ensuing landslides of 2019. Since the proposed project will identify the beneficiaries among the households that have already been enrolled, some of which have already started reconstruction, it will  require  40  percent  retroactive  financing  under  the  situations  for  urgent  need  and  capacity  constraints. Moreover, the US$689 million funding gap estimated by the GoN also suggests that second and third tranche payments to a large number of beneficiaries may get delayed, causing further debt burden on the beneficiaries who have completed the construction. This situation of urgent need warrants the use of condensed procedures available under “General Considerations Applicable to Paragraph 12 of Section III of the IPF Policy”. The financing agreement will address the triggering of paragraph 12 of Section III of the IPF Policy, to cater to the need for 40 percent  retroactive  financing  to  reimburse  the  eligible  beneficiary  households  who  have  already  received housing grant tranche(s). 

II. DESCRIPTION OF ADDITIONAL FINANCING 

24. The proposed AF2 is to scale up the components of original financing and the AF and does not propose major changes in the design and activities supported by the project. The proposed AF will support reconstruction of an additional 86,680 houses, increasing support from the existing 151,000 houses under EHRP and AF1 to a total of 237,680 houses.  

36ble 1. Revised Components Allocations 

Current Component Name 

Proposed Component Name 

Current Cost (US$, millions) 

Proposed AF Cost (US$, millions) 

Counterpart Financing 

(US$, millions) 

Total Cost (US$, millions) 

Housing Reconstruction  Housing Reconstruction  472.50  197.00 39.40 

708.90 

Disaster Risk Management Systems 

Disaster Risk Management Systems 

15.00  0.00 0.00 

15.00 

Project Implementation Support 

Project Implementation Support 

12.50  3.00  

0.00 15.50 

Contingency Emergency Response 

Contingency Emergency Response 

0.00  0.00 0.00 

0.00 

11 References from the Constitution of Nepal, 2015: (i) “Preparedness, rescue, relief and rehabilitation from natural and man‐made calamities” is a Schedule 7 subject, that is, concurrent between federal and provincial governments; (ii) Disaster Management is also a Schedule 8 subject, that is, concurrent between provincial and local governments and a Schedule 9 subject, that is, concurrent for all the three levels of government; (iii) Article 197 gives legislative powers to provinces with regard to Schedule 6, 7, and 9 and article 226 empowers municipal or local governments to frame laws with respect to schedule 8 and 9; (iv) At the federal level, according to Government of Nepal (Work Division) Regulation, 2074 published as Part‐3 of the Part 67 of the Nepal Gazette published on Falgun 11, 2074, the DRM‐related functions are divided among ‘Office of the Prime Minister and the Council of Ministers’ and nine federal ministries.

Page 19: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 10 of 38 

  Total:  500.00  200.00  39.40  739.40 

 

III. KEY RISKS 

25. The overall risk rating for the proposed second AF is Substantial. The most critical risks and mitigating measures associated with the second AF are summarized as follows: 

(a) Political and Governance risks are rated as Substantial.   In contrast to the frequent changes in government that  characterized  Nepal’s  decade‐long  transition  to  federalism,  the  new  government  enjoys  an unprecedented super‐majority in Parliament.  Along with new constitutional checks and a far fewer number of political parties, there is a much greater degree of optimism for stability in the coming days.  However, state  restructuring on  this  scale  is  uncharted  territory  for Nepal  and  smoothing  the  transition  from  the previous unitary system to the new federal one will remain a daunting task. The new system, in principle, provides opportunities to decentralize development benefits and make service delivery more effective and accountable. However,  the  risks of  jurisdictional overlap between  the  three  tiers of government,  lack of clarity and coherence between policies and devolved powers, and duplication of efforts will  remain high during the coming few years.  Key aspects of the new system require further definition and may continue to be contested by different population groups.  Despite the lack of clarity at this early stage to define roles, rules and create governance capacity at the provincial and local levels, the overall political and governance risk has decreased. 

(b) Technical  design  of  the  project  and  stakeholders’  risks  remain  Substantial.  The  owner‐driven  housing reconstruction approach adopted under the project is new to Nepal and providing socio‐technical assistance and  establishing  home  inspection  regime  in  remote,  mountainous  areas  have  proven  to  be  logistically challenging. This  risk  is being mitigated  through  technical assistance  (TA)  to  the PMU and  the PIUs with continuous  expanded  hands‐on  implementation  support.  There  is  a  need  to  expand  Socio‐technical assistance at the municipality level to provide TA to households. The World Bank has engaged three firms as third‐party monitoring agents (TPMA) under the MDTF as World Bank‐executed activities, to independently carry out field level monitoring to technically review the government’s inspection scheme on sample basis, and  provide  feedback  to NRA, District  Level  Project  Implementation Units  and  engineers  involved  in  the inspection.

(c) Institutional  capacity  for  implementation and  sustainability  risk  remains Substantial.  The  scope of  the umbrella housing reconstruction program is huge, and implementation capacities of the NRA and the PIUs have not been entirely satisfactory. While PMU remains fully staffed with all PIUs under its administrative control, capacity constraints still prevail in program management in general, and the FM and monitoring and evaluation in particular, as evident from persistent delays in conducting output verification of the completed houses and its timely reporting in desired quality. In view of the NRA’s sunset clause of December 2020, a possible handover to relevant ministries or local governments also pose sustainability risk.  

(d) Fiduciary risk remains High. The World Bank will continue the expanded implementation support, especially for synchronizing planning and budgeting, streamlined chart of accounts, and timely submission of financial reports. A number of mitigation measures have already been taken. NRA has established an FM working group  in  April  2017  supported  by  the  World  Bank,  USAID‐Public  Financial  Management  Strengthening Project, and Nepal European Union Action for Recovery and Reconstruction (NEARR). An FM team is in place at  the  NRA,  supported  by  consultants  seconded  by  development  partners.  An  FM  software  has  been customized and  installed  to  improve the FM and accounting functions, and training of  trainers has been completed. The streamlined use of software for budgeting and accounting will help address the quality and timeliness issues experienced in financial and audit reporting. The World Bank TPMA will be another source of data verification. Moreover,  the detailed earthquake household damage and characteristics survey  to 

Page 20: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 11 of 38 

identify beneficiaries, signed PAs while enrolling beneficiaries to the program, multitier grievance redressal mechanism (GRM) home inspection teams at the local level, and housing grant tranches disbursed through bank‐to‐bank transaction after verification have enhanced the transparency and helped manage fiduciary, stakeholder, and governance risks. 

(e) Environment and social risk remain Substantial. The risk for the proposed additional finance remains the same as for the parent project. The housing component of the project has been envisaged to respond to the reconstruction  needs  of  the  targeted  communities  for  new,  improved  and  resilient  housing.  There  are various  indigenous communities and vulnerable people residing  in the targeted communities who would receive  benefits.  The  project  is  designed  to  ensure  timely,  adequate,  and  appropriate  dissemination  of project  information,  and  their  full  participation  in  the  program  design  and  implementation.  Additional support is to be provided to vulnerable members of the communities. Due to the in‐situ reconstruction focus of the project activities, involuntary resettlement impact is expected to be quite limited.  

IV. APPRAISAL SUMMARY 

A. Economic and Financial Analysis 

26. The direct beneficiaries of the parent project are the members of approximately 55,000 participating households whose homes were destroyed in the earthquake. The AF approved in December 2017 added 96,000 additional households under housing reconstruction component and the proposed AF2 will add approximately 86,680 households as beneficiaries. An economic analysis (EA) performed for the parent project assessed the rate of return of capital investments needed for the reconstruction and recovery from the earthquake. Since it is difficult to make any assessment of benefits from resilient housing in terms of protection from future such earthquakes, the analysis adopted a more straightforward approach of calculating the returns to the households living in a resilient home and staying out of poverty compared to them not receiving any benefits to jumpstart their post‐disaster life. The main benefit component of this project is the shadow annualized rental income from the newly built multi‐hazard resilient housing units. The EA found the parent project to have the internal rate of return (IRR) of 21 percent and net present value (NPV) of US$265 million, with the benefit‐cost ratio (BCR) of 1.8,  indicating  that  the  project  was  economically  viable  by  conservative  estimates.  The  EA  for  the  first  AF approved in December 2017 found IRR of 24 percent, NPV of US$541.9 million, and BCR of 2 for the proposed AF’s  housing  reconstruction  component  of  US$287.5  million.  Using  similar  assumptions  for  the  EA  of  the proposed  AF,  IRR  of  27  percent,  NPV  of  US$490.5  million,  and  BCR  of  2.2  for  the  proposed  AF’s  housing reconstruction  component  of  total  US$236.40  million  ($197  million  from  IDA  and  $39.40  million  GoN counterpart financing) were found. The higher IRRs stem from costs savings resulting from the exchange rate depreciation  leading  to more housing  grant  beneficiaries  and higher  share of  investment  allocated  towards housing reconstruction component.  

B. Technical 

27. There  is  no  change  in  the  technical  analysis.  The  housing  reconstruction  component  scales  up  the provision of housing grants to the participating household beneficiaries in targeted areas. Core housing units are being reconstructed under owner‐driven housing reconstruction approach in compliance with the GoN/NRA's technical guidelines to ensure multi‐hazard resilience of the reconstructed houses. These technical guidelines cover the popular building construction technologies and locally available construction materials that are used in earthquake‐affected areas to ensure that the beneficiaries are likely to use them and have access to critical inputs. 

C. Financial Management  

28. The  FM  arrangements  under  the  original  project will  also  apply  to  the  AF2  since  the  implementing arrangements remain unchanged. NRA will be responsible for the overall FM arrangements under the project 

Page 21: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 12 of 38 

and will be supported through the FM arrangements in place at the CLPIUs and DLPIUs. The FM arrangements covering budgeting, accounting, reporting, funds flow, internal controls and audit were re‐assessed as part of the Pre‐Appraisal and found adequate. Financial controls for housing grants are supplemented through the TPM arrangement contracted by NRA. Adequate supporting documentation for tranche releases, of inspections and output verification is maintained and digitized within the MIS system allowing for easy retrieval and review. The AF2 will have a provision for retroactive financing for approx. US$80 million (40 percent of Credit) for Categories 1 and 2. There will also be counterpart funding from Government of Nepal to the tune of US$39.40 million, this will cover all first tranche payments made to identified beneficiaries prior to the retroactive financing period. Despite the recent improvements in internal controls and FM performance, the fiduciary risk is rated High given the large scope of the reconstruction program and capacity constraints in FM. World Bank will provide enhanced hands‐on implementation support, in addition to the bi‐annual reviews. The fiduciary risk will be reviewed during the implementation support and adjusted as necessary. The FM arrangements as currently assessed along with existing mitigating measures are considered adequate for the AF2. More details on the FM arrangements and internal controls are provided in the Annex‐3.  

D. Procurement  

29. The World Bank Procurement Regulations  for  IPF Borrowers,  July 2016 (revised November 2017 and August  2018),  will  apply  for  the  procurement  using  the  World  Bank  funds  from  the  AF2.  However,  the procurement arrangements for the original financing will remain unchanged. The PPSD and the Procurement Plan  for  the  first 18 months of  the project have been prepared  for smooth  implementation of procurement activities during project implementation. A summary of the PPSD and due diligence measures are in Annex‐2. 

E. Social and Environment (including Safeguards)  

30. Under  the original  financing,  the project  team experienced difficulties due  to complicated safeguard arrangements which involved developing environmental and social screening reports of each settlement in three districts,  totaling  to  approximately  1,000  environmental  and  social  screenings  and  several  cluster‐level Environment and Social Management Plans (ESMP). Meanwhile, the safeguard assessments carried out in the three original districts also  revealed  limited environmental and social  impacts arising  from project activities. Considering the lesson learned in three districts (Dolakha, Nuwakot, and Dhading) in terms of the feasibility and usefulness  of  the  safeguard  arrangements,  plus  the  recent  changes  in  governance  structure,  the  original Environment and Social Management Framework (ESMF) has been revised with mutual agreement between the GoN and the World Bank, to make it proportionate to environment and social risks and impacts and reflect legal, regulatory, and institutional regime changes. The scope of the revised ESMF excludes community relocation, integrated settlement development, urban areas, areas supported by other donors or  international/national nongovernmental  organizations,  and  reconstruction  of  heritage/cultural  sites  and  other  physical  and  social infrastructure and services. Preparation of a project‐level ESMP has been introduced as part of the ESMF which requires review, verification, and validation through the consultation with local government. A separate site‐specific ESMP along with an accompanying technical verification report will be prepared as needed for special cases of environmental and social  issues. Priority  is given  to coordinate and develop  links with other similar agencies for sharing mitigation measure costs; low‐cost options will be adopted and final mitigation costs must be approved by the NRA and relevant agencies. “Central Level PIU‐Grant Management and Local Infrastructure Development” of the NRA will then play a coordination and linking role with line agencies working in the sector to implement mitigation measures. The Resettlement Policy Framework has been prepared as part of the ESMF to  guide  the  resettlement  planning  process.  The  project‐level  ESMP  prepared  as  part  of  the  revised  ESMF identifies  sociotechnical  assistance  as  the  major  support  to  be  provided  under  the  project  to  address  the vulnerable groups.  

V. WORLD BANK GRIEVANCE REDRESS 

Page 22: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 13 of 38 

31. Communities  and  individuals  who  believe  that  they  are  adversely  affected  by  a  World  Bank  (WB) supported project may submit complaints to existing project‐level grievance redress mechanisms or the WB’s Grievance Redress Service (GRS). The GRS ensures that complaints received are promptly reviewed in order to address project‐related concerns. Project affected communities and individuals may submit their complaint to the WB’s independent Inspection Panel which determines whether harm occurred, or could occur, as a result of WB non‐compliance with its policies and procedures. Complaints may be submitted at any time after concerns have been brought directly to the World Bank's attention, and Bank Management has been given an opportunity to  respond. For  information on how to submit complaints  to  the World Bank’s corporate Grievance Redress Service  (GRS),  please  visit  http://www.worldbank.org/en/projects‐operations/products‐and‐services/grievance‐redress‐service. For information on how to submit complaints to the World Bank Inspection Panel, please visit www.inspectionpanel.org.  

Page 23: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 14 of 38 

        

VI    SUMMARY TABLE OF CHANGES 

 

  Changed  Not Changed 

Results Framework    ✔     

Components and Cost    ✔     

Safeguard Policies Triggered    ✔     

Implementing Agency        ✔ 

Project's Development Objectives        ✔ 

Loan Closing Date(s)        ✔ 

Cancellations Proposed        ✔ 

Reallocation between Disbursement Categories        ✔ 

Disbursements Arrangements        ✔ 

EA category        ✔ 

Legal Covenants        ✔ 

Institutional Arrangements        ✔ 

Procurement        ✔ 

Other Change(s)        ✔ 

  

VII   DETAILED CHANGE(S) 

   COMPONENTS 

Current Component Name  Current Cost (US$, millions) 

Action  Proposed Component Name 

Proposed Cost (US$, millions) 

Housing Reconstruction  472.50  Revised  Housing Reconstruction  669.50 

Disaster Risk Management Systems 

15.00    Disaster Risk Management Systems 

15.00 

Project Implementation Support 

12.50  Revised  Project Implementation Support 

15.50 

Contingency Emergency Response 

0.00    Contingency Emergency Response 

0.00 

Page 24: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 15 of 38 

TOTAL   500.00       700.00 

          Expected Disbursements (in US$)  DISBURSTBL 

Fiscal Year  Annual  Cumulative 

2015  0.00  0.00 

2016  20,000,000.00  20,000,000.00 

2017  35,000,000.00  55,000,000.00 

2018  55,000,000.00  110,000,000.00 

2019  120,000,000.00  230,000,000.00 

2020  130,000,000.00  360,000,000.00 

2021  130,000,000.00  490,000,000.00 

2022  130,000,000.00  620,000,000.00 

2023  80,000,000.00  700,000,000.00  

 SYSTEMATIC OPERATIONS RISK‐RATING TOOL (SORT) 

Risk Category  Latest ISR Rating  Current Rating  

Political and Governance   Substantial   Substantial   

Macroeconomic   Moderate   Moderate   

Sector Strategies and Policies   Moderate   Moderate   

Technical Design of Project or Program   Substantial   Substantial   

Institutional Capacity for Implementation and Sustainability 

 Substantial   Substantial   

Fiduciary   High   High   

Environment and Social   Substantial   Substantial   

Stakeholders   Substantial   Substantial   

Other         

Overall   Substantial   Substantial  

  Safguard_Table COMPLIANCE 

Page 25: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 16 of 38 

Change in Safeguard Policies Triggered 

Yes 

Safeguard Policies Triggered  Current  Proposed 

Environmental Assessment OP/BP 4.01  

Yes  Yes 

Performance Standards for Private Sector Activities OP/BP 4.03  

No  No 

Natural Habitats OP/BP 4.04  

Yes  Yes 

Forests OP/BP 4.36  

Yes  Yes 

Pest Management OP 4.09  

No  No 

Physical Cultural Resources OP/BP 4.11  

Yes  Yes 

Indigenous Peoples OP/BP 4.10  

Yes  Yes 

Involuntary Resettlement OP/BP 4.12  

Yes  Yes 

Safety of Dams OP/BP 4.37  

No  No 

Projects on International Waterways OP/BP 7.50  

No  No 

Projects in Disputed Areas OP/BP 7.60  

No  No 

    LEGAL COVENANTS2 

LEGAL COVENANTS – Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Sections and Description   OPS LEGAL CONVENANT CHILD NODATA No information available  Conditions 

   

Page 26: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 17 of 38

VIII. RESULTS FRAMEWORK AND MONITORING 

     

Results Framework COUNTRY: Nepal  

Second Additional Financing Earthquake Housing Reconstruction Project RESULT NO PDO Project Development Objective(s)  

The Project Development Objective (PDO) is to restore affected houses with multi‐hazard resistant core housing units in target areas and to enhance the government's ability to improve long‐term disaster resilience.

 

 Project Development Objective Indicators by Objectives/ Outcomes  

RESULT_FRAME_TBL_PDO       

Indicator Name  DLI  Baseline  End Target 

Restore affected houses with multi‐hazard resistant core housing units in targeted areas (Action: This Objective has been Revised) 

Households with resilient core housing reconstructed under the project (Number)     0.00  237,680.00 

Action: This indicator has been Revised  

Rationale:  

The target is revised in view of revised amount of financing. 

 

Out of which women headed households (Number)     0.00  61,797.00 

Action: This indicator has been Revised  

Rationale:  

Target is revised based on revised component allocation. 

 

Out of which women headed households (Number)     0.00  61,797.00 

Page 27: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 18 of 38

RESULT_FRAME_TBL_PDO       

Indicator Name  DLI  Baseline  End Target 

Action: This indicator has been Revised  

Rationale:  

Target is revised based on revised component allocation. 

 

Citizens made aware of earthquake resilient reconstruction (Number)     0.00  237,680.00 

Action: This indicator has been Revised  

Rationale:  

Target is revised. 

 

Enhance the Government's Ability to improve long‐term disaster resilience.  

Elected representatives and government officials of 32 earthquake affected districts are trained on disaster risk management and housing reconstruction with transfer of project records. (Number)  

  0.00  1,000.00 

Action: This indicator has been Revised    

Out of which, women elected representatives and officials of Local Level. (Number)  

  0.00  250.00 

Action: This indicator is New  

Rationale:  

 In ensuring inclusive DRM, enhancing DRM knowledge of women elected representatives and  women officials of local government is imperative. This will empower women in seeking the voice and agency in the policies and activities related to DRM so that women's different needs are recognized and addressed. 

  PDO Table SPACE 

 

Page 28: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 19 of 38

Intermediate Results Indicators by Components  

RESULT_FRAME_TBL_IO 

Indicator Name  DLI  Baseline  End Target 

Housing Reconstruction (Action: This Component has been Revised) 

Direct project beneficiaries (Number)     0.00  1,022,024.00 

Action: This indicator has been Revised    

Female beneficiaries (Percentage)     0.00  50.00 

Intended beneficiaries aware of project info. and project investments (%) (Percentage)  

  0.00  100.00 

Action: This indicator has been Revised    

Intended beneficiaries aware of project info. and project investments ‐ female (Number)  

  0.00  61,796.00 

Action: This indicator has been Revised    

Grievances registered related to delivery of project benefits addressed (%) (Percentage)  

  0.00  95.00 

Action: This indicator has been Revised    

Grievances related to delivery of project benefits that are addressed‐(number) (Number)  

  0.00  100,000.00 

Engineers and artisans trained in multi‐hazard resistant construction (Number)  

  9,319.00  12,000.00 

Action: This indicator has been Revised    

Page 29: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 20 of 38

RESULT_FRAME_TBL_IO 

Indicator Name  DLI  Baseline  End Target 

Women masons to be employed by the project in the provision of Socio‐Technical Assistance (Percentage)  

  0.00  10.00 

Action: This indicator is New  

Rationale:  

Masonry profession is where the gender gap is observed to be high.  In an effort to bridge the gender gap, the project will ensure that at least 10% of total mobile masons to be hired for Socio‐technical Assistance would be women.  

 

Employed women masons to be trained in Contract, Procurement and Logistics Management and Book‐keeping (Number)  

  0.00  95.00 

Action: This indicator is New  

Rationale:  

Capacity of employed women mobile masons will be further strengthened with  a number of training opportunities in contract and procurement management and book keeping to empower and encourage them in continuing the masonry profession beyond reconstruction. 

 

Disaster Risk Management Systems  

Structural Integrity of social infrastructure carried out across the country. (Number)  

  0.00  1.00 

Action: This indicator has been Revised    

 IO Table SPACE 

   

Monitoring & Evaluation Plan: PDO Indicators Mapped 

Indicator Name  Definition/Description  Frequency  Datasource Methodology for Data Collection 

Responsibility for Data Collection 

Households with resilient core housing reconstructed under the project 

Number completed houses of households that 

Daily  

Project's MIS Tablet‐based Data Digitization of Inspection 

CLPIU Building  

Page 30: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 21 of 38

received project financial and technical assistance, with seismic resilient features. 

carried‐out by Engineers.  

Out of which women headed households 

 Daily  

Project's MIS 

Tablet‐based Data Digitization of Inspection carried‐out by Engineers.  

CLPIU Building  

Out of which women headed households   Daily  

Project's MIS 

Tablet‐based Data Digitization of Inspection carried‐out by Engineers.  

CLPIU Building  

Citizens made aware of earthquake resilient reconstruction 

Number of participating household beneficiary. 

Daily  

Project's MIS 

Tablet‐based Data Digitization of Inspection carried‐out by Engineers.  

CLPIU Building  

Elected representatives and government officials of 32 earthquake affected districts are trained on disaster risk management and housing reconstruction with transfer of project records. 

NRA will carry out orientation training program of selected local governments' elected representatives and officials in batches, based on a concept note agreed by the Association. The program will also be used to transfer housing reconstruction record to concerned local 

NRA will submit quarterly updates.  

1. Monitoring Reports 2. Financial Reports 3. Third Party Monitoring Reports  

Data will be collected during regular implementation reviews.  

The Project Management Unit  

Page 31: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 22 of 38

governments. 

Out of which, women elected representatives and officials of Local Level. 

     Attendance list of participants.   

EHRP, PMU  

  ME PDO Table SPACE 

 

Monitoring & Evaluation Plan: Intermediate Results Indicators Mapped 

Indicator Name  Definition/Description  Frequency  Datasource Methodology for Data Collection 

Responsibility for Data Collection 

Direct project beneficiaries 

Direct beneficiaries are people or groups who directly derive benefits from an intervention (i.e., children who benefit from an immunization program; families that have a new piped water connection). Please note that this indicator requires supplemental information. Supplemental Value: Female beneficiaries (percentage). Based on the assessment and definition of direct project beneficiaries, specify what proportion of the direct project beneficiaries are female. This indicator is 

Daily  

Project's MIS  

Tablet‐based Data Digitization of Inspection carried‐out by Engineers.  

CLPIU Building  

Page 32: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 23 of 38

calculated as a percentage. 

Female beneficiaries 

Based on the assessment and definition of direct project beneficiaries, specify what percentage of the beneficiaries are female. 

       

Intended beneficiaries aware of project info. and project investments (%) 

This indicator intends to measure the effectiveness of consultation and communication mechanisms in terms of ensuring that information about the project and project supported investments have been communicated effectively. 

PMU Project's MIS  

Tablet‐based Data Digitization of Inspection carried‐out by Engineers.  

CLPIU Building  

Intended beneficiaries aware of project info. and project investments ‐ female 

This indicator intends to measure the effectiveness of consultation and communication mechanisms in terms of ensuring that information about the project and project supported investments have been communicated effectively. 

Daily  

Project's MIS  

Tablet‐based Data Digitization of Inspection carried‐out by Engineers.  

CLPIU Building  

Grievances registered related to delivery of project benefits addressed (%) 

This indicator measures the transparency and accountability mechanisms 

PMU Project's progress report, and 

GRM  

Daily  

Page 33: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 24 of 38

established by the project so the target beneficiaries have trust in the process and are willing to participate, and feel that their grievances are attended to promptly. It is understood that local sensitivities and tensions will not allow grievance or redress mechanisms to be established in all projects. 

GRM 

Grievances related to delivery of project benefits that are addressed‐(number) 

This indicator measures the transparency and accountability mechanisms established by the project so the target  beneficiaries have trust in the process and are willing to participate, and feel that their grievances are attended to promptly. It is understood that local sensitivities and tensions will not allow grievance or redress mechanisms to be established in all projects. 

Daily  

Project's MIS and Grievance Redressal Mechanism  

GRM  

CLPIU Grant Management and Local Infrastructure  

Engineers and artisans trained in multi‐hazard resistant construction 

Number of engineers and artisans that received training on multi‐hazard resilient housing 

Quarterly.  

CLPIU Building  

1. PMU's  Record 2. Implementation Reviews  

Project Management Unit  

Page 34: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 25 of 38

reconstruction. 

Women masons to be employed by the project in the provision of Socio‐Technical Assistance 

Socio‐technical Assistance team includes social mobilizers and mobile masons. 

 CLPIU Building/PMU  

   

Employed women masons to be trained in Contract, Procurement and Logistics Management and Book‐keeping 

Capacity of women mason will be further built, in contract , logistics and procurement management and book keeping to encourage in continuing masonry occupation beyond reconstruction. 

     CLPIU Building  

Structural Integrity of social infrastructure carried out across the country. 

Number of schools and health posts surveyed for structural integrity assessment. 

Monthly  

Project's progress report 

The concerned CLPIU Education will submit monthly status report.  

CLPIU Education  

  ME IO Table SPACE 

       

Page 35: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 26 of 38

Annex 1: Economic Analysis

1. The AF of  the project,  through  its different  components, will  provide both direct  and  indirect benefits  to  32  affected  districts  in  Nepal.  Direct  beneficiaries  include members  of  the  approximately 86,680  additional  households  in  the  targeted  areas,  whose  houses  were  destroyed/damaged  by  the earthquake. Among  those  receiving  social  assistance,  the most  vulnerable population will be  specially targeted to receive additional assistance.  

2. The EA for the AF follows the methods and assumptions used in the original project’s EA. For the EA of  the AF,  the major project component of US$236.40 million  for Housing Reconstruction  (US$197 million IDA credit and US$39.40 million in GoN’s counterpart funding) is examined. 

Housing Reconstruction 

3. Because of the AF, approximately 86,680 eligible households will have multi‐hazard resilient core housing units. A total of around 372,700 additional direct project beneficiaries will be safe from house collapse and potential death and injuries in case of future earthquakes.12 Many local construction workers will learn valuable construction skills. The local housing materials market will be active and help the local economy with multiplier effects.  

Costs Calculations 

4. For  the EA,  the  total  cost of Component 1 of  the project, building multi‐hazard  resilient  rural residential  houses,  is  considered.  Component  1  is  US$236.40  million  (US$197  million  IDA;  US$39.40 million GoN financing), which is 98.7 percent of the total Project costs. It is estimated that approximately 86,680 multi‐hazard resilient core housing units will be built using the additional funding.13 The cost is to be  disbursed  in  the  amounts  described  in  Table  1.1.  over  the  four‐year  period  from  2020  to  2023. Following the end of the project, the continued operating and maintenance costs of the project will be 1 percent of the overall costs. 

Table 1.1. Distribution of Project Costs 

  Project Duration (Years)     

  2020  2021  2022  2023  Overall 

Costs (US$, millions)  70  70  70  26.4  236.4 

Number of housing units built  25,135  25,135  25,135  11,275  86,680 

Counterfactual Benefit Calculations without the Project 

5. To understand the counterfactual, it is assumed that in the absence of the project, no new houses will be built. In other words, the potential beneficiaries will continue to live in temporary structures that have  no  significant  shadow  rental  value.  The  shadow  rental  value  of  housing  is  the  imputed welfare benefit of living in a house. Another way to look at it is to consider the absence of shadow rental value as an implicit cost of living in temporary structures. Thus, there will be no costs and benefits in the absence of the project.  

12 According to the 2010 household survey of Nepal, the average rural household size is five members per household. 13 As a result of exchange rate depreciation, the housing subsidy provided under this AF is expected to be US$2,750, instead of US$3,000 as originally assumed.

Page 36: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 27 of 38

Economic Analysis 

6. The main benefit  component of  this project  is  the shadow annualized rental  income from the newly built multi‐hazard resilient housing units, which the approximate 86,680 beneficiary households will  live  in.  It  is  assumed  that  with  the  use  of  improved  construction  methods  and  materials  the reconstructed houses will be significantly more valuable than their old homes. 

7. The EA focuses on the single benefit of shadow annualized rental income from the multi‐hazard resilient housing to the household receiving the housing grant. Other benefits such as the prevention of death  and  injuries  in  case  of  earthquake,  and  poverty  alleviation  through  livelihood  support  are  not considered  in  this  EA.  Therefore,  the  resulting  quantitative  indicators  of  economic  benefits  from  the project are underestimated.  

8. The AF benefits are based on the assumption in the original project’s EA: 

The average value of a multi‐hazard resilient new home will be US$15,000.14 

The value of home to rent ratio will be 20.15 

For the benefit calculations, the new homes will have a useful life of 20 years16 beginning the year after the unit was built. 

The discount rate is 10 percent.17 

Returns to Investments 

9. Based on the assumptions listed above, the benefit of living in multi‐hazard resilient houses for approximately  86,680  eligible  households  in  terms  of  shadow  rental  income  for  the  next  20  years  is considered.  Under  this  scenario,  only  the  benefit  of  living  in  homes  is  considered  and  the  additional benefits  of  prevention  of  potential  death  and  injuries  and  loss  of  other  assets  resulting  from  future earthquakes are ignored. 

10. Using similar assumptions for the EA of the proposed AF, IRR of 26.8 percent, NPV of US$490.5 million,  and  BCR  of  2.2  for  the  proposed  AF’s  housing  reconstruction  component  of  total  US$236.40 million ($197 million from IDA and $39.40 million GoN counterpart financing) were found. The higher IRRs stem from costs savings  resulting  from the exchange rate depreciation  leading  to more housing grant beneficiaries and higher share of investment allocated towards housing reconstruction component. Both the IRR and NPV of the benefits to the affected households show that the AF is economically viable by this conservative estimate. 

Conclusion 

14 The average value of a pre‐earthquake rural housing unit was US$7000 in current prices, based on the 2010 household survey. It is assumed that these old houses used construction methods and materials that were not multi‐hazard resilient. Note that the value of a house includes the value of the land and its location value such as access to market. New houses with improved construction and materials are assumed to be significantly more valuable than the old houses. 15 The house price to rent ratio is the price of the house divided by the annual rent. The estimated house price to rent ratio in Nepal was 35 for rural areas and 81 for urban areas based on the 2010 household survey data. These values are exceptionally high compared to the ratio in the United States. A more conservative ratio of 20 is used. 16 The common useful life of 20 years for infrastructure lending projects is used. 17 The standard discount rate is 12 percent. However, due to the humanitarian nature of the project, use a slightly lower social discount rate is used. 

Page 37: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 28 of 38

11. Based  on  the  qualitative  analysis  of  the  avoided  deaths,  injuries,  and  loss  of  assets  from  the resilient  housing  reconstruction  and  the  livelihood  support  and  the  calculated  IRRs  for  the  shadow annualized rental income from the multi‐hazard resilient houses, the AF is considered economically viable.  

References 

Original Project Appraisal Document of EHRP 

Nepal LSMS Survey 2010 

   

Page 38: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 29 of 38

Annex‐2: Procurement Arrangements   A. Project Procurement: The World Bank Procurement Regulations for IPF Borrowers, July 2016 (revised 

November 2017 and August 2018), will apply for the procurement using the World Bank funds from 

the AF2. However, the procurement arrangements for the original financing will remain unchanged. 

Given that the IDA disbursements under Component 1 are made against the agreed procedure for 

‘Housing Grants’, no procurement is involved under this component and the Procurement Regulations 

will not apply to this component. However, project implementation support will involve procurement 

activities, mainly selection of consulting firms and individual consultants and some procurement of 

goods. Procurement under these components will be carried out in accordance with the Procurement 

Regulations and the provisions stipulated in the Financing Agreement. The procurement of goods and 

consulting  services  as  agreed  in  the  Project  Procurement  Strategy  for  Development  (PPSD)  and 

Procurement  Plan may be  carried out  using national  competitive  bidding  as  per  the GoN’s  Public 

Procurement  Act  of  2007  and  regulations  thereunder,  along  with  the  additional  IDA‐prescribed 

caveats.  The NRA  is  the primary  responsible agency  for project  implementation and  for providing 

overall coordination and guidance to other implementing agencies. The NRA has gained experience 

in  managing  procurement  of  the  ongoing  EHRP.  The  current  Project  Operations  Manual,  with 

necessary update, will be followed for detailed guidance on project procurement management. To 

enhance and maintain its procurement management capacity, it was agreed that the NRA needs to 

engage a procurement consultant throughout the implementation period of the project to expedite 

the procurement process and ensure the quality of procurement carried out by the NRA. 

B: Project Procurement Strategy for Development 

Country  Nepal 

Full Project Name  EARTHQUAKE HOUSING RECONSTRUCTION PROJECT – 2nd Additional Financing 

Total Finance (US$)  200 million 

Project Number  P170565 

 This AF2 of EHRP will primarily fund for housing grants (US$197 million out of US$200) covering 

about 86,680 beneficiaries. US$ 3 million has been allocated for TA and incremental operating costs. 

No major procurement has been envisaged under this AF. A very minor procurement activities may 

be required for contracting some consulting firms, individual consultants, procurement of goods of 

office operating nature and non‐consulting services. These categories and volume of procurement 

can be acquired easily from the local market. The main procurement strategy for this AF remains the 

same as per the PPSD for EHRP‐AF (P163593).  

 

Page 39: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 30 of 38

Annex‐3: Financial Management   1. The FM arrangements under the ongoing project have been re‐assessed and found satisfactory. As such, the  same arrangements will  apply  to  the AF2 as well.  The detailed  arrangements  including enhanced internal controls are detailed below.   2.  Implementation Arrangements  ‐ The  implementing agency will  remain the National Reconstruction Authority. A Project Management Unit within NRA, headed by a Project Coordinator, will carry out the day to day project activities along with three central level PIUs – CLPIU‐GMaLI, CLPIU‐Building and CLPIU‐Education, and the District Level PIUs. All the PIUs are under the administrative control of the PMU.   3. FM staffing ‐ FM staffing is adequate at the NRA, CLPIUs and DLPIUs. The government‐deputed finance staff are supported by required level of FM consultants. No additional staffing is envisaged at this stage. Hands on support and training will be provided by the Bank as needed. FM Consultants would also cover the 18 districts to be additionally covered by the AF 2. The staffing structure is as below:  

Note: CLPIU‐Education has no activities under this project except for carrying out the Structural Integrity Assessment, hence no FM staff have been assigned to this unit.   4. Budgeting  ‐  The project  follows  the government process  for budget preparation and approval.  The DLPIUs, CLPIUs and NRA prepare their detailed budgets using the LMBIS (Line Ministry Budget Information system). The NRA‐PMU will thereafter consolidate the annual work program and budget for the project and submit to MoF for approval. Once the budget is approved, the approved budget is reflected in the MoF FMIS, and  is also uploaded to TABUCS (project accounting software) by NRA‐PMU. The budget  is 

NRA-PMU  

Accounts Officer } Accountant } Deputed from govt 3 financial consultants 1 banking coordination consultant 

CLPIU – GMaLI  

2 FM staff (deputed from govt) 1 FM consultant 

CLPIU – Building  

2 FM staff (deputed from govt) 1 FM consultant 

DLPIUs (32 districts)  

1 FM consultant in each of 14 focus districts 

DLPIUs (20 districts)  1 FM staff in each PIU (deputed) 

Page 40: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 31 of 38

detailed, and is broken down by funding source, spending units (cost centers) and activity code. There is a midyear budget review process where budget alignments can be requested.    5. Accounting and Reporting – Cash basis of accounting is used across the government. At the central level, MoF has FMIS (Financial Management Information System) where all disbursements are recorded. All payments processed by DTCOs (District Treasury Control Offices) through the Treasury Single Account are automatically reflected in FMIS. At the project level, the following is maintained by NRA‐PMU:  

TABUCS  (Transaction Accounting  and Budget Control  System) Accounting  Software –  This  is  a web‐based system with access provided to all cost centers (NRA, CLPIUs and DLPIUs). Transactions are recorded in the system at the point they originate and consolidated at NRA‐PMU. 

Excel records – Additional subsidiary books are records at the overall project level are maintained in excel by NRA‐PMU. These include general ledger, grant/credit register, withdrawal register, and bank book by funding source 

MIS  (Management  Information System) – This  is  a web‐based  system maintained  for Housing Grants with access down  to  the district  level.  The MIS captures detailed  information covering beneficiary data, Participation Agreements, tranche payments, supporting documents for each tranche, inspection information and third‐party verification. 

 6.  All  original  supporting  documents  for  project  expenditures  will  be  maintained  at  the  source  cost centers. In addition, for Housing Grants, all relevant supporting documents related to tranche releases and inspections will be digitized and uploaded to the MIS system.   7. Trimester (4 monthly) Interim Unaudited Financial Reports will be required under the project, in form and substance currently being followed. The IUFRs will be due within 45 days from the end of the reporting period. NRA‐PMU will prepare consolidated project IUFRs based on information from TABUCS, MIS and MoF FMIS. The IUFRs will continue to provide financial information segregated for each funding source.   8. Funds Flow and Disbursements – The funds flow and disbursement arrangements as designed under the original project is operating well. Under the ongoing project, there are two Designated Accounts, one for each IDA Credit.  In addition, a DA is also maintained under the MDTF financing. This will continue. Across  all  projects  in  Nepal,  the  government  pre‐finances  eligible  project  expenditures.  The reimbursement  mechanism  is  used,  whereby  the  government  reimburses  itself  from  the  Designated Accounts and documents the expenditures based on IUFRs. Mandatory Direct Payments (MDP) will be used for applicable contracts which will be identified and included in the procurement plan. Arrangements are in place at the PIU level to ensure only MDP will be used for such identified contracts. Expenditures under Category 1 are expected to be booked after  the allocations under original  financing and AF are booked.   9. Under  the proposed AF2,  no new DA will  be  established. Government will  continue  to pre‐finance project expenditures and eligible expenditures will be claimed from IDA by submitting reimbursement applications. The project coordinator and accounts officer will be authorized signatory for claiming from IDA  and  managing  funds  in  the  existing  DAs.  The  project  will  continue  to  follow  output  based disbursements  mechanism,  whereby  the  Housing  Grants  will  be  included  in  IUFRs  based  on  output verification. 

Page 41: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 32 of 38

- Documented with the World Bank against the DA advances under the current two IDA Credits and the MDTF.  

- Claimed from the World Bank through submission of reimbursement applications under the new IDA Credit for AF2.  

 10. Payments requests for Housing Grants as well as other expenditures will be processed by the cost centers through their respective DTCOs whose systems maintain disaggregated information for individual IDA sources and MDTF RETF. All payments will be made through bank transfers and cheques. Specifically, for Housing Grants, the following procedure will be followed.  11.  DLPIUs  will  request  DTCOs  to  issue  cheques  to  concerned  banks  for  making  payments  to  the beneficiaries’  bank  accounts.  The  concerned  banks,  on  receipt  of  cheques  from  DLPIUs,  will  make payments  to  the  beneficiaries’  bank  accounts  in  various  NRB  licensed  banks  or  acceptable  financial institutions. The bank accounts should have been authorized by beneficiaries and instructed by DLPIUs. The GoN will engage the services of banks or financial institutions, including a microfinance institution, or another entity having the capacity to provide the payment services in accordance with criteria set forth in  the POM. GoN will  enter  into  service agreements with  the payment  service providers  in a manner acceptable to the Bank. Detailed procedures are documented in the Operations Manual.   The following will be the categories of eligible expenditure: 

Category  Amount (in USD)  Percentage of Expenditures to be Financed 

(inclusive of taxes) 

(1) Goods, works, non‐consulting services, consulting services, Incremental Operating Costs, and Training and Workshops  

3,000,000  100% 

(2) Housing Grants   197,000,000  83% of amounts disbursed 

TOTAL AMOUNT  200,000,000   

  12. The Credit will have a provision  for  retroactive  financing  for approx. US$80 million  (40 percent of Credit)  to  cover  eligible payments made within one  year prior  to  the  signing date.  There will  also  be counterpart  funding  from Government of Nepal  to  the  tune of US$39.40 million,  this will  cover all 1st tranche payments made to identified beneficiaries prior to the retroactive financing period.   13.  Internal  Controls–  The  internal  control  mechanism  is  reasonably  robust  and  continues  to  be strengthened. There is proper segregation of duties and final approval for expenditures is given by the head of the respective cost enter. The preparation of payment request, check and approval processes are automated in TABUCS beginning FY 2019/2020. Periodic reconciliation is done by the cost centers as well as NRA‐PMU. The cost centers carry out monthly reconciliation of their expenditures with DTCO records, and also carry out annual reconciliation with FMIS. In addition, NRA‐PMU reconciles TABUCS records with FCGO records on a monthly basis. All accounting and reporting is done in a segregated manner for each funding source.   

Page 42: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 33 of 38

14. The DTCOs will conduct internal audits on trimester basis of the cost centers. The control processes in place at various stages for Housing Grants are covered in detail in the Operations Manual. Housing Grants are considered eligible expenditures only after output verification, and thereafter can be included in the IUFRs  and  documented/claimed  with/from  the  World  Bank.  All  payments  are  made  through  bank transfers and are  fully  traceable  (from government TSA  to beneficiaries’ bank accounts  in commercial banks).  It  is  supported  by  the  attribution  of  a  unique  beneficiary  identification  number  which  is  the continuous reference across the expenditure cycle. All supporting documents for tranche releases and the three inspections (the 3rd and final inspection being the output verification) including relevant forms and pictures are scanned and digitized  in the MIS. This enables  transparency, completeness and facilitates review  at  the  central  level.  Additional  layer  of  assurance  is  provided  through  the  TPM  arrangements engaged by the PMU as well as the Bank.   15. The bi‐annual FM supervision will focus in detail on Housing Grants to review funds withdrawn from IDA against Housing Grants paid by the government, expenditures documented, availability of supporting documents on a sample basis, time lag in digitizing supporting documents and documenting expenditures, and steps being taken to reduce the time lag.   16. External Audit ‐ The Office of the Auditor General (OAG) will conduct external audit of the project. NRA will prepare consolidated project financial statements for audit based on information generated from TABUCS  and  expenditure  reports  from  CLPIUs  and  DLPIUs  (and  reconciled  with  FMIS).  The  audited financial statements are due to be submitted to the World Bank within nine months from the end of each fiscal year. All records (including contracts, orders, invoices, bills, receipts and other relevant documents evidencing all expenditures) will be maintained properly at the respective cost centers to enable proper document trail and facilitate the audit. Bank's representatives will also have access to the records for the purpose of examination.   17.  There  are  no  unresolved  ineligible  expenditures  nor  overdue  audit  reports  under  projects implemented by National Reconstruction Authority.    18.  Fiduciary  Risk  ‐  Despite  the  recent  improvements  in  internal  controls  and  FM  performance,  the fiduciary risk is rated High given the large scope of the reconstruction program and capacity constraints in FM. Bank will follow a risk‐based approach to FM supervision to address and mitigate key FM risks. The FM section of the operations manual will be updated periodically as the need arises. The fiduciary risk will be reviewed during the implementation support missions and adjusted as necessary.   19. Supervision Plan ‐ Bank FM team will provide enhanced hands‐on implementation support, in addition to the bi‐annual reviews that will include field visits and transaction review as deemed necessary. Periodic review meetings  in between missions will also be held  to address any emerging FM  issues  in a  timely manner and to ensure sustained satisfactory FM performance.  20. Disclosure of  information: Project would be  required  to disclose  the  following:  i) Audited Project Financial Statements; ii) list of eligible beneficiaries; and, iii) details of major contracts.  

   

Page 43: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 34 of 38

Housing Grant Tranche Payment Process Flow   

   

Page 44: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 35 of 38

Annex 4: Targeted support towards improving gender outcomes 

1. The EHRP and EHRP MDTF have been providing technical assistance and advisory support to NRA in developing  various  policies,  guidelines  and  standards  related  to  reconstruction  with  gender‐sensitive approaches considered within the EHRP as well as in the umbrella Housing Reconstruction Program of the Government  of  Nepal.  Over  the  implementation  of  the  program,  several  positive  trends  have  been observed, not necessarily with IDA funding, on increased participation of women in technical jobs, social mobilization, financial access and inclusion, skill development/upgradation activities, and joint ownership of houses in the cases where houses are being relocated with additional GoN assistance. Some of these areas are illustrated below:  

a. Prioritizing women beneficiaries. By  the virtue of  the housing reconstruction program design, there are several ways the women beneficiaries have been prioritized. For example, single women are prioritized as beneficiaries under the On‐the Job Trainings (OJT) for masons, a 45‐day course tailored to train new masons for safer construction, wherein a new house is fully constructed as a model  during  the  training  period.  Recipients  of  the model  house  procure  the  construction materials but receive free labor and technical support through the construction. CLPIU Building has facilitated the construction of 153 houses belonging to single women. 

b. Increased participation in reconstruction workforce: Conventionally, the jobs in construction and allied  sectors  in  Nepal  have  a  very  limited  participation  of  women  as  engineers,  masons, electricians,  carpenters  and  plumbers,  mainly  due  to  sociocultural  norms.  As  per  the  Nepal Engineering Council, the percentage of women engineers who are licensed to work professionally at national level is only 12.5 percent. However, there has been a marked uptick in the share of women  engaged  in  housing  reconstruction  program.  For  example,  of  the  total  number  of engineers hired to provide technical assistance and conduct quality inspection of reconstructed houses, 18 percent have been women. This is quite significant since majority of these engineers were  deployed  in  field  locations.  Moreover,  80  percent  of  social  mobilizers  hired  under  the program and 15 percent recipients of construction related trainings are women.  

c. Financial access and inclusion. The Earthquake Housing Damage Characteristics Survey (EHDC; co‐financed by MDTF), conducted in 2015 after the earthquake recorded that only 21 percent of 1,036,478  households  surveyed  had  bank  accounts,  of  which  only  5  percent  bank  accounts belonged to women. The project’s mandatory provision of transferring housing grants directly to beneficiary  bank  accounts  facilitated  the  opening  of  bank  account  for  each  participating household. As per the NRA records, 30 percent of beneficiary bank accounts belong to women, thus recording six times increase in women bank account holders. This provision has introduced a large number of women to formal banking and financing with enhanced financial literacy. The 2018  Gender  Equality  and  Social  Inclusion  (GESI)  audit  observed  that  women  feel  more empowered due to their involvement in housing reconstruction and interaction with government officials and banks.  

d. Joint  ownership  by  women  under  relocation  assistance:  For  the  destroyed  houses  requiring relocation  due  to  hazard‐prone  location,  the  Government’s  Housing  Reconstruction  Program provides additional grant of NPR 200,000 for alternative land purchase for new safer construction of house under the policy “Land Purchase Standards for the relocation of earthquake affected people, 2017”. This policy has a mandatory provision of joint land ownership of both husband and 

Page 45: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 36 of 38

wife.  So  far,  2,157  households  deemed  eligible  for  relocation  have  purchased  land with  joint ownership and this provision will also ensure the joint ownership of houses constructed. 

e. Supporting  Economic  Recovery  through  Women‐led  Enterprises:  During  the  EHRP implementation, the World Bank has conducted two studies to examine economic recovery and entrepreneurship development opportunities in Nepal’s post‐earthquake reconstruction context and  construction  and  allied  sectors.  The  recommendations  of  these  studies  have  potential  to inform or scale‐up the NRA and other Government agencies’ efforts to support the earthquake affected  people  in  the  economic  recovery.  After  the  earthquake,  the  NRA  had  facilitated introduction  of  financing  schemes  by  Nepal  Rashtra  Bank,  Nepal’s  central  bank,  to  promote entrepreneurship among youth, women and marginalized communities. One of such concessional loan  schemes  provides  targeted  support  to  women  for  establishing  enterprises.  So  far,  529 women have availed these concessional loans amounting approximately US$ 3.25 million. 

2. While  these  have  been  invaluable  direct  and  indirect  co‐benefits  of  the  EHRP,  AF  and MDTF,  the proposed second AF aims at providing targeted support to  leverage and improve some of the gender‐specific  outcomes  in  view  of  the  gender  gaps  in  employment  in  the  construction  and  allied  sectors. According  to  data  from  NLSS  Wave  3  (2010/2011),  29  percent  of  male  wage  earners  work  in  the construction sector, compared to only 5.6 percent of female wage earners. Female wage earners in the construction sector work fewer days than men (on average 62 versus 112 days, annually) and earn less annual income (7,800 versus 21,000 NRs). Although the number of women in engineering and technical jobs has  increased during the  implementation of  this  large‐scale reconstruction program, a downward trend is likely once the program concludes and associated jobs in public sector reduces. However, with increased awareness on the need for earthquake‐resistant design and construction, there remains a scope of increased private sector jobs where the women engineers and artisans, trained and experienced during the earthquake reconstruction, would have opportunities.  

3. In view of the above, below are the areas that the proposed AF2 will target to achieve improved gender‐specific outcomes:  

a. Improved participation in skill development trainings and access to jobs. The AF2 will support women  technical  staff  (engineers,  sub‐engineers  and  assistant  sub‐engineers)  in  enhancing technical skills and improving job opportunities in the construction and allied sectors by targeted capacity  building  activities  on  earthquake‐resistant  construction  techniques  and  design, vocational trainings on masonry, entrepreneurship development etc.  

b. Ensuring a share of employment in socio‐technical assistance: NRA is in the process of recruiting 200 social mobilizers and 988 mobile masons under EHRP, wherein the project will ensure that at least  10  percent  of  mobile  masons  being  employed  are  women.  Women’s  participation  in masonry  was  almost  non‐existent  before  the  2015  earthquakes.  Nepal’s  large‐scale reconstruction program has provided unprecedented opportunity  for women to upgrade their skills and improve income potential in the work areas usually dominated by men. The provision to employ women mobile masons through the project would ensure share of employment in this male‐dominated  area  of  work.  Moreover,  government  employment  is  considered  a  highly respected occupation within the Nepali society, and the planned employment of women by NRA would convey a strong message to the communities in changing deep‐rooted socio‐cultural norms and  in  breaking  gender  stereotype.  These  recruited  mobile  masons,  together  with  social mobilizers  will  support  the  beneficiaries  in  expediting  resilient  reconstruction.  The  tailored 

Page 46: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 37 of 38

orientation/induction trainings provided to new employees will also include modules on contract management, project management and book keeping, procurement and logistics, and assessing the differentiated needs of persons with disabilities. These modules will  further enhance their capability  to manage  the construction contracts and projects and will equip  them to continue their skilled masonry occupations beyond the reconstruction phase.  

c. Ensuring  a  share  of  women  elected  officials  and  local  government  officials  in  Disaster  Risk Management and reconstruction orientation: The NRA is planning to carry out an orientation training program of targeted local governments' elected representatives and officials in batches, as per  the  third PDO  indicator of  the Project  towards  ‘Enhancing  the Government's Ability  to improve  long‐term  disaster  resilience’.  This  activity  will  also  facilitate  the  transfer  housing reconstruction records and systems to concerned local governments. The proposed AF2 will add a  new  Intermediate  Results  Indicator  under  this  PDO  indicator  to  ensure  that  25  percent  of elected representatives and government officials to be oriented on disaster risk management and housing reconstruction with transfer of Project records will be women. 

Proposed activities and indicators for gender‐specific outcomes:  

Activity/indicator  Baseline  Target 

10  percent  women employed as mobile masons under STA  

0*   At  least  98  women mobile  masons  employed  under  the Project.  

Tailored vocational and skill/capacity development trainings for women engineers and masons conducted  

0  1. At least 250 women masons/artisans trained on resilient construction and related skills such as safer masonry techniques using local materials and following MRT guidelines in construction; 

2. At least 250 women engineers/technical staff trained on earthquake‐resistant building design and construction, applying NBC guidelines in construction, contract and project management, procurement and logistics, approaches for universal access for disabled people, and innovative use of local building materials and Nepal’s heritage‐sensitive designs.   

New Intermediate Results Indicator: 

Existing PDO Indicator 

Activity/indicator  Baseline  Target 

Elected representatives and government officials given orientation on disaster risk management and housing reconstruction with transfer of project records. (Number)  

0.00  1,000.00 

New Intermediate Results Indicator 

Out of which, the number of  0.00  250.00 

Page 47: The World Bankdocuments.worldbank.org/curated/en/741541579316456847/...HRP Housing Reconstruction Program IPF Investment Project Financing IRR Internal Rate of Return IUFR Interim

The World Bank Second Additional Financing Earthquake Housing Reconstruction Project (P170565)

Page 38 of 38

women elected representatives and government officials (Number)  

* While this indicator aims at narrowing the gender gap persisting in skilled labor such as trained masons, in view of the lack of precise data on the gender gap as well as no mobile masons were recruited under the Project by NRA, a baseline has been proposed as 0, a starting point for employing and training women masons under the IDA financing. A detailed baseline and contribution towards bridging gender gap will be worked out during implementation. Once more data is available, this target will also be reviewed during implementation.