THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
THEMIS
Mission Assurance Critical Design Review
Ron Jackson
University of California - Berkeley
June 14-18, 2004
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
THEMIS Mission Assurance Team
• Ron Jackson Mission Assurance Manager
• Jorg FisherQuality Assurance Engineer
• Chris Scholz Quality Control Engineer
• Tom Clemons Quality Control Technician
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
Quality Assurance Flowdown
• UCB-PAIP – released – Pending approval by GSFC
• Swales PAIP – released – Approved by UCB• FGM/TUB PAIP – released – Approved by UCB• SCM/CETP PAIP – released – Approved by UCB• All other vendors - Purchase order Flowdown
Instrument Mission Assurance Requirements Document (MAR) was released on June 25, 2002.
UCB responded with a Performance Assurance Implementation Plan (PAIP):
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
Responsibilities of Quality Assurance
1.) Review and report on: a) Evaluate/Audit contractors facilities for the ability to
consistently produce quality flight hardware dailyb) Equipment calibration, temperature and humidity monitorsc) Clean room controlsd) Compliance to ESD requirementse) Workmanship procedures/processesf) Material handling and shelf life material storageg) Data packages and logbooksh) Nonconformance reporting / Problem reportsi) Assembly instruction / BOMj) Personnel training and certification to NASA standardsk) Part/Materials Alert Status
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
Responsibilities of Quality Assurance
2.) Support integration and test activities: a) Verify test set ups at board/instrument and
spacecraft levelsb) Monitor thermal testing at Box/instrument and
spacecraft levelsc) Witness vibration testing at instrument and
spacecraft levelsd) Verify magnetics testing at instrument levelse) All European suppliers – UCB shall review
Acceptance Package Data / Travelers and inspect component/Box upon delivery to U.S.
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
Responsibilities of Quality Assurance 3.) Provide electrical and mechanical inspections but not limited to:
a) Incoming materialsb) Solder workmanship, through hole and
SMT methods (verify coupon acceptance)c) Conformal coating and staking applicationsd) Witness board or Box closuree) Wire harness build, continuity test, Hi-pot
testing and routingf) Configuration verification, as designed vs.
as built
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
Contamination Control
• UCB Contamination Control– Class 100k clean room– Air particle count will be monitored– All flight hardware will be placed in clean bags
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
Software Assurance
• IV &V (IDPU & BAU)– To review software code– Develop metrics (Software risk assessment)– All software problems will be tracked on problem
reports– All software changes will be under configuration
review
• Probe Bus– Under UCB configuration management review– Software problems reports provided to UCB
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
Responsibilities of Quality Assurance
4.) Communications: a) Provide both written and verbal reports to
THEMIS project management – monthly
b) Participate in program telecons - as required
c) Problem/failure reporting may be informal up to the time of integration with flight hardware
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
THEMIS Parts Requirements
• 311- INST-001, Level 3– Parts in compliance with 311-INST-001, Level 3 requirements
and Standard Parts.– Use PPL 21 preferred parts, design permitting.
• PIND, per Mil-STD-750 and Mil-STD-883, required for cavity devices.– Impose on manufacture, if possible.– When needed, have DESC approved test facility perform
testing.• CSI and/or DPA for complex or known problem devices.
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
THEMIS Parts Requirements (continued)• Non-standard EEE parts will require at a minimum: PEM
– DPA, Preconditioning, HAST, CSAM• Radiation Testing
– Total Ionizing Dose Requirement 66 Krads (si)• Review existing test data from GSFC, JPL & Manufacturer• Review NASA “where used” historical data
– Parts o.k. to use if data and/or orbit requirements equals or exceeds THEMIS
• When needed, will perform Cobalt 60 TID testing– Single Event Effects: use existing data or historical use similarity
• Whenever possible, designers will use latchup immune devices• Latchup requirements 37mev• Exceptions are handled on case by case basis with THEMIS Project Office
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
THEMIS EEE Parts List• UCB QA will maintain EEE Parts Identification List (PIL)
• PIL will contain
– Manufacturer’s generic part number
– Military part number or SCD number
– Manufacturer(s)
– Where used (unique assembly) / Quantity used
– Quantity ordered
– Lot/Date Code
– Radiation status (TID / SEL)
– Project Approval Status
– Alert status
– Comments
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
THEMIS EEE Parts List (continued)• Parts will be procured to an approved Parts List
– Schedule permitting, Berkeley will do common buy.– Procurement of devices will be based upon design Engineers
Confidence-of-use factor of 70%.• Unique, high dollar items will be at 90% - 100% Confidence
Level– Minimum Attrition / Spares factor of 20% - 30% will be applied
to flight procurement quantities. Standard devices will have higher spares’ factor.
– Schedule and Cost permitting, Engineering test units will use flight qualified part. Especially where minimum buy quantities are imposed.
• ETU and Flight units– Procurements will run concurrently
• Flowdown PAIP requirements on subcontractors.
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
THEMIS EEE Parts List (continued)Parts Control Board (PCB)
• PCB members: THEMIS QA, Parts Engineer (GSFC), design Engineer and THEMIS – Berkeley Project Manger, or representative.
• PCB shall review EEE part for:– Testing, Screening and Qualification requirements– Alerts– Review non-standard parts requirements
• PCB will disposition EEE parts failures and nonconformance issues.
• UCB QA will coordinate PCB parts issues with GSFC Flight Assurance Manager, or his representative.
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
GIDEP Alert Review
• Microcircuits- 41 ea. Checked ok- 1 ea. Checked bad
• Semiconductor Devices– 49 ea. Checked ok– 1 ea. Checked bad
• Resistors/Capacitors– 31 ea. Checked ok
• Connectors– 6 ea. Checked ok
• Wire/Harness– 4 ea. Checked ok
• Misc. Materials– 0 ea. Checked
• Mechanical Parts– 0 ea. Checked
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
Parts Issues
EEE parts Alerts
Actel – FPGAIn-rush current problem
JANTXV1N5711-1ESD /Lead handling problem
Parts at up- screening
CA3080A @ GSFC
OP462HRU @ GSFC
LTC1604 @ GSFC
2N6519 @ GSFC
PT100 @ GSFC
AD5544 @ WYLE
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
THEMIS Parts Lists Status
Assembly List Developer Status Comments
EFI,SCM,FGE,PCB,LVPS,
DFB,BEB,DCB,ETC,ESA,SST
UCB Parts Status
University of California
In-Review at GSFC
Parts Control Board in-process
Probe,
Probe CarrierSwales Parts Status
Swales In-Review at UCB
Parts list to be submitted to GSFC for review
THEMIS Mission CDR JacksonUCB, June 14-18, 2004
Critical Design Review
THEMIS Materials Lists Status
Assembly List Developer Status Comments
EFI,SCM,FGE,PCB,LVPS,
DFB,BEB,DCB,ETC,ESA,SST
UCB Material Status
University of California
In-Review at GSFC
None
Probe,
Probe CarrierSwales Material Status
Swales In-Review at UCB
Material list to be submitted to GSFC for review