Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
69th Annual KU Environmental Engineering Conference
Thermal Hydrolysis – The Next Generation
Dustin Craig, P.E.
Environmental Engineer CDM Smith
Matt Bond, P.E,
Chief Engineering Officer
KC Water
69th Annual KU Environmental Engineering Conference
Agenda
Introduction to Thermal Hydrolysis (THP)
DC Water – 1st THP Installation
Startup Methodology
Seeding and Ramp Up
Commissioning Findings
KC Water – Blue River Biosolids Facility Project
69th Annual KU Environmental Engineering Conference
Thermal Hydrolysis – Background and History
BEFORE AFTER
Thermal Hydrolysis (THP) is a process by which sludge is heated and pressurized with the purpose of reducing organic
solids to make them more readily biodegradable….
In other words, it’s a pressure cooker.
69th Annual KU Environmental Engineering Conference
THP System Overview
To Dewatering
Thickened Primary Sludge
Screening Pre-Dewatering
Cake Storage
THPHEX
AnaerobicDigestion
Blending
ThickenedWAS
69th Annual KU Environmental Engineering Conference
Why Consider THP?
▪ Increase Capacity and Improved Performance of Digesters
Without THP With THP
AnaerobicDigestion
AnaerobicDigestion
AnaerobicDigestion
AnaerobicDigestion
AnaerobicDigestion
AnaerobicDigestion
Typical Mesophilic Digester
THP Mesophilic Digester
5%-6% Feed Solids ~10% Feed Solids
~20 day SRT 12 – 15 day SRT
40% to 50% VSR (WAS/PS dependent)
60% to 65% VSR
Class B Biosolids Class A Biosolids
69th Annual KU Environmental Engineering Conference
Why THP?
▪ Class A biosolids
▪ Increased downstream processing capacity
▪ Increased VSR and biogas▪ Projected 10–15% VSR
increase▪ Reduced digested solids
production▪ Potential energy neutrality
▪ Increased cake solids content▪ 10% increase
▪ Reduced digester foaming...and reduced odor
Without THP With THP
69th Annual KU Environmental Engineering Conference
Best Fits for THP
▪ Digestion capacity expansion
▪ New digester implementation
▪ Excessive hauling costs
▪ Class B limitations on land application
▪ Elimination of landfill options
▪ Agricultural demand for class A biosolids
▪ High electrical cost areas
69th Annual KU Environmental Engineering Conference
Digester Settling
1 minute 90 minutes 4 hours
69th Annual KU Environmental Engineering Conference
Hydrolyzed Sludge Settling
1 minute 90 minutes 28 hours
69th Annual KU Environmental Engineering Conference
Lower Odor of THP Biosolids Could Open Product Use Opportunities
25,000
15,000
10,000
5,000
0
20,000
Mea
n H
ead
spac
e D
etec
tio
n T
hre
sho
ld
(dilu
tio
ns
to t
hre
sho
ld)
THP with Centrifuge Dewatering
THP with BFP Dewatering
Conventional MAD with Centrifuge
THERMAL HYDROLYSIS PROCESSES CONVENTIONAL MESOPHILIC
Source: Murthy, 2012
69th Annual KU Environmental Engineering Conference
THP Background - History▪ First full scale THP system commissioned in
1995 by Cambi
▪ HIAS plant Lillehammer, Norway
▪ Original vessels are still in operation
▪ Kruger/Veolia 1st pilot plant 2004 (Biothelys) full scale ~2009.
▪ Kruger/Veolia 1st Exelys plant 2014
▪ First US Installation – DC Water Operational October 2014 (Cambi)
▪ 8 US THP Facilities in planning/design/construction
69th Annual KU Environmental Engineering Conference
THP Background - Manufacturers
▪ Cambi ~50 facilities. 1 operating in US. 8 Additional in US in next 3 years.
▪ Veolia/Kruger 2 types
▪ Biothelys – continuous batch ~7 facilities + 1 US pilot
▪ Exelys – continuous 2 facilities + 1 demonstration
▪ Sustec – 2 full scale, 3 pilot
▪ Haarslev – 2 pilot scale plants
69th Annual KU Environmental Engineering Conference
DC Water: First Operating THP Facility in North America
69th Annual KU Environmental Engineering Conference
Background
2.2 million water and
wastewater customers in DC
Annual operating budget $300M+
$3.8B 10 Year
CIP
1,100 employees
8-Time Winner
of National Association of Clean Water
Agencies Gold Peak
Performance Award
DC Water is the largest
power user in Washington,
DC
69th Annual KU Environmental Engineering Conference
Overview of Blue Plains AWTP
▪ 391 mgd average day capacity
▪ ~160 acres
▪ Largest Advanced WWTP in the world
▪ Serves DC, plus areas of Maryland and N. Virginia
▪ Advanced secondary treatment – filtration, N and P removal
▪ Discharge to Potomac
69th Annual KU Environmental Engineering Conference
Main Process Train Project
Solids Blending Tanks
Sludge Screening
Pre-Dewatering
Dewatered Sludge Storage and Pumping
Thermal Hydrolysis (Cambi)
Sludge Cooling
Digestion
Digested Sludge Transfer & Holding
69th Annual KU Environmental Engineering Conference
DC Water – Case Study
▪ Implemented THP/Digestion with Seeding beginning in October 2014
▪ Full throughput in February 2015
▪ Full acclimatization in late 2015
▪ Temporary Approval for Class B Land Application February 2015
▪ Approval for Class A Land Application May 2016
69th Annual KU Environmental Engineering Conference
Commissioning Objectives
▪ Initiate seeding of digesters with Class A biosolids
▪ Maintain solids throughput (estimated at 300 dtpd at start of commissioning)
▪ Continue Class B land application until Class A achieved and approved
69th Annual KU Environmental Engineering Conference
Startup Methodology▪ Fill all digesters ~60% with water
▪ Heat water to 100°F
▪ Continuous operation of HEX solids pumps for minimal mixing
▪ Transport sludge and fill remaining volume of two digesters with class A seed sludge (~1% solids in each digester)
▪ Continue heating digester with steam
▪ Begin mixing with draft tube mixers (startup mixers over 12 hour period)
▪ Begin feeding TH solids to first digester (overflow to adjacent digester)
▪ Ramp up solids based on VS in digesters
69th Annual KU Environmental Engineering Conference
Daily Feed Rates
0
50
100
150
200
250
300
350
400
450
Soli
ds
Thro
ugh
pu
t, d
tpd
Digester 1 Digester 2 Digester 3 Digester 4 Total
Average Mass Feed Rate = 303 dtpdAverage SRT = 21 days
69th Annual KU Environmental Engineering Conference
Seeding and Ramp Up Results
▪ First digester lower solids concentration▪ Initial sludge provided was more dilute
▪ Steam added water to digester
▪ Maintaining temperature required significant steam
▪ Initial decline of pH and Alkalinity▪ Added alkalinity to first 2 digesters
▪ Rapid increase in alkalinity after two weeks
69th Annual KU Environmental Engineering Conference
Solids Concentration in Digesters
0
1
2
3
4
5
6
7
8
Per
cen
t To
tal S
oli
ds
Date
Digester 1 Digester 2 Digester 3 Digester 4
69th Annual KU Environmental Engineering Conference
Volatile Solids Reduction
0
20
40
60
80
100
50
60
70
80
90
100
Per
cen
t V
ola
tile
So
lid
s R
edu
ctio
n
Per
cen
t V
ola
tile
So
lid
s
Date
Pre-Digestion Screened Blended Solids Final Thermal Hydrolysis & Digested Belt Filter Press Cake Volatile Solids Reduction
Average Feed VS = 81%Average VSR = 68.5%
69th Annual KU Environmental Engineering Conference
Fecal Coliform Results (Dewatered Biosolids) During Commissioning
69th Annual KU Environmental Engineering Conference
Meeting and Exceeding Class A Requirements –Long Term Operation
0
10
20
30
40
50
60
70
80
Feca
l Co
lifo
rm M
PN
/gra
m
Date
Final Thermal Hydrolysis & Digested Belt Filter Press Cake
Average Fecal Coliform <5 MPN/gramMax Fecal Coliform 72 MPN/gram
69th Annual KU Environmental Engineering Conference
Dewatered Solids Concentration – Long Term Operations
20
25
30
35
40
Per
cen
t To
tal S
oli
ds
Date
Final Thermal Hydrolysis & Digested Belt Filter Press Cake
Dewatered solids ~32%Polymer use ~20 to 22 lbs/ton
69th Annual KU Environmental Engineering Conference
Findings - Commissioning▪ Supplemental Heat Required
▪ Ramp up conservatively (max. 5% per day increase feed)
▪ Supplemental alkalinity allows faster ramp up (initial drop in pH)
▪ Digested solids not Class A for ~150 days (acclimatization)
▪ High VSR (60%+)
▪ Methane Concentrations 62%+▪ Reduced concentration is early sign of upset
▪ Ammonia elevated
▪ Rapid increases in feed can cause upset
69th Annual KU Environmental Engineering Conference
Findings - Operating Issues
▪ Mechanical Issues▪ Rotary Lobe Pumps▪ Cake Bin Gates▪ Centrifuge Solids Control▪ Wear on Mechanical Equipment
▪ Process Issues▪ Vivianite▪ Grit▪ Foam▪ Odors
▪ Support Equipment Issues▪ Steam Pressure▪ Flare Exhaust Results▪ Dilution Control
69th Annual KU Environmental Engineering Conference
Findings - Current Operations
▪ THP Temperature reduced caused excessive foam in digesters
▪ Use of plant effluent caused microbially induced corrosion (MIC) in heat exchangers
▪ Annual inspection of pressure vessels indicated high wear of steam nozzles due to grit
▪ Rapid changes in feed have resulted in foaming events
▪ Centrifuges require most operator attention of all components
KC WATERBlue River Biosolids Facility Project
M a t t B o n dC h i e f E n g i n e e r i n g O f f i c e r
A p r i l 2 0 1 9
• Combined water, wastewater, and
stormwater utility
• $409M Enterprise (FY19)
• 860+ Employees
• 470,000 residents served inside the city;
200,000 residents outside the city
• Over 2,800 miles of water mains and 2,800
miles of sewer mains in Kansas City across
318 square miles.
• Produces an average of 94 MGD
Over vi ew of KC WaterLar ge Ser vi ce Ar ea -Re l a t i ve ly Smal l Popul a t i on
KC 14% of Combined
Population of San Francisco,
Miami,
Philadelphia and
Boston
Blue River WWTP
Birmingham WWTP
Westside WWTP
COST
• Costly incinerator upgrades
• Air emissions challenges
• Landfills not available, no longer a viable option
• Class A product for beneficial reuse
DETERMINING THE NEED
32
33
OPTIONS CONSIDERED
Multi-Hearth Furnace
Photo Credit: Shaun O’Kelley , Blue River WWTP
Thermal Hydrolysis
Photo Source: Wikimedia, THP -https://commons.wikimedia.org/w/index.php?curid=50970357
Lime StabilizationPhoto Source: www.irishwaste.net/service/industrial-services/mobile-lime-stabilisation-plants/
Fluidized BedPhoto Source: Kuzu Grup, Fluid Bed -http://www.kuzugrup.com/en/proje/buski-fluidized-bed-sludge-
incineration-and-energy-production-plant/
34
QUADRUPLE BOTTOM LINE
Positive Impacts of Thermal Hydrolysis on Digester Biology, Rheology, Capacity and Up/Downstream Processes
Increase Digester Capacity• > 2 times the loading of conventional
digestion
• Reduced tankage install
Hygienization• Class A sterilization
• Makes mesophilic digestion more
robust
Thermal
Hydrolysis
Mesophilic
Anaerobic
Digestion
“Pressure
Cook”
20 minutes at
320 oF
Rheological Properties• Reduced viscosity (easier to pump)
• 10 percent sludge readily flows
• Reduced pumping and mixing
requirementsBiosolids Characteristics• >30 percent TS cake typical
• Stackable cake
• Low odor product
Biogas Production• Increased yield
• Higher methane content in gas
BENEFITS
36
Elimination of
incineration and
emissions
All solids
processed
through existing
digesters
Class A product,
beneficial use of
biosolids
Energy recovery Odor reduction
Proposed THP System
THP Units
Primary Sludge
PS Screens
East Sludge
Holding Tank
CentrifugesPre-dewatering
Polymer Feed System
THP Feed Tank
Thickened WAS
Existing Systems
New Process
To Land Application
or Landfill
Storage and Loadout
On-site Boiler/
Steam Generator
Combined Heat Power (future)
Biogas Cleaning
Anaerobic DigestersHeat Exchanger West Sludge
Holding Tank
Centrifuges
Polymer Feed System
Not Shown: Odor
Control, FOG, and
Sidestream Management Systems
Post-dewatering
Bioso lids Fac ilit y Conceptual Design
39
DRIVING INNOVATIONS
• Risk Management
• Collaborative Project Delivery (Design/Build)
• Building Information Model (BIM)
• Approved Financing• Water Infrastructure Financing
and Innovations Act (WIFIA) - 2018
• Clean Water State Revolving Fund (SRF)
Defin ing KC W ater ’s BIM Program
• 3D based design
• Automated interference detection
• Design and constructability reviews
• Contractor schedule/budget management, phasing scenarios
• Whole-life asset management
• Defined protocols for future BIM
40
Design
ReviewClash
Detection Analysis
Drawings &
Schedules
Visualization
SpecificationsScheduling
Cost
Estimating
SCHEDULE
41
COMPLETE PRELIMINARY
DESIGN
ISSUE RFQ
LATE SUMMER
2019
SHORTLIST
ISSUE RFP
FALL 2019
EVALUATE PROPOSALS
WINTER 2019
DESIGN/BUILDER
NOTICE TO PROCEED
SUMMER 2020
KC WATERBlue River Biosolids Facility Project
M a t t B o n dC h i e f E n g i n e e r i n g O f f i c e rm a t t . b o n d @ k c m o . o r g 8 1 6 - 5 1 3 - 0 1 6 8
A p r i l 2 0 1 9
69th Annual KU Environmental Engineering Conference
Discussion & Questions…
Dustin Craig, PE
Environmental Engineer
816.877.4802 [email protected]
Matt Bond, PE, WEF Fellow
Chief Engineering Officer
816.513.0168