Upload
safiullah
View
215
Download
0
Embed Size (px)
Citation preview
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
1/82
A Case Study on Effective Ways to Control a
Project
By
Ehsanullah Najib
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
2/82
A Case Study on Effective Ways to Control a Project
Submitted By: Ehsanullah Najib
Registration No: 302-061117
Supervised by: Mohammad Shahid Shams
This project report is submitted in partial fulfillment for the award of degree of Bachelor of Business
Administration
Department of Business Administration
KARDAN INSTITUTE OF HIGHER EDUCATION, KABUL
August 2010
i
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
3/82
PROJECT APPROVAL FORM
The undersigned certify that they have read the following project report and are
satisfied with the overall performance and recommend the report to the Faculty of
business Administration for acceptance.
Project Report Title:
The Effective Ways to Control a Project_______________________________________
_________________________________________________________________________
Submitted By: Ehsanullah Najib
Registration #: 302-06117
Degree Name in FullBachelor of Business Administration
Name of Discipline
Finance
Name of Supervisor Signature of Supervisor Mohammad Shahid Shams ______________________________
Signature of Head of the departmentName of Head of the department
Dr. Umar Farooq ______________________________
Signature of Vice ChancellorName of Vice Chancellor
Professor Anwar Shakeel Usmani ______________________________
Date:_______________________________
ii
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
4/82
DECLARATION FORM
I Ehsanullah Najib
Daughter/ Son of Najibullah Najib
Registration # 302-061117
Student of Bachelor of Business Administration at the Kardan Institute of Higher Education
Kabul, Afghanistan do hereby declare that the Project Report titled as
Effective Ways to Control a Project
Submitted by me in partial fulfillment of BBA (Hons.) degree, is my own work, and has notbeen submitted or published earlier. I also solemnly declare that it shall not, in future, be
submitted by me for obtaining any other degree from this or any other university or
institution.
Signature:
Name: Ehsanullah Najib
Date: August 23, 2010
iii
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
5/82
Acknowledgement
Initially I am grateful to Alimigity Allah for all the power, confidence, and patients who
provided me for successful completion of this degree, also I am blessing and praying toAlmighty Allah for providing additional power, confidence, and patients for successful
completion of my future educational objectives.
I am heartily thankful to my parents, who played a vital role in gaining this degree, their
encouragements, moral and financial support, and guidance during my secondary and high
school were supportive and consequences to a route for getting this degree.
I gratefully acknowledge my assigned supervisor Mr. Mohammad Shahid Shams, AssistantProfessor Kardan Institute of Higher Education (KIHE) for his encouragement, supervision
and support from the preliminary to the concluding level that enabled me to develop an
understanding of the research subject.
I am greatly thankful to my current employer International Relief and Development (IRD)
and my supervisor Eukeni Urrechaga, Program Controls Manager for the moral support and
allowing me to utilize IRDs office facilities and equipments in preparing this project.
Many thanks go in particular to my colleague Latifa Sadat, Project Controls Specialist who
helped me in getting access to EBSCOhost online research database which was a beneficial
resource for research papers about the subject and can be considered as a backbone of this
research project.
Lastly, I offer my regards and blessings to all of those who supported me in any respect
during the completion of the project.
Ehsanullah Najib
iv
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
6/82
Executive Summary
A project is a unique endeavor to produce a set of deliverables within clearly specified time,
cost and quality constraints. Control is exercised to achieve project objectives, and we know
that there are performance, cost, time, and scope targets that are always important. Execution
of the project according to the predefined project plan can be achieved through a control
methodology. Consequently, project control is a significant issue during the project life
cycle. This research was conducted to recognize and identify the effective ways of
controlling a project.
Findings in this research realizes that most important dimensions of control in a project are
cost, time and performance and by implementing control in all these three dimensions will
consequence a project within budget, time and according to specifications, this research
encounters in finding effective methodologies to control cost, time and performance.
Cost control is equally important in all projects, the successful competition of a project
within budget is extremely necessary for all project members i.e. project managers, senior
management and other stakeholders. Earned value management, cost estimating, cost
minimizing, cash flow management, and S curves are the effective cost control
methodologies which are explored and elaborated in this research.
In addition to cost control, completion of project on time (schedule) will endeavor to
successful completion of a project, it is necessary to have considerable attention in
monitoring and controlling schedules. Most projects typically involve a deadline for work
completion, so contractual agreements will force attention to schedules; the effective time
(schedule) control methodologies are also explored and elaborated in this research.
Project performance occurs on several different levels and stages of a project, all of which
are important to the organization. At its most basic level, performance refers to conformances
with technical specifications; this research also focuses on finding effective ways of
controlling performance.
v
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
7/82
The information in this research is manipulated from primary and secondary sources of
information, the primary source of information is the questionnaires distributed among
project managers, and the researcher used books, journals, and research papers from internet
and libraries for collecting of secondary information. The researcher analyzed and presented
information in accordance with research project template and assigned instructors
agreements.
The over all focus of this research is the exploration and elaboration of utilizing effective
project control methodologies of cost, schedule and performance that consequence to
successful completion of a project.
vi
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
8/82
Table of Content
Title Page ................................................................................................................................... i
PROJECT APPROVAL FORM ............................................................................................... iiDECLARATION FORM......................................................................................................... iii
Acknowledgement ................................................................................................................... ivExecutive Summary.................................................................................................................. vTable of Content ..................................................................................................................... vii
List of Figures ........................................................................................................................ viii
List of Acronyms ..................................................................................................................... ixCHAPTER 1 ............................................................................................................................. 1
INTRODUCTION .................................................................................................................... 11.1 Background of the Study ................................................................................................ 1
1.2 Background of the problem ............................................................................................ 21.3 Research Problem Statement .......................................................................................... 3
1.4 Objective of the Research ............................................................................................... 3
1.5 Scope and limitation of the study.................................................................................... 31.6 Significance of the study................................................................................................. 4
CHAPTER 2 ............................................................................................................................. 5
REVIEW OF RELATED LITERATURE................................................................................ 52.1 What Is a Project? ........................................................................................................... 5
2.2 What Is Project Management? ........................................................................................ 62.3 Understanding Project Management Processes .............................................................. 72.4 Initiating and planning the project .................................................................................. 7
2.5 Executing ........................................................................................................................ 82.6 Closing ............................................................................................................................ 8
2.7 Monitoring and controlling............................................................................................. 9
2.8 Literature Review.......................................................................................................... 10CHAPTER 3 ........................................................................................................................... 34METHODOLOGY ................................................................................................................. 34
3.1 Population ..................................................................................................................... 343.2 Sample Size................................................................................................................... 34
3.3 Procedure ...................................................................................................................... 343.4 Research Tools.............................................................................................................. 35
CHAPTER 4 ........................................................................................................................... 36FINDINGS AND ANALYSIS ............................................................................................... 36
CHAPTER 5 ........................................................................................................................... 45CONCLUSION AND RECOMMANDATIONS................................................................... 45
5.1 Conclusion .................................................................................................................... 455.2 Recommendations......................................................................................................... 59
APPENDICIES....................................................................................................................... 61BOBLIOGRAPGHY .............................................................................................................. 64
vii
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
9/82
List of Figures
Description Page#Figure 1 Which Project Functions Need the Most Improvement ........................................... 17
Figure 2 Expenditure and Progress Measures......................................................................... 18
Figure 3 Type of Construction Project Managed by Project Managers.................................. 36Figure 4 Areas to be Controlled in a Project........................................................................... 37Figure 5 Method of Schedule Control .................................................................................... 39
Figure 6 Methods of Cost Control .......................................................................................... 40
viii
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
10/82
ix
List of Acronyms
AACE Association for the advancement of Cost Engineering
ACWP Actual Cost of Work Performed
APMBoK Association for Project Management: Body of KnowledgeASHTO American Association of State of Highway Transportation Officials
ASTM American Society for Testing and Materials
BCWP Budgeted Cost of Work Performed
BCWS Budgeted Cost of Work Scheduled
BOQ Bill of Quantity
CBP Center for Business Practices
CPI Cost Performance Index
CPM Critical Path Method
ERP Enterprise Resource PlanningEV Earned Value
EVM Earned Value Management
EVMS Earned Value Management System
IPA Independent Project Analysis
IT Information Technology
MPCS Multidimensional Project Control System
NPV Net Present Value
PM Project Management
PMBOK Project Management Body of KnowledgePMIS Project Management Information System
PMQR Program Quality Monitoring Review
QA Quality Assurance
QC Quality Control
SPI Schedule Performance Index
TQM Total Quality Management
UK United Kingdom
USA United States of America
WBS Work Breakdown Structure
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
11/82
CHAPTER 1
INTRODUCTION
1.1 Background of the Study
The key success factor for a successful completed project is the effective control and
management of a project, every project either it is simple or complex in their nature need a
level of control to achieve the project goal and meet the specifications according to the scope,
budget and within the time,
Project management control systems in an organization are necessary for managing projectscope, cost and schedule. They are based on carefully defined process and document
controls, metrics, performance indicators and forecasting with capability to reveal trends
toward cost overrun and/or schedule slippage. Identifying those trends early makes them
more amenable to successful management.
Project controls is indispensable for all type of projects including vertical industries
engineering and construction, public sector, aerospace and defense, utilities, oil and gas,
manufacturing and high tech, and IT and services and it currently being practiced in huge and
small industries in the world.
The effective control of a project is based on the three distinct activities: Measuring,
Evaluating and Correcting, in measuring determining through formal and informal reports the
degree to which progress toward objective is being made, in evaluating cause of and possible
ways to act upon significance deviation from planned performance and in correcting taking
control action to correct an unfavorable trend or to take advantage of an unusually favorable
trend, overall in turn these three activities are based on three resource parameters, namely
Time, Cost and Performance. These three resource parameters need to be analyzed in an
integrated way and the objective is to regulate the activities, resources and events in order to
achieve the results as defined by the project plans.
1
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
12/82
This research was conducted to recognize the effective ways of having control on a project,
the research focuses on finding the effective ways and approaches to efficiently control time,
cost and performance that shall result a successful project outcome.
1.2 Background of the problem
Controlling is the third function of project management and it is necessary to have control all
over in each step of a project from planning to closing, all projects either they are simple or
complex in their nature need a level of control to achieve the project goal and meet the
specifications according to the scope, budget and within the time.
Lack of control in a project can cause failure to a project; the project failure can be employed
from three distinctive areas of cost, schedule and performance.
Cost control is equally important to all companies, regardless of size, small companies
generally have tighter monetary controls, mainly because of the risk with the failure of as
little as one project, but with less sophisticated control techniques, large companies may have
the luxury to spread project losses over several projects, whereas the small company may
have few projects. Too many people have a poor definition of cost control; cost control is not
only monitoring of costs and recording perhaps massive quantities of data, but also
analyzing the data in order to take corrective action before it is too late. Cost control should
be performed by personnel who incur cost, not the merely the project office.
In addition to cost control, project managers must also give considerable attention to
monitoring and controlling schedules. Most projects typically involve a deadline for work
completion, so contractual agreements will force attention to schedules. More generally,
delays in construction represent additional costs due to late facility occupancy or other
factors. Just as costs incurred are compared to budgeted costs, actual activity durations may
be compared to expected durations. In this process, forecasting the time to complete
particular activities may be required.
2
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
13/82
1.3 Research Problem Statement
Control deficiency in a project can constitute to unsuccessful completion of a project, a
project being with the status of over budgeted, behind schedule and not met the targeted
deliverables can be caused by not having effective control on a project, it is necessary to find
and establish the effective ways to control a project.
1.4 Objective of the Research
This research will elaborate the controlling function as part of managing a project; it will
discuss the necessity of controlling function and what areas need to put control on, also this
research is objected to discover the effective control methodologies.
Identify and find role and importance of control in a project.
Recognizing the foremost areas to be controlled in a project, cost, time and performance.
The importance of project cost and what are effective ways and methodologies of having
a project within the budget and cost.
The significance of time and schedule in a project and what are the efficient and effective
ways of having project completed on time.
1.5 Scope and limitation of the study
This research is a general and has high level of importance, gathering primary data would
add great value on this research, but due to deficiency in of time this was incorporated
mostly in using secondary source of information other than primary sources of
information.
This research was conducted in Afghanistan and controlling is not applied by most
companies and organization in their projects, it was difficult to find standard controlling
methods and procedure to put in this research.
Lack of developed a well resourced libraries, and research resource centers in
Afghanistan was a major limitation to find data for this research project.
3
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
14/82
1.6 Significance of the study
This research will provide the knowledge for Project owners and mangers to effectively
control those elements of a project that keeps the project on-track, on-time and within budget.
The main objective of this is on effective ways of controlling a project which leads to
successful completion of a project for all its assignees, members, stakeholders, customer and
owners.
4
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
15/82
CHAPTER 2
REVIEW OF RELATED LITERATURE
2.1 What Is a Project?
There are two types of work performed by organizations: operations and projects. An
operation is a series of tasks that are routine, repetitive, and ongoing throughout the life of
the organization. Operations are typically necessary to sustain the business. Examples of
operations are accounts receivable, employee performance reviews, and shipping and
receiving. Employee performance reviews might take place every six months, for example,
and although the names and circumstances of employees and supervisors might change, the
process of preparing and conducting employee reviews is always the same. In addition, its
expected that there will continue to be employee reviews throughout the life of the
organization.
On the other hand, projects are not routine or ongoing. That is, projects are unique and
temporary and are often implemented to fulfill a strategic goal of the organization. A project
is a series of tasks that will culminate in the creation or completion of some new initiative,
product, or activity by a specific end date. Some project examples include an office move, a
new product launch, the construction of a building, and a political campaign. It is never the
same project twicefor example, this years product launch is different from last years
product launch. Theres a specific end date in mind for the launch, after which the project
will be considered complete. After the project is complete, a new and unique product will be
on the market.
Projects come in all sizes. One project might consist of 100 tasks; another, 10,000. One
project might be implemented by a single resource; another by 500. One project might take
two months to complete; another might take 10 years. There can be projects within projects,
linked together with a master project consolidating them all. These subprojects, however, are
all unique and temporary, and all have a specific outcome and end date.
5
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
16/82
A project is a unique endeavor to produce a set of deliverables within clearly specified time,
cost and quality constraints.
2.2 What Is Project Management?
Project management is the coordinating effort to fulfill the goals of the project. The project
manager, as the leader of the project team, is responsible for this effort and its ultimate result.
Project managers use knowledge, skills, tools, and methodologies to do the following:
Identify the goals, objectives, requirements, and limitations of the project.
Coordinate the different needs and expectations of the various project
stakeholders, including team members, resource managers, senior management,
customers, and sponsors.
Plan, execute, and control the tasks, phases, and deliverables of the project based
on the identified project goals and objectives.
Close the project when completed and capture the knowledge accrued.
Project management is the discipline of planning, organizing, and managing resources to
bring about the successful completion of specific project goals and objectives.
Project managers are also responsible for balancing and integrating competing demands to
implement all aspects of the project successfully, as follows:
2.2.1 Project scope: Specifying the specific work to be done for the project.
2.2.2 Project time: Setting the finish date of the project as well as any interim
deadlines for phases, milestones, and deliverables.
2.2.3 Project cost: Calculating and tracking the project costs and budget.
2.2.4 Project human resources: Signing on the team members who will carry out the
tasks of the project.
2.2.5 Project procurement: Acquiring the material and equipment resources with
which to carry out project tasks.
2.2.6 Project communication. Conveying assignments, updates, reports, and other
information with team members and other stakeholders.
6
http://en.wikipedia.org/wiki/List_of_academic_disciplineshttp://en.wikipedia.org/wiki/Planninghttp://en.wikipedia.org/wiki/Organizinghttp://en.wikipedia.org/wiki/Managinghttp://en.wikipedia.org/wiki/Resourceshttp://en.wikipedia.org/wiki/Resourceshttp://en.wikipedia.org/wiki/Managinghttp://en.wikipedia.org/wiki/Organizinghttp://en.wikipedia.org/wiki/Planninghttp://en.wikipedia.org/wiki/List_of_academic_disciplines8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
17/82
2.2.7 Project quality. Identifying the acceptable level of quality for the project
goals and objectives.
2.2.8 Project risk. Analyzing potential project risks and response planning.
2.3 Understanding Project Management Processes
It might seem daunting when you realize that, as a project manager, youre responsible for
such a tremendous balancing act. However, this responsibility can be broken down into four
manageable processes:
2.3.1 Initiating and planning the project
2.3.2 Executing the project
2.3.3
Controlling the project
2.3.4 Closing the project
2.4 Initiating and planning the project
The initiation processes determine the nature and scope of the project. If this stage is not
performed well, it is unlikely that the project will be successful in meeting the business
needs. The key project controls needed here are an understanding of the businessenvironment and making sure that all necessary controls are incorporated into the project.
Any deficiencies should be reported and a recommendation should be made to fix them.
The initiation stage should include a plan that encompasses the following areas:
Analyzing thebusinessneeds/requirementsin measurable goals
Reviewing of the current operations
Financial analysisof the costs and benefits including abudget
Stakeholder analysis, including users, and support personnel for the project
Project charterincluding costs, tasks, deliverables, and schedule
After the initiation stage, the project is planned to an appropriate level of detail. The main
purpose is to plan time, cost and resources adequately to estimate the work needed and to
7
http://en.wikipedia.org/wiki/Businesshttp://en.wikipedia.org/wiki/Requirementhttp://en.wikipedia.org/wiki/Business_operationshttp://en.wikipedia.org/wiki/Financial_analysishttp://en.wikipedia.org/wiki/Budgethttp://en.wikipedia.org/wiki/Stakeholder_analysishttp://en.wikipedia.org/wiki/Project_charterhttp://en.wikipedia.org/wiki/Deliverablehttp://en.wikipedia.org/wiki/Deliverablehttp://en.wikipedia.org/wiki/Project_charterhttp://en.wikipedia.org/wiki/Stakeholder_analysishttp://en.wikipedia.org/wiki/Budgethttp://en.wikipedia.org/wiki/Financial_analysishttp://en.wikipedia.org/wiki/Business_operationshttp://en.wikipedia.org/wiki/Requirementhttp://en.wikipedia.org/wiki/Business8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
18/82
effectively manage risk during project execution. As with the Initiation process group, a
failure to adequately plan greatly reduces the project's chances of successfully accomplishing
its goals.
Project planning generally consists of
determining how to plan (e.g. by level of detail or rolling wave);
developing the scope statement;
selecting the planning team;
identifying deliverables and creating the work breakdown structure;
identifying the activities needed to complete those deliverables and networking
the activities in their logical sequence;
estimating the resource requirements for the activities;
estimating time and cost for activities;
developing the schedule;
developing the budget;
risk planning;
Gaining formal approval to begin work.
2.5 Executing
Executing consists of the processes used to complete the work defined in the project
management plan to accomplish the project's requirements. Execution process involves
coordinating people and resources, as well as integrating and performing the activities of the
project in accordance with the project management plan. The deliverables are produced as
outputs from the processes performed as defined in the project management plan.
2.6 Closing
Closing includes the formal acceptance of the project and the ending thereof. Administrative
activities include the archiving of the files and documenting lessons learned.
8
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
19/82
2.7 Monitoring and controlling
Monitoring and controlling consists of those processes performed to observe project
execution so that potential problems can be identified in a timely manner and corrective
action can be taken, when necessary, to control the execution of the project. The key benefitis that project performance is observed and measured regularly to identify variances from the
project management plan.
Control is the last element in the implementation cycle planning-monitoring controlling.
Information is collected about system performance, compared with the desired (or Planned)
level, and action taken if actual and desired performance differ enough that the controller
(manager) wishes to decrease the difference. Note that reporting performance, comparing the
differences between desired and actual performance levels, and accounting for why such
differences exist are all parts of the control process. In essence control is the act of reducing
the difference between plan and reality. Control is focused of the three elements of project-
performance, cost and time. The project manager is constantly concerned with these three
aspects of the project. Is the project delivering what it promised to deliver or more? Is it
making delivery at or below the promised cost? Is it making delivery at or before the
promised time? It is strangely easy to lose sight of these fundamental targets, especially in
large projects with a wealth of detail and a great number of subprojects. Large projectsdevelop their own momentum and tend to get out of hand, going their own way independent
of the wishes of the project manager and the intent of the proposal.
In project management field, there are few things that can cause a project to require the
control performance, costs or time.
2.7.1 Performance:
Unexpected technical problems arise. Insufficient resources are available when needed.
Insurmountable technical difficulties are present.
Quality or reliability problems occur.
Client requires changes in system specifications.
9
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
20/82
Inter functional complications arise.
Technological breakthroughs affect the project.
2.7.2 Cost:
Technical difficulties require more resources.
The scope of the work increases.
Initial bids or estimates were too low.
Reporting was poor or untimely.
Budgeting was inadequate.
Corrective control was not exercised in time.
Input price changes occurred.
2.7.3 Time:
Technical difficulties took longer than planned to solve.
Initial time estimates were optimistic.
2.8 Literature Review
1Erel and Raz (2000) state that the project control cycle consists of measuring the status of
the project, comparing to the plan, analysis of the deviations, and implementing any
appropriate corrective actions.
When a project reach the construction phase, monitor and control is critical to deliver the
project success. Project monitoring exists to establish the need to take corrective action,
whilst there is still time to take action. Through monitoring the activities, the project team
can analyze the deviations and decide what to do and actually do it ( 2Gardiner and Stewart
2000, p252). The purpose of monitor and control is to support the implementation of
corrective actions, ensure projects stay on target or get project back on target once it has gone
off target (Erel and Raz, 2000, p253).
1Erel,E. and Raz,T. ( 2000). Optimal timing of project control points. [online] European Journal of
Operational Research.127(2).pp 252-261.2Gardiner,P and Stewart,K.(1998).Revisiting the golden triangle of cost, time and quality of NPV inproject control, success and failure.[ online]International Journal of ProjectManagement.16 (5). pp258-256.
10
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
21/82
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
22/82
Based on the original plan(Gantt charts), we can analyze what activities are on the critical
path, what activities with no free float and what activities with less than a specified float via
network diagram, then monitoring these activities, take control actions to avoid delay.
Once an activity on critical path is going to delay, commonly, there are the ways to avoid
delay or even can shorten the time of activities:
a) Increasing resource levels, such as adding labour.
b) Improving resource efficiency, such as transferring high skill employees to the
activity, improving efficient tools.
c) And means that can shorten critical path timescales to bring a project back on target,
such as overtime, outsourcing, etc.
In addition, for shortening project time, it is still required to use early start or as soon as
possible approach for those activities having slack (float) time. Through this method, it is
more flexible for a project to adjust various resources when urgency burst into the activity on
the critical path. For example, an activity is on the critical path, it will delay inevitably if
there is no more people work on it. In most of this case, the people can move from non-
critical task to the urgent work. The non-delay concept was found to be more efficient in
reducing project risk, reducing project duration (6
Cohen, Sadeh and Zwikael, 2006).
Reconsidering activities precedence is another important control way for getting project back
on target (7Cotterell and Hughes,1995). Because the original project network will probably
have been produced for an ideal situation, with the project going, many issues will affect the
activity implement, the actual result is quite different with the imagination. The manager
should always combine the reality and think about the following questions:
a) Do unstarted activities really have to await the completion of other activities before
they can start? If no, start the activities
6Cohen,Y. Sadeh,A .and Zwikael,O.( 2006). Non-delay scheduling as a managerial approach for
managing projects. [online]International Journal of Project Management.24(4).pp330-3367Cotterell,M. and Hughes,B.Monitoring and control. [online] .Available from:
http://ourworld.compuserve.com/homepages/MouseNous/spm/Spm.pdf. [28 January 2009]
12
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
23/82
b) If an activity has to wait for the completion of other activities, can that activity be
broken down into sub-activities and some of the sub activities completed at an earlier
date? If no, breakdown the activity into sub-activities and start the urgent one at once.
8Herroelen and Reyck (1999) also state that managers have to tackle the challenging problem
of scheduling activities to minimize the project duration, in which the activities (a) are
subject to generalized precedence relations, (b) require units of multiple renewable, non-
renewable and doubly constrained resources for which a limited availability is imposed, and
(c) can be performed in one of several different ways, refected in multiple activity scenarios
or modes.
Considering optimal timing of project monitoring and control points is significant to success(
9Falco and Macchiaroli, 1998). Falco and Macchiaroli suggest that we should determine the
optimal frequency of the monitoring and reviewing to different activities in different stages.
It can help us to efficient monitor and correct control so as to reach time and cost target.
The main cost of a project includes staff cost, material cost and delay cost. To control these
cost, managers should first set up a cost control system to:
a) Allocate responsibilities for administration and analysis of financial data
b) Ensure all costs are properly allocated against project codes
c) Ensure all costs are genuinely in pursuit of project activities
d) Ensure contractors payments are authorized
e) Check that other projects are not using the budget.
Then, managers should monitor and control change to the project budget. It means the
following things:
8Herroelen,W. and Reyck,B.(1999). The multi-mode resource-constrained project scheduling problem
with generalized precedence relations. [online]European Journal of OperationalResearch .119.pp538-556.9Falco,M. and Macchiaroli, R.(1998).Timing of control activities in project planning. [online]
International Journal of Project Mnagement.16 (1).pp51-58.
13
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
24/82
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
25/82
b) Changes should take place once it is approved and be monitored to check whether it
worked as expected
c) All changes in project should be recorded in the project documentation (Voropajev,
1998,p18).
Project management and project control are not always synonymous. Many companies are
not handling project control functions as well as they should because control functions
sometimes are lumped into project management duties, according to Project Control
Functions: A Benchmark of Current Business Practice, from Havertown, Pa., USA-based
Center for Business Practices (CBP). The report, based on a survey designed to investigate
best practices in performing project control functions, found that half of the respondents
perform project control functions in the average to poor range. The report also indicates that
the most challenging control functions for organizations involve educating project teams
about proper project management processes, estimating project costs, and managing issue,
risk and change control. The failure to recognize project control as a specific job is a key
organizational mistake, according to the report, which notes that project managers generally
perform project control functions as part of their overall duties.
These findings confirm what many companies have begun to accept: Day-to-day project
control functions suffer when theyre assimilated into other project management duties, says
James Pennypacker, CBP director. Mr. Pennypacker says organizations will derive benefits
more quickly by giving intensive planning and control work to a person designated as a
project controller. In addition, the project manager is able to spend more quality time with
executives in explaining status, gaining insight into political and budgetary issues and
selling the project, Mr. Pennypacker says. The project management profession has made
significant advancements new industry trends surfaced, organizations flattened out and
information technology allowed people to communicate more effectively and reduce cycle-
times across all business processes, according to Reining in Your Project Controls by
Havertown, Pa., USA-based PM Solutions. As a result, management began pushing more
projects onto an increasingly complex organization, and the project manager suddenly
became the Jack-of-All-Trades, forced to be everything to everyone, the white paper
15
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
26/82
reports. The role of project manager is now very demanding, and requires an ever-
expanding arsenal of skills, especially soft or interpersonal skills.
Bloomington, Ill., USA-based State Farm Insurance Co. has had project controllers (whom
they refer to as project planners) in place for six years with positive results. What our
project managers are finding most helpful is that they can delegate time-consuming yet
critical tasks, like updating and analyzing schedules, says Jeanne Childers, director of State
Farms Systems project office. By utilizing this role weve been able to expand the capacity
of our project managers to handle more projects concurrently. Some organizations are
looking to outside specialists to help manage their project control functions, CBP says. More
than half of the respondents to its survey reported that they plan to use augmented services,
such as consulting, staffing and outsourcing, to perform project control functions in thefuture.
Educate the Project Team on
PROJECT CONTROL FUNCTIONS
Processes
Educate the Project Team on Proper Project Management Processes
Facilitate and/or Oversee Project Planning and Control Sessions
Develop the Project Schedule and Work Breakdown Structure
Manage the Critical Path to Ensure That Schedules are met
Estimate Project Costs
Track and Analyze Project Costs
Manage the Process of Issue, Risk and Change Control
Document and Deliver Project status Information.
16
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
27/82
Figure 1 Which Project Functions Need the Most Improvement
Independent Project Analysis (IPA) research, as reported in industry literature in 1994, had
shown that average cost growth (the ratio of actual/estimated costs) for projects was
declining. However, more recent research has shown that since 1994, neither average cost
growth nor variability (the plus or minus range) has improved. Past improvements in average
cost growth were largely driven by improved upfront project definition, prior to full
authorization of project funds (i.e., frontend loading or FEL). However, good FEL can
improve the cost outcome only so much before weaknesses in other practices becomes a
constraint. Owner cost engineering/project control practices used during the FEL and
execution phases of a project are one such constraint and an opportunity for improvement.
Project system benchmarking is used to identify industry trends and best practices, including
those for cost engineering. The benchmarking process compares a companys project system
performance with that of its competitors. To support benchmarking, data about actual project
practices (inputs) and results (outcomes) are collected. Using the empirical data in an
industry database, we perform statistical analysis to identify those inputs that drive the bestoutcomes.
We use an empirical industry database to research cost engineering practices and determine
which are best at improving cost and schedule outcomes. Many of our research findings
about cost engineering are common sense, but it is too easy for management to reject
17
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
28/82
common sense when other cost reduction options (often counter-productive) look so much
more attractive on paper. The practices discussed in this article have been empirically
demonstrated to work.
Before describing which practices are best, we need to explain the scope of the cost
engineering practices studied by IPA and the typical practices used in industry. The
practices studied include cost estimating, planning and scheduling, and cost/schedule control;
these practices collectively are often referred to as project control, which is a core subset of
the cost engineering field. Figure 2 illustrates the primary steps in the project control process,
as documented by AACE Internationals Total Cost Management Framework.
Source: Cost Engineering Vol. 45/No. 9 SEPTEMBER 2003
Figure 2 Expenditure and Progress Measures
Starting at the top-center of the process map in figure 1, the cost engineer estimates the
project cost and establishes the cost budget for the project. The cost engineer uses the
planning and scheduling step to translate the projects scope into a logical sequence of work
activities. The project activities are then executed while the cost engineer measures and
18
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
29/82
assesses the projects performance against the plan (i.e., cost/schedule control). On the left
side of the process map, the cost engineer identifies corrective actions when deviations from
the plans occur. Finally, the control cycle loop is closed when the cost engineer updates
project plans to address project trends and changes.
Through benchmarking, we have identified typical industry project control practices, both
good and bad. Typically, engineering and construction contractors perform most day-to-day
project control functions during project execution. Owners generally set project control
requirements, evaluate contractor estimates and proposals, review contractor progress
reports, and negotiate contract changes. If the project scope is well defined at the time of
project funds authorization (i.e., during FEL), then an engineering contractor prepares the
cost estimate and critical-path schedule to support both authorization and control. However,in many projects, definition is lacking in some way and owners will prepare a conceptual or
preliminary estimate and milestone schedule for funds authorization, and an engineering
contractor then prepares a detailed estimate and schedule later on (often too late) that will
serve as a basis for control.
For small projects (i.e.,
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
30/82
The estimate structure needs to be able to support physical progressing. During engineering
and construction, many project managers rely on subjective measures of progress and then
fall prey to over-optimism. Even worse are project managers who use the percentage of
budget hours or dollars consumed as an indication of progress. One all too common scenario
of poor progressing is the project manager who thinks the project n is 95 percent complete
and discovers while developing the punch list that only 75 percent of the work has been
completed. The project managers immediate reaction is to pile more people on the job to
accelerate the progress, but the crowding then causes a complete breakdown of discipline and
control. Another scenario is the project manager who ramps up construction crews too early;
the crews hang around waiting for drawings or materials that have been promised but not
delivered.
Project managers have plenty to handle in leading the project without performing all the tasks
of project control. Even if the heroic project manager can handle it all, the project is at risk of
disruption (particularly schedule slip) if the project manager is pulled off or otherwise leaves
the project (heroes are in great demand). The project control specialist does not need to be
assigned full time; in fact, it is common for one project control specialist to handle multiple
small projects (just as the project manager might).\ Owners who have project control
specialists to assign tend to have a project control process and an overall stronger project
system.
The historical cost database is where the owner closes the loop on the project control process.
To quantitatively validate an estimate, the cost specialist must have something against which
the estimate can be compared. A historical database provides absolute comparison project
data (estimated and actual), cost metrics, and ratios. External benchmarks should be obtained
as well. Another benefit of developing an historical database is that the practice of asking for
detailed cost proposals and detailed final closeout data shows the contractor that the owner
understands project costs and is not likely to be fooled. In fact, our research shows that
owners who quantitatively validates estimates and collects detailed cost data does obtain
better fixed-price proposals.
20
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
31/82
If your company has been deficientin project control practices, start now on building (or
rebuilding) your in-house functional knowledge and capabilities. As discussed, most day-to-
day project control activity is the responsibility of project contractors, but some tasks should
not be outsourced. Your company needs in-house personnel to quantitatively validate cost
estimates and bids based on cogent, up-to date knowledge of what asset and project costs
should be. In-house project control expertise is needed for establishing project control
procedures and requirements for contracts. During project execution, in house cost and
project control expertise supports the project managers efforts to effectively spot and
respond to project trends, address potential changes, negotiate change orders, and otherwise
control the project.
As described by
12
Mr. George B. Bradshaw, PE CCE 2008 establishing the project controlsorganization and functions early in the project life cycle of a large complex project. The
many technical aspects of project controls must be skillfully developed in order to implement
a strong project management approach for managing a highly complex project, such as
designing and constructing a nuclear power plant. Management cannot simply impose a
project controls system and expect good results. It must develop the project control function
in a manner that demonstrates its commitment and conviction that the investment is essential
for meeting cost and schedule objectives, while minimizing risk.
Management commitment to establishing a project controls program early in the life of a
large project can help manage and control the multitude of conflicts that will ultimately arise
because of constraints, choices, scarcity of resources, personalities, stakeholder requests,
regulations, turf battles, contracts, supplier problems, etc. Additionally, a strong project
controls organization provides investors the assurance needed for control of costs and
completion forecasts. However, the project controls function cannot, by itself, lead to a
projects success, but it is an essential ingredient for success.
Selection and commitment to a planning and scheduling system is one of the most important
decisions to be made on a large complex project. Frequently, the selection is based on the
12Mr. George B. Bradshaw, PE CCE Establishing a First Class Project Controls Organization for ManagingLarge Complex Projects, 2008
21
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
32/82
systems that exist within the AE/Constructors organization. However, a superior approach is
for the owner to evaluate, select, or design the control system in order to be flexible in
responding to changing needs and for promoting understanding and acceptance by the entire
project team. Over reliance on the AEs control system can result in conflicts and other
issues, such as feeling a loss of control. From a project management perspective, establishing
achievable project schedule goals is a key ingredient for obtaining commitment of the project
team.
A project schedule must be built step by step based on the best available information
available from all of the major project participants. For example, an integrated scheduling
system (engineering, procurement, construction and start-up) used on a large nuclear project
had the following levels and characteristics:
Level 1: Milestone Schedule (~200 activities including the total project)
Level 2: Master Project Schedule (~ 20,000 activities; half for construction)
Level 3: Detail Construction Schedule (~ 40,000 activities; expandedyearly;
replaces Level 2)
Level 4: Work Packages (~400,000; work planning tool to capture all work within
a defined cubic, or volumetric section of a building)
Level 5: Rolling Two-Week Look Ahead (daily scheduling tool)
This is a proven structure for planning and schedule control, for identifying resource
requirements and hazards, and for maintaining stability. It is designed to provide timely
feedback on performance problems and the tools for effecting corrective actions. A
scheduling system such as that described, requires a relatively large organization to
implement and maintain. These costs can be justified in terms of costs saved by driving the
schedule, and by demonstrating the project teams commitment in meeting objectives. Overthe past ten years more advanced planning and scheduling tools have been developed, such
22
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
33/82
as that described by 13M.Y. You l and J.H. Han [6]. Without full conviction on
managements part, even the best systems will not ensure success.
Work packages can be an essential element of a construction control system. A work package
is a group of documents, which identifies all work in detail within a cubic for a manageable
and identifiable time frame as established by an Area Director. Typically, a work package
will contain work plans, bill of material, open engineering and material summaries and a
control sheet. Work package preparation begins as Level 3 of the schedule logic is developed
and follows a predetermined development schedule, a minimum of three months prior to the
start of construction of the work described.
A detailed cost estimate is one of the most important tools that the project manager has for
implementing an effective project controls system and maintaining stakeholder confidence
that the project can be completed. Continual updates of the estimate, as the basis for the
controls system, are required due to the many uncertainties facing a large project such as
design changes, labor problems, and technical problems, mistakes in materials or
specifications, and interference from outside the project. These uncertainties require that the
estimate be expressed as a probability distribution, and serve as the basis for contingency, or
a management reserve account. Failure to provide timely updates results in large drops in the
incremental percent completes of a project and undermines confidence in the project
reporting tools.
A mainstay for construction cost control on large projects is the project quantity and worker-
hour Reporting (PQMR) system. This system is based on the project work breakdown
structure (linked to the code of accounts) and is initially populated with quantity information
from the detailed estimate and ultimately the definitive estimate. It is updated periodically as
the project estimate is reforecast to reflect new engineering detail and productivity
experience. These reports provide both a weekly and monthly measure of the productivity
being experienced on the project and are a vital indicator of potential problems. Causes of
productivity declines are required to identify root causes and corrective actions. The cost
13 Yoon, M.Y. and J.H. Han,A Study of Advanced Project Control System for Korean Nuclear Power PlantConstruction Project, AACE International Transactions (2006) :CSC.12.
23
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
34/82
reporting systems primary role is to provide feedback that the plans for effective utilization
of resources are being properly implemented.
Benchmarking can be a very useful tool for independently verifying estimates and schedules
and motivating the project team. One of the key virtues of project controls is the continual
emphasis on incremental progress.
One of the project managers most challenging tasks is to manage scope creep. Scope creep
emanates from many sources: engineers desire to improve their designs beyond
requirements; owners desire to correct an oversight; regulators tendency to impose standards
beyond those initially required; stakeholders need to be involved; innovations; imposition of
continuous performance improvements; etc. The role of project control is to assess and make
visible the impact on existing cost and schedule and other planned work activities if these
changes are approved. On a large complex project, whose execution has been carefully
planned, there is no such thing as a small change. Any change must be planned and
controlled using the same standards as the original work scope. One of the key roles of
project controls is to support the project manager in his efforts to control scope by ensuring
all of the technical and contractual requirements are met and by implementing a formal
change control process.
One of the more difficult tasks is to establish an agreed upon basis for the amount of
contingency when setting project forecasts. In the past environment of regulatory ratchets
and high inflation, history has demonstrated that it is a problematic task. Pre-defined decision
rules governing the use of contingency funds can segregate risk-based uses; especially those
that occur late in the project life cycle, from discretionary uses of contingency funds which
tend to occur earlier in the project life cycle. Whatever contingency amount and method is
selected, it should be owned by the project manager and should be based on a risk type
assessment of all of the possible impacts to the project. A value of 20 percent or more would
be expected in the early phases of construction. This amount would be adjusted based on
project progress and experience.
24
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
35/82
The physical progress of the job should be monitored on a daily, weekly and monthly basis.
The monthly report is typically based on a summary of the PQMR and is organized by the
project WBS and major budget categories. Earned value reports are frequently used, but need
to be supplemented by more detailed quantity status reports, system test and turnover status,
startup system status, material status, quality reports, cost trends, and others. The list of
project reports should be established early in the life of the project, but remain flexible
enough to respond to current needs and priority concerns, On large projects, a group should
be dedicated to the detailed analysis of project data in order to interpret trends and provide an
early warning of problems that need management attention. Analysis of project performance
data is a critical function for supporting sound management decisions. Progress reporting
should also include design, procurement, and material tracking and status. The material and
equipment expediting reports can provide valuable input to the progress reporting system.
It may sound trite, but the purpose of a critical path method (CPM) of scheduling is to
determine the critical path of the job. This is one of the project managers primary tools for
focusing management attention. The CPM schedule should be used as one of the primary
tools for determining the impact of any change to the project. On a well-designed schedule
around 15 percent of the project activities will fall on the critical path. Analysis of project
float on a monthly basis is also a valuable tool for evaluating trends.
The APMBoK takes a broad view of what is meant by the word control (APM, 2000).
Planning, measuring, monitoring, and taking corrective action are all usually included in the
control cycle. Typically, projects utilize a control system, which monitors the difference or
gap between the planning variables and the actual results. Project control systems indicate the
direction of change in preliminary planning variables compared with actual performance.
The successful performance of a project depends on appropriate planning. The PMBOK
Guide defines the use of 21 processes that relate to planning, out of the 39 processes required
for proper project management (14Globerson & Zwikael, 2002). Execution of the project
14Globerson, S., & Zwikael, O. (2002). The impact of the project manager on project management planning
processes.Project Management Journal 33(3), 5865.
25
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
36/82
according to the predefined project plan can be achieved through a control methodology.
Consequently, project control is a significant issue during the project life cycle.
The design of a project control system is an important part of the project management effort
(15Shtub, Bard, & Globerson, 2005). Furthermore, it is widely recognized that planning and
monitoring plays a major role as the cause of project failures. Despite the continuous
evolution in the project management field, it appears evident that the traditional approaches
still show a lack of appropriate methodologies for project control (De Falco & Macchiaroli,
1998). Many articles have supported the importance of control in the achievement of the
project aims and objectives. Project performance can be improved if more attention is given
to the issue of control (Avison, Baskerville, & Myers, 2001). The successful implementation
of a concurrent engineering methodology within a cross-country petroleum pipeline
construction project in India strongly recommends controlling projects through risk
management, quality monitoring, and an integrated information management system (Dey,
2000).
Another way of tackling the issue of the importance of control is by examining project
failures in order to identify the most effective project control rules. For example, a survey
was carried out among 1,450 companies in the public and private sectors (Whittaker, 1999).
The main conclusion was that lack of risk management was the most highly ranked factor
contributing to project failure. Other contributing factors were lack of required team skills
and lack of control.
Researchers surveyed construction projects in Jordan with the objective of identifying the
major causes of delay in the construction industry (Odeh & Battaineh, 2002).Findings
indicated that owner interference, inadequate constructor experience, financing and
payments, labor productivity, slow decision-making, improper planning, and subcontractors
were among the top 10 most important causes for delay.
15Shtub, A. (1997). Project segmentation a tool for project management. International Journal of Project
Management15(1), 1519.
26
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
37/82
During the past decade, leading projects in many industries were enterprise resource planning
(ERP) implementation projects. It was found that the recommended actions needed to bring
troubled ERP projects under control are as follows ( 16Motwani, Mirchandani, Madan, &
Gunasekaran, 2002): (a) redefining or subdividing the project; (b) improving project
management through the use of formal tools and techniques; and (c) using a team-based
approach to solve specific project problems. The key element is to somehow link these
factors to the project control system.
Another study showed that a useful control tool applied in the software industry to reduce
project failure is the identification and analysis of threats to success (17
Schmit, Lyytinen,
Keil, & Cule, 2001). This control process, developed in the USA, Finland, and Hong Kong
using the Delphi methodology, and control techniques for the analysis and presentation of all
possible resource requirements and outcomes were discussed in another study ( 18Lorance &
Wendling, 2001). The successful completion of a project within budgeted time, cost, and
perceived parameters depends to a great extent on the early identification and control of
immediate risks to the project (19Datta & Mukherjee, 2001).
Another project management approach refers to factors that lead to success in meeting the
entire range of multidimensional objectives. Much research has been conducted in order to
examine project success factors. A survey was carried out among a sample of Fortune 1000
companies that examined project success (20Pinto & Slevin, 1987). Another survey was
conducted on research and development project management in the Spanish industry
(21Snches & Prez, 2002), while yet another was done to capture the real world
16Motwani, J., Mirchandani, D., Madan, M., & Gunasekaran, A. (2002). Successful implementation of ERP
projects: Evidence from two case studies.International Journal of Production Economics 75(12), 8396.17Schmit, R., Lyytinen, K., Keil, M., & Cule, P. (2001). Identifying software project risks: An internationalDelphistudy.Journal of Management Information Systems 17(4), 536.18Lorance, R. B., & Wendling, R. V. (2001). Basic techniques for analyzing and presentation of cost riskanalysis. CostEngineering 43(1), 2531.19Datta, S., & Mukherjee, S. K. (2001). Developing a risk management matrix for effective project planningan empiricalstudy. Project Management Journal 32(2), 4557.20
Pinto, J. K., & Slevin, D. P. (1987). Critical factors in successful project implementation. IEEE TransactionsonEngineering Management 34(1), 2228.21
Snches, A. M., & Prez, M. P. (2002). R&D project managementin Spanish industry.International Journalof ProjectManagement 20(7), 545560.
27
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
38/82
experiences of people active in project management (22White & Fortune, 2002). This survey
took the form of a questionnaire that was sent to 995 project managers. Another survey
covered approximately 100 defense projects (23Sadeh, Dvir, & Shenhar, 2000), and another
survey was conducted among organizations with inter/intradepartmental projects (24
Fricke &
Shenhar, 2000). The common denominator resulting from all of the above-mentioned surveys
was a common checklist representing project success factors. This list included clear goals,
management support, ownership, a control mechanism, and communication. A great deal of
variation exists, however, among these success factors, which do not always have the same
dimensions.
Project control systems can be classified as: (1) one-dimensional control systems, and (2)
multidimensional control systems. Both one-dimensional and multidimensional control
systems execute one or more predefined project control objectives. In one-dimensional
control systems, such objectives are not integrated in any way, whereas multidimensional
control systems integrate several project control objectives.
The earned value (EV) methodology is probably the most commonly used multidimensional
project control method, integrating time and cost. Variations of multidimensional control
systems exist that are associated with risk management, theory of constraint, statistical
process control, and so on. These will be discussed later under their specific titles.
Another important factor in both project control systems is the ability to determine when to
perform the control activity. This point was addressed by a study that proposed an analytical
framework, based on dynamic programming, for determining the optimal timing of project
control points throughout the life cycle of the project (25
Raz & Erel, 2000).
22White, D., & Fortune, J. (2002). Current practice in project managementAn empirical study.International
Journal ofProject Management 20(2), 111.23Sadeh, A., Dvir, D., & Shenhar, A. J. (2000). The role of contract type in the success of R&D defenseprojects underincreasing uncertainty. Project Management Journal 31(3), 1422.24Fricke, S., & Shenhar, A. J. (2000). Managing multiple engineering projects in a manufacturing supportenvironment.IEEE Transactions on Engineering Management 47(2),258268.25
Dvir, D., Raz, T., & Shenhar, A. J. (2003). An empirical analysis of the relationship between projectplanning and project success.International Journal of Project Management21(2), 8995.
28
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
39/82
A survey, conducted on the integration of project control systems in clean-room construction
projects, emphasizes the importance of the multidimensional project control system (26El-
Mashaleh & Chasey, 1999).
Project management researchers and practitioners state that existing project control systems
have several deficiencies. One study reviewed an extensive array of research on various
aspects of project scheduling (27Kolisch & Padman, 2001). An important conclusion was that
matching project objectives with the appropriate methodology is an important goal that
remains to be explored. In the U.K., performance evaluation of new product developments
was surveyed (28
Driva, Pawar, & Meno, 2001). Without exception, all companies wished to
improve their use of performance measures. This implies that the methodologies used by
these companies were not satisfactory.
Another researcher supports this view and describes the need to use performance
measurements in project management, suggesting a list of preferred metrics (29
Bauly, 1994).
The deficiency of current project control systems is also presented in additional work
(30
Tukel & Rom, 1998). A thorough literature review regarding the contribution of
mathematical modeling to the practice of project management was conducted (31Williams,
2003). It was found that the synthesis of project management principles and operational
research principles could lead to a new managerial theory.
Surveying the literature regarding existing control systems suggests the following: The
project management world uses one-dimensional control systems although these do not
26ElMashaleh, M. S., & Chasey, A. D. (1999). Improving the cost and schedule control system. CostEngineering 41(7), 3941.
27Kolisch, R., & Padman, R. (2001). An integrated survey of deterministic project scheduling. Omega, TheInternationalJournal of Management Science 29(3), 249272.28Driva, H., Pawar, K. S., & Meno, U. (2001). Performance evaluation of new product development fromcompany perspective.Integrated Manufacturing Systems 12(5), 368378.29
Bauly, J. (1994). Measures of performance. World Class Design to Manufacture 1(3), 3740.30
Tukel, O. I., & Rom, W. O. (1998). Analysis of the characteristics of project in diverse industries.Journal ofOperations Management 16(1), 4361.31
Williams, T. M. (1999). The need for new paradigms for complex projects.International Journal of ProjectManagement17(5), 269273.
29
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
40/82
integrate project objectives in any way. The main reason for using the one-dimensional
control systems is its simplicity of implementation.
The dominant multidimensional project control system is the EV system, which is used
worldwide. This system integrates cost and scheduling and is simple to implement with many
computerized programs available in the marketplace. The main disadvantage of EV is that
other projects control dimensions, such as quality, design, and technology, are not integrated.
Consequently, a broader control picture is lacking, because project managers must have more
than two dimensions to achieve project objectives that go beyond time and cost. Much
research is needed in order to integrate additional control dimensions into the EV approach
and this would be fertile ground for future investigation.
The inclusion of an additional project control dimension defines a need for a
multidimensional control system such as MPCS. It has already been demonstrated that the
MPCS is fairly simple to use and understand. This tool still remains, however, at the research
and development phase and although a computerized version has recently become available,
there is little likelihood that the approach will be widely implemented. Nevertheless, this
multidimensional approach offers great potential for further research.
TOC has been shown to have a positive impact on project control. It is still in its
development stage and its applicability has yet to be demonstrated. Much research is needed
to identify these applications.
TQM principles were shown to be applicable to virtually every organization and its use in
project control can undoubtedly increase the added value of the system performance. Much
more research must; however, be done in this specific project area in order to extract the
principles for its effective application.
Finally, project risk management has been shown to be a controlling parameter for many
types of projects. Although nations still suffer from an inability to forecast major world
events, it is still expected that project managers will develop the means to forecast those
30
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
41/82
events that could eventually affect their projects. Hence, this too constitutes a potentially
fruitful area of research on project control.
Project plans have little value if they are not executed in a controlled way that holds
performance to plan. By 32Jeffrey K pinto and have little value if they are not executed in a
controlled way that holds performance to plan Jeffrey k pinot and Jeffrey w. Trailer have
addressed this critical requirement in their second offering of the project management
institutes Editors choice series Essentials of project control
The current volume comprises 13 articles reprinted from project management journal or PM
network. Each is a classic; selected for its lasting value to project management practitioners.
Together, the articles cover a broad range of topics that constitute a core knowledge set ofcontrol theories and techniques.
Earned value management is a central subject as the link among four related articles. Michael
A. Hatfield makes a case for earned value in a folksy article that describes it as the best and
only means of answering the question, ``How are we doing? ``33
Daniel A. Brandon
describes a mean of implementing earned value tools that Overcomes traditional problems
related do data acquisition, reporting methods, and employee/contractor resistance and
integrates it into executive information systems.
Daniel S. Christensen presents an analysis of cost overruns on deference acquisition contracts
using an earned value view. His research confirms previous observations that project are not
likely to recover from overruns once they reach 15- 20% completion. His preventive
prescription calls for more realistic projections of final costs that avoid distortion that may
arise from organization culture influences such as shoot the messenger responses, ``can
do`` optimism, and face-saving escalation.
32Project Management Journal; Jun2000, Vol. 31 Issue 2, p60, 2p, 1 Black and White Photograph33Project Management Journal; Jun2000, Vol. 31 Issue 2, p60, 2p, 1 Black and White Photograph
31
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
42/82
34Stephen A. Devaux goes beyond the traditional numbers association with earned value and
presents an easy-to-use index managements view to projected value of eventual product
sales compared to estimated costs to complete the project. This broader view link decisions
to deployment sales values and isolates them from shorter-sight financial or irrelevant
emotional considerations. Critical success factors across the project life cycle are presented
by pinto and co-author Dennis p. Slevin. Their research identifies 10 such factors and four
additional factors that are important, but often beyond the control of the project team. All are
predictive of project success. the project distribute the factors across the four phases of the
project life cycle and present implications related to the project mission client
communication ,schedules technical tasks leadership, and project urgency or importance.
35Erwin v. Martinez takes another view of basics by stressing fundamentals to avoid failures
in large scale information systems project. He briefly describes five mini cases and then
presents an extensive set of fundamental project management Functions organized by
executive, project team, and individual/support levels .each Function is associated with a
purpose and an effect on the project, if ignored. He discusses the functions by level and
suggests how they might be beneficially applied in both scoping and planning, and culture
and values assessment
Rework that is not sufficiently considered in project plans can be a cost and schedule buster.
36Kenneth G. cooper hits this head-on with two separate articles. One addresses quality and
rework discovery data, describing how it may be used to improve project progress
assessments, the other is a more comprehensive treatment of the rework issue. It describes
shortcomings of the critical path method and earned value tool and the fallacy that adding
overtime or additional staff is a remedy for schedule shortfalls .in the end, cooper warns that
the approach he suggests often runs counter to conventional wisdom and can be very difficult
to implement.
34Project Management Journal; Jun2000, Vol. 31 Issue 2, p60, 2p, 1 Black and White Photograph35Project Management Journal; Jun2000, Vol. 31 Issue 2, p60, 2p, 1 Black and White Photograph36Project Management Journal; Jun2000, Vol. 31 Issue 2, p60, 2p, 1 Black and White Photograph
32
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
43/82
Best practices for controlling technology based projects offered by 37Hans. Thamhain include
a variety of new analytical, procedural, and people oriented tools and techniques. Although
the need for these tools arises from changing work environments managers are often slow to
embrace them .Thamhain Presents 12 recommendations for effectively implementing
improved managerial controls.
Tabletop exercises are a powerful technique for crisis planning described in an article by
38Larry A. mallak,H .A. kurstedt, and G.A. Patzak. These exercises are versatile tools that
guide managers in thinking through decisions before a real crisis occurs.
Control has been described as the evil twin of paining: it is much less enjoyable, fraught with
problems and just plain hard work .Pinto and Trailer diver out the fear of conflict and
deadlines with enabling information that builds confidence and surety.
37Project Management Journal; Jun2000, Vol. 31 Issue 2, p60, 2p, 1 Black and White Photograph38Project Management Journal; Jun2000, Vol. 31 Issue 2, p60, 2p, 1 Black and White Photograph
33
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
44/82
CHAPTER 3
METHODOLOGY
3.1 Population
The purpose of this research is to study and find effective ways of control over projects, since
projects are broader area of study and can be of different types, the researcher choose
construction projects as a targeted population, the study has been conducted in five best
construction companies who are currently holding construction projects in Afghanistan , the
targeted construction projects are both vertical and horizontal structures which includes, road
construction, buildings, bridges and energy infrastructure projects.
3.2 Sample Size
A Questionnaire designed consists of 10 questions asking the respondents giving their ideas
on what project control is. What areas to be controlled in a project? And what methodologies
to be used to control cost, schedule and performance also it includes finding the effective
ways to control cost, schedule and performance; the questionnaire contains both multiple
choice and short descriptive questions. A sample of questionnaire is attached in appendix
section of this research.
The questionnaire is distributed among 20 project managers with construction experience
from different construction companies who are currently holding construction projects in
Afghanistan, the respondents of questionnaires are qualified project managers with 4 to 42
years of project management experience and with the experience of managing of both
vertical and horizontal construction projects with the highest project value of $1.2 billion.
3.3 Procedure
The information in this research is manipulated from primary and secondary sources of
information, the primary source of information is the questionnaires distributed among
project managers from different large construction companies, the researcher disseminated
questionnaires via emails and personnel visits, and later than the researcher had a timely
34
8/10/2019 Thesis Research Project -- A Case Study on Effective Ways to Control a Project-- Ehsanullah Najib Reg#302-06111
45/82
visits with respondents to recollect the questionnaires, the time period for dissemination and
recollection of questionnaires was planned 15 days. The researcher used books, journals, and
research papers from internet and libraries for collecting of secondary information and the
time period for secondary information was planned 30 days.
3.4 Research Tools
3.4.1 Primary Data: The primary data of this research is the information collected
form 20 project managers; this information was generated from a questionnaire with
10 specific questions of both close and open ended on the research topic, the
researcher distributed the questionnaires for pr