Microsoft O365
Microsoft O365 Project
• Shared Tenant Status
• Multiple Tenant Committee Status
• O365 Decision Package Update
• Project Timeline Update
• Transition / Education Team
Shared Tenant
Agencies using Office 365 in Pilot or Production
SharePoint Online
• DFW
• DSB
• DVA
• DRS
• ESD
• HCA
• MIL
• PARKS
• UTC
• WaTech
OneDrive for Business
• ESD
• MIL
• PARKS
• UTC
Exchange/Skype for Business
• MIL
Power BI
• HCA
• OFM
• PARKS
• WaTech
• GOV
• LNI
Project Online
• ESD
• WaTech
Dynamics 365
• DFW
• DVA
• PARKS
• UTC
Multi-factor Authentication
• MIL
• ESD
• PARKS
• WaTech
Agency Adoption 2016-Present
4,350
160 0
8,788
2,297
1,021
10,199
2,324 1,877
0
2000
4000
6000
8000
10000
12000
Azure Active Directory (AAD) Office 365 Enterprise Mobility + Security(EMS)
Jan-17
Jan-18
Jun-18
Agency Adoption 2016-Present
125
0
220177
75
651
212136
1,450
0
200
400
600
800
1000
1200
1400
1600
ADFS Federations Dynamics 365 OneDrive for Business
Jan-17
Jan-18
Jun-18
Agency Adoption 2016-Present
Multiple Tenant
Multiple Tenant Committee
• Committee created to develop and test an enterprise multiple tenant environment
• Members: DSHS, ECY, DOL, WaTech
• Project Management / Technical Expertise: Microsoft
• Approach: Agency’s collaborate on requirements, Microsoft defines the architecture
• Architecture meeting occurred Tuesday August 14, 2018
• Draft Architecture review and questions
• Review and identify additional validation cases
• (3) Representatives from each of the above agencies and Microsoft
GOAL: Secure, Supportable, Cost-effective Environment That Supports Multiple Microsoft Tenants (including a shared tenant) and Maintains Enterprise Collaboration!
Next Steps….
• Microsoft to complete design within six weeks – estimated week of September 24, 2018
• Proof of concept – work will be completed in pieces over 15 weeks
• Proof of concept approval – Week of December 2, 2018
O365 Decision Package
2020 – 2021 Decision Package
• GOAL:
• Migrate 57 agencies within Enterprise Active Directory to O365• Mitigate need for every agency to ask for a decision package to migrate
• Replace the following on-premise services with O365• Email
• SharePoint
• AirWatch
• Secure Email
• Skype
• Vault will be a different work effort due to records policies for each agency
• Complete migration by December 31, 2020 (This is the GOAL, a lot of unknowns)
Decision Package Ask: $33M
• Ask Includes:
• Cloud Highway / Express Route / Express Route Traffic Design
• Migration specialist (Vendor)
• Education/Transition team
• Internal technical team
• Microsoft PFE hours
• Microsoft O365 specialist support (Microsoft Office PODS)
• External Project Management
• Oversight
• Change Management
• NOTE: Agencies must still fund licensing separately
Migration Specialist Estimates
• Estimates based on discussions with other states and corporations:
• $65 - $100 per mailbox
• $180 per hour per resource mailbox
• $35 - $50 per Skype account
• $1000 - $2000 per SharePoint Site collection (they do not go by Farm but by site collection, and if template the costs increase)
• $75 per mobile account (Airwatch to InTune)
• $100 per mailbox conversion from current vault to O365 compliance (if agencies request)
• $1 million for planning and preparation for migration
• All of the above are estimates and the decision package is based on the highest estimation value.
Project Timeline
Jun-18 Dec-207/1/18 10/1/18 1/1/19 4/1/19 7/1/19 10/1/19 1/1/20 4/1/20 7/1/20 10/1/20
Oct 18 – Dec 18BUILD Pre-prod
environments for Exchange & Skype
Nov 18 – Jan 19Test EV.cloud
(Veritas archive solution)
Jan 19 – Mar 19TEST Hybrid
Exchange & Skype
Feb 19 – May 19TEST Integration of O365 &
EV.cloud
Mar 19 – Jun 19CONFIGURE Production
Exchange & Skype
Agency Readiness Timeline – O365 Migration
Mar 19 – Jun 19DECOMMISSION SharePoint Farm
REVEW TEAM: Is there more detail we need to add around the decommissioning of
SharePoint? It feels like it just shows up here without much prep work to decommission so
I added this duration box as a placeholder.
June 2020 – Dec 2020Agency Migration of Mailboxes
July 2018 – April 2019RFP Developed for:
Migration vendor, QA vendor & contract PM
GREEN = AGENCY READINESS
GRAY = WATECH REACINESS
Aug 181st of 3 Agency Education/Transition Teams Formed
Oct 18 – Nov 18MIGRATE EV12
DP FUNDED
Project FTEs start (Technical, transition teams) Contract vendors start (Migration, QA, PM)WaTech Transition Teams:
Plan for migration with agencies Develop tools (checklists) for
migration Coordinate with and support agencies
in readying for migration
7/31/18
Exchange 2016 Upgrade
Complete
10/15/18
Pre-prod availablefor agency
ECM testing(Optional)
Aug-19
Move CenteraData to target
1/1/2019 - 6/28/2019
Legislative SessionDPs under review
Jul-19 - Sep-19
EV.cloud Exit Plan:Develop, Communicate
to agencies
6/30/19
Exchange & SkypeHybrid Readyfor Agencies
7/31/20
Enterprise SharePoint Farm Decommissioned
Feb-19 - Feb-19
EV12 Communication Plan: Develop, communicate
to agencies
9/17/18
IdentifyTest Agencies for EV.cloud
(Veritas) Archive Pilot
12/28/18
Agency ID FixesComplete
Complete DBK Fix Synch to AAD Cloud Identity
Extend Identity to Cloud
Sep-19
Based on EV Exit Plancustomer selects:
- EvCloud- Ev Archive
-Agency ECMDec-20
All ExchangeMailboxes Migrated andThe following in O365:
- Skype - MDM
SharePoint Online-OneDrive for Business
-Secure EmailVault?
Nov-19 - Jan-20
Mail Relay Exit Plan:Develop, communicate
to agencies
1/1/19
Earliest agencies could Migrate mailboxes
(All ID Fixes MUST be resolved)
Oct-19
Cloud Transport Enabled(aka Cloud Hwy/Express Route)
Oct-19 - Dec-19
Secure Email Exit Plan: Develop, Communicate
to agencies
July 2018
Purple=technology readyRed=critical milestone/activity
Jun-18 Oct-19Jul-18 Oct-18 Jan-19 Apr-19 Jul-19 Oct-19
WaT
ech
Sh
are
d T
en
an
t T
ime
line
July 2018
Purple=technology readyRed=critical milestone/activity
Services available to agencies in production today
SharePoint Online
OneDrive for Business
Power BI Pro
Office O365 ProPlus Desktop Suite
Dynamics 365 CRM
Dynamics 365 Finance & Operations
Visio Online
Project Online
Office 365 Multi-factor Authorization (MFA)
6/28/19
DPs Approved
6/30/19
Exchange & Skype for BusinessHybrid Production Ready
10/31/18
DelegatedAdministration
Model Approved by EAD SC
10/9/18
Records Mgmt.Enterprise Policy
SettingsApproved by EAD
8/14/18
DLP/IRM Enterprise Policy
SettingsApproved by EAD
1/31/19
All agencies sync'd to Azure AD
6/27/18
OCS Writeback Approved
(Critical Path)
8/10/18
Final DPs Due
7/12/18
EAD SCapproval of
AAD Writeback
7/1/19
RFPs for MigrationVendor, QA Vendor and
PM Vendor Released
8/1/18
Azure SSPR & DeviceRegistration
(w/ writeback)
10/9/18
eDiscoveryEnterprise Policy
SettingsApproved by EAD
Future Releases
Teams InTune Phase 1 – SCCM InTune Phase 2 – BYOD MDM InTune Phase 3 - MAM
Transition / Education Team
Transition Assistance
• Team preparing checklists and other materials
• Will begin scheduling Agency meetings in September
• Team can educate regarding licenses
• Team will schedule educational sessions with Microsoft for Agencies
• Weekly Update through GovDel to start September