Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
TOLEDO BEND PROJECT
LOWER SABINE RIVER HEC-RAS HYDRAULIC MODEL
CALIBRATION/VERIFICATION REPORT FERC PROJECT NO. 2305
Prepared for: SABINE RIVER AUTHORITY OF TEXAS
and SABINE RIVER AUTHORITY, STATE OF LOUISIANA
Prepared by: HDR|DTA
Portland, Maine
May 2011
Toledo Bend Project Sabine River Authority FERC Project No. 2305
i
1.0 EXECUTIVE SUMMARY
The joint licensees of the Toledo Bend Project (FERC No 2305) (Project), the Sabine River
Authority of Texas (SRA-TX) and the Sabine River Authority of Louisiana (SRA-LA)
contracted with HDR|DTA to develop an unsteady flow hydraulic model of the Sabine River
downstream of the Project. The model is intended to be used to assist in evaluating the impact of
various operational scenarios of the Project on flow fluctuations extending from immediately
downstream of the Toledo Bend Dam to Shoats Creek at river mile 54. The hydraulic model was
developed using the one-dimensional U.S. Army Corps of Engineers Hydrologic Engineering
Center River Analysis System, HEC-RAS version 4.1.0 (USACE 2010a).
The purpose of this calibration/verification report is to document inputs and assumptions used in
the development of the Lower Sabine HEC-RAS model to demonstrate that the model
reasonably characterizes flow behavior downstream of the Project due to project peaking
operations, and that the model is adequate for use in evaluating the hydraulic-related effects of
alternative operating scenarios. The calibration process is used to estimate hydraulic parameters
and refine model geometry to optimize replication of observed data under a range of flow
scenarios. Verification assesses the reliability of the model under different hydrologic conditions
than those used for calibration.
HDR|DTA performed model calibration and verification using time series of water surface
elevations and flows recorded at downstream USGS gages as well as recorded river stages at
numerous levelogger locations throughout the modeled reach. The measured values were
compared to model results at the same locations. Calibration was conducted for the period of
August 8th through October 8th, 2009. The first four weeks of this period are representative of
typical Project operations, with the two Project turbine-generator units operating at full capacity
for 6 hours per day during the week and no unit operation on the weekends and a continuous
flow of approximately 150 cfs being discharged at the spillway. There was minimal impact on
flow patterns due to precipitation or unusual tributary contribution during this period. The
second half of the calibration period experienced periods of rainfall and increased tributary flows
on top of variable unit operations, which significantly impacted downstream flow patterns. The
Toledo Bend Project Sabine River Authority FERC Project No. 2305
ii
Lower Sabine HEC-RAS model was calibrated to optimize timing and magnitude of peak
elevations and the magnitudes of changes in elevation when compared to observed.
The modeled verification period extended from August 10th through September 24th, 2010.
During the first 4 weeks of this period the operations consisted of a single unit at full capacity for
2 hours on Mondays and Wednesdays and for 4 hours on Fridays, with no unit operations over
the weekends. Beginning on September 10th, both units commenced continuous operation for a
period of 11 days (continuous operating scenario). Continuous flows from the spillway occurred
throughout the verification period. The continuous operating scenario was included in the
verification run to further test the capabilities and limitations of the Lower Sabine HEC-RAS
model under varying Project operations. During the 11-day continuous operating scenario,
modeled flows began to overtop banks near river mile 77 approximately 30 hours after the
hydrograph began to rise at that location. This model is not designed to accurately simulate the
complex connectivity with the Sabine River floodplain that occurs under high tributary inflows
or unusual operation patterns. Powerhouse peaking flows under low and moderate tributary
contributions do not result in general overbank flooding. Model testing determined that flows
remained within cross section extents throughout the modeled reach for up to 20 hours of 2-unit
continuous operation during the September 2010 base flow conditions.
In the opinion of HDR|DTA, verification results show the Lower Sabine HEC-RAS model
compares favorably to measured data and is appropriate for use in evaluating the effects of
alternative operating scenarios compared to the base case normal peaking operations currently
used at the Project. As with any model, accuracy is highly dependent on input data, and
consequently, model results should be viewed in a relative, rather than an absolute context.
i
TOLEDO BEND PROJECT
LOWER SABINE RIVER HEC-RAS HYDRAULIC MODEL
CALIBRATION/VERIFICATION REPORT
TABLE OF CONTENTS Section Title Page No.
1.0 EXECUTIVE SUMMARY ........................................................................................ I
2.0 INTRODUCTION ................................................................................................ 2-1
3.0 LOWER SABINE HEC-RAS MODEL DEVELOPMENT ......................................... 3-1
3.1 CHANNEL GEOMETRY ........................................................................................ 3-6 3.2 HYDRAULIC PARAMETERS ............................................................................. 3-10 3.3 MODEL HYDROLOGY ........................................................................................ 3-11
4.0 MODEL CALIBRATION AND VERIFICATION ........................................................ 4-1
4.1 CALIBRATION ....................................................................................................... 4-1 4.2 VERIFICATION SCENARIO ................................................................................. 4-6
5.0 SUMMARY AND CONCLUSIONS ........................................................................ 5-1
5.1 SUMMARY .............................................................................................................. 5-1 5.2 CONCLUSIONS ...................................................................................................... 5-1
6.0 REFERENCES .............................................................................................. 6-1
APPENDICES APPENDIX A - CALIBRATION INFLOW HYDROGRAPHS APPENDIX B - CALIBRATION RESULTS
ii
TOLEDO BEND PROJECT
LOWER SABINE RIVER HEC-RAS HYDRAULIC MODEL
CALIBRATION/VERIFICATION REPORT
LIST OF FIGURES Figure Title Page No.
FIGURE 2-1 MODELED REGION OF THE LOWER SABINE RIVER SYSTEM ................. 2-3
FIGURE 3-1 LOWER SABINE HEC-RAS MODEL REACH NETWORK FROM DAM TO RULIFF GAGE (USGS 08030500) ................................................................... 3-2
FIGURE 3-2 LOWER SABINE HEC-RAS MODEL REACH NETWORK IN THE VICINITY OF THE TOLEDO BEND DAM ............................................................................ 3-3
FIGURE 3-3 LOWER SABINE HEC-RAS MODEL CHANNEL PROFILE FROM SPILLWAY TO RIVER MILE 35 .......................................................................................... 3-8
FIGURE 3-4 HABITAT SURVEY TRANSECT CHANNEL GEOMETRIES – RIVER MILE 139 .............................................................................................................. 3-9
FIGURE 3-5 LOWER SABINE HEC-RAS MODEL EXAMPLE CROSS SECTION 136.43 – SABINE RIVER 04 .......................................................................................... 3-10
FIGURE 4-1 LOWER SABINE HEC-RAS MAXIMUM CHANGES IN WEEKLY STAGE . 4-4
FIGURE 4-2 LOWER SABINE HEC-RAS MAXIMUM CHANGES IN DAILY STAGE DURING WEEKLY OPERATIONS ....................................................................... 4-5
FIGURE 4-3 VERIFICATION RESULTS AT BURKEVILLE GAGE (USGS 08025360) ... 4-7
FIGURE 4-4 VERIFICATION RESULTS AT BON WIER GAGE (USGS 08028500) ....... 4-8
FIGURE 4-5 VERIFICATION RESULTS AT RULIFF GAGE (USGS 08030500) ............ 4-8
iii
TOLEDO BEND PROJECT
LOWER SABINE RIVER HEC-RAS HYDRAULIC MODEL
CALIBRATION/VERIFICATION REPORT
LIST OF TABLES
Table Title Page No.
TABLE 3-1 LOWER SABINE RIVER USGS GAGE INFORMATION ........... 3-4
TABLE 3-2 LOWER SABINE HEC-RAS MODEL LEVELOGGER INFORMATION ........................................................................................... 3-4
TABLE 3-3 LOWER SABINE HEC-RAS MODEL HABITAT TRANSECT LOCATIONS ................................................................................................. 3-5
Toledo Bend Project Sabine River Authority FERC Project No. 2305
2-1
2.0 INTRODUCTION
The joint licensees of the Toledo Bend Project (FERC No 2305) (Project), the Sabine River
Authority of Texas (SRA-TX) and the Sabine River Authority of Louisiana (SRA-LA)
contracted with HDR|DTA to develop a hydraulic model of the Sabine River system downstream
of the Project. The model is intended to be used to assist in evaluating the impact of various
operational scenarios of the Project on flow patterns extending from immediately downstream of
the Toledo Bend Dam to Shoats Creek near river mile 54. The model extent is shown in Figure
2-1.
The hydraulic model was developed using the one-dimensional U.S. Army Corps of Engineers
Hydrologic Engineering Center River Analysis System, HEC-RAS version 4.1.0. The Lower
Lower Sabine HEC-RAS model simulates the routing of unsteady flows, extending from the
tailrace and spillway channels at the base of the dam to the downstream model boundary at the
Ruliff Gage (USGS 08030500) near river mile 35. The downstream model boundary is at a
sufficient distance not to influence flows at Shoats Creek, the downstream limit of interest for the
study. In addition to downstream routing, the HEC-RAS model is capable of simulating
backwater flow effects of powerhouse discharge on the spillway channel upstream of the tailrace.
HDR|DTA performed model calibration and verification using time series of water surface
elevations and flows at three downstream USGS gages and relative depths at levelogger
locations throughout the river system. These measured values were compared to model results at
the same locations. The calibration process is used to estimate hydraulic parameters and refine
model geometry to optimize model replication of the observed data under a range of flow
scenarios. Verification assesses the reliability of the Lower Sabine HEC-RAS model under
different hydrologic conditions than those used to calibrate the model.
Required model input includes separate time series of reservoir outflows into both the tailrace
and the spillway, as well as estimated tributary and accretion flows throughout the modeled
reach. The Lower Sabine HEC-RAS model is intended to simulate flows within the banks of the
primary channel, connected side channels and local off-channel storage. Complex floodplain
Toledo Bend Project Sabine River Authority FERC Project No. 2305
2-2
connectivity is not modeled and simulations of operations scenarios which result in overbank
flows beyond the extents of the model cross sections are not recommended. This type of
overbank flow may occur infrequently at some locations above RM 54 when peaking operations
are combined with high tributary accretion flows. Separate studies of bottomland forest
conditions found that the Sabine River bottomland ecosystem is in very good condition and
displays the characteristics of a healthy bottomland system (HDR|DTA 2011). Model testing
determined that flows remained within cross section extents throughout the modeled reach for up
to 20 hours of non-peaking 2-unit continuous operation during the September 2010 flow
conditions.
Toledo Bend Project Sabine River Authority FERC Project No. 2305
2-3
Figure 2-1 Modeled Region of the Lower Sabine River System
Toledo Bend Project Sabine River Authority FERC Project No. 2305
3-1
3.0 LOWER SABINE HEC-RAS MODEL DEVELOPMENT
The Lower Sabine HEC-RAS Study Area extends from the Toledo Bend Dam to Shoats Creek at
RM 54. To insure no impact from model boundary conditions at Shoats Creek, the model was
extended to the Ruliff Gage (USGS 08030500) at RM 35. The model includes the Sabine River
and three major tributaries, Bayou Toro, Bayou Anacoco, and Big Cow Creek, from the location
of the USGS gage on each tributary to their confluence with the Sabine River. The tributary
channels were modeled in order to approximate hydrograph attenuation from the gaged flow
location to the confluence. In addition, the model includes the tailrace channel and the current
spillway channel, as well as the old spillway channel and connected Bayou Toro loop to account
for additional channel storage. Figures 3-1 and 3-2 illustrate the reach network and the naming
of each reach segment between junctions.
The Lower Sabine HEC-RAS model geometry is based on a Triangular Irregular Network (TIN)
digital elevation model which was developed primarily from the USGS National Elevation
Dataset 1/9th Arc-Second (NED 1/9) 3-meter resolution LiDAR data (USGS 2011a) using
Geographical Information Systems (GIS)-based methodologies. The LiDAR data were
augmented by NED 1/3rd Arc-Second 10-meter resolution USGS DEM data (USGS 2011b) near
the spillway and in the upstream portions of the tributary reaches. The model datum is the North
American Vertical Datum of 1988 (NAVD88), which differs from mean sea level by -0.26 feet
near the dam and +0.15 feet at the Ruliff Gage (USGS 08030500). HEC-GeoRAS version 4.2.93
was used to cut cross sections from the elevation model and establish reach lengths and reach
connectivity. HEC-RAS is a one-dimensional model, so river meanders are taken into account
by distinguishing main channel and left and right overbank distances between each cross section.
The NED 1/9 LiDAR-derived data provide ground surface elevation information above the water
surface, so sub-water surface channels must be added after importing the cross-section data into
HEC-RAS. When modeling within-banks channel flows, the primary function of the LiDAR
data is to accurately establish bank locations and elevations, channel shape to the extent it is
depicted above the water surface, connections to off-channel storage, and the two-dimensional
flow line geometry.
Toledo Bend Project Sabine River Authority FERC Project No. 2305
3-2
Figure 3-1 Lower Sabine HEC-RAS Model Reach Network From Dam to Ruliff Gage (USGS 08030500)
Toledo Bend Project Sabine River Authority FERC Project No. 2305
3-3
Figure 3-2 Lower Sabine HEC-RAS Model Reach Network in the Vicinity of the Toledo
Bend Dam
Toledo Bend Project Sabine River Authority FERC Project No. 2305
3-4
Cross section locations were based on locations of observed data, including the USGS gage and
levelogger locations listed in Tables 3-1 and 3-2, as well as the habitat assessment survey
transect locations in Table 3-3 from the July 2010 study. Additional cross sections were placed
to capture significant surface geometry features, such as potential off-channel storage or
locations with lower bank elevations, and to retain sufficient cross-section spacing.
Table 3-1 Lower Sabine River USGS gage information
USGS Station Station Name/Location HEC-RAS Reach
ID
HEC-RAS Cross
Section 8025360 Sabine River at Toledo Bend Reservoir near Burkeville, TX N/A N/A 8025500 Bayou Toro near Toro, LA Bayou Toro 01 76407.62 8026000 Sabine River near Burkeville, TX Sabine River 04 131.64 8028000 Bayou Anacoco near Rosepine, LA Bayou Anacoco 01 137705.9 8028500 Sabine River near Bon Weir, TX Sabine River 05 91.35 8029500 Big Cow Creek near Newton, TX Big Cow Creek 01 177822.3 8030500 Sabine River near Ruliff, TX Sabine River 06 35.3 8031000 Cow Bayou near Mauriceville, TX N/A N/A
Table 3-2 Lower Sabine HEC-RAS model levelogger information
Levelogger No. HEC-RAS Reach ID
HEC-RAS Cross
Section Location (State)
Levelogger Time
Interval 146a Sabine River 01 145.95 Spillway (LA) 5-min
145-BT1 Bayou Toro 01 877.44 Toro Bayou (LA) 5-min 145 Sabine River 03 145.03 Spillway (LA) 5-min 143 Sabine River 03 142.88 Spillway (LA) 5-min
141-TR1 Tailrace 01 141.8 Tailrace at pipeline (TX) 5-min 140b Sabine River 04 139.9 Sabine River (LA) 5-min 136 Sabine River 04 135.65 Sabine River (TX) 5-min 133 Sabine River 04 133.02 Sabine River (TX) 5-min 120 Sabine River 04 120 Sabine River (LA) 15-min 114 Sabine River 04 113.6 Sabine River (LA) 15-min 100 Sabine River 05 99.66 Sabine River (LA) 15-min 90 Sabine River 05 89.96 Sabine River (LA) 15-min 82 Sabine River 05 82.56 Sabine River (LA) 15-min 73 Sabine River 05 73.25 Sabine River (TX) 15-min 63 Sabine River 06 63.1 Sabine River (LA) 15-min 55 Sabine River 06 55.03 Sabine River (LA) 15-min
Toledo Bend Project Sabine River Authority FERC Project No. 2305
3-5
Table 3-3 Lower Sabine HEC-RAS model habitat transect locations
Habitat Transect ID HEC-RAS Reach ID HEC-RAS
Cross Section
146-1 Sabine River 01 146.68 146-2 Sabine River 01 146.55 146-3 Sabine River 01 146.44 146-4 Sabine River 01 146.30 146-5 N/A N/A 146-6 Sabine River 01 146.10 143-1 Sabine River 03 142.88 143-2 Sabine River 03 143.02 143-3 Sabine River 03 143.1 143-4 Sabine River 03 143.16 143-5 Sabine River 03 143.26 143-6 Sabine River 03 143.3 143-7 Sabine River 03 143.43 143-8 Sabine River 03 143.56 143-9 Sabine River 03 143.75 141-1 Tailrace 01 141.25 141-2 Tailrace 01 141.3 141-3 Tailrace 01 141.37 141-4 Tailrace 01 141.44 141-5 Tailrace 01 141.49 141-6 Tailrace 01 141.56 141-7 Tailrace 01 141.69 141-8 Tailrace 01 141.8 141-9 Tailrace 01 141.94 139-1 Sabine River 04 139.67 139-2 Sabine River 04 139.78 139-3 Sabine River 04 139.9 139-4 Sabine River 04 140.02 139-5 Sabine River 04 140.13 139-6 Sabine River 04 140.28 132-1 Sabine River 04 132.57 132-2 Sabine River 04 132.38 132-3 Sabine River 04 132.25 132-4 Sabine River 04 132.13 132-5 Sabine River 04 131.99 132-6 Sabine River 04 131.82 120-1 Sabine River 04 120.18 120-2 Sabine River 04 120.28 120-3 Sabine River 04 120.43 120-4 Sabine River 04 120.6
Toledo Bend Project Sabine River Authority FERC Project No. 2305
3-6
Habitat Transect ID HEC-RAS Reach ID HEC-RAS
Cross Section
120-5 Sabine River 04 120.74 120-6 Sabine River 04 120.85 105-1 Sabine River 04 104.58 105-2 Sabine River 04 104.75 105-3 Sabine River 04 104.93 105-4 Sabine River 04 105.06 105-5 Sabine River 04 105.16 105-6 Sabine River 04 105.35 90-1 Sabine River 05 91.15 90-2 Sabine River 05 91.03 90-3 Sabine River 05 90.88 90-4 Sabine River 05 90.73 90-5 Sabine River 05 90.59 90-6 Sabine River 05 90.44 72-1 Sabine River 05 71.43 72-2 Sabine River 05 71.55 72-3 Sabine River 05 71.67 72-4 Sabine River 05 71.77 72-5 Sabine River 05 71.93 72-6 Sabine River 05 72.05 64-1 Sabine River 06 64.15 64-2 Sabine River 06 64.9 64-3 Sabine River 06 65.03 64-4 Sabine River 06 65.15 64-5 Sabine River 06 65.3 64-6 Sabine River 06 65.42
3.1 CHANNEL GEOMETRY
The digital elevation model provides the basic HEC-RAS model structure. Additional details of
sub-water surface channel shapes and vertical placement of the channels must be added for each
cross-section. Because the HEC-RAS model solves one-dimensional unsteady flow equations,
cross sections are essentially evaluated based on area versus elevation, so exact details of
channel shape are not essential for an accurate model. However, imperfect knowledge of
channel cross-section geometry and the slope between cross sections, or channel profile, can lead
to over or underestimation of flow volume and momentum, resulting in local differences in water
surface elevations when compared to actual measured values. The goal of model calibration is to
Toledo Bend Project Sabine River Authority FERC Project No. 2305
3-7
minimize these differences and sufficiently simulate the overall flow behavior of the river system
under the range of flow conditions intended.
The Sabine is an alluvial river system that can substantially adjust its geometry over time in
response to changes in stream flow and sediment load, especially as a result of high flow
conditions. These changes include channel profile, the meandering river geometry in plan view,
and cross-sectional form. USGS Fact Sheet 2010-3005 (Heitmuller et al. 2010) describes
changes in the channel cross sections near the Bon Wier Gage (USGS 08028500) over time,
demonstrating the significant variation in invert depth and changes in channel area versus
elevation. It is difficult to precisely model this type of dynamic alluvial system and explicitly
account for the degree of local variability in channel invert and shape. However, it is possible to
model representative flow behavior based on calibration to key locations.
HDR|DTA estimated a smoothed average channel profile to use in the model, not accounting for
local profile roughness. The profile shape is based on elevation information provided by SRA-
TX, elevations of USGS cross sections at the three downstream gages, and model calibration.
Figure 3-3 shows the HDR|DTA model profile in comparison to measured values, estimated
average slopes based on an analysis of DEM data (derived from Phillips 2007), and prior model
profiles (KBR 2010, Brown and Root 1993). The profile was used to set the invert elevation of
each channel cross section.
Toledo Bend Project Sabine River Authority FERC Project No. 2305
3-8
-20
0
20
40
60
80
100
34 54 74 94 114 134 154
Elev
atio
n (f
eet N
AVD
88)
River Mile
HDR|DTA HEC-RAS Channel Profile
Brown and Root Study
KBR Inundation Model
SRA Field Measurements (estimates)
USGS Gage Cross Section Inverts
Philips Slopes
Figure 3-3 Lower Sabine HEC-RAS Model Channel Profile From Spillway To River Mile 35
Channel cross sections were estimated from habitat survey transects and USGS gage cross-
section data. The habitat surveys provided 11-point depth profiles and stream widths for 6 to 9
transects at each of 10 study locations throughout the Sabine River, the spillway and the tailrace.
HDR|DTA assumed a uniform distribution of the depth measurements across each transect and
reconstructed representative channel geometries from these surveys. An example of the transect
geometries is shown in Figure 3-4. These geometries were used at the associated model cross
sections and also to approximate representative channel geometry at all other cross sections
within the river, spillway and tailrace. Representative geometries were chosen for each of these
cross sections based on channel width, location relative to the measured transect, and location
relative to river bends and straight sections. Geometries at some cross sections were adjusted
during the calibration process.
Toledo Bend Project Sabine River Authority FERC Project No. 2305
3-9
Figure 3-4 Habitat Survey Transect Channel Geometr ies – River Mile 139
Model cross sections were further refined by adding components such as levees and ineffective
flow areas. Without these, HEC-RAS computes flow area versus elevation for the entire cross
section, even if there is no connection between two regions of equal elevation within the same
cross section. In this case, the entire area is considered capable of conveying water. Levees can
be added to prevent inclusion of a portion of the cross section in the flow area calculation until
the levee is overtopped. These should be added in locations where there is no connection
between the channel and low-lying areas outside of the channel. Ineffective flow areas are added
where there is a connection with the channel, but the connected area acts as storage and does not
actively contribute to downstream flow. Accurate simulation of off-channel storage requires
careful cross-section placement to capture these regions, and post-processing using elevation
maps to determine connectivity to establish ineffective flow locations. An example cross section
with ineffective flow is shown in Figure 3-5.
Toledo Bend Project Sabine River Authority FERC Project No. 2305
3-10
Figure 3-5 Lower Sabine HEC-RAS Model Example Cross Section 136.43 – Sabine River 04
The bridges at the Burkeville Gage (USGS 08025360) and Bon Wier Gage (USGS 08028500)
were included in the model, as well as the railroad bridge below the Bon Wier Gage. It was not
necessary to model the bridge at the Ruliff Gage (USGS 08030500) because the model uses the
Ruliff Gage rating curve as the downstream boundary condition. Bridge geometry at the gages
was derived from the KBR inundation model, and the railroad bridge geometry was estimated
from aerial photos.
Tributary profiles were approximated using a constant slope and model cross sections were
interpolated to reduce model instability resulting from long distances between the cross sections
cut from the digital elevation model. The primary purpose of modeling the tributaries up to the
USGS gage location was to allow the model to approximate attenuation of the inflow
hydrograph.
3.2 HYDRAULIC PARAMETERS
The physical laws which govern open-channel flow are conservation of mass and conservation of
momentum. These laws are expressed as differential equations within the model. The
momentum equation takes into account pressure forces, gravitational force, and boundary drag,
Toledo Bend Project Sabine River Authority FERC Project No. 2305
3-11
or frictional force. The solution of these equations is a function of channel geometry (area and
profile) and channel roughness. Channel roughness is represented by Manning’s n coefficients.
Manning’s n is highly variable and is a function of surface roughness, vegetation, channel
irregularities, scour and deposition, obstructions, size and shape of the channel, stage and
discharge, seasonal changes, temperature, and suspended material and bedload (USACE 2010b)
The Lower Sabine River can experience large variations in stage and discharge during typical
Project peaking operations. During the calibration process HDR|DTA determined that Manning’s
“n” varies considerably as a function of discharge. This is not unusual, as low flows result in
higher friction losses because of local variation in the channel profile resulting from pools,
riffles, and sand bars, and a much higher wetted perimeter to area ratio. HEC-RAS
accommodates the specification of roughness factors to scale Manning’s “n” as a function of
discharge. This model feature was used during calibration to optimize the Lower Sabine HEC-
RAS model, matching elevations and timing of observed hydrographs. The scaling factor ranged
from a value of 4 in the tailrace to an average of 1.6 in downstream reaches.
Additional energy losses are modeled using expansion and contraction coefficients, which are
important at locations with abrupt changes in channel conveyance, and losses related to bridge
pier configuration. The Lower Sabine HEC-RAS model was relatively insensitive to these loss
coefficients and typical values were chosen.
3.3 MODEL HYDROLOGY
The Lower Sabine HEC-RAS model requires specification of inflow boundary conditions at the
following locations:
1. The first cross section in the tailrace channel, representing unit operations and leakage.
2. The first cross section in the spillway channel, representing gate operations.
3. The first cross section of each of the three modeled tributaries: Bayou Toro, Bayou
Anacoco, and Big Cow Creek.
4. At 16 cross sections throughout the reach below the tailrace junction, representing
approximate accretion flows.
Toledo Bend Project Sabine River Authority FERC Project No. 2305
3-12
5. The first cross section of the old spillway – a minimal flow of 0.25 cfs is used to fulfill
the model requirement for flow within each reach.
For the calibration and verification runs, the tailrace and spillway flows were derived from 15-
minute flow data from the Toledo Bend Reservoir Gage (USGS 08025360). These data
represent a composite of unit flows, unit leakage and gate flows and must be separated.
HDR|DTA assumed the minimum flow occurring at the spillway of 144 cfs and an approximate
wicket gate leakage of 35 cfs when the units are not in operation.
The tributary inflows were calculated from 30-minute USGS gage data for Bayous Toro and
Anacoco, and 15-minute data for Big Cow Creek. The flows were prorated by the ratio of
drainage area at the confluence to the drainage area at the gage.
Sub-basin delineation and drainage areas were provided by SRA-TX (Figure 2-1.) One or two
small tributaries were identified within each of the 15 sub-basins, and model cross sections
upstream of these tributaries were chosen as inflow locations. The sub-basin flows were
estimated using area-prorated combinations of the average daily flows at the four USGS tributary
gages within the basin. Gaged flows used to approximate the ungaged sub-basin flows were
chosen based on the relative location of the sub-basin. Average daily flows were used rather
than the higher resolution data in order to smooth the effects of hydrograph peaks local to the
gaged basins. This method approximates accretion flows throughout the reach.
HDR|DTA developed an additional hydrology inflow data set that is representative of daily flows
for the calendar year for the gaged and ungaged subbasins. This data set is derived from
proration and combination of the average daily flows at the four gaged subbasins for the
maximum extent of the overlapping period of record, from 1955 to the present. The purpose of
this data set is to provide a common base flow scenario for assessing the relative impacts of
alternative operating schemes. A “Base Case” scenario can be run using this data set and unit
and gate inflow time series developed to represent base case operations. Alternative operations
scenarios should be run using the same base case subbasin inflow hydrology for comparison to
the Base Case operations scenario.
Toledo Bend Project Sabine River Authority FERC Project No. 2305
3-13
The downstream boundary condition is set as the rating curve at the Ruliff Gage (USGS
08030500) shown in Figure 3-6. This boundary condition specifies water surface elevation
based on the model flows calculated from the differential equations. Sensitivity testing using a
normal depth boundary condition based on channel slope confirmed that water surface profiles
throughout the entire modeled system, and of particular interest, at the downstream limit of
investigation at Shoats Creek near RM 54, are insensitive to the downstream boundary condition.
0
5
10
15
20
25
30
0 20,000 40,000 60,000 80,000 100,000 120,000 140,000
Stag
e (f
eet N
AVD
88)
Flow (cfs)
Figure 3-6 Rating Curve: Ruliff Gage (USGS 08030500)
The HEC-RAS model also requires initial conditions in terms of flow at the top of each channel,
at every reach junction, and at the downstream model boundary. Initial conditions influence
flow in the reach at the beginning of the model run, especially for cases with rapidly varying
flows. This impact can be seen in the calibration and verification scenarios discussed in the
following sections. For the Sabine River model, it is best to compare flows after an initial
weekly operations cycle has established realistic base flows throughout the model.
Toledo Bend Project Sabine River Authority FERC Project No. 2305
4-1
4.0 MODEL CALIBRATION AND VERIFICATION
4.1 CALIBRATION
The calibration process is used to estimate hydraulic parameters and refine model geometry to
optimize model replication of the observed data under a range of flow scenarios. HDR|DTA
performed model calibration using time series of stage and flow at the three Lower Sabine River
USGS gages and relative depths at levelogger locations throughout the river system. Modeled
water surface elevations and the timing of hydrograph peaks were compared to observed data at
the same locations. Differences were minimized by adjusting channel shapes, channel profile,
Manning’s n, and the discharge-dependent roughness factors. The goal was to achieve an overall
“best match” to observed data throughout the river system and to replicate changes in stage
related to daily and weekly unit operations sequences.
Calibration was conducted for the period of August 8th through October 8th, 2009. The inflow
hydrographs for the tailrace and spillway channels are shown in Appendix A, Figure A-1. The
hydrographs were developed from the combined flow data provided by the USGS for the Toledo
Bend Reservoir Gage (USGS 08025360). To split the hydrograph, HDR|DTA assumed the
continuous flow at the spillway of 144 cfs, and wicket gate leakage into the tailrace of 35 cfs
during non-operation. The tributary inflow hydrographs are shown in Figure A-2.
Calibration results at the three downstream USGS gages are shown in Figures 4-1 through 4-3.
The blue line represents the modeled stage and the red line represents the observed USGS Gage
stage data. Comparison to observed data is appropriate after the first few days of modeled
operations in order to eliminate the effects of initial conditions. Observed stages at the USGS
Gage cross sections represent actual measured elevations and these locations were emphasized
during model calibration.
Toledo Bend Project Sabine River Authority FERC Project No. 2305
4-2
Figure 4-1 Calibration Results at Burkeville Gage (USGS 08025360)
Figure 4-2 Calibration Results at Bon Wier Gage (USGS 08028500)
Toledo Bend Project Sabine River Authority FERC Project No. 2305
4-3
Figure 4-3 Calibration Results at Ruliff Gage (USGS 08030500)
The first four weeks of the calibration period are representative of typical peaking operations,
with the two Project units operating at full capacity for 6 hours per day during the week and no
operation on the weekends. There was minimal impact on flow patterns from precipitation or
tributary contribution during this period. The Lower Sabine HEC-RAS model replicated
observed results well during this portion of the calibration period. Figures 4-4 and 4-5 illustrate
a comparison of modeled and observed weekly and mid-week minimum and maximum stage and
maximum rise throughout the reach. In general, modeled results overestimate peak elevations at
all observed locations, including the tailrace. This may result from several factors, including
overestimation of inflows into the tailrace, the distribution of roughness factors relative to the
magnitude of discharge, inaccuracies related to levelogger measurements, and model geometry.
Toledo Bend Project Sabine River Authority FERC Project No. 2305
4-4
0
2
4
6
8
10
12
14
16
0
10
20
30
40
50
60
70
80
90
100
30 50 70 90 110 130 150
Diff
eren
ce b
etw
een
Max
and
Min
Wat
er S
urfa
ce E
leva
tion
(fee
t)
Wat
er S
urfa
ce E
leva
tion
(fee
t)
River Stationing from Downstream to Upstream (Miles) Max Weekly Min Weekly Obs Max Weekly Obs Min Weekly Change in WSEL-Weekly Obs Change in WSEL-Weekly
Figure 4-4 Lower Sabine HEC-RAS Maximum Changes in Weekly Stage
Toledo Bend Project Sabine River Authority FERC Project No. 2305
4-5
0
2
4
6
8
10
12
14
16
0
10
20
30
40
50
60
70
80
90
100
30 50 70 90 110 130 150
Diff
eren
ce b
etw
een
Max
and
Min
Wat
er S
urfa
ce E
leva
tion
(fee
t)
Wat
er S
urfa
ce E
leva
tion
(fee
t)
River Stationing from Downstream to Upstream (Miles) Max Daily Min Daily Obs Max Daily Obs Min Daily Change in WSEL-Daily Obs Change in WSEL-Daily
Figure 4-5 Lower Sabine HEC-RAS Maximum Changes in Daily Stage Dur ing Weekly Operations
The second half of the calibration period experienced periods of rainfall and significant tributary
flows which impacted the upstream and downstream flow patterns resulting from operations.
This portion of the calibration period was more difficult to replicate because of uncertainties
associated with proration of tributary flows and the estimated average daily ungaged accretion
flows. Base flows underlying operations flows are not well represented, especially below Bayou
Anacoco. Differences in base flows affect peak arrival times and stages. However, the general
stage pattern resulting from operations is still apparent.
Toledo Bend Project Sabine River Authority FERC Project No. 2305
4-6
Hydrographs comparing modeled stages and relative levelogger stages at upstream and
downstream locations are shown in Appendix B. Stages at the levelogger locations were derived
from depth data with no association to an actual elevation. These results were vertically shifted
to generally match at low-flow elevations and visually demonstrate changes in measured depth
relative to the modeled results.
Figure B-1 shows the comparison of modeled elevations to the levelogger response in the
tailrace. Some backwater effects resulting from high flows from Bayou Toro can be observed in
the second half of the calibration period. Figures B-2 through B-5 demonstrate backwater effects
of operations flows in the channel originating from the spillway and in Bayou Toro. The timing
and elevation of the backwater hydrograph peaks in the spillway channel match the levelogger
data extremely well during the weekly operations in the first half of the calibration period. The
peaks in Bayou Toro differ by approximately a foot. Figures B-6 through B-16 show the
modeled to observed hydrograph comparisons for the levelogger cross sections downstream of
the tailrace.
4.2 VERIFICATION SCENARIO
The modeled verification period extended from August 10th through September 24th, 2010.
During the first 4 weeks of this period the operations consisted of a single unit at full capacity for
2 hours on Mondays and Wednesdays and for 4 hours on Fridays, with no unit operations over
the weekends. Beginning on September 10th, both units commenced continuous operation for a
period of 11 days. This period was included in the verification run to further test the capabilities
and limitations of the model under increased flow conditions.
Figures 4-3 through 4-5 show verification results at the three USGS gages. Although exact
elevations and depth changes are not replicated at every location, the pattern of flows is well-
represented throughout the river system for the different operating scenarios. The slightly
skewed hydrographs relative to observed data at the Bon Wier Gage (USGS 08028500) resulting
from the 4-hour unit operation are a result of the discharge-dependent roughness factors. The
Toledo Bend Project Sabine River Authority FERC Project No. 2305
4-7
peak flows fall within the range of rapidly changing Manning’s n and the HEC-RAS model
results appear to be less reliable.
The favorable comparison to observed results during the continuous operations period at the
Burkeville Gage (USGS 08025360) and Bon Wier Gage (USGS 08028500) demonstrates that the
model is capable of reliably simulating these higher flows. However, the model response at
Ruliff Gage (USGS 08030500) demonstrates the model limitation to within-bank flows. The
observed hydrograph has a slower rising limb, indicating connection to off-channel storage and
overbank flows that are not simulated in the hydraulic model. Under the continuous operating
scenario, modeled flows began to overtop banks near river mile 77 approximately 30 hours after
the hydrograph begins to rise at that location. This model is designed to simulate Project
peaking operations, and not connectivity with the floodplain that may occur when powerhouse
flows are at maximum and tributary flows are high. Model testing determined that flows
remained within cross-section extents throughout the modeled peaking operations.
Figure 4-3 Ver ification Results at Burkeville Gage (USGS 08025360)
Toledo Bend Project Sabine River Authority FERC Project No. 2305
4-8
Figure 4-4 Ver ification Results at Bon Wier Gage (USGS 08028500)
Figure 4-5 Ver ification Results at Ruliff Gage (USGS 08030500)
Toledo Bend Project Sabine River Authority FERC Project No. 2305
5-1
5.0 SUMMARY AND CONCLUSIONS
5.1 SUMMARY
The purpose of this calibration and verification report is to document inputs and assumptions
used in the development of the Lower Sabine HEC-RAS hydraulic model to demonstrate that the
model reasonably characterizes hydraulics within the modeled river system and is a reliable tool
for evaluating the hydraulic-related effects of alternative operating scenarios on upstream and
downstream flows and water surface elevations. As with any model, accuracy is highly
dependent on input data, and consequently, model results should be viewed in a relative, rather
than an absolute context.
5.2 CONCLUSIONS
The Lower Sabine HEC-RAS hydraulic model was calibrated and verified using two separate
periods of operation. The calibration process was used to adjust model geometry and hydraulic
parameters to best match observed stages at USGS Gages and relative changes in depths at
levelogger locations. Calibration at the three downstream USGS Gages was emphasized because
stages were tied to surveyed datums at these locations.
A separate verification scenario was run with a different weekly operating pattern to assess the
model calibration. Although exact elevations and depth changes are not replicated at every
location, the pattern of flows is well-represented throughout the river system for the different
operating scenarios. The verification scenario included a period of continuous operation of both
units. The comparison to observed results during this period demonstrates that the model is
capable of simulating higher flows adequately. However, this model is not designed to
accurately simulate the complex connectivity with the Sabine River floodplain that occurs under
high tributary inflows or unusual operation patterns. Powerhouse peaking flows under low and
moderate tributary contributions do not result in general overbank flooding. Model testing
determined that flows remained within cross section extents throughout the modeled reach for up
to 20 hours of 2-unit continuous operation during the September 2010 base flow conditions.
Toledo Bend Project Sabine River Authority FERC Project No. 2305
5-2
HDR|DTA has developed representative average daily flows for the calendar year to provide
“Base Case” hydrology for gaged tributary and ungaged basin inflows. These flows were based
on prorated and combined discharge data from the four tributary USGS Gages. Scenarios
developed to assess relative impacts of alternative operating schemes should all be run using the
same period of Base Case hydrology.
In the opinion of HDR|DTA, verification results show the Lower Sabine HEC-RAS model
compares favorably to measured data, reasonably characterizes the upstream and downstream
flow regime resulting from Project operations, and is appropriate for use in evaluating the effects
of alternative operating scenarios compared to the base case normal peaking operations currently
used at the Project. However, appropriate use of the results is cautioned. As with any model,
accuracy is highly dependent on input data, and consequently, model results should be viewed in
a relative, rather than an absolute context.
Toledo Bend Project Sabine River Authority FERC Project No. 2305
6-1
6.0 REFERENCES Brown & Root. 1993. Sabine River Flood Study, prepared for the Sabine Basin Task Force. HDR|DTA. 2011. Toledo Bend Relicensing Project, FERC No. 2305, Lower Sabine River Bottomland Connectivity Study Report. 116 pp. Heitmuller, F.T., Greene, L.E., and Gordon, J.D. 2010. An overview of historical channel
adjustment and selected hydraulic values in the lower Sabine and lower Brazos River Basins, Texas and Louisiana. U.S. Geological Survey Fact Sheet 2010–3005. 4 p.
KBR. 2010. Investigation and Analysis of Dam Break Floods. Technical Report. January 2010. U.S. Army Corps of Engineers’ (USACE). 2005. HEC-GeoRAS Software, Version 4.2.93.
Hydrologic Engineering Center. U.S. Army Corps of Engineers, Davis, CA. September 2005.
———. 2010a. HEC-RAS River Analysis System software, Version 4.1.0. Hydrologic
Engineering Center. U.S. Army Corps of Engineers, Davis, CA. January 2010. ———. 2010b. HEC-RAS River Analysis System Hydraulic Reference Manual Version 4.1.
Hydrologic Engineering Center. U.S. Army Corps of Engineers, Davis, CA. January 2010. U.S. Geologic Service (USGS). 2011a. 1/9 Arc-second Seamless National Elevation Dataset
(raster digital data). EROS Data Center. Sioux Falls, South Dakota. Data available from U.S. Geological Survey. [Online] URL: http://seamless.usgs.gov/index.php. (Accessed February 18, 2011.)
_______. 2011b. 1/3 Arc-second Seamless National Elevation Dataset (raster digital data).
EROS Data Center. Sioux Falls, South Dakota. Data available from U.S. Geological Survey. [Online] URL: http://seamless.usgs.gov/index.php. (Accessed February 18, 2011.)
pw:\\PWAPPTPA01:SouthEast_Tampa\Documents\Sabine_River_Authority_of_Texas\246_0001Toledo_Bend_Relicensin\Sabine_SF_Field_Support\06.00_Engineering\HEC-RAS Model\ToledoBendHEC-RASDraft-051011 (2)
APPENDICES
APPENDIX A
CALIBRATION INFLOW HYDROGRAPHS
Appendix A - Page 1
Figure A-1 Calibration Scenario Inflow Into Tailrace and Spillway
Appendix A - Page 2
Figure A-2 Calibration Scenario Inflow Into Tributaries
APPENDIX B
CALIBRATION RESULTS
Figure B-1 Calibration results at Cross Section 141.8 Tailrace
Figure B-2 Calibration results at Cross Section 142.88 Sabine River Above Tailrace
Figure B-3 Calibration results at Cross Section 145.03 Sabine River Above Tailrace
Figure B-4 Calibration results at Cross Section 145.95 Spillway
Figure B-5 Calibration results at Cross Section 877.4456 Bayou Toro
Figure B-6 Calibration results at Cross Section 139.9 Sabine River
Figure B-7 Calibration results at Cross Section 135.65 Sabine River
Figure B-8 Calibration results at Cross Section 133.02 Sabine River
Figure B-9 Calibration results at Cross Section 120 Sabine River
Figure B-10 Calibration results at Cross Section 113.6 Sabine River
Figure B-11 Calibration results at Cross Section 99.66 Sabine River
Figure B-12 Calibration results at Cross Section 89.96 Sabine River
Figure B-13 Calibration results at Cross Section 82.56 Sabine River
Figure B-14 Calibration results at Cross Section 73.25 Sabine River
Figure B-15 Calibration results at Cross Section 63.1 Sabine River
Figure B-16 Calibration results at Cross Section 55.03 Sabine River