Apptis Proprietary & Confidential – Do Not Copy Tools and Measures: Project Planning and Control Presented to the NIH Project Management Community Presented to the NIH Project Management Community October 10, 2007 October 10, 2007 Michele Duell, VP, Apptis Healthcare Solutions Michele Duell, VP, Apptis Healthcare Solutions

Tools and Measures: Project Planning and Control

  • Upload
    renata

  • View
    24

  • Download
    0

Embed Size (px)

DESCRIPTION

Tools and Measures: Project Planning and Control. Presented to the NIH Project Management Community October 10, 2007 Michele Duell, VP, Apptis Healthcare Solutions. - PowerPoint PPT Presentation

Citation preview

Page 1: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

Tools and Measures: Project Planning and

Control

Presented to the NIH Project Management Community Presented to the NIH Project Management Community October 10, 2007October 10, 2007

Michele Duell, VP, Apptis Healthcare SolutionsMichele Duell, VP, Apptis Healthcare Solutions

Page 2: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

Case Study – Ice Cube Maintenance System

The chilly ice cube department needed an enterprise software program to control routine and special ice cube maintenance and procurement procedures

Beltway custom systems integrations (CSI Beltway) brought a COTS application to chilly and managed the project

COST-LOTS owned a proprietary client-server ice cube maintenance program

Page 3: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

Project Kick-off

Chilly presented their 307 system requirements

CSI beltway’s project manager accepted the requirements and agreed to the FFP costs and the schedule

COTS-LOTS agreed to modify their client-server architecture to a browser-based solution (at no cost)

Page 4: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

Meltdown in Progress

•Software configuration – now development – continued for months beyond the original schedule

•Testing failed

•Progress reports were missed or misleading

•Cost overruns were at 300%

Page 5: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

What’s Missing?

•Project Plans/Lifecycle – loose/non-existent

•WBS - missing

•Progress Measurements/Reviews – missing

•Requirements Stability – missing

Page 6: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

A Detailed Project Plan Is the First Line of Defense Against Project Problems

• Establishes vision and scope

• Establishes budget and schedule

• Identifies risks and their mitigations

• Project resource identification (time, money, staff)

• Stakeholder involvement (reviews, change management)

Page 7: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

Gaining Benefit From the Project Plan

• Simulation of the project

• Approval document

• Internal contract

• Budget document

• Reality check

Page 8: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

How to Simulate the Project?

• To start very simply, go with the rule of thirds

• Iterations = phases = milestones

• Divide and conquer

Page 9: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

High Level Work Breakdown Structure

Page 10: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

Detailed Work Breakdown Structure

Page 11: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

Use the Resource Tab in the WBS to Track Budget

• Assign staff to tasks• Record the costs for using each resource• Earned value is now easy to calculate

Page 12: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

Project Plan May Be Used to Track Earned Value

• Steps to view earned value totals for a task:– On the view menu, click more views.– In the views list, click task sheet, and then click apply.– On the view menu, point to table, and then click more

tables.– In the tables list, click earned value, and then click

apply.

Page 13: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

All the Earned Value Formulas Will Be Displayed

Tip: To get detailed information about each Earned Value field, hover over its heading to see more information.

Page 14: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

Why Earned Value?

• Earned Value is a standardized method for measuring performance

• Common Earned Value measurements across PMO

• Used consistently, Earned Value contributes to success

Page 15: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

Most Common Earned Value Formulas

• BCWS – Budgeted Cost of Work Scheduled

• BCWP – Budgeted Cost of Work Performed

• ACWP – Actual Cost of Work Performed

• EAC – Estimate at Complete

Page 16: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

Ice Cube Maintenance – Gap From Requirements to Solutions

• Quality requirements and avoiding mistakes

• Provide for negotiation and iteration

• Discover missing information or incorrect assumptions

• Define relative priorities

• Eliminate ambiguous language

Page 17: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

Three Purposes of Requirements Management

• Gain agreement on requirements between all stakeholders

• Provide a basis for software design

• Produce a specification for testing

Page 18: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

More Than Project Planning and Requirements Management

• Many other aspects of project management• Balancing act • Confusing process with goals

Page 19: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy

One Framework for Assessing Current and Future Needs Is the Maturity Model Approach

• Adoption of a known model is a highly effective method of determining performance measures

• All of the formal models provide the ability to measure ROI

• Continuous improvement is inherent in the formal models, allowing for increased service without increasing resources

• Formal models include the CMMI, ITIL, EVMS, PMI, NIST 800-26

Page 20: Tools and Measures: Project Planning and Control

Apptis Proprietary & Confidential – Do Not Copy