TOWN HALL Presented By The Division of the State Architect
&
The Office Of Public School Construction And Project
Certification
Project Closeout And Project Certification Policy 09-04: 90 Day
Letters & Reopening Files for Certification Purpose &
Application Purpose
To streamline the process for issuing 90-Day Letters, and to
improve the re-opening of files when a project is closed without
certification Application Applies to ALL projects As of January 1,
2010, the re-opening fee for all projects will be based on a
projects construction cost regardless of closing date Project
Closeout: Background
Project certification is the process DSA uses to determine that a
project has been constructed compliant with the codes governing
school construction A project may be closed with our without
certification Project Closeout: Background
The 90-Day Letter initiates the closing & certification
process.The letter is issued when: The DSE determines the project
is essentially complete The project becomes occupied Construction
stops for one year or more DSA received a final verified report
from the project inspector and/or the design professional in
responsible charge of the project. Project Closeout:
Background
The 90-Day Letter requests that all outstanding requirements and
documents be submitted to DSA within 90 days (and lists the missing
documents) Close of File & Certification
After 90 days, DSA will close the file with or without
certification A letter of certification will only be issued if all
missing documents have been submitted and all outstanding issues
have been resolved DSA will take no further action on a closed file
until DSA receives a request from the Architect or school/college
district to re-open and re-examine the file in order to certify the
project Re-Opening & Re-Examining
A request from the Architect or school/college district to re-open
and re-examine a closed, uncertified project must include: A letter
with the project name & DSA Application number requesting that
the file be re-examined for certification A copy of the DSA Closed
Without Certification Letter A single COMPLETE comprehensive
package that includes all items, documents and issues listed on the
DSA Closed Without Certification Letter All outstanding Change
Orders, Addendums and Revisions or alternate documents, must be
approved prior to submitting the re-opening package. The re-opening
fee (if applicable) Fees After January 1, 2010 No fee is required
for a one-time project re-opening request received within 9 months
from the date the DSA 90-Day Letter expires After 9 months (or for
any 2nd or subsequent re-opening request), the fee is based on the
project construction cost $500 for projects less than $5 million
$750 for projects between $5 million and $50 million $1000 for
projects greater than $50 million Responsibility of Requester
Partial or otherwise incomplete submittals will be accepted DSA
will issue an updated Closed Without Certification Letter to show
remaining deficiencies Submitting parties have 90 days to resolve
deficiencies to obtain certification If more than 90 days pass
without resolution/DSA approval, the project will again be closed
WITHOUT certification Another re-opening fee is required to be paid
each time it is necessary to re-open the file At the Discretion of
DSA
90 Day Letters will NOT be extended, except at the discretion of
DSA under the following circumstances: Construction is not complete
& the contractor is still mobilized at the site No portions of
the project are occupied by staff and/or students IR A-20 discusses
new projects associated with uncertified projects IR A-20: New
Projects Associated with Existing Uncertified Projects Policy New
work involving uncertified projects cannot be approved by DSA until
the issue of the underlying certification is resolved DSA will NOT
approve (stamp out) plans and specifications for alteration and/or
addition projects or utilizing portions of, uncertified projects
except when the new project is solely for the purpose of upgrading
fire-life safety (FLS) aspects of the building/campus Exceptions to
Policy The scope of projects accepted for DSA approval under this
policy shall be limited to FLS alterations of the following types:
Campus or system-wide fire alarm upgrade Upgrade/replacement of the
uncertified buildings fire alarm system Written approval of the
alteration plans & specifications will state: The approval is
only for the FLS alteration The building itself remains uncertified
Disclosure The scopes of the projects and the uncertified buildings
on the alteration project must be clearly identified in the
following manner: The scope of the alteration project shall be
clearly shown on the cover sheet or index sheet of the plans Must
include this statement: DSA approval of these plans shall not be
construed as the Certification of Compliance for the following
buildings as required by the Field Act, Education Code Section and
Sections Immediately after the above statement, list all the
uncertified buildings on alteration project Other Projects DSA may
begin review of new projects associated with uncertified projects
but DSA approval of the plans and specifications will be withheld
until the underlying certification issue is resolved Clarifying
Situations
Many situations occur that may or may not involve uncertified
buildings/projects to the extent that a proposed new project may be
affected.This appendix lists some of those situations in an attempt
to provide clarity, uniformity and consistency in the application
of this IR Clarifying Situation Q. The district submits a project
for a fire alarm upgrade and/or fire alarm addition.The project
requires connecting the new fire alarm system/components into a
fire alarm panel that resides in an uncertified building. The new
project submittal must include the following two documents from
NFPA 72 to be completed and submitted with the project. Fire alarm
system record of completion. Fire alarm inspection and testing
form. DSA may begin review of new projects associated with
uncertified projects but DSA approval of the plans and
specifications will be withheld until the underlying certification
issue is resolved Clarifying Situation Q. A school building is not
certified and the district submits an application to DSA for an
alteration or addition to that building. DSA will accept the new
application and provide plan review but will not issue project
approval (stampout) until and unless the issue of certification is
resolved. Clarifying Situations
Q. The district submits an application to DSA for a new building
but the new building depends on portions of an uncertified project
to be minimum code compliant (e.g. accessible restrooms located in
uncertified buildings, path-of-travel part of an uncertified
project, parking part of an uncertified project, etc.). DSA will
accept the new application and provide plan review but will not
issue final approval (stamp out) until and unless the associated
project certification is resolved.(See also Project Certification
Guide on DSA website for potential alternatives). Clarifying
Situation Q. The district submits an application to DSA for a new
project on a campus but the entire campus (or portions of the
campus) is not certified. As long as the new project does not
depend on uncertified construction to satisfy minimum code
requirement (accessible restrooms, path-of-travel, parking, etc.)
DSA will accept the new project as a viable, approvable project.
Clarifying Situation Q.The district submits an application to DSA
for a new classroom building but another ancillary building
(gymnasium, administration building, shade structure, library etc.)
is not certified. As long as the new project does not depend on
uncertified construction to satisfy minimum code requirement
(accessible restrooms, path-of-travel, parking, etc.) DSA will
accept the new project as a viable, approvable project. Project
Certification Guide: Intent and Recent Updates Guideline Goal &
Intent
Provide information, procedures and concepts that lead to: Project
certification Consistency between DSA Regional Offices Projects
have been closed by DSA without certification The guide cannot
possibly address all scenarios or specific situations encountered
during the closeout process Experience and analytical skills are
essential when determining appropriate actions necessary to obtain
project certification Organization of Guideline
SECTION 1 Introduction SECTION 2 Re-Examination of Closed Files
SECTION 3 Contacting DSA SECTION 4 Documents Required For Project
Certification SECTION 5 Resolutions & Strategies For Project
Certification SECTION 6 Unique Structures Appendix Recent Changes
to the Guideline
The guideline has been updated for the following purposes:
Editorial changes Clarifications Updated with new policies and
procedures New alternates Change intent from use of guide for
pre-2007 projects to ALL projects Section 1: Introduction
Added to Section 1.5: If necessary, how can project certification
be proved to DSA? Copy of DSA certification letter Copy of DSA
history card showing certification DSA Tracker shows project is
certified Added to Section (causes for closing inititiation): DSA
received a final verified report from the project inspector and/or
the design professional in responsible charge of the project
Section 1: Introduction
Added to Section (closeout Type 3 letter): Clarifies Type 3 letter
causes Reported deviation in the construction Unconstructed by
required minimum scope Required documents were not received by DSA
or are otherwisemissing Required documentation was not properly
completed Missing testing and/or inspection reports Required
further and/or additional fees owed to DSA have notbeen paid
Unapproved documents such as change orders, deferredapprovals, and
addenda Section 1: Introduction
Added to Section (closeout Type 4 letter): Clarifies Type 4 letter
is reserved for safety related issues Unresolved safety issue Type
4 letter is issued for unresolved SSS, ACS, and/or FLSsafety
related deficiencies Specifically identified by DSA, Inspector or
design professional Missing documents are not considered as cause
to issue a Type4 letter Unconstructed scope, if resulting in a
potential unsafe condition,could cause a Type 4 letter to be issued
Type 4 letters must be approved by the DSA Regional Managerprior to
being issued Section 2: Re-Opening of Files
Change to Section 2.1 (General Requirements): Aligns the
certification guide re-opeing of the information with DSA Policy
09-04 How to file for re-opening Re-opening fee Length of time a
re-opening will be held open for resolution Section 6: Unique
Structures
Added new Section 6.3.7 Relocatable Building Fire Alarm Deferred
Approval California licensed Architect, or Electrical Engineer or
StructuralEngineer causes and witnesses fire alarm inspection and
testingin compliance with NFPA 72 Completion and submittal of NFPA
72, Fire Alarm SystemRecord of Completeness form Completion and
submittal of NFPA 72 Fire Alarm Inspection andTesting form Signed
letter from the Architect or Electrical Engineer orStructural
Engineer stating, I have witnessed the fire alarmsystem test for
the project and in my opinion the alarm is inessential compliance
with NFPA 72 Appendix Read and use Appendix B
Relocatable Buildings General Information on Certification This
appendix explains how relo buildings can be approved for use
depending on their certification status Appendix information can be
used to process relo buildings through DSA. Whats New at DSA
Improved Intake Process at DSA
Problem: Incomplete plans are being submitted to DSA, leading to
delays at intake and in plan review, if the plans are accepted
Solution: Effective March 1, 2010 plans will be considered
incomplete if Form DSA 1 or DSA 3 is missing, or information
required in the form(s), is incomplete or missing. DSA-1
Application for Approval of Plans and Specifications Provides
Project specifics as well as general project scope information
DSA-3 Project Submittal Checklist Provides a listing of documents
needed (i.e., title sheet, site plan, floor plans, structural
drawings, etc) as well as detailed project scope information needed
to allow for an efficient plan review New Intake Process When
required documents are missing at intake:
Incomplete projects will no longer be returned to
Architect/Engineer The Architect/Engineer and School District will
be notified by letter that plans are incomplete, what is missing
and that the plans will be held for four weeks to allow time to
correct the deficiencies If the Architect/Engineer does not comply
within four weeks the plans will be returned Plan reviews will only
commence when a complete submittal is made DSA Bulletin 10-02, DSA
Forms 1 & 3 Electronic Review Submittals ($400,000 or
less)
To allow DSA time to reduce bin time and streamline plan review
process: EffectiveMarch 3, 2010 mandatory submittal of electronic
plans is suspended Projects with an estimated cost not exceeding
$1,000,000 may be submitted electronically The electronic submittal
process will be re-evaluatedJune 20, 2010 Policy 09-02 Access Fees
The Access Fee was doubled effective February 16, 2010
The Access Fee has not been changed since 1984 Since some projects
may already or inadvertently submitted fees under the lesser fee
schedule, the following will apply: DSA will accept Access Projects
with the wrong fees until March 30, 2010 These projects will
receive an application number, but the project will not be stamped
out until the balance of fees due are paid in full Beginning April
1, 2010, the full Access fee must be submitted with the plans
Bulletin 10-01 Automatic Fire Sprinkler Systems (AFSS)
Currently, DSA allows AFSS to be deferred Effective July 1, 2010
AFSS will no longer be deferred Separating AFSS from plans leads to
delays When AFSS finally come in at deferred plan review stage the
plans are usually incomplete, leading to delays stamping plans out
Many of the other plan review jurisdictions in the state do not
allow deferrals of AFSS Policy 10-01 Questions? DSA is online at
www.dsa.dgs.ca.gov Call our offices:
Oakland Regional Office: (510) Sacramento Regional Office: (916)
Los Angeles Regional Office: (213) San Diego Regional Office: (858)
Headquarters: (916) Grid Neutral & The Green Code
Green Schools Grid Neutral & The Green Code Grid Neutral A site
that produces as much electricity as it uses in a year
Defining Grid Neutral A site that produces as much electricity as
it uses in a year Developing a Path to Grid Neutral
A series of workshops were held in 2008 to discuss the critical
steps to becoming grid neutral, including: Comprehensive Planning
Energy Efficient Design Energy Generating Technology Energy
Measurement Maintenance & Operations Innovative Funding
Comprehensive Planning
Assemble the right team Sponsors Beneficiaries Implementers Project
delivery methods Integrated Project Delivery (IPD) Building
Information Modeling (BIM) Energy Efficient Design
Program & Planning Site Selection Building Building Envelope,
Day-Lighting, Cool Roofs Building Systems HVAC, Lighting,
Transformers, Building Control Systems, Commissioning Furnishings,
Fixtures, and Equipment Energy Generating Technology
Photovoltaics (PVs) Solor-thermal Ground source heating pumps
Energy Measurement Benchmarking Utility bill analysis
Monthly usage Seasonal trends Peak demands Load isolation and
profiles Utility bill analysis Problem identification &
correction Conservation program persistence Maintenance &
Operations
Involve maintenance & operations from the start Perform
facility and energy evaluations Provide education & training
Innovative Funding Information on Grid Neutral
A guidebook was published and posted online at: A video about grid
neutral is available on YouTube at: Grid Neutral Guidebook
In addition to covering the six workshop topics, the Grid Neutral
Guidebook establishes these four steps to grid neutral: 1 New
School: Set Energy Performance Goal Existing School: Measure
Current Use, Set Goal 2 Implement & maintain appropriate energy
efficiency & conservation measures to lower electricity use. 3
Install solar or wind systems to create electricity to meet
remaining needs. 4 Maintain energy systems. Monitor electricity
consumption & production. The Green Code Developing the Green
Code
Stakeholders included CASH, CHPS, and the DSA Advisory Boards Green
Committee Used the Building Standards Commissions base code to
determine what measures should be mandatory and which measures
should be voluntary under the DSA-SS Green Code Tiered reach
standards seen in early drafts were ultimately left out of the
final draft of the DSA-SS Green Code Mandatory Measures
(DSA-SS)
Planning & Design Energy Efficiency Indoor Water Use Water
Resistance Construction Waste Reduction Building
Maintenance/Operations Pollutant Control Indoor Moisture Control
& Indoor Air Quality Voluntary Measures (DSA-SS)
The term grid neutral is codified Commissioning included among the
voluntary measures The Green Code includes a checklist of mandatory
and voluntary DSA-SS measures The tiers did not make the final
draft, but the DSA-SS Green Code does define three incremental
levels for grid neutral 35% 75% 100% Where We Are Going Next Steps
Hold a series of workshops bringing together school districts,
vendors, and utilities Collect information from school districts to
develop a database Have school districts obtained and installed
energy generating technologies at no cost?How? Develop an
interactive map Putting Californians to Work
Building Schools Putting Californians to Work SAB Programs School
Facility Program Emergency Repair Program
New Construction Modernization Critically Overcrowded Schools
Joint-Use Charter School Facilities High Performance Incentive
Career Technical Education Facilities Overcrowding Relief Grants
Seismic Mitigation Facility Hardship Emergency Repair Program State
Relocatable Classroom Program Deferred Maintenance Unused Sites
Application and Funding Process OPSC Application Processing
Preliminary review of complete application package Verification of
enrollment information and dwelling units, site visits to verify
classroom inventory 15-day and 4-day letters, if necessary, for
additional information Recommendations to district to maximize
funding Processing to SAB for approval OPSC Efforts to Expedite
Processing
Continuous identification of efficiencies Continuous implementation
of streamlined process improvements Cross-training of OPSC Project
Management teams to accommodate workload fluctuations Improved
customer service and outreach to keep districts informed and
provide application submittal tips that expedite processing Tips
for Expediting Review
Submit complete applications Talk to your OPSC Project Manager Take
advantage of OPSC Outreaches, Workshops, Publications Keep District
Representative information current Keep eligibility information
up-to-date Tips for Expediting Review
Ensure construction work in plans is 60 percent commensurate Ensure
application is signed by District and Architect Review all
certifications on forms Break down cost estimates for combination
projects including multiple facility programs Career Technical
Education Facilities Program (CTEFP)
New facilities ($3 million maximum grant) or reconfiguration of
existing ($1.5 million maximum) Funding for facilities and/or
equipment May be combined with a New Construction or Modernization
application Matching share requirement (loans available) CDE
approves program of study & scores application Reservation of
funds option Future funding cycle/s CTEFP Reservation of
Funds
CTEFP projects with an existing reservation of funds havepotential
for immediate impact on the economy To complete the project
submittal, submit the followingdocuments by the deadline (as
required depending on theproject scope): CDE Plan Approval letter
DSA-approved Plans and Specifications and DSA Plan ApprovalLetter
Detailed construction cost estimate (updated based on
approvedplans) Detailed cost estimate for site development (updated
based onapproved plans) Itemized list of equipment including cost
CTEFP Economic Impact First Cycle Apportionment Distribution
Statewide Totals by Industry Sector Agriculture & Natural
Resources: $28.6 M Arts, Media & Entertainment: $28.5 M
Building Trades & Construction: $23.1 M Education, Child
Develop. & Family Services: $0.6 M Energy & Utilities: $2.6
M Engineering & Design: $23M Fashion & Interior Design:
$0.7 M Finance & Business: $0.1 M Health Science & Medical
Technology:$15.3 M Hospitality, Tourism & Recreation: $22.4 M
Information Technology: $2.0 M Manufacturing & Product
Development: $7.8 M Marketing, Sales & Services: $0.7 M Public
Services: $3.9 M TOTALS $189M $2.3 M $2.4 M $21 M $9.3 M $12.7 M
$24.2 M $10 M $27.5 M $23.7 M $40.1 M $15.5 M 72 Upcoming CTEFP
Deadlines
Districts must submit DSA and CDE project approvals for first cycle
Reservation of Funds projects (approved at the March 26, 2008 SAB
meeting) by 3/26/2010 in order to avoid rescission Third funding
cycle (approximately $90 million available):Application for Career
Technical Education FacilitiesFunding (Form SAB 50-10) due to the
OPSC by 4/1/2010 Expediting Review of CTEFP Submittals
Equipment useful life > 10 years Combined projectsclearly
indicate which classrooms correspond to each application Indicate
associated New Construction or Modernization application number and
project tracking number on Form SAB 50-10, if applicable Full
funding applicationsindicate quantities and unit costs for all
expenditures on cost estimates Expediting Review of Combined
Projects
The review process for hybrid projects is more complex. When
submitting multiple applications under separate programs for a
hybrid project: Provide detailed cost estimates for each
application and a combined cost estimate for the total project
Indicate which classrooms correspond to each application Provide
all supporting documentation Thank You! We value your input Please
send comments and suggestions to: What to Expect in a School
Facility Program Audit School Facilities Program Audit Timeline
& Objectives
Verify self-certifications Verify compliance with statutes and
regulations Review expenditures for compliance Timelines Two years
to commence audit Six months to complete audit, unless School
Facilities Program Audit Process
OPSC pre-planning Audit Engagement Letter Field work OPSC In-house
review Draft Report Final Report OPSC Pre-Planning Identify and
review key regulations and statutes as applicable to project Review
prior OPSC desk reviews Review prior financial and Proposition 39
Audits Contact auditee to arrange entrance conference Audit
Engagement Letter
Fieldwork start date Entrance Conference date/time Audit
manager/supervisor contact information A list of documents required
documents for the audit (general ledgers, construction contracts,
architect contracts, notices to proceed, notices of completion,
warrants, invoices, etc) Field Work Entrance Conference Internal
Control review
Audit objectives Timeframes Internal Control review Accounting
system SFP Project tracking Field Work Site Visits Exit Conference
Preliminary audit findings
Next steps Reporting Draft Report Final Report Supervisory
review
District has 30 days to respond to draft Final Report Include
districts response Final report issued Questions? Steve Inman,
Fiscal Audit Supervisor (916) Michael Watanabe, Fiscal Audit
Supervisor (916) Suzanne Reese, Fiscal Operations Manager (916)
Rick Asbell, Fiscal Operations Manager (916) Additional Contact
Information: Thank You for Attending
From: The Division of the State Architect & The Office of
Public School Construction