33
. TRRC ,, j Gosselin c: Coburn, David Cynthia L. Taub ([email protected]), Vicki Rutson, Kenneth ,%-. Blodgett 10/18/2012 01:03 PM Danielle Gosselin Attorney Advisor Office of Environmental Analysis Surface Transportation Board Tel: (202) 245- Hi David, Attached pleased find letters from OEA regarding TRRC’s third-party contractor request and request to waive the 6 month pre-filing notice. Hard copies to follow. 3rd Party Cont. Letter.pdfPrefiling Waiver Letter.pdf Thanks, Danielle 4’

TR Scan No. 2_Redacted

Embed Size (px)

DESCRIPTION

FOIA Document production from Surface Transportation Board request no. 15-012

Citation preview

Page 1: TR Scan No. 2_Redacted

. TRRC,, j Gosselin c: Coburn, DavidCynthia L. Taub ([email protected]), Vicki Rutson, Kenneth

,%-.

Blodgett

10/18/2012 01:03 PM

Danielle GosselinAttorney AdvisorOffice of Environmental AnalysisSurface Transportation BoardTel: (202) 245-

Hi David,Attached pleased find letters from OEA regarding TRRC’s third-party contractor request and request

to waive the 6 month pre-filing notice. Hard copies to follow.

3rd Party Cont. Letter.pdfPrefiling Waiver Letter.pdf

Thanks,Danielle

4’

oehrlec
Sticky Note
Personal sticky note redacted.
Page 2: TR Scan No. 2_Redacted

SuizAcE TRANSPORTATION BoARDWashington, DC 20423

Office of Environmental Analysis

. . October 18,2012

David H. CobumSteptoe & Johnson LLP1 3 30 Connecticut Avenue, NW

.

Washington, DC 20036

Re: Docket No. FD 30186, Tongue River Railroad Company, Jnc.—RailConstruction and Operation—in Custer, Powder River and RosebudCounties, Mont; Approval of Third-Party Contractor

Dear Mr. Coburn:

Your request for approval under 49 C.F.R. § 1 1 05 . 1 0(d) and 40 C.F.R. § 1 506. 5 forretention of ICF International (ICF) as an independent third-party contractor for the abovereferenced project is approved. ICF will prepare the Environmental Impact Statement on behalfof the Surface Transportation Board (Board) in connection with the proposed project by theTongue River Railroad Company to construct and operate an approximately 80-mile rail linebetween Miles City and Ashland, Montana.

I have attached a disclosure statement that we ask you to forward to ICF to complete.Once the statement is signed by ICF, we request that ICF send it directly to us. As you know,the Board’ s Office of Environmental Analysis will direct, supervise, and control the work of theindependent third-party contractor and will be responsible for all environmental documentationprepared by the independent third-party contractor.

If we can be of further assistance, please feel free to contact me or Ken Blodgett of mystaffat (202) 245

‘ Sincerely,

I Victoria Rutson\J’ Director

Enclosure Office of Environmental Analysis

Page 3: TR Scan No. 2_Redacted

SURFACE TRANSPORTATION BOARD

DISCLOSURE STATEMENT

I, —, certify(name of contractor)

that I have no financial or other interest in the

outcome of the prospective application/petition of the

— to construct a rail(name of applicant/petitioner)

line near

(location)

Signed:

Date:

Page 4: TR Scan No. 2_Redacted

SURFAcE TRANSPORTATION BoARDWashington, DC 20423

1996/

Office of Environmental Analysis

Octoberl8.2012

David H. CoburnSteptoe & Johnson LLP1 330 Connecticut Avenue, NWWashington, DC 20036

Re: Docket No. FD 30186, Tongue River Railroad Company, Inc.—RailConstruction and Operation—in Custer, Powder River and RosebudCounties, Mont.; Waiver of Six-Month Prefihing Notice

Dear Mr. Cobum:

Pursuant to 49 C.F.R. § 1 105.10(c), we are granting your request ofOctober 9, 2012 fora waiver of the six month prefihing notice generally required for construction projects under 49C.F.R. § 1105.1O(a)(l).

On October 3, 2012, the Surface Transportation Board’s (Board) Office ofEnvironmental Analysis (OEA) met with you regarding the proposed construction and operationof a rail line in Custer, Powder River, and Rosebud Counties, Montana. At the meeting, youprovided OEA with an overview ofthe proposed project, and we outlined the generalrequirements of the environmental review process.

On October 1 6, 2012, your client, the Tongue River Railroad Corporation (TRRC), filed arevised application with the Board pursuant to 49 U.S.C. § I 0901 . In the application, TRRC statesthat it is seeking to construct and operate an approximately 80-mile rail line between Miles Cityand Ashland, Montana. The proposed rail line’s northern terminus would be located just westof Miles City, Montana, and the rail line would split into two branches near its southern end inAshland, Montana. The purpose ofthe new rail line would be to serve coal mines in the OtterCreek area.

Based on information from the initial meeting, the history ofthis proceeding, andTRRC’s application, OEA believes that it has adequate information and that the applicant issufficiently aware of the environmental process to grant this waiver request.

Page 5: TR Scan No. 2_Redacted

If you have any questions, please feel free to contact me or Ken Blodgett of my staff at(202) 245- .

DirectorOffice of Environmental Analysis

Sincerely,

Victoria Rutson

2

Page 6: TR Scan No. 2_Redacted

Page 1 of 1

/T FD 30 1 86, Tongue River Railroad CompanyCoburn, David

Vicki Rutson (RutsonVstb.dot.gov)01/11/2013 06:16 PMCc:“BlodgettKstb.dot.gov”Hide DetailsFrom: “Coburn, David” <DCobumsteptoe.com>To: “Vicki Rutson (RutsonVstb.dot.gov)” <RutsonVstb.dot.gov>Cc: “B1odgettKstb.dot.gov” <B1odgettKstb.dot.gov> •

History: This message has been replied to.2Attachments

,

Letter to STh re Alternatives Analysispdf TRRC Alternatives Screening Analysis.pdf ‘t”

Dear Ms. Rutson: Please see the attached alternatives screening analysis prepared byconsultants to Tongue River Railroad Company and a transmittal letter.

Regards. David Coburn/Attorney for Tongue River Railroad Company

David H. [email protected]

Steptoe+1 202 429 8063 direct Steptoe & Johnson LLP+1 202 262 7306 mobile 1330 Connecticut Avenue, NW+1 202 261 0565 fax Washington, DC 20036

www.steptoe.com

This message and any attached documents contain information from the law firm Steptoe & Johnson LLP that may be confidential and/orprivileged. If you are not the intended recipient, please do not read, copy, distribute, or use this information. If you have received thistransmission in error, please notify the sender immediately by reply e-mail and then delete this message.

file:///C:/Users/rutsonv/AppDatalLocaL/Temp/l/notesO9E97I /web7 I 5 8 .htm 1/15/2015

Page 7: TR Scan No. 2_Redacted

DadH.Coburn

[email protected]—--—-

SrEPTOE & JO-t4SON LLP

1330 Connecticut Avenue, NWWashington, DC 20036-17952024293000mainwww.steptoe.com

Januaryll,2013

VIA E-Mail

Ms. Victoria RutsonChiefOffice ofEnvironmental AnalysisSurface Transportation Board395 E Street, SWWashington, D.C. 20423

Re: Finance Docket No. 30186, Tongue River Railroad Company, Inc.--Rail Construction and Operation--In Custer, Powder River andRosebud Counties, MT

DearMs.Rutson:

Please find enclosed a copy of the Alternatives Screening Analysis that has been preparedon behalf of Tongue River Railroad Company, Inc. (“TRRC”) by its contractors, TranSystemsand Hanson Professional Services, Inc.

I also write to confirm that TRRC has previously submitted under separate cover to theBoard’s third-party contractor, ICF, certain technical files concerning TRRC’s preferredalignment and certain of the alternative alignments that your office may consider in connectionwith its review ofthe TRRC application. A description ofthis technical information is providedbelow:

. Four Google kmz files and an exhibit depicting four rail alternatives.

. Design files concerning certain rail alternatives and certain other files depicting theUSGS existing ground model and aerial photography used to prepare the design files.

. Revised Google kmz files and an exhibit depicting various design refinements.

Page 8: TR Scan No. 2_Redacted

Ms. Victoria Rutson. St?PtQe

siro & .OhNfl LU’Januaryll,2013Page 2

Please let me know if you have any questions concerning the information describedabove.

Respectfully,

,/David H. CoburnAttorney for Tongue River Railroad Company, Inc.

Enclosures

cc: Kenneth Blodgett

Page 9: TR Scan No. 2_Redacted

ALTERNATIVES SCREENING ANALYSIS

TONGUE RIVER RAILROADCUSTER, POWDER RIVER, AND ROSEBUD COUNTIES

MONTANA

STB FINANCE DOCKET NO. 30186

Prepared by

I I /

TranSystems

and

‘:HANSONHanson Professional Services Inc.

Januaryll,2013

Page 10: TR Scan No. 2_Redacted

.

Tongue River RailroadAlternatives Screening Analysis

Table of Contents

1. Proposed Action 32. Alternatives Development 3

3.1 CoistripAlternative 53.2 Tongue River Alternative 53.3 Tongue River Road Alternative 63.4 Moon Creek Alternative 6

4. Alternatives Screening Analyses 64. 1 Alternatives Screening Criteria 64.2 Railroad Construction Parameters 74.3 Railroad Operational Issues 74.4 Environmental Impacts to Land Use 11

4.4.1 Miles City Fish Hatchery 114.4.2 Interstate 94 114.4.3 LARRS ii4.4.4 Bureau of Land Management, Block Management Areas and Conservation Easements. 124.4.5 Impacts to Property 12

4.5 Topography and Soils 124.6 Water Resources 12

4.6.1 Surface Water and Wetlands 124.6.2 Groundwater 144.6.3 Floodplains 14

4.7 Biological Resources 144.7.1 Endangered and Threatened Species 144.7.2Flora 154.7.3 Terrestrial Wildlife 154.7.4 Aquatic Ecology 16

4.8 Cultural Resources 164.9 Transportation 164. 1 0 Right-of-Way Acquisition I 74.11 AirQuality 174.12 Noise and Vibration 184l3Parksand Recreation 184.14 Hazardous Materials and Waste Sites 184.15 Socioeconomics 18

5. No-Build Alternative 186. Alternatives Previously Considered and Eliminated from Detailed Study 19

6. 1 Rail Alternatives and Sub-Alternatives I 96.2 Non-Rail Alternatives 20

6.2.1 Conveyor 206.2.2 Coal Slurry Pipeline 216.2.3 Hauling by Truck 216.2.4 Mine-Mouth Power Generation 22

7. Conclusion 22

2 I TranSystems I Hanson

C\temp\TRRC Altemaitves Screening Analysis.DOCX

Page 11: TR Scan No. 2_Redacted

—--.--....‘“ ----—--—----Tongue River Railroad

.

Alternatives Screening Analysis

I . proposed Action

The Tongue River Railroad CompanY, inc. (TRRC) filed a Revised Application for Constructionand Operation Authority with the STB on December 17, 2012. The TRRC revised applicationproposes to construct and operate a rail line between the BNSF branch line at Colstrip, Montanaand Ashland/Otter Creek, Montana. As stated in the Revised Application, the purpose of theproject is to transport low-sulfur, subbitumin0uS coal from proposed and future mine sites inRosebud and Powder River Counties, including the proposed Otter Creek mine. The southernportion of the proposed rail line was previously authorized by the STB’s predecess0r theInterstate Commerce Commission (ICC), in 1986. The proposed line differs from that previouslyauthorized line as follows: (1) the northern connection point with BNSF trackage has beenshifted from Miles City to Colstrip and (2) refinements are being proposed to the previouslyauthorized alignment south of the Tongue River crossing. The proposed refinements addressrail operational considerations, including straightening and shortening the alignment. Also,TRRC does not intend to construct previouslYauth0rized rail lines south of Terminus Point I.BNSF is a partial owner of TRRC, is the proposed operator of the rail line, and is a party to theRevised Application.

The STB has determined that it will conduct a new environmental review of the currently-proposed project. To support the environmental review, a third-party contractor has beenretained to work with the STB’s Office of Environmental Analysis, as provided under the STB’srules.

To assist the STB and its contractor, TRRC provides this Alternatives Screening Analysis ofalternative alignments and other transportation options that have been considered by TRRC.This Analysis identifies four feasible alternatives that TRRC believes should be carried forwardfor further environmental study by the STB and also identifies other alternatives that TRRC hasdetermined are not feasible based on applicable screening criteria and therefore that it believesdo not warrant further detailed study. Detailed map data for each of the four alternatives hasbeen shared with the STB’s third party contractor.

2. AlternatiVes Development

TRRC has identified four rail alternatives that it recommends to be carried forward for furtherstudy, several rail alternatives that were considered bUt that it believes do not warrant furtherdetailed study, and several non-rail alternatives that were considered but that it also believes donot warrant further detailed study. ln assessing these alternatives, TRRC has relied to someextent on information previously gathered on these alternatives, supplemented by current orupdated information where available and relevant. The four rail alternatives that TRRCrecommends for further detailed study are shown on Figure 1.

3 TranSyStems I Hanson

C\temp\TRRC AlterflaitVes Screeflifl9 Analysis DCCX

Page 12: TR Scan No. 2_Redacted

Figure 1 Rail Alternatives Map

Tongue River RailroadAlternatives Screening Analysis

4 I TranSystems I Hanson

C:temp\TRRC Altemaitves Screening Analysis.DOCX

Page 13: TR Scan No. 2_Redacted

Tongue River RailroadAlternatives Screening Analysis

3. Rail Alternatives that Should be Considered for Further Study

3.1 Colstrip Alternative

The Coistrip Alternative was identified in TRRC’s December 17 Application as its preferredroute. The north end of the Colstrip Alternative will connect to the existing BNSF ColstripSubdivision just south of Colstrip, MT and continue east and south, crossing and parallelingCow Creek Road for about seven miles before crossing Rosebud Creek Road and thenGreenleaf Road. The rail line will then run generally parallel to Greenleaf Road for about elevenmiles to the south and east before crossing Tongue River Road and then the Tongue River.From just east of the Tongue River crossing, approximately nine miles north of Ashland, MT, thealignment matches the Tongue River Alternative going south to Ashland, dividing at thebifurcation point and continuing southwest and southeast of Ashland to Terminus Points Iand 2. The total length of new railroad construction for the Coistrip Alternative is about 42 milesincluding the trackage south of the bifurcation point serving both Terminus Points I and 2. Theestimated cost to construct the Colstrip Alternative is $41 6 Million (201 3 Cost). Upgrades to theexisting BNSF Colstrip Subdivision and the connection between the Colstrip and ForsythSubdivisions will be made to bring the branch line upto current main line standards as well.

3.2 Tongue River Alternative

The Tongue River Alternative was previously identified as TRRC’s preferred alternative. TRRChas previously proposed modifications to the version of this Alternative approved by the ICC inI 986 which are designed to straighten curves to facilitate modern unit train movements. It isthis modified version of the Tongue River Alternative that is considered here. This Alternativeoriginates at a wye connection to the existing BNSF mainline at Miles City. The currentconfiguration includes the west leg of the wye passing through the north eastern edge of theMiles City Fish Hatchery. The alignment would cross Interstate 94 beneath a new highwaygrade separation and then follow the west side of the Tongue River south from Miles City. Thisportion of the route would cross the United States Department of Agriculture Livestock andRange Research Station (LARRS). The alignment continues southward west of the TongueRiver, generally on high ground outside the floodplain of the river; however, at a few locations,due to the topography and river meanders, the alignment runs within about 500 to I ,000 feet ofthe river. About I 0 miles north of Ashland, the alignment crosses the Tongue River on a newbridge north of the Northern Cheyenne Indian Reservation in order to access the proposed OtterCreek Mine and Terminus Point I , which are both east of Tongue River. The alignmentcontinues southward on the east.side ofthe river, passing east ofAshland. The railroad wouldcross U.S. Route 212 and Otter Creek on new bridges, and then split into two branches, runningsouthwesterly and southeasterly, respectively, to mine sites at Terminus Points I and 2.Terminus Point I is near the previously permitted Montco Mine site and Terminus Point 2 isnear the proposed Otter Creek Mine site. The total length of new railroad construction is about83 miles, including the trackage south of the bifurcation point serving both Terminus Points Iand 2. The estimated cost to construct the Tongue River Alternative is $625 Million (2013Cost).1

I The cost ofthis option is higherthan the $490 Million cost estimated in TRRC’s October 16, 2012Revised Application for Construction and Operation Authority. That is because additional informationwhich supports the higher cost estimate has been developed since the filing of that Application.

5 I TranSystems I Hanson

Ctemp\TRRC Alternaitves Screening Analysis.DOCX

Page 14: TR Scan No. 2_Redacted

3.3 Tongue River Road Alternative

The northern portiOn of the Tongue River Road Alternative is the same as the Tongue RiverAlternative Both alternatives originate at a wye connection to the existing BNSF mainline atMiles City. The current configuration includes the west leg of the wye passing through thenortheastern edge of the Miles City Fish Hatche. The alignment would cross Interstate 94beneath a new highway grade separation and then follow the west side of the Tongue Riversouth from Miles City. This portion of the route would cross the LARRS. The alignmentcontinues about 2 miles south of the LARRS, and then crosses to the east side of the river on anew bridge. The route continues southward on the east side of the river, generally parallel to theeast side of Tongue River Road until the Tongue River Road turns and crosses to the west sideof the river, about 19 miles north of Ashland. The railroad continues southward Ofl the east sideof the river to Ashland. The portion of this route, from about 10 miles north of Ashland toTerminus Points I and 2, follows the same alignment as the Tongue River Alternative. Thealignment passes east of Ashland, crosses U.S. Route 212 and Otter Creek on new bridges,and then splits into two branches, running50twesterly and50theasterly, respectively, tomine sites at Terminus Points I and 2. The total length of new railroad construction for theTongue River Road Alternative is about 83 miles including the trackage south of the bifurcationpoint serving both Terminus Points I and 2. The estimated cost to construct the Tongue RiverRoad Alternative is $753 Million (2013 Cost).

3.4 Moon Creek Alternative

The Moon Creek Alternative was considered as an alternative to minimize impacts to the MilesCity Fish Hatcher( and the LARRS. This alternative originates at a wye connection to theexisting BNSF mainline, about 8.4 miles west of Miles City. Previous versions of this alignmentoriginated at the old Milwaukee Road alignment and required a new bridge crossing theYellowstone River; the current onfigurati0n does not cross the Yellowstone River. Thealignment runs southward and crosses Interstate 94 beneath a new highway grade separation.The alignment passes through about 2.4 miles of the western edge of the LARRS, and thencontinues50theasterIy along the Moon Creek drainage for about 17.2 miles toward the TongueRiver. The alignment then runs southward along the same alignment as the Tongue RiverAlternative, crossing the Tongue River and continuing southwest and southeast of Ashland toTerminus Points I and 2. The total length of new railroad construction for the Moon CreekAlternative is about 82 miles including the trackage south of the bifurcation point serving bothTerminus Points I and 2. The estimated cost to construct the Moon Creek Alternative is $731Million (2013 Cost).

4. Alternatives screening Analyses

4.1 AlternatiVes screening Criteria

The alternatives described in this Analysis were subjected to screening generally similar toanalyses conducted in the previous studies. The screening criteria included engineeringfeasibility (construction and operating)7environmental nsequence5 discernible at this stage,and cost considerations. In screening alternatives, attention was also paid to the length of thetrack that would need to be constructed, avoiding sensitive areas and reducing knownenvironmental impacts where possible. Track alignment was designed using current main line

6 TranSYstems I Hanson‘“

--

Tongue River RailroadAlternatives 5creening Analysis

C \temP\TRRC AltemaitVes Screening AnaIySSDOCX

Page 15: TR Scan No. 2_Redacted

Tongue River RailroadAlternatives Screening Analysis

standards, including maximum curvature of 2.5-degrees except at connections to existing BNSFtrackage and a maximum ruling grade of 1%, while minimizing cuts and fills to the extentpractical.

Table I summarizes the descriptions, environmental impacts, engineering issues, and relativeadvantages of each of the four alternatives identified for further analysis. Table 2 summarizesthe physical characteristics of each of these alternatives. The following sections discuss thescreening criteria and relevant data applicable to each of the four rail alternatives recommendedfor further study. General observations were made of portions of the potential alignments frompublic roadways. However, due to the lack of site access, no recent field studies have beenconducted to date to evaluate environmental features such as wetlands, flora and fauna, orcultural resources.

4.2 Railroad Construction Parameters

Each of the proposed rail alternatives would utilize conventional steel-wheel on steel-rail trainoperations with diesel-electric locomotives. The rail line would be a single track constructed ofcontinuous-welded rail and would be built and maintained to ERA Class 3 standards. Passingsidings will be constructed at locations to be determined during the design phase, depending onthe alternative selected for construction. The rail line is planned to occupy a minimum right-of-way of 200 feet, although the actual right-of-way at specific locations may vary depending onland acquisition conditions, topography requiring large cuts or fills, or other factors. Rail lineconstruction will include clearing and excavating earth and rock on previously undisturbed land.Due to the variable natural topography, construction will require both cuts and fills. To the extentpracticable, TRRC would attempt to adjust the design profile to balance cut and fill quantities.Typical railway culverts and bridges will be used to cross streams, drainageways, and grade-separated roadways where needed.

4.3 Railroad Operational Issues

TRRC anticipates that at full mine production for the Otter Creek mine, coal tonnage hauled willresult in about 26 round trips per week on a 7-day weekly schedule. Railroad operational issuesassociated with the four rail alternatives are generally associated with the grades encounteredalong each alignment. Estimated ruling grades against loads for each alternative are as follows:

. Coistrip Alternative: I .00% max, with about I 2.76 miles total length against load.

. Tongue River Alternative: 0.94% max, with about I .46 miles total length against load.

. Tongue River Road Alternative: I .00% max, with about I .46 miles total length againstload.

. Moon Creek Alternative: I .00% max, with about 4.88 miles total length against load.

7 I TranSystems I Hanson

C:\temp\TRRC Altemaitves Screening Analysis.DOCX

Page 16: TR Scan No. 2_Redacted

8IT

ranS

yste

ms

IH

anso

n

Tab

leI .

TR

RA

lter

nat

ives

Com

par

isor

Ton

gue

Riv

erR

ailr

oad

Alt

erna

tive

sS

cree

ning

Ana

lysi

s

Env

iron

men

tal/

.

Rou

teA

ltern

ativ

eL

engt

h(m

iles)

.E

nvir

onm

enta

l/O

pera

tion

alA

dvan

tage

sO

pera

tion

alIs

sues

Col

stri

p-4

2m

lto

TP

I&

TP

21.

Req

uire

sne

wgr

ade

sepa

rati

onof

1.S

hort

est

rail

line

leng

th.

us

212,

and

poss

ibly

Ton

gue

Riv

er2.

Lea

stgr

adin

gqu

anti

ties

and

exce

ssR

oad.

exca

vati

on.

2.L

onge

stto

tal

rulin

ggr

ade.

3.H

ighe

st%

para

llel

toex

istin

gtr

ansp

orta

tion

3.L

onge

stco

ntin

uous

rulin

ggr

ade.

corr

idor

s.4.

No

grad

ese

para

tion

of-9

4re

quir

ed.

5.D

oes

not

pas

sth

roug

hor

near

USD

AL

AR

RS.

6.D

oes

not

pas

sth

roug

hor

near

Mile

sC

ityFi

shH

atch

ery.

7.L

east

Rig

ht-o

f-W

ayA

cqui

sitio

n,in

clud

ing

Gra

zing

and

Irri

gate

dL

and

8.L

east

impa

cts

toB

LMla

nds.

9.A

ffec

tsan

dbi

sect

sle

ast#

ofla

ndow

ners

.I 0

.L

owes

tim

pact

sto

Blo

ckM

anag

emen

tA

reas

and

Con

serv

atio

nE

asem

ents

.II

.L

owes

tra

illin

ele

ngth

para

llel

toT

ongu

eR

iver

Val

ley.

12.

Low

est

num

ber

ofst

ream

cros

sing

s.13

.U

tiliz

esex

istin

gB

NSF

trac

kto

acce

ssth

eB

NSF

mai

nlin

e.A

lthou

ghcu

rren

tlylig

htly

used

,po

pula

tion

isac

cust

omed

toth

etr

ack

.

from

Col

stri

pto

the

mai

nlin

ene

arFo

rsyt

h.

Ton

gue

Riv

er—

83m

ito

TP

I&

TP

2I.

Sha

res

long

est

rail

line

leng

thw

ithI.

Lea

stIm

pact

sto

Sta

tean

dC

ount

yL

and.

Ton

gue

Riv

erR

oad

Alte

rnat

ive.

2.S

hare

ssh

orte

stto

tal

rulin

ggr

ade

with

Ton

gue

2.L

owes

t%

para

llel

toex

istin

gR

iver

Roa

dA

ltern

ativ

e.tr

ansp

orta

tion

corr

idor

s.3.

Sho

rtes

tco

ntin

uous

rulin

ggr

ade.

3.R

equi

res

new

grad

ese

para

tion

sof

-94,

US

212,

and

poss

ibly

Ton

gue

Riv

erR

oad.

4.S

hare

shi

ghes

tim

pact

toU

SDA

LA

RR

Sw

ithT

ongu

eR

iver

Roa

dA

ltern

ativ

e.5.

Pas

ses

thro

ugh

Mile

sC

ityFi

shH

atch

ery.

6.H

ighe

stim

pact

sto

Blo

ckM

anag

emen

tA

reas

and

Con

serv

atio

nE

asem

ents

.7.

Hig

hest

rail

line

leng

thpa

ralle

lto

Ton

gue

Riv

erV

alle

y.

C:t

emp\

TR

RC

Alte

mai

tves

Scr

eeni

ngA

naly

sis.

DO

CX

Page 17: TR Scan No. 2_Redacted

Ton

gue

Riv

erR

ailr

oad

Alt

erna

tive

sS

cree

ning

Ana

lysi

s

Env

iron

men

tal?

.

Rou

teA

ltern

ativ

eL

engt

h(m

iles)

.E

nvir

onm

enta

l/O

pera

tion

alA

dvan

tage

sO

pera

tion

alIs

sues

Ton

gue

Riv

er-8

3m

lto

TP

I&

TP

21.

Sha

res

long

est

rail

line

leng

thw

ithI.

Sha

res

shor

test

tota

lru

ling

grad

ew

ithT

ongu

eR

oad

.T

ongu

eR

iver

Alte

rnat

ive.

Riv

erA

ltern

ativ

e.2.

Hig

hest

grad

ing

quan

titi

esan

dex

cess

exca

vati

on3.

Req

uire

sne

wgr

ade

sepa

rati

ons

of-9

4,U

S21

2,an

dpo

ssib

lyT

ongu

eR

iver

Roa

d.4.

Sha

res

high

est

impa

ctto

USD

AL

AR

RS

with

Ton

gue

Riv

erA

ltern

ativ

e.5.

Pas

ses

thro

ugh

Mile

sC

ityFi

shH

atch

ery.

6.H

ighe

stR

ight

-of-

Way

Acq

uisi

tion,

incl

udin

gG

razi

ngan

dIr

riga

ted

Lan

d.7.

Aff

ects

and

bise

cts

high

est

#of

land

owne

rs.

8.P

asse

sne

aror

thro

ugh

mor

ere

side

ntia

ldr

ives

than

othe

rop

tion

s.

Moo

nC

reek

—82

mi

1.S

econ

dhi

ghes

tgr

adin

gqu

anti

ties

and

I .D

oes

not

pas

sth

roug

hor

near

Mile

sC

ityFi

shto

TP

I&

TP

2ex

cess

exca

vati

on.

.H

atch

ery.

2.R

equi

res

new

grad

ese

para

tion

sof

-94,

2.L

ess

impa

ctto

USD

AL

AR

RS

than

Ton

gue

US

212,

and

poss

ibly

Ton

gue

Riv

erR

iver

and

Ton

gue

Riv

erR

oad

Alt

erna

tive

s.R

oad.

3.Im

pact

sU

SDA

LA

RR

S4.

Mos

tim

pact

sto

BLM

land

s5.

Mos

tim

pact

sto

Sta

tean

dC

ount

yla

nd.

6.A

ffec

tsan

dbi

sect

sse

cond

-mos

tnu

mbe

rof

land

owne

rs.

7.S

econ

dhi

ghes

tra

illin

ele

ngth

para

llel

toT

ongu

eR

iver

Val

ley.

8.H

ighe

stnu

mbe

rof

stre

amcr

ossi

ngs.

9IT

ranS

yste

ms

1H

anso

n

C:t

emp\

TR

RC

Alte

mai

tves

Scr

eeni

ngA

naly

sis.

DO

CX

Page 18: TR Scan No. 2_Redacted

Tab

le2.

TR

RR

ail

Alt

ern

ativ

eC

har

acte

rist

ics

.

Ton

gue

Riv

erR

ailr

oad

Alte

rnat

ives

Scr

eeni

ngA

naly

sis

iEit

emab

eig

nmen

t Cha

ract

ehsc

sCo

istrip

Tong

ueR

ier

Tong

ueR

ner

Road

Moo

nC

reek

Leng

thof

New

Main

Trac

kC

onst

ruco

n(M

iles)

42.1

83.1

83.1

81.7

--C

ut(C

ubic

Yar

ds)

118

,100

000

25,3

00,0

0038

,800

000

36,2

00,0

003

Fill

(Cub

icY

ards

)1

1770

0.00

022

,900

000

34,6

00.0

0033

,100

.000

7Ex

cess

Cut

(Cub

icY

ards

)1

.40

0,00

02,

400,

000

4,20

0,00

03,

100,

000

5Le

ngth

ofPu

blic

Roa

dway

lmpa

cted

(Mile

s)8.

38.

992

8.9

ILe

ngth

Alig

nmen

t Par

alle

lsEx

istin

gTr

ansp

orta

tion

Corri

dor (

Mile

s(%

ofN

ewM

ainLe

ngth

))18

.1(5

2.5%

)10

.1(1

3.4%

)37

0(4

9.8%

)10

.1(1

3.6%

)7

iJig

nmen

t Req

uire

sN

ewIn

ters

tate

94C

ross

ing?

NoYe

sY

esYe

s•1

Cou

ntya

ndSt

ate

Publ

icR

oadw

ayC

ross

ings

53

44

9Le

ngth

Jign

men

t Im

pact

sU

SDA

Lhe

stoc

kan

dR

ange

Res

earc

hS

taon

(Mile

s)0.

09.

59.

52.

4•r

AH

gnm

entC

ross

esM

iles

City

Fish

Hat

cher

y?.

NoY

esY

esNo

Rig

ht-o

f-W

aykq

uisi

on(k

res)

22.

400

4,10

045

004,

300

Rig

ht-o

f-W

aykq

uisW

onof

Gra

ngLa

nd(A

cres

)2

1,56

03,

200

3,52

03,

020

13Ri

ght-o

f-Way

Acq

uisit

ion

ofirr

igat

edLa

nd(A

cres

)2

4090

230

90

:Leng

thof

lmpa

ctst

oB

urea

uof

Land

Man

agem

ent(M

iles)

0.7

3.6

2.4

4.6

Leng

thof

Impa

cts

toSt

ate/

Cou

nty

Land

(Mile

s)3.

47.

43.

416

.5

.!N

umbe

rofA

ffec

ted

Lan

dow

ners

344

5360

5417

Num

ber o

fBis

ecte

dL

ando

wne

rs4

3040

4241

MT

FW&

PB

lock

Man

agem

entA

reas

and

Con

sera

onEa

sem

ents

(Mile

s)9.

527

.79.

821

.8

!Le

ngth

Alig

nmen

t Par

alle

lsTo

ngue

Rir

Val

ley(

Mile

s)17

.068

.231

.857

.7N

umbe

rofS

tream

Cro

ssin

gs5

9927

025

029

821

Num

ber o

fRie

rC

ross

ings

11

11

Max

Curv

atur

e(E

xclu

ding

WeT

rack

s)22

0’?2

0’•

2*20

220’

23To

tal

Leng

thof

Cur

es(M

iles)

13.8

414

.81

23.5

417

.56

:Ru

ling

Gra

deC

ompe

nsat

edfo

rHod

ntal

Cun

esw

here

App

licab

le0.

91- 1.

00%

0.86

-0.9

4%0.

91-1

.00%

0.91

-1.00

%

.

Tota

lLe

ngth

ofRu

ling

Gra

deêa

inst

Loa

d6

(Mile

s)W

I-‘dP

I12

.76

1 .46

1.46

4.88

Max

Con

nuou

sLe

ngth

ofR

ulin

gG

rade

Aga

inst

Loa

d6

(Mile

s)7.

150.

801.

464.

8827

Tota

lLe

ngth

ofG

rade

Aga

inst

Load

b(M

iles)

1 8.7

226

.29

26.6

624

.22

28C

once

ptua

l Esf

imat

eofP

roba

ble

Cos

t(201

3$M

illio

n)41

662

575

373

1C

once

ptua

lE

smat

eof

Prob

able

Cos

tPer

Mile

(201

3$M

illio

nlM

ile)

9.88

7.52

9.06

8.95

1In

clud

esgr

adin

gfo

rpro

pose

dsi

ngle

mai

ntra

ckan

dpu

blic

road

relo

cafo

ns,b

utno

tforf

utur

etra

ckat

l5’t

rack

cent

ers

orad

jace

nttr

ack

acce

ssro

ad2

Incl

udes

R)W

forfu

ture

grad

ing

ofse

cond

track

atl5

’ tra

ckce

nter

san

dad

jace

nttr

ack

acce

ssro

ad.3

Affe

cted

Land

owne

risde

fined

here

asa

land

owne

rwho

sepr

oper

tyis

impa

cted

byth

epr

opos

edRi

ght-o

f-Way

4B

isec

ted

Land

owne

r isd

efin

edhe

reas

land

owne

rsw

hose

prop

erty

isim

pact

edan

dsw

ered

byth

epr

opos

edR

ight

ofW

ay5

Pere

nnia

l,In

term

itten

torE

phem

eral

Stre

ams;

may

bein

dica

fie

ofpo

tenf

ialw

efia

ndim

pact

s;.—

--. .

_

6G

rade

Aga

inst

Load

isde

fined

here

asth

eup

hill

grad

ew

hich

load

edtra

ins

mus

tfra

erse

head

ing

north

boun

d

10IT

ranS

yste

ms

IH

anso

n

C:te

mpT

RR

CA

ltern

aitv

esSc

reen

ing

Ana

lysi

s.DO

CX

Page 19: TR Scan No. 2_Redacted

The ruling grade is given as a maximum due to the fact that horizontal curves, and therebycue compensationsi do not apply to the entire length of ruling grade. BNSF has conductedtrain peOrmance modeling on each alternative to determine power and operating requirements.The results of the performance modeling show none of these ruling grades would precluderailroad operations. otably, the modeling indicat5 that the Colstrip alignment does not requireadditional locomotive power to haul current unit coal train lengths despite its longer lengthagainst load. Therefore, none of the four rail alternatives should be discarded based on railroadoperational issues.

4.4 Environmental tmpacts to Land Use

Among the potential environmental0sequenceS associated with the rail alignments aretempOra and permanent impacts to the Miles City Fish Hatche, the LARRS, Interstate 94,and local ranches and farms. Ithough poiOn5 of the rightOfWay for all the alternatives wouldbe acquired from private landowners, it appears that only one residence would be displaced,located north of Ashland on the alignment that is common to all the alternatives underconsideration. The railroad construction and operation may also cause environmental impacts tonatural and cultural resources. These potential environmental impacts that are currentlydiscernible are discussed in the following sections. Additional data will be developed during theEIS process.

4.4.1 Miles City Fish t-latcherY

The Tongue River and Tongue River Road Alternatives originate at ae connection to theexisting BNSF mainline at Miles City. The current nfigUrati0n for both alternatives includes thewest leg of the wye passing through the nohea5tern edge of the Miles City Fish Hatche.TRRC has reached a tentative agreement with the Montana Depament of Fish, Wildlife &Parks for an easement for the proposed railroad to pass through the fish hatche however,mitigation including construction of at least one replacement hatche basin would be required.The Moon Creek and ColstriP Alternatives do not run through or near the Miles City FishHatcherY.

4.4.2 Interstate 94

The Tongue River, Tongue River Road, and Moon Creek Alternatives would cross Interstate 94,likely beneath new highway grade separations. Traffic would be disruPted during construction ofthe overpass structures. The Colstrip Alternative does not require construction of a new highwaygrade separation; the existing BNSF ColstriP Subdivision track already passes beneathInterstate 94.

4.4.3 LARRS

The Tongue River and Tongue River Road Alternatives pass through about 9.5 miles of theeastern edge of the LARRS. Agricultural research could be disrupted to some degree byrailroad construction andlor train operations. The Moon Creek Alternative crosses only about2.4 miles of the western portion of the LARRS. The ColstriP Alternative does not cross or passnear the LARRS.

11 jTranSYStems’Haon“

.-

Tongue River RailroadAlternatives screening Analysis

C\temP\TRRC A1terfla1tV Screening Ana1yS.DOCX

Page 20: TR Scan No. 2_Redacted

4.4.4 Bureau of Land nagement, Block Management Areas and ConserVatb0Easements

The Tongue River, Tongue River Road, and Moon Creek Alternatives pass through about 2.4 to4.6 miles of Bureau of Land nagement parcels while the ColstriP Alternative crosses onlyabout 0.7 mile. ApproximatelY277 miles of the Tongue River Alternative passes throughMontana Fish Wildlife & Parks (MT FW&P) Block anagement Areas and Con5eati0n.Easements compared to 21 .8 miles of the Moon Creek Alternative, 98 miles of the TongueRiver Road Alternative and 9.5 miles of the ColstriP Alternative, which has the lowest impact.

4.4.5 Impacts to PropertY

All of the rail alternatives impact private propey. Some private propeY is impacted by the railalignment along the edge of parcels such that the remainder of the propey is usable, whileother parcels are bisected by the rail alignment such that a poiOfl of the propey may bereduced in utility even though it is not specifically needed for railroad rightOfway The numbersof impacted private properties and bisected private properties are as follows:

30 bisected I 44 impacted.40 bisected 1 53 impacted.42 bisected I 60 impacted.41 bisected I 54 impacted.

4.5 TopOgraPY and Soils

The topography of the area is characterized by hilly, rugged uplands terspersed with wide,rolling valleys. Most of the rail alternatives old run on high ground outside the Tongue Riverbasin, except where the alignments cr055 the Tongue River noah of Ashland and Otter Creekoth of Ashland. Due to the variable topograPhy construction of all the rail alternatives willrequire both cuts and fills. To the extent practicabIe TRRC would attempt to adjust the designprofile to balance cut and fill quantities. Table 2 shows the relative estimated cut and fillquantities.. All the rail alternatives appear to require more cut than fill, resulting in beeen 0.4million to 4.2 million cubic yards of excess earth, with the ColstriP AlternatiVe requiring the

.smallest volume of additional cut. Some of the excess material may be accounted for inmaterial shrinkage when soil and soft rock are cut from existing loose bank conditions andplaced in compacted railroad embankment. The remainder will be utilized onsite in flattened fillslopes.

Soils in the project area are not expected to be unsuitable for railroad construction. pending siteaccess, geotechnical estigatiofls are planned to characterize site soils and developfoundation recommendations for structures and large fills.

4.6 Water Resources

4.6.1 SurfaCe Water and Wetlands

All of the rail alternatives would cross the Tongue River once. The Tongue River, Moon Creek,and CoI5triP Alternatives all croSS the Tongue River at a location about I 0 miles noah of

Tongue River RailroadAlternatives 5creening Analysis

. ColStflP Alternative:

. Tongue River Alternative:

. Tongue River Road Alternative:

. Moon Creek Alternative:

‘12 TranSYStems I Hanson—

--.

----. .C:\temp\TRRC Altemaitves Screening Analysis DCCX

Page 21: TR Scan No. 2_Redacted

tongUe River RailroadAlternatives reening AnalysiS

Ashland. The Tongue River Road Alternative crosses the Tongue River about I 0 miles south ofthe BNSF connection at Miles City. The southern poiOfl of the railroad 5oth of the bifurcationpoint beeen ackage to Terminus points I and 2, which 5 common to all thealternatives crosses Qer Creek southeast of Ashland. All the alignments would cr055 othersmall streams and inagewaYs using culve5 and bridges depending on the length of thecrossing. Table 2 summarizes the required numbers of stream ros5ings estimated by revieWingUSGS0pograPhic maps and aerial photograPhY. Due to the lack of site access, no field studieshave been to date to veri the numbers or characteristics of potential to becrossed. The estimated numbers of stream ros5ings for each alternat including the tongueRiver and Otter Creek cros5ings are as follows:

. Col5tflP Alternative:

. Tong River Alternative:

. Tongue River Road Alternative:

. Moon Creek Alternative:

Due to the relatively shoer length of new rail construction and the higher elevations of theroute, the ColstriP Alternative has by far the fewest number of waterbody ros5ing5* However,all of the alternatives cross the tongue River and Otter Creek and up to five other perennialstreams. Relatively small culve5 and ridge5 are common elements of railroad construction,and following construction, the presence of culve5 and bridges is not expected to cause anysignificant0ntinuing impacts to area ainage, suace water quality or aquatic habitat.

Rail construction could also directly affect wetlands, if present within the new rail rightOf-waY(RO by clearing, grading and placement of fill material Wetlands adlacent, but outside of theROW, may be indirectly impacted by the fragmenting of habitat, ange5 in hydrol0gY andange5 in vegetation iver5ity.

Due to the lack of site access, no field studies have been conducted to date to determine anddelineate wetlands along the rail alternatives. Large wetlands have not been observed ingeneral observations made in some locations from public adway5. Most of the routes of thefour rail alternatives have not been mapped in the National Wetland lnvent0 (NWI) to identiwetlands Available NWI mapping of areas5oth of Miles City and of ColstriP generallyindicate intermient occurrences of small ergent or shrublscrub wetlands to streamsor ainage ways. Isolated stock ponds are also shoWn. eased on interpretation of the routeopograPhy limited visual observations from public oadways and extrapolation of the apparenttypical NWI mapping large ntiguOus wetland areas are not likely present in any of the four railalternat5Small intermittent wetlands may be present to the Tongue River and other

streams that may provide suffiQient hydrology for wetland establishment.

When site access is obtained, wetland and terbody delineations will be to supPOthe environmental review of the prolect and permiin requirements. The actual wetlanddeterminations will include evaluations of soil, vegetati0n and hydrology in accordance with theU.S. rmyC0rPs of Engineers Regional SupPlementto the Corps of Engineers WetlandDelineation Manual: Great Plains Region and the 1987 Corps Wetland Delineation Manual. Atthis time, qualitative evaluations of potential wetland impacts can be made based on the relativenumbers of stream ros5iflgs encountered by each alternative. Wetlands would be most likely tooccur at locations where sufficient hydrOl0g is present1 such as streams and ainage ways.

‘13 TrariSystems I HanSOfl—

*

•100 ros5ing5.271 crosSings.251 crossings.299 crossings.

C.\temP\TRRC AItemait creefl1flg AnaIYSfSCX

Page 22: TR Scan No. 2_Redacted

——.—— -:•--•::-

Tongue River RailroadAlternatives Screening Analysis

The relative numbers of stream crossings as shown above may represent the relative amountsof wetland impacts.

The northern sections of the Tongue River and Tongue River Road Alternatives appear to runwithin the floodplainS of the Tongue River for short stretches. A higher likelihood for wetlandsexists within the floodplaiflS. All of the rail alternatives cross the Tongue River once and followthe same southern alignment along Otter Creek to Terminus Point 2. TherefOre, potentialwetland impacts in the southern segments appear to be equivalent between the rail alternatives.Overall, the Colstrip Alternative appears to have the potential for significantly less wetlandimpacts than the other alternatives, due to its shorter length of new construction, fewer streamcrossings, and divergence from the Tongue River floodplain.

4.6.2 Groundwater

Construction of each of the alternatives would occur at or above grade, with cuts required on theupland side of construction due to the topography. Localized groundwater infiltration may bealtered within the footprint of the rail line. The rail line is not expected to cause significant effectsto groundwater movement or quality.

4.6.3 FloodplaiflS

Most of the routes for the four rail alternatives have not been mapped by FEMA to identifyfloodplaifls. The FEMA Flood Insurance Rate Map (FIRM) for Custer County shows Zone Afloodplaifls along the Tongue River for a few miles south of Miles City at the northern end of theTongue River and Tongue River Road Alternatives. The lack of flood hazard mapping overmuch of the project area suggests that the areas are not prone to flooding, although this has notbeen confirmed. The rail alternatives generally run on high ground. Flood-prone areas may becrossed at the Tongue River crossing and in a few locations where the alignment runs close tocurrent or abandoned river meanders. Stream crossing and drainage structures will behydraulically designed to convey the expected water flows. When an alternative is selected,TRRC will coordinate with the affected Counties to obtain floodplain development permits ifnecessary.

4.7 Biological Resources

4.7.1 Endangered and Threatened Species

According to the United States Fish and Wildlife Service (USFWS) list of Endangered,Threatened, Proposed, and Candidate Species in Montana Counties, the following listedendangered species may be present in Custer, Powder River, and Rosebud Counties:

. Pallid sturgeon;

. Interior least tern;

. Black400ted ferret;

. Whooping crane;

. Greater sage grouse (candidate species); and

. Sprague’s pipit (candidate species).

14 TranSyStemS I Hanson-

C\temp\TRRC AltemaitVeS Screening AnaIysiS.DOCX

Page 23: TR Scan No. 2_Redacted

Tongue River Railroad

Subject to updated review, no 5FWSdesignated critical habitat for these or other specieshave been identified for the project locations. The USFWS Montana Field Office issued aBiological Opinion on July 12, 2006 regarding the effects ofthe proposed railroad on listedspecies. The 2006 list of endangered species within the project counties included the specieslisted above plus the bald eagle, which has since been de-listed as an endangered species butis still protected under the Bald and Golden Eagle Protection Act. The Biological Opinionconcurred that the proposed action (constructing and operating the proposed railroad) was likelyto adversely affect the bald eagle, and was not likely to adversely affect the pallid sturgeon,whooping crane, interior least tern, and black-footed ferret. “Candidate species” indicates theUSFWS has sufficient information on the biological status and threats to these species topropose to list them as threatened or endangered. USFWS encourages their consideration inenvironmental planning and partnerships, however, none of the substantive or proceduralprovisions of the Endangered Species Act apply to candidate species.

Since all the alternative routes cross the Tongue River and traverse similar upland terrain, thepotential for these listed species or their habitat to be present within each alternative alignmentappears to be approximately equivalent. The Colstrip Alternative may cause the fewest impactsto listed species and their habitat because of its shorter length and its location adjacent toexisting roadways. The Colstrip Alternative also may cause fewer impacts to bald eagles since itdiverges away from the Tongue River where bald eagles may be likely to nest.

4.7.2 Flora

Rail line construction will include clearing surface vegetation and excavating earth and rock onpreviously undisturbed land. Secondary impacts to vegetation may include loss or alteration ofshrub or forested habitat, fragmentation of habitat types, and altered vegetation succession.Creation of staging areas and work pads would cause temporary vegetation impacts in all therail alternatives. Based on visual observation of the alternatives from public roadways, thenatural vegetation generally consists of variable grassland and shrublands interspersed withconiferous forests, with deciduous trees and shrubs in drainages and bottomland areas. Areasdisturbed during construction and not covered by railroad structures will be reseeded with nativespecies.

The Colstrip Alternative has the potential to cause the least amount of vegetation impactsbecause of its shorter length and its route adjacent to existing roadways where naturalvegetation has already been disturbed. The Tongue River Alternative is the longest in lengthand has a higher potential for impacts to established vegetation and scrubland forests.

4.7.3 Terrestrial Wildlife

A variety of wildlife species likely inhabit areas within all alternatives. The majority of land withinthe alternatives is open pasture or scrubland forests. Potential impacts to wildlife for eachalternative would vary based on the dependence of specific wildlife to a preferred habitat,sensitivity to habitat fragmentation and past and present population trends. Habitatfragmentation occurs when large areas of continuous core habitat are spilt into smaller pieces,thereby increasing the amount of habitat edge. Potential construction impacts common to allalternatives could include habitat alteration and loss, disturbance and displacement of wildlife,disruption of food sources and direct mortality from construction equipment and/or trains.Common potential impacts related to train operation could include animal/train collisions, habitat

15 TranSystems I Hanson

____________

Alternatives Screening Analysis

C\tempVfRRC Altemaitves Screening AnaIyss.DOCX

Page 24: TR Scan No. 2_Redacted

Tongue River RailroadAlternatives Screening Analysis

fragnientation, and potential exposure to spills. Appropriate mitigation will be adopted toaddress these potential impacts.

The Coistrip Alternative has the least potential for wildlife impacts due to its shorter length.Also, the Colstrip Alternative will create less habitat fragmentation than theother alternativeroutes because it is shorter and a significant portion is adjacent to established roadways. TheTongue River Alternative is the longest in length and has a higher potential for wildlife impacts.

4.7.4 Aquatic Ecology

All of the four rail alternatives cross the Tongue River, Otter Creek, and several named andunnamed tributaries that provide habitat for numerous fish and aquatic macroinvertebratespecies. Construction activities conducted in the waterbodies may cause temporary increases insedimentation and short-term degradation of water quality. Water quality and aquatic habitatwould be expected to return to normal conditions when construction is completed. Streamcrossings may result in some loss or alterations to in-stream and associated riparian habitat.Bridge crossings would likely result in less impact to aquatic habitat than installation of culverts.

Since the Colstrip Alternative crosses fewer waterbodies than the other rail alternatives, aspresented in Section 4.6.1 , the Colstrip Alternative can be expected to cause less aquaticspecies and habitat disturbance than the other alternatives, although operation of the railroad onany of the alternative alignments is not expected to cause significant long-term adverse effectsto aquatic ecology.

4.8 Cultural Resources

The alternative routes will be subject to updated comparative cultural resources reviews duringthe ElS and Section 106 processes. Those updated reviews have not yet been undertaken.Based on information reported in the Tongue River I EIS, the Colstrip Alternative would impactfewer total prehistoric and historic resources than each of the other alternatives, while theTongue River Road Alternative would impact a greater total of resources than the otheralternatives. Clearly, however, the additional cultural resources information, includinginformation on impacts to traditional Native American cultural properties, will need to begathered and the relevant impacts assessed.

4.9 Transportation

Most of the rail alternatives pass through sparsely-populated rural country that is generally usedfor rangeland and some crop production. The Tongue River Road and Colstrip Alternativesparallel existing transportation corridors through much of their lengths. Although thesealternatives may result in less division of agricultural parcels, these alternatives require moreroadway grade crossings than the other alternatives, leading to the potential for more trafficdelays and collisions.

Grade separations are anticipated at Interstate 94 (except for the Coistrip Alternative, whichwould not cross 1-94) and U.S. Route 212. Other roadways will be crossed at-grade, althoughthe Montana Department of Transportation has asked that Tongue River Road be evaluated forgrade separation. The numbers of public and private roadway grade crossings estimated for

16 I TranSystems I Hanson

C:\temp\TRRC Altemaitves Screening AnalysisDOCX

Page 25: TR Scan No. 2_Redacted

Tongue River RailroadAlternatives Screening Analysis

each alternative are as follows (additional private crossings may be required through landownernegotiation):

. . Colstrip Alternative: 5 public I I 8 private

. Tongue River Alternative: 3 public I 41 private.

. Tongue River Road Alternative: 4 public I 46 private.

. Moon Creek Alternative: 4 public I 36 private.

£1:.1O Right-of-WayAcquisition

Construction of the railroad will require acquisition of right-of-way from private and publiclandowners. The numbers of landowners directly affected by each alternative are as follows:

. Colstrip Alternative: 44 landowners.

. Tongue River Alternative: 53 landowners.

. Tongue River Road Alternative: 60 landowners.

. Moon Creek Alternative: 54 landowners.

Although portions of the right-of-way for all the alternatives would be acquired from privatelandowners, it appears that only one residence would be displaced, located north ofAshland onthe alignment that is common to all the alternatives under consideration. Due to the relativelyshorter length of new rail construction, the Colstrip Alternative directly affects the fewest numberof landowners. Property negotiations with fewer landowners may result in more expeditiousacquisition of right-of-way for the Colstrip Alternative. The relative numbers of landownersdirectly affected by the other alternatives are similar to each other, ranging from 53 landownerson the Tongue River Alternative to 60 landowners on the Tongue River Road Alternative.

Rail traffic utilizing the Colstrip Alternative would pass through the city of Colstrip on the existingBNSF track. Colstrip has an estimated population of 2,200 according to the 201 0 Census.

4.11 Air Quality

The U.S. Environmental Protection Agency (USEPA) National Ambient Air Quality Standards(NAAQS) regulations specify the maximum acceptable ambient concentration levels for sixprimary or “criteria” air pollutants: ozone (03), nitrogen dioxide (NO2), carbon monoxide (CC),sulfur dioxide (SO2), respirable particulate matter (PM), and lead (Pb). According to the USEPAThe Green Book ofNonattainmentAreas for Criteria Pollutants as ofJuly 2O 2012(httrdlwww.epa.gov/oar/oacips/qreenbklindex.html, accessed November 24, 201 2), the Lame Deerarea in Rosebud County, Montana persistently exceeds the NAAQS for PM (PM-I 0) and isdesignated as a “nonattainment area.” All other areas within the project alternatives are inattainment of the NAAQS.

Air emissions of PM may occur as fugitive dust from earthmoving activities during constructionof the rail line. However, fugitive dust emissions during construction are temporary and can bereadily controlled by water application. The Colstrip Alternative would result in the lowesttemporary PM during construction since it requires the least amount of earthwork.

17 I TranSystems I Hanson

C:\tempTRRC Alternaitves Screening Analysis.DOCX

Page 26: TR Scan No. 2_Redacted

Tongue River Railroad. Alternatives Screening Analysis

BNSF is currently performing modeling of locomotive emissions and fuel usage. A comparativediscussionwill follow upon completion ofthe modeling.

4.12 Noise and Vibration

TRRC has not conducted modeling to estimate noise or vibration effects caused by constructionor operation of the railroad except for specific evaluations performed previously at the Miles CityFish Hatchery. The Tongue River and Tongue River Road Alternatives pass through the MilesCity Fish Hatchery and LARRS, which may be sensitive receptors for noise and vibration. TheMoon Creek Alternative reduces the amount of trackage through the LARRS. The ColstripAlternative does not pass through the LARRS or the Fish Hatchery. Each of the rail alternativestraverses a common alignment east ofthe populated area ofAshland, so the potential effects ofnoise and vibration, if any, would be equivalent between the rail alternatives in that area. TheColstrip Alignment does not pass through any populated areas upon leaving the Tongue Rivervalley.

4.13 Parks and Recreation

There are no designated recreation areas within any of the rail alternative alignments. TheTongue River and Tongue River Road Alternatives pass along the western edge of the SpottedEagle Lake (Miles City) Recreation Area where the eastern leg of the wye connects to the BNSFmain line.

4.14 Hazardous Materials and Waste Sites

According to the USEPA EnviroMapper for Envirofacts(http:Ilwww.epa.govlemefdatalem4ef. html?ve=7,4622972869873047,-I 06.73079681 396484&pText=Rosebud , accessed November 24, 201 2), there are no uncontrolledhazardous waste sites or other listed sites that suggest possible areas of contaminated soilsthat may be encountered during construction of any of the rail alternatives.

4.15 Socioeconomics

Most of the rail alternatives pass through sparsely-populated rural country. Although portions ofthe right-of-wayfor all the alternatives would be acquired from private landowners, it appearsthat only one residence would be displaced, located north of Ashland on the alignment that iscommon to all the alternatives under consideration. Most socioeconomic impacts to the regionare expected to be the same for all the rail alternatives.

5. No-Build Alternative

The No-Build Alternative would result in no construction of any rail line to serve the Otter Creekmine or other mines in the Ashland area. The No-Build Alternative is based on theassumptions that either: 1) there will not be a need to transport coal from the proposed minesnear Ashland/Otter Creek; or 2) another mode of transportation is preferable to the proposedrailroad.

18 I TranSystems I Hanson

C \temp\TRRC Altemaftves Screening Analysis.DOCX

Page 27: TR Scan No. 2_Redacted

TongueRiverRailroadAlternatives Screening Analysis

At this time, permitting for the Otter Creek mine is progressing. Therefore, there will be a needto transport coal from the area. However, we assume that the No-Build Alternative will beevaluated during the current STB EIS proceedings.

6. Alternatives Previously Considered and Eliminated from Detailed Study

Certain rail alternative routings were considered during the screening process and eliminated asbeing unfeasible or otherwise clearly inferior to the four rail alternatives described above on thebasis of relevant screening criteria, including the length of required track construction or otherreadily discernible impacts. Non-rail alternatives for transporting coal from the Ashland/OtterCreek area also were evaluated in the previous environmental studies. The evaluations of thenon-rail alternative transportation modes concluded that the non-rail alternatives are unfeasible.TRRC believes that these conclusions remain valid. The following sub-sections summarize theevaluations of the rail and non-rail transportation alternatives that TRRC does not believewarrant detailed consideration.

6.1 Rail Alternatives and Sub-Alternatives

A previous alignment of the Tongue River Road Alternative has been discarded due to impactsthat it would have on newer developments on the east side of Miles City. Significant relocationsto commercial and industrial development would be required as the alignment passed throughthe east side of Miles City and then continued southward crossing Interstate 94 beneath newhighway grade separations. The rail line continued southward on the east side of the TongueRiver just north of Pumpkin Creek, and then turned west and crossed the Tongue River. Therail line then turned southward and ran about 10 miles before crossing the Tongue River again,and then running on the east side of the Tongue River to Terminus Points I and 2. The currentproposed alignment of the Tongue River Road Alternative originates on the west side of MilesCity and includes only one crossing of the Tongue River.

An alternative known as the Bureau of Land Management (BLM) Alternative has been evaluatedto determine approximate grading quantities and right-of-way impacts using the same criteria asthe updated evaluation of the four rail alternatives described above. The north end of thisalternative shares a common connection to the BNSF Forsyth Subdivision as the Moon CreekAlternative, which is a modification from the previously studied route. The connection point tothe Forsyth Subdivision studied previously was not feasible due to excessive cuts throughrugged terrain. The alignment runs south runs parallel to the Tongue River, but further west andalong higher ground than the Tongue River Alternative. Although the grades are comparable tothe Moon Creek Alternative, the grading quantities required to construct this alternative areabout 60 million cubic yards of cut and 60 million cubic yards of fill, even with the adjustment ofthe north end to reduce grading. The grading footprint is about triple, and right-of-way impactsare about double, that of the Tongue River Road Alternative, which contains the highest volumeof grading and right-of-way impacts of the four alternatives screened. For these reasons, it wasnot selected for further analysis.

Other alternative rail alignments were proposed during public scoping meetings in November201 2. Two of these alternatives would originate at Otter Creek and run east toward Broadusalong US 212 before paralleling Montana State Route 59 (MT59) to the north or south. The twoalternatives share a common alignment from the proposed Otter Creek Mine site north to US212, then turn east and run parallel to US 212 for about 40 miles before diverging. The north

19 I TranSystems I Hanson

C:\temp\TRRC Altemaitves Screening Analysis.DOCX

Page 28: TR Scan No. 2_Redacted

Tongue River RailroadAlternatives Screening Analysis

route turns north about 4 miles northwest of Broadus and runs parallel to MT59 for a distance of60 miles before connecting to the Tongue River Road Alternative about I 3 miles south of MilesCity. The south option turns south about 3 miles southeast of Broadus and runs parallel toMT59 for a distance of about 78 miles before connecting to the existing BNSF CampbellSubdivision in Campbell, Wyoming. The northern MT59 alternative would require about.1 19miles of new main track construction and the southern MT59 alternative would require about127 miles of new main track construction. Impacts associated with construction and energyconsumption would be at least double the impacts associated with any of the four alternativesidentified for further study. For these reasons, these alternatives were not selected for furtheranalysis.

Routings to the south of Ashland/Otter Creek were also considered. A rail route from TerminusPoint I to the existing Spring Creek rail spur near Decker, Màntana was originally proposed aspart of Tongue River II ElS and refined in Tongue River Ill EIS. Although approved during thoseprevious proceedings, significant concerns were raised by Native American groups and theNational Park Service due to the proximity of the route to the Wolf Mountains battlefield site,which was added to the National Register of Historic Places in 2001 and designated a NationalHistoric Landmark in 2008. Some concerns were also raised about the effect of vibrationscaused by rock excavation during construction on the Tongue River Reservoir, as well as visualand noise issues for recreational users ofthe reservoir. The approved Tongue River Ill southalignment extended approximately 38 miles south from Terminus Point I to the existing SpringCreek rail spur near Decker, Montana. A meaningful comparison to the current preferred railline would involve the route length from Terminus Point 2 to Miles City of approximately I I 9miles for east-bound traffic via the Colstrip Alternative and approximately 340 miles via theTongue River Ill south alignment. Terminus Point 2 to Jones Junction near Billings, MT requireswest-bound traffic to travel approximately 148 miles via the Colstrip Alternative andapproximately 209 miles via the Tongue River Ill south alignment. The additional route length of221 miles for east-bound traffic and 61 miles for west-bound traffic, as well as approximately52% more total grading and the aforementioned cultural resources and environmental impacts,are significant issues when compared to the Colstrip Alternative and do not merit furtherconsideration ofthe TRRC Ill south alignment alternative in this screening analysis.

6.2 Non-Rail Alternatives

6.2.1 Conveyor

The previous studies considered constructing a conveyor system to transport coal from the mineto a bulk transportation system to the BNSF main line at Miles City. However, the previousstudies concluded that building and operating the conveyor system would not be feasible for thefollowing reasons:

. The cost of constructing and operating a conveyor system from Terminus Point 2 toMiles City would be higher than the cost of transporting the product on the proposedrailroad. The higher cost would have a negative impact on the marketability of coal.Since the current proposed route to Colstrip is less than half the distance to Miles City,the total costs of a conveyor system would be less than the costs previously determined.It is assumed the costs of a conveyor and the proposed railroad to Colstrip would eachbe proportional to the shorter length of the current proposal. Therefore the conveyor

20 I TranSystems 1 Hanson

C:\temp\TRRC AlternaitveS Screening Analysis.DOCX

Page 29: TR Scan No. 2_Redacted

Tongue River RailroadAlternatives Screening Analysis

system would be expected to have a higher cost than the proposed railroad, althoughthis has not been confirmed in this Alternatives Screening analysis.

. The constructor or operator of a conveyor system would likely not have the legal powerof eminent domain to acquire right-of-way for the conveyor. It is not likely that all of therequired right-of-way could be acquired through negotiation.

. A conveyor system operating 24/7 may cause constant noise annoyance.

. The conveyor system would likely present a significant barrier to wildlife migration atmost or all portions of the conveyor route.

. Conveyor systems are normally designed for a specific tonnage capacity. With thepossibility of additional mines being developed in the Otter Creek area, any conveyorsystem would require upgrading, or re-construction, to handle additional tonnage fromnew mines.

. We are not aware of any conveyor system in existence that is over 20 miles long.

6.2.2 Coal Slurry Pipeline

The previous studies considered constructing a coal slurry pipeline to transport coal from themine to a bulk transportation system to the BNSF main line at Miles City. However, theprevious studies concluded that building and operating the coal slurry pipeline system would notbe feasible for the following reasons:

. The cost of constructing and operating a coal slurry pipeline system from TerminusPoint 2 to Miles City would be higher than the cost of transporting the product on theproposed railroad. The higher cost would have a negative impact on the marketability ofcoal. As described above for a conveyor system, a coal slurry pipeline would beexpected to have a higher cost than the proposed railroad, even along the shorterproposed route to Colstrip.

.The constructor or operator of a coal slurry pipeline system would likely not have thelegal power of eminent domain to acquire right-of-way for the conveyor. It is not likelythat all of the required right-of-way could be acquired through negotiation.

. A coal slurry pipeline system requires a reliable source of sufficient water to operate. It isunlikely that sufficient water supply is present in this area.

6.2.3 Hauling by Truck .

The previous studies considered hauling coal from the Ashland/Otter mines to Miles City bytruck using existing and new roadways. The previous studies concluded that hauling coal bytrucks would not be feasible for the following reasons:

. The cost of hauling coal by truck from Terminus Point 2 to Miles City would be higherthan the cost of transporting the product on the proposed railroad. The higher cost wouldhave a negative impact on the marketability of coal. The costs of hauling coal by truckvia Colstrip have not been determined, but typical cost per ton-mile for other similar haulsituations indicates that truck hauling costs would be significantly higher than rail.

. Hauling the coal by truck would likely have a greater negative impact on air quality thantransportation by rail, including higher fugitive dust emissions from the roadways andhigher diesel exhaust emissions from the required number of operating trucks comparedto the projected numbers of railroad locomotives.

21 I TranSystems 1 Hanson

C:\temp\TRRC Altemaitves Screening Analysis.DOCX

Page 30: TR Scan No. 2_Redacted

. The large number of trucks operating on public roadways would cause significantincreases in traffic, road damage, noise, and vibration. Using an assumption of38 tonsltruck maximum capacity for highway trucks with an additional trailer, theanticipated coal production of 20 MMTIyear would require I ,442 round trips via truckevery day of the year. This equates to approximately one round trip per minute.

6.2.4 MineMOUth Power Generation

Previous studies indicated that constructing and operating a mine-mouth electrical generatingplant near the proposed mine may be cost competitive with rail tran5POttati0I. The previousstudies concluded that constructing and operating a mine-mouth electrical generating plant nearthe proposed mine would not be comparatively vantageous to rail transportation for thefollowing reasons:

. The environmental impacts of constructing and operating an electrical generating powerplant in this area would be substantial, including the plant’s needs for large amounts ofwater, which would not be available in the area, and possible deterioration of air quality,including to the Northern Cheyenne Indian Reservation

. Substantial environmental impacts would also result from siting and constructing thenece55a highvOltage transmission lines from the plant.

7. COflCIUSIOfl

Based on the analysis presented above, all four alternatives are feasible, but the ColstripAlternative presents the shortest length of new construction, smallest grading footprint, leastrightOf-Way acquisition, least waterway crossings and significantly less length parallel to theTongue River valley compared to the other rail alternatives The Colstrip Alternative does notrequire a new grade separation of 1-94, would not impact LARRS or the Miles City Fish Hatcheryand follows existing transportation corridors to a far greater extent than the other railalternatives.

22 TranSYstems I Hanson—

--

Tongue Rlver RailroadAlternatives 5creefling Analysis

C\temp\TRRC AltemaltVes Screening AnaiySIS.D0CX

Page 31: TR Scan No. 2_Redacted

Re: FD 301 86, Tongue River Railroad CompanyT__ Vicki Rutson : David Coburn 01/1 1/2013 06:56 PM

Thank you for your submission, David.

Regards,

Vicki Rutson

From: “Coburn, David” [[email protected]]Sent: 01/1 1/2013 04: 16 PM MSTTo: “Vicki Rutson (RutsonVstb.dot.gov)” <RutsonVstb.dot.gov>Cc: “B1odgettKstb.dot.gov” <B1odgettKstb.dot.gov> .

Subject: FD 30186, Tongue River Raifroad Company

Dear Ms. Rutson: Please see the attached alternatives screening analysis prepared byconsultants to Tongue River Railroad Company and a transmittal letter.

Regards. David Coburn/Attorney for Tongue River Railroad Company

David H. [email protected]

Steptoe+1 202 429 8063 Steptoe & Johnson LLPdirect 1330 Connecticut Avenue, NW+1 202 262 7306 Washington, DC 20036mobile www.steptoe.com+1 202 261 0565 fax

This message and any attached documents contain information from the law firm Steptoe & Johnson LLP that may be confidentialand/or privileged. If you are not the intended recipient, please do not read, copy, distribute, or use this information. If you havereceived this transmission in error, please notify the sender immediately by reply e-mail and then delete this message.

Page 32: TR Scan No. 2_Redacted

Page 1 of 1

(RE: Tongue River Railroad -- Response to Information RequestCoburn, David

\. Ito:‘BlodgettKstb.dot.gov’, ‘Sunimerville, Alan’02/1 1/2013 03:22 PMCc:“Vicki Rutson (RutsonVstb.dot.gov)”, “Danielle.Gosse1instb.dot.gov”’, “Stein, Linda”Hide DetailsFrom: “Coburn, David” <[email protected]>To: “BlodgettKstb.dot.gov” <B1odgettKstb.dot.gov>, “Summerville, Alan”

@icfi.com>Cc: “Vicki Rutson (RutsonVstb.dot.gov)” <RutsonVstb.dotgov>,“Daniel1e.Gosselinstb.dot.gov” <Danielle.Gosse1instb.dot.gov>, “ Stein, Linda”<LSteinsteptoe.com>

1 Attachment,

.

Page 5.pdf

I have identified a typo on the last page of our Feb. 6 response to the information request — theword “employ” on the last line of the last page should be “empty.” A corrected page isattached. Thankyou. David

From: Coburn, DavidSent: Wednesday, February 06, 2013 1:27 PMTo: [email protected]; ‘Summerville, Alan’Cc: Vicki Rutson ([email protected]); [email protected]; Stein., LindaSubject: Tongue River Railroad -- Response to Information Request

Dear Ken and Alan — Please find attached TRRC’s reply to the January 23, 2013 information request.Regards. David Coburn

David H. coburnPartnerDCoburnãsteptoe.com

Steptoe .

+1 202 429 8063 direct Steptoe & Johnson LLP+1 202 262 7306 mobile I 330 Connecticut Avenue, NW+1 202 261 0565 fax Washington, DC 20036

www.steptoe.com

This message and any attached documents contain information from the law firm Steptoe & Johnson LLP that may be confidential and/orprivileged. If you are not the intended recipient, please do not read, copy, distribute, or use this information. If you have received thistransmission in error, please notify the sender immediately by reply e-mail and then delete this message.

file :1//C :/Users/rutsonv/ArrnData/Local/Temo/1/notesO9E97l /weh3 5 X7 htm 1 I 1 7 /‘?fl 1 S

Page 33: TR Scan No. 2_Redacted

Doing so would allow the environmental review and transportation merits assessments tobe accomplished at the same time as the review of the portion of the line that would servethe Otter Creek mine, thereby saving significant time and resources that otherwise wouldbe required were permitting ofthe Montco Mine spur to be delayed.

5. The Supplemental Application states that 3.7 trains per day would travel onthe Tongue River Railroad. Because this number represents the averagenumber of trains per day, please provide the maximum number of trains perday that could potentially travel on the Tongue River Railroad in thereasonably foreseeable future if the line is approved and constructed.

As discussed in TRRC’s Reply to Petition to Revoke, the predicted 3.7 averagenumber of loaded trains per day was based on the assumption that the Otter Creek minewill reach its anticipated maximum production level of 20 million tons of coal per year.This is a simple average based on the capacity of a unit coal train and this maximumproduction level. (20 million tons/year divided by 125 cars/train times 365 days/year)3.65 trains/day, which was rounded up to 3.7 trains/day in the Application.)

Many factors on the rail network can cause more or less trains to traverse the lineon a given day. These factors include track maintenance, service interruptions caused byderailments, weather or other issues; the level of any delays in loading rail cars at themine or delays at destination.

The maximum number oftrains/day that could use the line were no siding built onthe TRRC line is between 3 and 4 loaded trains and approximately 7 to 8 total (loadedand empty) trains/day. Were an 8500 foot siding built on the TRRC line (as theApplication notes is possible were traffic levels to demand the need for a siding) themaximum number of trains/day that could be transported would be about 5 loadedtrains/day or a total of about 10 loaded and empty trains/day.

5