Training Project Complete

Embed Size (px)

Citation preview

  • 7/27/2019 Training Project Complete

    1/64

    A REPORT ON

    VOCATIONAL TRAININGAT

    SUBMITTED BY

    SAYANTAN CHAKRABORTY

    DEPARTMENT OF CIVIL ENGINEERING

    JADAVPUR UNIVERSITY

    KOLKATA- 700 032

  • 7/27/2019 Training Project Complete

    2/64

    VOCATIONAL TRAINING PROJECT REPORTVOCATIONAL TRAINING PROJECT REPORT

    name of the project : UNIWORLD CITY RAJARHAT, KOLKATA

    name of the client : BENGAL UNITECH UNIVERSAL INFRASTRUCTURE

    PVT. LTD.

    name of the company : SIMPLEX INFRASTRUCTURES LIMITED.

    training period : 14th MAY 2012- 14th JUNE 2012

    name of the student : SAYANTAN CHAKRABORTY

    college roll number : 000910401065

    name of the college : FACULTY OF ENGINEERING AND TECHNOLOGY, JADAVPUR

    UNIVERSITY

    address : JADAVPUR UNIVERSITY

    2

  • 7/27/2019 Training Project Complete

    3/64

    INDEXINDEX

    Acknowledgement...................................................................................................04Acknowledgement...................................................................................................04

    Preface.....................................................................................................................05Preface.....................................................................................................................05

    Introduction.............................................................................................................06Introduction.............................................................................................................06

    Area statement.........................................................................................................07Area statement.........................................................................................................07

    Materials used.........................................................................................................08Materials used.........................................................................................................08

    Contract management.............................................................................................10Contract management.............................................................................................10

    Safety......................................................................................................................18Safety......................................................................................................................18

    Execution................................................................................................................26Execution................................................................................................................26

    Quantity survey.......................................................................................................31Quantity survey.......................................................................................................31

    3

  • 7/27/2019 Training Project Complete

    4/64

    Quality control........................................................................................................37Quality control........................................................................................................37

    Planning..................................................................................................................45Planning..................................................................................................................45

    Electrical department..............................................................................................48Electrical department..............................................................................................48

    Mechanical department...........................................................................................53Mechanical department...........................................................................................53

    Store........................................................................................................................58Store........................................................................................................................58

    Conclusion...............................................................................................................59Conclusion...............................................................................................................59

    4

  • 7/27/2019 Training Project Complete

    5/64

    ACKNOWLEDGEMENTACKNOWLEDGEMENT

    Apart from the efforts of me, the success of any project depends largely on the encouragement and guidelines of

    many others. I take this opportunity to express my gratitude to the people who have been instrumental in the

    successful completion of this project.

    I would like to thank Mr. S. K. Maiti (Sr.Vice-President, Simplex Infrastructures Ltd.) for accepting our training

    and keeping our request. I would like to show my greatest appreciation to Mr. Sanjay Chakrobarty (Project in-

    charge) and Mr. Ahindra Chowdhary (Manager). I wish my gratitude to him for his tremendous support and help. I

    feel motivated and encouraged after working under his sheer guidance and without whom this project would not

    have materialized.

    My special thanks to Miss. Jayashree Kar(Engineer, Planning) and Mr. Santibrata Samanta (Engineer, Quality) for

    their day-to-day motivation, suggestions and detailing about the various operations at site. I would also like to

    acknowledge and extend my heartiest gratitude to the following persons who have made the completion of this

    project possible:

    Mr. G Mukherjee (Manager, Accounts)

    Mr. P Biswas (Engineer, Safety)

    Mr. D Chakrobarty (Sr. Engineer, construction)

    Mr. Partho Kole (Sr. Engineer, construction)

    Mr. Bidyut Ghosh (Sr. Engineer, construction)

    Mr. Ranjit Pal (Plant Engineer)

    Mr. Abhra Chaudhuri (Officer, Accounts)

    Mr. Atish Srimani (Engineer)

    Miss Jayashree Kar (Engineer, Planning)

    Mr. Santibrata Samanta (Engineer, Quality)

    Mr. P Ghorui ( Engineer)

    5

  • 7/27/2019 Training Project Complete

    6/64

    I would also thank my Institution and my faculty members without whom this project would have been a distant

    reality. The guidance and support received from all the members who contributed to this project, was vital for the

    success of the project.

    PREFACEPREFACE

    The construction as well as the real estate business, is booming, at present in Kolkata, West

    Bengal. Major construction companies and builders have taken great strides in setting up of

    multi- storied buildings and mega housing complexes etc. with lots of amenities and facilities in

    the New Town, Rajarhat area. This business is becoming much more lucrative than before.

    Experienced Civil Engineers are key persons in any construction site. So in order to be well

    versed and knowledgeable in the construction field as well as to acquire site experience, training

    at site becomes very important.

    As a Civil Engineering student, in JADAVPUR UNIVERSITY, It was important for me to get

    familiar with all sorts of acquaintance of construction line.

    So getting a Vocational Training at this stage would be better for my development and as such I

    applied to Simplex Infrastructures Ltd. and was lucky enough to get an opportunity to complete

    my Vocational Training under this esteemed organization.

    Under Bengal Unitech Project; named UNIWORLD CITY the structures are constructed over

    100 acres out of which PHASE 4 consisting of 10 Towers with basement occupying 135802 sqm and PHASE 2A consisting of 5 TOWERS and basement occupying 77049 sq m are governed

    by SIMPLEX INFRASTRUCTURES LTD.

    During this training, which I underwent after appearing for the 6th Semester Examination of my

    college, I have learnt many things, both about construction as well as project management. I got

    to see a large number of site machineries, equipments and construction procedures, various

    6

  • 7/27/2019 Training Project Complete

    7/64

    safety measures adopted at site which are not common in ordinary sites. These are invaluable

    experience, which I believe will help me to a great extent, in the future.

    Civil engineering is a vast and diversified subject and there are lots of things yet to be learnt. As

    only a 3rd year student of this Engineering discipline, I knew I had my limitations, but I must say

    that this training program has made me more confident and has created more interest in me in

    learning the practical aspects of construction at site.

    SAYANTAN CHAKRABORTY

    DEPARTMENT OF CIVIL ENGG.

    JADAVPUR UNIVERSITY

    KOLKATA

    INTRODUCTIONINTRODUCTION

    ABOUT THE COMPANY

    NAME : SIMPLEX INFRASTRUCTURES LIMITED

    REGISTERED OFFICE : SIMPLEX HOUSE,

    27 SHAKESPEARE SARANI,

    KOLKATA- 700017

    FORMER NAME : SIMPLEX CONCRETE PILES (INDIA) LIMITED

    SPECIAL FEATURES AS CONSTRUCTION COMPANY:

    Company is in ISO family since 2004.

    It is an ISO 9001:2008 approved company.

    Major construction works are taken up.

    Company generally is undertaking infrastructures, construction of flyovers etc.

    Presently executing 100s of towers in India and abroad.

    Design, development, engineering & construction of civil, structural, geotechnical and other associated

    works.

    ABOUT THE PROJECT:

    7

  • 7/27/2019 Training Project Complete

    8/64

    BASIC INFORMATION:

    Total project area of UNIWORLD CITY at Rajarhat, Newtown is 100 acres. Simplex got contract to make

    HEIGHTS and CASCADES in PHASE 2A and PHASE 4 respectively. Uniworld City is conveniently located in

    the IT/ITES belt in New Town, Rajarhat. The area is situated between Salt Lake and the Airport and is 15 minutes

    to Park Circus. The proposed Metro will also originate from New Town and terminate in Howrah.

    Cascades is located at the grand pedestrian promenade which runs through the heart of Uniworld City and consists

    of 10 towers, which extend up to 24 stories. With 2 to 3 apartments on every floor, apartment sizes range from

    1,475 to 3,841 square feet. The design of Cascades is most prominently expressed in its landscape its spectacular

    water features & undulating landform.

    The complex includes food courts, amphitheatre, rock climbing wall, shopping facilities, swimming pool with

    children's pool, squash court, badminton court, tennis courts, piped gas, security and CCTV

    .

    Area statement

    GENERAL OUTLAY OF WORK:

    For Phase 2A:

    Floor

    Total

    no. of

    floors

    Total

    no. of

    apartme

    nts

    Size of

    each

    flat

    (m2

    )

    Built up

    area

    (m2)

    Appro

    x.

    floor

    areain

    buildi

    ng

    (m2)

    Tentative

    total floor

    area per

    tower (m2

    )

    8

  • 7/27/2019 Training Project Complete

    9/64

    Baseme

    nt

    1 14000 13000 13000

    T1 28 71 150 635 545 15237

    T2 26 64 120 525 420 10904

    T3 28 71 150 635 545 15237

    T4 26 64 120 525 420 10904

    T5 28 71 120 525 420 11767

    Total no. of apartments = 341

    Tentative basement car parking area = 9000 m2

    Tentative total area = 77049 m2

    For Phase 4:

    Floor

    Total

    no. of

    apartme

    nts

    Total

    no. of

    floors

    Tentative

    total floor

    area per

    tower (m2)

    Baseme

    nt

    1 46572

    T1 26 15 5547

    T2 26 15 5547

    9

  • 7/27/2019 Training Project Complete

    10/64

    T3 26 15 5547

    T4 52 21 9138

    T5 58 23 10086

    T6 58 23 10433

    T7 58 23 10433

    T8 58 23 10433

    T9 64 25 11033

    T10 64 25 11033

    Materials Used

    GRADE OF CONCRETE USED:

    Pile =M25

    Pile cap =M25

    Columns =M40 (for the tower)

    Slabs =M25

    Beams =M40

    Basement columns =M30

    Retaining wall =M25

    P.C.C. =M7.5

    Basement slab =M35

    10

  • 7/27/2019 Training Project Complete

    11/64

    Note:

    As per the design the basement slab was supposed to be constructed of M25

    grade concrete. But a road for the movement of heavy vehicles was

    proposed over the basement slab in which case the M25 mix would

    have not been sufficient to withstand the load over it, hence, the gradeof concrete was raised to M35 with the clients permission.

    DIAMETER OF REINFORCEMENT BARS IN COLUMNS OF

    VARIOUS SIZES:

    CONTRACT MANAGEMENTCONTRACT MANAGEMENT

    CONTRACT MANAGEMENT is a process which enables all the parties to a contract to meet

    their obligations in order to deliver the objectives required from the contract. It continues

    throughout the life of the contract and involves managing proactively to anticipate future needs

    as well as reacting positively to situations that arise.

    DOCUMENTS FORMING PART OF THE CONTRACT

    Contract agreement

    Letter of acceptance (LOC) & Notice to proceed (NTP)

    Contractors bid / tender document

    Contract data

    11

    SIZE OF COLUMNDIAMETER OF

    REINFORCEMENT BAR(mm)

    250mm X 750mm 16

    500mm X 500mm 20

    500mm X 750mm 20 & 25

    500mm X 900mm 32 & 25

    500mm X 1200mm 32 & 25

  • 7/27/2019 Training Project Complete

    12/64

    Conditions of contract

    Specifications

    Drawings

    Bill of quantities

    ESSENTIALS OF A CONTRACT

    Essential elements of a contract are:

    An agreement

    Offer and acceptance

    Lawful consideration

    Capacity to enter into contract

    Free consent of both parties

    Lawful object

    Intention to create a legal relationship

    TYPES OF CONTRACT:

    Unit rate/unit price contract

    Percentage rate contract

    Cost plus percentage contract

    Lump sum contract

    Turnkey/ EPC contract

    BOT contract

    FIDIC form contract

    12

  • 7/27/2019 Training Project Complete

    13/64

    TYPICAL SET OF RECORDS:

    Original contract tender document

    Drawings issued for construction and all subsequent revisions

    Instructions, notices, variation orders issued to contractors

    Sub-contractor quotations, purchase orders, work orders

    Daily records on Plant & Machinery use

    Daily time records and production logs e.g. concrete pours etc.

    Contract milestone schedule/master schedule

    Payment/billing status under the contract

    Contract correspondence

    Minutes of contractual meetings

    Minutes of site coordination meeting

    Notice of claims for delays and/ or cost by contractor

    Inspection reports

    Accident reports

    Progress photographs

    A filling record of all the record files that are being maintained

    BREACH OF CONTRACT

    A breach of contract occurs where a party repudiate or fails to perform one or more of the

    obligations imposed upon him by the contract. Any breach of a contract by one party gives the

    other party an immediate cause of action and a right to claim for damages as compensation, for

    losses flowing from the breach of contract.

    13

  • 7/27/2019 Training Project Complete

    14/64

    Sources of breach of contract:

    Failure to give possession of site

    Improper or cardinal changes

    Unreasonable delays

    Non-supply of material promised

    Different site conditions

    Different type of claims:

    Contractual claims

    Extra contractual claims

    Quantum merit claims

    Ex-gratia claims

    Counter claims

    Supporting evidence for claims

    Many delay claims by contractors fail due to lack of notice and/or failure to substantiate their

    claim due to lack of records.

    The following supporting evidence can contribute immensely in proving the claims:

    Correspondence

    Confirmation of verbal instructions

    Drawing register

    Minutes of meeting

    Labour allocation sheets

    14

  • 7/27/2019 Training Project Complete

    15/64

    Approvals

    Inspection

    Daily diary

    Photographs

    Programme and progress

    Quality assurance records

    Other records

    DISPUTE

    A dispute is a disagreement arising out of a contract. When many differences or issues remain

    unresolved, the party aggrieved becomes entitled to raise a claim in respect of the same.

    Sources of dispute:

    Changed conditions

    Additional work

    Delays

    Contract period

    ALTERNATE DISPUTE RESOLUTION/REDRESSAL MECHANISM (ADR)

    ADR is a holistic concept of a consensus- oriented approach to deal with potential and actual

    dispute. The Arbitration and Conciliation Act, 1996 promises to be efficient and effective

    alternate system of dispute resolution.

    ADR methods:

    Mediation

    Negotiation

    15

  • 7/27/2019 Training Project Complete

    16/64

    Conciliation

    Finally if all these mechanism fails by : an Arbitration

    CONTRACT CONDITIONS FOR HEIGHTS

    The scope of work shall mainly consist the following:

    i. Earthwork and dewatering works.

    ii. Plain / Reinforced cement concrete works.

    iii. Masonry works.

    iv. Steel works.

    v. Wood works.

    vi. Floor finishing works.

    vii. Wall finishes

    viii. Miscellaneous works.

    ix. Fire/ smoke check doors Roofing / water proofing works.

    SL.NO TOWER/

    BUILDING

    NO OF

    APPARTMENTS

    NO OF

    FLOORS

    TENTATIVE

    AREA(M2)

    1. Basement 1 1300

    2. Tower1 71 28 15237

    3. Tower2 64 26 10904

    4 Tower3 71 28 15237

    5. Tower4 64 26 10904

    6. Tower5 71 28 11767

    TOTAL 341 77049

    completion period : 18 months

    date of start : 1st November 2006

    date of completion : 30 April 2008

    total contract value : 462868562/-

    16

  • 7/27/2019 Training Project Complete

    17/64

    value of work : 444898233/-

    added service tax : 17970329 /-

    total : 462868562/-

    Cost of material

    supplied by the

    owner : 270000000/-

    (Which includes Ready mix concrete, Cement, Reinforcement steel)

    TERMS FO PAYMENT:

    Mobilization advance 10% of contract price.Immediately on award of work : 5.0%

    Mobilization of cranes and lifts : 2.5%

    Mobilization of 50% shuttering : 1.5%Mobilization of balance 50% of : 1.0%

    shuttering material _______________

    TOTAL 10.0%

    Security deposit:

    5% of work done to be deducted from running bill subjected to maximum of 60 lac.

    Performance guarantee : 5% of contract value

    ESCALATION

    Vm = 0.5(W-Wm)(C1-C0)/C0V1 = 0.3W(L1-L0)/L0

    Where;

    Vm = variation in material costV1 = variation in labour cost

    W = gross work done during the period

    Wm = gross work done during against time mentioned in BOQ with basic ratesC1 = All India wholesale price index

    C0 = All India wholesale price index in the month in which prices bids are opened.

    L1 = revised minimum labour wagesL0 = Minimum labour wages in the month in which price bids are opened.

    17

  • 7/27/2019 Training Project Complete

    18/64

    SUPPLY OF MATERIAL BY THE OWNER:

    Cement:Grey cement ( OPC in bags)

    Allowable wastage variation: +1%

    Recovery beyond allowable wastage = Rs- 250/- per bag

    Reinforcement bars

    Allowable wastage/variation = +3%Invisible wastage = 1

    Recovery beyond allowable = 50,000 per MT

    wastage

    Ready mix concrete

    Allowable wastage variation : N/A

    Recovery beyond allowable : NOT ALLOWEDWastage

    CONTRACT CONDITIONS FOR CASCADES

    The scope of work shall mainly consist the following:

    x. Earthwork and dewatering works.

    xi. Plain / Reinforced cement concrete works.

    xii. Masonry works.

    xiii. Steel works.

    xiv. Wood works.

    xv. Floor finishing works.

    xvi. Wall finishes

    xvii. Miscellaneous works.

    xviii. Fire/ smoke check doors Roofing / water proofing works

    SLNO

    BUILDING/TOWER

    NO OFAPPARTMENTS

    NO OFFLOOR

    TENTATIVEAREA (M2)

    1. BASEMENT 1 46572

    2 TOWER 1 26 15 5547

    3 TOWER 2 26 15 5547

    4 TOWER 3 26 15 5547

    18

  • 7/27/2019 Training Project Complete

    19/64

    5 TOWER 4 52 21 9138

    6 TOWER 5 58 23 10086

    7 TOWER 6 58 23 10433

    8 TOWER 7 58 23 10433

    9 TOWER 8 58 23 10433

    10 TOWER 9 64 25 1103311 TOWER 10 64 25 11033

    TOTAL 490 135802

    completion period : 27 months

    date of start : 15th April 2007

    date of completion : 14th July 2009

    super structural work : 648426277/-

    basement work : 161403064/-

    total contract value : 810329341/-

    cost of materialsupplied by the

    owner : 480000000/-

    (Which includes Ready mix concrete, Cement, Reinforcement steel)

    TERMS FO PAYMENT:

    Mobilization advance 10% of contract price.

    Immediately on award of work : 5.0%Mobilization of cranes and lifts : 2.5%

    Mobilization of 50% shuttering : 1.5%

    Mobilization of balance 50% of : 1.0%shuttering material _______________

    TOTAL 10.0%

    Security deposit:5% of work done to be deducted from running bill subjected to maximum of 60 lac.

    Performance guarantee : 5% of contract value

    ESCALATION

    19

  • 7/27/2019 Training Project Complete

    20/64

    Vm = 0.5(W-Wm)(C1-C0)/C0V1 = 0.3W(L1-L0)/L0

    Where;

    Vm = variation in material cost

    V1 = variation in labour costW = gross work done during the period

    Wm = gross work done during against time mentioned in BOQ with basic rates

    C1 = All India wholesale price indexC0 = All India wholesale price index in the month in which prices bids are opened.

    L1 = revised minimum labour wages

    L0 = Minimum labour wages in the month in which price bids are opened.

    SUPPLY OF MATERIAL BY THE OWNER:

    Cement:

    Grey cement ( OPC in bags)Allowable wastage variation: +1%

    Recovery beyond allowable wastage = Rs 250/- per bag

    Reinforcement barsAllowable wastage/variation = +3%

    Invisible wastage = 1

    Recovery beyond allowable = 50,000 per MTwastage

    Ready mix concrete

    Allowable wastage variation : N/A

    Recovery beyond allowable : NOT ALLOWEDwastage

    SAFETYSAFETY

    Safety engineering is an applied science strongly related to the system engineering and the

    subset system of safety engineering. Safety engineering assures that life critical system behavesas needed when pieces fails.

    20

  • 7/27/2019 Training Project Complete

    21/64

    SAFETY ASPECT OF THE PROJECT:

    If the working environment around you is clean, than automatically it brings confidence in you

    to work and gives best output. Simplex gives lots of importance to Safety aspect in Engineers,

    Workmen. The main aim safety is zero accident.

    OCCUPATIONAL HEALTH AND SAFETY POLICYOF THE COMPANY:

    Intends to maintain a safe and healthy environment and takes due care about

    occupational health and safety of its employees.

    Strives to achieve zero accident rates through having an effective and competent site

    management team and trained wowed to force.

    In case of emergencies, the project management team is always ready and quick to

    respond to them.

    The uses of protective gears like safety helmets, protective shoes, safety nets etc. are

    strictly enforced among the workers at the site.

    RESPONSIBILITY OF SAFETY & HEALTH COORDINATOR

    Carry out Safety Inspection of Work area daily.

    Organize campaigns, competitions & other special emphasis program to promote HSE at

    the workplace.

    Highlight the requirement of HSE through PEP talks. Help to prepare Job Safety

    Analysis (JSA) for critical job.

    Conduct Investigation of all Accidents / Dangerous occurrences & recommend

    appropriate Safety Measures.

    Convene Safety Meeting & minute the proceedings for circulation & follow up actions.

    Advice & Co-Ordinate for implementations of work permit system.

    Plan procurement of PPE, Safety devices & inspect before use as per the laid down

    norms.

    Report to RSC on all matters pertaining to status of Safety & promotional program at site

    level.

    Sending reports to Safety Coordinator.

    21

  • 7/27/2019 Training Project Complete

    22/64

    Facilitate Screening of all Workmen & Safety Induction.

    Facilitate administration of First Aid.

    SAFETY TRAINING AND MOTIVATIONAL SCHEME AT SITE

    Simplex Infrastructures Limited conducts several orientation and training programs for all

    persons at site so that they will be fully aware of site safety rules, restrictions and necessary safe

    working methods.

    SAFETY INDUCTION COURSE:

    It is the policy of the Simplex Infrastructures Limited that all workers shall be familiarized with

    there work environment. Each person shall be fully aware of rules, restrictions and safe working

    methods manners in his assigned work. Refreshers training will be also conducted through other

    specified courses as required with a view to ensure that each person at the site is competent to

    perform his work safely and efficiently.

    Each person assigned to the construction site, prior to starting site activities, will be given an

    admission orientation covering all aspects of his work and area.

    The orientation covers the following topics;

    The Safety Policy of Simplex Infrastructures Limited

    Safety organization of Simplex Infrastructures Limited

    The complex regulation for construction safety.

    Work in restricted areas and highly hazardous works.

    Supervisors and employee responsibilities

    Personal Protective Equipments & Other Safety Gadgets.

    Fire prevention and fire protection.

    Medical and first aid facilities

    TRAINING PROGRAMS

    Simplex Infrastructures Limited conducts training programs with specific emphasis

    on HSE issues pertaining to the site activities. For example,

    The statutory codes and regulation on HSE.

    22

  • 7/27/2019 Training Project Complete

    23/64

    Site safety rules and requirements.

    Lock out and Tag out

    Accident Prevention & Accident Investigation.

    Safety & Health inspection emergency and rescue.

    All staff member & workmen shall receive basic training on safety.

    Safety induction programs shall be conducted for the new workmen and refresher

    programs for the existing gangs on routine basis.

    Sufficient number of workmen and staff shall be trained in first aid/ artificial

    respiration /fire - fighting to ensure quick reaction in case of emergency.

    All workmen shall be trained to follow safe working procedure to execute their

    respective jobs in the concerned area with the help of the Safety Engg Dept.

    Examples of training programs are as follows:

    Regular training.

    Safety Induction for visitors, new joiners staff, workmen,

    Preparatory talk on daily basis & subject will be chosen as per the need / demand.

    Periodical training.

    Fire fighting, First aid, Emergency preparedness, Electrical safety, Working at height,

    Erection & dismantling,

    Job specific (critical activities) relevant to Risk assessment

    VARIOUS MEASURES TAKEN ON SITE:

    PEPTALK/ TOOL BOX TALK

    Regularly pep talk is organized to motivate workmen and meet job specific demand by

    concerned supervisor. The significance of personal protective appliance shall be impressed upon

    the workman and their use ensure by all concerned.

    All sub-contractor and their supervisor conduct pep talk when new work start and give awareness

    of the work in presence of Site in-charge and Safety coordinator.

    Simplex provided PPE for employee and labours. Various PPE listed below:

    Sl. No Activity Suggested PPE

    1 Site Transport Safety Helmet, Safety Shoe.

    2. Handle of diesel Rubber hand gloves and Goggles.

    3. Material handling Safety Helmet, Safety Shoe, Hand gloves.

    4. WeldingWelding face shield attached with welding helmet, hand salves, safety

    shoe.

    5. Grinders Face shield attached with welding helmet, Safety Shoe, Hand gloves

    6. Gas cutting Face shield attached with welding helmet, Safety Shoe, Hand gloves

    7. Erection Safety Helmet, Safety Shoe, Hand gloves

    8. Crane operator Safety Helmet, Safety Shoe, Hand gloves

    23

  • 7/27/2019 Training Project Complete

    24/64

    9. Working at heights Safety Helmet, Safety Shoe, Safety belt.

    10. Excavation& Backfilling Safety Helmet, Safety Shoe, dust mask.

    11. Concrete work Safety Helmet, Safety Shoe, dust mask, gumboot &hand gloves.

    MEDICAL AND FIRST AID FACILITIES

    First Aid is an immediate and temporary care given to the victim of an accident. It may involve

    improvising with facilities and materials available at time.

    The main objectives of first aid are:-

    To preserve life

    To prevent the worsening of the condition

    To promote reconvenes

    FIRST AID FACILITY AT SITE

    Main first aid centre is established within the site premises at local convenient locationwith adequate facilities to handle the following emergence. Two full fledged first aider are made

    available at aid centre shift wise to extend to first aid service round the clock. First aid trainee is

    given to sub-contractor also. There be at least one standby emergence vehicles on site during

    working time.

    For shifting of critical patient who required hospitalization emergency vehicles is provided

    with medical facility.

    Simplex is tie up with some of the hospital having sufficient amenities to handle critical

    case effectively.

    SAFETY MATERIALS

    1. Safety Net:Safety nets are nets generally used in the side of the towers to stop some falling objects from the

    tower top. Sometimes it is useful for saving human life. It is made of Poly propelene Ropes.Generally it is of dimension (10mX4m). It has a mesh size of (2X2). The border rope is of

    diameter 12mm.

    2. ELCB/RCCB:An Earth Leakage Circuit Breaker(ELCB) device always checks for any leakage of current. An

    ELCB works by comparing the input current in the hot current line feeding a load and the return

    current in the central line coming back from the load. If the return current is less than the inputcurrent by a quiet small amount

    Usually only about 30 mA ,it means there must be a leakage current.RCCB means Residual Current Circuit Breaker which operates when there is a difference in

    current between any two phases.

    3. Barricading tape:The portion of the site under work is generally barricaded by a tape which notifies others for not

    entering the particular area .These kind of tapes are known as the Barricading tapes.

    4. Fall Arrester:

    24

  • 7/27/2019 Training Project Complete

    25/64

    It is a safety device connected with the rope and safety belts which protects the person working

    vertically at the top of the building from falling down.

    5. Flashback Arrester:

    It is a safety device generally used in gas cutting set. It is a one way valve which prevents fireand explosion the heat coming from nozzle.

    SCAFOLDING

    Scaffolding are structures erected besides the tall buildings which acts as a platform for work.

    The different parts of scaffolding are given below:

    Bay : The space between the center line of two adjacent standards.

    standard : A vertical or near vertical tubes based on the ground or a structure.

    Ledger : A longitudinal tube normally fixed parallel to the face of a building in the

    direction of the larger dimension of the scaffold. It acts as a support of the transoms are

    frequently for the tie tubes and ledger braces and is usually jointed with the adjacent

    standards.

    Brace : a tube placed diagonally with respect to the vertical or horizontal members of a

    scaffold and fix to them to afford stability.

    Working platform: the deck from which the building operations are carried out.

    Coupler : A components used to fix the scaffold tubes together.

    Toe Board : An up stand at the edge of a platform intended to prevent materials or

    operatives feet from slipping off the platform.

    There are four types of scaffolding.

    These are :

    Tower Scaffolding : The scaffolding consisting of four standards and not extended at any

    side.

    Independent Scaffolding : The scaffolding consisting of three or more standards in long but

    only two standards in wide. Bird cage Scaffolding : The scaffolding consisting of six or more standards in each

    direction.

    Hanging Scaffolding: The scaffolding hung from overhead.

    Tower & independent scaffolding

    25

  • 7/27/2019 Training Project Complete

    26/64

    SCAFFOLD CLASSIFICATION

    Scaffolds are classified by type according to their purpose for use. Each scaffold will have set

    maximum loadings, which in turn will determine the maximum bay centers as follows:

    TYPES USES Platform loading No. of

    boards &

    standard

    CRS

    Maximum bay

    centresKN/m2 Kg/m2

    Very light duty Independent Inspection 0.75 76 3(0.77m) 1

    Light duty Independent Plasterers, Painting and

    Cleaning

    1.5 153 4(1.0m) 2

    General purpose

    Independent

    Building work

    light brick work

    2.0 204 5(1.2m) 2 plus 1 very

    light duty

    Heavy duty Independent Brickwork

    Heavy cladding

    2.5 255 5(1.2m) 2 plus 1 very

    light duty

    Special or masonryIndependent

    Masonry work ConcreteBlock work

    3.0 306 6(1.45m) 1 plus 1 verylight duty

    Putlog duty birdcage New Brickwork 2.5 255 5(1.2m) 1

    Light duty birdcage Inspection, Painting,

    Cleaning

    0.75 76 Fully

    boarded

    1

    Hoist tower To change Hoist N/A N/A NILL N/A

    SAFETY FROM FIRE

    Fire: Fire is a chain reaction which involves the oxidation of combustible materials, heat and

    light energy emitted.

    Causes of fire:

    Ignorance

    Carelessness

    Poor

    Fire Triangle: Three main factors are essential to combustion

    Presence of fuel that is wood, petrol, paper etc.

    Presence of OXYGEN

    Temperature

    Principle of extinguishment of fire:

    Fire extinguishment involves removal of any one or more factors depicted by the fire triangle.

    The principle of extinguishment may be classified as follows:

    Starvation; By eliminating fuel

    Cooling; if the rate at which the heat is generating by combustion is less than the

    rate which is dissipated, then the combustion doesnt persist

    Smothering: By eliminating the air or oxygen from the fuel.

    26

  • 7/27/2019 Training Project Complete

    27/64

    CLASSIFICATION OF FIRE

    Class A-Ordinary/general/carbonaceous fire

    Class B-Flammable liquid fire

    Class C-Flammable gas fire

    Class D-Reactive metal fire

    CLASS EXAMPLE EXTINGUISHING EFFECT

    A Paper, wood, cloth etc. Cooling, smothering ,starvation

    B Petrol, diesel, oil, acetone

    etc.

    Smothering

    C Acetylene, methane,

    hydrogen, LPG etc.

    Smothering, cooling

    D Potassium, sodium,

    aluminum etc.

    Cooling, smothering ,starvation

    FIRST AID FIREFIGHTING APPLIANCES:

    Sand bucket

    Fire hook

    Fire beater

    Portable fire extinguisher

    Hose reel hose

    27

  • 7/27/2019 Training Project Complete

    28/64

    SAFETY INSTRUMENTS

    A SAFETY SIGN BOARD AT SIMPLEX

    FIRE EXTINGUISHER USE AS PER CLASSIFICATION

    EXTINGUSHIR CLASS

    A B C D

    SODA ACID X X X

    WATER CO2 X X XFOAM X X X

    DCP

    CO2 X X

    28

  • 7/27/2019 Training Project Complete

    29/64

    EXECUTIONEXECUTION

    FINISHING ACTIVITIES:

    Finishing is the major part of building. Cost of the finishing is 70% of the total cost of building.

    Finishing work done in some parts are as follow:-

    Brick work

    Door frame

    Window frame

    Railing

    Plastering

    Tilling &stone work

    Plaster of Paris

    Indian patent stone (IPS)

    False ceiling

    29

  • 7/27/2019 Training Project Complete

    30/64

    Painting

    BRICK WORK:

    Brick work is masonry produced by a bricklayer, using bricks and mortar to build up brickstructure such as walls. This project site walls are build up reinforcement brick work forhigh rise building (tower). Reinforcement bars is provided after three layers of brick differ.

    Here thickness of brick work are 125mm & 250mm .250mm thickness of brick work used

    for main wall with proportion of mortar 1:6 & 125mm thickness of brick work used forpartition wall with proportion of mortar 1:4 ( cement : sand).

    METHODOLOGY

    Bricks are properly soaked into the water.

    The brickwork surface is also properly wetted

    Then two brick placed as stretcher perpendicular to the line of brickwork.

    Then the alignment is checked and a straight string is tied in to the brick previously

    placed along the line of brickwork is to be done as the outer boundary line.

    Then the bricks are placed and joined by the mortar of specified mixed ratio.

    After finishing the complete row the next row brickwork is done by following the same

    procedure.

    The joint of the brickwork must be discontinues.

    Reinforced brick work is being carried out hence after every three layer two bars of

    diameter 6mm is provided in brickwork for lateral support.

    PLASTERING :

    Plaster is done on internal wall , external wall and ceiling. Thickness of internal

    plaster is 12mm with 1:4 (cement: sand) proportion. Ceiling plaster thickness is 6mm with

    1:3. Thickness of external plaster should be 15mm with proportion 1:6. Generally it may be18-20mm thickness.

    METHODOLOGY

    The wall is inspected for electrical conduits, window frames, door frames etc.

    The brick wall surface is properly wetted with water.

    Chicken mesh is used to make brick wall monolithic with columns.

    Placing the cement mortar in patches of 12 to 15 mm thickness as per the requirement.

    Covering the whole wall with mortar maintaining the thickness with respect to the

    patches.

    30

  • 7/27/2019 Training Project Complete

    31/64

    Levelling of mortar is done with the help of aluminium bar

    If there is any void space after the levelling that is filled by the mortar.

    Finally the whole wall is levelled properly and our plastering work is

    finished.

    TILING & STONE WORK :

    In phase 2A two types are used:

    Ceramic tiles

    Vitrified tiles.

    METHODLOGY

    The floor is cleaned by removing dust and debris.

    Then the surface is wetted by water.

    After that the cement sand mortar is prepared.

    Levelling patches are provided at different places to maintaining the level at the time of

    placing of tiles.

    The whole area is then covered by the mortar up to the level of patches.

    Then the cement slurry is spread over the surface

    Then the tiles are gently placed over the surface with the gap of 3 mm

    The gap is finally files by thin cement slurry.

    Finally the tiles were clean and the tiling work is finish

    BACKING FOR TILING:-

    12-15 mm thick backing for tiling is used for wall. Generally 20-25mm thickness

    backing is used for floor.

    Use tiling mortar with 1:4 (cement: sand) proportion for floor.

    Use tiling mortar with 1:3 proportion for wall.

    31

  • 7/27/2019 Training Project Complete

    32/64

    Cement water paste is used on back side of tiles.

    STONE WORK :

    The following stones are used in the site:

    Crown pink stone: Crown pink stone is used for flooring at lobby.

    Marigold granite stone: Marigold stone is used at beside the lift facial.

    Kota stone: Kota stone is used in stair case. Udaipur green Kota stone is

    also used at duplex stair case. Dado of Kota stone is 100mm.To complete

    flooring in stair case 2.5 mason and 2.5 numbers labours are required for two

    flight, mid landing, final landing and dado finishing.

    INDIAN PATENT STONE (I.P.S.):

    Indian patent stone is one type of flooring with is used in bedroom of all

    apartments in project. In this case the total floor area is divided in several panels (1mx1m)by using PVC strip. Dimension of these strips are 4mm in thickness & 40mm in width.

    Then concreting is done in alternate to create a non homogeneous joint as we can prevent

    huge repair cost when repairing is needed. Mix ratio of IPS is 1:2:4 where sand is medium

    coarse sand and stone chips are 12mm down. After IPS the flooring is covered by woodenblock by using adhesive material.

    PLASTER OF PARIS(POP):

    POP is done to get smooth surface on wall. Pop is done in some steps:

    Clean the plastered wall surface.

    Watering the surface.

    Make a suitable lay of Paris.

    Apply the POP on wall.

    In our project we use 3mm-4mm POP covering on internal wall surface But we can use4mm-6mm thick POP finishing.

    In market 50 kg bag is available which covers 20m2 wall area. One painter can paint 20m2

    wall area in a day .VACUUM DEWATERED FLOORING

    32

  • 7/27/2019 Training Project Complete

    33/64

    Methodology:

    A bed of silver sand of thickness 650mm is laid first.

    The sand is then compacted and a thin plastic is laid over it

    50mm PCC done over the plastic layer.

    Reinforcement bars of diameter 8mm and 10 mm with clear cover 25 mm is laid over thePCC at a distance of 200mm centre to centre.

    The PCC surface first scratched and then wetted before the casting.

    100mm thick slab is casted and vibrated with the use of vibrator for better compaction.

    A thin net is laid over the casted layer after about 10-15 minutes of casting.

    A mat with arrangement for suction is spread over the net

    Water is drawn out with the help of VDP(Vacuum Dewatering Pump)

    After dewatering, hardener named SIKA CHAPDUR is spread over the surface @

    4Kg/m2

    The surface is levelled properly with the help of power trowel

    Finally after proper levelling, brushing of the surface is done.

    Advantages of VDF:

    The compressive strength of floor increased

    Theres a gain in tensile strength

    Cement consumption is reduced as no cement is required separately for finishing the

    surface.

    Abrasion resistance of the floor increased resulting in less wear and rear of the floor

    surface

    Shrinkage of concrete is reduced and floor warps less.

    Grade of Concrete:

    Minimum grade of concrete used shall be M15 conforming to IS-456. Only Design MixConcrete shall be used

    Water-Cement ratio:

    Water-cement ratio upto 0.65 shall be allowed to obtain better slump& workability. Actual ratio

    shall be decided with approval of the Engineer-in-charge. Only measured quantity of water

    shall be used in the mix.

    Special Requirement:

    All works covered by this specification shall be carried out by an experienced agency having

    sufficient expertise in vacuum Dewatering concrete system. Only skilled and experienced

    operators shall be employed for the purpose. Prior approval of the agency shall be obtainedfrom the Engineer-in-Charge before starting the work. All the equipment shall be of approved

    33

  • 7/27/2019 Training Project Complete

    34/64

    and proven types and suitable for the work involved.

    Concrete Laying:

    Concrete laying pattern shall be decided in consultation with the Engineer-in-Charge and with his

    approval. The maximum width of a slab strip shall not generally exceed 4 meters and minimum number

    of construction joints shall be used. Alternate slab strips shall be sequentially laid. Any damage to the

    already finished top surface shall be avoided. At construction joints no overflow of mortal or slurry on

    the already hardened surface shall be allowed while concreting the intermediate slab strip. Such

    construction joints shall be marked with a thread in a straight line while the concrete is still green.

    Continuity of reinforcement shall be maintained while laying concrete in slab strips. Edges at expansion

    joints shall be protected and proper arrangement of shear-transfer shall be provided.

    QUANTITY SURVEY

    34

  • 7/27/2019 Training Project Complete

    35/64

    TOTAL BRICK WORK, TILING AND PLASTERING ON A TYPICAL FLOOR

    SL NO. DESCRIPTION UNIT NUMBER LENGTH HEIGHT WIDTH QUANTITY

    TOTAL

    QUANTITY

    BRICK WORK

    A 250 mm thick wallx10^6mm^3

    1 MASTER BEDROOM 2 3325 2450 250 4073.125

    1 1750 1100 250 481.25

    1 1475 2700 250 995.625

    1 600 2700 250 405

    2 BED ROOM 2 1750 1100 250 962.5

    1 325 2450 250 199.0625

    1 600 3150 250 472.5

    1 675 2700 250 455.625

    1 250 2450 250 153.125

    3 LIVING ROOM 2 250 2450 250 306.25

    1 2331 2450 250 1427.7375

    1 731 2700 250 493.425

    4 DINING ROOM 2 440 2450 250 539

    5 STORE ROOM 2 1360 2700 250 1836

    6 LIFT 2 1950 2700 250 2632.5

    1 450 2700 250 303.75

    1 450 2700 250 303.75

    7 STAIR ROOM 2 2160 2450 250 2646

    1 1290 1100 250 354.75

    1 750 600 250 112.5

    1 1085 2600 250 705.25

    1 1615 500 250 201.875

    1 750 500 250 93.75

    1 1755 2600 250 1140.75

    8 TOILET 2 750 600 250 225

    1 850 2450 250 520.625

    1 2300 2775 250 1595.6251 850 2450 250 520.625

    1 850 2700 250 573.75

    9 GARBAGE BINS 1 1700 2700 250 1147.5

    1 1250 2450 250 765.625

    1 1250 2600 250 812.5

    1 800 2700 250 540

    1 750 2700 250 506.25

    35

  • 7/27/2019 Training Project Complete

    36/64

    10 UTILITY 1 1365 2450 250 836.0625

    1 890 2700 250 600.75

    1 860 2700 250 580.5

    1 750 600 250 112.5

    11 KITCHEN 1 775 3150 250 610.3125

    1 1075 1100 250 295.625

    1 125 2450 250 76.5625

    12 LIVING/DINING 1 1365 2450 250 836.0625

    1 2790 2450 250 1708.875

    1 1175 2450 250 719.6875

    1 2160 2450 250 1323

    1 1826 1400 250 639.1

    1 3060 2100 250 1606.5

    1 709 3150 250 558.3375

    1 675 2450 250 413.4375

    13 MASTER BEDROOM 1 2790 2450 250 1708.875

    1 700 1400 250 245

    14 TOILET 1 805 2450 250 493.0625

    1 475 2450 250 290.9375

    42157.7875

    B 125 mm thick wall 0

    1 BED ROOM 2 3800 2700 125 2565

    1 2200 2700 125 742.5

    1 725 2775 125 251.484375

    1 1825 2450 125 558.90625

    1 600 3150 125 236.25

    2 TOILET 2 2800 2700 125 1890

    1 1100 2700 125 371.25

    1 1425 3150 125 561.09375

    1 600 3150 125 236.25

    1 2090 2700 125 705.375

    1 700 3150 125 275.625

    1 575 3150 125 226.40625

    1 1235 2700 125 416.8125

    1 880 3150 125 346.5

    1 1803 2450 125 552.168751 625 2450 125 191.40625

    1 750 3150 125 295.3125

    3 DINING 2 2800 2700 125 1890

    4 KITCHEN 2 1150 2450 125 704.375

    1 2625 2700 125 885.9375

    1 2250 3150 125 885.9375

    36

  • 7/27/2019 Training Project Complete

    37/64

  • 7/27/2019 Training Project Complete

    38/64

    1 635 475 30.1625

    1 1630 1053 171.639

    3 STORE 2 2380 1860 885.36

    1 940 750 70.5

    1 555 350 19.425

    3274.5115

    F PLASTERING 0

    1 MASTER BEDROOM 2 5550 3035 3368.85

    1 1500 3035 455.25

    1 3925 3035 1191.2375

    1 1225 3035 371.7875

    1 600 3035 182.1

    1 250 3035 75.875

    1 1700 3035 515.95

    1 1000 3035 303.5

    1 2450 3035 743.575

    1 675 3035 204.8625

    1 1750 3035 531.125

    2 BED ROOM 2 2200 3035 1335.4

    1 3800 3035 1153.3

    1 2925 3035 887.7375

    1 600 3035 182.1

    1 1100 3035 333.85

    1 600 3035 182.1

    1 1750 3035 531.125

    1 750 3035 227.625

    1 900 3035 273.15

    3 BED ROOM 2 1350 3035 819.45

    1 3725 3035 1130.5375

    1 2400 3035 728.4

    1 425 3035 128.9875

    1 3575 3035 1085.0125

    1 750 3035 227.625

    1 2350 3035 713.225

    1 500 3035 151.751 350 3035 106.225

    1 900 3035 273.15

    4 LIVING ROOM 2 3500 3000 2100

    1 2575 3000 772.5

    1 1800 3000 540

    1 1700 3000 510

    38

  • 7/27/2019 Training Project Complete

    39/64

    1 6130 3000 1839

    1 4660 3000 1398

    1 7331 3000 2199.3

    1 475 3000 142.5

    1 2200 3000 660

    1 731 3000 219.3

    5 STORE ROOM 1 1500 3000 450

    1 3005 3000 901.5

    1 2100 3000 630

    1 1360 3000 408

    1 880 3000 264

    6 KITCHEN 2 1960 3150 1234.8

    1 900 3150 283.5

    1 2725 3150 858.375

    1 2100 3150 661.5

    1 1150 3150 362.25

    1 600 3150 189

    1 1000 3150 315

    1 1250 3150 393.75

    7 DINING 2 2925 3000 1755

    1 2450 3000 735

    1 565 3000 169.5

    8 BALCONY 2 1000 3000 600

    1 725 3000 217.5

    1 875 3000 262.5

    1 815 3000 244.5

    1 875 3000 262.5

    1 725 3000 217.5

    1 1125 3000 337.5

    1 875 3000 262.5

    1 670 3000 201

    1 250 3000 75

    1 2450 3000 735

    1 1250 3000 375

    1 3500 3000 1050

    1 2331 3000 699.31 1800 3000 540

    9 TOILET 8 750 3000 1800

    1 1550 3000 465

    1 725 3000 217.5

    1 2340 3000 702

    1 2340 3000 702

    39

  • 7/27/2019 Training Project Complete

    40/64

    1 2300 3000 690

    2 750 3000 450

    1 825 3000 247.5

    1 575 3000 172.5

    1 1475 3000 442.5

    1 1235 3000 370.5

    1 2800 3000 840

    1 975 3000 292.5

    1 725 3000 217.5

    1 875 3000 262.5

    1 1053 3000 315.9

    1 875 3000 262.5

    1 625 3000 187.5

    1 1440 3000 432

    53556.3375

    QUALITY CONTROLQUALITY CONTROL

    QUALITY CONTROL ASPECT OF THE PROJECT:

    As quality play very important role in every project, Simplex also gives lot of importance to

    Quality control and Quality assurance aspect. Keeping in mind, the company has prepared Quality policy

    and planned for the quality and necessary action in advance so that the quality of work meets the I.S

    standards and contract specification and full the needs of the Clients.

    40

  • 7/27/2019 Training Project Complete

    41/64

    Simplex has set up well equipped quality laboratory in the site where all the tests being

    performed in the presence of consultant client. Records are being maintained as per ISO standards

    QUALITY POLICY OF THE COMPANY:

    We, in the Simplex Infrastructures Limited, are committed to executed project as per customer

    requirement ensuring customer satisfaction through implementation quality management systems in

    according with ISO 9001:2008 and making continual effort to enhance quality.

    QUALITY OBJECTIVES OF THE COMPANY:

    To inculcate in the minds of our employee the culture of project execution with continent quality

    assurance and adherence to milestone as per customer requirement through development of programmeand guidelines.

    To ensure and improve customer satisfaction.

    To maintain a conducive environment and infrastructural facilities at work place with

    due consideration for occupational health and safety legislations.

    VARIOUS TESTS BE CONDUCTED ON THE SITE:

    Cube Compressive Strength tests.

    Slump test (Workability)

    Test for bricks.

    Aggregate test.

    Tests on all incoming Materials as per specifications.

    VARIOUS TESTS CONDUCTED IN LABS:

    Reinforcement test

    Cement test

    Water test

    TESTS FOR CONCRETE:

    Workability of concrete is proportional to the water cement ratio and is inversely proportional to the

    strength i.e. water cement ratio is inversely proportional to the strength.

    Compressive Strength Test:

    Cube test is used for measuring the compressive strength of concrete.

    We take 6 cubes of dimension (150mmX150mmX150mm) for testing purpose.

    Here 3 cubes are used to test after 7 days and the rest 3 cubes used in 28 days for getting the result.

    About 2/3rd of the strength is gained in 7 days.

    PROCEDURE:

    41

  • 7/27/2019 Training Project Complete

    42/64

    A mould of dimension (150mmX150mmX150mm), made of 3 parts is used for the test.

    Concrete is being filled and tampered.

    The upper surface is smoothed and levelled.

    The cube is hence prepared.

    The cube is compressed in the compressive testing machine after 7 and 28 daysrespectively.

    The compressive strength of the concrete is read from the reading of the pressure gauge.

    Slump Test:

    Slump test is used to determine the workability of concrete on site.

    Testing instrument:

    Slump cone

    Tampering rod.

    PROCEDURE:

    Slump cone is filled with concrete in 4 layers.

    Each layer is being filled and tampered for about 25 times for compaction.

    The upper surface is then smoothed and leveled.

    The slump cone is then vertically lifted.

    The tampering rod is marked with a measurement scale.

    The level of fall of concrete from the top determines the workability.

    Slump results for some specific cases:

    heavy slump 100mm

    slump for mass concrete 50mm

    slump for concrete used in road (25 to 50)mm

    slump for pump concrete (120 to 150)mm

    If the slump value of concrete exceeds 150, then it is called loose concrete.

    42

  • 7/27/2019 Training Project Complete

    43/64

    The 7 days strength should not be less than 67%

    Average 28 days strength of all the cubes should be fck +3

    Individual strength of cubes should not be less than fck

    If RMC fails in compressive strength retrofitting works or remedial measures are applied

    such as:

    dismantling

    jacketing using steel sheets grouting

    In-situ test for concretes:

    load test

    hammer test

    core-cutter test

    NOMINAL MIX FOR VARIOUS GRADES OF CONCRETE:

    GRADE NOMINAL MIX

    M7.5 1:4:8PCC

    M10 1:3;6M15 1:2:4

    RCCM20 1:1.5:3

    M25 1:1:2

    PLACES OF USE OF VARIOUS GRADES OF CONCRETE AT UNITECH SITE:

    M7.5 Plain Cement Concrete

    M25 Casting of slabs, beams, VDF, Pile Caps, Deck Slabs, Lintels, Retaining WallsM30 Columns (10th to top floor)

    M35 Columns (4th to 10th floor)M40 Columns (basement to 4th floor)

    CEMENT:

    Types of cement used nowadays are as follows:

    43

  • 7/27/2019 Training Project Complete

    44/64

    Type of Cement

    (with relevant grade and IS code)

    Compressive Strength

    3days 7days 28days

    OPC (33 Grade) IS-269,1989 16 Mpa 22Mpa 33Mpa

    OPC (43 Grade) IS-8112, 1989 23 Mpa 33Mpa 43Mpa

    OPC (53 Grade) IS-12269, 1987 27 Mpa 37Mpa 53Mpa

    -

    16 Mpa 22Mpa 33MpaPPC(Fly Ash Based) IS-1489 (P1), 1991

    PPC (Calcined Clay Based) IS-1489 (P2), 1991

    TESTS FOR CEMENT:

    Tests for reinforcement steel:

    There are two grades of steel are used in our site.

    Fe-500

    Fe-415 HYSD bars.(High Yield Steel Deformed Bar)

    The bars used are TMT bars that is Thermo Mechanically Treated bars.

    44

    Type of test Permissible Value Equipment used

    Fineness of Cement Cement retained not more than 10% IS sieve of 90 micron (sieving time 2min)

    Normal Consistency 28% - 30%

    Vicat ApparatusInitial setting Time not less than 30min.

    Final setting Time not more than 600min i.e. 10hr.

    Soundness Expansion not more than 10mm La-Chartlier

    Specific Gravity 2.89 3.00 Specific Gravity bottle

    Compressive

    Strength test

    Cube mould of size (70.6mm x 70.6mm x 70.6mm)

    No of Sample casted 9nos for 3days, 7days, 28days tests (each test 3nos cube).

    Proportion of mortar for cube casting-200 gm Cement : 600 gm Standard Sand (GrI 200 gm,GrII 200 gm, GrIII 200 gm)

    Water Added [(P/4)+3]% , P = Normal Consistency in %

    Mixing time 3 min. - 4 min., Time of Vibration 2min.

    Frequency of test for each Batch 1no of test, for each lot 1 no of test

  • 7/27/2019 Training Project Complete

    45/64

    Tests are classified into two categories.

    Physical test.

    Chemical test

    Physical tests:

    NATURE OF TEST REQUIREMENTS AS PER IS 1786-1985

    Grade Fe500

    Tensile strength(N/mm2) 545(min)

    Yield strength(N/mm2) 500(min)

    % elongation at break on a gel 12.0(min)

    Weight per meter length(kg/m) 3.85for 25 mm dia

    Bend No sign of crack should be visible

    Chemical Tests:

    NATURE OF TESTS REQUIREMENTS

    Carbon(C) % 0.3%(max)

    Sulphur(S) % 0.055%(max)

    Phosphorus(P) % 0.055%(max)

    TEST FOR AGGREGATESTypes of aggregate:

    Coarse aggregate (CA) Fine aggregate (FA)

    Types of test:

    Grading Analysis. (CA & FA).

    Specific gravity. (CA & FA).

    Bulk density. (CA & FA).

    Moisture content. (CA & FA).

    Bulking of sand. (FA).

    Water absorption value. (CA).

    Aggregate crushing / impact value. (CA) (not > 45% for Concrete, 30% for Road, runway)

    Abrasion value. (CA) (not > 50% for Concrete,30% for Road, runway) Flakiness index. (CA).

    Elongation index. (CA).

    Soundness of aggregates. (CA)

    45

  • 7/27/2019 Training Project Complete

    46/64

    TESTS FOR WATER:

    For testing of construction water As per IS 456: 2000

    CHARACTERISTICS Permissible Limit Max CHARACTERISTICS Permissible Limit Max

    Inorganic Matter

    (mg/l)

    3000 Sulphate (mg/l) 500

    Suspended Matter

    (mg/l)

    2000 pH not less than 6

    Chloride (mg/l) 1000 Organic Matter 200

    46

  • 7/27/2019 Training Project Complete

    47/64

    For testing of construction water As per IS 14543, 1998

    TESTS FOR BRICKS: (as per IS-3495)

    Dimension (250x125x75)mm

    Shape and size

    Colour

    Metallic ringing sound when collide each other.

    Warpage test

    Water absorption test(20% max)

    Efflorescence test (moderate upto 12.5%)

    Strength test Compressive strength(not less than 10.0 less than 12.5)

    TESTS FOR SHUTTERING PLY:

    The type of ply is used in our site is red ply named Laminated Ply. Another type of ply is

    available in the market called white ply or commercial ply.

    Ply dimensions: 1.22mx2.44mx12mm

    47

    CHARACTERISTICS Requirement Max CHARACTERISTICS Requirement Max

    Colour (Colour unit, Max) 5.0 pH 6.5 8.5

    Odour Unobjectionable Zinc Zn (mg/l, Max) 5

    Taste Agreeable Aluminum Al (mg/l, Max) 0.03

    Turbidity (NTU) 5 10 Chloride Cl (mg/l, Max) 250

    Total Dissolved solids (mg/l,

    Max)

    500 Sulphate SO4 (mg/l, Max) 200

    Hardness as CaCO3 (mg/l, Max) 300 600 Copper Cu (mg/l, Max) 0.05

    Alkalinity (mg/l, Max) 200 600 Calcium Ca (mg/l, Max) 75

    Magnesium Mg (mg/l, Max) 30 Iron Fe (mg/l, Max) 0.3 1.0

    Manganese Mn (mg/l, Max) 0.1 Fluoride F (mg/l, Max) 1.0 1.5

    Phenolic Compound (mg/l, Max) 0.001 Nitrate (mg/l, Max) 45

    Residue free Chlorine (mg/l, Max) 0.2 Mineral oil (mg/l, Max) 0.01

    Mercury Hg (mg/l, Max) 0.001 Cadmium Cd (mg/l, Max) 0.01

    Arsenic As (mg/l, Max) 0.05 Cyanide CN(mg/l, Max) 0.05

    Lead Pb (mg/l, Max) 0.05 Chromium Cr (mg/l, Max) 0.05

    Coliform Organisms

    (MPN/100ml)

    10 Pesticides (mg/l) Absent

  • 7/27/2019 Training Project Complete

    48/64

    Weight of the ply: 30 to 35 kg per piece.

    CALIBRATION OF MACHINES:

    Certified from Superintendence Co of India (P.) ltd.(NABL Accredited & ISO 9001:2000)

    NABL National Accrediation Board for Testing and Calibration Laboratories.ISO/IEC 17025:2005

    The instruments are to be tested after every 1 year. The various instruments being tested are:

    pressure gauge

    vernier calipers

    wire gauge

    micrometer and screw gauge

    digital balance

    slump cone

    hot air oven

    measuring cylinder

    IS sieve

    Silt And Clay content in sand

    Silt and clay content should be tested to know the quality of sand. It is done by taking a sample

    of sand in a measuring cylinder and fully saturating it. After a while two layers are produced at

    the top of the sand i.e. clay and silt layers respectively. The permissible limit for clay and silt

    content is 10%. It should not be more than that.

    WATER PROOFING AGENT (SIKA LATEX)

    Material repair work/plaster wall painting Putty

    SIKA 1 1 1

    WATER 6 4 2

    CEMENT as per requirement 6 1

    48

  • 7/27/2019 Training Project Complete

    49/64

    SAND as per requirement - 1

    PLANNINGPLANNING

    A systematic, time maintaining, economic, quality controlled and safety process that is beingprepared before the commencement of a project for t is being prepared structure wise.

    ASPECT OF PLANNING IN A CONSTRUCTION JOB:

    Construction planningis a fundamental and challenging activity in the management and

    execution of construction projects. It involves the choice of technology, the definition of work

    tasks, the estimation of the required resources and durations for individual tasks, and theidentification of any interactions among the different work tasks. A good construction plan is the

    basis for developing the budget and the schedule for work. Developing the construction plan is a

    critical task in the management of construction, even if the plan is not written or otherwise

    formally recorded. In addition to these technical aspects of construction planning, it may also benecessary to make organizational decisions about the relationships between project participants

    and even which organizations to include in a project. For example, the extent to which sub-

    contractors will be used on a project is often determined during construction planning.Planning is mainly of four types:

    Material plan

    Labour or man-power planMachine plan

    SELECTION OF MACHINE:

    Output of the machine: According to the scope of work and depending on the output of themachine we can choose the correct machine for a particular work.

    Efficiency: The ratio of the output to the input of a machine is known as efficiency of that

    machine. So to choose a particular machine we should first choose its efficiency.

    Place of work: The type of machine required for a particular job hugely depends on the place or

    location of the project. According to the climate and temperature change a suitable kind ofmachine is to be chosen.

    Size & Shape: The shape and size of the machine depends on the quantity of work to be done

    and also the amount of space available at the site for work.

    Cost or hire Charge: The machine is to be chosen depending on its cost and hire charge. It

    largely depends on the amount allotted for that particular project.

    Availability of operator: If we choose a particular type of machine, we should make sure that a

    good operator is also available for the operation of that machine.

    49

  • 7/27/2019 Training Project Complete

    50/64

    Transportation: The machine to be hired should not be supplied from a great distance so as to

    cut the cost of transportation.

    Fuel consumption: We should choose such a kind of machine which is economical in fuel

    consumption.

    Cost & Availability of parts: If any machine is imported, we should make sure that all the parts

    of the machine are available in nearby location to retard the cost of the project.

    Maintenance cost: While hiring a machine we should always keep in mind that a hiring cost

    should also be allotted with it.

    Longevity of machine: Machine should be handled in such a way that it could be used for a

    longer period of time.

    Storage: The machine should be selected such that it could be stored in a shed in the project site

    or nearby easily.

    Standardisation: The machine should always be standardised for all the works.

    SELECTION OF SUPPLIER

    Cost: At first the rate of all the contractors is to be taken so that we can decide whom to give

    the work to.

    Quality: Before giving the contract to a supplier we should consult with the market about the

    goodwill and the supplying quality of that supplier. Transportation: We should keep in mind that the supplied materials from the supplier are not far

    away from the site, or else we have to think about extra transportation charges. We can also deal

    by making the contractor give the transportation charges.

    Behaviour: While making the contract we can make sure that the contractors behaviour is well

    or else he could make problem while supplying the material.

    Delivery time: While making the contract we should firmly mention the delivery time some

    days before the project or else it may cause delay in project.

    Payment terms: Payment terms should be mentioned as per deal with the contractor so that he

    could not raise any argument further. The dealing may be in terms of months, total or as per

    supply.

    SELECTION OF SUB-CONTRACTOR

    Time: While giving a contract to a subcontractor we should always bind his time limit so

    that he does not take a much longer time to finish the project.

    50

  • 7/27/2019 Training Project Complete

    51/64

    Cost: The cost of the project part handled by the subcontractor should be discussed

    before giving him the contract. Thus we could estimate the profits and cost of project

    under that particular subcontractor.

    Labours: We should always check the ability of the contractor to supply labours. Based

    on the number of labours he could provide, we decide to give him the contract.

    Experience: The experience of the contractor should be kept in mind so that we canmake sure that he will give a good output.

    Quality: We should always check from the previous work of the subcontractor to make

    sure that he is capable of doing good quality of work.

    Labour accommodation: Labour accommodation should be well known so as to make

    their place for living in the site or nearby.

    Payment terms: Payment terms should be mentioned as per deal with the contractor so

    that he could not raise any argument further. The dealing may be in terms of months,

    total or as per supply.

    Origin of labour: The origin of the labour is essential as we could clearly acknowledge

    the time the labours will be absent during the festivals. Behaviour: While making the contract we can make sure that the contractors behaviour

    is well or else he could make problem while supplying the material.

    Efficiency: Performance of a supplier is his past reputation and ability of his supply. The

    performance of the supplier should always be noticed before giving the contract.

    51

  • 7/27/2019 Training Project Complete

    52/64

    ELECTRICAL DEPARTMENTELECTRICAL DEPARTMENT

    In a word electrical dept means that dept which governs all works or job concerning electricity.

    Simplex Infrastructure Limited concentrate on this dept and develop an authentic electrical deptby appointing good electrical engineer in every project site. In BUUIPL , Rajarhat site simplexhas developed an electrical dept which look after all the electrical machines and other

    component concerning electricity.

    ASPECT OF ELECTRICAL DEPT IN A HIGHRISE BUILDING PROJECT:

    As like other civil engineering works , in high rise building project we need several electrical

    machines which can not be operated without electricity and the project can not be done withoutthese machines. These machines are supervised by the mechanical dept , so there should be good

    connection between these two dept. Tower crane, building hoist, builder hoist, vibrator ,

    submersible pump , concrete mixer machine, bar bending machine, bar cutting machine etc arethe electrical machines can not work without electricity. So we need electricity connection from

    some other outside agencies or we have to generate electricity. In BUUIPL, Rajarhat site

    simplex has arranged some diesel generator to generate the electricity. Diesel Generators are the

    one most important machines which are supervised by our electrical dept.

    SOME IMPORTANT ELECTRICAL MACHINES AND EQUIPEMENT:

    DIESEL GENERATOR (D.G.):

    Diesel generator means the generator which generates electricity from diesel. There are

    several types of D.G. available in market of various capacity ,eg; 150 kVA,125kVA,100 kVA,75 kVA etc.

    In our site there are several DG of several capacity.

    1kVA is equivalent to 1.4 Amp.

    So 125 kVA is equivalent to 175 Amp.

    But for safety we apply only 80% load of maximum permissible load. So we can apply 140

    Amp load (max) on a 125 kVA D.G.

    D.G. produce generally 65 to 80 Amp current in form of direct current. We transform this DC toAC by using rectifier and then we use either Automatic Voltage Regulator (AVR) or step up

    transformer to get the desired amount of electricity.

    Fuel consumption:

    For 125 kVA DG:

    15 lit/hr (on 80% load of max. permissible load=112 Amp)20% extra = 18 lit/hr (on maximum permissible load=140 Amp)

    52

  • 7/27/2019 Training Project Complete

    53/64

    ELECTRICAL APPIANCES RUNNING INSIDE SITE OFFICE

    Place Tube

    light

    Ceiling

    Fan

    Stand

    fan

    exhaust refrigerator 3 phase

    UPS

    Wall

    fan

    CFL AC 3 phase

    motor

    3-phase

    compressive

    Kitchen 1 1 1 1

    Dining 6 3 1

    Toilet 2 2 1 1

    Quality 6 2

    Planning 2 4

    Accounts

    1

    2 1 1 1

    Accounts2 3 2

    PM 3 2 1

    Tea hut 1 4

    Store 3 3 1 4

    Mech/electric

    3 2 3

    verandah 4

    Sl no. Item number power Total power

    1 Tube light 34 40 13602 Ceiling fan 23 80 1840

    3 Stand fan 2 140 280

    4 Exhaust 3 40 120

    5 Wall fan 1 40 40

    6 CFL 9 20 180

    7 AC 1 2000 2000

    8 Metal hailde 3 400 1200

    9 3 phase UPS 1 10 KVA 8000

    10 Motor 1 2 HP 1500

    11 Refrigerator 1 180 180

    12 Oven 1 3 HP 225013 3 phase motor 1 3 HP 22500

    14 3 phase cube tester 1 3 HP 2250

    Total power consumed : 22.1 KW

    D.G required for = 15.47 KW (assuming 80% of load at a time)

    53

  • 7/27/2019 Training Project Complete

    54/64

    Use 50 KVA DG (avoiding 25 KVA by being on safer side in case of full load)

    50 KVA DG

    Capacity= 80% of 50 KW= 40 KW

    Can be used for= 80% of 40 KW= 32 KW

    D.G capacity

    Hire charge= 14000/month (current charge)

    Maintenance= 2000/month

    Fuel= 1800 litre/month

    Mobil= 0.1 litre/hr

    15 18 litre/hr

    Total cost= 1800x40.6 + 15x176 + 14000 + 2000 = 91720

    Rate= ( 91720/(12x30x30)) = 8.49 KW /unit/day

    TOWER CRANE:

    Tower cranes are very important machines in highrise building project. Tower crane

    can not be operated without electricity, so although it is a mechanical machine but also anelectrical machine which is supervised by both dept mechanical and electrical. The detailtechnical specifications are listed below.

    MOTOR POWER : Rated power - 91.5 KW

    Working power - 84.4 KW

    SUPPLY CAPACITY : 125 KVA

    SUPPLY VOLTAGE : 415 V

    SUPPLY FREQUENCY : 50 Hz

    54

  • 7/27/2019 Training Project Complete

    55/64

    TOWER CRANE

    Various limit switches in a tower crane:

    All the limit switches are provided in a tower crane to avoid any type of accident. When the

    operator is absent minded then these limit switches protect the machines and avoid all type of

    accident by cut the electrical circuit.

    Over load limit switch :

    This limit switch works when we lift a weight more than the permissible limit of the crane.When a weight more than the given limit is lifted by the crane then this limit switchautomatically cut the electrical circuit and so the no accident can take place.

    Movement limit switch:This limit switch is used in a tower crane to limit the swing movement of the tower boom from

    a permissible limit.

    Hoist limit switch:

    This limit switch is provided in a tower crane to control the vertical

    movement of weight lifted when it is moved in upward or downwarddirection.

    Hoisting height(m)

    Fall Travelling Attached

    a=2 56 205

    a=4 56 103

    Hoisting capacity max.(t) 10 ton

    Radius (m) Radius max 65

    55

  • 7/27/2019 Training Project Complete

    56/64

    Radius min. 2.5

    Hoisting

    Fall Twin motor type

    a=2 Hoisting capacity(t) 5 2.5

    Speed(m/min) 9~55 9~110

    a=4 Hoisting capacity(t) 10 55

    Speed(m/min) 4.5~27.5 4.5~55Power (kW) 230/30/7.5

    Slewing mechanism

    Drive mode 1

    (fixed frequency)

    Clogged torque (Nm) 27.5

    Speed (r/min) 0.6

    Drive mode 2 (variable

    frequency)

    Clogged torque (Nm) 2x7.5

    Speed (r/min) 0~0.8

    Trolley travel mechanism Power (kW) 5.5/3/1.1

    Speed(m/min) 52/26/8.5

    Travelling mechanism Speed(m/min) 23.52Power (kW) 2x7.5

    Climbing mechanism

    Speed(m/min) 0.54

    Power (kW) 11

    Hydraulic system pressure

    (Mpa)

    30

    Counter weight Jib length (m) 47.5 52.5 60 65

    Mass (t) 19 20.6 25.63 27.53

    Total power (kW) 91.5 (not including hydraulic pump station motor)

    Wheel X axle gauge(m) 6x6

    Operating temperature -20 C~+40C

    Hoisting performance table for QTZ160F(JL6516) tower crane:

    R 2.5-15 17 19 21 23 25 27 29 m

    a=4 10 8.66 7.61 6.78 6.09 5.51 5.03 4.61 ton

    a=2 5 4.66 ton

    R 31 35 37 39 41 43 45 47 m

    a=4 4.25 3.65 3.4 3.18 2.98 2.8 2.63 2.48 ton

    a=2 4.30 3.70 3.45 3.23 3.03 2.85 2.68 2.53 ton

    R 49 51 53 55 58 60 63 65 m

    a=4 2.35 2.22 2.10 1.99 1.84 1.75 1.63 1.55 ton

    a=2 2.40 2.27 2.15 2.04 1.89 1.80 1.68 1.60 ton

    56

  • 7/27/2019 Training Project Complete

    57/64

    MECHANICAL DEPARTMENTMECHANICAL DEPARTMENT

    MECHANICAL ASPECT OF THE PROJECT:

    As mechanical mechineries are must needed component of any construction project so

    Simplex gives a lots of importance on mechanical dept and has developed a good mechanical

    dept with efficient mechanical personnel for BUUIPL,Rajarhat site to maintain wholemechanical mechineries , lab instruments etc which are essentially needed for completion our

    job within the given time period according our planning.

    VARIOUS TYPES OF MECHANICAL MACHINES:

    There are so many machines which are essentially needed for civil engineering projects.

    Here we concern about those machines which are effectively used for high rise buildingprojects. Simplex has some own machines for high rise building projects. Again Simplex have

    to hire some machines from other agencies. Some such machines are listed below.

    Tower crane

    Vibrator

    Passenger hoist / Building hoist

    Builder hoist

    Jumbo drain pump

    Submersible pump

    Back hoe loader

    Tipper( Hyva)

    Diesel generator

    TOWER CRANE:

    Tower crane is one of the most useful machine which is very much essential for high

    rise building construction specially for lifting heavy material in vertical direction as well as inhorizontal direction.

    Typical details of a tower crane which is used in our project:

    Make : Jianglu

    Model : QTZ160 (JL6516)Capacity : 10 ton

    Boom length : 65 m

    Height of base mast : 4 m

    57

  • 7/27/2019 Training Project Complete

    58/64

    Height of general mast : 3 m

    Height of swing mast : 1.4 m

    Counter weight : 27530 kg

    3800 kg

    65 m

    27530 kg

    INSTALLATION OF FIXED BASE SECTION:

    Capacity plates / base plates, which are made of iron , are fixed on the pile cap by the nut

    extending from the pile cap and then the fixed base section is bolted on the base plate by the

    embedded anchor bolt.

    58

    3800 kg

    3800 kg

    3800 kg3800 kg

    3500 kg

    3130 kg

    1900 kg

  • 7/27/2019 Training Project Complete

    59/64

    BASE SECTION

    INSTALLATION OF THE UNDERCARRIAGE:

    First assemble the undercarriage and the cross-beam and then sling them on the concretefoundation , then fix and align them using clamp plates and M30 nuts.

    HOISTING AND ASSEMBLING COUNTERWEIGHT BLOCKS:

    First we calculate the weight of counterweight blocks according to the jib length,

    sling the counterweight blocks on the counter-jib using a mobile crane.

    Collocate the counterweight blocks according to the jib length.

    59

  • 7/27/2019 Training Project Complete

    60/64

    AFTER INSTALLATION

    VIBRATOR:

    Efficiency : 80%Frequency : 50HZ

    RPM : 2830

    Power : 2hp

    There are two types of needle that is used for the vibrator

    40mm : used for compaction for casting of beam and slab 60mm : used for compaction for casting of columns.

    Needle consist of a hollow tube fitted with end cap by threading

    A solid shaft is inserted inside the hollow tube

    The solid shaft is not completely made up of iron rod but inside the rod oil is filled

    Oil is used to reduce the weight as well as work as coolant

    A hexagonal sap is there to connect the shaft of motor to the shaft of vibratos.

    PUMP :

    If the water pump bode is connected to the fry wheel of the generator then the whole setup

    works as water pump.On our project site single cylinder and double cylinder 4 stroke pumps are available.

    Single cylinder pump : 5KVA

    Double cylinder pump : 10KVAPiston diameter : 50mm

    60

  • 7/27/2019 Training Project Complete

    61/64

    JUMBO DRAIN PUMP:

    Jumbo drain pump is used to pump water (specially muddy water) from the foundation.

    HYBA (TIPPER):

    For material transportation simplex has arranged a tipper of 10 cu m capacity for the BUUIPL,

    Rajarhat site for full time of the working period.

    TIPPER

    BAR CUTTING MACHINE:

    Bar cutting machine mechanical unit with foot and hand operated.

    Machine cutting capacity 8 mm to 42 mm

    Bar cutting machine are ideally suitable for large production

    .

    BAR BENDING MACHINE:

    61

    DIAMETER OF BARS NO. OF BARS TO BE CUT8 8

    10 6

    12 4

    16 2

    20 1

    25 1

    32 1

  • 7/27/2019 Training Project Complete

    62/64

    This machine has many advantages such as stable performance, fully automatic bending, manual

    button and highly safe. It is perfect equipment bending the small diameter steel and also an

    important complementary equipment of medium and large steel bar benders.

    EARTH COMPACTOR

    POWER : 3.68 KW ( 5 hp)

    RPM : 3600

    FULE : A CLASS

    VACUUME DEWATERING PUMP

    POWER : 7.5 hp

    PHASE : 3 Phase

    VOLTAGE : 440 volt

    FREQUENCY ; 50 HZ

    MAN HOIST

    On our project site there are two types of man hoist are being used:

    Potential and Mekaster

    SPECIFICATIONS POTENTIAL MEKASTER

    Power 111 KW 18.4 KW

    Speed 2 (gear1 and gear2) 1

    Capacity 4 1

    STORESTORE

    The store consists of various materials of various sizes and prices. All these items could not be

    acknowledged by human brain itself. Thus a systematic process has been made so as to make all

    the works of store easy and handy. This system is known as E.R.P (Enterprise Resource

    Planning).

    E.R.P consists of following systems:

    Master Purchase Order

    Inventory

    MASTER:

    Item master viewSite asset view

    Supplier master

    62

  • 7/27/2019 Training Project Complete

    63/64

    Hired plant & machinery master

    PURCHASE:

    Indent (forwarding) Request for quotation Quotation Purchase order (P.O.)

    Inventory Inspection Inspection number Goods receipt note (G.R.N) Goods issuenote (G.I.N)

    HIRING PURPOSE:

    Requisition for hiring requirement Order for hiring equipment Log sheet Billing

    Indent (cash) Inventory Cash goods receipt note Goods issue note

    UTILITY OF THE TRAINING PROGRAMME

    The application of the theoretical aspects that were taught in the

    classrooms to the practical problems faced at the constructionsite.

    An idea about the actual nature of work in the field was

    acquired.

    Important lessons on management of human resources werelearnt.

    63

  • 7/27/2019 Training Project Complete

    64/64

    Familiarization with the field conditions.

    Procedure of planning the day-to-day as well as the monthly and

    overall work.

    The process of preparing daily, monthly and quarterly reports

    was observed.

    The systematic nature of the work in the site was properly

    studied.

    I am grateful to SIMPLEX INFRASTRUCTURES LTD for providing me this goldenopportunity because now I am returning back with a huge pile of knowledge.

    I trust with my strongest confidence that what I learned in this training period will

    benefit me in future.