Upload
sonugarg4u
View
17
Download
1
Embed Size (px)
Citation preview
1
INTRODUCTION Due to high rate of increasing population day by day, widening gap between
power demand and its availability was one the basic reason for envisaging the G.N.D.T.P.
for the state of Punjab. The other factors favoring the installation of the thermal power
station were low initial cost and comparatively less gestation period as compared to hydro
electric generating stations. The foundation stone of G.N.D.T.P. at bathinda was laid on 19th
November 1969, the auspicious occasion of 500th
birth anniversary of great Guru Nanak Dev
Ji.
The historic town of bathinda was selected for this first and prestigious thermal
project of the state due to its good railway connections for fast transportations of coal,
availability of canal water and proximity to load center.
The total installed capacity of the power station 440MW with four units of 110MW
each. The first unit of the plant was commissioned in September, 1974. Subsequently second,
third and fourth units started generation in September 1975, March 1978, January 1979
respectively. The power available from this plant gives spin to the wheels of industry and
agricultural pumping sets.
Guru Nanak Dev Thermal Power Plant is a coal-based plant. The requirement of coal
for four units based on specific fuel consumption of 0.60 kg / kwh . The conveying and
crushing system will have the same capacity as that of the unloading system. The coal comes
in as large pieces. This coal is fed to primary crushers, which reduce the size of coal pieces
from 400mm to 150mm. Then the coal is sent to secondary crusher through forward
conveyors where it is crushed from 150mm to 200mm as required at the mills. Then the coal
is sent to boilers with the help of primary fans. The coal is burnt in the boiler. Boiler includes
the pipes carrying water through them; heat produced from the combustion of coal is used to
convert water in pipes into stThis steam generated used to run the turbine.
The basic requirements are:-
♣ Fuel (coal)
♣ Boiler
♣ Steam turbine
♣ Generator
♣ Ash handling system
2
Thermodynamics is the main subject of Thermal Engineering. It deals with the
behavior of gases and vapors, when they are subjected to varying temperatures and pressure.
In a thermal power plant, heat energy of the steam is converted to mechanical energy of the
turbine, which is further converted to electrical energy with the help of a generator. The
simple circuit of thermal plant can be drawn as below:-
\
Fig 2.1
Some of the definitions dealing with the thermodynamics are as below:-
GAS:- A gas is the name given to the state of any substance of which the evaporation from
the liquid state is complete. For example Hydrogen, Oxygen and air etc.
VAPOUR:-A vapor may be defined as a partially evaporated liquid and consists of the pure
gas state along with particles of liquid in suspension. It does not behave in the same way as
the gas, as the substance is further liable to the evaporation. The laws of gases do not apply
to vapors. When a vapor becomes completely evaporated, it is said to be dry and any further
heating of a dry vapor is termed as super heating. Once a vapor is superheated it is approx.
behaves as a gas.
HEATING OF A GAS:- A gas may be heated while either its volume is kept constant or its
pressure is kept constant, when the volume is kept constant, the temperature, pressure will
increase as the heat is supplied to a gas. But there will be no work done by the gas as there is
no change in volume. But when the gas is heated at constant pressure then the volume
increases and some work is done by the gas in expanding.
BASICS OF THERMAL
POWER PLANT
3
Work = pressure x change in volume
INTERNAL ENERGY OF GAS:- The internal energy of a gas is the heat energy stored in
the gas. It is quantity of heat. If the quantity of steam is applied to a gas, the temperature of
gas may increase or its volume may increase thus doing external work or it may do both, the
result will depend upon certain set of conditions under which heat is supplied to gas. If this
heating is accompanied by a rise of temperature, the gas will increase its internal energy.
This means that some of the heat supplied has been stored in gas in the form of heat energy.
Thus producing the rise of temperature the gas will have increased its internal energy. This
means that some of the heat supplied has been stored in the form of heat energy, remaining is
given out by gas as the form of external work as gas increased its volume. The increase in
heat energy stored in the gas due to rise of temperature is called the increase of internal
energy.
LAW OF CONSERVATION OF ENERGY:-
Total heat supplied to a gas must be equal to the increase of internal energy plus any
external work done by the gas in expanding.
H = total heat supplied to gas
E = increase in internal energy
W = external work done by gas
Then H = W + E
ISOTHERMAL EXPANSION:- Heat can be supplied to a gas keeping its temperature
constant. In this case the gas will expand doing external work equal to the amount of heat
supplied. This type of expansion is called Isothermal Expansion.
ADIABATIC EXPANSION:- When a gas expands, doing external work in such a manner
that no heat is supplied or rejected during the expansion. Such an expansion is called
adiabatic expansion.
ENTHALPY :-The total heat of substance is known as its enthalpy.
BASIC TYPE OF STEAM POWER PLANT :- The conversion of heat energy of organic
or nuclear fuel into mechanical energy with the aid of steam is carried out in steam power
plant. A diagrammatic view of the simplest steam power plant is shown on next page :-
4
Fig 2.2
The initial state of the working body is assumed to be water, which at a certain
temperature is compressed by the pump BFP and is fed into boiler ‘B’ through economizer
‘E’. In the Boiler water is heated at constant pressure process (4-5), to its Boiling point.
When the vaporization takes place in the same boiler process (5-6), since dry saturated steam
is rarely used in power plants, it is superheated to the required temperature in superheated
state.
The steam which is superheated through a pipe flows to steam turbine ‘T’. Where it
undergoes adiabatic expansion producing some external work (process 1-2). To have the
steam produce more work, its pressure at the turbine outlet must be as low as possible. For
this purpose steam from turbine is exhausted to a special apparatus condenser ‘C’, in which
the pressure of below atmosphere (vacuum) is created. In the condenser latent heat of
vaporization is removed from the steam with the aid of cooling water and the steam
condenses into liquid (the process of condensation 2-3) at a constant pressure and
temperature. Then this cycle is reheated. The basic cycle of the steam power plant
considered above is called the Rankine cycle.
ηR = H1 – H2
H1 – Hw
where
ηR = Rankine efficiency
H1 = enthalpy of steam at turbine inlet
H2 = enthalpy of steam at turbine outlet
Hw = enthalpy of condensate
5
METHODS OF INCREASING EFFICIENCY:-
Raising the initial steam pressure:- By increasing the initial pressure at turbine inlet, the
enthalpy drop (H1 –H2) can be increased. Thereby increase in thermal efficiency of Rankine
cycle. However it must be mentioned that an increase in the initial steam pressure results in
increase in the wetness of the steam at the end of expansion. The drops of liquid of steam can
appearing in the steam at the last stage of the turbine cause erosion of blades and reduce
overall efficiency of turbine.
In order to avoid this increase in steam wetness above the tolerated value, an increased
temperature of the superheated steam as well as reheating may be employed.
REHEATING:-
Fig2.3
Reheating:- Reheating consists of subjecting steam to repeated super heating, after it
has expanded in the first cylinder of the turbine, at originally constant pressure in the
reheaters to original temperature, then the steam is directed into the second cylinder of the
turbine T2, where the steam expands and goes to the condenser. Reheating increases dryness
fraction of steam. It also results in the thermal efficiency of the cycle.
Raising the temperature of superheating:- By raising the temperature of superheated
steam at constant pressure, the heat drop (H1-H2) increases. As a result efficiency increases.
Increasing the temperature of superheated steam also increases the dryness factor. In modern
6
steam power plants the temperature of superheating is limited. By the heat resistant
properties of the metal used.
Increasing the vacuum at condenser or reducing pressure at final:- A reduction in the
final pressure increases the heat drop (H1-H2) which results in the increase in the thermal
efficiency of the cycle.
Regenerative feed heat cycle:- In this system, the steam is fed from the turbine at certain
points during its expansion and is utilized for preheating the feed water supplied to the boiler.
At certain sections of turbine a small quantity of wet steam is drawn from the turbine. This
steam is circulated around the feed water pipe leading from the hot well to boiler. The
relatively cold water causes this steam to condensate. The heat thus lost by the steam being is
transferred to the feed water; the condensed steam then drains into the hot well.
The net effect of this process is to supply the boiler with hotter water while a small
amount of work is lost by the turbine. There is a slight increase in efficiency due to this
process, but there efficiency depends upon following factors:-
� Steam pressure
� Degree of superheat in steam
� Reheat/nonreheat
� Vacuum in condenser
� Regenerative/ non regenerative cycle
7
PROJECT AREA:-
Power plant 238 acres
Ash disposal 845
Lake 180
Residential colony 285
Marshalling yard 256
Total area 1804
TOTAL COST: - Rs. 115 crores
STATION CAPACITY: - four units of 110MW.each
BOILER:-
Manufacturers B.H.E.L
Maximum continuous rating (M.C.R.) 375T/hr.
Superheater outlet pressure 139kg/cm²
Reheater outlet pressure 33.8 kg/cm²
Final superheater/reheater temperature 540°C
Feed water temperature 240°C
Efficiency 86%
Coal consumption per day per unit 1400 tones (Approximate)
STEAM TURBINE:-
Manufacturers B.H.E.L.
Rated output 110MW.
Rated speed 3000 r.p.m.
Number of cylinders three
Rated pressure 130kg/ cm²
Rated temperature 535°C
Condenser vacuum 0.9 kg/cm²
GENERATOR:-
Manufacturers B.H.E.L.
PLANT SALIENT
FEATURES
THE PLANT
8
Rated output (Unit- 1 & 2) 125000KV
(Unit -3 & 4)137000KVa
Generator voltage 11000 volts
Rated phase current (unit –1 & 2) 6560 Amps.
(unit –3 & 4) 7220 Amp
Generator cooling hydrogen
BOILER FEED PUMPS
Number per unit two of 100% duty each
Type centrifugal
Rated discharge 445 T/hr.
Discharge head 1960 MWC .
Speed 4500 r.p.m.
CIRCULATING WATER PUMPS:-
Numbers for two units five of 50% duty each
Type mixed flow
Discharge head 24 MWC.
COOLING TOWERS:-
Numbers four
Water cooled 18000 T/hr.
Cooling range 10°C
Height 120/12 1metres
COAL PULVERISING MILLS:-
Numbers three per unit
Type drum-ball
Rated output 27 T/hr.
Coal bunkers 16 per unit
9
RATING OF 6.6 KV AUXILLIARY MOTORS:-
Coal mill 630 KW
Vapour fan 320 KW
C.W. Fan 800/746 KW
Coal crusher 520 KW
Primary air fan 320 KW
Forced draught fan 320 KW
Boiler feed pump 3500 KW
10
Coal received from collieries in the rail wagon is mechanically unloaded by
Wagon Tippler and carried by belt Conveyor System Boiler Raw Coal Bunkers after
crushing in the coal crusher. The crushed coal when not required for Raw Coal Bunker is
carried to the coal storage area through belt conveyor. The raw coal feeder regulates the
quantity of coal from coal bunker to the coal mill, where the coal is pulverized to a fine
powder. The pulverized coal is then sucked by the vapour fan and finally stored in
pulverized coal bunkers. The pulverized coal is then pushed to boiler furnace with the help
of hot air steam supplied by primary air fan. The coal being in pulverized state gets burnt
immediately in the boiler furnace, which is comprised of water tube wall all around through
which water circulates. The water gets converted into steam by heat released by the
combustion of fuel in the furnace. The air required for the combustion if coal is supplied by
forced draught fan. This air is however heated by the outgoing flue gases in the air heaters
before entering the furnace.
The products of combustion in the furnace are the flue gases and the ash. About 20%
of the ash falls in the bottom ash hopper of the boiler and is periodically removed
mechanically. The remaining ash carried by the flue gases, is separated in the electrostatic
precipitators and further disposed off in the ash damping area. The cleaner flue gases are let
off to atmosphere through the chimney by induced draught fan.
The chemically treated water running through the water walls of boiler furnace gets
evaporated at high temperature into steam by absorption of furnace heat. The steam is further
heated in the super heater. The dry steam at high temperature is then led to the turbine
comprising of three cylinders. The thermal energy of this steam is utilized in turbine for
rotating its shaft at high speed. The steam discharged from high pressure (H.P.) turbine is
returned to boiler reheater for heating it once again before passing it into the medium
pressure (M.P.) turbine. The steam is then let to the coupled to turbine shaft is the rotor of
the generator, which produces electricity. The power pumped into power grid system
through the generator transformer by stepping up the voltage.
WORKING OF
THERMAL PLANT
11
Fig4.3
12
The steam after doing the useful work in turbine is condensed to water in the
condenser for recycling in the boiler. The water is pumped to deaerator from the condenser
by the condensate extraction pumps after being heated in the low pressure heater (L.P.H)
from the deaerator, a hot water storage tank. The boiler feed pump discharge feed water to
boiler at the economizer by the hot flue gases leaving the boiler, before entering the boiler
drum to which the water walls and super heater of boiler are connected.
The condenser is having a large number of brass tubes through which the cold water
is circulated continuously for condensing the steam passing out sides the surface of the brass
tubes, which has discharged down by circulating it through the cooling tower shell. The
natural draught of cold air is created in the cooling tower, cools the water fall in the sump
and is then recirculated by circulating water pumps to the condenser.
GENERAL LAYOUT OF THERMAL POWER PLANT
The general layout mainly consists of four circuits:-
1) Coal and ash circuit.
2) Air and gas circuit.
3) Feed water and steam flow circuit.
4) Cooling water circuit.
Thermal power plant using steam as working fluid basically works upon the principle
of Rankine cycle. Steam is generated from water in boiler, expanded in prime mover and
then condensed in condenser and again fed into the boiler.
1) Coal and Ash circuit: - In this circuit the coal from storage is fed to boiler through coal
handling equipment for generation of steam. Ash produced due to combustion of coal is
removed to ash storage through ash handling system. Coal fed to boiler is first dried by
hot air to remove moisture and to increase the combustion rate.
2) Air and gas circuit: - Air is supplied to the combustion chamber of the boiler either
through induced draught fan or forced draught fan or both. The dust is removed from air
through filters before supplying to the combustion chamber. The exhaust gases carrying
13
sufficient amount of heat and ash are passed through air pre-heater , where exhaust heat
of gas is removed before exhausting the gases to atmosphere through chimney.
3) Feed water and steam circuit: - The steam generated in boiler is fed to steam prime
mover to convert heat of steam into mechanical work. This steam coming out of prime
mover is condensed and then fed to boiler with the help of a pump. The condensate is
heated in feed heaters using steam trapped from different points of turbine.
Some of the steam and water is lost passing through different components of
system. Therefore feed water is supplied from external source to compensate this loss.
The feed water supplied from external source to compensate this loss. The feed water
supplied from external source is passed through purifying plant to reduce the dissolved
salts to an acceptable level. This purification is necessary to avoid the sealing of the
boiler tubes.
4) Cooling water circuit: - The quantity of cooling water required to condense
the steam is considerably large and this steam i.e. condensed steam is fed to boiler. The
cooling water is taken from canal.
The different types of systems and components, which are used in thermal power
plant are listed below :-
a) Coal handling system
b) Ash and dust handling system
c) Draught
d) High pressure boiler
e) Prime mover
f) Condenser and cooling water
g) Compressors
h) Feed water purification plant
i) Different components used as economizer, superheater, feed heater etc. to
increase the thermal efficiency of the plant.
14
BOILER FEED PUMP:-
As the heart is to human body, so is the boiler feed pump to the steam power plant. It is
used for recycling feed water into the boiler at a high pressure for reconversion into steam.
Two nos. 100% duty, barrel design, horizontal, centrifugal multistage feed pumps with
hydraulic coupling are provided for each unit. This is the largest auxiliary of the power plant
driven by 3500 KW electric motor.
The capacity of each boiler at GURU NANAK DEV THERMAL PLANT is 375
tones/hr. The pump which supplies feed water to the boiler is named as boiler feed pump.
This is the largest auxiliary in the unit with 100% capacity which takes suction of feed water
from feed water tank and supplies to the boiler drum after preheating the same in HP-1, HP-2
and economizer. The delivery capacity of each boiler feed pump is 445 tones/hr. to meet
better requirements corresponding to the various loads, to control steam temperature, boiler
make up water etc. The detailed particulars checking of protections and inter locks, starting
permission etc. are as below:-
Particulars of BFP and its main motor:-
� BOILER FEED PUMP: - The 110 MW turboset is provided with two boiler feed
pumps, each of 100% of total quantity. It is of barrel design and is of horizontal
arrangement, driven by an electric motor through a hydraulic coupling.
Type 200 KHI
No. of stages 6
Delivery capacity 445 t/hr.
Feed water temperature 158°C
Speed 4500 rpm
Pressure at suction 8.30 kg/cm²
Stuffing box mechanical seal
Lubrication of pump by oil under pressure And motor bearing
supplied by hydraulic coupling
Consumption of cooling water 230 L/min.
WATER TREATMENT PLANT:-
The water before it can be used in the boiler has to be chemically treated, since untreated
water results in scale formation in the boiler tubes especially at high pressure and
GENERAL
DESCRIPTION
15
temperatures. The water is demineralised by Ion Exchange Process. The water treatment
plant has production capacity of 1800 Tones per day for meeting the make-up water
requirement of the power station.
COAL MILL:-
Coal Mill pulverizes the raw coal into a fine powder before it is burnt in the boiler furnace.
The pulverizing of coal is achieved with the impact of falling steel balls, weighing 52.5
tonnes, contained in the mill drum rotating at a slow speed of 17.5 r.p.m. The raw coal is
dried, before pulverizing, with inert hot flue gases tapped from the boiler. Three coal mills
each with a pulverizing capacity of 27 T/hr. are provided for one unit.
INDUCED DRAUGHT FAN:-
Two nos. axial flow Induced Draught Fans are provided for each unit to exhaust ash laden
flue gases from boiler furnace through dust extraction equipment and to chimney. The fan is
driven by an electric motor through a flexible coupling and is equipped with remote
controlled regulating vanes to balance draught conditions in the furnace. The fan is designed
to handle hot flue gases with a small percentage of abrasive particles in suspension.
CONTROL ROOM:-
The control room is the operational nerve center of the power plant. The performance of all
the equipments of the plant is constantly monitored here with the help of sophisticated
instrumentation and controllers. Any adverse deviation in the parameters of various systems
is immediately indicated by visual and audio warning and suitable corrective action is taken,
accordingly. The control room is air conditioned to maintain the desired temperature for
proper functioning of the instruments.
SWITCH YARD:-
Electricity generated at 11 KV by the turbo-set is stepped-up by unit transformers to 132/220
KV for further transmission through high tension lines to Maur, Muktsar, Malout, N.F.L.,
Sangrur and Ludhiana. Transmission of power to grid is controlled through 7 nos. 220 KV
16
and 15 nos. 132 KV. Air Blast Circuit Breakers along with their associated protective
systems.
WAGON TIPPLER:-
The coal received from the collieries, in more than 100 rail wagons a day, is unloaded
mechanically by two nos. wagon tipplers out of which one serves as a standby. Each loaded
wagon is emptied by tippling it in the underground coal hopper from where the coal is
carried by conveyor to the crusher house. Arrangements have been provided for weighing
each rail wagon before and after tippling. Each tippler is capable of unloading 6-8 rail
wagons of 55 tonnes capacity in an hour.
CRUSHER HOUSE:-
Coal unloaded by the wagon tippler is carried to crusher house through conveyors for
crushing. Two nos. hammer type coal crushers are provided, which can crush coal to a size
of 10 mm. The crushed coal is then supplied to Boiler Raw Coal Bunkers. The surplus coal is
carried to coal storage area by series of conveyors. Crushing of coal is an essential
requirement for its optimum pulverizing and safe storage.
COOLING TOWERS:-
Cooling Towers of the power plant are the land mark of the Bathinda City even for a far
distance of 8-10 kilometers. One cooling tower is provided for each unit for cooling 18000
tones of water per hour by 10°C. cooling towers are massive Ferro-concrete structure having
hyperbolic profile creating natural draught of air responsible for achieving the cooling effect.
Cooling tower is as high as 40 storey building.
BOILER:-
It is a single drum, balanced draught, natural circulation, reheat type, vertical combustion
chamber consists of seamless steel tubes on all its sides through which water circulates and is
converted into steam with the combustion of fuel. The temperature inside the furnace where
the fuel is burnt is of the order of 1500°C. The entire boiler structure is of 42meter height.
17
BOILER CHIMNEY:-
The flues from the boiler, after removal of ash in the precipitators, are let off to atmosphere
through boiler chimney, a tall Ferro-concrete structure standing as high as the historic Qutab
Minar. Four chimneys, one for each unit, are installed. The chimney is lined with fire bricks
for protection of ferro-concrete against hot flue gases. A protective coating of acid resistant
paint is applied outside on its top 10 meters.
CIRCULATING WATER PUMP:-
Two nos. of circulating water pumps provided for each unit, circulate water at the rate of
17200 T/hr. in a closed cycle comprising of Turbine Condenser and Cooling Tower. An
additional Circulating Water Pump provided serves by for two units. The water requirement
for bearing cooling of all the plant auxiliaries is also catered by these pumps.
18
TURBINE SECTION
Turbine
Turbine is a prime mover for the Generator in the power plant. In steam turbine, the potential
energy of steam is transformed into kinetic energy and later in its turn is transformed into the
mechanical energy of the rotation of the turbine shaft. The common types of turbines are:-
���� IMPULSE TURBINE:- In this type of turbine, steam expands in the nozzles
and its pressure does not alter as it moves over the blades.
� REACTION TURBINE:- In this type of turbine, the steam expands
continuously as it passes over the blades and thus there is a gradual fall in
pressure during expans
19
Fig 7.1
Different types ofsteam turbines are used in Thermal Power Plant but the ones which are
used at G.N.D.T.P. are categorized as follows:-
Sr. No. Type of Turbine Turbines at G.N.D.T.P.
1 Horizontal/Vertical Horizontal
2 Single/Multi-cylinder Multi-cylinder (3-cylinder)
3 Impulse/Reaction Impulse
4 Condensing/Non-condensing Condensing
5. Reheat/Non-reheat Reheat
6 Regenerative/Non- Regenerative With bypass (ST-1)
7 With bypass/Without bypass Without bypass (ST-2)
MAIN TECHNICAL DATA
a) The basic parameters:
Rated output measured at Terminal of the generator. 110.000KW
Economical output. 95.000KW
Rated speed. 3.000RPM
20
Rated temp. of stearn just before the stop valve. 535°C
Max Temp. of steam before the stop valve. 545°C
Rated pressure of steam before the MP casing. 31.63°C
Max. pressure of steam before the MP casing 35°C
Rated temp. of steam before the MP casing. 535°C
Max. temp. of steam before the MP casing. 545°C
b) System of turbine:
4 Governing valves +2 interceptor valves HP cylinder- 2 Row Curtis wheel +8 moving
wheels.
Wt. Of HP rotor approx. 5,500 Kg.
MP cylinder - 12 Moving wheels.
Wt. Of MP rotor. Approx. 11,000 Kg.
LP cylinder - 4 Moving wheels of double flow design.
Wt. Of MP rotor approx. 24,000 Kg.
Direction of the turbine rotation - To the right, when looking at the turbine from the front
bearing pedestal.
TURBINE ASSEMBLY WITH LOWER CASING
Fig 7.2
21
TURBINE ACCESSORIES AND AUXILIARIES:
The following are turbine accessories and auxiliaries:
1. Surface condensers.
2. Steam jet air ejector
3. LP and HP heaters.
4. Chimney steam condenser.
5. Gland stearn condenser.
6. Oil purifier of centrifuge.
7. Clean oil pumps with clean oil tank.
8. Dirty oil pumps with dirty oil tank.
9. Auxiliary oil pump with aux. Oil tank.
10. Starting oil pumps.
11. Emergency oil pumps (AC and DC).
12. Jacking oil pumping.
13. Bearing or turning gear.
1. SURFACE CONDENSERS
Two no. surface condensers are used for condensing the steam which has worked in
the turbine. The coolant for condensing the steam is circulating water, which is inside the
condenser brass tubes, and steam is outside.
TECHNICAL DATA OF EACH CONDENSER:
Cooling area 3330 m2
No. of brass tube 6000
Circulating water required for each condenser 7500T/Hr.
Circulating water required for both condense r2x7500T/Hr. 15000T/Hr.
Allowable difference between inlet & outlet C.W. water 10°C Temp.
Vacuum in the condenser 0.90 Kg/cm2
22
2. STEAM JET AIR EJECTORS
Starting ejector or hogger is used for quick evacuation of the turbo set during starting
whereas main steam jet air ejector (Duplex Type) is used to maintain the vacuum in the
condenser. Steam Jet Air Ejector works on the principle of venture with steam working
media to eject air from the condenser.
3. STEAM HEATERS
In regenerative system there is a stream of 5 LP heater, one desecrator and 2 HP
heaters. All LP and HP heaters are of surface type i.e. condensate of feed water is inside the
heaters tubes and steam extractions are outside the heater tubes in the heater shells. LP
heaters are of single flow type whereas HP heaters are of double flow type i.e. feed water is
flowing twice through the HP heaters in order to extract total HP latent heat and super heat
of steam going into HP heaters, desecrator is a contact type heater in which steam and
condensate come in direct contact with each other.
Details of Steam Extraction:
Steam into HP heater NO. 2 is from cold reheat line.
Steam into HP heater NO.1 is from MP turbine, LPH- 4 LPH- 5 is from MP casing at
differently steam pressures and temperatures.
4. CHIMNEY STEAM AND GLAND STEAM CONDENSERS
There are the additional two heater stages provided in the regeneration system of the
turbine for heating the condensate flowing through it. Steam leak offs from the turbine a
gland is used for heating the condensate in these heaters.
5. STARTING OIL PUMPS AND ARRING GEAR
S.O.P supply necessary turbine oil during starting of the turbine and up to turbine
speed of 2930 RPM till the main oil pump mounted on the turbine rotor at the HP extension.
takes manually in order to provide lub. Oil for turbo set.
Emergency pumps (AC & DC) are meant to start on auto when turbine trips and lub.
Oil pressure falls in order to provide lubrication of turbine and generator bearings.
23
6. JACKING OIL PUMP AND ARRING GEAR
Jacking oil pump is used in order to lift the turbine rotor before it is put on barring
gear jacking oil pump takes suction from the turbine lub. Oil system and provide a thin film
of oil for lifting the rotor. Barring gear motor used to rotate the turbine rotor at 62 RPM after
engaging the rotor with the gear during starting and stopping of the turbine.
7. CIRCULATING WATER PUMPS
Two nos. circulating water pumps provide for each unit circulate water @17200
tonnes per hour in a closer cycle comprising of turbine condenser and cooling tower. An
additional circulating water pump provide, serves as a stand by for two units. The water
requirement for bearingcooling of all plant auxiliaries is also catered by these pumps.
(II) STEAM JET AIR EJECTOR
Starting ejector is used for quick evacuation of the turbo set during starting whereas main
steam jet air ejector is used to maintain Vacuum in the condenser. It works on the principle
of ‘VENTURI’ with steam working media to eject air from the condenser.
(III) LP AND HP HEATERS
In regenerative system there is a steam of 5 LP heaters, one Deaereator, 2 HP heaters. All LP
and HP heaters are of surface type i.e. condensate or feed water is inside the heater tubes in
the heater shells. L.P. heaters are of single flow whereas HP heaters are of double flow type.
Deaereator is contact type heater in which steam and condensate come in direct contact.
(IV, V) CHIMNEY STEAM AND GLAND STEAM CODENSER: - There are additional
two heating stages provided in the regeneration system of the turbine for heating the
condense flowing through it steam leaks off from the turbine glands is used for heating the
condensate in these heaters.
(VI, VII, VIII, IX, X) VARIOUS OIL PUMPS
Centrifuge is an oil purifier used to remove moisture and other impurities from the turbine
oil. Maximum allowable moisture content in the turbine oil is 0.2%. In case the oil level of
24
the main oil tank is to be made up then either oil can transferred from clean oil tank to main
oil tank with centrifuge or from dirty oil tank to main oil tank with centrifuge.
(XI) STARTING OIL PUMPS AND EMERGENCY OIL PUMPS
Starting oil pumps supply the necessary turbine oil during starting of the turbine and upto
turbine speed of 2930 rpm till the main oil pump mounted on the turbine rotor at the HP
extension takes manually in order to provide lubrication oil for the turbo set. Emergency oil
pumps are meant to start on auto, when turbine trips and lubrication oil pressure falls in order
to provide lubrication to the turbine and generator bearings.
MAIN TECHNICAL DATA ABOUT TURBINE
a) The Basic Parameters
• Rated output measured at terminal of the generator. 110,000KW
• Economical output. 95,000KW
• Rated speed 3,000 RPM
• Rated temp. Of steam just before the stop valve. 535°C
• Max temp. Of steam before the stop valve 545°C
• Rated pressure of steam before the MP casing 31.63 atm
• Max. Pressure of steam before the MP casing 35 atm
• Rated temp. Of steam before the MP casing 535°C
• Max. Temp. of steam before the MP casing 545°C
•
(a) System of turbine:
Governing valves 2 interceptor valves
HP cylinder 2 Row Curtis wheel +8 moving wheels.
Wt. of HP rotor is approx. 5,5000kg.
MP cylinder 12 moving wheels.
Wt. Of MP rotor is approx. 11,000kg
LP cylinder 4 Moving wheels of double flow design.
Wt. of MP rotor is approx. 24,000.
Direction of the
25
FUNCTION AND TYPES OF STEAM TURBINE
FUNCTION OF STEAM TURBINE
Steam turbine is a from of heat engine in which the available heat energy in from of
steam is converted into kinetic energy, to rotate the turbine rotor, by expansion of steam in a
suitable shaped nozzle, the pressure on the blades causing rotary motion is purely dynamical
and is due solely to the change of momentum of the steam jet during its passage through
these blades.
TYPES OF STEAM TURBINE
The steam turbines are broadly classified into three groups depending on the
conditions of operations of the steam on the rotor blades.
1) Impulse Type
This is again subdivided into:-
a) Simple Impulse
b) Compound Impulse
(Pressure, Velocity and Pressure & Velocity compounded)
c) Combined Impulse
2) Reaction Type
This is again grouped into:-
a) Axial Flow
b) Radial flow
c) Mixed flow
3) Impulse reaction Type
Fig 7.3
26
IMPULSE TURBINES
In an impulse turbine the potential energy in the steam due to pressure and superheat is
converted into kinetic energy in the form of weight and velocity by expanding it in suitably
shaped nozzles. The whole of the expansion takes place in the fixed nozzles. The steam
pressure at the inlet and outlet edges of the rotor blades are equal as there is no expansion in
the rotor bicycles. The steam impinges on the wheel I blades causing the wheels to rotate.
The expansion is carried out in stages referred to as “Pressure, Stages the commonest type of
impulse turbine is the Delaval turbine.
REACTION TURBINE
In the type of turbines the steam expands in both the stationary and moving blades.
So, the steam pressure, at inlet to the moving blades is greater than the exit pressure. The
term” reactions” is strictly not correct as no turbine practice works on pure reaction principle.
The action on the balding is both impulse an “reaction”.
The steam turbine installed is a 3 cylinder,(HP , IP and LP r condensing, reheat cycle
type with 8 non~regulated extractions for regenerative heating pf the boiler feed water. The
cross section through a typical 110 MV steam turbine.
The high-pressure turbine is made of two horizontally split concentric casings. The
inner casing is placed inside the, outer casing so as to permit the expansion of the casing at
all directions. The main steam from the boiler is admitted into the HP turbine through t-{O
quick clashing~) t09 valves.(HPQCV)and four nos of Governing va1VBs. These v81ves are
operated hydraulically and they operate on increase / decrease of secondary oil pressure. In
the HP turbine, steam expands in a two row Curtis stage called the impulse stage and further
in 8 stages of fixed and moving blades” Labyrinth type seals are provided for the HP turbine
at both front and II rear ends and CRH steam or 11 at PRDS steam is used for sealing glands.
The medium pressure part of the turbine is a horizontally divided casing. The guide
wheels are partly mounted in the casing in carriers and directly in the casing. The steam after
HP turbine enters the reheater, gets heated to 540°C and returns to the MP, turbine through
27
MPOCSV and interceptor valves steam entering the MP part flow through 12 fixed and
moving blades and taken to the low pressure turbine through the two corrosive pipes.
The MPQCSV and IVs are also operated Hydraulically.
MEDIUM PRESSURE TURBINE
Fig 7.4
The low pressure turbine is split horizontally into three parts and all the parts are connected
by vertical flanges. The extreme parts of the L.P. turbine are connected rigidly with surface
condensers mounted on sturdy spring supports. The steam entering the L.P. casing flows in
both directions through 4 stages and finally exhausted into the condenser. The middle part of
the L.P. casing houses tube nests of first and second low pressure heaters for heating the
condensate.
The flanges of H.P., M.P. casings are designed to be heated by steam during the
starting up to turbine generator. By heating of the flanges, the differences in temperature
between the cylindrical portion of the casing, flanges and the connecting bolts are reduced
hence limiting the additional stresses on the bottles. The very important criteria for starting
and rate of loading the machine is the difference between the temperature of the steam
admitted in and that of the internals of the turbine. For the purpose of measuring the
temperature of the casing and the steam transfer piping there monopoles are provided at
appropriate points.
28
The turbine is the prime mover for the generator in the power plant Different types of steam
turbines used in thermal power plants, but the ones. Which are used at G.N.D.T. P. are
categorized as follows
S.No. Type of Turbine Turbine at GNDP at
1. Horizontal/vertical Horizontal
2 . Single/multi cylinder
Multicylinder
3. Condensing/non condensing condensing
4. Reheat/ non-reheat Reheat
5. Regenerative/non
regenerative
Regenerative
6. With by pas/without by pass with by pass (stage-1)
Without by pass (stage-2)
BASIC WORKING OF TURBINE
First of all the turbine is run on gear motor with the help of exciter. At that time
steam is kept on recirculating with the help of by pass valve. When the pressure of steam is
increased to on optimum level and turbine acquires a particular rpm then steam is introduced
in the H.P. (high-pressure) cylinder first. The temperature of steam at entrance is 540°C and
pressure is about 139 Kg/cm2. After doing its work on the H.P. Turbine, the steam is taken
out for reheating rated temperature of steam at reheater inlet is 360°C. The temperature of
steam is increased up to 535°C in the boiler shell and steam is again introduced in M.P
(Medium pressure) turbine. After M.P.turbine, the steam is passed on to L.P. (Low-pressure)
turbine. This process helps the turbine to reach the speed of 3000 rpm. After L.P. turbine, the
steam is condensed in condenser, build below the turbine unit. The condenser contains a
number of brass tubes through which cooling out from L.P. turbine it comes in contact with
colder brass tubes then steam get transformed into water. This water get collected in HOT
WELL just below the condenser. From here the hot water is again pumped with the help of
condensate pumps. The cooling water is used to condense steam gets heated up and is cooled
29
by falling from cooling tower. This completes the processing of steam through turbine and
condenser.
4. STEAM CYCLE
The design of the power cycle based on the modern concept, where a unit consists of a steam
generator with its independent firing system tied to the steam generation. The steam
generator is designed for maximum continuous rating of 375-tonnes/hr. and steam Pressure
of 139-kg/cm2 at temperature of 540°C respectively. The steam generator is designed to
supply to a single reheat type condensing steam turbine with a 8 non regulated extraction
points of steam for heading the condensate and feed water. The steam cycle can be classified
into the following three divisions: -
(a) Main steam
(b) Reheat steam
(c) extraction steam
(a) MAIN STEAM
Saturated steam from the steam generator drum is led to the super heater bank to heat if up to
540°C saturated steam from the drum is led to the ceiling super hearter (between SHH1 and
SHH2) from ceiling super steam goes to convection
30
Super heater (between SHH2 and SHH3) the first regulated infection for at temperature takes
place after convection super heater (between SHH9 and SHH10). Before entry to final super
heater the steam is again at temperature by regulated injection. The steam is coming out from
the final super heater normally at a pressure of 139 kg/cm2 at a temperature of 540
oC. This
steam is feed to the control valve. In each of the two live steam lines there is one turbine side
main steam stop valve and one high pressure quick closing valve along with two control
valves.
(b) EXTRACTION STEAM
Steam for heating of the condenser and the feed steam is extracted from 8 non regulated
extraction points from the turbine. Heating is carried out in five stages of L.P. heaters, one
deareating heater and in two H.P. heaters extraction 1, 2, 3, is taken from L.P. turbine.
Extraction 4, 5, 6 and 7 are taken from M.P. turbine. Extraction 8 is obtained from C.R.H.
line first and second stage of heating is done by two sets of twin low-pressure heaters
mounted directly in the L.P. casing of the turbine. Extraction 3, 4 and 5 are connected to the
deaereating heater placed above feed water storage tank 7th
and 8th
extraction steam is fed to
the vertical H.P. heaters respectively.
31
(C) REHEAT STEAM
Exit steam from the H.P. turbine is taken back to the reheater section of the steam generating
unit. Reheating is done in two stages both by flue gas and by super heated steam. The steam
to be reheated is first pass through the triple-heated exchanger, where super heated steam is
used as the heating media. The steam is finally reheated in final reheaters (RHH3) RHH4
and RHH5) suspended in the horizontal pass of the furnace. Reheat steam at a normal
pressure of 36.4 kg/cm2 at a temperature of 540°C respectively is fed to the M.P. cylinder by
two hot reheat steam pipes through strainers and combined stop and interceptor valves. In
each of the cold reheat steam lines from H.P. cylinder a non-return valve is operated by oil
pressure is provided.
5. Turbine Accessories and Auxiliaries
I. Surface condenser.
II. Steam jet air ejector
III. LP and HP heaters.
IV. Chimney steam condenser.
V. Gland steam condenser.
VI. Oil purifier or centrifuge.
VII. Clean oil pump with clean oil tank
VIII. Dirty oil pump with clean oil tank.
IX. Auxiliary oil pump with auxiliary oil tank
X. Starting oil pump.
XI. Emergency oil pump.
(I) SURFACE CONDENSER
Two surface condensers are used for condensing the steam which has worked in the turbine.
The coolant for condensing the steam is circulating water which is inside the condenser brass
tubes and steam is outside.
Technical data of Condenser
• Cooling Area 3300 msq.
• Number of brass tubes 6000
• Circulating water required 7500 tonnes/hr.
• Vacuum in the condenser 0.90 kg/cm sq.
32
Fig.7.5 surface condenser
HIGH PRESSURE TURBINE
INTRODUCTION
HP turbine or high-pressure turbine is a single flow turbine. The heated steam enters
from one side and expands in one direction before exhaust. The main steam lines to HP
turbine are shown in figure. The super heated steam flow from boiler enters the turbine in the
direction shown in figures. This line is known as HRH lines. The HP turbine has a throttle
control valve. Steams on expansion again go to boiler from the turbine via CRH line. The
properties of steam when it enters are as:
1. Pressure at inlet :142 Kg/cm2
2. Temperature at inlet :540 C
3. Conditions of steam :Superheated
DESIGN
HP turbine casing is designed as a barrel type casing without axial joint.
An axially split guide blade carriers is arranged in the barrel type casing. The barrel type
casing has neither an axial nor a radial flange. This prevents mass accumulation with high
thermal stresses. The almost perfect rotational symmetry permits moderate wall thickness of
nearly equal strength at all the sections. The inner casing is axially split and kinematically
33
supported. As the pressure difference across the wall of inner casing confines to below
horizontal flange and connection bolts can be kept small. Barrel type casing is preferred due
to following reasons:
� Rotational symmetry.
� Remain constant in shape and leak proof during quick change in temperature.
INNER CASING
The guide blade carrier is attached in the horizontal and
vertical plane in the barrel type casing so that it can freely expand rapidly in all direction and
axially from a fixed when heating up while maintaining concentricity relative to the turbine
rotor. On the admission side four projections of guide blades carrier and on the exhaust side
two projections fitted into corresponding grooves in the barrel type casing.
34
INTERMEDIATE PRESSURE TURBINE
INTRODUCTION The IP turbine is double flow type turbine. This turbine is after the HP
turbine. IP turbine has two inlets at center and four exhausts, two at each end. Similar to HP
turbine, IP turbine has moving as well as stationary blades. IP turbine has 20 stages. This is
also a reaction type turbine. Constructional features are as follows:
1. Pressure at inlet : 38 Kg/cm2
2. Temperature at inlet :345 C
DOUBLE SHELL CONSTRUCTION
The casing IP turbine is split horizontally and is of double shell construction. A
double flow inner casing is supported in outer casing. Steam from the HP turbine after
reheating enters the inner casing from above and below through two inlet nozzles flanged to
the mid section of the outer casing. This arrangement provides opposed double flow in the
two sections and compensates axial thrust. The center flow prevents the steam inlet
temperature form affecting the support brackets and bearing sections.
INLET AND EXTRACTION NOZZLES
The angle sealing ring forms the connection of the inlet and extraction nozzles
with the inner casing. One leg of the angle ring at such a connection bears against the back of
the collar of the threaded ring in the inner casing, while the other fits into an annular groove
in the inlet nozzle. The Threaded ring is fitted in such a way that the short leg of the angle
sealing ring can slide freely between the collar of the threaded ring and the inner casing. The
steam pressure prevailing on the inside forces the sealing ring against the face of the inner
casing. The tolerances of the annular grooves in the inlet nozzle (7) are dimensioned to allow
the long legs of the annular rings to slide in the groove. The angle rings are flexibly
expanded by the pressure on the inside and their outer areas forced against the annular
grooves to provide the desired sealing affect.While providing a light seal, this arrangement
35
permits the inner casing to move freely in all direction. The inlet nozzle and the extraction
nozzle are bolted to the outer casing.
IP TURBINE BLADING
The IP turbine blading consists of several drum stages. All the stages are reaction stages with
50%. The stationary and moving blade of the front stage is provided with T-root. Their cover
plates are machined in integral with the blades and provides a continues shroud after
insertion.
The moving and stationary are inserted into appropriately shaped grooves in the
shaft or inner casing and bottom caulked with caulking material. The insertion slot in the
shaft is closed by a locking blade which is either by taper pins or grub screws. Special end
blades which lock with the horizontal joint are used at the horizontal joints of the inner
casing. Grub screws which are inserted from the joint secure the stationary blades in the
grooves.
The rear stages have stationary with the hook type roots, which are secured in
annular grooves in the inner casing by filler pieces. The shrouds of these blades are riveted to
the blades in sections. The moving blades of these have design as those of the front stages.
Fig 7.6. Intermediate turbine
36
LOW PRESURE TURBINE
CONSTRUCTION
The LP turbine casing consists of a double flow unit and has a triple shell welded
casing. The outer casing consists of front and rear walls, the later longitudinal support being
and the upper part. The front and the rear walls, as well as the correction areas of the upper
part are reinforced by means of the circular box beams. The outer casing supported by the
ends of the longitudinal beams on the bare plates of the foundation.
1. Pressure at inlet : 35 Kg/cm2
2. Temperature at inlet :540 C
3. Conditions of steam :Superheated
STEAM INLET
Steam inlet to the LP turbine from the IP turbine flows into the inner
casing from both sides through inlet nozzles before the LP blading. Expansion joints are
installed in the steam piping to prevent any undesirable deformation of the casing due to
thermal expansion of the steam piping.
INNER CASING
The double flow inner casing, which is of double shell construction,
consists of the outer shell and the inner shell. The inner shell is attached in outer shell with
the provision for free thermal movement. Stationary blading is carried by the inner shell. The
stationary blade row segments of the LP stages are bolted to the outer shell of the inner
casing.
37
DRUM BLADING
The drum blading of the double flow LP turbine is of reaction type.
The stationary blades are located in the inner shell of the inner casing and from the inlet
group of blading of the LP turbine. The LP exhaust stages following these blades are
described in detail in a separate section.
The stationery blades of the first stage have T-roots,. They are fitted in the inner casing in
grooves of corresponding design where they are secured by caulking material. The remaining
stationary blades, which have hook-type roots, are secured in their grooves by means of filter
pieces. Special locking blades are used at the horizontal joint, secured by means of grub
screws.
The moving blades have T-roots, which are inserted into grooves of corresponding design in
the LP turbine shaft and secured by caulking material. The insertion slot is closed by means
of a locking blade, which is attached to adjacent blades by means of taper pins.
All T-roots blades have integral shroud, which upon installation, form a continuous
shroud. The blades with hook-type roots have riveted shrouds. Inorder to keep the
blade tip losses low, replaceable sealing strips are caulked into the inner casing and the
turbine shaft.
38
LOW PRESSURE HEATER
INTRODUCTION There are shell and tube type of heat exchanger with heating
steam on shell side and condensate on tube side. These are used to take the advantage of the
access steam in turbines. Some portion of superheated steam at different points is extracted.
This steam is made to flow in LPH. Here the condensate water coming from Drain Cooler
takes the heat and passes to dearator. There are three heaters LPH 1, LPH 2, and LPH 3.
The condensate first comes in LPH 1, then in LPH 2, and at last in LPH 3.
� TEMPERATURE AT INLET LPH 1 : 50 C
� TEMPERATURE AT INLET LPH 2 : 60 C
� TEMPERATURE AT INLET LPH 3 : 85 C
� TEMPERATURE AT OTULET LPH 3 : 120 C
After the LPH 3, the heated water goes to dearator.
The main parts of LPH are given below:
• SHELL
• TUBE SYSTEM
• WATER SYSTEM.
These parts are described below
SHELL
The shell is of cylindrical construction with dished end welded at bottom and
having a flange at the upper end for assembly of tube system and water box. The shell is
provided with a suitable steam inlet and drain connection along with other nozzle
connections to accommodate various fittings.
39
TUBE SYSTEM
Tube system consists of U-shaped brass tubes (90/10 Cu-Ni ) which have been
fixed in he tube holes, at both ends, by rolling. Tube system have been provided rollers to
facilitate its withdraw. Tube plate is of mid steel and is secured to the water box and shell
flange by means of nuts and bolts.
WATER BOX
Water box is a fabricated shell having on one end for fixing with the tube plate and
shell and the other end is enclosed by dished end. Partition plates have been provided for
making the heater four-pass on water side. Suitable nozzle have been provided for inlet and
outlet.
40
HIGH PRESSURE HEATER
INTRODUCTION
The high pressure feed water heaters are employed to increase the overall
efficiency of the regenerative cycle by heating the feed water by the steam extracted from the
suitable stages of turbine .the feed water passes through the U-tubes and the steam/drain
passes over the tubes. /these heaters are located on the discharge side oil feed pump and use
superheated steam for heating the feed water .the heaters are therefore subjected to very high
pressure and temperatures. There are two High Pressure Heaters HPH 5, HPH 6.
WORKING OF HPH
The high-pressure heater consists of following three zones:
1) DESUPERHEATING ZONE:
The steam first enters the desuperheating zone and
looses its superheat to the feed water. The steam enters into this section and flows over the
tubes through specially designed disc and baffles.
This reduces the pressure drop on steam side and increases the efficiency of the heater disc
and baffles are provided to regulate the steam flow for efficient heat transfer and prevention
of tube viberations.
`
2) CONDENSING ZONE
slightly superheated steam coming out of desuperhating
zone condenses in condensing zone giving its sensible and latent heat to the feed water
41
flowing through the tubes. This zone is provided with specially designed baffles to prevent
tube viberations and for efficient heat transfer.
3 ) DRAIN COOLING ZONE:
Condensed steam I.e., drain from condensing zone passes over the tubes in drain
cooling zone and finally goes out of the heater and is sent to lower stage heater. In this zone
segmental baffles have been provided for efficient heat transfer and for prevention of
vibration. Flow of feed water is counter to drain flow direction feed water flows through the
tubes and then to condensing zone and finally to D.S. zone. Feed water after leaving the
lower stage heater goes to top H.P.heater and from there to boiler.
42
TURBO-GENERATOR (T.G.)
INTRODUCTION: The generator is directly coupled to the turbine shaft, converts
mechanical energy of turbine shaft into electrical energy. It consists of two electrical
windings. One is mounted on the turbine shaft, rotating with it, and is called the rotor. The
other is arranged as a shroud around the rotor, fixed to the floor, and is called stator. The
relative motion of rotor and stator generates the electricity. The generator, which is hydrogen,
cooled produces electricity at 15,750Volt.
The T-G is two pole type with cylindrical rotor (Non -Salient Pole type) using direct water
cooling of stator winding, including phases connecting bus bar, terminal bushing and direct
hydrogen cooling of rotor winding. The stator frame is of pressure –resistant and gas tight
construction with 4 horizontal coolers in the frame itself forming part of ventilation and
closed cooling circuit.
GENERATOR CAPABILITY
The generator is capable of delivering 247MVA continuously at 15.75KV terminal voltage,
9050 Amps stator current and 3.5Kg/Cm2 hydrogen pressure with cold gas temperature not
exceeding 44degrree Celsius and distillate temperature at inlet of stator winding not
exceeding 45 degree celicsus. Output of the generator at the various lagging and leading
power factors at rated hydrogen pressure are as per the generator capability curve given.
Characteristics (O.C.C, S.C.C) and v-curves of the generator are shown on the diagrams.
HYDROGEN COOLER:
The turbo-generator has been provided with four Nos. gas coolers mounted longitudinally in
side stator body for cooling of hot gas, thus taking away the heat looses generated by rotor
winding, stator core and wind age losses. The gas cooler is a shell and tube heat exchanger
consisting of cooling tubes with coiled copper wire around them to increase the surface area
of cooling. Cooling water flows through the tubes while hydrogen flowing across coolers
comes into contact with external surface of cooling tubes. Heat removed from hydrogen is
dissipated through cooling water.
43
AUXILIARIES
SEAL OIL SUPPLY SYSTEM
The shaft seals are supplied with seal oil from a separate circuit, which consists to
the following principal component Vacuum Tank, AC seal oil pumps 1&2, DC seal
oil pump, Vacuum pump, oil coolers, and Seal oil filters, Intermediate oil tank.
A vacuum tank pump keeps the seal oil in the vacuum tank under vacuum and largely
extracts the gas absorbed by the oil while passing through the hydrogen and air atmospheres.
The seal oil is drawn from the vacuum tank and delivered to the shaft seals via a cooler and
filter. In the event of a failure of seal oil pump1. Seal oil pump 2. Automatically takes over
the seal oil supply. Upon failure of seal oil pump2, the standby DC seal oil pump is
automatically takes over the oil supply to the shaft seals.
GAS SUPPLY SYSTEM
The gas system has the following functions:
• To provide means for safely putting H2 into or taking it out of the machine.
• To maintain gas pressure in the machine at the desired value.
• To indicate to the operator at all tomes the condition of gas in the machine, its
pressure and purity.
• To dry the gas in the machine and remove any water vapour which may get into it
from the seal oil.
The gas system essentially comprises the following equipments
• H2 and CO2 cylinders
• Pressure reducers
• CO2 vaporizer
• Gas drier
• Humidity Monitors
• Purity measuring instruments.
Hydrogen is admitted to the generator through a perforated pipe header extending
along the length of the casing at the top. To prevent formation of an explosive mixture in the
generator casing during filling and removing the hydrogen. The air or hydrogen in the casing
44
is first removed with carbon dioxide respectively. The latter is introduced through CO2 feed
pipe, and the air or hydrogen in the casing is discharged to atmosphere through the hydrogen
feed line. The hydrogen driers, services to dry the gas inside the generator.
STATOR WATER COOLING SYSTEM
The water for cooling the stator winding, phase connection and bushing is circulated in a
closed circuit. To ensure uninterrupted generator operation 100% capacity pumps sets are
provided. In the event of a failure of one pump the standby pump is immediately cut in by
automatic starting equipment.
The stator water supply systems essentially comprise the following components:
• Expansion Tank
• Stator Water Pump A&B
• Stator Water Cooler A&B
• Stator Water Filter A&B
The operating pump draws the water from the expansion tank. The water after
passing through water coolers, filters enter the winding and returns back to the expansion
tank.
START UP OF GENERATOR
Prior to start up, it should be ascertained that the following auxiliaries are in operation and
will continue to remain in service.
• Seal oil system
• Gas System
• Stator water system
• Secondary cooling water system
Prior to startup, all the connections should be rechecked. This applies to the piping as
well as to cabling. When checking the cabling, special attention should be paid to testing the
metering and signal cables. All alarm systems should be checked. All temperature
measuring points should also be checked . This applies to the local as well as remote reading
thermometers.
SHUT DOWN OF GENERATOR
When shutting down the generator all excitation should be removed by the time speed
45
reaches to 2000rpm. If this is not done the field winding temperature will rise to lack
ventilation since rate of gas circulation is proportional to speed.
CONDENSATE AND BOILER FEED SYSTEM
The steam after doing the useful work in the turbine is exhausted into the condensers
where it is condensed by the cooling water (circulating water) flowing through a network of
tubes. After condensation, the condensate is collected in the hot wells of the condensers.
From the hot wells, the condensate is handled by the condensate extraction pumps and is
taken back to the closed loop system. Condensate pump delivers the condensate into the
deaerator through the main ejectors, chimney steam condenser, gland steam condenser and
low-pressure heaters. There are three number of condensate extraction pumps of vertical
turbine type installed for the above purpose. The pump capacity of 160 T/hr and develops
215 MWC head. Under normal conditions of operation of the unit (including full load
condition) two pumps are required to be kept in service while the third is a standby.
The condensate tapped off from the condensate extraction pumps discharge header is
utilized for the following services:-
1. Sealing of valves in the vacuum system. Condensate booster pump stuffing box
sealing.
2. L.P. gland sealing de-super heaters.
3. de-super heaters in the chimney steam condenser.
4. Cooler in the TG-exhaust.
5. Dilution of phosphate and hydrazine solutions.
The make up to the closed cycle is added at the condenser hot well by means of the
make up water pumps. There are 5 numbers D.M. transfer pumps installed which take their
suction from a D.M. water storage tank.
The condensate entering the desecrator under goes desecration process in which all
the dissolved gases in the condensate are removed to a greater extent and the desecrated
water is collected in the feed water tank which is an integral part of the deaerator. The feed
water tank is installed at a sufficiently higher elevation to provide a positive suction to the
boiler feed pumps.
46
The flow path of feed water is schematically shown in fig. The boiler feed pumps
(locted in the ground floor of the turbine hall) take their suction from the feed water tank and
deliver the feed water into the boiler drum through high pressure heater, feed control station
and economizer.
Two Nos. of boiler feed pump each of capacity- 445 /hr (8180 1 pm) developing 178
atm. head is installed. Out of two pumps, one pump is required to be kept in service while
the other one is a standby.
The feed control station consists of three branches of feed lines- a low load line
meant for up to 20% MCR and other two lines meant for 100% MCR conditions. (Out of the
two 100% MCR lines, one will be service while other is a standby).
The feed water for the de-super heaters of the SH and RH is tapped off before the
feed control station. Provisions are made to use the condensate booster pump for initial
filling of the boiler drum.
PROTECTIONS AND INTERLOCKS
The main turbine trip relay (TTX) energizes the turbine and trips the turbine under
the following conditions:-
1. Under frequency protection.
2. Generator shut-down energization.
3. Remote trip (P.B).
4. Generator distance relay actuation.
5. Generator negative sequence.
6. Generator transformer ground.
7. Generator loss of excitation.
8. Boiler master trip.
9. L.P.G. heater no.1 level high.(left or right: 775mm).
10. L.P. heater no. 2 level high (left or right: 775mm).
11. Axial shift thrust bearing high: (± 0.65mm).
12. Hydro mechanical protection axial shift very high: (±0.85mm).
13. Primary governing oil pressure high: (3.05atm.).
14. Bearing oil pressure very low: (0.8atm.).
47
15. Main oil pump discharge very low: (7 atm.).
16. Exhaust pressure very high: (0.5 atm.).
EXPLANATION OF TURBINE SYSTEM :-
First of all the steam is generated in the steam generator i.e. boiler. From second pass
of the boiler the steam is generated at 530°C and at a pressure of 110 kg/cm2 enters the high
pressure turbine. The steam works i.e. expands along the rows of blades and the prime mover
i.e. turbine starts moving. After working in the high pressure turbine the steam again enters
the second pass of the boiler for reheat. All the turbines are coupled to a single rotor. The
high pressure turbine is of reaction turbine, horizontal type multicylinder. In reaction turbine
the steam expands continuously as it passes over the rows of blades and thus there is gradual
fall in pressure during expansion.
The steam from high pressure turbine enters the second pass of boiler for reheat at
30kg/cm2 at 360°C. After reheating the steam again enters the medium pressure turbine at 28
kg/cm2 . The temperature of the steam entering the medium pressure turbine is 530°C. After
working the steam leaves the medium pressure turbine is of impulse type. In impulse
turbines steam expands in the nozzles and its pressure does not alter as it moves over the
blades. So the pressure of the steam entering the MP and leaving MP remains 28kg/cm2.
With in the casing of the MP. Number of tappings namely 4,5,6,7 are made for low pressure
heaters. Tapping number six is the dummy tapping.
Tapping number 5 from the MP turbine goes to the LP turbine goes to the heater NO.
2. The condensate of all the three LPHs goes to the deaerator. Tapping no.7 from MP turbine
goes to high pressure heater no.2, HPH no.1 gets connestion from the cold reheat from the
high pressure turbine. The condensate of the high pressure heaters goes to the economizer.
The outlet temperature of condensate from HPH is 240°C. From the deaerator after deaerator
the condensate through boiler feed pump goes to HPHs from where this enters to economizer.
48
From the MP turbine the steam enters the LP turbine. After working, the steam enters
the condenser, four LPHs are also placed within the casing of the LP turbine. The condensate
from these heaters through a single pipe enters the ejector, fromwhere the condensate enters
the chimney steam condenser and then to the gland steam condenser through which the
condensate enters the HPHs and then goes to economizer. The steam leaves the LP turbine at
-0.90 kg/cm2 i.e. it works under vacuum.
The work of the ejector is to create vacuum. The condensate from the ejector enters
the main steam to the condenser. After condensation the condensate entersthe condensate
enters the well of the condenser which is at 45°C. One tapping from the well goes to the
ejector. a level of the water is maintained in the well. The condensate from the gland steam
condenser and chimney steam condenser enters the water well.
With in the medium pressure turbine a dummy tapping is there. The steam enters this
turbine at 530°C from two sides. The pressure of steam is 28
The cold reheat from the HP turbine enters the second pass of the boiler. The turbine
speed is controlled by electro-hydraulic governing device, from where governing is done.
49
CONSTRUCTION OF TURBINE :-
The turbine is a tandem compound machine with HP, IP and LP parts. The HP part is
single flow cylinder and IP and LP parts are double flow cylinders. The individual turbine
rotors and the governor rotors are connected by rigid couplings.
In designing the supports for the turbine on the foundation, attention is given to the
expansion and contraction of the machine during thermal cycling. Excessive stresses would
be caused in the components if the thermal expansion or contraction were restricted in any
way. The method of attachments were restricted in any way. The method of attachments of
the machine components and their coupling together are also decisive factors in determining
the magnitude of the relative axial expansion between the rotor system and turbine casing.
CASING EXPANSION:-
The front and rear bearing housing of the HP turbine can slide on their base plates in
an axial direction. Any lateral movement perpendicular to the machine axis is prevented by
fitted keys. The bearing housings are connected to the HP and IP turbine casing by guides
which ensures that the turbine casing maintain the central position while at the same time
allowing axial movement. Thus the origin of the cumulative expansion of the casing is at the
front bearing housing of the IP turbine.
ROTOR EXPANSION:-
The thrust bearing is in corporated in the rear bearing housing of the HP turbine.
Since this bearing housing is free to slide on the base plate. The shafting system moves with
it. Seen from this point both the rotors and casing of the HP turbine expand towards the front
bearing housing of the HP turbine. The rotor and casing of the IP turbine expand towards the
generator in a similar manner.
DIFFERENTIAL EXPANSION:-
Differential expansion between the rotor and casing results from the difference
between the casing expansion. Originally from the bearing housing behind the IP turbine.
CONSTRUCTION OF TURBINE (HP) :-
Casing :- Barrel type without axial joint. An axially split guide blade carrier is arranged in
the barrel type casing suitable for quick start up and loads.
Blading :-The HP turbine blading consists of several stages. All the stages are reaction stages
with 50%.
50
FOR IP TURBINE:-
Casing :- The casing of IP turbine is split horizontally and is of double shell construction.
Casing :- The LP turbine casing consists of a double flow unit and has a triple shell welded
casing. The turbine has a hydraulic speed governor MAX46BY00l and electro-hydraulic
turbine controller. The hydraulic speed governor adjusts main control values MAA10 +
20AA002 and MAB10 + 20AA00l by way of hydraulic convertor.
51
BOILER
Boiler section
The steam generating unit is designed to meet the nominal requirements of
110MW turbo generator set. The unit is designed for a maximum continuous rating of 375
tones/hr. at a pressure of 139kg/cm2 and a steam temperature of 5400°C. the reheated steam
flows at MCR 32H tones/hr. at the feed water temp at MCR is 2400°C. The unit is a balance
draught dry bottom; single drum natural circulation, vertical water tube type, construction
with skin casing and a single reheat system. The furnace is arranged for dry ash discharge
and is fitted with burners located at the four corners. Each corner burner comprises coal,
vapour oil and secondary air compartments. The unit is provided with three ball mills and
arranged to operate with intermediate cool powder bunker. The steam super heater consists
of 4 stages Viz. Ceiling, convection, platen and final superheated. The ceiling super heated
forms the roof of the furnace and horizontal pass and finishes as the rear wall of the second
pass. The convection super heated is made up of horizontal banks located in the second pass.
While the platens are located at the furnace exit, the portion above the furnace nose encloses
52
the final superheated reheater are in two stages, first stage is the triflux heat exchangers
located in the second pass, which absorbs heat from superheated steam as well as from the
flue gases. The second stage is exit reheater located in the horizontal pass as pendant tubular
loops.
(a) The flue gas for drying the cool in the mills is tapped off after the triflux heat exchangers.
The damper located in the hot flue gases pipe leading to mill controls the quantity. Control
the circulating vapour of the mill entry effect temperature control.
Immediately after the triflux heat exchanger, the air heaters and economizers are located.
The air heater is in 2 stages.
(b) The hot air for combustion from air heater stage 2 is led into the common wind box
located on the sided of the furnace. 4 cool air mixed pipes from pulverized coal bounders are
connected to 4 cool burners’ nozzle at the corners. There will be totally 16 coal nozzles. 4
located in each corner. Oil guns will be located in the secondary air nozzle for coal burning.
The turn down ratio of the guns will be so selected that it will be possible to use them also
for pulverized fuels flame stabilization while operating under load below the control point.
(c) Take into consideration the high % age of ash and the relatively poor quality of coal due
regards has been paid to wide pitching the tubes and to the gas velocity across the heating
surface areas. In order to insure reliable and continuous operation sample sot blowing
equipment is provided. There are short retractable steam root blowers provide at the top of
furnace fully retractable rotary type blowers are located for cleaning of the secondary super
heater and final heater partly retractable steam blowers are arranged for the horizontal
reheater and super heaters in the second pass. The steam root blowers are electrically
operated.
(d) Root blowing nozzles using blow down from boilers drum are provide for the cleaning of
areas around the burners nozzles zone for dislodging of slag boulder if any in the bottom ash
hopper in the furnace.
(e) Two FD fans are provided per boiler. The FD fans are of the axial type driven by constant
speed motor. The regulation of quantity and pressure is done by inlet vane control. The flue
gases are sucked through the mechanical and electrostatic precipitators by I.D. fans and
delivered into the chimney. Two I.D. fans are provided for each boiler and they are of the
axial type driven by constant speed motors. Inlet vane control effects the capacity change
53
with reference to load. Both the I.D. and FD fans have been dimensioned taking into account
the minimum margins of 15% on volume and 32% on pressure.
Specification
• Manufacturer B.H.E.L
• Maximum continuous rating 375tones/hr.
• Super heater outlet pressure 139kg /cm2
• Reheater outlet pressure 33.8 kg/cm2
• Final super heater temperature 540 deg.c
• Feed water temperature 240deg.c
• Efficiency 86% (stage-1)
• Coal consumption per day 1500 tones
54
Fig 11.1
The G.N.D.T.P. units are primarily coal-fired units and the coal consumption at
maximum continuous rating (M.C.R.) per unit is about 58 T/Hr. the coal used at G.N.D.T.P.
is of bituminous and sub-bituminous type and this is received from some collieries of M.P.
and Bihar. The designed composition of coal is as below:-
� Type Bituminous Coal
� Net calorific value 4300 kcal/kg
� Moisture content in coal 10%
� Ash content 30%
� Volatile matter in combustibles 24%
� Grind ability index 50 Hard Groove
The coal handling plant at G.N.D.T.P. has been supplied and erected by M/s Elecon
Engineering Company Limited, Vallabh Vidya Nagar, Gugarat. Coal is transported from the
coal mines to the plant site by Railways. Generally, the raw coal comes by railway wagons
of either eight wheels weighing about 75 to 80 tones each or four wheels weighing about 35
to 40 tones each. The loaded wagon rake is brought by railways main line loco and left on
COAL HANDLING PLANT
(CHP)
55
one of the loaded wagon tracks in the power station marshalling yard. The main line loco
escapes through the engine track. The station marshalling yard is provided with 8 tracks. The
arrangement of the tracks in the marshalling yard is as follows:-
DESTINATION NO. OF TRACKS
Loaded wagons receiving tracks Four
Empty wagon standing tracks Three
Engine escape tracks One
UNLOADING OF COAL:-
In order to unload coal from the wagons, two Roadside Tipplers of Elecon make are
provided. Each is capable of unloading 12 open type of wagons per hour. Normally one
tippler will be in operation while the other will be standby. The loaded wagons are brought
to the tippler side by the loco shunters. Then with the help of inhaul beetle one wagon is
brought on the tippler table. The wagon is then tilted upside down and emptied in the hopper
down below. The emptied wagon comes back to the tippler table and the outhaul beetle
handles the empty wagons on the discharge side of the tippler. The tippler is equipped with
the integral weighbridge machine. This machine consists of a set of weighing levers centrally
disposed relative to tippler. The rail platform rests on the weighing girders and free from rest
of the tippler when the wagon is being weighed. After weighing the loaded wagons is tipped
and returned empty to the weighing girders and again weighed. Thus the difference of the
gross weight and the tare weight gives the weight of the wagon contents. The tipplers are run
by motors of 80 H.P. each through gears only.
Fig11.2 WAGON TIPPLER
56
The tippler is designed to work on the following cycle of operation:-
Tipping 90 seconds
Pause 5-12 seconds
Return 90 seconds
Weighing 30 seconds
Total 215-222 seconds
Allowing 85 seconds for wagon changing it will be seen that 12 eight-wheel wagons
or 24 four-wheel wagons per hours can be tipped. However since the coal carrying capacity
is 500 tones per hour load of 12 wagons comes to 8 to 9 per hour.
DUST TRAPPING SYSTEM:-
The tippler is also provided with the dust trapping systems by which the dust
nuisance will be minimized. As the tippler rotates, a normally closed hopper valve opens
automatically and the discharged material passes through it into the hopper with its dust-
setting chamber, there is an air valve of large area, which opens, simultaneously with the
hopper valve. The object of this air valve is to blow back through the hopper valve into the
tipping chamber, which must occur if, the settling chamber were closed, it being
remembered that a large wagon contains some 240 cubic feet of material and that this
volume of dust air would be forced back at each tip if the hopper chamber were a “closed
bottle”. The air valve and the hopper valve are shut immediately on reversal of the tippler
and are kept shut at all times except during the actual discharge. The hopper valve is
operated by a motor of 10 H.P., 415 Volts and the air valve is operated by electro-hydraulic
thruster. Inlet valve consists of large number of plates sliding under the wagon tippler grating.
Coal in the wagon tippler hopper forms the heap and as such obstructs the movement of
sliding valve and damaging the plates. The inlet and outlet valves have therefore been
bypassed.
The unloaded material falls into the wagon tippler hopper (common to both tipplers)
having a capacity of 210 tones. The hopper has been provided with a grating of 300mm X
300mm size at the top so as to large size boulders getting into the coal stream. There is also a
provision of unloading the wagons manually into the MANUALLY UNLOADED HOPPER
57
of 110 tones capacity. Manually unloading will be restored to while unloading coal from sick
wagons or closed wagons.
MAGNETIC PULLEYS:-
On belt conveyor no. 4A and 4B, there have been provided high intensity
electromagnetic pulleys for separating out tramp iron particles/pieces from the main stream
of coal conveying. D.C. supply for the magnet is taken on 415 volt, 3 phase, 50 cycles A.C.
supply system.
In addition to above high intensity suspension type electromagnets have also been
provided on belt conveyors 4A and 4B for separating out tramp iron pieces/particles.
RECLAIMING:-
If the receipt of coal on any day more than the requirement of the boilers, the
balanced material will be stocked via conveyor 7Aand 7B and through telescopic chute fitted
at the end of the conveyor. At the end of the chute one tele level switch is provided, which
automatically lifts the telescopic chute to a predetermined height every time. The tele level
switch is actuated by the coal pile. When the telescopic chute reaches maximum height
during operation, which will be cut off by limit, switch and stop the conveying system.
When the pile under the telescopic chute is cleared, the telescopic chute can be
independently lower manually by push buttons.
There are five bulldozers to spread and compact the coal pile. Bulldozers of Bharat Earth
Movers Limited Make are fitted with 250 H.P. diesel engines. Each bulldozer is able to
spread the crushed coal at the rate of 250 tones/hr. over a load distance of 60m the coal can
be stacked to a height of 6m the stockpile stores coal for about 45 days for four units with an
annual load factor of 0.66.
Whenever coal is to be reclaimed the bulldozers are employed to push the coal in the
reclaim hopper having a capacity of 110 tones. The coal from the reclaim hopper is fed either
9A or 9B belt conveyor through vibratory feeders 8A and 8B.
58
CRUSHER HOUSE:-
The crusher house accommodates the discharge ends of the conveyor 4A, 4B
receiving ends of conveyor 5A, 5B and conveyor 7A and 7B, two crushers, vibrating feeders
and necessary chute work. There are two crushers each driven by 700H.P. electric motor, 3
phase, 50 cycles and 6.6 kV supply. The maximum size of the crushed coal is 10mm. The
capacity of each crusher is 500 tones/hr. one crusher works at a time and the other is standby.
From the crusher the coal can be fed either to the conveyors 5A, 5B or 7A, 7B by adjusting
the flap provided for this purpose. There is built in arrangement of bypassing the crusher by
which the coal can be fed directly to the conveyors bypassing crusher.
Fig. 11.3
CONVEYER BELT AND CRUSHER HOUSE
59
Spending Our six week of training in Guru Nanak Dev Thermal Plant,
Bathinda, We concluded that this is a very excellent industry of its own type. They have
achieved milestones in the field of power generation. They guide well to every person in the
industry i.e. trainees or any worker. We had an opportunity to work in various sections
namely switch gear, Boiler section, Turbine section, EM-2 CELL etc. while attending
various equipments and machines. We had got an endeverous knowledge about the handling
of coal, various processes involved like unloading, belting, crushing and firing of coal. The
other machines related to my field that we got familiar with boiler, turbine, compressors,
condenser etc. We found that there existed a big gap between the working in an institute
workshop and that in the industry. Above all the knowledge about the production of
electricity from steam helped me a lot to discover and sort out my problems in my mind
related to the steam turbine, their manufacture, their capacity, their angle of blades and their
manufacturing. The training that We had undergone in this industry will definitely help me
to apply theoretical knowledge to the practical situation with confidence.
CONCLUSION
60
REFERENCES
1. MANUAL OF NANAK DEV THERMAL PLANT, BATHINDA.
2. Thermal Engineering , R.S khurmi & J.K Gupta
3. www.wikipedia. com
4. A textbook of power plant engineering: - Er. R.K.RAJPUT