Trans Pricing NPTI 090811

Embed Size (px)

Citation preview

  • 7/28/2019 Trans Pricing NPTI 090811

    1/76

    Sharing of Inter StateTransmission Charges

    Eastern Regional Load Despatch Centre

  • 7/28/2019 Trans Pricing NPTI 090811

    2/76

    Contents

    Historical Background

    Overview of proposed framework

    Important decisions of Implementation

    Committee Important decisions of Validation Committee

    Orders on removal of difficulties Progress of Implementation

    Results of Computation of PoC Charges and

    Losses for 2011-12

  • 7/28/2019 Trans Pricing NPTI 090811

    3/76

    Fundamental Principles

    Objectives of Pricing system

    Promote the efficient day-to-day operation of the bulkpower market;

    Signal locational advantages for investment in

    generation and demand; Signal the need for investment in the transmission

    system;

    Compensate the owners of existing transmissionassets;

    Simple and transparent

    Politically implementable

  • 7/28/2019 Trans Pricing NPTI 090811

    4/76

    Desirable Features of a

    Transmission Pricing SchemeReasonable revenue to the transmission system

    owners

    Equitable sharing of the above payment between thetransmission system users, according to benefits

    derived

    Inducement to transmission system owner to enhance

    the availability of the system

    Ensuring that merit - order dispatch of generating

    stations does not get distorted due to defectivetransmission pricing

  • 7/28/2019 Trans Pricing NPTI 090811

    5/76

    Desirable Features of a

    Transmission Pricing Scheme

    Ensures that planned development / augmentation ofthe transmission system, which is otherwisebeneficial, does not get inhibited

    Appropriate commercial signal for optimal location ofnew generating stations and loads

    Treatment of transmission losses whether handledseparately or as a part of transmission charges

    Priority of transmission system usage between usersunder different categories

  • 7/28/2019 Trans Pricing NPTI 090811

    6/76

    Desirable Features of a

    Transmission Pricing Scheme

    Revenue of transmission system owner, in a vertically

    unbundled scenario, should not depend on dispatchdecisions and actual power flows

    To the extent possible, the users should know upfrontwhat charges they would have to pay, andretrospective adjustments should be avoided

    Dispute-free implementation on a long-term basis

  • 7/28/2019 Trans Pricing NPTI 090811

    7/76

  • 7/28/2019 Trans Pricing NPTI 090811

    8/76

    Policy Mandate

    Electricity Act 2003Electricity Act 2003

    National Electricity PolicyNational Electricity Policy

    Tariff PolicyTariff Policy

  • 7/28/2019 Trans Pricing NPTI 090811

    9/76

    Policy Mandate

    National Electricity Policy

    Section 5.3.2.Prior agreement with the beneficiaries would not be a

    pre-condition for network expansion

    Section 5.3.5

    ..The tariff mechanism would be sensitive to

    distance, direction and related to quantum of flow.

  • 7/28/2019 Trans Pricing NPTI 090811

    10/76

    Policy Mandate Tariff PolicySection 7.1 : Transmission Pricing

    Section 7.1.1

    The National Electricity Policy mandates that the national tariffframework implemented should be sensitive to distance, direction

    and related to quantum of power flow

    Section 7.1.2Transmission charges, under this framework, can be determined on

    MW per circuit kilometer basis, zonal postage stamp basis, or some

    other pragmatic variant, the ultimate objective being to get the

    transmission system users to share the total transmission cost inproportion to their respective utilization of the transmission

    system

    Contd..

  • 7/28/2019 Trans Pricing NPTI 090811

    11/76

    Historical Background

  • 7/28/2019 Trans Pricing NPTI 090811

    12/76

    Development of Transmission System

    GENERATION

    DISTRIBUTION

    TRANSMISSION

    GENCO

    TRANSCO

    DISCO

    Unbundling

  • 7/28/2019 Trans Pricing NPTI 090811

    13/76

    Scenario in Recent Past

    TRANSMISSION

    SERVICEPROVIDER(TSP 1)

    Transmission Assets (T1A 1-n)

    UTILITY (U-2)

    UTILITY (U-1)

    UTILITY (U-4)

    UTILITY (U-3)

    UTILITY (U-n)

    TRANSMISSIONSERVICE

    PROVIDER(TSP 2)

    Transmission Assets (T2A 1-n)

    ONE REGIONAL GRID

    Multiple Utilities With Two Transmission Service Providers

  • 7/28/2019 Trans Pricing NPTI 090811

    14/76

  • 7/28/2019 Trans Pricing NPTI 090811

    15/76

    Future Scenario : More Complexities

    REGIONAL GRID -1

    TSP 1Transmission Assets (T1A 1-n)

    U-2

    U-1

    U-4

    U-3

    U-n

    TSP 2Transmission Assets (T2A 1-n)

    TSP mTransmission Assets (TmA 1-n)

    TSP 3Transmission Assets (T3A 1-n)

    D-1 D-n

    D-1 D-n

    D-1 D-n

    D-1 D-n

    D-1 D-n

    REGIONAL GRID -2

    TSP 1Transmission Assets (T1A 1-n)

    U-2

    U-1

    U-4

    U-3

    U-n

    TSP 2Transmission Assets (T2A 1-n)

    TSP mTransmission Assets (TmA 1-n)

    TSP 3Transmission Assets (T3A 1-n)

    D-1 D-n

    D-1 D-n

    D-1 D-n

    D-1 D-n

    D-1 D-n

    Inter-Regional Interconnections

    TSPs in One Region Having Customers in Another Region Also

  • 7/28/2019 Trans Pricing NPTI 090811

    16/76

    Elegant Model

    TSP 1

    Transmission Assets (T1A 1-n)

    TSP 2Transmission Assets (T2A 1-n)

    TSP mTransmission Assets (TmA 1-n)

    TSP 3Transmission Assets (T3A 1-n)

    U-2

    U-1

    U-4

    U-3

    U-n

    D-1 D-n

    D-1 D-n

    D-1 D-n

    D-1 D-n

    D-1 D-n

    AGENCYFOR

    PLANNING

    U-2

    U-1

    U-4

    U-3

    U-n

    D-1 D-n

    D-1 D-n

    D-1 D-n

    D-1 D-n

    D-1 D-n

    Region

    -1

    Region-2

    AGENCYFOR

    COMPUTATION

    OFTRANMSSION

    CHARGES

    AGENCYFOR

    BILLING&

    COLLECTION

  • 7/28/2019 Trans Pricing NPTI 090811

    17/76

  • 7/28/2019 Trans Pricing NPTI 090811

    18/76

    Sharing of Transmission charges -

    earlier Methodology

    Regulation 33 of Terms and Conditions of Tariff

    Regional postage stamp

    Shared by beneficiaries in the same region as well as other regions

    Generating companies if beneficiary not identified

    Medium term users

    Pooling of all ISTS assets as on 1.4.2008

    Charges of new ATS

    By respective beneficiaries if pooling not agreed

    Part pooling / part by respective beneficiaries

    Treatment of inter-regional link charges

    Step down transformers and down-stream system after 28.3.2008

    By beneficiary directly served

  • 7/28/2019 Trans Pricing NPTI 090811

    19/76

  • 7/28/2019 Trans Pricing NPTI 090811

    20/76

  • 7/28/2019 Trans Pricing NPTI 090811

    21/76

    Drivers for change in pricing

    framework Pricing inefficiency in the emerging circumstances

    Synchronous integration of Regions- Meshed Grid

    Changes caused by law and policy

    Open Access and Competitive Power Markets Pricing Inefficiencies, Market Players concern

    National Grid / Trans-regional ISGS Changing Network utilization

    Agreement of beneficiaries a challenge

    Ab-initio identification beneficiaries difficult

  • 7/28/2019 Trans Pricing NPTI 090811

    22/76

    Regulatory Initiatives

    Discussion Paper on Sharing of Charges and losses inInter-State Transmission System (ISTS) (2007)

    Approach Paper on Formulating Pricing Methodology forInter-State Transmission in India (May 2009)

    Draft Regulation on Sharing of Inter-State TransmissionCharges and Losses (February 2010)

    Regulation on Sharing of Inter-State TransmissionCharges and Losses (June 2010)

  • 7/28/2019 Trans Pricing NPTI 090811

    23/76

    New Methodology

    In Rs. per MW per monthNodal / Zonal ChargesSeparate Injection & Withdrawal Charges

    To be made known upfrontTo be applied on Medium Term and ShortTerm Trades

    Based on Load Flow StudiesHybrid of Average Participation andMarginal Participation methods

    To begin with 50% Uniform Charges and50% PoC ChargesGradual movement towards 100% PoCCharges

    Three Slab Rates for initial years.

  • 7/28/2019 Trans Pricing NPTI 090811

    24/76

  • 7/28/2019 Trans Pricing NPTI 090811

    25/76

    CERC Regulations on Sharing of

    Transmission Charges & Losses Notification of Regulations : 15th June 2010

    Applicable to:

    Designated ISTS Customers

    Inter State Transmission Licensees NLDC, RLDC, SLDCs, and RPCs

    Regulations to come into force from 1.1.2011 For a period of 5 years unless reviewed or extended by

    the Commission

  • 7/28/2019 Trans Pricing NPTI 090811

    26/76

  • 7/28/2019 Trans Pricing NPTI 090811

    27/76

    What is Power Tracing?:

    DefinitionPower Tracing is a tool, applied Post-facto power flow snap-shot

    that provides complete power audit information like:

    Share of loads in Generation

    Generators contribution in Loads

    Loss allocation to generators and Loads

    Decomposition of Transmission line flows into Generator and Load Components

    on

    Wh i i f P

  • 7/28/2019 Trans Pricing NPTI 090811

    28/76

    What are pre-requisites of Power

    Tracing?

    Power Flows over lines and,

    Injections at generator and load busesand,

    Network topology (single line diagram)

    State Estimation Solution

    Or

  • 7/28/2019 Trans Pricing NPTI 090811

    29/76

    Power Tracing: Two VersionsDownstream Algorithm

    Upstream Algorithm

    Generator SideStatements

    Load Side

    Statements

    Each Generators contribution in Transmission Line flows

    Each Generators contribution in Transmission Line losses

    Net power sent to a particular load

    Each Loads contribution in Transmission Line flows

    Each Loads contribution in Transmission Line losses

    Power received from a particular generator includinglosses

  • 7/28/2019 Trans Pricing NPTI 090811

    30/76

  • 7/28/2019 Trans Pricing NPTI 090811

    31/76

    Introduction to the PoC

    Charge Computation Algorithms/ Processes

    AC Load flow and transmission losses

    Slack bus determination- Average Participation method

    Participation factor of a node- Marginal Participation method

    Loss allocation factor of node- Marginal Participation method

    Input Network data for modeling the power system

    Nodal injection / Nodal withdrawal for a scenario

    Yearly Transmission Charges to be apportioned

    Output

    Point of Connection Charge- Demand Zone/ Generation Zone

    Point of Connection Losses- Demand Zone/ Generation Zone

  • 7/28/2019 Trans Pricing NPTI 090811

    32/76

  • 7/28/2019 Trans Pricing NPTI 090811

    33/76

    STU/SEBs/CTU

    Implementing

    Agency

    NetworkParameters Line wise YTC

    Designated

    ISTS

    Customers

    Nodal

    Demand /

    Generation

    Medium Term

    Injection /

    Withdrawal

    Approved

    InjectionApproved

    WithdrawalBasic

    Network

    Network

    Parameters

    ForecastInjection /

    Withdrawal

    Flow Chart for Input Data Acquisition

  • 7/28/2019 Trans Pricing NPTI 090811

    34/76

    YTC assigned

    to each line

    Slack bus

    Point of

    Connection

    Loss

    Point of

    Connection

    Transmission

    Charge

    Power System

    Model

    YTC of line + YTC of

    substation apportioned to

    lines of a voltage level

    Information flow chart

    Average Transmission Charge

    per ckt kilometer for a voltage

    level & conductor configuration

    Basic Network

    data

    ApprovedNodal

    Injection &

    withdrawal

    Truncation of basic

    network, (creation of

    virtual generators /

    loads) load flow, &

    Transmission losses of

    truncated network

    Load flow on

    completenetwork

    Algorithm

    for averageparticipation

    Algorithm forcomputingmarginal

    participation

    Generation Zone

    Demand Zone

    PoC for billing

    Generation Zone

    Demand Zone loss

    for scheduling

    List of state lines

    used as ISTS

  • 7/28/2019 Trans Pricing NPTI 090811

    35/76

  • 7/28/2019 Trans Pricing NPTI 090811

    36/76

    Determination of PoC Charges (2)

    Compilation & checking of network data

    Assumptions for missing data

    Formulation of Base case for load flow studies Based upon the Network Data submitted by the DICs

    All elements up to 132 kV included in the model

    Load Flow Studies on the Full Network Truncation for the purpose of PoC Charge

    Determination

    Network truncation at 400 kV

    Except NER, where it is done at 132 kV.

  • 7/28/2019 Trans Pricing NPTI 090811

    37/76

    Determination of PoC Charges (3)

    Inputs to the WebNetUse Software

    Truncated Network Data

    YTC Details

    Load Flow Study by WebNetUse

    Identification of Slack Bus

    Calculation of Marginal Participation Factors foreach line/bus

    Calculation of PoC Charges for each Node

    Results obtained from WebNetUse Node wise PoC Charges

    Injection charge

    Withdrawal charge

  • 7/28/2019 Trans Pricing NPTI 090811

    38/76

    Sample Calculation

  • 7/28/2019 Trans Pricing NPTI 090811

    39/76

    Timelines for Submission of Information

    Details of data submitted by DICs Injection and Withdrawal forecast for different blocks of

    months (Peak and Other than Peak):

    April to June (for May 15) July to September. (for August 31)

    October to November (for October 30)

    December to February.. (for January 15)

    March (for March 15)

    In case the dates appearing in brackets fall on a

    weekend/public holiday, the data shall be submitted forworking days immediately after the dates indicated

  • 7/28/2019 Trans Pricing NPTI 090811

    40/76

    Determination of PoC Charges (4)

    Philosophy for identification of coherentnodes for zoning

    Zones to be geographically and electrically proximate Shall contain relevant nodes whose costs determined by

    the hybrid method are within same range

    State control areas to be separate demand zone exceptin the case of North Eastern States, which areconsidered as a single demand zone.

    State control areas considered as generation zone

    except NER states which are considered as a singlegeneration zone.

    All thermal plants 1500 MW / hydro plants 500 MW

    connected directly to ISTS or through pooling stations tobe considered as separate generation zone.

  • 7/28/2019 Trans Pricing NPTI 090811

    41/76

  • 7/28/2019 Trans Pricing NPTI 090811

    42/76

  • 7/28/2019 Trans Pricing NPTI 090811

    43/76

  • 7/28/2019 Trans Pricing NPTI 090811

    44/76

  • 7/28/2019 Trans Pricing NPTI 090811

    45/76

    Billing of Transmission Charges

  • 7/28/2019 Trans Pricing NPTI 090811

    46/76

    Central Transmission Utility (CTU) shall be responsiblefor

    Raising the bills, collection and disbursement to ISTS licenseesbased on Accounts issued by RPC

    Bill to be raised only on DICs

    SEB/STU may recover such charges from DISCOMs, Generators

    and Bulk Consumers connected to the intra-state system.

    The billing from CTU for ISTS charges for all DICs shallbe :

    In 3 parts on the basis of Rs/MW/Month and;

    the fourth part for deviations would be on the basis ofRs/MW/Block

    Billing of Transmission Charges

    Billing and Collection of Charges by CTU

  • 7/28/2019 Trans Pricing NPTI 090811

    47/76

    CentralTransmission

    Utility

    Central

    TransmissionUtility

    First Part(Based on Approved

    Injection/Withdrawal and

    PoC Charge)

    Third Part(Adjustments Based on

    FERV, Interest,

    Rescheduling ofCommissioning)

    Fourth Part(Deviations)

    Second Part(Recovery of Charges forAdditional Medium Term

    Open Access)

    Afterissuanceof RTA

    After

    issuanceof RTA

    Biannually(1st Day ofSeptember

    and March

    18th Day

    of aMonth

    Billing and Collection of Charges by CTU

    Treatment of Deviations : Generator

  • 7/28/2019 Trans Pricing NPTI 090811

    48/76

    Generator

    NetInjection

    NetDrawl

    1.25 timesPoC Charge

    Deviation upto

    than 20%

    Deviation

    Greaterthan 20%

    PoC Charge1.25 times

    PoC Charge

    Treatment of Deviations : Generator

  • 7/28/2019 Trans Pricing NPTI 090811

    49/76

  • 7/28/2019 Trans Pricing NPTI 090811

    50/76

    Information on Public Domain Approved Basic Network Data and Assumptions, if any

    Zonal or nodal transmission charges for the next financialyear differentiated by block of months;

    Zonal or nodal transmission losses data;

    Schedule of charges payable by each constituent for thefuture Application Period, after undertaking necessary

    true-up of costs

  • 7/28/2019 Trans Pricing NPTI 090811

    51/76

    Implementation Related Issues Definition of Approved Injection

    Approved Withdrawal Determination of YTC & Substation Cost

    Apportionment

    Multiple Scenarios for PoC computation and Basisof furnishing nodal generation and withdrawal data

    Collection and disbursement of STOA Charges

    Avoidance of double charging

    Connectivity without Long Term Access

    Treatment of HVDC Links

  • 7/28/2019 Trans Pricing NPTI 090811

    52/76

    CERC Orders on Removal of

    Difficulties

    Definition of Approved Injection /

  • 7/28/2019 Trans Pricing NPTI 090811

    53/76

    Definition of Approved Injection /

    Withdrawal Long Term Access (LTA) or PPA/ Contracts

    LTA: Most Sacrosanct figure for transmission PPA/Contracts: used for scheduling purpose

    Transmission is a sunk investment

    Recovery as per approved Transmission Access

    Entities availing long term transmission services :

    liable to pay

    Proper signal for transmission planning

    Incentive for submitting correct transmission

    requirement

    53

  • 7/28/2019 Trans Pricing NPTI 090811

    54/76

  • 7/28/2019 Trans Pricing NPTI 090811

    55/76

  • 7/28/2019 Trans Pricing NPTI 090811

    56/76

  • 7/28/2019 Trans Pricing NPTI 090811

    57/76

  • 7/28/2019 Trans Pricing NPTI 090811

    58/76

  • 7/28/2019 Trans Pricing NPTI 090811

    59/76

  • 7/28/2019 Trans Pricing NPTI 090811

    60/76

  • 7/28/2019 Trans Pricing NPTI 090811

    61/76

  • 7/28/2019 Trans Pricing NPTI 090811

    62/76

    Progress of Implementation(2)

  • 7/28/2019 Trans Pricing NPTI 090811

    63/76

    CERC Order on Determination of PoC Rates andTransmission Losses in accordance with the SharingRegulations dated 29th June 2011

    CERC Order on Approval of Procedure of DataCollection along with formats, Procedure forComputation of PoC Transmission Charges and

    Procedure for Sharing of Losses under the SharingRegulations

    Inputs on PoC Charges for each Regional Entityprovided to the Power Exchanges on 30th June 2011

    PoC Charges and Losses for 2011-12 implementedw.e.f 1st July 2011

    Weekly Loss Application

    Provisional RTA

    g p ( )

  • 7/28/2019 Trans Pricing NPTI 090811

    64/76

    Results of PoC Computation ofCharges and Losses

    (2011-12)

    Handling Bulk Data

  • 7/28/2019 Trans Pricing NPTI 090811

    65/76

    Handling ulk ata

    Buses 4830

    Generating Stations 557

    Generating Units 1148

    Loads 2672

    Branches

    DC Lines 7

    765 kV 2

    400 kV 622

    220 kV 3034

    132 kV 5130Total 8795

    Transformers 2031

    Yearly Transmission Charges

  • 7/28/2019 Trans Pricing NPTI 090811

    66/76

    y g

    ISTS NEW Grid SR Grid Total

    POWERGRID 6605.5 1593.7 8199.2

    POWERLINKS 268.1-

    268.1

    RPTL 80.0 - 80.0

    Jaypee

    Powergrid 141.8 - 141.8

    UPPTCL* 15.6-

    15.6

    RRVPNL* 1.8 - 1.8

    PDD J&K* 10.1 - 10.1

    GETCO* 5.7-

    5.7

    Mahatransco* 20.6 - 20.6

    Total 7149 1594 8743

    ISTS NEW Grid SR Grid Total

    POWERGRID 6605.5 1593.7 8199.2

    POWERLINKS 268.1-

    268.1

    RPTL 80.0 - 80.0

    Jaypee

    Powergrid 141.8 - 141.8

    UPPTCL* 15.6-

    15.6

    RRVPNL* 1.8 - 1.8

    PDD J&K* 10.1 - 10.1

    GETCO* 5.7-

    5.7

    Mahatransco* 20.6 - 20.6

    Total 7149 1594 8743

    * RPC Certified Lines* RPC Certified Lines

    All Figures in Rs Cr/AnnumAll Figures in Rs Cr/Annum

  • 7/28/2019 Trans Pricing NPTI 090811

    67/76

  • 7/28/2019 Trans Pricing NPTI 090811

    68/76

    Slab Rates : NEW Grid

  • 7/28/2019 Trans Pricing NPTI 090811

    69/76

    Rs/MW/Month

    Slab Rates : SR Grid

  • 7/28/2019 Trans Pricing NPTI 090811

    70/76

    Rs/MW/Month

  • 7/28/2019 Trans Pricing NPTI 090811

    71/76

    COMPARISION OF POC CHARGESAND

    PRE-POC TRANSMISSION CHARGES

  • 7/28/2019 Trans Pricing NPTI 090811

    72/76

  • 7/28/2019 Trans Pricing NPTI 090811

    73/76

    2.562.30

    19.24 15.93

    0.02

    7.90

    25.96

    73.93

    1.95

    16.84 15.64

    0.00

    7.34

    22.16

    2.55

    66.47

    0.00

    10.00

    20.00

    30.00

    40.00

    50.00

    60.00

    70.00

    80.00

    SIKKIM WEST

    BENGAL

    ORISSA POWERGRID

    PUSAULI

    JHARKHAND BIHAR DVC Sub -Total

    POC TOTAL Pre-POC TOTAL

    Rs.

    inC

    rore

    Monthly Transmission charges of ER DICs

    Regionwise comparison of PoC & existing monthly transmission charges

  • 7/28/2019 Trans Pricing NPTI 090811

    74/76

    301.13

    197.12

    130.46

    73.93

    25.94

    309.90

    191.66

    138.03

    66.47

    22.52

    0

    50

    100

    150

    200

    250

    300

    350

    NR WR SR ER NER

    POC TOTAL

    Pre-POC TOTAL

    R

    sinC

    rore

    PoC Losses

  • 7/28/2019 Trans Pricing NPTI 090811

    75/76

    Paid in Kind

    Entities to be placed in the slabs based on the

    moderated PoC Losses

    Moderation to be done based on the average losses ofpast 52 weeks

    On Regional Basis.

    Slab Rates for PoC Losses

    Average Loss + 0.3%

    Average Loss

    Average Loss 0.3%

    Average Loss to be declared by RLDCs on weeklybasis.

  • 7/28/2019 Trans Pricing NPTI 090811

    76/76

    Thank You!