Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Transformative Opportunities in Natural Resource Management, Energy and
Transport Sectors in Africa
Presentation to Japanese Companies By
Jamal Saghir
Senior Regional Adviser
Africa Region
The World Bank
Tokyo, November 2014
Structure of the Presentation:
I. World Bank Strategic Vision: Critical Development Challenges and
Need for Transformative Activities in Africa
II. Examples of Ongoing Transformative Projects
III. Illustrative Additional Opportunities for Transformative Projects
IV. Next Steps to Make These a Reality
Nov 2014
I. Strategic Vision: World Bank’s10-year Vision for Africa:
3
Accelerated growth:
At least 20 countries with GDP growth of 3–4 percent a year
Another 20 countries with growth of 1–2 percent per year
Poverty rate reduced by 12 percentage points
Growth achieved with a more diversified production mix, with manufacturing and services growing rapidly and absorbing labor, and agricultural productivity increasing. Aim is for 15 countries—up from the current 8—to register at least 5 percent average annual agricultural GDP growth.
The continent’s share in world trade doubled to 8 percent, with regionally integrated infrastructure providing services at globally competitive costs.
Access to modern energy services increased to at least half of households.
Climate change adaptation measures will be put in place.
Source: Africa’s Future and the World Bank’s Support to It, March 2011
I. Strategic Vision:
To Meet the Transformative Challenge, Bank’s Africa
Strategy Rests on Two Pillars 4
Pillar 1: Enhancing competitiveness and increasing
employment to harness private sector growth for
sustainable poverty reduction and wealth creation
Pillar 2: Reducing vulnerability and building
resilience to shocks of all kinds
Both pillars to be supported by a foundation of improving governance
and public sector capacity
I. Strategic Vision
Strengthening these Pillars Requires Action on Many Fronts
5
Three key areas are:
Water and Other Natural Resource Management
Transport
Energy
I. Strategic Vision
Better Management of Water, Land, and Other Natural Resources is Critical to
Increase Competitiveness, Reduce Vulnerability to Climate Shocks, and
Promote Sustainable Growth 6
Critical for increasing agricultural productivity: yields lag other regions, partly because
irrigation is underutilized
While less than 3 percent of total renewable water resources are used, Africa has by far the lowest
irrigation development rate of any region in the world: < 5% of farmers benefit from water
management.
Intensification needed to combat land degradation and deforestation
Disaster management: resilience hinges on water management
Overwhelming majority of Africans hurt by disasters are affected by droughts or floods
Climate change will increase frequency of extreme events
Urbanization: basic services need scaling up to close the access gap in fast-growing
urban centers
In many countries, less than 65% of population has access to an improved water source
I. Strategic Vision
… And Transport Challenges Must be Addressed to Make Africa
Competitive in Global Markets and Promote Intra-regional Trade
7
Challenging geography: Land-locked countries cover 30% of Africa’s area and population—including Ethiopia, the most populous landlocked country in the World—with on average 50% higher transport costs.
Road systems are in poor condition: of the 50,000 km. of trans-African highways, 30% are unpaved and 50% in poor condition.
Poor inter-modal connectivity.
Congestion in ports: delays and higher costs for shippers.
Aged infrastructure facilities and technology.
Many man-made inefficiencies
Inefficient customs and logistics services
Illegal roadblocks/ checkpoints
Trucking cartels/ monopolies
Bottom line result: the cost of transport in Africa is the highest in the world. Without fixing this, Africa will never be competitive.
I. Strategic Vision
Energy access reduces poverty, promotes shared prosperity
8
Access to modern energy services linked to each of MDGs and SE4All targets call
for universal access to energy:
Low access and low supply: currently, generation is ~80 GW; 600 M people and 10 M SMEs
without access
Competitiveness: energy growth not in pace with GDP growth; demand growing to about 800
TWh by 2020
Quality of life: many countries below the 500kWh/capita consumption; 80% of households
rely on solid biomass
Great opportunities for transformative impact for the WB along the energy
value chain
Knowledge and Partnerships
Access Transmission
and Distribution
Generation
Leverage our limited resources and expand south to south cooperation
Regional integration
(regional power pool
development)
Improved pricing
(sector reform, effective
tariff structures)
Reduced cost of production
(low carbon, low cost
generation)
9
Some high risk/high reward projects are transformative because of their impacts, stemming from environmental, social and economic good practices (strategic environmental and social assessments upfront, the use of offsets and associated conservation measures, systematic monitoring of impacts, livelihood programs, adaptable management, etc). Examples:
Loess Plateau, China
Terraced 3000 km2 of degraded land
More than 2.5 million people in four of China’s poorest provinces—Shanxi, Shaanxi and Gansu, as well as the Inner Mongolia Autonomous Region—were lifted out of poverty.
Sediment flow to Yellow river was reduced by 100 t/yr
Nam Theun 2, Laos
Created1,070MW hydroelectric capacity: 75MW use in Laos, 995MW equivalent export to Thailand
Government of Laos transferring revenues (e.g. US$19 million in FY11) to poverty reduction and environmental protection
Risks: resettlement of 6,000+ people, livelihood improvements in adjacent areas, biodiversity protection, road access enhanced to mitigate isolation.
II. Examples
Ongoing Transformative Projects: Global Examples (1)
10
Some projects are transformative because they fix the “missing links” in regional transport corridors, playing a central role in enhancing intra-regional trade and eventually catalyzing sustainable growth in many sectors, especially for landlocked countries. Examples:
The TRACECA corridor (Europe-Caucasus-Asia corridor – the “New Silk Route”)
Planned to be operational by 2015, the corridor will run from Romania to Georgia and Azerbaijan, and will cross the Caspian Sea to Turkmenistan, Uzbekistan, Kazakhstan, ending in China
Will transform economic relations, trade and transport communications in Europe, the Black Sea region and Asia
Will ensure intermodal access to the world market for road and rail transport and commercial navigation
Includes traffic security, cargo safety and environmental protection, as well as harmonization of transport policy and legal structure
The Brazil-Bolivia-Peru-Chile corridor
Opened up trade opportunities for western part of Brazil and landlocked Bolivia through Port Arica in northern Chile
Regional transport volume through Bolivia increased significantly (about 40% increased) in 5 years after the corridor opened. This has contributed significantly to the growth of Bolivia’s economy
II. Examples
Ongoing Transformative Projects: Global Examples (2)
11
Nigeria Erosion and Watershed Management Project $500m program addresses severe erosion issues in south-eastern Nigeria that threaten livelihoods and assets
Program seeks to develop partnership across Federal and State agencies for common goal
Kandadji Growth Program (Niger River Basin) Access to water for 45,000 ha irrigation development
Additional 130MW hydroelectricity capacity
IDA resources leverages co-financing from 10 other development partners as well as counterpart financing from the Government of Niger (total US$785 million program).
Risks: political insecurity/instability, regional complexities, substantial resettlement of 35,000+, multi-purpose objectives, and weak institutions.
Shared River Basin Programs (e.g. on Niger, Senegal, Nile, Zambezi, etc.) Institutional capacity, networking , and knowledge enhancement
Facilitating cooperative investments
Irrigation Development and Agribusiness Programs (e.g. Zambia, Burkina Faso, Ghana, Senegal etc.) Irrigation projects involving public-private partnerships (PPPs) with commercial agribusiness investors, with
spillover effects for smallholder farmers and local communities.
Small projects can be ''transformational'' if they are innovative and replicable on a wider scale. Humbo Village, Ethiopia,-- innovative carbon emissions reduction project has had transformational impacts through a
landscape approach. It restored over 2,700 hectares and a barren, degraded landscape four years ago with a 70% loss in yields affecting nearly 50,000 impoverished people now enjoys good yields; more water and wood availability; tree products; more biodiversity; and up to 880,000 metric tons of CO2 over the course of the 30-year carbon crediting period. Revenue from the carbon credits is being reinvested in additional community-driven activities such as firewood sales, clothes tailoring, etc.
II. Examples of Ongoing Transformative Water and NRM
Projects in Africa
12
Regional W. Africa Transport and Trade Facilitation Project
Help improve land-locked countries’ access to ports; develop alternatives to historical corridors
Relieve congestion in Tema, a Ghanaian port, and increase efficiency at border crossings in the region
Reduce non-tariff barriers by introducing more mobile customs transit monitoring system to replace escort system
Regional E. Africa Transport and Trade Facilitation Project
Support implementation of EAC customs union
Improve efficiency and reliability of transport and logistics services
Reduce need for fiscal transfers to railways
Projects to reduce man-made inefficiencies, smuggling and corruption
Abidjan-Lagos Corridor Project: improve trade facilitation in port of Abidjan; monitor implementation of policy decisions in corridor; improve roads
CEMAC Corridors Project: improve customs efficiency and reduce legal and illegal barriers through cargo tracking systems, border post construction/ upgrading, custom performance contract systems, upgrading roads and railways
Projects to enhance inter-modal connectivity
Tanzania Intermodal Rail Project: Rehabilitate railway tracks and rolling stock; strengthen regulatory framework
II. Examples of Ongoing Transformative Transport Projects
in Africa: Moving Beyond Incremental Changes
13
II. Examples of Ongoing Transformative Energy Projects in
Africa
Bujagali Hydropower Project, Uganda (Commissioned in 2012)
$360 M in loans and guarantees, Approved by Bank Board in FY08
250 MW additional capacity
Reduces electricity tariff by 25% (From $0.17/kWh to $0.13/kWh)
Improves access to electricity, economic development, reduces grid carbon intensity
Eastern Africa Electricity Highway (Ethiopia-Kenya Interconnector)
$900 M under APL1 (Regional) approved by Bank Board in FY12
Key interlink (backbone) for EAPP - 400 MW bilateral trade initially
Kenya expects 20% reduction in tariff (From $0.17/kWh to $0.14/kWh)
Promotes regional trade, increases regional energy security & cooperation
Nigeria Electricity and Gas Improvement Project and Sector Reforms
PRGs for gas suppliers for an amount up to US$400 million (Approved in 2009)
Improves the availability & reliability of gas supply to increase power generation
Improves the power network’s capacity and efficiency to distribute electricity
Establishes credit enhancement and commercial framework for gas sales
Support for utility privatization and increased private sector participation
Improved pricing with multi year tariff orders (MYTO)
Kenya Geothermal Development and Electricity Expansion Project
US$330M IDA project (Approved in 2010) - total investment US$1,391M
280 MW ‘green’ geothermal additional capacity in African Rift Valley
Adding 220,000 customers a year, up from 60,000 customers four years ago
Electricity for some of the country’s largest slums and most remote rural areas
14
Sampling of projects
presented here are in
are at various stages of
preparation, and with
varying degrees of
World Bank involvement.
Projects include: Niger Basin •Fomi Project
•Rehabilitation of Lake Chad
•Benue Investments
Zambezi Basin •Kariba Dam Rehabilitation
•Malawi Shire valley Irrigation Project
Nile Basin •Kenya Water Security and Climate
Resilience Project
•Eastern Nile Multipurpose Development
•Nile Equatorial Lakes Water Resource
Management
•Regional Rusumo Falls Hydroelectric
Volta Basin •Pwalugu MPP
Regional & sub-regional • S. Africa Transport and Trade Facilitation
Project
• Tanzania Inter-modal and Railway
Rehab (incl. Rwanda and DRC in later
phases)
• Regional intermodal study for EAC
transport corridor
• Lesotho Highlands Water Project - Phase
2
• Africa Hydromet Program
• Africa Sustainable Land Mgmt
III. Additional Opportunities: Transformative Water Projects
Throughout Africa
III. Additional Opportunities:
Planned Water Projects with Transformational Benefits 15
Enhanced government revenue -- Lesotho Highlands Phase 2 could provide Lesotho revenues of 3-5% of GDP from water sales to South Africa
Hydropower generation -- Rusumo Falls Hydro uses run of river to minimize environmental and social footprint; Inga Hydro
Should be joint use (hydropower & irrigation)whenever possible – Fomi; Benue Investments; Kariba Dam Rehab; Batoka Gorge; Eastern Nile Multipurpose Development; Pwalugu Multipurpose; Kenya Water Security and Climate Resilience
Irrigation for agriculture/Water supply for rapidly growing urban areas -- Malawi Shire Valley Irrigation Project; Pwalugu Multipurpose; Lesotho Highlands Phase 2
Flood control -- Most dams enhance flood control for areas downstream; Kariba Dam rehab could prevent devastating downstream damages from dam failure
Community development -- Nile Equatorial Lakes WRM
Preservation of biodiversity and environmental services -- Lake Chad Rehab: 22 million people depend on resources of Lake Chad
Watershed management/ Adaptation to climate change -- Nile Equatorial Lakes WRM, Africa Hydromet Program for Climate Resilience; Kenya Water Security and Climate Resilience; Africa Sustainable Land Management
III. Additional Opportunities: Planned Transport Projects
with Transformational Benefits 16
Example: Southern Africa Trade and Transport Facilitation Project
Project rationale
The North-South corridor (Dar-es-Salaam to Durban) is a very important strategic trade route
Well-endowed with physical assets, but transport costs along the corridor are among the highest in the world: 7 days and 5000$ for the 2000km trip by road between Dar and Lusaka
Port performance remains a crucial issue for the corridor
Border crossings: 15% of the cost and 37% of the time between Durban and Lubumbashi, DRC
Proliferation of legal and illegal checkpoints: the total additional time is more than 5 hours – more than time savings from any physical improvement
Patchwork of (sometimes inconsistent) national regulations
The corridor also has a high social cost: spread of HIV/AIDS and road traffic crashes
Regional, multi-sector, and multi-phase project intended to facilitate trade integration by contributing to the alleviation of institutional, legal, policy and road infrastructure constraints
Activities
Institutional arrangements for transit and transport facilitation
Assessment of options to improve the port at Dar-es-Salaam
Definition and piloting of a regional customs bond
Diagnostic of divergence between different agreements and practice
Improvement of the professionalism of customs brokers, and harmonization
Upgrading or rehabilitating road transport infrastructure and improving transit facilities
Mitigating the social costs
III. Additional Opportunities: Other Planned Transport
Projects with Transformational Benefits 17
Tanzania Intermodal Rail Project A new intermodal transport strategy, integrating rail,
port and road systems, based on a clear business model for key
market and reliable services at a regional level. It will alleviate
bottlenecks, delays and increased transport costs for six
landlocked neighbors (eastern DRC, Rwanda, Burundi, Uganda,
Zambia, Malawi)
Activities
Implementation of regular and reliable containers rail services from
Dar-es-Salaam to Isaka intermodal platform
Rehabilitation of rolling stock and railway tracks between Dar-es-Salaam and Isaka
Strengthening of railways Institutional framework and regulation, with clear functional separation between infrastructure, operation and regulation .
East Africa Community Transport Corridor Scope of the study: Definition of a Regional Intermodal Strategy and Action Plan to implement an
efficient rail-centric intermodal transport system along the Central and Northern EAC Corridors
Stages:
Review of current operations and state of infrastructure and inter-connections (including ports)
Identification of effective maintenance and operation concepts
Preparation of traffic forecasts, cost estimates and business plan
Environmental and social scoping study
Expected completion: end 2013
III. Additional Opportunities: Planned Energy Projects with
Transformative Impact through Increased Generation 18
Country Hydro developed in last decade
(GW)
Hydro potential in next decade
(GW)
Ethiopia 2.8 8.2
Guinea 0.8 4.3
DRC 1.3 4.0
Sudan 1.4 3.7
Mozambique 0 3.2
Others ~2.2 ~6.6
TOTAL 8.5 30.0
Country IPPs to
date (GW)
Potential
(GW)
Technologies
South Africa 0.6 4.8 Coal, Gas
Nigeria 1.3 2.0 Gas
Botswana 0 1.2 Coal
Kenya 0.2 1.0 Geothermal, oil
Mozambique 0 0.8 Coal, Gas
Others ~0.8 0.8 Coal, Gas, Oil
Next 5-7 years 4.0 Mainly gas
TOTAL 3.1 13.3
Thermal 3.1 GW of thermal
IPPs to date
4 GW potential in next 5-7 years
5 highest potential: South Africa, Nigeria, Botswana, Kenya, and Mozambique
Opportunities in Gas to Power, in particular
Hydro 8.5 GW developed
in last decade 30 GW potential for
next decade 5 highest potential:
Ethiopia, Guinea, DRC, Sudan, and Mozambique
III. Additional Opportunities: Other Planned Energy
Projects with Transformative Impact 19
Power Pools
West Africa Power Pool
Finance key regional interconnection and large generation (e.g. hydro) projects
Support national utilities in project preparation & implementation
TA to WAPP Secretariat for investment planning
Key potential project: Cote d’Ivoire-Liberia-Sierra Leone-Guinea (US$400 m.)
East Africa Power Pool
Finance investments on key system-to-system interconnectors
Capacity building to national utilities
TA to EAPP Secretariat for regional planning and coordination
Key potential projects (US$ million): Kenya National Backbone ($2,400m.); Ethiopia-Kenya ($1,200m.); Zambia-Tanzania-Kenya line (780)
Southern Africa Power Pool
Finance investments on national transmission backbones and key interconnectors
Support national utilities in preparation of key generation expansion projects (Inga)
TA and risk mitigation at national/regional level
Key potential projects (US$ million): Inga-Zambia Interconnector ($655m.); Zambia Backbone ($100m.); Zimbabwe Backbone ($96m.) DRC-Angola (TBD); Mozambique Regional Transmission Backbone ($2,094m.) (Phase I, Stage I)
Central Africa Power Pool : Support early thinking about developing power pool.
Scaling up Energy Access
Major investment in large-scale high impact projects and PRGs for expanding generation base
Efforts to enhanced energy access and on fragile states
Complementary off-grid solutions (Lighting Africa, Clean Cooking)
Continuous policy dialogue to create better institutions/frameworks - can help bring private sector
Enhanced Affordability – reforming tariff structure taking into account the political economy of tariffs
Reducing inefficiencies of supply to reduce costs
Regulatory regimes to provide incentives and penalties
Sustainable business model for the utilities
Key projects: Inga III(DRC- $8,000m.); Lom Pangar (Cameroon -- $460m.); Menengai (Kenya -$850m.); Souapiti (Guinea - $1,000m.); Kaleta (Guinea - $450m.); Cahorra Bassa – North Bank (Mozambique$1,300m.)
IV. Next Steps
High Reward, but not Without Challenges 20
Resettlement/ environmental issues require careful assessments.
Complex financing issues require innovative solutions.
Implementation capacity lacking.
Regional water, energy and transport projects require regional, watershed-wide, power pool-wide cooperation, which has proven difficult.
Bank seen as go-to institution to tackle complex transboundary issues
Lack of adequate knowledge base in some areas at present.
No system for monitoring quality and quantity of freshwater resources to Lake Chad
Need for assessment of impacts of climate change on hydrology for dams
The potential of gas to transform national and regional power markets
The role of mining sector as an anchor customer for energy generation
Strong vested interests oppose reform: e.g. trucking cartels and corrupt officials fight measures to increase competition and reduce barriers to transit.
Poorly understood political economy of reform.
Asymmetrical distribution of benefits from improving transport, especially between landlocked countries and those with sea access.