TRANSPORTATION & HANDLING
OF TRAFFIC MANAGEMENT
ORGANISED BY:
MASTER BUILDERS ASSOCIATION MALAYSIA
TOTAL ROAD ACCIDENTS BY STATES, MALAYSIA,
2016
Source: Transport Statistics Malaysia 2016 by Ministry of Transport Malaysia
Source: Transport Statistics Malaysia 2016 by Ministry of Transport Malaysia
CASUALTIES AND DEATHS CAUSED BY ROAD
ACCIDENTS, MALAYSIA, 2007-2016
Death
Severe Injuries
Minor Injuries
NEWS REPORT
Source: Sinar Harian Source: Utusan Malaysia
TRAFFIC MANAGEMENT• Field of traffic control that involves redirecting and diverting
traffic around any construction area.
• It details the specific plan to implement the project’s Traffic Management Strategy.
• To improve the traffic flow, ease congestion and at the same time, minimizing accidents or other road disruptions during construction.
• Part of precaution measures to ensure the safety of traffic management team, emergency response team, construction workers, pedestrians and drivers.
WHAT IS TRAFFIC MANAGEMENT?
DESIGN PHASE
PRE-CONSTRUCTION
PHASE
CONSTRUCTION PHASE
LANE REDUCTION
• The construction of flyover. Lanes has been reduced from 3 to 2 temporarily to accommodate the installation of column and beam
LANE WIDTH REDUCTION
• The upgrading of existing road from 2 to 4 lanes. Reduction of lane width while maintaining the number of existing lanes to accommodate the upgrading works.
ROAD DIVERSION
• Total road closure for beam launching resulting to road diversion.
WHAT IS TRAFFIC MANAGEMENT?
W.A.R.P
To protect both road users andconstruction workers
To reduce accident rates especiallyalong construction zones
To give advance warning to roadusers approaching construction area.
To avoid undesirable events withinconstruction area
THE IMPORTANCE OF TRAFFIC MANAGEMENT?
MALAYSIA
TRAFFIC MANAGEMENT AROUND THE WORLD
TRAFFIC MANAGEMENT AROUND THE WORLD
SINGAPORE
TRAFFIC MANAGEMENT AROUND THE WORLD
PHILIPPINES
TRAFFIC MANAGEMENT AROUND THE WORLD
AUSTRALIA
TRAFFIC MANAGEMENT AROUND THE WORLD
UNITED STATES
DEFINITION TRAFFIC CONTROL PLAN (TCP) WORK ZONE
TMP refers to a compiled document consisting of method statement of
Traffic Management, work programme, TCP & etc.
Shows the placement of Traffic Control Devices (TCD) according to the construction sequence
Provide information on the types of areas that
will be involved.
WHAT IS TRAFFIC MANAGEMENT PLAN (TMP)?
DESIGN PHASE
DESIGN PHASE
TCP must cover overall project site
TCP must be audited by Road Safety Auditor during the RSA Stage 3 Audit
Road Design Engineers design a conceptual TCP
The Road Authorities or the person/parties carrying out works on the road should
allocate funds for the execution of traffic management at work zones
For the purpose of costing, Consultants and Contractors are to refer to
ATJ 2C/85 (Pindaan 2017)
PRE-CONSTRUCTION
PHASE
THE DESIGNING OF TMP
ATJ 2C/85 (PINDAAN 2017)
- Urban Road
- Rural Road
MANUAL FOR TMP DESIGN
Lembaga Lebuhraya Malaysia (LLM)
- Highway Road
MANUAL FOR TMP DESIGN
SAMPLE
TRAFFIC CONTROL PLAN (TCP)
MENAIKTARAF LALUAN B49
PERSIARAN MOKHTAR DAHARI
DAERAH PETALING, SELANGOR
DARUL EHSAN
STAGE 1
STAGE 2
STAGE 3
STAGE 4
OBTAINING APPROVAL FROM AUTHORITY
CONSTRUCTION
PHASE
PERSONNEL TMT / ERT TEAM TRAFFIC CONTROL DEVICES (TCD)
Traffic ManagerTraffic Management Officer
Traffic SupervisorTraffic Controller
Flagman
The teams involved during implementation are Traffic Management Team (TMT) and Emergency Response
Team (ERT)
Temporary signboards, cones, barriers, blinkers &
etc.
THE IMPLEMENTATION OF TMP
THE IMPLEMENTATION OF TMP
02
03
04
05
• Contractors’ Representative
• Fully responsible for the safety of road users who are within the
limits of the working area
• Record of equipment deficiencies, losses and defects
• Ensure that all equipment is sufficient before work is carried out
• Patrol and check the traffic conditions and all available facilities on
the road
• Maintain all traffic equipment.
• Controls and ensures access to the project site area is in good
condition
01• Contractors’ Representative
• Responsible for the whole team
TRAFFIC MANAGEMENT PERSONNEL
Implementing the TrafficManagement Plan whichhas been duly approvedand ensured the safety ofcontractors and road usersduring construction work.
TRAFFIC MANAGEMENT TEAM (TMT)
Addressing emergencysituations such asaccidents or naturaldisasters that may occurwhen performing specificwork activities involvingclosure of roads and otherrelated traffic managementworks.
EMERGENCY RESPONSE TEAM (ERT)
TMT/ERT VEHICLE
EXAMPLE FLAGMAN SAFETY OUTFIT
TRAFFIC CONTROL DEVICES
PLASTIC BARRIER
CONCRETE BARRIER
PLASTIC HOARDING
PLASTIC CONE
TRAFFIC CONTROL DEVICES
BLINKERS STRING DELINEATOR GENSET
ARROW FLASHER SPOTLIGHT
MATERIAL FOR TEMPORARY SIGNBOARD
3M Diamond Grade Reflective Sheeting (H.I.P)
AVERY T-6000 High Intensity Prismatic
Fluorescent Orange – AVERY
Fluorescent Orange – 3M
MATERIAL FOR TEMPORARY SIGNBOARD
STANDARD SPECIFICATION FOR TCD
JKR/SPJ/2017-S19
CURRENT ISSUES
Inadequate TCD
Inappropriate signage
Lack of maintenance
Not enough workers
Lack of safety auditing of work zones
POSSIBLE SOLUTIONS
The Road Authorities and
Supervising Engineers must review TMP to
ensure best practice are
implemented and optimum materials
used
New additions to the Standard Specifications
must be strictly implemented
Constant checks to the work zones