Transportation Investment ActProgram Delivery Committee
Kenneth Franks, State TIA Administrator
TIA Regions
River Valley HOGA
CSRA
Southern Georgia
TIA Timeline
First 6 Years of TIA
521 Projects Advanced to Construction
Revenue Collections by RegionRegion Total Approved
Investment List (75%)Local Discretionary
(25%)
CSRA $376,616,735* $282,462,551* $94,154,184*
River Valley $262,398,229* $196,798,671* $65,599,557*
HOGA $166,376,723* $124,782,542* $41,594,181*
Southern Ga $0.00 $0.00 $0.00
Totals(*rounded amounts)
$805,391,687 $604,043,764 $201,347,922
TIA 2018 Highlights
95TIA Projects Let to Construction in 2018
66TIA Projects Completed 2018
$75,459,582TIA Program Expenditures in 2018
CSRA Project Overview84
Total Projects
$538,965,884Final Investment List
Project Total
16In Construction
40Projects Completed
$160,234,172Total Expenditure to Date
(as of 11.13.18)
Wilkes Lincoln
Richmond
Columbia
BurkeJefferson
Jenkins
Hancock
Washington
Warren
Lewiston Road at I-20 Interim Improvement
Lewiston Road at I-20 Interim Improvement
HOGA Project Overview
764Total Projects
$255,524,067Final Investment List
Project Total
12In Construction
439Projects Completed
$89,634,894Total Expenditure to Date
(as of 11.13.18)
Johnson
Emanuel
Wayne
Evans
Tattnall
Candler
ApplingJeff
Davis
Telfair
Dodge
Wilcox
Laurens
HOGA Project Status
Vidalia Projects
River Valley Project Overview
Harris Talbot
Taylor
Macon
Dooly
Crisp
Sumter
Randolph
Stewart
Marion
Schley
23Total Projects
$380,828,512Final Investment List
Project Total
7In Construction
7Projects Completed
$117,177,263Total Expenditure to Date
(as of 11.13.18)
Lake Blackshear
Southern GA Project Overview151
Total Projects
$408,763,452Final Investment List
Project Total
Band 184 ProjectsBand 2
34 ProjectsBand 3
33 Projects
ATKINSON
BENHILL
BERRIEN
CHARLTONCLINCH
COFFEE
COOK
ECHOLS
IRWIN
PIERCETIFT
WARE
Southern GA Timeline
Southern GA Citizen’s Review Panel
Mr. Walter HudsonIrwin County
Mr. Patrick JonesWare County
Mr. D.W. HarperIrwin County(CRP Vice-Chair)
CommissionerRobert GrinerBerrien County
Chairman Bill SlaughterLowndes County
(CRP Chairman)
Southern GA ProjectsProject Type # of Projects
Resurfacing/ Paving 94Bridge 14Safety/ Operations 13Sidewalks 13Widening/ Passing Lanes 10Airport 4Interchange 2New Roadway 1
TIA 2019 Highlighted Projects• CSRA-Flowing Wells Road widening in Columbia Co. ($20M)• CSRA-SR4/15th St. Widening in Richmond Co. ($21M)• HOGA-Hillcrest Parkway widening in Laurens Co. ($17.5M)• HOGA-SR 135 over the Altamaha River Montgomery and Jeff Davis
($7M)• RV-SR 1/US 27 Harris Co. NB Passing Lane ($2.9M)• RV-Buena Vista Road Interchange Muscogee Co. ($47M) • RV-Buena Vista Road Intersection(Spider Web) ($40M)• SG-I-75 @ SR 31 (Exit 11) Interchange Recon. Lowndes Co.
($19.5M)• SG-Ware Street Resurface & Minor Widening Pierce Co. ($2.6M)• SG-Clinch Co. Resurfacing Bundle ($2.5M)
The TIA Office
Kenneth FranksTIA Administrator
(404) [email protected]
Brent MoseleyTIA Regional Coordinator
SG & HOGA(912) 661-7157
William EastinTIA Regional Coordinator
River Valley & SG(404) 631-1810
Eric WilkinsonTIA Regional Coordinator
CSRA, HOGA, & SG(478) 538-8522
www.ga-tia.com
Questions?
SUMMER 2019