08/03/2020
1
Trenchless rehabilitation of 96” combined sewer
Brian Shiels, PE
Project Manager
Iselin, NJ
Jersey City Municipal Utilities Authority Phase 3-4 Sewer Rehabilitation
Introduction The ProjectConsider design alternatives
Summary
Presentation overview
08/03/2020
2
• Serves 250,000 residents
• 230 miles of sewers
The client
08 March 2020Mott MacDonald | ECP/Emerging Leader Showcase 3
Jersey City Municipal Utilities Authority
• 5,000+ Catch Basins
• Under an Administrative Consent Decree
The Project
Approximately
12,000 linear feet of open cut replacement
30,000 linear feet of cleaning and CIPP Lining
All around Jersey City
Port Authority Jurisdiction (Holland Tunnel)
08 March 2020Mott MacDonald | Presentation 4
JCMUA Phase 3-4 Sewer Rehabilitation
08/03/2020
3
Interested Parties
Contractor & Subcontractor
JCMUA
JC police
City of Jersey City
NJDOT
NJ Turnpike Authority
PANYNJ
NJ I-Bank
Residents
08 March 2020Mott MacDonald | Presentation 5
The Holland Tunnel approach
08/03/2020
4
Preliminary investigations
Cleaning and assessment
Consider design alternatives
Rehabilitate 96” steel pipe
Project stepsAccess Agreement and approvals from the various Authorities
Preliminary Investigations
08/03/2020
5
The 96-inch pipe
Cleaning and Assessment
08/03/2020
6
CleaningNJDOT Utility Opening Permit
Access Pit Under Rt 139
The 72” access pit
08/03/2020
7
Safety
Consider Design Alternatives
08/03/2020
8
Rehabilitation design challenges
08 March 2020Mott MacDonald | Presentation 15
Corrosion Corrosion
Obstructions / Corrosion
Steel Pipe Corrosion / Pitting
Traffic
Pipe Material
Pipe condition
Time Restrictions
Sags
Design alternativesRehabilitation of 2,400 LF of 96-inch riveted steel combined sewer pipe
1Guniting (original design)
2Geopolymer(spincastapplication)
3CIPP lining (field wet-out)
4Slip lining
5Open cut installation
08/03/2020
9
Styrene Free
08 March 2020Mott MacDonald | Presentation 17
Gunite vs. Geopolymer
Sample photo from Milliken Infrastructure
Guniting
Unit Cost = $ 1,250 per LF
2,400 LF => $ 3,000,000
Coating Removal ~ $600,000
Total = $ 3,600,000
08 March 2020Mott MacDonald | Presentation 18
Cost Comparison of Two alternatives
CIPP Lining
Unit Cost = $ 1575.00 per LF
2,400 LF => $ 3,780,000
Traffic Control $ 180,000
Inversion Access Area Rehab $ 52,000
Total = $ 4,012,000
08/03/2020
10
Rehabilitate 96-inch Steel Pipe
08/03/2020
11
Cutting access for liner
Prepping the CIPP liner
08/03/2020
12
More prep photos
Creating a vacuum
08/03/2020
13
Opening Pores / Beat the liner
08 March 2020Mott MacDonald | Presentation 25
Improve resin circulation
Resin
08/03/2020
14
Resin and catalyst
Verify mixture & dye
08/03/2020
15
Elevating the liner
Water
Wet-out/Inversion ~ 240,000 gallons
(3 days continuous)
Tail End Phase ~ 240,000
(8-10 hours)
Cool Down Phase ~ 240,000
(10-12 hours)
08/03/2020
16
Tent cover
CIPP lining (pre-liner)40-52.9 mm (1.57-2.08 in)
08/03/2020
17
08 March 2020Mott MacDonald | Presentation 33
Backstop
Prevent end of liner from over stretching or opening
08 March 2020Mott MacDonald | Presentation 34
08/03/2020
18
Finished Product
Value for client
Design Life
Cost
Minimize motorist interruption
Thank you
Brian Shiels, PE