18
08/03/2020 1 Trenchless rehabilitation of 96” combined sewer Brian Shiels, PE Project Manager Iselin, NJ Jersey City Municipal Utilities Authority Phase 3-4 Sewer Rehabilitation Introduction The Project Consider design alternatives Summary Presentation overview

Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

1

Trenchless rehabilitation of 96” combined sewer

Brian Shiels, PE

Project Manager

Iselin, NJ

Jersey City Municipal Utilities Authority Phase 3-4 Sewer Rehabilitation

Introduction The ProjectConsider design alternatives

Summary

Presentation overview

Page 2: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

2

• Serves 250,000 residents

• 230 miles of sewers

The client

08 March 2020Mott MacDonald | ECP/Emerging Leader Showcase 3

Jersey City Municipal Utilities Authority

• 5,000+ Catch Basins

• Under an Administrative Consent Decree

The Project

Approximately

12,000 linear feet of open cut replacement

30,000 linear feet of cleaning and CIPP Lining

All around Jersey City

Port Authority Jurisdiction (Holland Tunnel)

08 March 2020Mott MacDonald | Presentation 4

JCMUA Phase 3-4 Sewer Rehabilitation

Page 3: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

3

Interested Parties

Contractor & Subcontractor

JCMUA

JC police

City of Jersey City

NJDOT

NJ Turnpike Authority

PANYNJ

NJ I-Bank

Residents

08 March 2020Mott MacDonald | Presentation 5

The Holland Tunnel approach

Page 4: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

4

Preliminary investigations

Cleaning and assessment

Consider design alternatives

Rehabilitate 96” steel pipe

Project stepsAccess Agreement and approvals from the various Authorities

Preliminary Investigations

Page 5: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

5

The 96-inch pipe

Cleaning and Assessment

Page 6: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

6

CleaningNJDOT Utility Opening Permit

Access Pit Under Rt 139

The 72” access pit

Page 7: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

7

Safety

Consider Design Alternatives

Page 8: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

8

Rehabilitation design challenges

08 March 2020Mott MacDonald | Presentation 15

Corrosion Corrosion

Obstructions / Corrosion

Steel Pipe Corrosion / Pitting

Traffic

Pipe Material

Pipe condition

Time Restrictions

Sags

Design alternativesRehabilitation of 2,400 LF of 96-inch riveted steel combined sewer pipe

1Guniting (original design)

2Geopolymer(spincastapplication)

3CIPP lining (field wet-out)

4Slip lining

5Open cut installation

Page 9: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

9

Styrene Free

08 March 2020Mott MacDonald | Presentation 17

Gunite vs. Geopolymer

Sample photo from Milliken Infrastructure

Guniting

Unit Cost = $ 1,250 per LF

2,400 LF => $ 3,000,000

Coating Removal ~ $600,000

Total = $ 3,600,000

08 March 2020Mott MacDonald | Presentation 18

Cost Comparison of Two alternatives

CIPP Lining

Unit Cost = $ 1575.00 per LF

2,400 LF => $ 3,780,000

Traffic Control $ 180,000

Inversion Access Area Rehab $ 52,000

Total = $ 4,012,000

Page 10: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

10

Rehabilitate 96-inch Steel Pipe

Page 11: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

11

Cutting access for liner

Prepping the CIPP liner

Page 12: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

12

More prep photos

Creating a vacuum

Page 13: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

13

Opening Pores / Beat the liner

08 March 2020Mott MacDonald | Presentation 25

Improve resin circulation

Resin

Page 14: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

14

Resin and catalyst

Verify mixture & dye

Page 15: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

15

Elevating the liner

Water

Wet-out/Inversion ~ 240,000 gallons

(3 days continuous)

Tail End Phase ~ 240,000

(8-10 hours)

Cool Down Phase ~ 240,000

(10-12 hours)

Page 16: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

16

Tent cover

CIPP lining (pre-liner)40-52.9 mm (1.57-2.08 in)

Page 17: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

17

08 March 2020Mott MacDonald | Presentation 33

Backstop

Prevent end of liner from over stretching or opening

08 March 2020Mott MacDonald | Presentation 34

Page 18: Trenchless rehabilitation of 96” combined sewer Annual...Mott MacDonald | Presentation 17 08 March 2020 Gunite vs. Geopolymer Sample photo from Milliken Infrastructure Guniting Unit

08/03/2020

18

Finished Product

Value for client

Design Life

Cost

Minimize motorist interruption

Thank you

Brian Shiels, PE

([email protected])