Upload
others
View
12
Download
0
Embed Size (px)
Citation preview
TRENT GLOBAL UNIT 4: SITE ESTABLISHMENT & PROCUREMENT
• UNIT 4: SITE ESTABLISHMENT AND PROCUREMENT
• 4.1 INTRODUCTION
• 4.2 SITE OBLIGATIONS – LAYOUT AND ENABLING WORKS
• 4.3 PRE CONTRACT COMMENCEMENT
• 4.4 SITE MANAGER’S DUTIES
• 4.5 SITE DOCUMENTATIONS AND FORMS
• 4.6 SITE PROCUREMENT
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• 4.1 Introduction.
• As there are too many variables and unpredictability, no single project is
the same. Different factors result in different time frame, cost, quality and
productivity conclusions. All the management skills in the world will be
incapable of bailing a construction project if methods were wrongly
conceptualized and planned from the beginning.
• 4.2 Site Obligations – Layout and Enabling Works.
• Site visit is important to have first hand assessment of constraints and restrictions that
may affect your planning and layout. A poor layout can cause problems like inadequate
space for staging, storage and the use of certain construction methods.
• Other considerations include verifying access roads, utilities availability in the immediate
vicinity and also the type of neighbours (eg schools will result in some disruption to
working hours during examination period.)
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• Environmental factors such as drainage, groundwater and possibility of floods can also be
detrimental to site progress. Another concern is the presence of hazardous material
which requires costly leaning up procedures.
• Some common Site Facilities to be catered for:
• a) Site Safety, Health and Welfare – a sound knowledge of various Factories Acts and
Work Rule Agreement is essential and the site manager has to ensure strict adherences.
Welfare can range from provision of clean sanitary facilities, regular waste disposal and
housekeeping to a comfortable workers’ mess as well as recreational facilities.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• b) Site Administration and Security – normally included in project’s overheads. Although
supporting roles they are just as critical in the smooth running of the project. Vandalism
and trespass are common problems. So security will ensure that the site is secure
throughout the active construction duration. Fenced compound will require gates and
sometimes cctv surveillance. Though cost of security is high, it may be balanced against
wastage, damage, theft, loss and delay.
• c) Legitimacy and Competence of all Workmen – some countries like S’pore has
statutory bodies to strictly govern and ensure those recruited are of a specified level of
skill or trade through accredited certifications. These workers have to carry their original
work permit at all times on site. Any infringement of employing illegal workers may result
in hefty fines and imprisonment to Company’s top management.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• d) Plant and Equipment – while a checklist reduces the risk of omission, attention
should be paid to ancillary items, essential accessories and components that
enable the plants to perform efficiently. Location of plants and storage are also
critical and considerations given during planning so as to maximize its running
efficiency.
• e) Scaffolding – may be examined under the headings of external and internal
works and in full compliance with statutory requirements. Installation must be
done by registered contractor and erectors. Mobilization and installation must be
incorporated into the schedule.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• f) Protection against Inclement Weather – where heavy rainfall is a norm, additional
waterproofing measures in the forms of temporary or portable shelters, waterproofed
sheeting have to be stored and prepared for use, to protect against water ingression.
• g) Water Supply – the availability of temporary water and its proximity is critical for all site
operations. Where necessary inquiries should be made with the authorities on its charges and
availability. (likewise waste discharge is just as important)
• h) Lighting and Electrical supply – like water, electrical requirements and its capacity in
relation to the allowed plants on site must be carefully planned. Similarly its availability and
charges need to be checked with the Authority. A LEW (licenced electric worker) has to be
appointed to certify the fitness of the installation.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• i) Temporary Access – site access is critical as it affects mobility and may delay progress
throughout the duration of the project. This applies to site entrance as well as access
within the site. Provision of multiple entrances/ exits will ease congestion but at the
expense of more wash bays and security. The type and quality of the internal access must
also be considered so as to ensure the smooth and efficient traffic flow with in the site.
For eg a mud laden access will require a longer washing time at the exit; Temporary
concrete though costly will enhance the neatness of the site and reduces travelling time
and exits quickly.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• j) Temporary Site Accommodation and Store – usually located far away from public view
and where necessary netting are used to shield them. Provision of well racked general
store sheds, allocation of open storage areas and secured storage on site, is important
and necessary for proper stock-keep, maintenance and its security.
• k) Temporary Communications and Computing Facilities – subject to contract
requirements, Contractor must furnish accordingly including temporary phone , facsimile,
internet connections as well as basic computer set-ups including all peripheral support
equipment.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• l) Temporary Traffic Diversions and Signage – traffic problems and requirements vary in
accordance with location (whether it is city or rural area). In accordance to local traffic
regulations and in consideration of the locality of the site and its access, the Contractor
needs to plan such that it does impede the existing traffic flow and to enhance localized
traffic safety with approved safety barriers, signage, lighting etc.
• m) Temporary Hoardings, Protective Barriers, Screens etc – temporary fencing may be
part of security hoardings, screens etc. Others like covered walkways, screens
(sometimes sound barriers) are all part of Site facilities under the obligation of the
Contractor.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• n) Planning of Site Routines - obligated to plan before site establishment. These include
delegating of minuting of site meetings, cleaning of washrooms, plant maintenance, store
accountability. Routine will be flexible to allow for varying conditions and the appointed
shall be responsible and accountable.
• o) Procedure in Cases of Emergency - contingency and considerations can range from
escape routes, fire assembly points, location of nearest telephone, emergency contact
numbers, location of nearest medical facility, after hour contact number, telephone
number of local police station etc.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• 4.2.1 General Site Layout
• Site layout is commonly divided into “administrative” and “construction” zones.
• 1) Administrative Zone – includes store, offices, subcontractors’ huts, canteen,
accommodation. Located with quick access to site for control reasons. Ease of
connectivity of telephone facilities, electricity for power, compressed air, lighting and
heating facilities, water supply and waste disposal. Careful planning is required to
minimize the need to move the administrative area during the contract period.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• 2) Construction Zone – includes the actual site of the building being constructed,
materials and equipment. Positioned to minimize the time for handling and movement.
Areas need to be properly identified to avoid the possibility of dumping materials in the
wrong position and hence double handling.
• With this in mind, basic planning considerations are as follows:
• a) Site Conditions and Access – will limit the type of plant to be used; wet sites need to
use tracked machines in the case of excavators and mobile cranes; for sloped sites the
use of rail mounted cranes not feasible; confined sites – insufficient room for a mixer or
mixing plant; site close to adjoining building need the use of a derricking jib.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• b) Nature of Job – different types of structures and form, size and detailing will have
effect on the way the contract is planned. It will also influences decisions on the type of
equipment and material to be used.
• c) Plant – General considerations include its capabilities, limitations, outputs, maintenance
frequency and cost:
• Excavation – type of excavation to be carried out, nature of soil to be excavated, volume and
depth of soil to be excavated, haulage distance.
Handling – quantity and type of materials to be handled, degree of Tower Crane utilization,
weight of materials, avoid double handling, siting of plant in relation to building.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
Mixing – Quality and quantity required; site conditions; cost comparisons among
various methods.
Type of Plant – Nature of job, sequence of work, method of construction, amount
of work, cost of equipment and running cost.
• d) Design Factors – simplicity of construction and detailing; separation of
trades; phasing of works; continuity of works.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• 4.3 Pre- Contract Commencement
• Assuming that all essential documents such as site plans, organization charts, method
statements etc have all been finalized, then the focus should be on physical establishment of a
site, with selection of common temporary works, plants and equipment.
• Upon receipt of Letter of Award, the contractor will depart from post-tender phase and begin
pre-contract stage. Good planning will enable the site to be smoothly run throughout the
duration of the project and reduces unnecessary cost arising from double-handling, shifting
etc.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• 4.4 Site Manager’s duties
• Upon accepting the position, he must be prepared to accept full responsibility for
everything that takes place on site, both directly and indirectly. It is essential that he is
given the authority to implement his responsibility.
• The individual has to be empowered as a Site Manager (sometimes known as Site Agent,
Project Manager or Construction Manager) who shall represent, act and decide for and
on behalf of the Contractor.
• He shall ensure that all notifications and applications are made to relevant contract
parties and statutory authorities prior to contract progress.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• Other duties include conceptualise in house plans, detailed project schedules, method
statements, procurement strategies, statutory submissions (safety, permits, Factories acts
etc);
• Thorough clarifications must always be sought to resolve possible ambiguities arising
from contract documents.
• It may be common to embark on a project without timely confirmations of material,
methods of construction, approved location of site office and facilities. Hence the SM’s
duties is to resolve and upon all the pending issues that will affect construction progress
soonest possible.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• 4.5 Site Documentation and Forms
• It is always important to have proper documentation for tracability, ISO
compliance, future disputes whether contractual or otherwise. So a proper
documentation set up has to be established upon site possession and a
comprehensive archive for future benchmarking.
• The Site Manager has to outline the various paperwork and templates commonly
used and required by his Company and tailor a system that suits the project
efficiently and safely.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• Some common documents:
• Plans and assessments – such as Health and Safety Plans or Policy; others
include Project chronological schedules, site rules and regulations, method
statements, assessments (risk), checklist and inspection forms, site dairy,
training records, minutes of meeting, visitors book, drawing registry,
licences and permits.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• 4.6 Site Procurement
• Any ordering must be done competitively and systematically. Normally the
QS is responsible for organizing the sub-contract and the Procurement
Dept (normally in Head office) will arrange in accordance to site
requirement. Sometimes loose tools are ordered by site team but if not
properly controlled, it can be a large amount. So it desirable to be
centralized in the head office.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• 4.6.1 The Organisation
• Staff recruitment – unlikely that the Company can fill all the positions through internal
transfer; so options include recruitment company, self recruit of permanent staff or short
term contract staff. The final choice depends on the Company’s short or long term
planning and industry’s economic demands.
Key skills that Managers look for are knowledge and authority, experience and
personality. Appropriate recruitment is a key factor to the success of the project but it
must be done within the available budget..
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• Labour recruitment – very rarely will a Company be able to keep a permanent labour
force employed and available when needed on a construction site. Notwithstanding the
Company’s sub-contracting policy there will always be a requirement for workmen to be
recruited.
As it is a short term nature of the work, many labourers will have experienced being laid
off frequently and this leads to cynicism and disloyalty. Recruiting new labour will
probably require a time frame for familiarization. Hence most prefer to recruit those
who are already employed so as to operate the site safely and efficiently. The use of
agency is common but their workers may not necessary suitable.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• 4.6.2 Site Procurement
• Site Buying – Plant and material are routinely procured on site with the orders going
through the Head office. So it is critical that the requisitions are clearly specified with the
site requirements set down in the Company’s procedures. Often the site team are in a
better position to negotiate the project specific items of plant or materials and the office
is used as a checking process to confirm that the selected item is money for value and
within allowable cost in the tender. For some items some bulk purchase across few
projects allow a better bargaining advantage by the head office. (sample form on pg 66)
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• Sub Contract Orders – normally done through a combination of head office and site. The
contracts dept will normally asked for quotations and then individually assessed through
interviews and cost comparisons. Important point to note is the exclusions and
attendances in their quotations which are actually converted into financial consequences.
This is where site team participation in interviews are critical.
• Procurement Controls – All site buying must be supervised by the Head office with
checks and controls preventing the site placing orders that are not sanctioned.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL
• Procurement Issues – Most site procurement is undertaken in conditions that are far
from ideal. The site staff are under pressure to deliver the project on time, on budget and
to the necessary safety, quality and sustainability requirements. Often procurement are
condensed to match the site programme and often insufficient time is allocated for
sourcing. All too often orders are not placed with the most cost effective provider
because he cannot meet the programme or delivery schedule.
TRENT UNIT 4: SITE ESTABLISHMENT & PROCUREMENT GLOBAL