19
Tri - Lateral Monitoring Systems Audit NTMWD Angela Kilpatrick - Trinity River Authority Allen Pappas Previously of Red River Authority TCEQ CRP FY2017 Statewide Partner Meeting September 285, 2016

Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

Tri-Lateral Monitoring Systems Audit – NTMWDAngela Kilpatrick -Trinity River Authority

Allen Pappas – Previously of Red River Authority

TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016

Page 2: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

Presentation Overview

• What is Sub-Participant Oversite?

• A Unique Situation

• The Tri-Lateral Monitoring Systems Audit Approach

• Outcomes

Page 3: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

What is Sub-Participant Oversight?

Basin Planning Agencies are required to oversee the activities addressed in their QAPPs and must conduct formal

audits of all sub-participants who conduct field monitoring. If all work is

performed by the Basin Planning Agency (i.e. there are no sub-

participants participating in the Basin’s CRP program), these audits are not required. Negotiate the timing and scope of oversight activities, and

document in the QAPP.

Page 4: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

What is Sub-Participant Oversight?

• There are two acceptable types of sub-participant field monitoring audits:

• readiness reviews, and • monitoring systems audits.

• Perform at least one audit at the sub-participant’s office, field station, or other appropriate location at least once during each contract cycle (biennium), in the case of on-going projects; or once during a project’s lifetime, in the case of short-lived special studies.

Page 5: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

A Unique Situation

• Historically, the North Texas Municipal Water District (NTMWD) had been in one (1) CRP QAPP

• Beginning in FY2016-17, NTMWD had interest in conducting CRP monitoring in multiple river basins, and multiple QAPPs including:

• Red River Authority of Texas• Trinity River Authority• Sulphur River Basin Authority

Page 6: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

A Unique Situation

• Based on current TCEQ CRP Task 2 Guidance, each of the three (3) river authorities should have conducted some form of “sub-participant oversight”:

• TRA / SRBA – Readiness Review• RRA – Monitoring Systems Audit

• High duplication of effort and potential for other negative ramifications:

• Differences in how the audit(s) were conducted• Differences in finding(s) from audit(s)• Administrative burden could create delays in data

collection

• Tri-Lateral MSA approach

Page 7: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

Tri-Lateral MSA Approach

Pre-Audit• Conference call to discuss Tri-Lateral

approach • TCEQ CRP Project Managers• TCEQ CRP Quality Assurance• River Authority Project Managers

• Developed a plan• Pre-Audit / Audit / Post-Audit

• Assigned “Lead Partner Role”• Red River Authority• Responsible for organizing MSA and

“represented” CRP Partners to simplify paperwork

Page 8: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

Tri-Lateral MSA Approach

Pre-Audit• NTMWD was contacted to inform them of

the Tri-Lateral approach

• NTMWD was notified by the “Lead Partner” in writing of the MSA

• All CRP partners were included on the letter and CC’d when documents were emailed to NTMWD

• Conference call to discuss how to handle the actual audit when on-site

• Areas of interest• Documentation needs/wants

Page 9: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

Tri-Lateral MSA Approach

Audit Process• Entry meeting amongst staff to discuss

scope, intent and goals of the MSA and to outline the proposed MSA schedule

• TRA representative• SRBA representative• RRA representatives• NTMWD representatives

• Discuss any questions/concerns before beginning

Page 10: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

Tri-Lateral MSA Approach

Audit Process• Reviewed at NTMWD Facility:

• Review of previous findings• Sample receiving and storage• Bacteriological sample analysis• Document control / record keeping• Sonde calibration (pre/post), calibration

records, maintenance• Sample containers (prep/storage/cleaning)

• Reviewed in the field:• Mock event to include all aspects of data

collection (field measurements, flow, sample collection so forth)

Page 11: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

Tri-Lateral MSA Approach

Audit Process• Exit meeting amongst staff to discuss the

MSA report/response process:• TRA representative• SRBA representative• RRA representatives• NTMWD representatives• NTWMD management

• All potential findings were discussed

• Discuss any questions/concerns before departing

Page 12: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

Tri-Lateral MSA Approach

Post-Audit• Audit findings and documentation was

compiled by “Lead Partner” and distributed to all partners and TCEQ

• Additional information/notes from partners was compiled into a final document and findings were prepared

• Findings were submitted to TCEQ for review

Page 13: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

Tri-Lateral MSA Approach

Post-Audit• Once findings were approved by TCEQ and

all partners/TCEQ agreed with MSA report, NTMWD was notified

• This process was greatly hindered due to the nature of one particular finding (flow measurement method/procedure)

• This finding was discussed at length between partners and TCEQ which led to the report being delayed

• Initial report was sent to NTMWD on 11/04/15

• Approximately 43 days after MSA was conducted

Page 14: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

Tri-Lateral MSA Approach

Post-Audit• NTMWD responded on 12/18/15

• Approximately 45 days after the MSA report

• This was largely impacted by two factors:• There was still ongoing discussion amongst

partners, NTMWD and TCEQ regarding the audit finding related to flow measurement method/procedure

• NTMWD was concerned about data-loss impact on affected parameter codes for data that had already been submitted/accepted by TCEQ

Page 15: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

Tri-Lateral MSA Approach

Post-Audit• After much discussion a revised MSA

report was sent to NTMWD on 01/26/16 (40 days)

• NTMWD responded on 02/19/16 (25 days)

• After much discussion, the audit was closed on 03/21/16 (32 days)

• The audit process lasted approximately 181 days since the actual MSA was held on 09/23/15

Page 16: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

Tri-Lateral MSA ApproachInitial

Discussion with TCEQ

Conference Call

Conference Call

Audit Notification

09/01/15

Tri-Lateral MSA 09/23/15

MSA Report 11/04/15

Audit Closure 03/21/16

NTMWD Response 12/18/15

Finding Discussion

Response Discussion

NTMWD Response 02/19/16

Response Discussion

Revised MSA Report

01/26/16

Page 17: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

Outcomes

Positive Outcomes of the Tri-Lateral Approach• Prevented a “duplication of effort”• Reduced the administrative burden of CRP

on NTMWD• Ensured uniformity across CRP partners

Negative Outcomes of the Tri-Lateral Approach• Is very time intensive which can be difficult• Input from multiple partners slows the

process down• Audit findings impact participating partners

very differently

Page 18: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

OutcomesPotential considerations going forward:• Consider revising TCEQ CRP Task 2 Guidance to clarify

scenarios that justify and/or require additional MSA activities in the same biennium

• Consider revising TCEQ CRP Task 2 Guidance to add language detailing the suggested audit process for sub-participants in multiple QAPPs

• Consider revising TCEQ CRP Task 2 Guidance to include addendums with example audit documents (audit notification, comment matrix, so forth)

• Consider revising the Monitoring Systems Audit Checklist to accurately reflect current field practices and TNI Standards

• Consider revisions to the SWQM Procedures Manual

Page 19: Tri-Lateral Monitoring Systems Audit – NTMWD · 2016. 12. 1. · TCEQ CRP FY2017 Statewide Partner Meeting – September 285, 2016. Presentation Overview • What is Sub-Participant

Questions?

Angela KilpatrickTrinity River [email protected]