Upload
robert-wilonsky
View
224
Download
0
Embed Size (px)
Citation preview
7/28/2019 Trinity Trail Update.pdf
1/18
7/28/2019 Trinity Trail Update.pdf
2/18
7/28/2019 Trinity Trail Update.pdf
3/18
Trinity Trails Network Update
Trinity River Corridor Project Committee
June 10, 2013
7/28/2019 Trinity Trail Update.pdf
4/18
Purpose
The Purpose this briefing is to provide anoverview of:
Current status of the Trinity Trails Network
Optional alignment of All Weather Joint UseMaintenance Road / Trinity Floodway Trails
Future priorities for expanding the trailsystem
2
7/28/2019 Trinity Trail Update.pdf
5/18
Trinity Trails NetworkBackground Trinity Trails Network is a subset of the
Citys Trail Network System
Extends from Royal Lane near Luna in theNorth to I20 & Dowdy Ferry in the South
Hard surface trails 62.7 miles planned(7 miles in service)
Soft surface trails 15.5 miles in service
3
7/28/2019 Trinity Trail Update.pdf
6/18
Elm Fork Greenbelt Trails
4
7/28/2019 Trinity Trail Update.pdf
7/18
Trinity Floodway Trails
Trinity TrailsTiger V Application
Distance: Approx. 9 miles(Bachman Lake to Sylvan)
Trinity TrailsComplete
Distance: Approx. 1 mile(Santa Fe Trestle Trail to I35E)
Trinity TrailsFunded
Distance: Approx. 3 mile(I35E to Sylvan)
Margaret McDermott Bridge
Trinity TrailsPlanned
Distance (Approx. 10miles)
5
7/28/2019 Trinity Trail Update.pdf
8/18
Trinity Forest Trails
6
7/28/2019 Trinity Trail Update.pdf
9/18
Audubon to
ArboretumTrail
7
Audubon to
Arboretum
Trail
7/28/2019 Trinity Trail Update.pdf
10/18
Trinity Floodway Trails
2012 Bond Program included $6,418,400for design & construction of TrinityFloodway Trails
Design activities in FY12-13
- Consultant award planned for August
Construction activities in FY14-15
Construction would follow the Corps
Environmental Impact Statement for the BalancedVision Plan (EIS)
EIS estimated to be complete in August 14
8
7/28/2019 Trinity Trail Update.pdf
11/189
2012 Bond Program Alignment
7/28/2019 Trinity Trail Update.pdf
12/18
Proposed Alignment for All Weather JointUse Maintenance Road / Trinity FloodwayTrails
To advance this trail ahead of the Corps EIS,
the 2012 Bond Program proposed alignmentcould be modified and constructed as an all
weather joint use maintenance road for: Maintenance trucks and other equipment
Pedestrians
Cyclists
10
7/28/2019 Trinity Trail Update.pdf
13/18
Maintenance Roads
11
7/28/2019 Trinity Trail Update.pdf
14/18
Culvert Crossings
12
7/28/2019 Trinity Trail Update.pdf
15/18
Optional Alignment for All Weather Joint UseMaintenance Road / Trinity Floodway Trails
Connects the existing delineator near IH 35 toSylvan Avenue
Avoids existing and proposed wetlands
Utilizes existing culvert crossings
Approximately 16 feet wide
In some locations, the width increases to 18-21 feet
to accommodate line of sight concerns and culvertcrossings
Culvert crossings will include 42min. railing
for safety of the pedestrian and cyclist
13
7/28/2019 Trinity Trail Update.pdf
16/18
Benefits of Optional Alignment
Does not require additional permits from theCorps, expediting the schedule by approximately12 months
Facilitates maintenance and levee surveillancefor operations especially during wet conditions
Construction could begin this summer becausedesign would be done by staff
Cuts down on dust
14
7/28/2019 Trinity Trail Update.pdf
17/18
Constraints of Optional Alignment
Does not include separation between all users
Roadway will require more maintenance thantypical trails due to location and uses
Long term, paving the existing maintenanceroad and a separate trail should be constructed.Funding is currently available for only one of
these.
15
7/28/2019 Trinity Trail Update.pdf
18/18
Optional Schedule IF the All WeatherJoint Use Maintenance Road/Trinity
Floodway Trails is built.
Complete in-house design July/August2013
Begin construction August 2013
16