Truck set-up scheduling for the Elgin, IL facility

Vijay Viswanathan, Graduate StudentDr. Jaejin Jang, Associate Professor

Department of Industrial Engineering

Page 2: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Overview of Presentation

• Introduction• Detailed Problem Description• Objective of Project• Assumptions• The Scheduling Algorithm• Simulation Input• Summary of Results• Conclusion

Page 3: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Introduction

• Wisconsin Lift Truck corporation sells, rents, services trucking equipment like…– Aerial lift and

construction equipment– Cranes– Lift Trucks – Industrial Cleaning

Equipment– Loaders – Pallet Trucks – Personnel Carriers

Page 4: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Introduction

• They have seven locations in Wisconsin and two locations in Illinois

• Our contact for this project is – Kristine Rauch

• Industrial Engineer, WLT, Brookfield, WI

Page 5: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Receive Truck

Stock Sold to Customer

Inventory WIP

Schedule for Set-Up

Stage

Delivery(Corp run or

Branch truck)

Set-Up(Bay Area)

Page 6: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Problem Description

• Bay has maximum capacity of 25– 5 stations with capacity of 5 trucks each

• 4 are considered WIP • 1 truck is being worked on

• 5 techs available for scheduling– one tech assigned to each of the 5 bays

Page 7: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Problem Description Cont’d

• 4 set-up types• 19-Used Truck Setup

– 3 types of New Truck Setups• 20-N.T SET-UP• 36-NEW RTL SET-UP• 76-I/C NT SETUP

Page 8: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Tech 1

Tech 2

Tech 3

Tech 4

Tech 5

Schematic of the Truck Set-up Bays

Page 9: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Scheduling Objective

• Minimize the time it takes for stock and new customer truck set ups to get from WIP to the delivery area

• Minimize tardiness to ensure timely delivery of trucks to customers as much as possible

Page 10: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Assumptions• There will be no preemption during

setup, once a job is started, it is completed – If we cannot finish a truck without

stopping in the middle of processing, we do not start the truck

• Once a tech has completed a setup they will start the next set up right after

• Both stock and customer trucks are taken together as number of stock trucks is negligible

• 6 hour work day

Receive Truck

Schedule for Set-Up

Truck set for

delivery

Set-Up(Bay Area)

Page 11: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Scope for scheduling

• 2 areas where scheduling can be done– When picking trucks from the infinite

arrival area into one of the 5 WIPs– When selecting one truck for set-up in

each bay station

Page 12: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Raw Data Analysis• Data From: Jan 2005 – May 2006 i.e.; 16

months– Job Type 76 – 515 jobs– Job Type 36 – 43 jobs– Job Type 19 – 97 jobs– Job Type 20 – 449 jobs– Total Significant Jobs: 1104

• % of Job Type 76 – 46.65%• % of Job Type 43 – 3.89%• % of Job Type 19 – 8.79%• % of Job Type 20 – 40.67%• Total No. of Trucks - 1974• No. of Stock Trucks [IMH RENTAL] - 89

[4.5%]• No. of Sold Trucks – 1885 (95.5%)

Page 13: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Simulation Input Data

–Setup times for each job type• Total labor $$ billed on each truck available• Tech billed at $97 per hour

–Distributions for inter-arrival times, by job type

• Used ARENA Input Analyzer module to fit each of these into standard probability distributions

Page 14: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

More Simulation Inputs..

• Due dates were assigned as an attribute to every job arriving– Due date distribution also determined

from invoice data

• Results were used to design an ARENA simulation so that different scheduling algorithms could be implemented and their performance evaluated.

Page 15: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Scheduling LOGIC

• Experimented with 4 different hybrid scheduling algorithms.

• Scheduling Algorithms used are a simple combination of standard algorithms with modifications made to suit this problem.– LST and SPT

• Process trucks in both WIP and bay queues in order of lowest value of the sum of Slack time and Processing time.

• In doing so, we anticipate minimizing flowtime as also reducing slack.

– LST OR SPT• A modification of the above algorithm where incoming trucks

are processed as per the least slack time, if (slack >0), else SPT is used to select trucks from the queues.

Page 16: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Scheduling Logic

– EDD With Priority• Modification of the EDD algorithm to incorporate a

priority mechanism for new truck types over old truck types

• Selection rule is – least value of (due date/priority), where priority is “50” for a new truck type and “10” for a used truck type (type 19)

– Shortest Processing Time • Plain ol’ SPT in least order of processing time

Page 17: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Simulation run Parameters

• Replication Length – 180 Days• Hours/day – 6 hrs• Warm up period – 10 Days• Number of Replications -4

Page 18: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Simulation Results [ALL UNITS DAYS]

JOB TYPE 20

RULE Combination Avg. Flowtime Max. Flowtime Avg. Lateness Max. Lateness

LST_SPT 5.33 19.48 517.44 1832

LST_OR_SPT 5.53 31.75 638.97 1681.74

EDD_PRIO 7.34 41.28 393.22 1705.47

SPT 7.09 59.86 422.55 1507.55

JOB TYPE 19 [USED TRUCK]

RULE Combination Avg. Flowtime Max. Flowtime Avg. Lateness Max. Lateness

LST_SPT 2.65 16.14 406.02 1104

LST_OR_SPT 5.84 31.12 466.45 1373.9

EDD_PRIO 7.38 29.55 501.92 1550.34

SPT 4.87 56.84 618.11 1527.85

Page 19: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Conclusion• The combination of LST and SPT works best to

minimize overall flow time (but not tardiness).• If either LST/SPT is used depending on

whether the job is slack or not, this leads to a significant reduction in max. lateness, compared to using LST + SPT in all cases.

• SPT scheduling yields the least max. lateness.• A priority based scheme predictably decreases

the avg. lateness for new truck set-ups. • Future Work Idea

– An Intelligent scheduler that can decide on the right scheduling algorithm based on a reasonable guess of whether incoming jobs will be late or not.

Page 20: Truck set-up scheduling for the Elgin, IL facility Vijay Viswanathan, Graduate Student Dr. Jaejin Jang, Associate Professor Department of Industrial Engineering

Thank you!