PROJECT : EPC PACKAGE SEWAGE TREATMENT PLANT,
STAGE 1
Project No. Contract No. Document No. Rev
AR 05/13 122-C01R 0
Date 20/07/2014 Sheet 1 from 12
METHOD STATEMENT
FOR
CABLE TRAY INSTALLATION
ROYAL COMMISSION FOR JUBAIL AND YANBU
JUBAIL, KSA
REV Date Designation Name Visa Name Visa Name Visa
Issued by: Verified by : Approved by:
Signature: Signature: Signature:
Method Statement for Cable Tray Installation
Date: 20/07/2014
Page: 2 of 12
TABLE OF CONTENTS
1. TITLE. 3
2. SCOPE OF WORK 3 2.1 General description. 2.2 Tools and equipment. 2.3 Materials. 2.4 planning & preparation 2.5 Work methodology. 2.6 Organization, Responsibilities & Supervision. 2.7 Work Force.
3. HEALTH & SAFETY 5 3.1 Safety Action plan 3.2 E S & H Contractor Requirements 3.3 Protective & Safety Equipment 3.4 Contractual Requirements 3.5 Information to personnel 3.6 Emergency Procedures 3.7 Permit Requirements 4. ENVIRONMENTAL ISSUES 7 4.1 E S & H Contractor Requirements 4.2 Contractual Requirements. 5. QUALITY ASSURANCE 8 5.1 Contractual Requirements. 5.2 Critical works. 5.3 Inspection & Testing. 5.4 Follow up & Evaluation. 6. APPENDICES 8 A. Risk Assessment (Task, Hazard, Consequences and Control Measures) B. Briefing Register C. Job safety analysis
Method Statement for Cable Tray Installation
Date: 20/07/2014
Page: 3 of 12
1. TITLE
METHOD STATEMENT FOR Cable Tray Installation 2. Scope of Work
2.1. General Description
This method statement is to outline the sequences and methods of works intended to be used for the Cable Tray Installation.
This procedure shall be applied to the Inspection, method and criteria for installation work carried out by the electrical department.
2.2. Tools and equipment
Electrical Grinder
Electrical Drill
Hand Tools
Ladder
Wire cutters
Hacksaw
Measuring tape
Wooden Hammer
Flat File
Screw Drivers
Open and box spanners
2.3. Materials
Materials used will be as per the material submittal approved by the Royal commission and
routing as well and sizes will be as per the approved drawings.
2.4. Planning and Preparations
Before commencing work a Site Supervisor will be assigned as responsible for the activity covered by this method statement. A site specific briefing on this method statement, risk
assessment and the emergency procedures will provided to all operatives and a briefing
register will be signed. A copy of the method statement and emergency procedures will be
kept on site in welfare facilities.
Plan of this work to be according to Royal Commission.
All material and Equipment should be checked and stored properly at site.
Safety measures and instruction should be issued to all staff in charge.
All necessary signs, barricades and warning tape will be applied in the field.
Prepare the safe access to the sites for workers and equipments.
Method Statement for Cable Tray Installation
Date: 20/07/2014
Page: 4 of 12
2.5. Work Methodology
Installation
Ensure that proper materials are available and are approved for use, as well as the approved drawings.
Verify site access / routing and mark support locations. Install / erect proper scaffoldings and ladders where ever required during installation of
supports and cable trays.
Fix the support on the natural structures, by drilling appropriate holes. Fix the vertical trays channel on the support. The cable trays shall be installed in such a way that, as often as possible the cables can be
laid directly in place rather than being pulled through.
Clearance shall be maintained / observed during Cable Tray Installation as per specified on approved drawings and specifications.
Cable Trays & Ladders shall be supported adequately and fix bolt and clamps as per specifications and drawings.
Sharp edges of cable trays shall be reamed to smooth and paint. Touch up paint shall be applied to the scratches / damaged surface of cable trays. Care to be taken to avoid corrosion and rust formation during installation. Earth continuity conductors shall be provided . Ensure that cable trays and ladders are erected correctly, inspected by QC and approved by
Royal commission Engineer prior to cable laying.
All cable shall be securely fixed to the tray, work and the complete installation must be carried out in a neat and workmanlike manner without crossovers
All materials and documentation relevant to the work will be checked by Quality Control Engineer prior to the commencement of works. Ensure that all materials to be installed are
inspected by QC and accepted by the RC Engineer.
2.6. Organization, Responsibility & Supervision
Construction Manager shall be responsible for the work procedure to ensure that Cable Tray Installation is carried out as per method statement. He shall ensure works shall be executed
in accordance with RC specification standards section 16055 and strictly imposed the safety regulation on the site.
The Quality Control Engineer shall be responsible for conducting surveillance and inspection of work and ensuring all records and test results will be acquired & recorded. He
shall prepare all the documents required for inspection.
The Electrical Field engineer/foreman is responsible to closely supervise the Installation of Cable Tray.
The Quality Control Engineer and RC Field Engineer shall be responsible to carry out inspections and release hold point for the preceding works.
Method Statement for Cable Tray Installation
Date: 20/07/2014
Page: 5 of 12
2.7. Work Force
Electrical Site Engineers (1)
Electrical QA /QC Engineer (1)
Electrical Foreman (1)
Safety Officer (1)
Electrician (1)
Skilled Worker(3)
3. SAFETY & HEALTH
3.1. Safety Action Plan
Tool box talk shall be conducted and brief safety measures required for the ensuring days will be discussed.
First Aid facility will be available during the process of work site. Correct PPE and Safety precautions requirements will be taken for the entire works. Safety Harness will be used whenever work is carried out on the above grade
elevations.
Proper housekeeping at the end of the day is a part of mandatory task assigned to workers to avoid accidents due to littered tolls and materials.
3.2. Environmental Safety & Health Contractor Requirements
Al Jazea / EPPM shall maintain safe working conditions at all times. And Conduct weekly tool box meeting discussing the safe working habit and procedure in case
of emergency.
All hazardous materials found should be reported to RC Safety Department and dumped in a designated dumping area.
3.3 Protective & Safety Equipment
Safety shoes
Rubber bootsas required
Safety harnessas required
Safety Gloves
Safety Helmet
Safety Eye Glasses
Dust Mask
Ear Protection
Method Statement for Cable Tray Installation
Date: 20/07/2014
Page: 6 of 12
3.4. Contractual Requirements
Maintain safety at all times in the job site.
All workers will be equipped with the required PPE while at site and during the execution of the works.
Al Jazea / EPPM shall provide Safety Officer to monitor the safety of manpower and equipment at the job site.
Stop the work when unsafe condition occurs.
Report any near miss or accident at the job site to the RC Safety Department.
3.5. Information to Personnel
In case of any emergencies the following responsible staff shall be Contacted:
NAMES POSITION CONTACT NO.
MAHER
AKKASH
Project Manager 0503128734
HAMED
ROMDHANI
Construction
Manager
0506284904
YASER Civil Supervisor 0541377615
ADEL MSELMI Electrical Field
Engineer
0545097267
NORBINTO
G.SALCEDO
Male Nurse 0547730914
RC Security and Safety Department Tel. No. 033417777
IJAZ SHAH Safety Manager 0552890503
Method Statement for Cable Tray Installation
Date: 20/07/2014
Page: 7 of 12
Emergency Contact Numbers:
Ambulance 997
Fire 998
Police 999
Emergency Radio Call 401
Maadden PMC Main clinic 0515014293
Maadden PMC Emergency 0515012677
3.6. Emergency Procedure
In case of emergency AAD/CR18B ambulance is always available to pickup workers from the site when something goes wrong to the workers during the work.
Heat shelter will be provided in case workers will experience anxious or heat stress.
When heavy sand storm occur AAD/CR18B Safety Officer shall distribute dust mask to all workers immediately.
Medical Staff shall be at all times ready to respond any emergency situation on site.
3.7. Permitting Requirements
Daily Work Permit, As Required
4. ENVIRONMENTAL ISSUES
4.1. Safety & Health Contractor Requirement
Al Jazea / EPPM shall maintain safe working conditions at all times.
Al Jazea / EPPM shall follow ES and H policy and procedure during the execution of the works.
Sufficient portable drinking water will always be available on the site with cups.
All hazardous materials found should be reported to RC and dumped in a designated dumping area.
Proper housekeeping & waste segregation shall be strictly enforced in the jobsite.
4.2. Contractual requirement
RC Environmental, Safety and Health Policies and Procedure should be strictly followed.
Method Statement for Cable Tray Installation
Date: 20/07/2014
Page: 8 of 12
5. QUALITY ASSURANCE
5.1. Contractual requirements
Al Jazea & EPPM shall comply with RC Specifications Section 01450
5.2. Inspection & Testing
The Al Jazea / EPPM QC Engineer and RC Field Engineer shall witness all quality control testing requirement of the work done.
Hold points will be carried out as required by the Inspection & Test plan.
5.3. Follow up and Evaluation
The Construction Manager shall always monitor the work activities to check if all the safety, environmental requirements and work procedure stated in this Method
statement are strictly followed.
Safety Manager/Officer shall always monitor the safe working condition at site during the execution of this activity.
The Al Jazea / EPPM QC Engineer to monitor the site as the work progresses.
The Site Engineer/Foreman shall monitor all works accomplished per the technical specification and quality requirements of the project.
6. APPENDICES
A. Risk Assessment (Task, Hazard, Consequences and Control Measures)
B. Briefing Register
C. Job safety analysis.
Method Statement for Cable Tray Installation
Date: 20/07/2014
Page: 9 of 12
Appendix A-Risk Assessment
Risk Assessment Matrix
1. Negligible 1. Improbable 90%
RISK INDEX
The risk index is then simply defined by multiplying together the frequency index and
severity index. With this ranking system this will yield a number between 1 and 25. Refer
to the following table and read off the priority rating:
1
2
3
4
5
1 2 3 4 5
SEVERITY/CONSEQUENCE
The following shading indicates the level of risk:
Intolerable 17-25
Tolerable 6-16 Negligible 1-5
1 2 3 4 5
2 4 6 8 10
3 6 9 12 15
4 8 12 16 20
5 10 15 20 25
Method Statement for Cable Tray Installation
Date: 20/07/2014
Page: 10 of 12
Appendix B-briefing register
CONTRACTOR: AL JAZEA CONTRACTING & TRADING CO.
CONTRACT NO: 122-C-1R
SUBJECT OF BRIEFING:
CARRIED OUT BY:
DATE CARRIED OUT
PROJECT TITLE: EPC PACKAGE SEWAGE TREATMENT PLANT (STAGE 1)
NO. NAME PROFESSION SIGNATURE
Method Statement for Cable Tray Installation
Date: 20/07/2014
Page:11 of 12
Appendix C- Job Safety Analysis
Complete prior to commencement of equipment operation
JOB INFORMATION
Date: Project: Location: Job Description:
Site supervisor: Safety Engineer: Equipment Operator:
Personal Conducting Analysis
Name: Position: Name: Position:
Preliminary Precautions
Does the equipment and
equipment operator have the
appropriate license?
Yes No
Are utility lines present in the
work area? Yes (Where? _______________
____________________________
____
Is excavation being done
manually? ___, if not, why?
____________________________
___)
No
Has a lift plan been prepared? Yes (Where? ___________________)
No (Why? __________
____________________)
Method Statement for Cable Tray Installation
Date: 20/07/2014
Page: 12 of 12
Are above utilities identified
and barricaded? Yes No (Why? __________
____________________)
Are spotters in place? Yes (Who? _____________________)
No (Why? __________
____________________)
(1) Job/Tasks
List all types of work tasks being performed in your work location. Remember to include all
functions and positions and be specific with the tasks, potential hazards, and preventative measures.
(Continued on next page)
All Job/Tasks All Potential Hazards Related to
Job/Tasks
Preventive Measures
Reviews and Signatures (To be reviewed and signed by all contractor and RC managers on-site)
Name: Signature: Name: Signature: