Upload
leung-mk
View
215
Download
0
Embed Size (px)
Citation preview
1 INTRODUCTION
The project (Photo 1 and Photo 2) is to provide a public library and an indoor recreation centre to meet the
cultural and recreational demand of a population of 271 000 in Tin Shui Wai, Hong Kong. The completed
building also signifies the idea of a town hall with a piazza as a place for gathering. The whole building is
divided into two parts: a public library and an indoor recreation centre. The site (Figure 1), which is of a
trapezoidal shape on plan with a length varying from about 89m to 105m and with a width of about 55m, is
located at the junction of Tin Fuk Road and Ping Ha Road. The site is sloping gently downwards from
+7.9mPD at the northwestern tip to +6.1 mPD at the southeastern end. The proposed development (Figure 2)
is a reinforced concrete structure, with steel trusses on 2/F of clear span 25m×25m, on 3/F of clear span
25m×25m and on roof of clear span 44m×42m, and with a basement of maximum excavated depth of 7m. The
construction works commenced in April 2009, and the indoor recreation centre has been in use since end-2011
and the new public library has been opened to the public in end-2012. The engineering and architectural
designs were awarded respectively Structural Excellence Grand Award 2012 of the Hong Kong Institution of
Engineers and Medal of the Year 2012 of the Hong Kong Institution of Architects.
Photo 1. Outlook of Completed building
Photo 2. Front Elevation of Completed building
ABSTRACT
This paper will present a trail that demonstrates the process of the planning, design and
construction of the foundation and basement in a very difficult ground with cavernous karst in
Scheduled Area No. 2 in Tin Shui Wai, Hong Kong with thorough considerations of technical
issues and alternative solutions. In this project, an appraisal was carried out to determine the
effect of geological constraints on the foundation design and to assess the suitability of different
types of foundation systems for the project with a basement of 7m depth. Sinkhole hazard is
another major challenge to engineers when founding a structure and/or carrying out excavation in
cavernous karst area. Formation of a sinkhole usually leads to a sudden depression on the ground
surface caused by the collapse of cavities. This paper will further describe how the sinkhole
hazard was investigated and/or dealt with at the planning, design and construction stages of this
project.
Foundation Design and Construction in Cavernous Karst : a Local Experience
K.P. YIM
Greg Wong & Associates Ltd
C.Y. KAN, C.T. WONG & M.K. LEUNG Architectural Services Department, Hong Kong
Figure 1 Site location plan Figure 2 Internal arrangement of proposed development
Figure 3 Geological Section across the Site
Figure 4
(Source: Adapted from GEO 2007)
2 SITE GEOLOGY
2.1 Fundamental soil mechanics theories
The development lies on an area designated by Geotechnical Engineering Office (“GEO”) of Hong Kong SAR
Government as “Scheduled Area No. 2”, in which geology is very complex with cavernous karst. Scheduled
Area No. 2 is an elongate curved valley (Figure 4) with a northwesterly trend (Darigo 1989; Frost 1989), with
granitic and volcanic rocks forming the high relief topography on either side of the valley, weathered
metasedimentary rocks forming low hills adjacent to the granitic rock and thrust and reverse faults running in
northeast direction at about 60o, which are interrupted by a series of northwest to southeast cross-faults. The
bedrock underlying the superficial deposit includes marble, metasiltstone, sandstone, and conglomerate of the
Carboniferous Yuen Long Formation and Lok Ma Chau Formation (where large cavities may be found), and
volcanic rocks of Jurassic Repulse Bay Volcanic Group. A large portion of Tin Shui Wai area is underlain by
volcaniclastic breccias, and only a few areas are underlain by the Yuen Long Formation (Darigo 1989; Frost
1989; and Lai and Tang 2006). However, the site in this project falls squarely within one of such a few areas,
and the underlying rock is pure white marble belonging to Ma Tin Member of the Yuen Long Formation. Ma
Tin Member consists of pure marble bedrock of virtually pure calcium carbonate, which renders it susceptible
to dissolution (Frost 1989). Cavities of maximum height of 24.5m have been recorded (Lai 2004).
3 GROUND INVESTIGATION AND GEOPHYSICAL SURVEY
The site is located at a karstic formation with extensive cavities, which imposes geological constraints on the
choice and design of foundation. Firstly, excessive stresses on the roof of the cavities due to the foundation
load may cause the collapse of cavities, especially when the rock thickness above the roof of the cavities is
thin. Secondly, an increase in the overburden pressure during dewatering above the cavities may trigger
sinkhole collapse. Extensive ground investigation (including the sinking of 50 nos. of drillholes with full
geological logging and installation of 9 nos. of standpipe piezometers) have also been carried out to avoid
overstress of underneath cavities and to tackle the sinkhole hazard. To locate the spatial extent of cavities in a
karst site, conventional method by sinking drillholes would be very time consuming and expensive (Morris et
al 2005). In particular, sinking drillholes can only provide information on the “vertical height” of the cavities
but not the “spatial extent” of the cavities. Cross-hole seismic geophysical method was employed to delineate
the spatial extent of the cavities. 13 cased drillholes with depths between approximately 25m and 43m and
eight sections were selected to conduct the tomographic survey. A vertical spacing of the sparker source
(which serves as the emitters) at 1m c/c was chosen, and a 24-channel hydrophone spaced at 1m c/c was used
at the receiver side. About 16,000 travel times were determined and used for tomographic inversion. However,
the method of tomographic survey is limited in spatial resolution depending on the drillhole distances and the
geometrical density of ray paths. Cavities with smaller dimensions (e.g. less than 1m or 1.5m) or thin rock
covering may not have clear identification. Figure 5 shows one of the seismic tomograms superimposed with
the results of drillholes obtained in this site.
With extensive ground and geophysical investigation, the underground conditions underlying the
development have been defined. The site was reclaimed from old low-lying agricultural land in the 1980s.
The ground level varied between +7.9mPD and +6.1mPD. Geologically, there are 10m to 25m thick
superficial deposits of fill (about 5m to 7m thick) and alluvium overlying the decomposed sedimentary,
metamorphosed and granitic rocks (Figure 3). Three fault lines run across the site. Rockhead at most parts of
the site could be found at 20m to 25m below ground. However, in the eastern part of the site, cavities were
found in marble. A zone of deeper rockhead was found at the north-eastern corner of the site and the rockhead
may be as deep as 75m below the existing ground level. Infilled cavities of “height” up to 11m were found
mainly in the marble on the north-eastern part of the site, and the bottom of these cavities is at about 55m
below the existing ground level. Besides, there are three nos. of faults running across the site.
Figure 5 Tomographic image of the site superimposed with results of drillholes
3 PROJECT PLANNING AND FOUNDATION CONSIDERATION
In constructing an annex to TWG Hospitals Kwok Yat Wai College adjacent to this site, many of the driven
H-piles were damaged from hard-driving through the karstic layer and pile slippage along sloping bedrock
(Sze 2006). With a clear geological and hydrogeological model showing especially the spatial extent and
distribution of the cavities underneath the proposed development, the layout of the building was re-planned at
the early stage of the project, such that the proposed structure was shifted away from the northeastern portion
of the site as far as possible (Figure 3), and hence avoiding potential difficulties and reducing cost and time in
constructing the foundation works. This approach (termed by Lee and Ng (2004) as the “first rule” in the
foundation design in cavernous karst area) has been employed by in a project in Tin Shui Wai and a project in
Ma On Shan (Fletcher et al 2004; Wightman and Lai 2006).
Commonly adopted foundation systems in cavernous karst areas in Hong Kong include: shallow
foundation; floating piled-foundation (e.g. Pakt-in-Place (PIP) piles); driven steel H-piles; and large diameter
bored piles or rock-socketted steel H-piles. For this project, shallow foundation in the form of pad or raft
footing was ruled out, as founding the building on either the fill or alluvium layers will result in excessive
settlement in the building. For a floating piled-foundation using PIP piles, the karst surface should lie at deep
level so that the stress induced at the pile tips will not overstress the roof of cavities (Wong 2003). In this
project, the founding level of the pile tips is just at a few metres above the karst surface at some locations, and
the thin layer of intact rock above the cavities may cause the roof over cavities to collapse. Driven steel H-pile
with or without pre-boring is one of the most popular options for piles in cavernous karst area with due
allowance on pile redundancy for uncertainties. However, in this project, driving steel H piles without pre-
boring was not technically feasible as founding H-piles on top of karst surface might again possibility cause
the collapse of the roof over cavities within the karst. Driving steel H-piles with pre-boring was also
undesirable because of the environmental sensitivity of the site, with three secondary schools, a West Rail
Station and a Light Rail adjacent to the site.
Large diameter bored pile socketted into rock was therefore adopted, especially due to relatively shallow
rockhead (about 20m to 25m below ground) at over three-quarters of the site. The base of the socket was
located at a depth where there are no cavities existing within the zone below the pile base to a depth equal to
the diameter of the pile base. Karst area also contains steeply inclined bedrock surfaces inducing additional
stress from one pile onto the adjacent piles and/or the adjacent cavities. In designing the length of rock socket
of pile, the founding level of rock socket was required to pass through the adverse joints, and to follow the
commonly adopted rule of thumb in Hong Kong with an “angle of stress dispersion” between 30o and 45o to
the vertical (Wai 1991). Similar to large diameter bored pile socketted into rock, rock-socketted steel H-piles
could also be a solution. However, for cavernous karst area, such foundation system may have difficulties in
pre-boring and forming rock sockets, as it is difficult for the casing shoe to bring the casing through the
cavities and to form rock socket on the sound bedrock, except that a secondary permanent casing is left for
pile installation; but this would lead to a high construction cost of foundation. Indeed, there is no published
case on the successful employment of rock-socketted steel H-piles in cavernous karst area in Hong Kong.
Hence, a compromise scheme was to adopt rock-socketted steel H-piles only at areas with cavity-free marble
and/or granitic bearing rock underneath, whereas large diameter bored piles are used at areas with cavernous
marble bedrock. The final adopted foundation design employed a total of 50 nos. of large diameter bored piles
with either 1.5m or 2m diameter, and 99 nos. of rock-socketted steel H-piles. With the adoption of two
different piling systems, the design of the pile caps and superstructure was also required to cater for the
possibility of differential settlement due to the difference in the elastic shortening of reinforced concrete bored
piles and structural steel rock-socketted steel H-pilesIn order to develop a simple and workable design
equation for friction piles in soil especially including the effect of the pile construction method on the K value
and the variation of tanδ with depth for each construction method, ArchSD has been carrying out loading tests
on a number of meticulously instrumented friction piles (nominal diameter 300-600 mm or more) with
different construction methods since the mid 1990s. Among these piles, at least four different construction
methods have been adopted. The typical details of these piles are as summarised in Table 1, and the geology
and soil strata of various sites (together with the SPT-N values versus depths) are summarised in Table 2.
4 PILING AND BASEMENT CONSTRUCTION WORKS
In constructing the rock-socketed piles, the presence of karst cavities may result in a large amount of
overbreak, leading to concrete loss from pile and hence affecting the pile integrity. Different construction
methods (e.g. filling with lean concrete for cavities up to 1.5m and installing permanent secondary corrugated
liner for cavities over 1.5m in Figure 6) were therefore adopted in this project, such that no excessive ground
settlement or sinkhole collapse would be induced. Moreover, constructing a 7m-deep basement and removing
a total of 18,000m3 spoil soil together with dewatering of up to a maximum 3m drawdown in this project is a
challenging task for every engineer, particularly when the site lies adjacent to the West Rail, the Light Rail
and a school. A cofferdam of sheet piles around the perimeter of the basement was driven to a maximum
depth of about 13m below the existing ground level down to the -8.0mPD, which provides an effective cut-off
for the drawdown. Three rows of waling were installed, and raked shoring was employed (Photo 3).
Moreover, the excavation was divided into two zones, and each zone was carried out in two stages, so that
when dewatering commenced on site, the increase in the effective stress at the karst surface would have
partially been compensated by the removal of overburden soil. During the construction works, all
measurements during the construction of accumulative distortion, total movement, vertical or horizontal
pressure on the structures and peak particle velocity induced on the structures were closely monitored with 15
nos. of settlement markers, 5 nos. of tilting check points, 5 nos. of check points and 15 nos. of standpipe, such
that the effects of construction works on the nearby railway structures were found to be within the acceptable
limits. The piling works was completed in May 2009, and the superstructure works commenced in June 2009.
No sinkhole subsidence was noted throughout the construction period.
(a) Filling with lean concrete (b) Installing corrugated liner
Figure 6 Methods of constructing large diameter bored piles through cavities
Photo 3 Excavation and lateral support system during basement construction
5 EPILOGUE
From the planning, design and construction of this project in cavernous karst area, the following concluding
remarks could be made:
(a) Appropriate ground investigation is crucial for the success of sitting of building, design and construction of
foundation for this type of project with very difficult ground condition. Early recognition of the geological
constraints at cavernous karst area can permit the subsequent detailed ground investigations to be targeted
to obtain specific information for the design. Mapping the particular site in the geological maps is also vital
for the planning of ground investigation, and in the choice and design of the foundation systems. If large
cavities are likely to be present (e.g. in Ma Tin Member of the Yuen Long Formation), geophysical survey
method using cross-hole seismic tomography, wherever affordable, may be used, which can provide more
information on the spatial extent of cavities and hence removing some uncertainty or risk of foundation
design and construction. This will obviously not only improve the design of foundation, but also benefit the
project on cost and time.
(b) With more comprehensive information on the complicated geology underneath the site, the building layout
can be redesigned to minimize costs and construction time. Similarly, alternative foundation systems are
available. Floating piles or shallow foundation in general are most economical if the loadings are not high.
If, however, cavities are present at high level near ground surface, rock-socketted large diameter bored
piles passing through cavities are recommended.
(c) Roofs over cavities within the karst may collapse due to the increase in the stress and construction
activities, and it is vital for engineer to study carefully the increase in the stress induced by the foundation
and the dewatering process.
ACKNOWLEDGEMENT
The authors would like to record their thanks to the Director of Architectural Services, Hong Kong SAR
Government for his kind permission in publishing this paper.
REFERENCES
Darigo, N J (1989), “A Volcanic Breccia in the Buried Karst of Hong Kong”, Proceedings of the Third Multidisciplinary
Conference on Sinkholes and the Engineering and Environmental Impacts of Karst, St Petersberg, Florida, 2-4
October 1989, pp. 225-32.
Fletcher, C J N, Pang, V P Y and Yim, K P (2004), “Geological Modeling and Foundation Appraisal for Project Planning
of Development Sites in Tin Shui Wai, Northwestern New Territories”, Proceedings of the Conference on Foundation
Practice in Hong Kong, Hong Kong, 4 September 2004, pp. F1-14.
Frost, D V (1989), “Palaeokarst of Yuen Long, North West New Territories, Hong Kong”, Proceedings of the Third
Multidisciplinary Conference on Sinkholes and the Engineering and Environmental Impacts of Karst, St Petersberg,
Florida, 2-4 October 1989, pp 239-46.
GEO (2007), GEO Publication No. 1/2007: Engineering Geological Practice in Hong Kong (Hong Kong: Geotechnical
Engineering Office).
Lai, K W (2004), “The Influence Factors of Buried Karst upon the Foundation Design of Hong Kong”, Proceedings of
the Conference on Foundation Practice in Hong Kong, Hong Kong, 4 September 2004, pp. I1-10.
Lai, K W and Tang, D L K (2006), “The Characteristics of Marble and Marble-Bearing Rocks in Hong Kong and Their
Influence on Foundation Engineer”, Proceedings of the Seminar on Geotechnical Works in Karst in South-East Asia,
Hong Kong, 26 August 2006, pp. 79-92.
Lee, D M and Ng, M (2004), “Design Strategies for Deep Foundation in Areas of Marble Formation in Hong Kong”,
Proceedings of the Conference on Foundation Practice in Hong Kong, Hong Kong, 4 September 2004, pp. C1-17.
Morris, V, Gehrig, D and Bryant, T (2005), “Detection of Three-Dimensional Voids in Karstic Ground”, Proceedings of
the Tenth Multidisciplinary Conference, 24-28 September 2005, San Antonio, Texas, pp. 562-71.
Sze, W C (2006). “Case Study for a Driven Steel H-Pile Foundation in the Tin Shui Wai Marble Area”, Proceedings of
the Seminar on Geotechnical Works in Karst in South-East Asia, Hong Kong, 26 August 2006, pp. 155-78.
Wai, M (1991), Technical Note TN 2/91: Checking Procedures and General Requirements for Foundations in Areas
Underlain by Marble (Hong Kong: Geotechnical Control Office).
Wong, H Y (2003), “Design and Construction of Soil Friction Bored Piles in Hong Kong, with Particular Reference to
Marble Areas”, Proceedings of the 23rd
Annual Seminar, Geotechnical Division, The Hong Kong Institution of
Engineers, 9 May 2003, pp. 265-82.