7
TUNNEL WIDENING TUNNEL WIDENING 27 New technologies for widening road, motorway and rail tunnels without taking them out of service The first application in the world at Nazzano (Rome) TUNNEL WIDENING 1 - INTRODUCTION It is well known that as volumes of traffic progressively increase, the need to widen roads, motorways or rail- ways to augment their capacity becomes increasingly urgent. While meeting these needs does not present any huge problems as long as the routes run completely on the surface, it is very complicated when they run through stretches of tunnel, because it is indispensable in these cases to resort to costly alternative routes to construct the new tunnels in addition to those that already exist. And then a tunnel can only be widened while it is in ser- vice if it is possible to: - guarantee the necessary safety of users and limit incon- venience within an acceptable threshold; - solve the technical and operational problems connec- ted with driving the widening face in ground that has already been disturbed by the previous excavation; - construct the new load bearing structure at the same time as the old one is demolished and deal adequately with any stress-strain conditions without any danger to tunnel users and to any human activity there may be on the surface. Experimentation of a construction method is at an advanced state of progress in Italy which is actually able to satisfy all the above requirements and make it pos- sible to widen existing road, motorway and rail tunnels without interrupting traffic flow during construction work. Figure 1 - Excavation of ground of the widening face and demolition of old tunnel Figure 2 - The stage of placing of an arch of prefabricated segments is alternated to the stage of excavation of the widening face 2 - ILLUSTRATION OF THE TECHNIQUE The technique consists of three main stages (Fig. 1 and 2) a first stage of ground improvement and excavation in steps during which the work, if necessary, to reinforce the face and/or to preconfine the excavation is performed, depending on the geological and geotechnical condition and then the ground between the theoretical profile of the future widened tunnel and that of the old existing tunnel is excavated;

TUNNEL WIDENING - AFTES · experimentally for the first time in the world to widen the Nazzano tunnel located on the A1 Milan-Rome-Naples motorway between Orte and Fiano Romano, between

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TUNNEL WIDENING - AFTES · experimentally for the first time in the world to widen the Nazzano tunnel located on the A1 Milan-Rome-Naples motorway between Orte and Fiano Romano, between

TU

NN

EL

WID

EN

ING

TUNNEL WIDENING

27

New technologies for widening road, motorway and rail tunnels without taking them out of serviceThe first application in the world at Nazzano (Rome)

TUNNEL WIDENING

1 - INTRODUCTION

It is well known that as volumes of traffic progressivelyincrease, the need to widen roads, motorways or rail-ways to augment their capacity becomes increasinglyurgent. While meeting these needs does not present anyhuge problems as long as the routes run completely onthe surface, it is very complicated when they runthrough stretches of tunnel, because it is indispensablein these cases to resort to costly alternative routes toconstruct the new tunnels in addition to those thatalready exist.

And then a tunnel can only be widened while it is in ser-vice if it is possible to:

- guarantee the necessary safety of users and limit incon-venience within an acceptable threshold;

- solve the technical and operational problems connec-ted with driving the widening face in ground that hasalready been disturbed by the previous excavation;

- construct the new load bearing structure at the sametime as the old one is demolished and deal adequatelywith any stress-strain conditions without any danger totunnel users and to any human activity there may be onthe surface.

Experimentation of a construction method is at anadvanced state of progress in Italy which is actually ableto satisfy all the above requirements and make it pos-sible to widen existing road, motorway and rail tunnelswithout interrupting traffic flow during constructionwork.

Figure 1 - Excavation of ground of the widening face and demolition of old tunnel

Figure 2 - The stage of placing of an arch of prefabricated segments is alternated to the stage

of excavation of the widening face

2 - ILLUSTRATION OF THE TECHNIQUE

The technique consists of three main stages (Fig. 1 and 2)

• a first stage of ground improvement and excavation in steps during which the work, if necessary, to reinforce the faceand/or to preconfine the excavation is performed, depending on the geological and geotechnical condition and then theground between the theoretical profile of the future widened tunnel and that of the old existing tunnel is excavated;

27a33NAZZANO ITAL 24/08/05 10:18 Page 27

Page 2: TUNNEL WIDENING - AFTES · experimentally for the first time in the world to widen the Nazzano tunnel located on the A1 Milan-Rome-Naples motorway between Orte and Fiano Romano, between

TTUNNEL WIDENING

28

• a second lining stage in which the final lining is placedimmediately behind the face, consisting of one or morearches of prefabricated segments employing the activearch principle;

• a third foundation stage during which the foundation(tunnel invert) of the widened tunnel is placed, if necessary.

During the first two phases which must be performed incycles with an extremely regular rythm, a steel traffic pro-tection shield is employed inside the profile of the tunnelto be widened. All the machinery used to perform thework is operated and moves above that shield. The cavitybetween that steel shield and the lining of the existing tun-nel is filled with sound absorbing anti-shock material. Thesteel shield is around four times the diameter of the tunnelto be widened and occupies relatively little space withinit, making it possible to perform work without interruptingtraffic on the pre-existing traffic lanes. When, after tunneladvance, the distance between the face and the front endof the shield reaches a minimum safety threshold, theshield is moved forwards and the various stages continueto be repeated in cycles until the widening of the entiretunnel is complete.

We will now look in detail at how each operational stageis performed.

2.1 - The first operational stage(ground improvement and excavation)As has been said, the first stage of operations consists, ifnecessary, of firstly intervening to improve the ground inadvance of the face, and then to excavate in steps (thelength of which will depend on the characteristics of theground concerned) of the material between the theoreti-cal profile of the future widened tunnel and that of theexisting tunnel.

Action to improve the ground ahead of the face willdepend on the geological and geotechnical conditionsand may consist of reinforcing the face and/or of preconfi-nement of the cavity such as: horizontal jet-grouting,mechanical pre-cutting or ground improvement usingglass-fibre structural elements with valves that are injec-ted, placed around the future cavity to widen the tunnel.They may be placed ahead of the face or radially, opera-ting from within the existing tunnel and in any casealways above the steel traffic protection shield.

Advance of the widened tunnel starts after ground impro-vement in advance, if required, has been performed (seeFig. 1). This is done by excavating the ground and demoli-shing the lining of the existing tunnel in small steps [from60 cm. to 200 cm. depending on the stress-strain condi-tions of the material being tunnelled and the size of theprefabricated segments designed for the final lining (seeparagraph 2.2: The second construction stage (lining)). Ifthe stress-strain conditions allow, tunnel advance mayproceed in steps that are as long as several lining segmentlengths.

The machinery used for ground improvement and liningoperations operates completely above the steel trafficprotection shell and is equipped with all the equipmentneeded.

2.2 - The second construction stage(lining)The second construction stage entails placing the finallining of the widened tunnel consisting of prefabricatedconcrete segments.

Excavation in steps with the final lining consisting of pre-fabricated concrete segments placed immediately accor-ding to the active arch principle constitutes the key factor.It halts any possible deformation phenomena before itstarts at a short distance from the face and overcomes allthe problems of the deformation response of the rockmass. This is the most characteristic feature of the tech-nique presented here.

The operations involved in this stage are as follows (Fig. 2):

A) transport of the concrete segments to the face usingconveyor belts and/or fork lift trucks positioned on the twosides of the widened tunnel;

B) the application of slow setting epoxy resins on the twosides of the segment to be placed and on the front end thatwill be in contact with the arch of the lining already pla-ced;

C) raising and positioning of the segments using a specialerector machine which places the lower segments first onboth sides of the tunnel and then the upper segments untilthe arch is completed with the key segment in the roof;

D) mortar is introduced between the extrados of the prefa-bricated segments and the wall of the excavation behind it;

E) the pressure jack in the key segment is then activated tobring the segments into firm contact with each other andimmediately produce the confinement pressure requiredon the ground around the tunnel according to the activearch principle.

2.3 - The third construction stage(foundation)If a foundation structure is needed, it can be placed accor-ding to the situation either by simply joining the lining ofthe widened tunnel to the tunnel invert of the old tunnelor a genuine new tunnel invert is cast. To do this, trafficmust be deviated as illustrating in the paragraphs below.

3 - RESOLUTION OF PARTICULAR PROBLEMS TO MAINTAIN TRAFFICFLOW DURING THE THIRD OPERATIONAL STAGE

A distinction must be made between road and rail tunnelsas far as maintaining traffic flow during the third operatio-nal stage is concerned.

3.1 - Rail tunnelsOnce the tunnel has been widened rail traffic will have tobe interrupted to change the layout of the tracks in the newsituation. The structure to join the final lining of the wide-ned tunnel with the existing tunnel invert or, alternatively(if the static conditions require it), the casting of a new tun-nel invert can be performed in this interval of time.

TUNNEL WIDENING

27a33NAZZANO ITAL 24/08/05 10:18 Page 28

Page 3: TUNNEL WIDENING - AFTES · experimentally for the first time in the world to widen the Nazzano tunnel located on the A1 Milan-Rome-Naples motorway between Orte and Fiano Romano, between

TUNNEL WIDENING4 - USE OF THE SYSTEM FOR THE WIDENING OF THE NAZZANO TUNNEL

As has been said the new technology is being appliedexperimentally for the first time in the world to widen theNazzano tunnel located on the A1 Milan-Rome-Naplesmotorway between Orte and Fiano Romano, betweenchainage km. 522+00 and km 523+200 (Fig. 4). The routeof this tunnel is completely rectilinear and lies at an alti-tude of 166 m. a.s.l.. It is 337 m. long and runs under anoverburden of 45 m. From a geological viewpoint, thetunnel runs through sandy and silty-clayey ground of thePlio-Pleistocene series on which the town of Nazzano islocated (Fig. 5).

G

29

3.2 - Road (single tunnel) or motorway(twin tunnel) with 2 lanes in eachdirectionTraffic in road tunnels can always be kept flowing on atleast one lane in each direction by appropriate organisa-tion of the works to construct the foundations and towiden the road itself. Similarly, two lanes in each direc-tion can always be kept open with twin motorway tunnelsby switching the works between the two tunnels anddeviating traffic flow accordingly onto lanes as theybecome free (as illustrated in the example in Fig. 3).

TUNNEL WIDENING

Figure 3 - The regulation of traffic during tunnel widening works

27a33NAZZANO ITAL 24/08/05 10:18 Page 29

Page 4: TUNNEL WIDENING - AFTES · experimentally for the first time in the world to widen the Nazzano tunnel located on the A1 Milan-Rome-Naples motorway between Orte and Fiano Romano, between

TTUNNEL WIDENING

30

Given the type of ground to be tackled, the design firstspecifies the creation of a shell of fibre reinforced shot-crete around the tunnel using mechanical precuttingbefore starting excavation to widen the tunnel.

Tunnel widening therefore takes place in the followingfour main stages (Fig. 6);

1) creation of a mechanically precut shell (5.5 m. inlength, thickness 35 cm.) around the future tunnel (19.74m. span) and ground improvement ahead of the wideningface if necessary (Fig. 7);

2) demolition of the old lining in steps under the protec-tion of the previously improved ground and excavation ofthe ground until the design profile of the widened tunnelis reached (Fig. 8);

TUNNEL WIDENING

Figure 4 - Nazzano Tunnel: location

Figure 6 - Nazzano Tunnel: tunnel widening operatio-nal stages

Figure 7 - Nazzano tunnel: mechanical precutting operation

Figure 5 - Nazzano Tunnel: ground situation

3) immediate erection of the final lining behind the face(4 - 5 m. max.) by placing an arch of prefabricatedconcrete segments, using the active arch principle (Fig. 9);

4) construction of the foundation structure (new tunnelinvert).

All the operations for the first three stages are performedprotecting the road with a self propelled steel traffic pro-tection shell under which vehicles may continued to passin safety (Figures 10 and 11). The shield used has a lengthof 60 m. and extends for a length of approximately 40 m.ahead of the widening face. It consists of a modular steelstructure and is equipped with runner guides, anchors,motors, sound proof and anti shock panels to absorb theshock of falling blocks of material during excavation anddemolition of the existing tunnel including any groundthat falls accidentally. All the machinery for performingthe various operations moves and operates above theshield. When tunnel widening advances to the point

27a33NAZZANO ITAL 24/08/05 10:18 Page 30

Page 5: TUNNEL WIDENING - AFTES · experimentally for the first time in the world to widen the Nazzano tunnel located on the A1 Milan-Rome-Naples motorway between Orte and Fiano Romano, between

TUNNEL WIDENING

31

TUNNEL WIDENINGG

Figure 8 - Nazzano tunnel : demolition of the old lining andexcavation of the ground of the widening face

Figure 9 - Nazzano tunnel: final lining of prefabricated segments

Figure 10 - Nazzano tunnel: all the operations are performed protecting the road with a “steel traffic protection shell”

where the distance between the face and the front end ofthe shield reaches what is considered the minimum safetylimit for vehicle traffic, it is moved forward and the variousstages repeated in cycles until the whole tunnel has beenwidened.

5 - THE MACHINE AND ITS EQUIPMENT

The design of the machine prototype and its equipmentrequired particular effort because a series of operating func-tions had to be optimised to work in a very limited spacebetween the finished tunnel and the shield: precutting at

the face, excavation, placing of the segments, various mor-tar operations, demolition of the existing tunnel.

The problems were solved by using innovative technologyand the result was a versatile and compact design, highlycomputerised capable of performing all the functionsrequired with movements and therefore also operatingtimes reduced to a minimum.

Basically it consisted of a robust double arch steel struc-ture (Fig. 12) connected at the bottom by telescopicbeams which gave rapid and precise longitudinal move-ment forwards and backwards. Centring in the cross sec-

27a33NAZZANO ITAL 24/08/05 10:18 Page 31

Page 6: TUNNEL WIDENING - AFTES · experimentally for the first time in the world to widen the Nazzano tunnel located on the A1 Milan-Rome-Naples motorway between Orte and Fiano Romano, between

TTUNNEL WIDENING

32

tion and correct positioning of the height are achieved byhydraulic control systems.

A particularly sophisticated carriage is fitted on the arch atthe face which carries the precutting blade. The circularmovement of the carriage around the arch is obtained by agear reduction motor and a rack and pinion and the singleand complex movements of the different equipment allowthe different operations specified in the design to be per-formed.

A dual system is also appropriately positioned on thesame arch to manage the tubing used for filling the cutmade with the precutting blade with mortar and the spacebetween the segments and the walls of the excavation.

The rear arch was designed for placing the concrete seg-ments. A carriage runs on it, equipped with an erector

capable of grabbing the segments and placing them. Themovement of the erector is totally powered by electricityand hydraulics and it is controlled from a panel equippedwith a display which gives information on manoeuvresand errors that may have been committed.

Before the key segment of the arch is placed and it conse-quently becomes self supporting, the segments rest onspecial telescopic structures anchored to the arch. Theyare equipped with sensors which allow the differentmanoeuvres to be made in safety.

The structure is equipped with various service gangwaysto allow personnel to work with a clear view of opera-tions.

The various functions of the equipment are controlled bya PLC (Programmable Logic Controller), which recognisescommands it receives and sends information to the dis-play for correct and safe control of the equipment.

The table below contains the main technical specifica-tions of the machine used.

TUNNEL WIDENING

Figure 11 - Nazzano tunnel:during the widening works trafficgoes regularly on under the steel traffic protection shell

Figure 12 - Nazzano tunnel: view of the machine

TECHNICAL SPECIFICATIONS OF THE MACHINE

Cutting capacity of the blade L = 5.50 m ; th. = 35 cm

Erecting of the segments max load = 7 ton at 10.70 m

Rated power 214 kW

Power electricity-hydraulic

Movement hydraulic controlled by a

Programmable Logic Controller

Table 1

27a33NAZZANO ITAL 24/08/05 10:18 Page 32

Page 7: TUNNEL WIDENING - AFTES · experimentally for the first time in the world to widen the Nazzano tunnel located on the A1 Milan-Rome-Naples motorway between Orte and Fiano Romano, between

TUNNEL WIDENING

33

6 - STATE OF PROGRESS OF THE WORKS

Regular advance rates for tunnel widening were achievedafter first overcoming problems of an exclusively contrac-tual and financial nature, which delayed the actual start ofwidening operations several times and secondly after sol-ving a series of problems connected with advance throughthe portal zone with shallow overburdens and the subse-quent calibration of the system.

Approximately 210 m. of widened tunnel had been com-pleted in May 2005 with advance rates of between 0.7and 0.8 m. per day.

Optimisations applied to the system and the advancecycle mainly regarded the adoption of a longer cuttingtool to perform a pre-cut of 5.5 m and a thickness of35 cm..

The pre-cut is then followed by two stages of demolitionof the existing tunnel and placing of shotcrete at the face,each two metres in length with the erection of two conse-cutive active arches each with a length of 1 metre.

7 - CONCLUSIONS

The first results of the experimentation indicate that thetechnology illustrated effectively solves the typical pro-blems of widening tunnels while keeping them open totraffic during construction work.

The main features of this technology are:

• the adoption of a final lining consisting of prefabricatedconcrete segments to stabilise the widened tunnel placedin short steps according to the active arch principle, whichtherefore comes into operation at a very short distancefrom the widening face (4.5 to 6.5 m. max). As a conse-quence passive stabilisation operations such as shotcreteand steel ribs are avoided;

• the final lining can be put under pressure by using jacksin the key segment designed to recentre unsymmetricalloads should there be bending moments sufficient tomake partial the resisting section of the arch of prefabrica-ted segments;

• the ability to perform ground improvement ahead ofthe face, if required, to contain or even completely elimi-nate deformation of the face and of the cavity and there-fore avoid the uncontrolled loosening of the rock massand thereby ensure operational safety;

• intense mechanisation of the various constructionstages, including the operations for ground improvementahead of the face if required, with consequent regularadvance rates and shorter construction times, all factorsthat have advantageous side effects for site economics andthe production rates that can be achieved;

• the extremely linear production rates obtainable(industrialised tunnelling), which it is predicted will bearound 0.6 - 1.2 m./day of finished tunnel;

• the ability to perform all construction operations whileprotecting the road with a "steel shell" under which trafficcan continue to flow in safety;

• the extreme versatility of the machine used, which isable to operate under extremely varied ground and stress-strain conditions.

After a lengthy phase during which the system was cali-brated and fine tuned, because the technology employedto widen a tunnel with traffic flowing was completelynew, the experimentation, currently underway, hasalready demonstrated that this technology is capable of:

• controlling the effects of the probable presence of aband of ground around the existing tunnel which hasalready been subjected to plasticization phenomenon andwhich must not be disturbed further;

• widening the cross section of a tunnel without triggeringharmful deformation of the ground and therefore preven-ting the development of very strong thrusts on final liningof the widened tunnel and of differential subsidence onthe surface which would be dangerous to any structureexisting there;

• ensuring compliance with time schedules set at thedesign stage regardless of the type of ground and thestress-strain conditions, containing and planning costsconstruction times with certainty, thereby reducing devia-tions of traffic lanes and therefore hardship for tunnelusers to a minimum.

TUNNEL WIDENINGG

Name of Project: Milan to Naples motorway, widening to three lanes in each direction

Location: Nazzano (Rome), Italy

Tunnel use: Motorway tunnel

Client: Autostrade per l’Italia S.p.A.

Design: Rocksoil S.p.A. (Milan)

Direction of the work: Stone S.p.A.

Contractor: Cossi Costruzioni S.p.A.

Roughwork Costs: 26.881.000 e

BIBLIOGRAPHY

[1] Lunardi P., Calcerano G., “A new constructionmethod for widening highway and railway tunnels,Proceedings of the AITES-ITA 2001 Word TunnelCongress on “Progress in Tunnelling after 2000”,Milan, 10-13 June 2001, vol. 2, pp. 665-671

27a33NAZZANO ITAL 24/08/05 10:18 Page 33