60
Tunnels, Reclaims, & Soil Borings Grain Entrapment & Other Safety Areas Presented By: Rodney Carpenter, P.E.

Tunnels, Reclaims, & Soil Borings

  • Upload
    ngothu

  • View
    227

  • Download
    3

Embed Size (px)

Citation preview

Page 1: Tunnels, Reclaims, & Soil Borings

Tunnels, Reclaims, & Soil Borings

Grain Entrapment & Other Safety Areas

Presented By: Rodney Carpenter, P.E.

Page 2: Tunnels, Reclaims, & Soil Borings

TUNNELS & RECLAIMS

The purpose of reclaims in tunnels is to give better access for operation, maintenance, & cleaning to both the gates & reclaim along with protecting the area from the elements

Page 3: Tunnels, Reclaims, & Soil Borings

Center Unloading

Page 4: Tunnels, Reclaims, & Soil Borings

Unloading Conditions

Clean

Dry

Free Flowing

In Condition

Page 5: Tunnels, Reclaims, & Soil Borings

Unloading Not a Simple Process When:

• Gates plug• Grain develops clumps• Foreign items end up in the conveyors• Grain goes out of condition & becomes

non-free flowing

Page 6: Tunnels, Reclaims, & Soil Borings

Off Center Unloading

Page 7: Tunnels, Reclaims, & Soil Borings

Grain Facilities Today

• Grain facilities have evolved to a highly complex operation compared to the past. Today there is more automation for high volume incoming & outbound grain.

• The increase has taxed the present state of practical design. The new direction is to give a higher level of consideration to operations, safety, cleanliness, & maintenance.

Page 8: Tunnels, Reclaims, & Soil Borings

History

• Facilities that handled over 2 million bushels used to be concrete clusters

• Grain bin storage was maxing out at 750k bushels per bin

• Conveying at 40k bph was high speed• Filling large dia. bins took days to weeks • Soil loads at 4000psf allowable were great

to build on.

Page 9: Tunnels, Reclaims, & Soil Borings

Today

• Facilities can have over 2 million bushels in 2 corrugated bins

• A single grain bin is capable of storing 1.3 million bushels

• Conveying has moved toward 100k bph• Now able to fill large diameter bins in

hours, not days.• Geopiers, pilings, soil additives, & soil with

5000psf is being required.

Page 10: Tunnels, Reclaims, & Soil Borings

Larger Grain Facility

Page 11: Tunnels, Reclaims, & Soil Borings

Tunnels, Reclaims, & Soil Borings

• Tunnels– Type of tunnels– Dimensional design– Safety– Access

Page 12: Tunnels, Reclaims, & Soil Borings

Types of Tunnels– No trench or tunnel

• Equipment on top of ground or floor• Conveying under aeration floors

– Equipment trench• Just wide enough for equipment• Top of equipment at surface or floor (usually)

– Equipment only tunnel• Room for equipment • No real access for operations or maintenance

– Equipment tunnel with access

Page 13: Tunnels, Reclaims, & Soil Borings

No Tunnels

Page 14: Tunnels, Reclaims, & Soil Borings

No Tunnels

• Floor access but below aeration floors

• Limited access to flighting, drag, or belt

• No gate access when filled with grain

• Grating over gates

Page 15: Tunnels, Reclaims, & Soil Borings

Pros & Cons

Benefits• Low expense• Minimum planning• Can patch if need to

move

Drawbacks• No gate access• Not always sure gate is

closed• No access to blocked

gates• Can reach conveyor from

bin floor

Page 16: Tunnels, Reclaims, & Soil Borings

Trench Only

Page 17: Tunnels, Reclaims, & Soil Borings

Trench

• At top edge of concrete

• No gate access when filled with grain

• Trench should run all the way through bin

Page 18: Tunnels, Reclaims, & Soil Borings

Trench

• Inside bin access by removing cover

• Flighting, chain close to the surface

• Maintenance when bin is empty

• No gate access• Grating of gates

Page 19: Tunnels, Reclaims, & Soil Borings

Pros & Cons

Benefits• Low expense• Requires planning• Fixed location

Drawbacks• No gate access• Not always sure gate is

closed• Blocked gates• Can reach conveyor from

bin floor

Page 20: Tunnels, Reclaims, & Soil Borings

Tunnel Equipment Only

Page 21: Tunnels, Reclaims, & Soil Borings

Tunnel Equipment Only

• No access for people• Equipment takes up

the space in tunnel• Treated as a confined

space• No access to flighting,

chain, or belt from bin floor

Page 22: Tunnels, Reclaims, & Soil Borings

Pros & Cons

Benefits• Requires planning• Blocked gates• Usually can not reach

conveyor from bin floor

Drawbacks• Expense• Fixed location• Poor gate access• Maintenance is difficult• Clean out is difficult• Confined space

Page 23: Tunnels, Reclaims, & Soil Borings

Tunnel With Access

• Room to walk & access gates

• Room to maintenance equipment

• Easy to clean

Page 24: Tunnels, Reclaims, & Soil Borings

Pros & Cons

Benefits• Requires planning• Maintenance• Clean out• Gate access• Allows for access to clean

out a blocked gate

Drawbacks• Expense• Fixed location

Page 25: Tunnels, Reclaims, & Soil Borings

Location of Tunnels

• Above grade• Below grade• Part in grade &

part out

Page 26: Tunnels, Reclaims, & Soil Borings

Dimension For Tunnels

• Min height of tunnel– 6’ 8” min (Nebraska)– Min height to transition

to conveyor• Width of tunnel

– Belt conveyor width add 5ft

– Chain conveyor width add 3.5ft

Page 27: Tunnels, Reclaims, & Soil Borings

Nebraska

• NFPA 101 requires that above ground tunnels also be minimum 6’8” high

• Also minimum 36” clear width through the entire length of the tunnel.

• Max travel distance 50ft. for dead end or single exit

• Max travel distance in tunnels is 200ft. with 2 exits

• Max travel distance in tunnels is 400ft. if sprinkled

Page 28: Tunnels, Reclaims, & Soil Borings

Dimensions for Tunnels– Keep conveyor off floor 12in no less than 6in– Keep drives outside of tunnel when possible

Page 29: Tunnels, Reclaims, & Soil Borings

Access To Tunnels

• Personnel access• Equipment hatches

4-6ft. X 10ft.• Personnel access per

OSHA, Fire Marshal• Access every 100ft. • Check Nebraska

Page 30: Tunnels, Reclaims, & Soil Borings

Lack of Maintenance Space

Page 31: Tunnels, Reclaims, & Soil Borings

Cleaning & Maintenance

• Tunnel with lights (emergency)

• Add compressed air lines and/or water lines

• Portable vac system to pick up grain and/or dust

• Electric outlets (110V)

Page 32: Tunnels, Reclaims, & Soil Borings

Cleaning Difficult

Page 33: Tunnels, Reclaims, & Soil Borings

Tunnel Drainage

• Sumps in all below grade tunnels

• Crown tunnel based on soil report, usually 2-4in

• Drain outside water away from tunnel

Page 34: Tunnels, Reclaims, & Soil Borings

Reclaims• Drags 5k to 40k bph

– Shorter runs– Multiple discharges– Less height to load a drag

• Enclosed Belts 20k to 80k bph– Longer runs– Single discharge– Height to load – Low horsepower

• Screws 1.5k to 10k bph– Shorter runs – Lower capacity

Page 35: Tunnels, Reclaims, & Soil Borings

Loading a Reclaim

Page 36: Tunnels, Reclaims, & Soil Borings

Tunnels

Walkway

Room for maintenance

Keep reclaim off the floor

Access to gates

Page 37: Tunnels, Reclaims, & Soil Borings

Gates, Wells, & Sumps

Page 38: Tunnels, Reclaims, & Soil Borings

Gates, Wells, & Sumps

• Location of grain sumps– Spread

• Approximately 10ft. apart• Have at least 2 sumps less than ¼ of the radius of

the bin– Sweep wheels should miss all sumps– Types

• Primary• Intermediate grain sumps

– Last sump within 3ft. to 5ft. of the bin wall

Page 39: Tunnels, Reclaims, & Soil Borings

Grain Sump Capacity

• 50 to 90 bu/sq inch rule of thumb for spouting (We use 70 bu/sq inch)

• Sumps use 50 bu/sq inch when possible• Keep sumps as large as realistic for the

application

Page 40: Tunnels, Reclaims, & Soil Borings

Flow Rates (bph)

Gate Size Area Max bu Normal Conservativeinches^2 90 70 50

10 by 10 120 10,800 8,400 6,000 12 by 12 144 12,960 10,080 7,200 14 by 14 196 17,640 13,720 9,800 16 by 16 256 23,040 17,920 12,800 18 by 18 324 29,160 22,680 16,200 20 by 20 400 36,000 28,000 20,000 22 by 22 484 43,560 33,880 24,200 24 by 24 576 51,840 40,320 28,800 30 by 30 900 81,000 63,000 45,000 36 by 36 1,296 116,640 90,720 64,800

Larger is better for sumps in grain bin floors

Page 41: Tunnels, Reclaims, & Soil Borings

Typical Sump

Page 42: Tunnels, Reclaims, & Soil Borings

Grating vs. No Grating of Sumps

• Grate sumps when flighting, chain, or belts can be reached from the bin floor

• Grate sumps next to bin entry doors• Grating will cause more blockage for grain• We recommend Grating all gates

? Which is safer: grating or dealing with sumps that will not flow…

Page 43: Tunnels, Reclaims, & Soil Borings

Gates & Transitions

• Keep flow angles at 45° or greater • Access opening for probing in transition

above the gates• Keep gates easy to access• Use a key lock system on all intermediate

gates

Page 44: Tunnels, Reclaims, & Soil Borings

Gate Control

Procedure • Unload center gate to bin

floor• Unlock intermediate

gates• Then unload intermediate

gates from the center out

Page 45: Tunnels, Reclaims, & Soil Borings

Gate With Wheel Control

Page 46: Tunnels, Reclaims, & Soil Borings

Gate Control

Page 47: Tunnels, Reclaims, & Soil Borings

Gate Control

Page 48: Tunnels, Reclaims, & Soil Borings

Tunnel & Reclaim Design Process

• Design equipment• Allow access left & right of reclaim• Locate sumps • Transition to gates• Transition to reclaim• Build tunnel around equipment• Crown floor keeping minimum head room

required• Add in lights, electrical, air, and/or water

Page 49: Tunnels, Reclaims, & Soil Borings

Layout Sumps

Center Sump Intermediate Sump

Layout Sumps

Page 50: Tunnels, Reclaims, & Soil Borings

Sumps, Transitions, & Gates

• Sump size center – 50% larger than normal flow– Sweeps will limit flow

• Gate– Center gate(s) proportional– Intermediate gates rack & pinion – Gate size, keep close to flow rate– Gates slow moving; do not slam shut!

Page 51: Tunnels, Reclaims, & Soil Borings

Transitions

Transitions• Widen sumps• Place pipe connection for

probing• Transition at 45°

Gate

Clearance under conveyor

Pipeconnection

Page 52: Tunnels, Reclaims, & Soil Borings

Gates & Sumps

Large

Alternate center

Probe access

Lock policy

Page 53: Tunnels, Reclaims, & Soil Borings

Soil Borings

Yes!! You need them & not necessarily from the

lowest bidder!

Page 54: Tunnels, Reclaims, & Soil Borings

Information Geotech’s Need

• Proposed layout • Loads of major structures

(grain bins, towers, etc.)• Allowable, piling, soil

improvement

Page 55: Tunnels, Reclaims, & Soil Borings

Information DesignEngineer Needs

• Allowable soil pressure • Settlement: uniform & differential• Excavation & removal• Backfill & soil improvement options• Modulus of subgrade reaction

Page 56: Tunnels, Reclaims, & Soil Borings

Information Design Engineer Needs

• Seismic site classification• Lateral earth pressures• Equivalent fluid pressure• K active• K passive• Friction coefficient for the soil

Page 57: Tunnels, Reclaims, & Soil Borings

Information DesignEngineer Needs

• Water level & possible dewatering• Ram aggregate piers• Piling recommendations

Page 58: Tunnels, Reclaims, & Soil Borings

Borings

• 90ft. & above– Borings: 3 equally spaced & one in center

• 80 to 54ft. – Borings: 2 equally spaced & one in center

• 48 ft. dia. – Borings: 1 in the center

Page 59: Tunnels, Reclaims, & Soil Borings

Depth of Boring

• Min 40ft.• Should be about dia. of the bin• Geotech on site should make the final

determination

Page 60: Tunnels, Reclaims, & Soil Borings

Thank you

Questions can be emailed to [email protected]