Upload
phamtu
View
217
Download
0
Embed Size (px)
Citation preview
TURKEYTRANSMISSION NETWORK OPERATION AND INTERCONNECTIONS FOR REGIONAL MARKETS
Budak Dilli
05 July 2010 1Budak Dilli
• Energy, driving force for socio‐economic and technological development.
• Energy supply– uninterrupted, reliable, low cost and environmentally friendly
– secure • Power Network:
– Generation‐Transmission‐Distribution– Power System Control and Operation
• Dispatch, control of flows, security, stability, frequency…etc.
• The role of transmission system– Back bone, vitally important from technical point– Getting more importance in market environment
ELECTRICAL ENERGY AND TRANSMISSION SYSTEM
2Budak Dilli
ELECTRICAL ENERGY AND TRANSMISSION SYSTEM• Role of Transmission in Internal and Regional Electrical
Energy Markets– Conventional systems: Vertically integrated, monopolistic, generally
state owned• Integrated system operation more easy, decisions based on only technical and
economic considerations
– Liberal Internal Markets: Unbundled, multi players, commercially driven
• Transmission System Operators are carrying others’ energy (= $$$$$ )• Market operation + system operation• Non discriminatory access to the grid• Unbundled, independent from other market operations• Technically necessary ancillary services with commercial agreements
– Regional Markets: multi players + multi national control centers• More Coordination, Technical+ COMMERCIAL Cross‐Border exchange rules..
• Without sufficient and technically viable transmission network and successful system operation, markets (internal or regional) cannot work efficiently.
3Budak Dilli
TURKEYI. GENERAL OUTLOOK
• POPULATION (2009): 72.5 million• GDP (per capita‐2009): 8 590 US $• Electrical energy consumption (per capita): 2200 kWh• Installed Capacity: 45500 MW ( state 53%, private 47%)
– Thermal: 29604 MW– Hydro: 14802 MW– Other Renewable (wind, geothermal..): 1097 MW• Gross Generation (2009): 194,8 TWh• 46% state,54% private• 80% thermal, 20%hydro and other renewable• Import: 812 GWh • Export: 1545 GWh• Gross Consumption(2009): 194,08 TWh
4Budak Dilli
STATE• Policy development on
macro scale • Ministry of Energy &
Natural Resources (MENR)
• Regulation, control, supervision of the markets • Energy Market
Regulatory Authority (EMRA)
• State-owned generation and distribution
PRIVATE SECTOR• investments• market activities
– Generation– Distribution– Wholesale– Retail– import – export.......
ELIGIBLE AND CAPTIVE CUSTOMERS
TURKEYII. Electricity Market Structure
5Budak Dilli
TRANSMISSION
DISTRIBUTION AND RETAIL
GENERATION STATE OWNED GENERATION
(EÜAŞ)AUTOPRODUCERSPRIVATE
GEN.COs
PRIVATE WHOLESALERS
STATE OWNED WHOLESALE CO.(TETAŞ)
TURKISH ELECTRICITYDISTRIBUTION CO.
(TEDAŞ)
PRIVATE DIST.COs
TURKISH ELECTRICITYTRANSM ISSON CO.
(TEİAŞ)
WHOLESALE
TURKEYII. Electricity Market Structure
6Budak Dilli
TEK
1994 2001
TEDAŞ
TEAŞ TETAŞ
TEİAŞ
EÜAŞ
TEDAŞ
Distribution
VerticallyIntegrated
Generation,Transmission &
Trade
Trade
1970
Transmission
Generation
Distribution
TURKEYIII. Unbundling
7Budak Dilli
TRANSMISSION SYSTEMTurkish Electricity Transmission Co.‐ TEIAŞ
– State owned
– Transmission system owner & operator (TSO)
– Market Operator
– Provision of connection to and use of transmission system services to all users without discrimination.
• Through “Connection and Use of System Agreements”
– Monitoring real‐time system reliability, purchase and provide ancillary services.
• Through “Ancillary Service Agreements”
– International interconnection activities
• Development of infrastructure.
8Budak Dilli
TRANSMISSION SYSTEM OF TURKEY
- 400 kV Substation: 75- 220 kV Substation: 1- 154 kV Substation: 497- 66 kV Substation: 15- TOTAL 587 Substation (93.226 MVA)
- 14622,9 km 400 kV OHL
- 31874,3 km 154 kV OHL
- 84 km 220 kV OHL
- 508.5 km 66 kV OHL
-213 km 154 kV and 380 kV Cable
-TOTAL 47090,2 km Transmission Line
Turkish Electricity Transmission Grid
9Budak Dilli
400 KV NETWORK
BLACKSEA
MEDITERRANEAN
ALTINKAYA
EREĞLİ
AMBARLI
BULGARİSTAN
FILIPPI
H.UĞURLUKAYABAŞI
ÇANKIRI
TİREBOLU
BORÇKA
GÜRCİSTANBATUM
ERMENİSTAN
GUMRI
BALIKESİR
SOMA
ALİAĞA
DENİZLİ
YATAĞAN
KEMERKÖYOYMAPINAR
SEYDİŞEHİR
KONYA
ADANAERZİN
G.ANTEP
ANDIRIN
ELBİSTAN
KANGAL
YEŞİLHİSAR
KAYSERİ
ÇAYIRHAN
GÖLBAŞI
KEBAN
KARAKAYA
ATATÜRK
DİYARBAKIR
Ş.URFA
BATMAN
HAKKARİ
KARS
ÖZLÜCEERZURUM
HORASAN
IĞDIR
D.BEYAZIT
DIMODICHEV
SURİYE
DERİNER
İSKENDERUN
İRAN
IRAK
HALEP
PS3
ZAKHO
KHOY
BAZARGAN
BABEK
KALKANDERE
KOCATEPE
TEİAŞ-APK 2008
220 kV EİH154 kV EİH
HES (PLANLANAN)
HES (MEVCUT)
TS (MEVCUT)
TL (MEVCUT)TL (PLANLANAN)
TS (PLANLANAN)
Y.TEPE
ALİBEYKÖY
TUNÇBİLEK
D.PAŞA
KARABİGA
ADA-GEBZE
PAŞAKÖYOSMANCA
GÖKÇEKAYA
TEMELLİ
SİNCAN
BABAESKİHAMİTABA
T
ÜMRANİYE
BURSA
AYDIN
YENİKÖYBİRECİK
SEYİTÖMER
IŞIKLAR
ADAPAZARI
YUNAN
İSTA
N
KIZILTEPE
AĞRI
Z.KÖY
TEPEÖREN
UNIMAR
HİLVAN
ILISUDOĞANLI
ÇUKURCA
CİZRE
VAN
ERMENEK
MERSİN
HATAY
İKİTELLİ
A.ALANI
KAPTAN
UZUNDERE
HİSAR
GÜRSÖĞÜT
KARGI SİVASDEÇEKO
YUSUFELİ
KAVŞAK
İSDEMİR
BOYABATAMASRA
KARABÜK
X
BEYKOZÇARŞAMBA
HOPA
VARSAK
MANİSA
HABİPLER
SAMSUN DGKÇ
BORASCO
SAN-SEL TES
SAMSUN TES
CENGİZ
AKFEN DGKÇ
SİNOP TES
AKFENÇAYLI TES
ÇAN
İÇDAŞ
İÇDAŞ
AKSA
SİLOPİ TES
K.KALE DGKÇ
İÇANADOLU DGKÇ
BAĞLUM
KAYRAKTEPE
YEDİGÖZE
İSPİR
ARKUN
AKINCI
ORDU-2
TATVAN
ÇETİN
MUSUL
10Budak Dilli
Control Centers• Operation and Maintenance of the transmission lines and
substations is carried by regional directories, directly reporting headquarters at Ankara.
• The Turkish transmission system is operated by the National Control Centre (NCC) and 9 Regional Control Centers (RCCs).
System Operation, Control and Dispatch
SCADA & Energy Management System
…….… … … … … …11Budak Dilli
System Operation, Control and Dispatch400 kV Network operations carried by National Control Center (NCC), 154 kV network is operated by Regional Control Centers
12Budak Dilli
NCC
System Operation, Control and Dispatch
13Budak Dilli
Market Operation
• TEIAS: Market Operator
• Day‐Ahead Programming, and day ahead market operations.– Collecting generation and price proposals,
– Determining economic merit order dispatch
– Marginal pricing
• Intra‐Day Balancing and Settlement– Balancing: Conventional, through dispatch centers
– Settlement: Determination of commercial transactions
– Effect of transmission system faults and contingencies.
14Budak Dilli
• Difficulty in long term network Planning and timely investment– Liberal market environment, generation investors are private companies. Predetermined Rules and regulations are necessary for generation Licensing.
– Promotion of renewable generation: small hydro and wind. Hundreds of these kind, dispersed, remote locations. New transmission lines, substations, capacity increase in the existing substations. Regional and basin based planning necessary.
– Too many small projects, financing investments for timely completion.
Transmission System DevelopmentChallenges
15Budak Dilli
Transmission System OperationChallenges
• Preserving the technical quality of the system– Grid Code : Set of rules for transmission system users‐ generators, Dis.
Cos..
• Managing the effects of intermitted generation– Difficulty of day‐ahead generation programming,
– Balancing the supply ‐ demand due to fluctuations of the generation, keeping the system frequency in prescribed limits.
– New and additional control system to supervise the wind farms, forecasting the wind, keeping sufficient hot reserve.
• Determination and handling the Ancillary Services– Voltage Control, frequency control, hot stand‐by.. etc commercial‐
technical agreements with system users
16Budak Dilli
380 kV 154 kV 66 kV and below TOTAL
YEARS NUMBERCAPACITY
(MVA) NUMBERCAPACITY
( MVA) NUMBERCAPACITY
(MVA) NUMBERCAPACITY
(MVA)
1980 20 3060.0 279 8067.0 295 1544.0 594 12671.0
1990 61 9410.0 531 18008.7 151 1347.0 743 28765.7
2000 106 18160.0 821 39053.9 138 1315.4 1065 58529.3
2009 * 182 34720.0 1031 57874.0 54 632.0 1267 93226.0
ANNUAL DEVELOPMENT OF TRANSFORMERS IN TURKEY BY PRIMARY VOLTAGE LEVEL
ANNUAL DEVELOPMENT OF TRANSMISSION LINES (km.)
YEARS 380 kV 220 kV 154 kV 66 kV TOTAL
1980 2985.1 15.7 15490.1 2332.0 20822.8
1990 8334.3 84.6 23560.7 1408.2 33387.8
2000 12957.3 84.6 27949.9 560.9 41552.7
2009* 14622.9 84.6 31874.3 508.5 47090.3
Transmission System Development
17Budak Dilli
TRANSMISSION SYSTEM INVESTMENTSAND FINANCING
• AMOUNT:– BETWEEN 2005‐2009, TOTAL TRANSMISSION LINE AND SUBSTATION
INVESTMENT AMOUNT IS:
1,2 Billion US $
• FINANCING:– 319 Million US$ ‐ LOAN from WB
– 881 Million US$ ‐ TEIAS Resources• TEIAS revenues from approved transmission tariff and connection charges.
• IN THE LAST TEN YEARS, TEIAS USED APPROXIMATELY 473 MILLION US$ LOAN FROM WB.
• FOR SOME POWER PLANT PROJECTS DEVELOPED BY PRIVATE SECTOR, POWER PLANT INVESTOR FINANCE THE TRANSMISSIN LINE AND IT IS PAID BACK FROM TRANSMISSION SYSTEM USE TARIFF IN 10 YEARS.
18Budak Dilli
ELECTRICITY INTERCONNECTIONS OF TURKEY
400 kV Existing400 kV Under Construction220 kV Existing154 kV Existing
IRAQ
SYRIA
IRAN
ARMENIA
GEORGIA
BULGARIA
GREECE
19Budak Dilli
FROM S/S TO S/S U, kV Note
Hopa (Turkey) Batumi (Georgia) 220 Currently Operated for Import. (Isolated
Region Mode)
Kars (Turkey) Gumri (Armenia) 220 Not operated.
Iğdır (Turkey)Babek (NahcievanAzerbaijan)
154 Currently Operated for Import. (Isolated Region Mode)
Doğubeyazıt (Turkey)
Bazargan (Iran) 154 Not operated.
T-Connection (Engil s/s –Bagisli s/s 154 kV line) (Turkey)
Khoy (Iran) 400 Currently Operated at 154 kV for Import. (Isolated Region Mode)
EXISTING INTERCONNECTIONS OF TURKEY
20Budak Dilli
FROM S/S TO S/S U, kV Note
Karkey (Turkey)
Zakho(Iraq)
400 Currently Operated at 154 kV for Export. (Isolated Region Mode)
Birecik HPP (Turkey)
Aleppo (Syria) 400 Currently Operated for Export. (Isolated
Region Mode)
Hamitabat(Turkey)
Maritsa(Bulgaria)
400 Not Operated Yet (ENTSO /UCTE)
Babaeski(Turkey)
Maritsa (Bulgaria) 400
Not Operated. (ENTSO /UCTE)
Babaeski(Turkey)
Phillippi(Greece)
400Not Operated. (ENTSO /UCTE)
EXISTING INTERCONNECTIONS OF TURKEY
21Budak Dilli
Future Interconnections
Turkey‐Georgia:Construction of a new 400 kV Akhaltsikhe‐Borçka transmission line together with a DC Back‐to‐back station at Georgian side.Turkey‐Romania:400 kV HVDC submarine cable under Black Sea with carrying capacity 600 MW and converter stations at the end points of the cable is agreed to be constructed between two countries. Feasibility Studies are ongoing.Turkey‐Iraq:Construction of 400 kV Cizre (Turkey) ‐Musul (Iraq) interconnection line is under planning stage. Turkey‐Iran:In order to improve the energy exchange between the countries a new project is under consideration by providing asynchronous connection through construction of a DC Back‐to‐Back station to be linked to existing 400 kV Khoy‐Başkale‐Van transmission line.Mediterranean Electricity Ring Project.
Black Sea Electricity Ring Project.
22Budak Dilli
Turkey-UCTE (ENTSO-E) Connection: (Synchronous operation of Turkish Power system with Europe)
1. Complementary Technical Studies for the Synchronization of Turkish Power System with the UCTE System started at 2003 and finalized with success in April 2007. Within this project, required technical conditions for Turkish Power System was determined, for synchronization with the ENTSO-E Continental Europe Power System.
2. Rehabilitation of the Frequency Control Performance of Turkish Power System for Synchronous Operation with UCTE ( started at 2007 ongoing). Within the scope of the project, Turkish Power System is being prepared for parallel operation with ENTSO-E, regarding power and frequency control, steady state and transient stability.
Integration With European Internal Market via Southeast European Regional Market
• Optimization and Rehabilitation work completed in many thermal (lignite and natural gas fired) and hydraulic power plants for primary and secondary frequency control.
• The existing inherent frequency control problem has already been eliminated.
• The SPS at the interface to manage extreme contingencies is implemented .
• Measures to damp the 0.15Hz inter‐area oscillations implemented.
• HPP governor tunings, AVR & PSS tuning, Installation of STATCOM completed. 23Budak Dilli
Tests in Island Mode of Operation were successfully performed under maximum load conditions in January 2010 and will be performed under minimum load conditions in March 2010.
Trial synchronous operation with ENTSO-E Continental Europe System will start at September18.
After successful trial synchronous operation, Turkish transmission network will be a part of Continental European Network and Energy exchange will be possible via 3x400 kV transmission Lines.
Cross-Border trade rules will be in accordance with EU Internal MarketDirectives.
Coordination in regional market will be carried by Southeast Europe regional coordination center.
Integration With European Internal Market via Southeast European Regional Market
24Budak Dilli
Frequency Deviation Improvement
Absolute Frequency Deviation (minutely avarages) df>50, df>100, df>150
42,7
6 45,4
9
49,4
4 51,1
8
51,6
8
44,0
4
50,7
1
48,1
1
42,2
46,9
6
45,4
8
46,0
7
46,1
1
41,2
4
41,4
2
47,6
4
46,1
2
43,1
6
39,0
8
39,2
9
40,4
5 43,0
6
51,5
8
48,4
7
47,7
8
33,3
2
28,6
3
27,0
3 30,2
2
31,2
6
31,6
6
23,8
3
23,9
1
23,1
4
8,58
11,6
4
12,9
9 14,8
14,7
6
9,71
13,7
3
13,2
8
10,2
2
13,7
2
12,1
5
12,4
4
13,1
6
10,1
9 12,9
2
16,2
9
15,9
5
12,7
8
11,0
5
12
11
12,6
5
18,0
8
14,5
3
14,2
2
5,03
3,04
2,59
2,48 3,
25 4,5
2,03
2 1,68
1,61 2,
37 2,63 3,
85
3,48
1,79 2,
95 3,48
2,51 3,
75
3 2,89 3,46
2,63 3,
86 5,66
5,79
3,94
3,4 4,06
3,29
3,5
5,65
4,03
3,88
0,7
0,36
0,36
0,17
0,35 0,76
0,25
0,23
0,12
0
10
20
30
40
50
60
June
2007
July
2007
Augus
t 200
7
Septem
ber 2
007
Octobe
r 200
7
Novem
ber 2
007
Decem
ber 2
007
Janu
ary 20
08
Februa
ry 20
08
March 2
008
April 2
008
May.08
June
2008
July
2008
Augus
t 200
8
Septem
ber 2
008
Octobe
r 200
8
Novem
ber 2
008
Decem
ber 2
008
Janu
ary 20
09
Februa
ry 20
09
March 2
009
April 2
009
May.09
June
2009
July
2009
Augus
t 200
9
Septem
ber 2
009
Octobe
r 200
9
Novem
ber 2
009
Decem
ber 2
009
Janu
ary 20
10
Februa
ry 20
10
March 2
010
months
% d
f
df>50df>100df>150
25Budak Dilli
Frequency Control Performance(11.04.2009)
26
System Frequency vs time
Budak Dilli